PROJECT PROGRESS REPORT JANUARY 2019 QUESTIONS? Contact: Dr. Dennis Pauli, District Administrator [email protected] 608.561.6101 WHAT’S NEW? Since voter approval of the November 2018 referendums, the District has kicked-off the planning and design process. The Core Planning Team (CPT), made up of district staff and administrators, has begun meeting with Bray Architects and JP Cullen to refine floor plans at the high School and elementary school, and is making progress on the secure entries at both Yahara Valley Elementary and the middle school. WHAT’S NEXT? In the month ahead, the District will be working with Bray Architects to establish subcommittees made up of staff from both the high school and Community Elementary. These subcommittees will be charged with providing guidance and feedback on the daily operations of each of the buildings in regards to the proposed floor plans. The District and its design/construction partners are also working on scheduling tours of schools for the CPT and subcommittees to get a sense of what other districts in the area are doing. WHEN WILL CONSTRUCTION BEGIN? Construction is scheduled to run from June 2019 through August 2020. The projects will be completed in phases to keep as much of the buildings operational as possible during the construction process. In an effort to keep the community, students and staff informed and engaged throughout the process, the District will continue to provide monthly progress reports throughout the design and construction phases. Updates will be shared on the district website: www.edgerton.k12.wi.us

Upload: others

Post on 01-Aug-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PROJECT PROGRESS REPORT - Edgerton High School...PROJECT PROGRESS REPORT JANUARY 2019 QUESTIONS? Contact: Dr. Dennis Pauli, District Administrator dennis.pauli@edgerton.k12.wi.us 608.561.6101

PROJECT PROGRESS REPORTJANUARY 2019

QUESTIONS? Contact:Dr. Dennis Pauli, District Administrator

[email protected]

WHAT’S NEW?Since voter approval of the November 2018 referendums, the District has kicked-off the planning and design process. The Core Planning Team (CPT), made up of district staff and administrators, has begun meeting with Bray Architects and JP Cullen to refine floor plans at the high School and elementary school, and is making progress on the secure entries at both Yahara Valley Elementary and the middle school.

WHAT’S NEXT?In the month ahead, the District will be working with Bray Architects to establish subcommittees made up of staff from both the high school and Community Elementary. These subcommittees will be charged with providing guidance and feedback on the daily operations of each of the buildings in regards to the proposed floor plans. The District and its design/construction partners are also working on scheduling tours of schools for the CPT and subcommittees to get a sense of what other districts in the area are doing.

WHEN WILL CONSTRUCTION BEGIN?Construction is scheduled to run from June 2019 through August 2020. The projects will be completed in phases to keep as much of the buildings operational as possible during the construction process.

In an effort to keep the community, students and staff informed and engaged throughout the process, the District will continue to provide monthly progress reports throughout the design and construction phases.

Updates will be shared on the district website: www.edgerton.k12.wi.us

Page 2: PROJECT PROGRESS REPORT - Edgerton High School...PROJECT PROGRESS REPORT JANUARY 2019 QUESTIONS? Contact: Dr. Dennis Pauli, District Administrator dennis.pauli@edgerton.k12.wi.us 608.561.6101

2018 2019 2020OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

COMMUNITY ELEMENTARY SCHOOL (A,B + C)

DESIGN

BIDDING

CONSTRUCTION

» SITE IMPROVEMENTS (C)

» ADDITION & AREA A RENOVATION (A)

» AREA B RENOVATION (B)

MOVE-IN / OCCUPANCY

EDGERTON HIGH SCHOOL (E + D)

DESIGN

BIDDING

CONSTRUCTION

» ADDITION (E)

» ALL RENOVATION* (E + D)

MOVE-IN / OCCUPANCY

YAHARA / MIDDLE SCHOOL SECURE ENTRIES

DESIGN

BIDDING

CONSTRUCTION (F + G)

MOVE-IN / OCCUPANCY

PRELIMINARY PROJECT SCHEDULES

The schedules above are preliminary and are subject to change.

*Note that we are comfortable working with the district to see if we can advance the science wing renovation to hit the first summer.

Denotes summer months.

Page 3: PROJECT PROGRESS REPORT - Edgerton High School...PROJECT PROGRESS REPORT JANUARY 2019 QUESTIONS? Contact: Dr. Dennis Pauli, District Administrator dennis.pauli@edgerton.k12.wi.us 608.561.6101

bray architects solid foundation. forward thinking.

Project #: 3349

Additions - June 2019 - August 2020 Remodel - May 2020 - August 2020

Note: Some work at night & break between January 2020 & May 2020

KEY

A Community Addition/Area A Renovation B Community Renovation Area B C Site D High School - Science, Math, Library Renovation

E Commons/Band/Entry Addition & Renovation F Middle School - Secure Entry G Yahara Elementary - Secure Entry

Site Plan SCALE: Not to Scale

Edgerton School District Edgerton, WI

January 10, 2019