pse4ne2 - power system analysis 101
TRANSCRIPT
1
NATIONAL ELECTRIFICATION ADMINISTRATION
U. P. NATIONAL ENGINEERING CENTER
Training Course in
Power System Engineering for Non-Engineers
Competency Training and Certification Program in Electric Power Distribution System Engineering
U. P. NATIONAL ENGINEERING CENTER
Power System Analysis 101
2
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Power System Analysis
Reliability AnalysisReliability
Short Circuit AnalysisSafety
System Loss AnalysisEfficiency
Load Flow AnalysisPower Quality
Power System Analysis
Performance Standards
2
3
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
LOAD FLOW ANALYSIS
4
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
1. What is Load Flow?
2. Uses of Load Flow Studies
3. Load Flow Control
Load Flow Analysis
3
5
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
What is Load Flow?
What are the Voltages, Currents, Power and Losses of the Distribution System?
Bus1
Utility Grid
Bus2Bus3
Bus4V1 = 67 kV
Lumped Load A2 MVA 85%PF
Lumped Load B1 MVA 85%PF
V2 = ?
V4 = ?
V3 = ?
I23 , Loss23 = ?
I24 , Loss24 = ?
I12 , Loss12 = ?
P1 , Q1 = ?
P2 , Q2 = ?
P3 , Q3 = ?
P4 , Q4 = ?
6
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Can we see how electric power flows in the system, coming from the sources (where power is purchased) and down to all customers (where power is sold)?
Can we determine:
• If any customer is being provided with voltage that is too low (or even too high)?
• If too much power flow through any of our equipment, especially our transformers?
• How much power is lost along the lines and equipment?
YES! LOAD FLOW ANALYSIS
Load Flow of an Existing System
What is Load Flow?
4
7
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Can we have a picture of the system as we
contemplate possible changes?
Can we determine in advance the effects of:• Growth or addition of new loads• Addition of generating plants• Upgrading of Substation• Expansion of distribution lines• Installations of equipment such as capacitors
before the proposed changes are implemented?
YES! LOAD FLOW ANALYSIS
Load Flow of a Contemplated System
What is Load Flow?
8
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Load Flow (also called Power Flow) is a snapshot picture of the power system at a given point.
Load Flow Analysis simulates (i.e., mathematically determine) the performance of an electric power system under a given set of conditions.
What is Load Flow?
5
9
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
How would the engineers do that?
• Identify physical components
• Know the characteristic of components
• Mathematically represent the behavior of components
• Calculate electrical parameters
What is Load Flow?
10
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
G
What is Load Flow?
6
11
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Utility Grid or Generator
Bus
Load
Substation Transformer
TransmissionLine
DistributionLine
G
DistributionTransformer
What is Load Flow?
Load Flow mathematically determines the Voltages, Currents, Power and Losses
12
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Basic Information From a Load Flow Study
Voltage Profile
Injected Power (Pp and Qp)
Line Currents (Ipq and Ipq)
Power Flows (Ppq and Qpq)
Line Losses (I2R and I2X)
Uses of Load Flow Studies
7
13
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Other Information From a Load Flow Study
Overvoltage and Undervoltage Buses
Critical and Overloaded Transformers and Lines
Total System Losses
Uses of Load Flow Studies
14
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Sensitivity Analysis
9) Add or remove rotating or static var supply to buses.
8) Increase or decrease transformer size.
7) Change transformer taps.
6) Change bus voltages.
5) Increase conductor size on T&D lines.
4) Add new transmission or distribution lines.
3) Add, remove or shift generation to any bus.
2) Add, reduce or remove load to any or all buses.
1) Take any line, transformer or generator out of service.
Uses of Load Flow Studies
8
15
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
1) ANALYSIS OF EXISTING CONDITIONS
• Check for voltage violations� PGC: 0.95 – 1.05 p.u. (For Transmission)� PDC: 0.90 – 1.10 p.u (For Distribution)*
*Recommended 0.95 – 1.05 p.u.
• Check for branch power flow violations� Transformer Overloads� Line Overloads
• Check for system losses
� Caps on Segregated DSL
Uses of Load Flow Studies
16
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
2) ANALYSIS FOR CORRECTING PQ PROBLEMS
• Voltage adjustment by utility at delivery point� Request TransCo to improve voltage at
connection point� TransCo as System Operator will determine
feasibility based on Economic Dispatch and other adjustments such as transformer tap changing and reactive power compensation
Uses of Load Flow Studies
9
17
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
• Transformer tap changing� Available Taps
� At Primary Side
� At Secondary Side
� Both Sides
� Typical Taps � Tap 1: +5%
� Tap 2: +2.5%
� Tap 3: 0% (Rated Voltage)
� Tap 4: -2.5%
� Tap 5: -5%
Uses of Load Flow Studies
2) ANALYSIS FOR CORRECTING PQ PROBLEMS
18
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
•Capacitor compensation• Compensate for Peak Loading• Check overvoltages during Off-Peak• Optimize Capacitor Plan
• System configuration improvement
Uses of Load Flow Studies
2) ANALYSIS FOR CORRECTING PQ PROBLEMS
10
19
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
3) EXPANSION PLANNING
• New substation construction• Substation capacity expansion• New feeder segment construction / extension• Addition of parallel feeder segment• Reconducting of existing feeder segment/ circuit • Circuit conversion to higher voltage• Generator addition
Uses of Load Flow Studies
20
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
4) CONTINGENCY ANALYSIS
Reliability analysis of the Transmission (Grid) and Subtransmission System
5) SYSTEM LOSS ANALYSIS
Segregation of System Losses
Uses of Load Flow Studies
11
21
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
1. For Generating plants, the amount of power that can be delivered
can be controlled by the plant operator (as long as within the
capacity of the plant)
2. Flow of power is affected by the voltages and impedances across
the components
• Specialized Transformers and other equipment may be
utilized to control the flow of power across the network
3. Capacitors are used to improve the voltage profile across the
network
• The current drawn by the load is reduced
• The voltage drop across the line is reduced
• The voltage at the load side is increased
Load Flow Control
22
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
SYSTEM LOSS ANALYSIS
12
23
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
1. Components of Distribution System Losses
2. Segregation of Distribution System Losses
3. System Loss Reduction and Control
System Loss Analysis
24
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Components of Distribution System Losses
The Philippine Distribution Code (PDC)
mandates system losses to be segregated into the following components:
a. Technical Loss;
b. Non-Technical Loss; and
c. Administrative Loss.
13
25
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Total Distribution System Losses
Administrative
Loss+
Total Distribution
System Losses
=
Energy Delivered to the Distribution
System
Energy Delivered to Users
-
Technical Loss Non-Technical Loss+
Bundled Technical & Non-Technical Losses
26
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
The electric energy used by the Distribution Utility in the proper operation of the Distribution System.
a. Distribution Substations;
b. Offices, warehouses and workshops of the DU; and
c. Other essential electrical loads of the Distribution Utility.
Components of Distribution System Losses
Administrative Losses
14
27
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Load and no-load losses in:
a. Sub-transmission lines and substation transformers;
b. Primary distribution lines and distribution transformers;
c. Secondary distribution lines and service drops;
d. Voltage regulators, Capacitors and reactors; and
e. All other electrical equipment necessary for the operation of the distribution system.
Components of Distribution System Losses
Technical Losses
28
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
The component that is not related to the physical characteristics and functions of the electrical system, and is caused primarily by human error, whether intentional or not.
Includes the electric energy lost due to pilferage, tampering of meters and erroneous meter reading.
Errors that are attributable to inaccuracies in metering and billing.
Components of Distribution System Losses
Non-Technical Losses
15
29
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Total DSL = Energy Input - Energy Output
Total DSL
= Σ[Energy delivered by the Transmission System]
+ Σ[Energy delivered by Embedded Generating Plants]
+ Σ[Energy delivered by Other Distribution Systems]
+ Σ[Energy delivered by User Systems with Generating Units]
- Σ[Energy delivered to the Users of the Distribution System]
Total Distribution System Losses
30
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Unbundling the Technical and Non-Technical Loss
Technical
Losses
Non-Technical
Losses+
-Technical
Losses
Shall be quantified through 3-Phase (Unbalanced) Load Flow Simulations
Non-Technical
Losses
=Residual after
subtracting Administrative &
Technical Losses from the Total Distribution
System Losses
16
31
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Technical Loss
= ΣΣΣΣ[Hourly Load and No-Load (or Fixed) Losses in all electrical equipment, devices and conductors]
g) Voltage Regulators
h) Capacitors
i) Reactorsj) Other electrical equipment
a)Sub-transmission Lines
b)Substation Power Transformersc)Primary Distribution Lines
d)Distribution Transformers
e)Secondary Distribution Lines
f) Service Drops Hourly Load Flow Simulations
Unbundling the Technical and Non-Technical Loss
Plus Calculated Metering Equipment Loss
32
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Primary Distribution Lines
(Main Feeder)
Substation
Transformer
Residential
Subtransmission Lines
Primary Distribution Lines (Laterals)
Distribution
Transformer
Commercial Industrial
Misc Loads
Secondary Distribution Lines
Service
Drop
Three-Phase Unbalanced Load Flow Simulations
a)Sub-transmission Lines
b)Substation Power Transformersc)Primary Distribution Lines
d)Distribution Transformerse)Secondary Distribution Linesf) Service Drops
g)Voltage Regulatorsh)Capacitorsi) Reactorsj) Other electrical equipment
Load Losses and
No-Load (Fixed) Losses
Unbundling the Technical and Non-Technical Loss
17
33
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Potential Transformer Loss
= Power Loss in PT (kW) x Number of PT x Number of Operating
Hours in the Billing Period
Current Transformer Loss
= Power Loss in CT (kW) x Number of CT x Number of Operating
Hours in the Billing Period
Electric Meter Potential Coil Loss
= Power Loss in Electric Meter Potential Coil (kW) x Number of
Electric Meters x Number of Operating Hours in the Billing Period
Electric Meter Current Coil Loss
= Power Loss in Electric Meter Current Coil (kW) x Number of
Electric Meters x Number of Operating Hours in the Billing Period
Operating Hours = No. of days x 24 hours – SAIDI
Calculation of Metering Equipment
Unbundling the Technical and Non-Technical Loss
34
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Non-Technical Loss
= Total Distribution System Losses
- Administrative Loss
- Technical Loss
- Recovered Losses
Note: Losses recovered from anti-pilferage activities are subtracted from the total distribution system losses.
Unbundling the Technical and Non-Technical Loss
18
35
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Customer Energy Bill
Distribution System Data
Distribution System Loss Segregation
Program
(3-phase Load Flow)
Segregated
Technical
Loss(Billing Period)
Metering Equipment
LossMetering Equipment Inventory
Distribution Reliability Assessment
DSL Segregation
36
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Segregated Distribution System Losses
�Monthly DSL Segregation
� Segregated DSL for the Whole Distribution System
� Segregated DSL Per Receiving/Metering Point
� Segregated DSL per Substation
� Segregated DSL per Feeder
� Segregated DSL per Distribution Transformer
19
37
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Distribution Network Models
Impedance/
Admittance
parameters of
Distribution
System Element
IA
IB
IC
Ia
Ib
Ic
VA VB VC Vc Vb Va
Ground (Reference Node)
A
B
C
a
b
c
Distribution System Element
Distribution Network Model must capture the unbalance characteristics of the System
38
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Distribution Load Models
0
50
100
150
200
250
300
350
Dem
an
d (
W)
Customer Energy Bill
Customer Energy Bill Converted to Hourly Power
Demand
Area under the curve
= Customer Energy
Bill
Normalized Customer Load
Curve
0
0.2
0.4
0.6
0.8
1
1.2
Time (24 hours)
Norm
alized D
em
and (per unit)
20
39
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Data Requirements
ERC-DSL-21
ERC-DSL-20
ERC-DSL-19
ERC-DSL-18
ERC-DSL-17
ERC-DSL-16
ERC-DSL-15
ERC-DSL-14
ERC-DSL-13
ERC-DSL-12
ERC-DSL-11
ERC-DSL-10
ERC-DSL-09
ERC-DSL-08
ERC-DSL-07
ERC-DSL-06
ERC-DSL-05
ERC-DSL-04
ERC-DSL-03
ERC-DSL-02
ERC-DSL-01 Administrative Load Data
Customer Data
Billing Cycle Data
Customer Energy Consumption Data
Load Curve Data
Bus Data
Subtransmission Line Data - Overhead
Subtransmission Line Data - Underground/Submarine Cable
Substation Power Transformer Data - Two Winding
Substation Power Transformer Data - Three Winding
Primary Distribution Line Data - Overhead
Primary Distribution Line Data - Underground Cable
Primary Customer Service Drop Data - Overhead
Primary Customer Service Drop Data - Underground Cable
Distribution Transformer Data
Secondary Distribution Line Data
Secondary Customer Service Drop Data
Voltage Regulator Data
Shunt Capacitor Data
Shunt Inductor Data
Series Inductor Data
40
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Optimal Level of System Loss
Cost
System LossHigh Low
System Loss
Reduction
Program CostUnrecovered
Energy Cost
Total Cost
Optimal
21
41
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
TECHNICAL LOSS REDUCTION
PROGRAM
NON-TECHNICAL LOSS
REDUCTION PROGRAM
SEGREGATED DISTRIBUTION SYSTEM LOSSES ANALYSIS
TECHNICAL, ECONOMIC & FINANCIAL
ANALYSIS
TECHNICAL, ECONOMIC & FINANCIAL
ANALYSIS
BENECO DSL Segregation
42
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
11.9698%33,836,577 TOTAL
5.5951%15,487,726Non-Technical
6.3153%18,181,059Technical
0.0594%167, 791Administrative
%KwhrLoss
TEST YEAR SEGREGATED
DISTRIBUTION SYSTEM LOSSES
Administrative
Loss, 0.50%
Technical
Loss,
52.76%
Non-
Technical
Loss,
46.74%
BENECO DSL Segregation
22
43
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
13.2KV SYSTEM
23KV SYSTEM
TOTAL LOSSES
Non-Technical Loss
Technical Loss
Administrative Loss
SEGREGATED SYSTEM LOSSES
17.7088%
7.4183%
9.8906%
0.3998%
13.2 KV System
TOTAL LOSSES
Non-Technical Loss
Technical Loss
Administrative Loss
SEGREGATED SYSTEM LOSSES
11.6324%
5.4879%
6.1051%
0.0393%
23 KV System
BENECO DSL Segregation
44
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
DSL RESULT PER FEEDER PER HOUR PER DAY IN A MONTH
23
45
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
46
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
100.0000%6.3153%Total Technical Loss
5.0350%0.3180%kWhR Meter Loss
0.0456%0.0029%Shunt Capacitor Loss
1.0937%0.0691%Secondary Service Drop
34.2848%2.1652%Secondary
27.5469%1.7397%Dist. XF No-Load Loss
5.4445%0.3438%Dist. XF Load Loss
0.0000%0.0000%Primary Service Drop
21.8597%1.3805%Primary Line
3.7559%0.2372%Power Transformer No-Load Loss
0.9338%0.0590%Power Transformer Load Loss
% SHARE% LOSSSEGREGATED TECHNICAL LOSS
BENECO DSL Segregation
24
47
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
TECHNICAL LOSS ALLOCATION
Shunt Capacitor Loss
0%
Pow er Xformer Load Loss
1%
kWhR Meter Loss
5%
Secondary Service Drop
1%
Pow er Xformer No-Load
Loss
4%
Secondary
34%
Dist. XF No-Load Loss
28%
Primary Line
22%
Dist. XF Load Loss
5%
TECHNICAL LOSS DISTRIBUTION
BENECO DSL Segregation
48
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
5.5951%5.4879%7.4183%15,816,480.83 14,651,941.84 1,164,538.99
Non-Technical Loss
11.9698%
11.6324%
17.7088%33,836,576.60 31,056,634.21 2,779,942.39 TOTAL LOSSES
6.3153%6.1051%9.8906%17,852,304.63 16,299,669.83 1,552,634.80 Technical Loss
0.0594%0.0393%0.3998%167,791.14 105,022.54 62,768.60
Administrative Loss
Total23 KV System
13.2 KV SystemTotal23 KV System13.2 KV System
PERCENT (%) TECHNICAL LOSSESKWHR TECHNICAL LOSSES
SEGREGATED SYSTEM LOSSES
TEST YEAR SEGREGATED DISTRIBUTION SYSTEM LOSSES
PER SYSTEM VOLTAGE
BENECO DSL Segregation
25
49
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
TEST YEAR SEGREGATED TECHNICAL LOSSES
PER SYSTEM VOLTAGE
6.3153%6.1051%9.8906%17,852,305 16,299,670 1,552,635 Total Technical Loss
0.3180%0.2792%0.9779%898,866 745,359 153,507 kWhR Meter Loss
0.0029%0.0029%0.0025%8,147 7,753 394 Shunt Capacitor Loss
0.0691%0.0715%0.0272%195,254 190,979 4,275 Secondary Service Drop
2.1652%2.2141%1.3342%6,120,623 5,911,176 209,447 Secondary
1.7397%1.6205%3.7661%4,917,765 4,326,553 591,212 Dist. XF No-Load Loss
0.3438%0.3520%0.2054%971,968 939,729 32,239 Dist. XF Load Loss
0.0000%0.0000%0.0000%6 6 -Primary Service Drop
1.3805%1.2927%2.8732%3,902,460 3,451,427 451,032 Primary Line
0.2372%0.2117%0.6708%670,517 565,221 105,295 Power Xformer No-Load
Loss
0.0590%0.0605%0.0333%166,700 161,467 5,232 Power Xformer Load Loss
Total23 KV System13.2 KV SystemTotal23 KV System13.2 KV System
PERCENT (%) TECHNICAL LOSSESKWHR TECHNICAL LOSSES
TECHNICAL LOSSES
BENECO DSL Segregation
50
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
FORECASTED SEGREGATED DISTRIBUTION SYSTEM LOSSES
5.5951%7.0604%0.0493%12.7071%442,271,657 2010
5.5951%6.8604%0.0491%12.5074%405,588,445 2009
5.5951%6.7477%0.0535%12.3994%372,339,284 2008
5.5951%6.6187%0.0583%12.2757%341,755,055 2007
5.5951%6.4611%0.0621%12.1222%313,577,324 2006
Non Technical Loss(%)
Technical Loss (%)
Administrative Loss(%)
Total System
Losses (%)
Energy Input (KWH)
YEAR
BENECO DSL Segregation
26
51
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
PROPOSED DISTRIBUTION SYSTEM LOSS CAPS
218,2182.7644%6.5249% to 7.5959%2010
199,1473.1278%6.3431% to 7.3778%2009
199,1473.8585%6.2431% to 7.2523%2008
199,1474.7486%6.1281% to 7.1094%2007
194,7415.5951%5.9833% to 6.9388%2006
AdministrativeLoss Cap (Annual
KWH)
Declining Non-Technical Loss
Caps
Technical LossCap
YEAR
FORECASTED DISTRIBUTION SYSTEM LOSS
2010
2009
2008
2007
2006
YEAR
10.4191%-9.3467%
10.5639%-9.5279%
11.1733%-10.1628%
11.9251%-10.9425%
12.6047%-11.6480%
FORECASTED SYSTEM LOSS RANGE
52
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
P 111,876,2965.595%15,816,481 Non-Technical Loss
P 126,276,4926.315%17,852,305 Technical Loss
P 1,186,8540.059%167,791 Administrative Loss
P 239,339,64111.970%33,836,577 Total System Loss
Peso Equivalent (Php)(as of February 2007
costing**)Percentage (%)Energy (KWHR)Distribution System Loss
P 126,276,4926.3153%17,852,305Total Technical Loss
P 6,358,0360.3180%898,866kWhR Meter Loss
P 57,6260.0029%8,147Shunt Capacitor Loss
P 1,381,1080.0691%195,254Secondary Service Drop
P 43,293,6172.1652%6,120,623Secondary
P 34,785,3211.7397%4,917,765Dist. XF No-Load Loss
P 6,875,1170.3438%971,968Dist. XF Load Loss
P 420.0000%6Primary Service Drop
P 27,603,6581.3805%3,902,460Primary Line
P 4,742,8330.2372%670,517Power Xformer No-Load Loss
P 1,179,1340.0590%166,700Power Xformer Load Loss
Peso Equivalent (Php)(as of February 2007
costing**)Percentage (%)Energy (KWHR)Technical Losses
BENECO SEGREGATED DISTRIBUTION SYSTEM LOSS (base year 2004)
BENECO SEGREGATED TECHNICAL LOSS (base year 2004)
27
53
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
15.9540%10.5949%0%26.5489%66,364 44,072 -110,435
LUELCO
9.1927%9.6377%0%18.8304%181,600 190,389 -371,989
NPC-Itogon
10.9641%9.3068%0.0838%20.3546%135,549 115,060 1,036 251,644
Ambuclao
9.1774%5.8537%0%15.0311%38,613 24,629 -63,242
Ampuhaw Mini-hydro
3.5755%8.5662%0%12.1417%7,378 17,677 -25,055
Bakun Mini-hydro
9.9594%6.5027%0%16.4621%59,151 38,621 -97,772
Asin Mini-Hyrdo
5.9394%8.6889%0.1846%14.8130%373,918 547,017 11,625 932,559
Mankayan
8.0217%10.9053%0.6136%19.5406%655,073 890,558 50,108 1,595,739
Atok
7.6186%4.2450%0%11.8636%1,722,755 959,893 -2,682,647
NPC-Beckel
5.8312%5.9870%0.0454%11.8636%4,843,859 4,973,278 37,680 9,854,817
NSC New 20MVA
6.2669%5.5626%0.0341%11.8636%4,104,556 3,643,277 22,323 7,770,156
NSC Old 20MVA
4.7940%7.0544%0.0152%11.8636%2,094,032 3,081,395 6,636 5,182,063
Irisan
3.1611%6.8564%0.0791%10.0966%1,533,634 3,326,440 38,384 4,898,458
Lamut
Non-TechnicalLoss
Technical LossAdmin Loss
MeteringConnection Pt.Loss
Non-TechnicalLossTechnical Loss
AdminLoss
MeteringConnection Pt.Loss
LOSSES IN PERCENTAGE (%)ENERGY LOSSES (KWHR)
Metering Connection
SEGREGATED SYSTEM LOSS PER METERING CONNECTION POINT
54
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
5.5951%P 116,429,07015,816,480.83 TOTAL
15.9540%0.0235%P 488,51866,363.50 LUELCO
9.1927%0.0642%P 1,336,802181,599.91 NPC-Itogon
10.9641%0.0480%P 997,809135,548.81 Ambuclao
9.1774%0.0137%P 284,24338,613.44 Ampuhaw Mini-hydro
3.5755%0.0026%P 54,3137,378.26 Bakun Mini-hydro
9.9594%0.0209%P 435,42459,150.85 Asin Mini-Hyrdo
5.9394%0.1323%P 2,752,501373,917.67 Mankayan
8.0217%0.2317%P 4,822,153655,072.51 Atok
7.6186%0.6094%P 12,681,6271,722,754.60 NPC-Beckel
5.8312%1.7135%P 35,656,8584,843,859.12 NSC New 20MVA
6.2669%1.4520%P 30,214,6634,104,556.00 NSC Old 20MVA
4.7940%0.7408%P 15,414,6932,094,031.95 Irisan
3.1611%0.5425%P 11,289,4651,533,634.21 Lamut
NTL % (Feeder)NTL % (System)Cost of Unrecovered
NTL (Pesos)Non-Technical Loss
(kWhr)Metering Connection
NON-TECHNICAL LOSS PER METERING CONNECTION POINT
ACTIVITIES CONSIDERED AND COSTED FOR NON-TECHNICAL LOSS REDUCTION OPTIMIZATION COMPUTATION
Sole-Use Distribution Transformer Monitoring►
Phased-Out Kwhr Meter Replacement (Old kwhrmeters)►
Kwhr Meter Replacement (apprehended and defective)►
Inspection, Calibration and Apprehension►
Communal Distribution Transformer Block Metering►
Software and Hardware Requirements Procurement►
Loose Connection Correction►
Right-of-Way Clearing►
Streetlight Photo Switching►
Streetlight kwhr Metering►
28
55
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
1321Bakun Mini-hydro13434Bakun Mini-hydro13
1242Mankayan111,723Mankayan11.5
1169Ambuclao121,442Ambuclao11.5
1077Atok102,120Atok10
983Asin Mini-Hyrdo92,366Asin Mini-Hyrdo9
6105Ampuhaw Mini-hydro82,413Ampuhaw Mini-hydro7
886Irisan56,326Irisan6.5
5107NPC-Itogon62,977NPC-Itogon5.5
4155LUELCO72,765LUELCO5.5
788Lamut46,786Lamut5.5
3157NSC New 20MVA211,009NSC New 20MVA2.5
2201NPC-Beckel310,194NPC-Beckel2.5
1430NSC Old 20MVA138,722NSC Old 20MVA1
RANKKWHR NTL / NO. OF METERSRANKKWHR NTL / NO. OF DT's
INSPECTION, APPREHENSION, CALIBRATION
Metering Connection
COMMUNAL TRANSFORMER BLOCK METERING
Metering ConnectionAverage Rank
PRIORITY RANKING IN TERMS OF SELECTED NTL ACTIVITES FOR IMPLEMENTATION
Feeder 6
Feeder 5
NSC Old 20MVA
Feeder 4
Feeder 3
Irisan
Feeder 2
Feeder 1
Lamut
Totalizer 2
Totalizer 1
NPC-Beckel
Feeder 10
Feeder 9
Feeder 8
Feeder 7
NSC New 20MVA
Circuit 5
Circuit 4
Mankayan
Circuit 3
Circuit 2
Circuit 1
Atok
Multi-Feeder Metering Connection Points
LUELCO
NPC-Itogon
Ambuclao
Ampuhaw Mini-hydro
Bakun Mini-hydro
Asin Mini-Hyrdo
Single Feeder Metering Points
FEEDER COVERAGE
56
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
P 54,130,376.192.8308%2.7644%5.5951%TOTAL =
242,309.48 0.0127%7.343%8.611%15.954%LUELCO
739,469.91 0.0387%3.659%5.534%9.193%NPC-Itogon
649,735.01 0.0340%3.195%7.769%10.964%Ambuclao
135,238.81 0.0071%4.426%4.752%9.177%Ampuhaw Mini-hydro
42,656.16 0.0022%0.520%3.056%3.575%Bakun Mini-hydro
225,901.85 0.0118%4.337%5.623%9.959%Asin Mini-Hyrdo
1,929,917.47 0.1009%1.408%4.532%5.939%Mankayan
2,984,882.11 0.1561%2.618%5.403%8.022%Atok
4,950,875.25 0.2589%4.382%3.237%7.619%NPC-Beckel
17,019,823.88 0.8901%2.802%3.029%5.831%NSC New 20MVA
9,544,620.05 0.4991%4.113%2.154%6.267%NSC Old 20MVA
9,021,486.28 0.4718%1.741%3.053%4.794%Irisan
6,643,459.93 0.3474%1.137%2.024%3.161%Lamut
Optimized ProjectCost for NTL Reduction
% Recovered NTL as per Entire System
% Recovered NTL per Feeder
Level of Optimum %NTL per Feeder
% UnrecoveredNTL per Feeder
Metering Connection
SUMMARY OF OPTIMIZED PROJECT COST FOR NON-TECHNICAL LOSS REDUCTION PROGRAM
NOTE:
Project Cost for implementation per Metering Connection at targeted reduced Non-technical Loss
percentage SHALL NOT EXCEED the computed Optimized Project Cost.
29
57
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Cost of Unrecovered VS NTL Reduction Program
0
10
20
30
40
50
60
70
80
90
100
110
120
5.5
95
1%
5.3
85
3%
5.1
75
5%
4.9
65
7%
4.7
55
9%
4.5
46
1%
4.3
36
2%
4.1
26
4%
3.9
16
6%
3.7
06
8%
3.4
97
0%
3.2
87
1%
3.0
77
3%
2.8
67
5%
2.6
57
7%
2.4
47
9%
2.2
38
1%
2.0
28
2%
1.8
18
4%
1.6
08
6%
1.3
98
8%
1.1
89
0%
0.9
79
1%
0.7
69
3%
0.5
59
5%
Mil
lio
ns
Non-Technical Loss (%)
Co
st
(Ph
p)
Cost of Unrecovered NTL
Cost NTL Reduction Program
BENECO NON-TECHNICAL LOSS REDUCTION ECONOMIC ANALYSIS
OPTIMUM LEVEL OF NON-TECHNICAL LOSS REDUCTION = 2.7644%
EQUIVALENT PROJECT COST = P53,447,802.55
Optimum level of loss reduction
58
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
System Loss Reduction and Control
� Reduction and Control of Technical Losses
� Reduction and Control of Non-Technical Losses
30
59
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
� Use the results of the Distribution System Loss Segregator for System Loss Reduction Program.� Ranks the losses from the highest to lowest ( Per
Substation, Per feeder, per distribution transformer)
� Prepare a Specific Technical Loss Reduction Program
based on your technical analysis!!!
� Simulate your proposed technical loss reduction solutions
to quantify the technical loss reduction
� Optimize your proposed technical loss reduction solutions
Reduction and Control of Technical Losses
60
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
� Distribution Rehabilitation Plan� Safety
� Power Quality Problem Correction
� Reduce Technical Losses
� Distribution Expansion Plan� Capacity that complies with Power Quality Standards and
Controlled Technical Losses
PDC: Distribution Development PlanPDC: Distribution Development Plan
•• Technical Analysis Technical Analysis •• Economic Analysis Economic Analysis •• Financial AnalysisFinancial Analysis
Reduction and Control of Technical Losses
31
61
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
NEA SLRP
� Causes of Pilferages� Long run of secondary networks “conducive” for illegal
tapping
� Services run from one building to the next and attached to various structures (e.g., trees) making it difficult for meter readers to follow the wires or spot illegal connections
� Secondary wiring with “rat’s nest” appearance due to poor workmanship
� Inaccessible meters (located indoor or inside a compound)
� Control of meter seals
� Poor meter records (where and when the meters are installed, maintained, removed, condemned, etc.)
Reduction and Control of Non-Technical Losses
62
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
NEA SLRP
� Detection of Pilferages� Surveillance Teams (working full time)
� Consumer connections inventory to assure that:• All service connections are metered• All energized services are in an “active” status in the billing system
• There are no illegal taps, by-passed meters, or tampered meters
• Each household is metered separately (no flying taps)
• Each consumer is properly classified1. Match all service connections found in the field to a
distribution transformer2. Match the meter number to the account number3. Check meter reading against previous readings to assure
that meter readings are being properly reported
Reduction and Control of Non-Technical Losses
32
63
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
NEA SLRP
� Tampered Meters
� In-Place Quick-test for Accuracy
� Hard-to-Detect Tampering• Gear teeth removed• Small hole bored at the top of the meter housing• “Floating Neutral”• Swapping the line-side and load side
� Correcting Problems• Service conductors are not properly supported• Service wire insulation has deteriorated
Reduction and Control of Non-Technical Losses
64
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
NEA SLRP
� Apprehension of Pilferers
� Confronting the consumer
� Documenting the findings
� Calculating the amount of electricity stolen
� Setting the penalty amount to be charged
� Disconnecting service and removing the meter
• May include policemen or barangay officials
Reduction and Control of Non-Technical Losses
33
65
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
NEA SLRP
� Punitive Measures Against PilferersR.A. 7832 – Theft of electricity is a crime
� Removal of fraudulent hook-ups
� Collection for unregistered consumption
� Penalty charge
� Connection charge
� Disconnection of service
� Filing charges with judicial authorities
� Charging for tampering with seals
� Regularly scheduled inspections
Reduction and Control of Non-Technical Losses
66
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
NEA SLRP
� Prevention of Pilferage by Service Entrance Modification
� Installation of meters on the service pole
� Meter clustering in apartment buildings
� Better meter seals
� Security plates or cabinets
� Coaxial service cable
Reduction and Control of Non-Technical Losses
34
67
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
NEA SLRP
� Political and legal measures
� Strengthening of laws that would impose severe penalties
on employees who collaborate with consumers for the
purpose of defrauding the DU
� Modification of Procedures for recovery and prosecution
� Elimination of political interference with bill collections
� Consistent enforcement practices
� Publicize successes
Reduction and Control of Non-Technical Losses
68
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
NEA SLRP
� Complaints for low voltage from the customers
� Look for the overload distribution transformers and compared the billings of all customers connected to that DT.
� Distribution transformers that always trips may be suspected for illegal connections.
Reduction and Control of Non-Technical Losses
35
69
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
SHORT CIRCUIT ANALYSIS
70
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
1. What is Short Circuit?
2. Short Circuit Studies
3. Selection of Device Duties
Short Circuit Analysis
36
71
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
+
-
Very Large
Current
Flow
Short Circuit
Very Small Resistance
What is Short Circuit?
∞⇒→
=0R
VI
72
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
What is Short Circuit?
Analogy of Normal and Short Circuit Current in a Hydroelectric plant
37
73
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Equipment Explosion because of Short Circuit
What is Short Circuit?
74
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Line-to-Line Fault
Double Line-to-Ground Fault Single Line-to-Ground Fault
Three Phase Fault
Type of Faults
What is Short Circuit?
38
75
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
FaultMV
LV
UtilityG
Fault Current Contributors
Sources of Short Circuit Currents
What is Short Circuit?
76
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
� Low Voltage Fuses
� Up to 1000 Volts
� High Voltage Fuses
� Above 1000 Volts
What is Short Circuit?PROTECTIVE DEVICES: FUSE
39
77
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
What is Short Circuit?PROTECTIVE DEVICES: LOW VOLTAGE
CIRCUIT BREAKERS
Molded-Case Circuit Breakers
Low Voltage Power Circuit
Breakers
78
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Substation Vacuum Circuit Breakers
Outdoor-Type Circuit Breaker in Switchyard
What is Short Circuit?PROTECTIVE DEVICES: HIGH VOLTAGE
CIRCUIT BREAKERS
40
79
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
What is Short Circuit?PROTECTIVE DEVICES: HIGH VOLTAGE
CIRCUIT BREAKERS
Indoor Type Circuit Breaker in a Switchgear
80
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Short Circuit Studies
Short Circuit Current and Time Characteristics of Protective Devices
41
81
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Short Circuit Studies
� Comparison of Momentary and Interrupting Duties of Interrupting Devices
� Comparison of Short-time or withstand rating of system components
� Selection of rating or setting of short circuit protective devices
� Evaluation of current flow and voltage levels in the system during fault
82
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
� First Cycle Fault Current
� Short circuit ratings of low voltage equipment
� Ratings of Medium Voltage (MV) to High Voltage (HV) switch and fuse
� Close & Latch (Making) capacity or ratings of HV Circuit Breakers
� Maximum Fault for coordination of instantaneous trip of relays
Short Circuit Studies
42
83
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
� 1.5 to 4 Cycles Fault Current
� Interrupting (breaking) duties of HV circuit breakers
� Interrupting magnitude and time of breakers for coordination
� 30 Cycles Fault Current
� For time delay coordination
Short Circuit Studies
84
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
� ANSI/IEEE: American National Standards Institute/ Institute of Electrical and Electronics Engineers
� IEC: International ElectrotechnicalCommission
Prescribes Test Procedures and
Calculation Methods
Selection of Device Duties
43
85
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Selection of Device Duties
40.277428013.8 KV13.8 – 1000
30.45813.56013.8 KV13.8 – 750
19.637214013.8 KV13.8 – 500
46.97848.6804.16 KV4.16 – 350
33.25835604.16 KV4.16 – 250
10.11910.5204.16 KV4.16 – 75
Short-Circuit Capability (Symmetrical RMS Current at 3-Cycle Parting
Time
Closing and Latching
Capability (Total First Cycle RM Current)
Interrupting Rating (Total RMS Current at 4-cycle Contact-Parting Time
Momentary Rating (Total 1st-Cycle RMS Current
Example Maximum System Operating Voltage
Circuit Breaker Nominal Size Identification
8-Cycle Total-Rated Circuit Breakers (KA)
5-Cycle Symmetrical-Rated Circuit Breakers (KA)
86
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
COMPARISON OF DUTIES
S/S 3 2.30005 1.99190 2.86464 2.76467 2.86464 15 524 % Adequate
PG-17 3 2.09517 1.81447 2.32896 2.21705 2.32896 4 172 % Adequate
PG-26 3 1.98127 1.71583 2.10904 1.96635 2.10904 4 190 % Adequate
PG-40 3 1.82417 1.57978 1.85435 1.66821 1.85435 4 216 % Adequate
PG-52 3 1.70334 1.47514 1.68370 1.46936 1.70334 4 235 % Adequate
PG-53 3 1.69336 1.46650 1.67035 1.45395 1.69336 4 236 % Adequate
PG-63 3 1.59908 1.38485 1.54879 1.31529 1.59908 4 250 % Adequate
PG-17-1 3 2.08156 1.80268 2.30059 2.18533 2.30059 4 174 % Adequate
PG-17-2 1 0.00000 0.00000 0.00000 2.14564 2.14564 4 186 % Adequate
PG-17-1-3 1 0.00000 0.00000 0.00000 2.01008 2.01008 4 199 % Adequate
PG-17-2-3 1 0.00000 0.00000 0.00000 2.06014 2.06014 4 194 % Adequate
PG-17-3-7 1 0.00000 0.00000 0.00000 1.87921 1.87921 4 213 % Adequate
PG-26-5 3 1.86883 1.61845 2.15303 1.79814 2.15303 4 186 % Adequate
PG-26-5-3 1 0.00000 0.00000 0.00000 1.54157 1.54157 4 259 % Adequate
PG-40-2 3 1.78352 1.54457 1.83166 1.61561 1.83166 4 218 % Adequate
PG-40-2-5 1 0.00000 0.00000 0.00000 1.50666 1.50666 4 265 % Adequate
PG-40-2-6 1 0.00000 0.00000 0.00000 1.58620 1.58620 4 252 % Adequate
PG-52-7 1 0.00000 0.00000 0.00000 1.38134 1.38134 4 290 % Adequate
PG-53-1 1 0.00000 0.00000 0.00000 1.44395 1.44395 4 277 % Adequate
LATERAL LINES
LATERAL LINES
LATERAL LINES
BACKBONE LINES
LATERAL LINES
LATERAL LINES
RemarksSLGF
(KA)
MAX
I
SC
DutyMargin
TFF
(KA)BUS ID
LLF
(KA)
DLGF
(KA)PHASE
44
87
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
POWER SYSTEM RELIABILITY ANALYSIS
88
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Reliability Analysis
1. What is Reliability?
2. Measuring Reliability
3. Component Reliability
4. System Reliability
5. Distribution System Reliability
6. Economics of Power System Reliability
45
89
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
� Outage (Component State)
Component is not available to perform its intended function due to the event directly associated with that component (IEEE-STD-346).
� Interruption (Customer State)
Loss of service to one or more consumers as a result of one or more component outages (IEEE-STD-346).
� Types of Interruptions
Momentary Interruption. Service restored by switching operations (automatic or manual) within a specified time (5 minutes per IEEE-STD-346).
Sustained Interruption. An interruption not classified as momentary
What is Reliability?
90
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
A reliable piece of equipment or a System is understood to be basically sound and give trouble-free performance in a given environment.
But, How do you measure reliability? How do we compare reliability of the same equipment from two different manufacturers?
Definition of Reliability
Reliability is the probability that an equipment or system will perform satisfactorily for at least a given period of time when used under stated conditions.
What is Reliability?
46
91
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
System
Failure
Failure
Events
Mathematical
Reliability
Model
Reliability Data
Application
(Reliability Index)
1
2
3
4
5
Measuring Reliability
Power System Reliability Evaluation
92
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
INCIDENTS
HISTORICAL
ASSESSMENT
COMPONENT
PERFORMANCE
PREDICTIVE
ASSESSMENT
ORGANIZATION,
CUSTOMER, kVA
COMPONENT
POPULATION
SYSTEM
DEFINITION
HISTORICAL SYSTEM
PERFORMANCE
MANAGEMENT
OPERATIONS
ENGINEERING
CUSTOMER INQUIRIES
PREDICTED SYSTEM
PERFORMANCE
COMPARATIVE EVALUATIONS
AID TO DECISION-MAKING
PLANNING STUDIES
Measuring Reliability
47
93
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Component Reliability
Component Failure Data
26610
1869
1418
1117
866
635
464
343
202
81
Time-to-Failure (hrs.)Item No.How Reliable
is the
component?
94
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Failure Density Function
f(t)
80186 – 266
45141 – 186
30111 – 141
2586 – 111
2363 – 86
1746 – 63
1234 – 46
1420 – 34
128 – 20
80 – 8
f(t)∆∆∆∆tiTime
0013.080
101=
0022.045
101=
0033.030
101=
0084.012
101=
0074.014
101=
0084.012
101=
0125.08
101=
measure of the overall speedat which failures are occurring.
0059.017
10=
0043.023
101=
0040.025
101=
1
Component Reliability
48
95
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
0.2
0.4
0.6
0.8
1.0
1.2
1.4
100 200 300
f(t)
fra
ctiona
l fa
ilure
s/h
r.x1
0-2
00
Operating time, hr.
Failure Density Function from Component Failure Data
Component Reliability
96
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Failure Hazard Function h(t)
80186 – 266
45141 – 186
30111 – 141
2586 – 111
2363 – 86
1746 – 63
1234 – 46
1420 – 34
128 – 20
80 – 8
h(t)∆∆∆∆tiTime
0125.08
101=
093.012
91=
0096.014
81=
0119.012
71=
0111.030
31=
0111.045
21=
0125.080
11=
measure of the instantaneous speed of failure
[Propones to Failure]
0098.017
61=
0087.023
51=
0100.025
41=
Component Reliability
49
97
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
0.2
0.4
0.6
0.8
1.0
1.2
1.4
100 200 30000
h(t
) fa
ilure
s/h
r.x1
0-2
Operating time, hr.
Hazard Function from Component Failure Data
Component Reliability
0.011 failure/hr x 8760 hrs/yr = 97 failures/yr
98
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Component Reliability
( )( )∫=
−t
dh
etR 0ττ
Reliability Function
For a component with a constant Hazard
h = 0.01 f/yr
h = 0.02 f/yr
R(1) = 0.99
R(1) = 0.98
[Probability that the component will not fail in 1 year]
For the component with a hazard rate of 0.011 f/hr,
R(1 hour) = 0.989 R(24 hours) = 0.768
50
99
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
( )th
λ
t
a. Constant Hazard b. Increasing Hazard
Component Reliability
t
( )th
Kt
( )th
t
0K
10 KK0t
a. Decreasing Hazard
( )( )∫=
−t
dh
etR 0ττ
Reliability Function
100
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
a. Hazard Function
b. Failure Density Function
The Bathtub Curve
Component Reliability
51
101
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Hazard Model for Different System
a. Mechanical b. Electrical c. Software
Component Reliability
102
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Hazard function
( ) Kth
1
2
3
4
5
1 2→t5.0m −=
0m =5.0m =
1m =
2m =3m =
Weibull Model (A General Reliability Model)
Component Reliability
Reliability function
( )tR
1
2
3
4
5
1 2→τ
5.0m −=0m =
5.0m =
1m =2m =3m =
52
103
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
• 1997: 996 DT Failures
• Average of three (3) DT Failures/day
• Lost Revenue during Downtime
• Additional Equipment Replacement Cost
• Lost of Customer Confidence
Distribution Transformer Failures
RELIABILITY ASSESSMENTof MERALCO Distribution Transformers*
* R. R. del Mundo, et. al. (2000)
� Identify the Failure Mode of DTs
� Develop strategies to reduce DT failures
Component Reliability
104
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
•Gather Equipment History (Failure Data)
• Classify DTs (Brand, Condition, KVA, Voltage)
•Develop Reliability Model
•Determine Failure Mode
• Recommend Solutions to Improve Reliability
METHODOLOGY: Reliability Engineering(Weibull Analysis of Failure Data)
Component Reliability
53
105
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Parametric Model
• Shape Factor Failure Mode
• Characteristic Life
Shape Factor Hazard Function Failure Mode
< 1 Decreasing Early
= 1 Constant Random
> 1 Increasing Wear-out
Component Reliability
106
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
MERALCO DTs (1989–1997)
51,1292,3381,5881,11844,341TOTAL
69----H
79----G
168----F
192----E
2,344-901162,037D
6,5612131496,358C
6,5862691351185,986B
34,7122,0481,33383529,960A
TotalConvertRewindRecondNewBrand
Note: Total Include Acquired DTs
Component Reliability
54
107
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Reliability Analysis: All DTsInterval Failures Survivors Hazard
200 1444 57095 0.0269
400 797 48852 0.0178
600 638 39997 0.0174
800 508 32802 0.0167
1000 475 27515 0.0189
1200 363 22129 0.0178
1400 295 18200 0.0178
1600 224 14690 0.0167
1800 159 11865 0.0151
2000 89 9010 0.0114
2200 98 6473 0.0177
2400 51 4479 0.015
2600 19 2254 0.0122
2800 2 821 0.0042
3000 0 127 0
Component Reliability
108
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
0
0.005
0.01
0.015
0.02
0.025
0.03
0 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 3000
Haza
rd
Time Interval
Weibull Shape = 0.84
Reliability Analysis: All DTs
Failure Mode: EARLY FAILURE
Is it Manufacturing Defect?
Component Reliability
55
109
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
BRAND Size Shape Failure Mode
A 34712 0.84 Early Failure
B 6586 0.81 Early Failure
C 6561 0.86 Early Failure
D 2344 0.76 Early Failure
E 192 0.85 Early Failure
F 168 0.86 Early Failure
G 79 0.76 Early Failure
H 69 0.98 Early Failure
Reliability Analysis: By Manufacturer
Component Reliability
110
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
BRAND New Reconditioned Rewinded Converted
A 1.11 1.23 1.12 1.4
B 0.81 1.29 1.27 1.23
C 0.81 1.13 0.77 0.94
D 0.67 1.11 1.49 -
Reliability Analysis: By Manufacturer & Condition
Component Reliability
56
111
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Reliability Analysis: By Voltage Rating
PRI SEC All DTs New DTs
20 7.62 0.75 -
20 120/240 0.79 0.94
20 139/277 1.14 1.1
20 DUAL 0.72 1.03
13.2 120/240 0.88 1.54
13.2 240/480 0.91 -
7.62 120/240 0.99 1.46
7.62 DUAL 0.77 -
4.8 120/240 0.87 1.61
3.6 120/240 0.78 1.17
2.4 120/240 1.15 -
Component Reliability
112
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
KVA Shape Failure Mode
10 1.3 Wear-out
15 1.25 Wear-out
25 0.92 Early
37.5 0.83 Early
50 0.73 Early
75 1.05 Random
100 1.04 Random
167 1.16 Random
250 1.11 Random
333 1.46 Wear-out
Reliability Analysis: By KVA Rating (New DTs)
Component Reliability
57
113
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
MERALCO Distribution Transformer Reliability Analysis: Recommendations
• Review Replacement Policies
- New or Repair
- In-house or Remanufacture
• Improve Transformer Load Management Program
- Predict Demand Accurately (TLMS)
• Consider Higher KVA Ratings
• Consider Surge Protection for 20 kV DTs
Component Reliability
114
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Hazard
rate
m 2m 3m
Effect of PM on Decreasing Hazard Rate
Hazard
rate
m 2m 3m
Effect of PM on Constant Hazard Rate
Hazard
rate
m 2m 3m
Effect of PM on Increasing Hazard Rate
Component Reliability
Preventive Maintenance and Hazard Rates
58
115
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Component Reliability
RELIABILITY ASSESSMENTof MERALCO Power Circuit Breakers*
* R. R. del Mundo & Melendrez (2001)
VOLTAGE OCB VCB GCB MOCB ACB
34.5 KV 149 160 41
13.8 KV 7 28 2 36 12
6.24 KV 26 3 122
4.8 KV 2 11
TOTAL 156 216 43 39 145
Number of Feeder Power Circuit Breakers
116
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Annual Failures of 34.5 kV OCBs
2.6363145414961553158Totals
0.645----1155--Mechanism Failure
1.3171145314931551158Bushing Failure
1.152145114921552158Contact Wear
FailedInstalled FailedInstalledFailedInstalledFailedInstalled
Average Failures
(Units/yr)
2000199919981997Causes of
Failure
3 Circuit Breakers failing per year!
Preventive Maintenance Policy: Time-based (Periodic)
Component Reliability
RELIABILITY ASSESSMENTof MERALCO Power Circuit Breakers*
59
117
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
HAZARD FUNCTION CURVE FOR ALL PCBs CONSIDERED
0
0.1
0.2
0.3
0.4
3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48 51 54 57 60
Time Interval (months)
Ha
za
rd R
ate
.
All PCBs
HAZARD FUNCTION CURVE FOR 34.5 KV OCBs
0
0.1
0.2
0.3
0.4
3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48 51 54 57 60
Time Interval (months)
Ha
za
rd R
ate
34.5 kV OCBS OCBs
HAZARD FUNCTION CURVE FOR 34.5 KV GCBs
0
0.05
0.1
0.15
0.2
6 12 18 24 30 36 42 48 54 60
Time Interval (months)
Ha
za
rd R
ate
34.5 kV GCBs
HAZARD FUNCTION CURVE FOR 13.8 KV MOCBs
0
0.1
0.2
0.3
0.4
3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48 51 54 57 60
Time Interval (months)
Ha
za
rd R
ate
13.8 kV MOCBs
HAZARD FUNCTION CURVE FOR 6.24 KV MOCBs
0
0.1
0.2
0.3
0.4
3 6 9 12 15 18 24 30 36 42 48 54 60
Time Interval (months)
Ha
za
rd R
ate
6.24 kV MOCBs
HAZARD FUNCTION CURVE FOR 6.24 KV ACBs
0
0.05
0.1
0.15
0.2
6 12 18 24 30 36 42 48 54 60
Time Interval (months)
Ha
za
rd R
ate
6.24 kV ACBs
Reliability Assessment of MERALCO Power Circuit Breakers
TIME-BASED HAZARD FUNCTION
118
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
TRIPPING OPERATIONS-BASED HAZARD FUNCTION
HAZARD FUNCTION CURVE FOR 34.5 KV OCBs
00.05
0.10.15
0.20.25
5 10 15 20 25 30 35
Tripping Interval
Ha
za
rd R
ate
HAZARD FUNCTION CURVE FOR 34.5 KV OCBs
00.05
0.10.15
0.20.25
5 10 15 20 25 30 35
Tripping Interval
Ha
za
rd R
ate
y = 0.00006x2 – 0.0007x
+ 0.032
HAZARD FUNCTION CURVE FOR 34.5 KV GCBs
0
0.01
0.02
0.03
0.04
0.05
25 50 75 100 125 150
Tripping Interval
Ha
za
rd R
ate
All PCBs
34.5 kV OCBS OCBs 34.5 kV GCBs 13.8 kV MOCBs
6.24 kV MOCBs 6.24 kV ACBs
HAZARD FUNCTION CURVE FOR 34.5 KV GCBs
0
0.01
0.02
0.03
0.04
0.05
25 50 75 100 125 150
Tripping Interval
Ha
za
rd R
ate
HAZARD FUNCTION CURVE FOR 6.24 KV
MOCBs
0
0.1
0.2
0.3
5 10 15 20
Tripping Interval
Ha
za
rd R
ate
HAZARD FUNCTION CURVE FOR 6.24 KV
MOCBs
0
0.1
0.2
0.3
5 10 15 20
Tripping Interval
Ha
za
rd R
ate
Reliability Assessment of MERALCO Power Circuit Breakers
60
119
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Schedule of Servicing for 41XV4
0
0.02
0.04
0.06
0.08
0 10 20 30 40 50 60 70
Number of Tripping Operations
Hazard
Rate
Reliability-BasedPreventive Maintenance Schedule
Component Reliability
RELIABILITY ASSESSMENTof MERALCO Power Circuit Breakers*
120
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
System Reliability
Series Reliability Model
This arrangements represents a system whose subsystems of components form a series network. If any of the subsystem of component fails, the series system experiences an overall system failure.
R(x1) R(x2) R(x3) R(x4)
Series System
( )∏=
=n
i
is xRR1
61
121
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Parallel Reliability Model
R(x1)
R(x2)
R(x3)
R(x4)
Parallel Network
This structure represents a system that will fail if and only if all the units in the system fail.
( )[ ]∏=
−−=n
i
is xRR1
11
System Reliability
122
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Standby Redundancy Model
This type of redundancy represents a distribution with one
operating and n units as standbys. Unlike a parallel network
where all units in the configuration are active, the standby units
are not active.
R(x1)
R(x2)
R(x3)
R(x4)
System Reliability
62
123
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
K-Out-of-N Reliability Model
This is another form of redundancy. It is used where a specified number of units must be good for the system success.
R(x1)
R(x2)
R(x3)
The system reliability for k-out-of-n number of independent and identical units is given by
∑=
−−
=
n
ki
ini
s )R(Ri
nR 1
System Reliability
124
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Primary side
Secondary side
1
2
3
45
6
7
89
10
11
12
13
14
15
1617
18
19
2021
22
23
2425
26
27
28
29
30
31
32
33
34
35
3637
38
39
40
41
4243
44
4546
47
4849
50
51
52
5354
55
56
57
58
Scheme 1: Single breaker-single bus(primary and secondary side)
Reliability Network Models for Typical Substation Configurations of MERALCO*
System Reliability Networks
* Source: A. Gonzales (Meralco) & R. del Mundo (UP), 2005
63
125
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
15λλλλc 29λλλλct 2λλλλbus 4λλλλd1 2λλλλb1λλλλp 2λλλλb2 3λλλλd2
Summary of Substation Reliability Indices for Scheme 1
0.8287840.2471521.0Total
Opened 115kV bus tie breaker & opened 34.5kV bus tie breaker (normal condition)
0.8287840.2471521.0
Us (hr/yr)λs (failure/yr)ProbabilityEvent 1
where: λλλλs - substation failure rate or interruption frequency
Us – substation annual outage time or unavailability
Reliability Network Diagram of Single breaker-single bus scheme (Scheme 1)
System Reliability Networks
126
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Primary side
Secondary side
1
2
3
4
7
65
8
9
10 11
12
13
14
15
1617
18
1920
21
22
23
24
25
26
2728
2930
31
32
3334
35
36
37
38
39
40
41
42
43
44
45
46
4748
49
50
51
5253
5455
61
5657
58
5960
62
6364
6566
67
68
69
70
71
72
7374
75
76
77
78
79
80
81
82
8384
8586
8788
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104105
106107
108
109
110111
112
113
114
115
116
117
118
119
120
121
122123
124125
126
127128
129
130
131132
133
134
135136
137
138
139
140
141
L1 L2
Bank 2Bank 1Scheme 2: Single breaker-double bus (primary side) and two single breaker-single bus with bus tie breaker (secondary side)
Reliability Network Models for Typical Substation Configurations of MERALCO
System Reliability Networks
64
127
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
16λλλλc 29λλλλct 2λλλλbus 3λλλλd1 2λλλλb1λλλλp 2λλλλb2 3λλλλd2
20λλλλc 37λλλλct 3λλλλbus5λλλλd1 2λλλλb1
λλλλp 2λλλλb2 3λλλλd2
20λλλλc 37λλλλct 2λλλλbus 3λλλλd1 2λλλλb1λλλλp 3λλλλb2 5λλλλd2
20λλλλc 37λλλλct 2λλλλbus 3λλλλd1 2λλλλb1λλλλp 3λλλλb2 5λλλλd2
Event 1: Opened 115kV and 34.5kV bus tie breakers; P1 = 0.997985
Event 2: Closed 115kV bus tie breaker & opened 34.5kV bus tie breaker; P2 = 0.000188
Event 3: Closed 115kV bus tie breaker & closed 34.5kV bus tie breaker; P3 = 0.000000344
Event 4: Opened 115kV bus tie breaker & closed 34.5kV bus tie breaker; P4 = 0.00182614
Substation Reliability ModelsSubstation Reliability Models
Reliability Network Diagram of Single breaker-double bus with normally opened 115kV bus tie breaker (Scheme 2)
128
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
0.8492750.2518661.0Total
1.0238400.3089360.0018264
1.0238400.3089360.0000003443
1.0083740.3029660.0001882
0.8489190.2517520.9979851
Us (hr/yr)λs (failure/yr)ProbabilityEvent
Summary of Substation Reliability Indices for Scheme 2
Event 1: With two primary lines energized & opened 34.5kV bus tie breaker; P1 = 0.997985
Substation Reliability ModelsSubstation Reliability Models
65
129
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
λλλλΒ4λλλλ54 λλλλΒ3
λλλλΒ1
λλλλΒ6λλλλΒ4
λλλλΒ3
λλλλΒ7
λλλλΒ2
λλλλΒ7
λλλλΒ3λλλλΒ1
λλλλΒ4
λλλλΒ3
λλλλ29
λλλλΒ1
λλλλ17
λλλλΒ1
λλλλΒ9λλλλΒ4
λλλλΒ3
λλλλ29
λλλλΒ2
λλλλΒ6
λλλλΒ3λλλλΒ2
λλλλΒ5
Event 1: With two primary lines energized & opened 34.5kV bus tie breaker; P1 = 0.997985
Substation Reliability ModelsSubstation Reliability ModelsReliability Network Diagram of Single breaker-double bus with normally closed 115kV bus tie breaker (Modified Scheme 2)
Event 2: With one line, L2 interrupted & opened 34.5kV bus tie breaker; P2 = 0.000188
λλλλB1 λλλλB2 λλλλB3 λλλλB4λλλλB5
λλλλ17
Event 3: With one line, L2 interrupted and closed 34.5kV bus tie breaker; P3 = 0.000000344
λλλλ29 λλλλB1 λλλλB2λλλλ17 λλλλB5
λλλλB8 λλλλB9 λλλλB10 λλλλB11
130
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Event 4: With two lines energized and closed 34.5kV bus tie breaker; P4 = 0.001826140
λλλλΒ1
λλλλΒ6
λλλλΒ10
λλλλΒ1
λλλλΒ7 λλλλΒ4
λλλλΒ3
λλλλ17
λλλλΒ6
λλλλΒ7
λλλλΒ3λλλλΒ2
λλλλΒ5 λλλλΒ8
λλλλΒ4
λλλλΒ3
λλλλΒ6
λλλλΒ2
λλλλ111λλλλ29 λλλλΒ11
λλλλΒ6
λλλλΒ9 λλλλΒ4
λλλλΒ3
λλλλΒ8
λλλλΒ7
λλλλΒ9
λλλλΒ3λλλλΒ7
λλλλΒ4
λλλλΒ3
λλλλ17
λλλλΒ7
Substation Reliability ModelsSubstation Reliability ModelsReliability Network Diagram of Single breaker-double bus with normally closed 115kV bus tie breaker (Modified Scheme 2)
0.5839230.1761941.0Total
0.7584720.2332610.0018264
1.2615490.3771200.0000003443
0.8476210.2511220.0001882
0.5835480.1760760.9979851
Us,(hr/yr)λs (failure/yr)ProbabilityEvent
Summary of Substation Reliability Indices for Modified Scheme 2
66
131
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
0.5839230.176194Modified (closed 115kV bus tie breaker)
0.8492750.251866Original (opened 115kV bus tie
breaker)
Us (hr/yr)λs (failure/yr)Scheme 2
Comparison of Substation Reliability Indices for Scheme 2
Note: A remarkable 30% improvement in the performance of Scheme 2 by making the 115kV bus tie breaker normally closed.
Substation Reliability ModelsSubstation Reliability Models
132
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Primary side
Secondary side
1
2
3
4
5
67
8
9
1011
1213
1415
16
17
18
19
2021
22
23
2425
26
27
2829
30
31
32
33
34
35
36
37
38
3940
4142
43
4445
46
47
48
49
5051
5253
54
55
5657
58
59
6061
62
63
64
65
66
67
6869
7071
7273 74
75
7677
7879
8081
82
83
95
84
8586
87
88
8990
9192
93
94
96
97
98
99
100101
102
103
104 105
106
107
108109
110
111
112
113114 115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
B2
B3
B5
B6
B7 B8
B10
B9
B1 B4
3 69
Bank 1 Bank 2Scheme 3: Ring bus (primary side) and two single breaker-single bus with bus tie breaker (secondary side)
Reliability Network Models for Typical Substation Configurations of MERALCO
System Reliability Networks
67
133
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
λλλλ17
λλλλB1
λλλλB4
λλλλB1
λλλλB5
λλλλB6
λλλλB4
λλλλB2
λλλλB3
λλλλB2
λλλλB5
λλλλ51 λλλλB7 λλλλB10
Event 1: With two primary lines energized & opened 34.5kV bus tie breaker; P1 = 0.997985
Event 2: With two primary lines energized & closed 34.5kV bus tie breaker; P2 = 0.00182614
λλλλ31
λλλλB1
λλλλB4
λλλλB1
λλλλB5
λλλλB6
λλλλB4
λλλλB2
λλλλB3
λλλλB3
λλλλB6
λλλλB8 λλλλB9 λλλλ51 λλλλB10
Substation Reliability ModelsSubstation Reliability ModelsReliability Block Diagram of Ring Bus Scheme (Scheme 3)
134
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Event 3: With one primary line (L2) interrupted and opened 34.5kV bus tie breaker; P3 = 0.000188056
λλλλ17
λλλλB2
λλλλB3
λλλλB2
λλλλB5
λλλλB7 λλλλ51 λλλλB10λλλλB1
λλλλB2
λλλλ31
λλλλB2
λλλλB6
Event 4: With one primary line (L2) interrupted and closed 34.5kV bus tie breaker; P4 = 0.000000344
λλλλ31
λλλλB2
λλλλB3
λλλλB3
λλλλB6
λλλλB8 λλλλB9 λλλλ51λλλλB1
λλλλB3
λλλλ17
λλλλB3
λλλλB5
λλλλB10
Substation Reliability ModelsSubstation Reliability ModelsReliability Block Diagram of Ring Bus Scheme (Scheme 3)
CONT.
68
135
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
0.4368360.1380341.0Total
0.6501140.2044670.0000003444
0.4682330.1472830.0001883
0.6183790.1951120.0018262
0.4364990.1379280.9979851
Us (hr/yr)λs (failure/yr)ProbabilityEvent
Summary of Substation Reliability Indices of Ring Bus (Scheme 3)
Substation Reliability ModelsSubstation Reliability Models
136
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Secondary
side
Primary
side
1
2
34
56
78
9
1
0
1
1
1
2
1
3
1
4
1
5
16
1
7
1
8 19
2
02
12
2 232
4 2
62
82
9
3
0313
23
33
4 353
6 3
73
83
94
0414
2
11
9
4
3
44
4
5
7
9
4
6
4
74
8 4
9505
15
25
3 5
455 5
6575
85
9 606
1
6
263 6
46
56
66
76
86
9 7
07
1 7
27
374
7
5767
7
7
8
8
0
8
1
8
2
8
3
8
4
8
5
8
6
8
7
8
8
8
9
9
0
9
1
9
2
93
94
9
59
6979
8 9
910
010110
2 10
310
4 10
5
10
610
710
810
911
0 111
11
211
311
4 11
511
6 11711
8
12
0
121
12
2
12
3
12
412
5 126
12712
812913
0 13
113
213
313
4 13
5136 13
713
813
914
0
141
14
2
14
3
14
414
5
14
6
14
7
148
14
9
150
15
1
15
2
153
154
3
2
9
8
0
10
5
B1
B2
B3
B4
B5
B8
B6
B7
B9 B10
B1
1
2
52
7
L
1
L
2
Bank
1
Bank
2Scheme 4: Breaker-and-a-half bus (primary
side) and two single breaker-single bus with bus tie breaker
(secondary side)
Reliability Network Models for Typical Substation Configurations of MERALCO
System Reliability Networks
69
137
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
λλλλΒ1
λλλλΒ5
λλλλΒ12
λλλλΒ3
λλλλΒ4
λλλλΒ2
λλλλΒ8
λλλλ6
λλλλ17
λλλλΒ1λλλλ6
λλλλ17
λλλλ7
λλλλΒ1
λλλλΒ7
λλλλ33
λλλλΒ2
λλλλΒ3
λλλλΒ7
λλλλΒ6
λλλλΒ1
λλλλ34
λλλλΒ3
λλλλ33
λλλλΒ5
λλλλΒ2
λλλλΒ3
λλλλΒ4
λλλλΒ3
λλλλ119
λλλλΒ3
λλλλΒ7
λλλλΒ3λλλλΒ3
λλλλΒ9 λλλλ62
λλλλΒ4
λλλλΒ3
λλλλΒ8
λλλλΒ3
A
Event 1: With two primary lines energized and opened 34.5kV bus tie breaker; P1 = 0.997985
λλλλΒ2
λλλλΒ5
λλλλ6
λλλλ119
λλλλΒ3λλλλ6
λλλλΒ8
λλλλ7
λλλλΒ3
λλλλΒ5
λλλλ33
λλλλΒ2
λλλλΒ3
λλλλ17
λλλλΒ5
λλλλΒ3
λλλλ34
λλλλΒ3
λλλλ33
λλλλΒ6
λλλλΒ3
λλλλΒ5
λλλλΒ2
λλλλΒ2
λλλλ6
λλλλΒ4
λλλλΒ1λλλλ6
λλλλ119
λλλλ7
λλλλΒ1
λλλλΒ2
λλλλ33
λλλλΒ2
λλλλΒ3
λλλλΒ7
λλλλΒ2
λλλλΒ1
λλλλ34
λλλλΒ3
λλλλ33
λλλλΒ8
λλλλΒ1
λλλλΒ2
λλλλ34
λλλλΒ3
λλλλ33
λλλλ17
λλλλΒ1
λλλλΒ4A
λλλλ33
λλλλΒ2
λλλλΒ3
λλλλ119
λλλλ17
λλλλΒ1
Substation Reliability ModelsSubstation Reliability Models
Reliability Block Diagram of Breaker-and-a-half Scheme (Scheme 4)
138
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
λλλλΒ1
λλλλΒ5
λλλλΒ12
λλλλΒ7
λλλλΒ8
λλλλΒ2
λλλλΒ8
λλλλ6
λλλλ17
λλλλΒ5λλλλ6
λλλλΒ7
λλλλ7
λλλλΒ1
λλλλΒ2
λλλλ33
λλλλΒ2
λλλλΒ3
λλλλΒ7
λλλλΒ6
λλλλΒ1
λλλλ34
λλλλΒ3
λλλλ33
λλλλΒ5
λλλλΒ2
λλλλΒ3
λλλλΒ4
λλλλΒ3
λλλλ119
λλλλΒ7
λλλλΒ7
λλλλΒ3λλλλΒ3
λλλλΒ11 λλλλ62
λλλλΒ4
λλλλΒ3
λλλλΒ7
λλλλΒ4
Aλλλλ139λλλλΒ10
λλλλΒ2
λλλλΒ5
λλλλ6
λλλλΒ7
λλλλ119λλλλ6
λλλλ17
λλλλ7
λλλλΒ4
λλλλΒ5
λλλλ33
λλλλΒ2
λλλλΒ3
λλλλΒ8
λλλλΒ6
λλλλΒ5
λλλλ34
λλλλΒ3
λλλλ33
λλλλΒ6
λλλλΒ4
λλλλΒ5
λλλλΒ2
λλλλΒ4
λλλλ6
λλλλΒ5
λλλλΒ2λλλλ6
λλλλ119
λλλλ7
λλλλΒ2
λλλλΒ5
λλλλ33
λλλλΒ2
λλλλΒ3
λλλλΒ6
λλλλΒ5
λλλλΒ3
λλλλ34
λλλλΒ3
λλλλ33
λλλλΒ8
λλλλΒ2
λλλλΒ5
λλλλ34
λλλλΒ3
λλλλ33
λλλλ17
λλλλΒ3
λλλλΒ5A
λλλλ33
λλλλΒ2
λλλλΒ3
λλλλ119
λλλλ17
λλλλΒ5
λλλλΒ2
λλλλΒ5
λλλλ6
λλλλΒ6
λλλλ119
Event 2: With two primary lines energized and closed 34.5kV bus tie breaker; P2 = 0.001826
Substation Reliability ModelsSubstation Reliability Models
Reliability Block Diagram of Breaker-and-a-half Scheme (Scheme 4)
70
139
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
λλλλΒ3
λλλλΒ4 λλλλΒ4
λλλλΒ3
λλλλΒ8
λλλλΒ6
λλλλΒ7
λλλλΒ3λλλλΒ6
λλλλΒ4
λλλλΒ3
λλλλ119
λλλλΒ6
AλλλλΒ12λλλλΒ9 λλλλ62 λλλλΒ5
λλλλΒ4
λλλλΒ3
λλλλΒ4
λλλλΒ6
λλλλΒ4
λλλλΒ3
λλλλ17
λλλλΒ7
λλλλΒ8
λλλλΒ3 λλλλΒ4
λλλλΒ3
λλλλΒ4
λλλλ17
λλλλ119
λλλλΒ3λλλλ17
λλλλΒ4
λλλλΒ3
λλλλΒ4
λλλλΒ2
λλλλΒ4
λλλλΒ3
λλλλΒ2
λλλλ119
λλλλΒ4
λλλλΒ3
λλλλΒ3
λλλλ119
λλλλΒ7
λλλλΒ2 λλλλΒ4
λλλλΒ3
λλλλ17
λλλλΒ8
λλλλΒ3
λλλλΒ3λλλλΒ7
λλλλΒ4
λλλλΒ3
λλλλΒ2
λλλλΒ8
A
Event 3: With one primary line (L1) interrupted and opened 34.5kV bus tie breaker; P3 = 0.000188
Substation Reliability ModelsSubstation Reliability Models
Reliability Block Diagram of Breaker-and-a-half Scheme (Scheme 4)
140
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
λλλλΒ12λλλλΒ11 λλλλ62
λλλλΒ7
λλλλΒ8λλλλΒ4
λλλλΒ3
λλλλ17
λλλλΒ7
λλλλΒ7
λλλλΒ3λλλλΒ6
λλλλΒ4
λλλλΒ3
λλλλΒ2
λλλλΒ7
λλλλ139λλλλΒ10
λλλλΒ7
λλλλΒ3λλλλΒ4
λλλλΒ3
λλλλΒ7
λλλλ119
λλλλΒ7
λλλλΒ3λλλλΒ4
λλλλΒ5
Event 4: With one primary line (L1) interrupted and closed 34.5kV bus tie breaker; P4 = 0.000000344
Summary of Substation Reliability Indices of Breaker-&-a-half (Scheme 4)
0.4355450.1374131.0Total
0.6431650.2044730.0000003444
0.4669720.1466740.0001883
0.6114330.1951200.0018262
0.4352140.1373060.9979851
Us (hr/yr)λs (failure/yr)ProbabilityEvent
Substation Reliability ModelsSubstation Reliability Models
� Reliability Block Diagram of Breaker-and-a-half Scheme (Scheme 4)
71
141
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
0.4355450.137413Scheme 4 (Breaker-and-a-half bus)
0.4368360.138034Scheme 3 (Ring bus)
0.849275
0.583923
0.251866
0.176194
Scheme 2 (Single breaker-double bus)- with normally opened 115kV tie bkr.- with normally closed 115kV tie bkr.
0.8287840.247152Scheme 1 (Single breaker-single bus)
Us (hrs/yr)λs (failures/yr)Configuration
Comparison of Substation Reliability Indices (Scheme 1 to 4)
Note: Scheme 3 & 4 - better than Scheme 1 & 2 by 44% & 45% respectively for substation failure rates.Scheme 3 & 4 - better than Scheme 1 & 2 by 47% & 49% respectively for substation interruption duration or unavailabilty.Scheme 3 & 4 - better than Modified Scheme 2 by 22% & 25% for substation failure rates & unavailability, respectively
Substation Reliability ModelsSubstation Reliability Models
System Reliability Networks
142
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Distribution System Reliability
CUSTOMER-ORIENTED RELIABILITY INDICES
System Average Interruption Frequency Index (SAIFI)*The average number of interruptions per customer served
during a period
System Average Interruption Duration Index (SAIDI)The average interruption duration per customer served during a
period
servedcustomers of number Total
onsinterrupti customer of number otalTSAIFI =
servedcustomers of number Total
duration oninterrupti customer of umSSAIDI =
Note: SAIFI for Sustained interruptions. MAIFI for Momentary Interruptions
72
143
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
CUSTOMER-ORIENTED RELIABILITY INDICES
Customer Average Interruption Frequency Index (CAIFI)
The average number of interruptions per customer interrupted
during the period
Customer Average Interruption Duration Index (CAIDI)
The average interruption duration of customers interrupted
during the period
dinterrupte customers of number Total
onsinterrupti customer of number otalTCAIFI =
dinterrupte customers of number Total
duration oninterrupti customer of umSCAIDI =
Distribution System Reliability
144
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
CUSTOMER-ORIENTED RELIABILITY INDICES
Average Service Availability Index (ASAI)
The ratio of the total number of customer hours that service
was available during a year to the total customer hours
demanded
Average Service Unavailability Index (ASUI)
The ratio of the total number of customer hours that service
was not available during a year to the total customer hours
demanded
Distribution System Reliability
demanded hours Customer
serviceavailable of hours ustomerCASAI =
demanded hours Customer
serviceeunavailabl of hours ustomerCASUI =
73
145
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
LOAD- AND ENERGY-ORIENTED RELIABILITY INDICES
Average Load Interruption Index (ALII)
The average KW (KVA) of connected load interrupted per year
per unit of connected load served.
Average System Curtailment Index (ASCI)
Also known as the average energy not supplied (AENS). It is
the KWh of connected load interruption per customer served.
Distribution System Reliability
load d connecte Total
oninterrupti load TotalALII =
servedcustomers of number Total
tcurtailmenenergy TotalASCI =
146
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
LOAD- AND ENERGY-ORIENTED RELIABILITY INDICES
Average Customer Curtailment Index (ACCI)
The KWh of connected load interruption per affected customer
per year.
Distribution System Reliability
affected customers of number Total
tcurtailmenenergy TotalACCI =
74
147
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Required Data:
1. Exposure Data
N - total number of customers served
P - period of observation
2. Interruption Data
Nc - number of customers interrupted on interruption i
d - duration of ith interruption, hours
Number of
customers
interrupted
Time
1N
1d
2N
2d3N
3d
Historical Reliability Performance Assessment
Distribution System Reliability
148
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
L1 L2 L3
A B CSource
S 1 2 3
Load PointNumber of
Customers
Average Load
Demand (KW)
L1 200 1000
L2 150 700
L3 100 400
SYSTEM LOAD DATA
Interruption
Event i
Load Point
Affected
Number of
Disconnected
Customers
Average Load
Curtailed (KW)
Duration of
Interruption
1 L3 100 400 6 hours
INTERRUTION DATA
Distribution System Reliability
75
149
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
yr-customeroninterrupti 222222.0
100150200
100
N
NSAIFI
C
=
++==
∑∑
( )( )
yr-customerhours 333333.1
100150200
6100
N
dNSAIDI
C
=
++==
∑∑
( )( )
oninterrupti-custumerhours 6
100
6100
N
dNCAIDI
C
C
=
==∑∑
Distribution System Reliability
150
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
000152.0
8760
333333.1
8760
SAIDI
8760
NdNASUI
C
=
===∑∑
999848.0
000152.01ASUI1ASAI
=
−=−=
( )( )
yrcustomerKWh 333333.5
100150200
6400
N
dL
N
ENSASCI
a
−=
++===
∑∑
∑
Note: ENS - Energy Not Supplied
Distribution System Reliability
76
151
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Outage & Interruption Reporting
Distribution System Reliability
152
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
1 01/08/04 3 1.5 Line Fault at C
2* 02/06/04 All 4 Transmission
3 02/14/04 5, 6 0.5 Line Fault at D
4* 03/15/04 4, 5, 6 3 Pre-arranged
5 04/01/04 6 1.5 Overload
6* 05/20/04 3, 4 3.5 Pre-arranged
7 05/30/04 1, 2, 3 0.5 Line Tripped
8 06/12/04 1 2 Line fault
9 07/04/04 5 1 Line Overload
10* 07/25/04 All 5 Transmission
11 07/30/04 5 1 Line Fault
12* 08/15/04 4 2 Pre-arranged
13 09/08/04 2 1 Line Fault
14* 09/30/04 1, 2, 3 2.5 Pre-arranged
15 10/25/04 3 1.5 Line Tripped
16 11/10/04 2, 3 1.5 Line Fault at A
17* 11/27/04 3 2 Pre-arranged
18* 12/14/04 3, 4, 5 3.5 Pre-arranged
19* 12/27/04 2, 3 3 Pre-arranged
20 12/28/04 1, 2, 3 0.075 Line Fault
Outage & Interruption Reporting
*Not included in Distribution Reliability Performance Assessment
Historical Reliability Performance Assessment
hoursAffectedDate
77
153
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Month 1 2 3 4 5 6 Total
January 900 800 600 850 500 300 3,950
February 905 796 600 855 497 303 3,956
March 904 801 604 854 496 308 3,967
April 908 806 606 859 501 310 3,990
May 912 804 608 862 509 315 4,010
June 914 810 611 864 507 318 4,024
July 917 815 614 866 512 324 4,048
August 915 815 620 872 519 325 4,066
September 924 821 622 876 521 328 4,092
October 928 824 626 881 526 331 4,116
November 930 826 630 886 530 334 4,136
December 934 829 635 894 538 332 4,162
Annual Average 916 812 615 868 513 319 4,043
Outage & Interruption Reporting
Customer Count
Distribution System Reliability
154
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Interruption
Number
Load
Points
Affected
Number of
Customers
Affected
Duration
(Hrs.)
Customer
Hours
Curtailed
Date
1 3 600 1.5 900 01/08/04
5 497 0.5 248.5
6 303 0.5 151.5
5 6 310 1.5 465 04/01/04
1 912 0.5 456
2 804 0.5 402
3 608 0.5 304
8 1 914 2 1,828 06/12/04
9 5 512 1 512 07/04/04
11 5 512 1 512 07/30/04
13 2 821 1 821 09/08/04
15 3 626 1.5 939 10/25/04
2 826 1.5 1,239
3 630 1.5 945
11/10/0416
3
7 05/30/04
02/14/04
Outage & Interruption Reporting
Distribution System Reliability
78
155
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Outage & Interruption Reporting
Calculate the Annual Reliability Performance of the Distribution System (according to Phil. Distribution Code)
∑∑
=N
NSAIFI
C
∑∑
=N
dNSAIDI
C
∑∑
=N
NMAIFI
C
Distribution System Reliability
156
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Required Data:
1. Component Reliability Data
λi - failure rate of component i
ri - mean repair time of component i
2. System Load Data
Ni - number of customers at point i
Li - the demand at point i
Distribution
SystemSource
A
B Loads
C
λB, rB, UBSource
A
B Loads
C
λA, rA, UA
λC, rC, UC
Distribution System Reliability
Predictive Reliability Performance Assessment
79
157
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
1 2 S
1
2
P
For series combinations:
n
λλλλs = Σ λλλλii=1
n
Σ λλλλirii=1
rs = _________
λλλλs
λλλλp = λλλλ1λλλλ2 (r1 + r2)
r1 r2rp = __________
r1 + r2
For parallel combinations:
Load Point Reliability Equivalents
Distribution System Reliability
158
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
L1 L2 L3
A B CSource
S 1 2 3
Feederλλλλ
(f/year)
r
(hours)
A 0.2 6
B 0.1 5
C 0.15 8
COMPONENT DATA
Load PointNumber of
Customers
Average Load
Demand (KW)
L1 200 1000
L2 150 700
L3 100 400
SYSTEM LOAD DATA
Distribution System Reliability
80
159
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Load Point Reliability Equivalents
� For L1
� For L2
� For L3
yrf 0.2
A1
=
= λλ
hrs 6
rr A1
=
=( )( )
yrhrs 1.2
62.0
rU 111
=
=
= λ
yrf 0.3
0.10.2
BA2
=
+=
+= λλλ
( )( ) ( )( )
hrs 676666.5
1.02.0
51.062.0
rrr
BA
BBAA2
=
+
+=
+
+=
λλ
λλ
( )( )yrhrs 1.7
5.6666673.0
rU 222
=
=
= λ
yrf 0.45
0.150.10.2
3
=
++=
++= CBA λλλλ
( )( ) ( )( ) ( )( )
hrs 4444446
1501020
8150510620
3
.
...
...
rrrr
BBA
CCBBAA
=
++
++=
++
++=
λλλ
λλλ
( )( )yrhrs 9.2
6.44444445.0
rU 333
=
=
= λ
160
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
�Reliability Indices
( )( ) ( )( ) ( )( )
yrcustomeroninterrupti 288889.0
100150200
10045.01503.02002.0
N
NSAIFI
i
ii
−=
++
++==
∑∑λ
( )( ) ( )( ) ( )( )
yr-customerhours 744444.1
100150200
1009.21507.12002.1
N
NUSAIDI
i
ii
=
++
++==
∑∑
oninterrupti-customerhours 038462.6
288889.0
744444.1
SAIFI
SAIDI
N
NUCAIDI
ii
ii
=
===∑∑
λ
81
161
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
000199.0
8760
744444.1
8760
SAIDI
8760
NNUASUI
iii
=
===∑∑
999801.0
000199.01ASUI1ASAI
=
−=−=
( ) ( )( ) ( )( ) ( )( )
yr-customerKWh 888889.7
100150200
9.24007.17002.11000
N
UL
N
ENSASCI
i
iia
i
=
++
++===
∑∑
∑
162
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
A
B
C
D
1 2 3 4Source
a b c d
Typical radial distribution system
Distribution System Reliability
82
163
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Length (km) λλλλ (f/yr) r (hrs)
1 2 0.2 4
2 1 0.1 4
3 3 0.3 4
4 2 0.2 4
a 1 0.2 2
b 3 0.6 2
c 2 0.4 2
d 1 0.2 2L
ate
ral
Component
SYSTEM RELIABILITY DATA
Ma
in
Component No. of Customers Ave. Load Connected (KW)
A 1000 5000
B 800 4000
C 700 3000
D 500 2000
SYSTEM LOAD DATA
164
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
1 0.2 4 0.8 0.2 4 0.8 0.2 4 0.8 0.2 4 0.8
2 0.1 4 0.4 0.1 4 0.4 0.1 4 0.4 0.1 4 0.4
3 0.3 4 1.2 0.3 4 1.2 0.3 4 1.2 0.3 4 1.2
4 0.2 4 0.8 0.2 4 0.8 0.2 4 0.8 0.2 4 0.8
a 0.2 2 0.4 0.2 2 0.4 0.2 2 0.4 0.2 2 0.4
b 0.6 2 1.2 0.6 2 1.2 0.6 2 1.2 0.6 2 1.2
c 0.4 2 0.8 0.4 2 0.8 0.4 2 0.8 0.4 2 0.8
d 0.2 2 0.4 0.2 2 0.4 0.2 2 0.4 0.2 2 0.4
2.2 2.73 6.0 2.2 2.73 6.0 2.2 2.73 6.0 2.2 2.73 6.0
RELIABILITY INDICES FOR THE SYSTEM
Total
Load pt. A Load pt. B Load pt. C Load pt. D
Main
Late
ral
Component
failure
∑∑∑∑ === λλλ Ur ;UU ; :where totaltotaltotal
83
165
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
( )( ) ( )( ) ( )( ) ( )( )
yrcustomerint 2.2
5007008001000
5002.27002.28002.210002.2
N
NSAIFI
i
ii
−=
+++
+++==
∑∑λ
( )( ) ( )( ) ( )( ) ( )( )
yr-customerhours 0.6
5007008001000
5000.67000.68000.610000.6
N
NUSAIDI
i
ii
=
+++
+++==
∑∑
oninterrupti-customerhours 727273.2
2.2
0.6
SAIFI
SAIDI
N
NUCAIDI
ii
ii
=
===∑∑
λ
166
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
000685.0
8760
0.6
8760
SAIDI
8760
NNUASUI
iii
=
===∑∑
999315.0
000685.01ASUI1ASAI
=
−=−=
( )( ) ( )( ) ( )( ) ( )( )
yr-customerKWh 0.28
5007008001000
0.620000.630000.640000.65000
N
ULASCI
i
iai
=
+++
+++=
=∑∑
84
167
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
� Effect of lateral protection
A
B
C
D
1 2 3 4Source
a b c d
Typical radial distribution system with lateral protections
Distribution System Reliability
168
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
1 0.2 4 0.8 0.2 4 0.8 0.2 4 0.8 0.2 4 0.8
2 0.1 4 0.4 0.1 4 0.4 0.1 4 0.4 0.1 4 0.4
3 0.3 4 1.2 0.3 4 1.2 0.3 4 1.2 0.3 4 1.2
4 0.2 4 0.8 0.2 4 0.8 0.2 4 0.8 0.2 4 0.8
a 0.2 2 0.4
b 0.6 2 1.2
c 0.4 2 0.8
d 0.2 2 0.4
1.0 3.6 3.6 1.4 3.14 4.4 1.2 3.33 4.0 1.0 3.6 3.6
RELIABILITY INDICES WITH LATERAL PROTECTION
Total
Load pt. A Load pt. B Load pt. C Load pt. D
Ma
inL
ate
ral
Component
failure
∑∑∑∑ === λλλ Ur ;UU ; :where totaltotaltotal
85
169
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
( )( ) ( )( ) ( )( ) ( )( )
yrcustomerint 153333.1
5007008001000
5000.17002.18004.110000.1
N
NSAIFI
i
ii
−=
+++
+++==
∑∑λ
( )( ) ( )( ) ( )( ) ( )( )
yr-customerhours 906667.3
5007008001000
5006.37000.48004.410006.3
N
NUSAIDI
i
ii
=
+++
+++==
∑∑
oninterrupti-customerhours 387283.3
153333.1
906667.3
SAIFI
SAIDI
N
NUCAIDI
ii
ii
=
===∑∑
λ
170
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
000446.0
8760
906667.3
8760
SAIDI
8760
NNUASUI
iii
=
===∑∑
999554.0
000446.01ASUI1ASAI
=
−=−=
( )( ) ( )( ) ( )( ) ( )( )
yr-customerKWh 266667.18
5007008001000
6.320000.430004.440006.35000
N
ULASCI
i
iai
=
+++
+++=
=∑∑
86
171
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
� Effect of disconnects
A
B
C
D
1 2 3 4Source
a b c d
Typical radial distribution system reinforce with
lateral protections and disconnects
Distribution System Reliability
172
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
1 0.2 4 0.8 0.2 4 0.8 0.2 4 0.8 0.2 4 0.8
2 0.1 0.5 0.05 0.1 4 0.4 0.1 4 0.4 0.1 4 0.4
3 0.3 0.5 0.15 0.3 0.5 0.15 0.3 4 1.2 0.3 4 1.2
4 0.2 0.5 0.1 0.2 0.5 0.1 0.2 0.5 0.1 0.2 4 0.8
a 0.2 2 0.4
b 0.6 2 1.2
c 0.4 2 0.8
d 0.2 2 0.4
1.0 1.5 1.5 1.4 1.89 2.65 1.2 2.75 3.3 1.0 3.6 3.6
RELIABILITY INDICES WITH LATERAL PROTECTION AND DISCONNECTS
Total
Load pt. A Load pt. B Load pt. C Load pt. D
Ma
inL
ate
ral
Component
failure
∑∑∑∑ === λλλ Ur ;UU ; :where totaltotaltotal
87
173
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
( )( ) ( )( ) ( )( ) ( )( )
yrcustomerint 153333.1
5007008001000
5000.17002.18004.110000.1
N
NSAIFI
i
ii
−=
+++
+++==
∑∑λ
( )( ) ( )( ) ( )( ) ( )( )
yr-customerhours 576667.2
5007008001000
5006.37003.380065.210005.1
N
NUSAIDI
i
ii
=
+++
+++==
∑∑
oninterrupti-customerhours 234105.2
153333.1
576667.2
SAIFI
SAIDI
N
NUCAIDI
ii
ii
=
===∑∑
λ
174
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
000294.0
8760
576667.2
8760
SAIDI
8760
NNUASUI
iii
=
===∑∑
999706.0
000294.01ASUI1ASAI
=
−=−=
( )( ) ( )( ) ( )( ) ( )( )
yr-customerKWh 733333.11
5007008001000
6.320003.3300065.240005.15000
N
ULASCI
i
iai
=
+++
+++=
=∑∑
88
175
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
� Effect of protection failures
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
1 0.2 4 0.8 0.2 4 0.8 0.2 4 0.8 0.2 4 0.8
2 0.1 0.5 0.05 0.1 4 0.4 0.1 4 0.4 0.1 4 0.4
3 0.3 0.5 0.15 0.3 0.5 0.15 0.3 4 1.2 0.3 4 1.2
4 0.2 0.5 0.1 0.2 0.5 0.1 0.2 0.5 0.1 0.2 4 0.8
a 0.2 2 0.4 0.02 0.5 0.01 0.02 0.5 0.01 0.02 0.5 0.01
b 0.06 0.5 0.03 0.6 2 1.2 0.06 0.5 0.03 0.06 0.5 0.03
c 0.04 0.5 0.02 0.04 0.5 0.02 0.4 2 0.8 0.04 0.5 0.02
d 0.02 0.5 0.01 0.02 0.5 0.01 0.02 0.5 0.01 0.2 2 0.4
1.12 1.39 1.56 1.48 1.82 2.69 1.3 2.58 3.35 1.12 3.27 3.66
RELIABILITY INDICES IF THE FUSES OPERATE WITH PROBABILITY OF 0.9
Total
Load pt. A Load pt. B Load pt. C Load pt. D
Ma
inL
ate
ral
Component
failure
∑∑∑∑ === λλλ Ur ;UU ; :where totaltotaltotal
176
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
� Effect of load transfer to alternative supply
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
1 0.2 4 0.8 0.2 0.5 0.1 0.2 0.5 0.1 0.2 0.5 0.1
2 0.1 0.5 0.05 0.1 4 0.4 0.1 0.5 0.05 0.1 0.5 0.05
3 0.3 0.5 0.15 0.3 0.5 0.15 0.3 4 1.2 0.3 0.5 0.15
4 0.2 0.5 0.1 0.2 0.5 0.1 0.2 0.5 0.1 0.2 4 0.8
a 0.2 2 0.4
b 0.6 2 1.2
c 0.4 2 0.8
d 0.2 2 0.4
1.0 1.5 1.5 1.4 1.39 1.95 1.2 1.88 2.25 1.0 1.5 1.5
RELIABILITY INDICES WITH UNRESTRICTED LOAD TRANSFERS
Total
Load pt. A Load pt. B Load pt. C Load pt. D
Ma
inL
ate
ral
Component
failure
∑∑∑∑ === λλλ Ur ;UU ; :where totaltotaltotal
89
177
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
λλλλ
(f/yr)
r
(hrs)
U
(hrs/
yr)
1 0.2 4 0.8 0.2 1.9 0.38 0.2 1.9 0.38 0.2 1.9 0.38
2 0.1 0.5 0.05 0.1 4 0.4 0.1 1.9 0.19 0.1 1.9 0.19
3 0.3 0.5 0.15 0.3 0.5 0.15 0.3 4 1.2 0.3 1.9 0.57
4 0.2 0.5 0.1 0.2 0.5 0.1 0.2 0.5 0.1 0.2 4 0.8
a 0.2 2 0.4
b 0.6 2 1.2
c 0.4 2 0.8
d 0.2 2 0.4
1.0 1.5 1.5 1.4 1.59 2.23 1.2 2.23 2.67 1.0 2.3 2.3
RELIABILITY INDICES WITH RESTRICTED LOAD TRANSFERS
Total
Load pt. A Load pt. B Load pt. C Load pt. DS
ec
tio
nD
istr
ibu
tor
Component
failure
∑∑∑∑ === λλλ Ur ;UU ; :where totaltotaltotal
� Effect of load transfer to alternative supply
178
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Case 1 Case 2 Case 3 Case 4 Case 5 Case 6
λ (f/yr) 2.2 1.0 1.0 1.12 1.0 1.0
r (hrs) 2.73 3.6 1.5 1.39 1.5 1.5
U (hrs/yr) 6.0 3.6 1.5 1.56 1.5 1.5
λ (f/yr) 2.2 1.4 1.4 1.48 1.4 1.4
r (hrs) 2.73 3.14 1.89 1.82 1.39 1.59
U (hrs/yr) 6.0 4.4 2.65 2.69 1.95 2.23
λ (f/yr) 2.2 1.2 1.2 1.3 1.2 1.2
r (hrs) 2.73 3.33 2.75 2.58 1.88 2.23
U (hrs/yr) 6.0 4 3.3 3.35 2.25 2.67
λ (f/yr) 2.2 1.0 1.0 1.12 1.0 1.0
r (hrs) 2.73 3.6 3.6 3.27 1.5 2.34
U (hrs/yr) 6.0 3.6 3.6 3.66 1.5 2.34
SUMMARY OF INDICES
Load Point A
Load Point B
Load Point C
Load Point D
Distribution System Reliability
90
179
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Case 1 Case 2 Case 3 Case 4 Case 5 Case 6
SAIFI 2.2 1.15 1.15 1.26 1.15 1.15
SAIDI 6.0 3.91 2.58 2.63 1.80 2.11
CAIDI 2.73 3.39 2.23 2.09 1.56 1.83
ASAI 0.999315 0.999554 0.999706 0.999700 0.999795 0.999759
ASUI 0.000685 0.000446 0.000294 0.003000 0.000205 0.000241
ENS 84.0 54.8 35.2 35.9 25.1 29.1
ASCI 28.0 18.3 11.7 12.0 8.4 9.7
Case 3. As in Case 2, but with disconnects on the main feeders.
Case 4. As in Case 3, probability of successful lateral distributor fault clearing of 0.9.
Case 5. As in Case 3, but with an alternative supply.
Case 6. As in Case 5, probability of conditional load transfer of 0.6.
Sytem Indices
SUMMARY OF INDICES (cont.)
Case 1. Base case.
Case 2. As in Case 1, but with perfect fusing in the lateral distributors.
Distribution System Reliability
180
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Economics of Power System Reliability
Supply Cost
• Investment Cost
• Operation and Maintenance Cost
• Fuel Cost
Annual Supply Cost (ASC) =
Annual kWh Generation
IC + O&M + FC
91
181
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Supply Cost
1.111.310.730.08
1.141.300.310.04
1.091.3820.21
1.061.5040.45
1.031.6170.94
1.011.73131.88
0.942.00386.25
0.902.117012.26
Supply Cost(Php/kWh)
Duration(Hours)
Frequency(per year)
LOLP(days/yr)
Luzon Grid Supply Cost*
Source: del Mundo (1991)
182
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Supply Cost
Luzon Grid Supply Cost
Source: del Mundo (1991)
92
183
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
� To Electric Utility• Loss of revenues• Additional work• Loss of confidence
� To Customers• Dissatisfaction• Interruption of productivity• Additional investment for alternative power supply
� To National Economy• Loss value added/income• Loss of investors• Unemployment
Outage Cost
Impact of Power Interruptions
184
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Impact to National Economy:
�NEDA Study (1974)� P 342,380 per day – losses due to brownout in Cebu-Mandaue
area
�Business Survey (1980)� P1.4 Billion – losses due to brownouts in 1980
�CRC Memo No. 27 (1988)� P 3.4 Billion – loss of the manufacturing sector in 1987 due to
power outages
�Viray & del Mundo Study (1988)� P 25 – losses in Value Added per kWh curtailment
�Sinay Report (1989)� 45% – loss in Value Added in the manufacturing sector in
Cebu due to power outages
Outage Cost
93
185
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Impact to Customers:
A. Short-Run Direct Cost• Opportunity losses during outages• Opportunity losses during restart period• Raw materials spoilage• Finish products spoilage• Idle workers• Overtime• Equipment damage• Special operation and maintenance during restart period
B. Long-Run Adaptive Response Cost• Standby generators• Power plant• Alternative fuels• Transfer location• Inventory
Outage Cost
186
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
(0.0086 + 0.0023D)F + 0.1730 Pesos/kWh
Source: del Mundo (1991)
Outage Cost to Industrial Sector in Luzon
Where, F – Frequency of Interruptions
D – Average Duration of Interruptions
Outage Cost
Losses of MERALCO Industrial Customers in 1989
Energy Sales: 3.781 billion kWhOutage Cost: Php 0.3544/kWhTotal Losses: Php 1.34 billion
94
187
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Outage Cost
0.181.310.730.08
0.181.300.310.04
0.201.3820.21
0.221.5040.45
0.261.6170.94
0.341.73131.88
0.682.00386.25
1.122.117012.26
Outage Cost(Php/kWh)
Duration(Hours)
Frequency(per year)
LOLP(days/yr)
Luzon Grid Outage Cost*
Source: del Mundo (1991)
188
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Outage Cost
Luzon Grid Outage Cost
Source: del Mundo (1991)
95
189
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Total Cost
ATC = ASC + AOC
1.291.311.110.08
1.321.301.140.04
1.291.381.090.21
1.281.501.060.45
1.291.611.030.94
1.351.731.011.88
1.622.000.946.25
2.022.110.9012.26
Total Cost(Php/kWh)
Outage Cost(Php/kWh)
Supply Cost(Php/kWh)
LOLP(days/yr)
Luzon Grid Total Cost
Source: del Mundo (1991)
190
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101
Optimal Reliability Level
Source: del Mundo (1991)
Luzon Grid Total Cost
96
191
Power System Engineering
for Non-EngineersU. P. National Engineering Center
National Electrification Administration
Power System Analysis 101