provision of third party access to licence exempt electricity and gas networks andy pace 4 october...

10
Provision of third party access to licence exempt electricity and gas networks Andy Pace 4 October 2012 1 | Energy Networks Association - DCMF

Upload: rebecca-baldwin

Post on 03-Jan-2016

216 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Provision of third party access to licence exempt electricity and gas networks Andy Pace 4 October 2012 1 | Energy Networks Association - DCMF

Provision of third party access to licence exempt electricity and gas networks

Andy Pace

4 October 20121 | Energy Networks Association - DCMF

Page 2: Provision of third party access to licence exempt electricity and gas networks Andy Pace 4 October 2012 1 | Energy Networks Association - DCMF

Background

2 | Energy Networks Association – DCMF

The Electricity and Gas (Internal Markets) Regulations 2011 introduce new obligations on licence exempt distribution and supply undertakings, including a duty to facilitate third party access to their electricity and gas networks.

Relevant DECC documents

DECC Draft Guidance: Provision of third party access to licence exempt electricity and gas networks, 14 October 2011.

DECC Revised Guidance: Provision of third party access to licence exempt electricity and gas networks, February 2012.

Relevant Ofgem documents:

Guidance on third party access charges for licence exempt gas and electricity distribution networks 151/11 dated 10 November

4 October 2012

Page 3: Provision of third party access to licence exempt electricity and gas networks Andy Pace 4 October 2012 1 | Energy Networks Association - DCMF

Proposed Solutions

3 | Energy Networks Association – DCMF

Full Settlement Metering Approach

All premises within the unlicensed network have meters.

All premises are charged DUoS as normal

No DUoS charged at boundary meter

No settlement issues

Difference Metering Approach

Some premises on unlicensed network elect to move supplier

These premises will be required to have half hourly metering

Meter readings of these premises will go through normal settlement process.

Boundary meter reading of the unlicensed network will be reduced by the units of the premises who have elected to move supplier.

Implications on how DUoS derived

4 October 2012

Page 4: Provision of third party access to licence exempt electricity and gas networks Andy Pace 4 October 2012 1 | Energy Networks Association - DCMF

Difference Metering Approach

4 | Energy Networks Association – DCMF

4 October 2012

Page 5: Provision of third party access to licence exempt electricity and gas networks Andy Pace 4 October 2012 1 | Energy Networks Association - DCMF

TPA Working Group

5 | Energy Networks Association – DCMF

TPA working group has met twice and includes customer representatives

No issues with DUoS billing for full settlement metering approach

Consultation completed on 2 options for apply DUoS under the difference metering approach:

OPTION 1: Apply DUoS at boundary

DUoS charged at boundary as normal on raw meter data (not adjusted for difference metering)

Supplier of premises within unlicensed network not charged DUoS for site

Unlicensed network provider charges premises using their approved methodology for use of system charges (via supplier)

Requires raw data and difference data to be available for the boundary meter.

Implications on settlement process

4 October 2012

Page 6: Provision of third party access to licence exempt electricity and gas networks Andy Pace 4 October 2012 1 | Energy Networks Association - DCMF

TPA Working Group

6 | Energy Networks Association – DCMF

OPTION 2: Apply DUoS at boundary and individual premises

DUoS charged to premises on unlicensed network who have elected to move suppler as follows:

• Same unit rates as applied at boundary meter

• Zero capacity charges (unlicensed network operator will charge this element)

• Zero reactive charges (unlicensed network operator will charge this element)

• Possibly an element of the fixed charge

DUoS charged at the boundary meter as follows (on adjusted meter readings):

• Capacity charge (based on MIC)

• Reactive charges

• Unit rates

• Fixed charge (possibly reduced)

• Gross flow required to determine excess capacity

• Gross flow required to determine full reactive charge

4 October 2012

Page 7: Provision of third party access to licence exempt electricity and gas networks Andy Pace 4 October 2012 1 | Energy Networks Association - DCMF

7 | Energy Networks Association – DCMF

4 October 2012

Page 8: Provision of third party access to licence exempt electricity and gas networks Andy Pace 4 October 2012 1 | Energy Networks Association - DCMF

8 | Energy Networks Association – DCMF

4 October 2012

Page 9: Provision of third party access to licence exempt electricity and gas networks Andy Pace 4 October 2012 1 | Energy Networks Association - DCMF

Analysis of TPA Charging Methods

9 | Energy Networks Association – DCMF

4 October 2012

Charging Method

Strengths Weaknesses

Boundary•One bill to the supplier

•Favoured by majority of DNOs

•Follows general industry approach of network billing

•Ensures cost reflectivity regarding the supplier licence

•Simplest flows of data and billing

•Customers at the meeting were not keen on this

option, preferring the Customer charging option

•Needs a new flow of gross data

Customer •Preferred option for the customers that attended the

meeting and some of their suppliers

•Customers believe that this approach will allow them to

clearly be able to see their direct DUoS cost

•Needs a new flow of gross data

•More complex solution with additional data and

billing movements and more scope for error/double

counting

•Increased financial risk for parties given the number

of billing transactions

•Unclear if legal under DNO licences

•Likely to be more expensive due to the increased

flows information and billing, through administrative

costs

•Majority of DNOs favoured Boundary option

•Suppliers receive multiple bills

Page 10: Provision of third party access to licence exempt electricity and gas networks Andy Pace 4 October 2012 1 | Energy Networks Association - DCMF

Next Steps

10 | Energy Networks Association – DCMF

Draft document circulated to working group

Agreed document will be sent to Ofgem with 2 key questions:

Confirm the legality/appropriateness of the customer charging option

Request clear guidance on Ofgem’s preference on charging

4 October 2012