project portfolio web version june 10 2015

150
intelligent engineering project portfolio

Upload: qipei-mei

Post on 15-Aug-2015

42 views

Category:

Documents


11 download

TRANSCRIPT

Page 1: Project Portfolio Web Version June 10 2015

intelligent

engineering project portfolio

Page 2: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Project Portfolio | June 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

CONTENTS RECENT PROJECTS 1. Stadia 2. Buildings 3. Bridges 4. Industrial 5. Maritime OTHER INFORMATION 6. Engineering 7. Production 8. Publications 9. Company Profile

June 2015

Page 3: Project Portfolio Web Version June 10 2015

Intelligent Engineering (UK) Limited | SPS Terraces – USTA Grandstand | June 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

USTA Flushing Meadow - Grandstand SPS Terraces

June 2015

Owner: US Tennis Association

Architect: Rossetti

Engineer: WSP-NY Office

Construction Manager: Hunt Construction

In partnership with the Walters Group, IE has won the contract for a new order for SPS Terraces from HUNT Construction Group in a supply-install contract for the USTA in Flushing Meadows NY. This is the second stadia project for USTA and is a 5,800 seat venue to be constructed near the existing Court 17 facility built with SPS in 2012. The Grandstand stadium is scheduled for completion in July 2016 – a very ambitious build program with SPS Terraces erected by November 2015.

USTA Flushing Meadow - Court 17 SPS Terraces

May 2015 Construction Manager: Design Build Erector: Anchor contracting Southern Bleacher Company

Page 4: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | London Olympic Stadium | April 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

London Olympic Stadium West Stand Mid Tier SPS Terraces

April 2015

Owner: Greater London Authority

Architect: Populous

Structural Engineer Buro Happold

Contractor: Balfour Beatty

As part of the London 2012 legacy, the iconic Olympic Stadium is being upgraded to a UEFA Category 4 Football Stadium – the highest category possible of football stadium in the world. The lightweight SPS system was selected for the cantilevered terracing in the First Class Hospitality Suite areas. The SPS components were successfully installed by the end of April 2015.

Page 5: Project Portfolio Web Version June 10 2015

Intelligent Engineering (UK) Limited | MSU Softball Stadium | April 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

Mississippi State University Softball Stadium April 2015

Location: Starkville Mississippi Owner: Mississippi State

University Architect: Wier Boerner Allin Engineer: Structural Engineering

Associates LLC

Together with our partner Southern Bleacher Co of Graham Texas, the project includes the supply and installation of SPS Terraces and related products for the construction of the new Mississippi State University Softball Stadium.

Page 6: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Anfield Stadium Redevelopment | April 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

Liverpool Football Club April 2015

Project contractors, Carillion, signed off the SPS design for Liverpool Football Club’s iconic Anfield Stadium redevelopment. Production of 139 SPS terraces including six vomitory landings is now underway. Delivery is scheduled for early August 2015 and will be installed in time for the start of the 2016/17 EPL Season.

Main Contractors: Carillion Architects: KSS Engineers: Jacobs Owners: Liverpool LFC

Page 7: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Studio City | March 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

Studio City, Macau SPS Terraces, Floors, Walls

March 2015

Melco Crown Entertainment are currently constructing a cinematically-themed entertainment, retail and gaming resort in Macau, China. SPS is being utilised to construct the terracing, wall and stage floor components of the combined 3,000 seat cinema and theatre leisure facilities. SPS components will be installed in October 2014, with the complex due to open mid 2015.

Owner: Melco Crown Entertainment

Architect: HKS

Structural Engineer Buro Happold

Contractor: Paul Y – Yau Lee Joint Venture

Page 8: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Terraces – SJEQ Stadium | February 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

San José Earthquakes Stadium SPS Terraces February 2015

Owner: Earthquakes Soccer LLC

Architect: 360 Architecture

Structural Engineer Magnusson Klemencic Associates

Contractor: Devcon Construction

Time lapsed video of the construction of the stadium is available on the following link:

https://www.youtube.com/watch?v=P-PaGOQzN2Q This demonstrates how quickly the SPS Terraces can be installed. Pay careful attention around the 70-second marker or you’ll miss it!

“We congratulate you and your team on the successful installation of your SPS Terracing … [and] … thank the SPS team for all the efforts to make the Avaya stadium one of the best in North America. We hope that there will be future opportunities to work together in new stadium or arena.” Dave Kaval President, San Jose Earthquakes Avaya Stadium

SPS and Steel Systems Engineering, Inc. win 2014 Tekla award in BIM category. “For coordination of fabricator and general contractor requirements, providing accurate, latest drawings and minimising workload.”

Page 9: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Terraces – Philippine Arena | July 2014 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

Philippine Arena SPS Terraces

July 2014

Owner: New Era University

Architect: HaeAhn

Contractor: Hanwha Engineering & Construction Co (HENC)

The Philippine Arena is the world’s largest mixed-use indoor theatre. SPS Terraces account for approximately 40,000 of the 55,000 seats. The use of SPS enabled the terraces to be installed after the roof had been completed. This key benefit offered programme flexibility and cost effectiveness which could not be achieved by any other method or material.

Page 10: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Terraces - Mock-up | March 2014 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Terraces Mock-up for Moveable Stands

March 2014

The lightweight (20% of conventional concrete) and the very solid feel of SPS terraces make them ideal for use in stadia which require moveable stands. The erection of the entire bay shown was completed in just over three hours, with a three man crew and lightweight crane.

Page 11: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Terraces – NGA Azerbaijan | July 2013 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

National Gymnastics Arena

Baku, Azerbaijan SPS Terraces

July 2013

Owner: Pasha Insaat

Architect: Broadway Malyan

Main Contractor: Mace International Ltd “The SPS units were so light and easy to position. We simply followed the keyplan and erected it just like steel - in fact easier.”

Umut Özdemir Project Management Chief

Sinerji (Erector)

Page 12: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Aquatics Centre | May 2013 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

Aquatics Centre - London 2012 Olympics

Architect: Zaha Hadid Engineers: Arup Contractor: Balfour Beatty

Conversion - May 2013

Construction - January 2011

Completed - June 2012

The two temporary wing-like seating stands containing SPS Terraces were removed during the building’s conversion to a public swimming pool, in-line with the Olympic organisers’ goal of creating a sporting legacy for London.

The SPS Terraces have been sold on for re-use in a new venue.

Page 13: Project Portfolio Web Version June 10 2015
Page 14: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Project Portfolio | June 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

CONTENTS RECENT PROJECTS 1. Stadia 2. Buildings 3. Bridges 4. Industrial 5. Maritime OTHER INFORMATION 6. Engineering 7. Production 8. Publications 9. Company Profile

June 2015

Page 15: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Cape Canaveral | June 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

Cape Canaveral June 2015

Intelligent Engineering has won a contract for the design and supply of SPS panels. The details are confidential. Delivery is expected in July 2015.

Page 16: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | 58 Victoria Embankment | April 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

58 Victoria Embankment April 2015

The use of SPS Floor panels at 58 Victoria Embankment shows diversification in usage as they move into the multi-storey arena. The panels will be used on four of the seven floors, including the roof. SPS overcame the restricted head height issues faced when reconfiguring the interior floor layout, which could not be resolved using conventional materials.

Contractor: Kier

Consultant: Waterman Plc

Architect: TP Bennett

Developer: Kier Developments

Steel Erector: Bourne Steel

Page 17: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Birmingham New Street Station | February 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

Birmingham New Street Station North Access Ramp

Phase I - May 2012, Phase II – February 2015

Phase I - Completed May 2012

Phase II – Completed February 2015

SPS Floors were installed on the north access ramp located on the concourse level as part of a two phase redevelopment of the station. SPS Floors provided a solution that is light weight and easy to handle and install given there was no access from below.

Owner: Network Rail Engineer: Atkins Contractor: Mace Steel Erector: Severfield

Page 18: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Daytona Hospitality Suite Walkway | September 2014 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

Daytona Hospitality Suite Walkway September 2014

SPS is contributing to the Daytona Speedway’s enhanced spectator experience by providing improved access to the Grand Stand and Hospitality Suites. SPS was selected as it fulfilled the requirement of ‘lightweight decking’ to minimise load on the existing support structure.

Owner: Daytona International Speedway Architect: Rossetti Engineer: Walter P Moore Contractor: Barton Malow Steel Erector: SteelFab

Page 19: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Popout Panels | November 2013 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Popout Panels November 2013

Owner: Intel Corporation Contractor: Hoffman Construction

• 53,000 SPS Popout Panels cover access ports on raised floor of chip manufacturing plant

• Weight reduction from 95lb to 28lb, allowing one man to remove and replace panels

• Able to carry the point load of fully laden forklift truck without deflection

• SPS Popout Panels awarded “best known method” status within Intel

1. Concrete form 2. Centre beam 3. Unistrut safety cage 4. SPS Popout Panel

Page 20: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | ICE Building | March 2013 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Floors - University of Alberta Innovation Centre for Engineering

March 2013

Owner: University of Alberta

Architect/Engineer: Dialog

Contractor: EllisDon Construction

Steel Fabricator/Erector: Supreme Group

SPS panels provided many advantages on this project

1) Installation was very easy and took a

fraction of the time required for concrete 2) Eliminated winter heating requirements,

risk of freezing damage to finished surfaces and waste materials

3) Thinner panels gave more headroom (40mm vs.150mm for concrete)

I would highly recommend SPS and Intelligent Engineering.

Robert S Holmes, Senior Superintendent, University of Alberta ICE Project, EllisDon

Page 21: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Panels – Custody Cells | October 2012 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Modular Construction - Volumetric London Metropolitan Police Custody Centres (Brixton, Kingston, Wood Green, Walworth)

October 2012

SPS delivered as a ‘Modular System’

Lightweight SPS Cells lifted directly into position

Clean architectural finishes

Owner: Metropolitan Police Architect: Raymond Smith Partners Main Contractor: Wates Construction

SPS delivered as a ‘Flat Panel System’

Lightweight SPS Panels quickly aligned and installed SPS Cell roof forms load

bearing floor above

SPS Modular Construction - Flat Panel London Metropolitan Police Custody Centres

(Croydon) August 2011

Page 22: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Floors - nnnle | September 2012 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Floors nnne Retail Store Mock Up (Pre-completion)

California, USA September 2012

Owner: --------------------on Architect: Foster & Partners Construction Manager: DPR/Skanska Steel Fabricator/Erector: Schuff Steel

• SPS floor plates used in a large two storey mock-up of a new design for ------’s Asia retail stores

• Lightweight SPS panels used to create 45ft cantilever design with a thin leading edge

• 18 SPS floor plates erected in less than half a day

Page 23: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Floors – London Gatwick Airport | April 2011 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

London Gatwick Airport North Terminal Interchange Extension

SPS Floors April 2011

Architect: Capita Symonds

Engineers: WSP Group

Erector: Fisher

Page 24: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Carnegie Hall | February 2011 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

Carnegie Hall - New York Renovation using SPS Floor Panels

February 2011

Shrink wrapped pallet of 14 SPS Floor panels (630 sq.ft.)

Restricted access by exterior hoist

Architect: iu + bibliowicz

Structural Engineers: Robert Silman Associates

Construction Manager: Tishman Construction

Steel Erector Fabricator: Metropolitan Walters

Lightweight, easily handled panels facilitate installation in constrained site

Page 25: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Installation Weston Pier | October 2010 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

Installation of SPS Floor Panels

Weston-super-Mare Pier, UK October 2010

Architect: Angus Meak Contractor: John Sisk & Sons SPS Floors were key to meeting the challenges of rebuilding on an old and damaged structure with limitations on weight, restricted access and a demanding schedule. Intelligent Engineering has gone the extra mile in supporting us from design to installation to ensure the success of the project.” Andy McGoldrick, Project Director, John Sisk & Sons Ltd

Page 26: Project Portfolio Web Version June 10 2015

jkfeofsfn

Intelligent Engineering (UK) Limited | SPS Floor Benefits | June 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

Data & Calculations concrete SPS SPS extra floor

total gross area (sqm) 118,450 118,450 120,918gross area per floor (sqm) 2,468 2,468 2,468

total floors 48 48 49

total net lettable area (sqm) 76,650 77,183 78,975average NLA per floor (sqm) 1,597 1,608 1,612increase in NLA 1% 3%

floor height (mm) 4,000 3,900 3,900building height above ground (m) 176 172 176construction duration (weeks) 145 132 133

Summary ($m) concrete SPS SPS extra floor

foundation, shell and core 89 83 84floor 17 38 39cladding 98 96 98prelims 72 66 66other 137 137 140sub-total - build cost 413 419 427change 6 15

earlier completion 19 17extra area per floor 8 8extra floor 28sub-total - benefits 27 54

Total Benefit to Owner 20 39

SPS shear walls can also be used to replace concrete core eliminating concrete above ground level, further reducing construction duration and increasing net lettable area,

and increasing total benefit to owner by an additional $20m

SPS Floors Example of Economic Benefits

Generic Tall Building Example

Location: London, UK Rental Rate ($/sqm/year): 960 Annual Rental Yield: 6.2%

Page 27: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Project Portfolio | June 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

CONTENTS RECENT PROJECTS 1. Stadia 2. Buildings 3. Bridges 4. Industrial 5. Maritime OTHER INFORMATION 6. Engineering 7. Production 8. Publications 9. Company Profile

June 2015

Page 28: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Grand Duchess Charlotte Bridge | June 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

Grand Duchess Charlotte Bridge (Pont Rouge) SPS Bridge Panels and SPS Overlay

June 2015

SPS will be used to widen and strengthen the Grand Duchess Charlotte Bridge in Luxemburg this year. SPS Overlay will be used to strengthen the four 355m long vehicle lanes (4,899m²). SPS Bridge Deck panels will form new pedestrian and cycle lanes on either side of the bridge. IE’s German partner, EDS, will manufacture the new SPS panels with IE supporting and undertaking all injection work.

Page 29: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Pulaski Skyway Bridge - SPS Expansion Joint Covers | March 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

Pulaski Skyway Bridge Temporary SPS Expansion Joint Cover Plates

March 2015

The Pulaski Skyway Bridge is a four-lane bridge in north-east New Jersey State providing access to Manhattan from Newark. A rehabilitation programme for the bridge structure, required to meet the current safety standards and demands, is on-going. During construction, the existing expansions joints at 10 different locations were removed. Temporary SPS expansion joint cover plates span over these until the permanent expansion joints are installed.

Owner: New Jersey DOT Engineer: Hardesty & Hanover Contractor: CCA Civil Inc.

Page 30: Project Portfolio Web Version June 10 2015

Intelligent Engineering (UK) Limited | SPS – Deck Plates & Tub Girders | May 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

jkfeofsfn

Integrated SPS Bridge Deck Plates and Steel Tub Girders

Pre-Assembled Modules for Transportation

GENERAL • bridge design concept integrating SPS plates and steel tub girders • allows bridge replacements to be executed quickly and efficiently FABRICATION & SHIPMENT • SPS bridge deck plates are bolted to steel girders to create:

− exterior modular units with pre-attached guardrails − interior modular units that can be connected on-site

• fabricated modules can be stacked on a truck bed for transportation to site ERECTION • rapid site erection of units • sequence shown in the figure below • modules are field welded along the length of the bridge

Integrated SPS Bridge Deck Plates and Steel Tub Girders

exterior

interior

shaped splice plates

Page 31: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Bridge Panels – Ovingham & Staniforth Bridge | March 2014 - July 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

Regional Council Bridges Ovingham Bridge and Staniforth Bridge

March 2014 – July 2015

SPS was specified for two road and rail infrastructure refurbishment projects in Northern England. In each case, the new SPS deck replaced the existing deck. The reduced weight of the SPS deck eliminates load restrictions and allows an increase in live road capacity. The Ovingham Bridge is due to be installed in July 2015 whilst the Staniforth Bridge has been installed and is in service.

Ovingham Bridge prior to installation of SPS

SPS panels in production

Owner: Northumberland County Council/Sheffield City Council Engineer: Northumberland County Council in conjunction with IE/Amey Contractor: Northumberland County Council/Henry Boot

SPS panels in production

Staniforth Bridge in Service June 2014

Page 32: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Mettlach Bridge | January 2015| page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

Mettlach Bridge SPS Bridge Panels

January 2015

Old concrete deck being removed

New SPS deck being installed

• Renovation of Mettlach Bridge in Germany carried out by Eiffel Deutschland Stahltechnologie (EDS) using prefabricated SPS panels to replace existing concrete deck

• Use of SPS reduced deck weight by 300 tonnes allowing load restrictions to be lifted. Works completed within four months

• Project received prestigious Ulrich Finsterwalder Engineering Award in January 2015

Page 33: Project Portfolio Web Version June 10 2015

Intelligent Engineering (UK) Limited | SPS - Bridge in a Box | December 2014 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

jkfeofsfn

SPS – Bridge in a Box

GENERAL • new construction • bridge rehabilitation, deck replacement

− maintains roadway elevation − reduces weight − elimination of load restrictions − increase number of lanes (traffic volume)

FABRICATION • pre-engineered, prefabricated bridges • no formwork required • no camber of longitudinal girders required SHIPPING / ERECTION • container (24 tonne capacity for standard 40 ft container)

− 80 m2 of bridge deck − transverse beams / diaphragms − curbs and guardrails

• open transport for wide deck plates • no on-site concrete work required • no weather delays MAINTENANCE • 75+ year design life for SPS deck plates • 10+ year design life for road surface between renewal • de-icing chemicals or salts can be applied as deck is

protected with waterproofing membrane and lightweight wearing surface

40 ft container guardrail posts

SPS deck plate with integrated curb

transverse beams, diaphragms

standard SPS deck plate

2438 (8 ft)

2438 (8 ft)

coupler profile

SPS deck plate – longitudinal girder connection detail

SPS selected by American Association of State Highway and Transportation Officials as best-in-class product. “we will, over the next several years, watch this technology move forward to become accepted practice across the nation” Richard Tetreault Chairman, TIG

Page 34: Project Portfolio Web Version June 10 2015

Intelligent Engineering (UK) Limited | SPS - Fly Over | November 2013 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies | Proprietary

jkfeofsfn

SPS – Fly Over

Existing Condition

SPS Fly Over

• construct a 750 m long movable roadway above existing roadway allowing traffic flow over sections being reconstructed

• minimizes traffic disruption; fuel cost saving based on idling traffic ~$1.6M/day

• safer work conditions - separation of traffic and construction

• provides weather enclosure reducing associated risks and construction time

Renewal Construction Sequence

Enabling Works • rerouting local services • install local foundation and rail system • erection of fly over section (with ramps)

Staged Reconstruction • removal of existing deck section • reconstruction/rehabilitation of piers • erection of new steel girders and

prefabricated SPS deck plates • advancement of the fly over section to

the next stage

Erection of Fly Over Section

Renewed Elevated Expressway

Rehabilitated Structure

Optional Second Tier Construction (e.g. Gardiner Expressway - Toronto, Canada)

• fly over deck plates can be reused for the first 750 m of the second tier construction

• provides increased capacity and space for rapid transit

• possible to minimize ground level traffic and reuse the space for urban integration

Second Tier Construction

URBAN INTEGRATION

(transform ground level into

retail and office space)

Page 35: Project Portfolio Web Version June 10 2015

jkfeo fs

fn

fåíÉääáÖÉåí=båÖáåÉÉêáåÖ=ErhF=iáãáíÉÇ==ö==qÜçêÅ~ÄêáÇÖÉ===ö==aÉÅÉãÄÉê=OMNO==ö==é~ÖÉ=N=çÑ=N=oÉÖáëíÉêÉÇ=áå=båÖä~åÇ=PNUQURN==ö==^=ãÉãÄÉê=çÑ=íÜÉ=fb=dêçìé=çÑ=`çãé~åáÉë==

First Thorcabridge Hillegom, Netherlands

December 2012

Page 36: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Dawson Bridge | July 2010 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

Dawson Bridge - Edmonton, Canada Rehabilitation using SPS Bridge Deck Panels

July 2010

The SPS Bridge Deck allowed the entire project to be completed months faster and millions of dollars less expensively than a traditional concrete deck.

March 2011 issue of the official AISC publication, Modern Steel Construction “Three-Part Perfection, Jeff DiBattista, Kris Lima, Shiraz Kanji”

Winner of the 2011 Sustainability Award

Alberta Steel Design Awards of Excellence Canadian Institute of Steel Construction

Owner City of Edmonton

Engineer: Dialog (formerly Cohos Evamy)

Contractor: ConCreate USL Ltd

Page 37: Project Portfolio Web Version June 10 2015

Intelligent Engineering (UK) Limited | Ma Fang Bridge | December 2009 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

jkfeofsfn

Ma Fang Bridge, China

SPS Overlay - Bridge Repair December 2009

• SPS offered the solution of strengthening the orthotropic bridge deck

• The SPS construction activities were contained such that vehicle and rail traffic could continue to utilise the bridge

• The skills necessary to undertake the works are available globally as this project in China demonstrates

Page 38: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Project Portfolio | June 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

CONTENTS RECENT PROJECTS 1. Stadia 2. Buildings 3. Bridges 4. Industrial 5. Maritime OTHER INFORMATION 6. Engineering 7. Production 8. Publications 9. Company Profile

June 2015

Page 39: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Pop-up Panels | May 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Pop-up Panels May 2015

The first SPS prototype of a rising anti-ram SPS vehicle barrier has now been tested in the UK to industry standards. The initial tests successfully brought a 40 tonne truck to a complete standstill.

Page 40: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Flood Panel | April 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Flood Panel April 2015

IE worked with Florida based Flood Panel LLC to develop a flood protection product for small businesses hardest hit by Hurricane Sandy for the New York City Economic Development Corporation. The SPS Flood Panel was selected from 200 applicants for the city’s $30 million federally-funded RISE: NYC competition to find the world’s most promising resiliency technologies to prepare businesses for future storms, sea level rise and other effects of climate change.

Page 41: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Mining Truck Body | December 2014 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Mining Truck Body

December 2014

• Heavy mining trucks carry payloads up to 400 tons; structures are vulnerable to impact damage and rapid wear

• Analysis verifies engineering and economic benefits of SPS

− reduced weight increases payload − reduced wear-rate and impact damage increases service life

• SPS solution applicable to reinstatement of existing vehicle and construction of new vehicles

Page 42: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Transformer Casing | November 2013 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Transformer Casing November 2013

• SPS Transformer Casings increase stiffness, reduce weight and dampen vibration and sound

• Six projects completed to date, using the Overlay method in-situ, to verify design and benefits

• High volume production will use prefabricated SPS panels

Page 43: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Project Portfolio | June 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

CONTENTS RECENT PROJECTS 1. Stadia 2. Buildings 3. Bridges 4. Industrial 5. Maritime OTHER INFORMATION 6. Engineering 7. Production 8. Publications 9. Company Profile

June 2015

Page 44: Project Portfolio Web Version June 10 2015

Intelligent Engineering (UK) Limited | Citadel Access Protection | May 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

jkfeofsfn

SPS Citadel Access Protection May 2015

Background Citadel protection is a proven concept that has a successful track record for protecting ships and crew from piracy. The internationally recognised Best Management Practice to Deter Piracy in the Gulf of Aden and off the Coast of Somalia recommends that due consideration should be given to establishing a secure Citadel that “is designed and constructed to resist a determined pirate trying to gain entry for a fixed period of time”. SPS is an ideal product for Citadel hardening.

Slice through SPS panels View from inside Citadel View from outside Citadel

Location: Access openings leading to safe area or “Citadel” SPS protection panels Design: 3-15-3 Installation: By ship’s crew/steel contractors Fleet Deals: BP Fleet

SPS Citadel Access Protection provides: • A new final barrier to delay and deter

pirate attacks

• Protection within 90 seconds

• Enhanced protection from impact loads, blasts and projectiles

• FB6 ballistic compliant designs available

Page 45: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Safe Concordia | April 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Overlay Safe Concordia

April 2015

SPS Overlay was used to strengthen the cargo deck on-board this semi-submersible. SPS Overlay mitigated the need for steel removal which would have increased the project’s complexity, significantly increasing the repair schedule and associated costs.

Page 46: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Petrobras | December 2014 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Overlay Side Impact Protection of three Petrobras SA FPSOs

December 2014

SPS compact double hull (CDH) was selected to provide side shell impact protection to the boat landing areas of three FPSOs operated by Petrobras SA. This innovative use of SPS Overlay meets the low energy impact resistance requirements of IMO MARPOL Annex I Requirements for FPSOs and FSUs. The solution which protects the adjacent cargo oil tanks was approved by Class Society DNV-GL. The work was carried out at Enseada do Paraguaçu S.A. Shipyards (EEP) in Brazil and COSCO (Dalian) Shipyard, China. These projects were undertaken during the course of 2014, with the final project being completed in December 2014. A total 2,824m² of SPS Overlay has been installed on the three vessels.

Owner: Petrobras Repair Location: China and Brazil Class: DNV-GL

Page 47: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Fuel Tank Conversion | December 2014 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Overlay Fuel Tank Conversion for 2015 Emissions Requirements

December 2014 Project Summary Three tankers needed thermal insulation boundaries installed between two Heavy Fuel Oil (HFO) tanks to create a Marine Gas Oil (MGO) tank as part of the shipowner’s strategy to meet new exhaust gas emission requirements. IMO MARPOL 73/78 Annex VI has been amended to require new standards for marine fuel oils when vessels are operating in defined Emission Control Areas (ECA), specifying a reduction of the sulphur content (SOx) to below 0.1% from January 2015. This was the first time that SPS Overlay had been used in this application; and was verified by Lloyds Register (LR). Carried out in Qatar, by Intelligent Engineering’s partner, CTS Offshore and Marine Limited, for a global shipping company, the three ships had areas of 50m² of SPS Overlay fitted to bulkheads between two adjacent fuel tanks.

Benefit of using SPS Overlay: • Cost effective insulation of

boundary between adjacent HFO and MGO tanks

• Maximum HFO and MGO tank capacity due to compact thickness of SPS

• No change to existing structure • Zero through-life maintenance

Page 48: Project Portfolio Web Version June 10 2015

jkfeo fs fn

Intelligent Engineering (UK) Limited | Transocean John Shaw | March 2014 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Overlay Strengthening of Pontoon Shell Plating of John Shaw

March 2014

Project Summary

The semi-submersible oil platform “John Shaw” is one of many that have benefited from an SPS Overlay repair to solve a problem that is difficult to achieve by any other means. At the time of repair, the vessel was floating alongside and the repair location was several meters below the waterline making conventional “crop and renew” method impossible without a costly and unscheduled dry-docking. During normal operations semi-submersible platforms occasionally receive minor contact damages from positioning tugs and offshore support vessels, particularly in heavy swells. SPS Overlay was installed in way of two such areas to protect and reinforce the hull plating. In this application, SPS Overlay provides a class-approved permanent repair without the need to dry-dock the platform, saving the operators additional time and maintenance costs associated with an unscheduled docking.

Owner: Transocean Ltd Repair Shipyard: Semco Maritime, Esbjerg Class: DNV Design: 8-25-Existing

Page 49: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Spudcan Reinforcement| March 2014 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

Wind Turbine Installation and Maintenance Vessel Jack-up Leg Strengthening

March 2014

Bottom of leg before SPS strengthening High risk of permanent damage

Bottom of leg with SPS Overlay Reduced stresses and deflections

Structural analysis model of leg and boulder

SPS Overlay provides an innovative solution to minimising operational risk and extending the service capability of self-elevating wind turbine and installation vessels. These specialist ships must be capable of safe operation in a wide variety of environmental conditions. In particular, submerged rocks on the sea-bed represent a significant risk to safety and operational integrity. SPS’s inherent resistance to impact and concentrated loads provides a technically superior solution which is fast and cost-effective to apply. SPS Spudcan Reinforcement delivers: • Increased structural protection from concentrated loads caused by contact with large rocks on the sea bed. • Reduced operational risk and extended ship service capability.

Owner: MPI Offshore Limited Class: DNV

Page 50: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Quad204 Escape Tunnel | January 2014 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

Quad204 Escape Tunnel January 2014

Owner: BP Builder: Hyundai Heavy Industries Class: Lloyd’s Register

The blast and fire resistant escape tunnel for the new FPSO Quad204 runs the length of the processing modules and is designed to withstand the harsh environmental conditions of the North Sea and resist extreme emergency loads. Arranged in a novel double-layer, the SPS panels provide a primary barrier to survive accidental loads from both an initial blast and subsequent hydrocarbon and jet fires so that shipboard staff can escape safely to their muster points.

Page 51: Project Portfolio Web Version June 10 2015

jkfeo fs fn

Intelligent Engineering (UK) Limited | BP FPSO Quad 204 EOR Tanks | November 2013 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Overlay Thermal Insulation in EOR Tanks of New Build FPSO Quad 204

November 2013

Project Summary

A special fluid is injected into the well to increase the oil recovery. However, the fluid is heat sensitive (coagulates at elevated temperatures); and because the Enhance Oil Recovery (EOR) tanks are adjacent to the fuel oil tanks (usually maintained at around 60 degree C) there is a concern. The EOR fluid is circulated in the tanks to prevent “hot-spots”. BP required the tank walls to be insulated for safety reason. The internal surfaces of the EOR tanks are stainless steel (clad/explosion bonded SS/CS plating) with a thermal resistance through SPS Overlay (R-value) is 0.2819 m²C°/W.

Owner: British Petroleum (BP)

Builder: Hyundai Heavy Industries Ltd.

Class: Lloyd’s Register

Design: 8-50-Existing with stainless steel (LR Grade 316)

Page 52: Project Portfolio Web Version June 10 2015

jkfeo fs fn

Intelligent Engineering (UK) Limited | P&O Maritime MV Aurora Australis | May 2013 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Overlay and Penguins at Antarctica Inhibit Future Crack at Fuel Oil Tank Plating of Aurora Australis

May 2013

Project Summary

The ice breaker research vessel Aurora Australis travels between Australia and Antarctica transporting essential fuel and supplies to the research team. SPS Overlay was used to solve a historical fatigue crack problem that periodically affected a knuckle joint in the bulkhead separating the fuel oil and water ballast tanks. This can lead to a risk of contamination of both fuel and water ballast, which would have a serious impact on vessel operations. Used in this location, SPS Overlay significantly reduces the local stress levels and virtually eliminates the risk of further fatigue in the knuckle joint. At the same time, SPS Overlay provides an extra barrier, giving a second level of defence against future fuel and ballast water contamination.

Owner: P&O Maritime Services Pty Ltd

Repair Yard: Sembawang Shipyard Pte Ltd, Singapore

Class: Lloyd’s Register

Design: 8-20-Existing

Page 53: Project Portfolio Web Version June 10 2015

jkfeo fs fn

Intelligent Engineering (UK) Limited | Passenger/RoRo Vessel | April 2013 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Overlay Sound Deadening and Vibration Elimination on

Deck Plating of Passenger/RoRo Vessel April 2013

Project Summary

DSME applied SPS Overlay on the bottom shell plating in way of Deck no.3 and Deck no.6 as a sound-deadening and vibration elimination solution. This concludes a 2-phase program of both SPS Overlay and “Underlay”, with the original deck plating unaffected and post-fire strength the same or better after the SPS material is fitted. All SPS work, including steelwork, has been carried out with a riding squad from Marseille and Genoa, across the Mediterranean, to Tunis without affecting the vessel’s sailing schedule.

Builder: Daewoo Shipbuilding & Marine Engineering Co. Ltd (DSME)

Class: Bureau Veritas

Design: 6-25-Existing

Page 54: Project Portfolio Web Version June 10 2015

jkfeo fs fn

Intelligent Engineering (UK) Limited | MODEC FPSO Kwame Nkrumah MV21 | February 2013 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Overlay Side Shell and Bulkhead Reinstatement for

FPSO Kwame Nkrumah MV21 February 2013

Client Testimonial

“Utilizing the non-intrusive SPS Overlay to reinstate the plates on the void tanks and forepeak tank side shells and bulkheads of FPSO Kwame Nkrumah MV21 enabled our FPSO to remain in operation. The SPS Overlay team completed this excellent job under difficult conditions and with minimal impact on our productivity. The work was finished with excellent results.”

Bai Li Guo, Project Director - MODEC Offshore Production Systems (Singapore) Pte Ltd

Owner: MODEC Inc.

Repair Location: On station repair at Ghana Offshore

Class: American Bureau of Shipping

Design: 8-25-Existing

Page 55: Project Portfolio Web Version June 10 2015

jkfeo fs fn

Intelligent Engineering (UK) Limited | Princess Cruise Sea Princess | October 2012 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Overlay Diesel Oil Tanks Top Plating Reinstatement on

Cruise Vessel Sea Princess October 2012

Project Summary

SPS Overlay reinstatement was carried out in way of Diesel Oil Tanks while passengers enjoyed the wonderful atmosphere of the Sea Princess in the middle of the Pacific Ocean, crossing both the Equator and the International Dateline.

Owner: Princess Cruise Lines, Ltd.

Builder: Riding squad, from San Francisco to New Zealand and Australia

Class: Lloyd’s Register

Design: 8-20- Existing

Page 56: Project Portfolio Web Version June 10 2015

jkfeo fs fn

Intelligent Engineering (UK) Limited | SBM FPSO Cidade De Ilhabela | August 2012 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Overlay Side Shell Protection on FPSO Cidade De Ilhabela

August 2012

Client Testimonial

“SPS Overlay Side Shell Protection improves Impact Resistant of the vessel in way of Supply Boat Landing Area. It is a particularly good solution for single hull tankers like the FPSO CDI as it eliminates the cost of additional void tanks construction and at the same time with no reduction of cargo compartments space of the FPSO. The IE team performed this task on FPSO CDI project in a professional manner.”

Olejniczak Adam, Construction Manager - Single Buoy Moorings Inc.

Owner: Single Buoy Moorings Inc.

Conversion Yard: Guangzhou Dockyard, China

Class: American Bureau of Shipping

Design: 15-30-Existing

Page 57: Project Portfolio Web Version June 10 2015

jkfeo fs fn

Intelligent Engineering (UK) Limited | LNG FSU | April 2012 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Overlay Reinstatement of Trunk Way Upper Deck and

Sloping Bulkhead of LNG FSU April 2012

Project Summary

SPS Overlay was applied to the upper surface of the sloping trunk deck on a LNG Floating Storage Unit. The objective was to restore the structural properties of the steel plating and stiffeners which had suffered corrosion due to condensation build-up in the enclosed void space above the LNG tanks. The use of SPS Overlay allowed a safe, fast and unhindered repair, while the low-heat-input operations, made possible by the unique design of the Overlay repair, avoided damage to the cryogenic membrane containment system located directly beneath the sloping deck.

Conversion Yard: Malaysia Marine and Heavy Engineering (MMHE) Shipyard

Class: American Bureau of Shipping

Design: 8-25-Existing

CLASS SUBMISSION & TENDER DOCUMENT

LON GL GD R 1510 2 OCL

LON GL GD R 1510 2 OCL

1500

EXI STIN G BKT

TRU N K D EC K 2750 0 ABL

TRU N K D EC K 2750 0 ABL DET "B"

SPS 8 (GR E)-25 -EXISTIN G (T YP)

L ON GL GD R 1510 2 OCL

* SPS PANEL 8(GR E) -25-EXI STIN G * SPS PANEL

8(GR E) -25-EXI STIN G SEE

DET "B" SEE

DET "F " SI M T O DET "E"

SEE DET "F " TSL1 3

SEE DET "L " SEE

DET "A" (T YP)

SEE DET "E" (T YP)

PL AT E SEAMS T O BE AR R AN GED IN PANEL S

T O SUI T FI TTIN G

UPPER D EC K 2420 0 ABL

DET "C "

SEE DET "K"

PART SECTION @ INT BKT SC AL E 1:50

UPPER D EC K 2420 0 ABL *

SPS PANEL 8(GR E) -25-EXI STIN G

DET "D "

TSL1 4

200

*

DET "A" (T YP)

SPS PANEL 8(GR E) -25-EXI STIN G

TSL1 5 SID E SH ELL LON GL BH D 2080 0 OCL 18621 OC L

SID E SH ELL LON GL BH D 2080 0 OCL 18621 OC L

TYPICAL SECTION SC AL E 1:50

DET "D "

EXI ST G PL 11 T H K

CP

TYPICAL SECTION @ WEB FRAME SC AL E 1:50

SEAL WELD DET

DET "K" SPS PANEL

5 CP TR AN SV WEB,

BHD OR BR AC KET 25 x 5

BAC KI N G BAR

L ON GL GD R 15102 OC L

EXI ST G PL 11 T H K

SPS 8(GR E)-25 -EXI STIN G

L ON GL GD R 15102 OC L

T O SUIT L ON GL GD R

SPS 8(GR E)-25 -EXI STIN G

DETAIL "C" SC AL E 1:4

EXI ST G PL DETAIL "B"

SC AL E 1:4 40 x 5

BAC KI N G BAR

4 TH K C OLL AR PL T O SEAL C AVIT Y

(FI T T ED ON E SID E OF WEB ONL Y)

THI S EDGE OF C OL L AR T O BE SEAL ED WI T H C AUL KIN G

DET "M"

* EXI ST G PL 22 T H K

"C " 8(GR E) -25-EXI STIN G

* DET "L "

KN UC KL E

5 25 x 5

BAC KI N G BAR

100 x 15 0 x 25 TH K PL T CORN ER S T O BE C H AMF ER ED

EXI ST G PL TO BE WELD ED & BON D ED IN PL AC E SI MIL AR T O D ET"H"

EXI ST G STIF R 300 x 1 1 H P

40 x 25

PERI MET ER BAR

CP *

SPS 8(GR E)-25 -EXI STIN G EXI ST G PL

SPS 8(GR E)-25 -EXI STIN G 25 x 5

DETAIL "F" @ END OF C AVIT Y WI TH SPS ON ON E SID E ONL Y

SC AL E 1:4

DETAIL "D" SC AL E 1:4

BAC KI N G BAR 100 x 150 x 2 5 TH K PL T C OR N ER S T O BE CH AMF ER ED

DETAIL "A" TO T O SUIT L ON GL GDR

IN PL AC E BE WEL D ED & BOND ED

STIF F EN ER C P FL AN GED SC AL E 1:4 SIMIL AR T O D ET "H "

25 x 5 BAC KI N G BAR

C OR N ER

EXI ST G PL 11 T H K

L ON GL GD R 15102 OC L

EXI ST G PL

* N O WELD C OLL AR T O BE SEAL ED WI T H C AUL KIN G

PI PE D R AIN SPI GOT

* IN T H ESE L OC ATI ON S

DET "J" T O BE FIT T ED AT AF T EN D OF C AVITI ES

50

350 MI NI MU M SI M T O D ET "H "

EXI STI N G D EC K PL AT E T O BE R EN EWED (AS R EQUI R ED ) PR I OR T O

IN ST ALL ATI ON OF SPS OVERL AY

DETAIL "L" SC AL E 1:4

DETAIL "K" SC AL E 1:4

GAPS T O BE FILL ED WI TH SEAL AN T

DETAIL "F" @ END OF C AVIT Y WI TH SPS ON BOT H SID ES

SC AL E 1:4 3000 (T YP)

1 1/4 " SCH 8 0 PI PE

SEAL WEL D GRIN D FL U SH

SID E SH ELL 2080 0 OCL

EXI STIN G T RAN SV TYPICAL DETAIL OF SPS CAVITIES TR AN SV

WEB WEB FR AME

EXI STIN G T RAN SV WEB FR AME

5 CP 5 TR AN SV

WEB

PL AN AT SL OPIN G BH D & U PPER D EC K ST BD SI D E D R AWN POR T SID E SI MIL AR T O OPP H AND

SC AL E 1:2 0

TR AN SV WEB

50x2 5 T H K RI N G PL T AROUN D PEN ETR ATI ON S 25 x 5

BAC KI N G BAR L ON GL GD R

80 L ON G x 2 4 T H K PL (WID T H T O SUIT ) C OR N ER S T O BE CH AMF ER ED 25 x 5

BAC KI N G BAR T O SUIT EXI STI N G WELD S

DETAIL "G" TO BE BOND ED I N PL AC E SC AL E 1:4

DETAIL "J" SC AL E 1:4

25 x 5 BAC KI N G BAR

100 x 15 0 x 25 TH K PL T CORN ER S T O BE C H AMF ER ED

T O SUIT EXI STI N G WELD S T O BE BON D ED IN PL AC E

40 x 25 PERI MET ER BAR

25 x 5 BAC KI N G BAR

EXI ST G PL

SPS T OP PL T R ADIU SED T O SUI T SIZ E OF EXI STIN G SC ALL OPS

IN WEB FR AME PL T T O BE FI TT ED I N T HI S AR EA

25 x 5 BAC KI N G BAR

L ON GL 4 TH K

C OLL AR

DET "G"

25 x 5 BAC KI N G BAR

8(GR E) TH K SPS F AC E PL

DETAIL "J" 3 L OC N S P&S

I. W.O. COF F ERD AM SC AL E 1:4

DETAIL "M" SC AL E 1:4

100 x 15 0 x 25 TH K PL T AF T ER IN JECTI ON S

5 C OR N ER S T O BE CH AMF ER ED

T O SUIT EXI STI N G WELD S T O BE WEL D ED & BOND ED I N PL AC E

100 x 15 0 x 25 TH K PL T CORN ER S T O BE C H AMF ER ED

T O SUIT EXI STI N G WELD S T O BE BON D ED IN PL AC E

8(GR E) TH K SPS DET F AC E PL "H "

25 x 5 BAC KI N G BAR DETAIL "E"

SC AL E 1:4 DETAIL "H"

SC AL E 1:4

NOTES 1. ALL DIMENSIONS IN mm AND TO BE CONFIRMED AT SHIP

PRIOR TO WORK COMMENCING.

2. STEEL - ABS GRADE A OR EQUIVALENT EXCEPT SPS TOP PLATE WHICH IS TO BE GRADE E.

3. ALL STEEL ON INTERIOR OF SURFACES OF SPS CAVITIES

IS TO BE GRIT BLASTED TO A SURFACE ROUGHNESS OF

60+MICRONS, AND BE CLEAN,DRY,FREE OF GRIT, GREASE

AND OTHER CONTAMINANTS .

4. SPS CAVITIES MUST BE AIR TIGHT. 5. THERE SHALL BE NO SUBSTITUTIONS OF MATERIALS

WITHOUT PRIOR WRITTEN APPROVAL OF

INTELLIGENT ENGINEERING OR THE ABS SURVEYOR.

6. WELDING TO ABS STANDARDS. 7. ALL WELDING TO BE COMPLETE PRIOR TO ELASTOMER

INJECTION.

8. ALL FILLET WELD SIZES SHOWN ARE LEG LENGTH.

9. ALL WORK TO BE PERFORMED IN ACCORDANCE WITH INTELLIGENT ENGINEERING TENDER SPECIFICATION

FOR SPS SLOPING BHD REINSTATEMENT FOR THE

"TENAGA SATU" PREPARED FOR MISC BERHAD.

10. ALL FIT-UP AND WELDING IS TO BE TO THE SATISFACTION

OF THE ATTENDING SURVEYOR. 11. 25 x 5 FB BACKING BAR IS TO BE USED IN ORDER TO FIX

THE SPECIFIED 25mm ELASTOMER THICKNESS AT PANEL

BOUNDARIES.

PROPRIET ARY AND CONFIDENTIAL COPYRIGHT INT ELLIGENT ENGINEERING 2010

2 2011- 10-27 SPS AREA MODIFIED DET "L" & "K" REVISED CJO OS 1 2011-09- 12 SPS AREA REVISED CJO OS

REV DATE MOD DRN CHK DRA WN BY:

CJO

DATE:

2010-09-22

PROJECT No.:

10-178

CHE CKED:

OS

DATE:

2010-09-23

DRA WING No.:

10178-001-02

SCAL E:

AS SHOWN

SHEET SIZE: A1

SHEET OF

2 2

PROJECT:

FSU LEKAS (IMO # 7428457) TITL E:

SPS OVERLAY SLOPING BHD

FIL E NAME: 2011-10-27 10178-001 Rev2.dwg

Intelligent Eng inee r ing (C anad a) Limited 14 Cha mbe rlain Avenue Otta wa, Ontario Canada Te l: +1 -613 -569-311 1

Fax: +1 -613-569-3 222

intelligent engineering

20

35

0 M

INIM

UM

UPPE

R DE

CK

SL

OPIN

G BH

D

Page 58: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | DSME “Storium” | October 2011 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

DSME “Storium” Floating Museum and Exhibition Centre

South Korea - October 2011

The “Bow Hunter” is the first vessel built by Daewoo Shipbuilding and Marine Engineering. The ship is now converted to a company museum and exhibition centre celebrating more than 35 years of shipbuilding and marine engineering.

The project involved rapid installation of 3,500m² of SPS decks on two levels,

providing a flat rigid floor with excellent dynamic and acoustic response.

Page 59: Project Portfolio Web Version June 10 2015

SPS Marine Technologies Limited | SPS Hatch Cover | January 2010 | page 1 of 1 Registered in BVI BC No 1533855

First SPS Hatch Cover goes into service January 2010

Page 60: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Project Portfolio | June 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

CONTENTS RECENT PROJECTS 1. Stadia 2. Buildings 3. Bridges 4. Industrial 5. Maritime OTHER INFORMATION 6. Engineering 7. Production 8. Publications 9. Company Profile

June 2015

Page 61: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Project Portfolio | June 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

6. ENGINEERING

• Tests - shear - fire (intumescent coatings) - blast - fire (extreme events)

• Data Sheets - terraces - floors - bridge decks

• Load Span Tables

• Published Documents - R&D and approvals - technical notes - method statements

Page 62: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Shear Test | May 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Shear Test May 2015

Testing Facility: ATLSS Engineering Research Centre Lehigh University, Pennsylvania, USA

• Independent large scale tests at world renowned structures laboratory demonstrate; − strength and stiffness of SPS plates providing diaphragm capacity for floors and

roofs, and shear capacity for shear cores/walls − energy dissipation capacity (resistance) for seismic loads

• SPS shear cores provide two key benefits − eliminates concrete above ground level − thinner walls increase net lettable area (NLA) - e.g. at 3m²/elevator/floor, a 40-

storey building with 8 elevators gains 960m² of extra NLA with a value of $15M (in the London office market)

• actuator capacity ~ 8000 kN (816 tonnes)

• mass of frame ~ 84 tonnes

• frame dimensions ~ 13m x 8m (42’x26’)

• SPS 4-25-4 test panel dimensions: 2m x 4m (6.5’x13’)

Page 63: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Flooring with Intumescent Coatings – Fire Resistance | May 2015 | Registered in England 3184851 | A member of the IE Group of Companies |

SPS Flooring With Intumescent Coatings – Fire Resistance May 2015

1. SPS Floors Fire Resistance

SPS Floors with underside fire protection have been tested to the US and European fire standards ASTM E119 (UL 263) and BS EN 1365-2 passing the insulation, integrity and loadbearing criteria for 2 hours. These ratings apply to SPS floors with mineral board (stone wool) and with cementitious spray fire protection.

Fig. 1 – SPS Floor: 2-hour Fire Resisitance Test to UL 263

a) During Test b) After Test

2. SPS Floors with Intumescent Protection An indicative fire test has been conducted on 4-50-4BC SPS Floor with a thin film intumescent coating: Interchar 2060 at 1mm thickness. The test comfortably passed 2 hours fire resistance. The SPS Floor is scheduled to be tested in accordance with BS EN 1365-2 at BRE Global. Interchar 2060 from International Paints is an industry standard intumescent widely used on structural steel: it gives a hard, durable coating, ideal for factory application to SPS panels.

Fig. 2 – Intumescent Coated SPS Floor before Testing

a) SPS Plate b) SPS Floor

This innovation allows SPS floor plates to be delivered to site with inherent fire resistance, ready to be quickly fitted and avoiding the need for any follow on trades.

Thermocouples

Page 64: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Escape Tunnel Blast Resistance | September 2013 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Blast Resistance September 2013

• Escape tunnel for new BP FPSO Quad204

• Blast tests at GLND Spadeadam

• 2.3 bar blast pressure – major explosion

• Panels performed as predicted by computer modelling

• Full structural integrity and still provides protection against fire and further blasts – occupants safe

Page 65: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Extreme Fire Resistance | September 2013 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Resistance to Extreme Fire Events September 2013

• Escape tunnel for new BP FPSO Quad204 • Fire protection against extreme oil / gas / product fires • 2 hours hydrocarbon fire resistance • 1 hour jet fire resistance – supersonic blast of heated propane • Full structural integrity – occupants safe • LR fire certificates: H120, J60

Page 66: Project Portfolio Web Version June 10 2015

Data Sheet (Metric)

www.ie-sps.com May 2015

Terraces

SPS Terraces are designed for each application to provide suitable static and dynamic responses for the relevant spans, applied loads and venue use. Terrace stiffness and natural frequency, which are typically key design criteria, can be changed by selecting the appropriate thicknesses of the terraces’ metal faceplates.

Design

Materials Faceplates: Steel (S235)

Core: Polyurethane

Geometries Possible SPS Terraces are custom made to suit each venue with geometries designed to suit each area of the bowl including facetted corners and parabolic bowls

SPS Specification 4-20-4

Steel Grade 235

Tread (mm) 800mm for all scenarios shown (different tread widths can be provided)

Span (m) 6.00 7.65 9.00

Rise (mm) ≥200 ≥250 ≥300

Weight (kg/m2) ≥106 ≥109 ≥113

Natural Frequency (Hz) 10 9 7

Deflection (L/-) 400 350 300

Note: Unit weight is quoted as kg/m2 on plan and varies with terrace geometry and specification.

Note: Natural frequency is for the bank of SPS Terraces only and must be combined with the natural frequency of the supporting frame to assess the natural frequency of the whole stand.

Performance & Quality

Typical Service Loads

SDL: 0.75 kN/m²; LL: 5 kN/m² (other load combinations readily accommodated)

Ultimate Capacity Ultimate capacity of SPS Terraces is equal to plastic capacity of steel faceplates in bending and exceeds the effects of standard imposed building loads (greater than 10 kN/m²).

Stability SPS Terraces act as diaphragm. Lateral forces are transferred through the bolted connection between the terrace treads and the stools attached to the raker frame which then distributes these forces to the lateral load resisting system.

Fire Resistance

Up to 120:120:120 minutes using conventional fire protection which is either factory or field applied. The thickness of the protection is tailored to the period of protection required.

(Note: The fire engineering can be used to show that, given the rapid evacuation requirements of venues, SPS Terraces do not require fire protection to provide a safe structure during a fire.)

Acoustics SPS Terraces offer similar acoustic performance to concrete terraces for reflection, transmission and impacts.

Coating

SPS Terraces are factory coated with epoxy or polyurethane systems to meet venue “life-to-first-maintenance” requirements within the local environment. Typically, 150 microns on all faces for a 15 year requirement in a C3 environment.

The treads of SPS Terraces are coated with an additional 75 micron non-slip layer.

SPS Terraces are typically grey (or black for indoor concert venues) but can be provided in any RAL colour.

Watertight Seals

Joints on the rises of SPS Terraces are naturally watertight.

Joints between adjacent bays of terraces directly above the rakers are made watertight by a continuous tape that runs from the top to the bottom of the bank. The tape is adhered into a recess at the edge of each tread.

Geometric Tolerance ±3 mm over 10m Flatness ±3 mm over 3m

Note: All performance characteristics proven by full-scale independent tests. Full performance documentation available. Design guidelines and engineering models also available.

Page 67: Project Portfolio Web Version June 10 2015

Data Sheet (Metric)

www.ie-sps.com May 2015

Terraces

Detailing

Rise to Rise Connections

Socket Button Head Bolts, Tension Control Bolts, Lindapter Hollobolts or Structural Rivets used to connect overlapping steel rises using factory drilled holes typically set at 500mm centres. All central rises of factory assembled double or triple banks fully bolted prior to shipping.

Tread to Raker Connections

Hexagonal Head Bolts are used to connect treads to top flange of raker stools. Bolt holes in treads factory made with recess to allow head of bolt to sit in depth of tread and be covered with steel capping plate finished to match tread.

Front & Rear Connections

The fore or rearmost rise of the bank of SPS Terraces are either supported by structural hollow sections or connected to concrete slabs using expansion anchors.

Upstands A forward upstand can be created in factory by welding vertical SPS panel to front of foremost tread prior to coating. Top of upstand can be fitted with variety of railing details.

Seat Brackets Seats can be attached to the rise or tread of SPS Terraces. For rise mounted seats, bolt holes are pre-drilled in the factory (field drilling possible if required). For tread mounted seats, insert plates are welded as required into during the manufacturing process to accommodate connections.

Balustrades and Rails

Rails can be attached to the rise or tread of SPS Terraces. For rise mounted rails, bolt holes are pre-drilled in the factory (field drilling possible if required). For tread mounted rails, insert plates are welded as required into during the manufacturing process to accommodate connections.

Insert Steps Single or double insert steps can be supplied and are made from folded steel plates with acoustic damping placed inside. The steps are fully coated to the same finish as the terraces with nose highlighting. The steps can be manually lifted into place and are adhered to the treads.

Fit-out M&E details are attached to the SPS Terraces with Hilti studs or Tek screws.

Penetrations We aim to make penetrations in factory before shipping. On site, penetrations can be made using industry standard core drilling or cold cutting methods.

Drainage Treads are sloped at 2° down towards the front of the terrace and drained at the lowest terrace which may have reverse slope. Drainage holes are incorporated in or between the treads.

Delivery & Erection

Off-site Manufacture & Finishing

SPS Terraces delivered to site as fully finished, coated and incorporating as many details as is practical. Apart from bolting and joint sealing no work to the terraces is required on site.

Delivery SPS Terraces are delivered to site on flat bed trucks stacked in order of a defined erection sequence. Between 30-45 SPS Terraces, pre-assembled as doubles or triples, can be delivered per truck depending on their length and weight.

Erection Trade Single trade erection, typically by same steel erector as frame. All connections to frame use industry standard bolting – no additional crew training required.

Crew Size 4 erectors for panel lifting, aligning and fitting initial bolts. 4 erectors to complete bolting, adhere sealing strip above raker and fix insert steps.

Erection Equipment Crane: typical lifts between 1.5 and 2.5 tonnes. Scissor lift: for bolting from below (if required). Lifted with: vacuum lift; or chains with threaded lifting eyes using factory made holes in the treads.

Installation Rate 600-900 seats erected/day/crane (assuming 15 to 20 lifts/day) as part of frame steel erection.

Through-life

Penetrations In-situ penetrations carried out with magnetic based drills, core drills or cold saws. Procedure is quick, dry, dust free and causes limited disturbance. Cut piece is light and easily removed.

Demountable (Demolition)

SPS Terraces should be unbolted and lifted off the frame. The supporting steel frame is then readily unbolted and can be re-used rather than demolished and recycled.

Reuse SPS Terraces can be recoated and reused on future venues.

Recycling Both the steel and polyurethane elements of the SPS Terraces can be recycled. The steel is recycled within the steel market. The polyurethane is crushed and used as filler in future SPS panels.

Page 68: Project Portfolio Web Version June 10 2015

Data Sheet (Metric)

www.ie-sps.com May 2015

Floors

SPS Floors are designed for each application to provide suitable static and dynamic responses for the relevant spans, applied loads and building use. Panel stiffness, which is typically a key design criteria, can be changed by selecting the appropriate thicknesses of the metal faceplates and elastomer core.

Design

Materials Faceplates: Steel (S235-S355), stainless steel or aluminium are available Core: Polyurethane (fillers are used to lighten core when appropriate)

Geometry Typically rectangular (cut-outs and curved edges possible)

SPS Specification 3-20-3 4-20-4 4-25-4 4-40B-4 4-50B-4

Length (m) Typical Length: 5-12m (smaller and larger sizes can be provided

Width (m, typical) Up to 1.5m Up to 1.75m Up to 2.0m Up to 2.5m Up to 3m

Thickness (mm) 26 28 33 48 58

Weight (kg/m²) 84 98 106 97 102

U Value (W/m²K) 3.85 3.85 3.55 2.95 2.65

Note: Unit weight varies with panel size and edge detail. Weights listed are typical for panels with associated SPS specification.

Performance

Typical Service Loads

SDL: 1.5 kN/m²; LL: 4.5 kN/m² (other loads and combinations readily accommodated)

Deflection Typically less than L/750 (for widths and live load listed above).

Dynamic Response The stiffness of SPS panels and supporting beams are adjusted to meet the needs of a particular building or room (e.g. Rfactor 6 is readily achieved for office floors).

Point Loads Once bolted in place, SPS Floors are readily able to carry most typical wheel loads from equipment such as cherry pickers, scissor lifts, fork lifts etc.

Ultimate Capacity Ultimate capacity of SPS Floor panels is equal to plastic capacity of steel faceplates in bending and exceeds the effects of standard imposed building loads (greater than 7.5 kN/m²).

(Note: Ultimate capacity of beams is not covered by this data sheet)

Composite Action Achieved through bolts connecting edges of SPS Floor panels to top flanges of supporting beams. Welded connections also possible.

Stability SPS Floors panels transfer diaphragm forces to the lateral load resisting system via bolts connecting edges of panels to top flanges of supporting beams. Welded connections also possible.

Fire Resistance

Up to 120:120:120 minutes using conventional fire protection which is either factory or field applied. When shorter periods are required the thickness of the protection is reduced accordingly.

(Note: an untreated SPS panel achieves an inherent 30 minute resistance with a 20mm core thickness, and 60 minutes for 25mm and thicker cores.)

Acoustics

Finished floors incorporating SPS Floor panels meet standard acoustic insulation requirements for airborne, impact and flanking noise for all conventional building types. For instance: SPS Floor design for hotels and offices provides: 49 dB of airborne sound insulation; and 46 dB of impact sound absorption provided standard hotel finishes are applied

Note: All performance characteristics proven by full-scale independent tests. Full performance documentation available. Design guidelines and engineering models also available.

Page 69: Project Portfolio Web Version June 10 2015

Data Sheet (Metric)

www.ie-sps.com May 2015

Floors

Detailing & Quality

Connections Bolts connecting edges of panels to top flanges of supporting beams. Typically at 500mm centers. Use of tension control bolts minimizes bolting work. Welded connections also possible.

Attachments All industry standard fixing solutions compatible with SPS Floor panels (including: threaded fasteners, powder-actuated nailing, through bolts, chemical anchors).

Penetrations

Typically made in factory before shipping. On site coring or penetrations can be undertaken using standard industry methods. Up to 0.65m² of penetration within 9m² area without need for additional floor reinforcement. Either as single penetration or multiple smaller penetrations. Penetrations can be made in any location within a panel. Larger penetrations can be made if panel is locally stiffened with secondary framing.

Finishes All conventional floor finishes have been tested on SPS Floors and are easily installed. High panel stiffness limits risk of ceramic floor finishes cracking in service.

Geometric Tolerance ± 3mm over 10m

Flatness ± 3mm over 3m

Delivery & Erection

Off-site Manufacture Individual SPS Floor panels delivered to site pre-formed to required geometries and ready to be installed on frame directly from truck.

Off-site Finishing IE works with project teams to incorporate all appropriate penetrations, attachment details, floor finishes and fit-out items on the SPS Floor panel in the factory.

Delivery Delivered to site on flat bed trucks stacked in order of expected installation. 200-275m² delivered per truck.

Erection Trade Single trade erection, typically by same steel erector as frame. All connections to frame use industry standard techniques - no additional crew training required.

Crew Size (direct crew only)

4 erectors for panel lifting and locating 3 erectors to complete bolting

Erection Equipment Crane: lifts between 1 and 4 tonnes Scissor lift: to complete bolting work from below

Installation Rate 500-750m² erected/day/crane (assuming 20 to 30 lifts/day) as part of frame steel installation

Site Safety

Reduced on-site processes, trades and personnel. Reduced construction work and hazards on site. Immediate full capacity working floors closely following the main steel erection work front provide a safe working platform for steel erection crews and a built-in protection deck for following trades working on floors below.

Through-life

Penetrations In-situ penetrations carried out with magnetic based drills, core drills and cold saws. Procedure is quick, dry, dust free and causes limited disturbance to building environment. Cut piece is light and easily removed.

Modifications Complete or partial panels can be unbolted, cut-up to size and removed from the building with limited disturbance using standard equipment. New panels can also be readily installed as required with limited impact on the existing frame.

Demountable (Demolition)

SPS Floor panels should be unbolted and lifted off the frame. This also allows the supporting frame to be demounted and reused rather than demolished and recycled.

Reuse SPS Floor panels can be reused on future buildings. Their supporting beams can also be used with the panels on a next building.

Recycling Both the steel and polyurethane elements of the SPS Floor panels can be recycled. The steel is recycled within the general steel market. The polyurethane is crushed and used as filler within future SPS panels.

Page 70: Project Portfolio Web Version June 10 2015

Data Sheet (Metric)

www.ie-sps.com May 2015

SPS Bridge Decks are designed for each project to provide suitable performance for the relevant spans, applied loads and bridge use. Panel strength and stiffness can be changed by selecting the appropriate thickness of the metal faceplates and elastomer core.

Typical Designs

Materials Faceplates: Steel (S275-S355), weathering steel also available Core: Polyurethane

Geometry Typically rectangular (tapered, skewed, and curved edges possible as well as cut-outs). Details available for incorporating deck camber, crossfall, and superelevations.

SPS Specification 8-30-8 10-25-10 10-30-10 12-25-12 12-30-12

Panel Length (m) Typical Length : 5-12m (smaller or larger sizes can be provided)

Span / Panel Width (m) 2.00 2.20 2.60 2.80 3.00

Thickness (mm) 46 45 50 49 54

Weight (kg/m²) 188 207 214 235 242

Bolt Spacing (mm) 150 150 150 150 150

Min Flange Thickness (mm) 26 28 30 38 32

Unit weight varies with panel size and edge detail. Weights listed are typical for panels with associated SPS specification.

Performance

International Standards Used

Canada CAN/CSA-S6

USA AASHTO LRFD

Eurocode 3 Part 2 BS EN 1993-2006

Typical Service Loads

CL 625 HL-93 Country specific

Deflection Typically less than L/300

Construction Loads Once bolted in place, SPS Bridge Deck panels are readily able to carry most typical wheel loads from equipment such as mobile cranes, telehandlers and fork lifts.

Ultimate Capacity SPS Bridge Deck designs are governed by serviceability and fatigue requirements, therefore the SPS Bridge Deck has significant capacity beyond the maximum factored loads for design.

Composite Action Up to 100% composite action achieved through bolts connecting edges of SPS Bridge Deck panels to top flanges of supporting girders or stringers.

Stability SPS Bridge Deck panels transfer diaphragm forces to the lateral load resisting system via bolts connecting edges of panels to top flanges of supporting girders or stringers.

Design Life SPS Bridge Deck panels are designed to have a typical design life of 120 years, with well maintained structures likely to last for significantly longer.

Note: All performance characteristics proven by full-scale independent tests. Full performance documentation available. Design guidelines and engineering models also available.

Page 71: Project Portfolio Web Version June 10 2015

Data Sheet (Metric)

www.ie-sps.com May 2015

Detailing & Quality

Connections Slip critical bolted connections along edges of panels to top flanges of supporting girders and stringers. Use of tension control bolts simplifies the pre-tensioning process.

Attachments Standard details available for attaching barriers (steel guardrails or pre-cast concrete Jersey barriers), expansion joints, curbs, signage, and lighting.

Drains Typically made in factory before shipping. SPS Bridge Deck panels arrive on site with openings to accept steel drains. These are connected to the SPS panels by field weld.

Wearing Surfaces Both asphalt and lightweight thin screed systems have been tested on SPS Bridge Decks and are easily installed. Reduced deck curvatures limit local cracking of asphalt and increases life.

Geometric Plan Tolerance

±3mm for dimensions up to 12m

Flatness ±3mm over 3m

Delivery & Erection

Off-site Manufacture Individual SPS Bridge Decks panels are delivered to site prefabricated to required geometries and ready to be installed on the superstructure directly from truck.

Off-site Finishing IE works with project teams to incorporate all appropriate drains, attachments and other details on the SPS Bridge Deck panels in the factory.

Delivery Delivered to site on flat bed trucks stacked in order of expected installation. 125m² delivered per truck.

Erection Trade Single trade erection, typically by same steel erector. All connections to structural frame use industry standard techniques. No additional crew training required.

Crew Size 4 erectors required for panel lifting, locating and bolting (direct crew only).

Erection Equipment SPS Bridge Deck installation proceeds in sequence with the advancing lifting equipment (mobile cranes or telehandlers).

Access SPS Bridge Deck panels can support mobile crane loads immediately upon installation and prior to completion of bolting.

Installation Rate 400-600m² erected / day assuming 15 lifts/shift/crew with one crew at each end of bridge.

Site Safety Reduced on-site processes, trades and personnel. Reduced construction work and hazards on site. Immediate, full capacity, working decks provide a safe working platform for steel erection crews and a built-in protection deck for space below.

Through-life

Penetrations In-situ penetrations carried out with magnetic based drills, core drills and cold saws. Procedure is quick, dry, and causes limited disturbance to environment. The cut-out sections are light and easily removed.

Repair Complete or partial panels can be unbolted and removed from the bridge with limited disturbance using standard equipment. New panels can also be readily installed as required with limited impact on the existing superstructure.

Demolition (demounting)

SPS Bridge Deck panels may be unbolted and lifted off the structural framing. This also allows the supporting structure to be demounted and reused rather than demolished and recycled.

Reuse SPS Bridge Deck panels and supporting superstructure can be reused on future bridges.

Recycling Both the steel and polyurethane elements of the SPS Bridge Decks can be recycled. The steel is recycled within the general steel market. The polyurethane is crushed and used as filler within future SPS panels.

Maintenance Typically weathering steel is used for the fabrication of SPS Bridge Decks eliminating the need for coating maintenance. The topside of the SPS Bridge Deck is coated using industry standard methods to provide a protective barrier against standing water as required for weathering steel.

Page 72: Project Portfolio Web Version June 10 2015

Floors

SPS Load Span Tables

www.ie-sps.com

Lighter Structures Shorter Schedules

Smart

Fast

Economic

Page 73: Project Portfolio Web Version June 10 2015

SPS Load Span Tables February 2013 Floors

Intelligent Engineering Ltd [email protected] 2

Introduction Sandwich Plate System (SPS) is a structural floor plate comprised of two steel faceplates bonded together with a polyurethane elastomer core. Integrated steel perimeter bars contain the elastomer. The plates are generally bolted through the bars and act compositely with the supporting beams. SPS is an alternative to both stiffened steel, reinforcing concrete and composite concrete decking. SPS delivers a high stiffness to weight ratio and improved performance.

SPS achieves its thin dimension and low weight by utilising the elastomer core which transfers shear between each faceplate and prevents local buckling. Flexural strength and stiffness can be tailored to meet the specified structural requirements by selecting the appropriate thicknesses for each sandwich element. This datasheet assists the selection of panel thickness for different design criteria.

More than 200,000 m2 of SPS has been successfully used in building floor and wall configurations, shear walls, blast walls, as well as ships, bridges and stadium terraces. All structures are designed and produced to relevant codes and standards. SPS Floors provide an effective economic alternative to reinforced concrete or composite concrete/decking floors with identified benefits listed below.

Generally SPS floor plates are rectangular in plan but other shapes are possible (trapezoidal, curved edge etc).

Summary of SPS Benefits

Characteristic Benefit Result

lighter

structural frame is lighter steel cost savings

reduced foundations cost savings and shorter programme

camber of secondary beams not required simpler beam fabrication

thinner

reduced overall floor thickness and storey height cladding cost saving

potential extra floor available on taller buildings

full structural capacity upon installation

reduced activities at site

faster construction time; earlier start for follow up trades; shorter

programme

improved tolerances and floor quality

provides material storage, acts as an erection platform and protects works below

eliminates programme lag for concrete and curing

less weather dependent

fixings, penetrations and inserts pre-installed

interfaces more controlled faster construction

leading edge protection can be incorporated improved safety

single trade erection simpler site control and coordination management cost savings

sustainability

reduced total material; reduced construction waste; fewer vehicle movements

comparable carbon footprint to other forms of floor construction re-useable faceplates with large percentage of

recyclable material

Page 74: Project Portfolio Web Version June 10 2015

SPS Load Span Tables February 2013 Floors

Intelligent Engineering Ltd [email protected] 3

Notes for the Load Span Tables: • These load span tables can be used for preliminary selection of SPS panel sections. The spans given are

based on deflection criteria as these govern. The span is defined as the distance between supporting beams. • Designs are in accordance with BS/EN 5950.

• Applied loads include all superimposed dead and live loads other than SPS panel self weight.

• Unit mass of SPS panels is based upon an elastomer density of 1150 kg/m3 and a steel density of 7850 kg/m3.

(Unit mass calculations exclude the weight of panel perimeter bars which typically weigh 10 kg/m.) • Tables are included for deflection limits of L/360 and L/750. Recommended limits for different uses are given.

The more stringent limits are to provide acceptable dynamic performance. • Tables for differing loads and deflection limits are available from Intelligent Engineering upon request.

• Spans calculated assume a one way spanning panel with an aspect ratio greater than 3.

• A fully detailed design can be developed from BS/EN 5950 in conjunction with the recommendations given in

“Engineering Design Guidelines for SPS Floors” available from Intelligent Engineering upon request. • Tables are provided for solid core and bubble core panels. A solid core contains 100% elastomer. A bubble

core has approx. 50% of the elastomer displaced by hollow polypropylene balls of a diameter equal to the core thickness, thus reducing the weight of the panels and minimising the quantity of elastomer.

• In most design instances, there will be a suitable option using either solid core or bubble core panels for any

given superimposed load and required span. The selection of the preferred option will be a function of the desired panel thickness, weight and product cost. IE will advise as required.

• SPS panels provide diaphragm capacity.

• Beams can be made composite with the SPS panels using bolted connections.

Recommended Maximum Values for Deflections for Specified Design Live Loads

Building Type Applications Maximum Deflection

industrial buildings

simple span members supporting elastic roof coverings L/180

simple span members supporting inelastic roof coverings L/240

simple span members supporting floors L/300

all other buildings

simple span members of floors and roofs supporting construction and finishes not susceptible to cracking L/300

simple span members of floors and roofs supporting construction and finishes susceptible to cracking L/360

deflection limit estimate for floor plates to give a dynamic performance of R=8 for footfall induced vibrations L/600 < δ < L/750

Page 75: Project Portfolio Web Version June 10 2015

SPS Load Span Tables February 2013 Floors

Intelligent Engineering Ltd [email protected] 4

Load Spans: Solid Core = L/360

SPS Floor Plates (Solid Core) Deflection Limit = L/360

t

c

t

Simply Supported

Span (mm)

SPS Floor Plate t-c-t

Unit Mass, kg/m2

Applied Load, kN/m2

2.0 2.5 5.0 7.5 10.0 3-20-3 70.1 2640 2450 1930 1670 1510 3-25-3 75.9 3010 2790 2200 1910 1730 3-30-3 81.6 3360 3120 2460 2130 1930

4-20-4 85.8 2990 2770 2180 1890 1710 4-25-4 91.6 3390 3140 2480 2150 1940 4-30-4 97.3 3770 3500 2760 2390 2160

5-20-5 101.5 3310 3070 2410 2090 1890 5-25-5 107.3 3740 3460 2730 2370 2140 5-30-5 113.0 4140 3840 3020 2620 2370 5-35-5 118.8 4530 4200 3310 2870 2590 5-40-5 124.5 4900 4540 3580 3110 2810

6-20-6 117.2 3610 3340 2630 2280 2060 6-25-6 123.0 4060 3760 2960 2570 2320 6-30-6 128.7 4490 4160 3270 2840 2570 6-35-6 134.5 4890 4530 3570 3100 2800 6-40-6 140.2 5280 4900 3860 3350 3020

8-20-8 148.6 4170 3870 3050 2640 2390 8-25-8 154.4 4660 4320 3400 2950 2660 8-30-8 160.1 5120 4740 3730 3240 2920 8-35-8 165.9 5560 5150 4050 3520 3180 8-40-8 171.6 5980 5540 4360 3790 3420

10-20-10 180.0 4710 4360 3440 2980 2690 10-25-10 185.8 5220 4830 3810 3300 2980 10-30-10 191.5 5700 5280 4160 3610 3260 10-35-10 197.3 6170 5720 4500 3900 3530 10-40-10 203.0 6620 6130 4830 4190 3780

Page 76: Project Portfolio Web Version June 10 2015

SPS Load Span Tables February 2013 Floors

Intelligent Engineering Ltd [email protected] 5

Load Spans: Bubble Core = L/360

SPS Floor Plates (Bubble Core) Deflection Limit = L/360

t

c

t

Simply Supported

Span (mm)

SPS Floor Plate t-c-t

Unit Mass, kg/m2

Applied Load, kN/m2

2.0 2.5 5.0 7.5 10.0 4-30-4 80.1 3730 3450 2700 2330 2090 4-40-4 85.8 4440 4110 3210 2770 2490 4-50-4 91.6 5090 4710 3690 3190 2870 4-60-4 97.3 5710 5280 4140 3580 3220

5-30-5 95.8 4100 3790 2960 2550 2290 5-40-5 101.5 4850 4490 3510 3030 2720 5-50-5 107.3 5550 5130 4020 3470 3120 5-60-5 113.0 6210 5740 4500 3880 3490

6-30-6 111.5 4430 4100 3200 2760 2480 6-40-6 117.2 5230 4830 3780 3260 2920 6-50-6 123.0 5960 5520 4310 3720 3340 6-60-6 128.7 6660 6160 4820 4160 3740

8-30-8 142.9 5060 4680 3650 3140 2820 8-40-8 148.6 5910 5470 4270 3680 3300 8-50-8 154.4 6710 6210 4850 4180 3750 8-60-8 160.1 7470 6910 5400 4660 4180

10-30-10 174.3 5640 5210 4070 3500 3140 10-40-10 180.0 6540 6050 4720 4070 3650 10-50-10 185.8 7390 6830 5340 4600 4130 10-60-10 191.5 8190 7580 5920 5100 4580

Page 77: Project Portfolio Web Version June 10 2015

SPS Load Span Tables February 2013 Floors

Intelligent Engineering Ltd [email protected] 6

Load Spans: Solid Core = L/750

SPS Floor Plates (Solid Core) Deflection Limit = L/750

t

c

t

Simply Supported

Span (mm)

SPS Floor Plate t-c-t

Unit Mass, kg/m2

Applied Load, kN/m2

2.0 2.5 5.0 7.5 10.0 3-20-3 70.1 2050 1900 1490 1290 1160 3-25-3 75.9 2340 2170 1700 1470 1320 3-30-3 81.6 2620 2420 1900 1640 1480

4-20-4 85.8 2320 2150 1690 1460 1310 4-25-4 91.6 2640 2440 1910 1650 1490 4-30-4 97.3 2940 2720 2130 1840 1660

5-20-5 101.5 2570 2380 1860 1610 1450 5-25-5 107.3 2910 2690 2110 1820 1640 5-30-5 113.0 3220 2980 2340 2020 1820 5-35-5 118.8 3520 3260 2560 2210 1990 5-40-5 124.5 3810 3530 2770 2390 2150

6-20-6 117.2 2810 2600 2030 1760 1580 6-25-6 123.0 3150 2920 2290 1980 1780 6-30-6 128.7 3490 3230 2530 2180 1960 6-35-6 134.5 3800 3520 2760 2380 2140 6-40-6 140.2 4110 3800 2980 2580 2320

8-20-8 148.6 3240 3000 2350 2030 1830 8-25-8 154.4 3620 3350 2620 2270 2040 8-30-8 160.1 3980 3680 2880 2490 2240 8-35-8 165.9 4320 4000 3130 2700 2430 8-40-8 171.6 4650 4300 3370 2910 2620

10-20-10 180.0 3660 3390 2650 2290 2060 10-25-10 185.8 4060 3750 2940 2540 2280 10-30-10 191.5 4430 4100 3210 2770 2490 10-35-10 197.3 4790 4440 3470 3000 2700 10-40-10 203.0 5140 4760 3730 3220 2900

Page 78: Project Portfolio Web Version June 10 2015

SPS Load Span Tables February 2013 Floors

Intelligent Engineering Ltd [email protected] 7

Load Spans: Bubble Core = L/750

SPS Floor Plates (Bubble Core) Deflection Limit = L/750

t

c

t

Simply Supported

Span (mm)

SPS Floor Plate t-c-t

Unit Mass, kg/m2

Applied Load, kN/m2

2.0 2.5 5.0 7.5 10.0 4-30-4 80.1 2880 2660 2060 1760 1570 4-40-4 85.8 3430 3170 2450 2100 1870 4-50-4 91.6 3940 3640 2820 2420 2160 4-60-4 97.3 4420 4080 3170 2720 2430

5-30-5 95.8 3160 2920 2260 1930 1720 5-40-5 101.5 3750 3460 2680 2290 2040 5-50-5 107.3 4290 3960 3070 2630 2340 5-60-5 113.0 4800 4430 3440 2950 2630

6-30-6 111.5 3420 3160 2440 2080 1850 6-40-6 117.2 4030 3720 2880 2460 2190 6-50-6 123.0 4610 4250 3290 2820 2510 6-60-6 128.7 5150 4750 3680 3150 2810

8-30-8 142.9 3900 3600 2780 2370 2110 8-40-8 148.6 4560 4210 3250 2780 2470 8-50-8 154.4 5180 4780 3700 3160 2810 8-60-8 160.1 5770 5320 4120 3520 3140

10-30-10 174.3 4350 4010 3090 2640 2350 10-40-10 180.0 5040 4650 3590 3070 2730 10-50-10 185.8 5700 5260 4060 3470 3090 10-60-10 191.5 6320 5830 4510 3850 3430

Page 79: Project Portfolio Web Version June 10 2015

SPS Load Span Tables February 2013 Floors

Intelligent Engineering Ltd [email protected] 8

Revision Record

Revision Number Date Comments

Rev 0 21.02.13 First issue

Page 80: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Technical Documents | May 2015 | page 1 of 5 Registered in England 3184851 | A member of the IE Group of Companies

SPS Technology R&D and Approvals Documentation

Technology Area # Documents General SPS Technology

1.0 PU RD and Approvals 1.1 Technical Summary 2001 1.2 Material Characterisation Report 2002 1.3 Technical Notes and Method Statements (listed below) 1.4 Elastomer Type Approval Submission Document 1.5 Elastogran General SPS Summary 1.6 Elastocore 9010/100 Technical Data Sheet 1.7 SPS Panel Production 1.8 SPS Fire Safety Programme – list of tests 1.9 Unified Bond Strength Criterion 2011 1.10 Generic QA Plan for SPS Panels 1.11 Material and Failure Models for SPS Subjected to Extreme Loads 1.12 Sustainability Analysis

SPS Overlay 2.0 SPS Guidelines for Owners and Yards 2.1 SPS Overlay Technology Summary 2.2 SPS Overlay Standard Details 2.3 SPS Overlay Process Documentation 2.4 SPS Overlay Scantling Calculations and Renewal Limits 2.5 Deep Dish Cavity Process Guide 2.6 RWTH Magnets Study Report

SPS Shipbuilding 3.0 Revised LR Rules 3.1 LR Rules 2006 3.2 RCT PED Programme Report 3.3 RCT PED Phase 2 Assembly Report 3.4 DSME SPS Hatchcover, 2007 3.5 DSME Liftable Car Deck Summary, 2007 3.6 LR Fire Engineering Analysis of SPS Funnel Casing, 2003

SPS Bridges 4.0 SPS Bridge Research, 2006 4.1 SPS Bridge Deck Panels for Austrian Military, 2004 4.2 Shenley Bridge Load Test Report, 2004 4.3 RWTH – SPS D-Bridge Overlay Expertise Report, 2004 (German) 4.4 RWTH – Krefeld Asphalt Application Test Report, 2005 (German) 4.5 SPS Bridge Deck Test, VTech, 2005 4.6 RWTH – SPS Berlin Bridge Expertise Report, 2005 4.7 RWTH - SPS Overlay for Schonwasserpark-Bruke Krefeld Expertese

Report, 2006 (German) 4.8 SPS Overlay for the Berlin Viaduct 4.9 Engineering Guidelines for Bridges (imperial and metric versions)

Page 81: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Technical Documents | May 2015 | page 2 of 5 Registered in England 3184851 | A member of the IE Group of Companies

SPS Terraces 5.0 Engineering Guidelines for SPS Terraces

5.1 SPS Stadium Risers Test Report, 2002 5.2 BRE Test Report 5.3 UoS Riser Report 5.4 BRE Vibration Testing Summary 5.5 BRE Certificate ABP 008 5.6 UL Terrace Fire Certificate

SPS Flooring 6.0 Engineering Guidelines for SPS Floors 6.1 BRE Certification Test Programme Summary 6.2 BRE Fire Test 2 Hours Report 6.3 BRE Floor Load and Dynamics Test Report 6.4 BAA Floor Test Report 6.5 Arups Dynamics Test Results 6.6 University of Sheffield Dynamics Test Report 6.7 BRE Acoustics Test Report 6.8 Sol acoustics Test Report 6.9 SPS Floor Fire Test Summary 6.10 SPS Pipe Penetration Fire Test Report 6.11 BRE Certificate 154/11 6.12 HILTI Fastener Loads 6.13 UL Floor Fire Certificate

SPS Cores 7.0 Engineering Guidelines for SPS Building Cores

Page 82: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Technical Documents | May 2015 | page 3 of 5 Registered in England 3184851 | A member of the IE Group of Companies

Technical Notes

# Title 001 SPS Bubble Core - Analytical Predictions for Laboratory Test 002 Void Detection in SPS Plates 003 SPS Overlay In Way of Existing Doubler Plate 004 SPS Polyurethane Disposal 005 Critical Buckling Capacity of SPS Plates with Voids in Elastomer 006 Fatigue Resistance at Steel-Elastomer Interface 007 SPS Bridge Panels – SPS Elastomer Subjected to Elevated Temperatures 008 Temporary Restraint Beams 009 PosiTest Adhesion Test Procedure 010 Welding Attachments Foundations and Penetrations to SPS Plates 011 Bi-Axial Loading Strength Test 012 SPS Dimensional Accuracy – PED 1.2 013 SPS Structural Damping Characteristics 014 Environmental Impact of SPS in Maritime Structures 015 SPS Overlay – Low Heat Input Solutions 016 SPS Panel Fabrication 017 Recycling of Polyurethane Core 018 Plug Welded Spacers and Continuously Welded Perimeter Bars 019 Polyurethane Core Hardening and Removal of Restraint Beams 020 Repairing SPS Panels 021 Galvanised SPS Plates 022 Polyurethane Core Development and Approvals 023 Surface Preparation of Old Steel Plates 024 SPS Overlay Scantling Calculations and Renewal Limits 025 SPS Bond Strength for Steel Plates with Surface Rust 026 Removal of Damaged SPS Panels 027 Lashing Pot Pull Tests 028 SPS in Ships: Recycling & Scrapping 029 SPS Overlay in Cold Climates 030 Ageing Characteristics of Polyurethane and Fatigue Resistance of Sandwich Plates 031 The Buckling Behaviour of SPS 032 Elastomer Shear Strength 033 Fatigue Properties of Connections 034 SPS Overlay Warranty Inspections 035 SPS Behaviour Under Impact Loads

Page 83: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Technical Documents | May 2015 | page 4 of 5 Registered in England 3184851 | A member of the IE Group of Companies

036 Control of Noise and Vibrations using SPS Plates 037 Static and Repeated Patch Load for SPS Plates 038 Temperature Control Pressure Relief Valves (TCPRVs) 039 Permissible Fillet Welding to SPS Faceplates 040 SPS Thermal Cycling and Low Temperature Performance 041 SPS Overlay Vertical Injections – No Restraint 042 Cavity Preparation – Vent and Injection Ports 043 SPS Hatch Cover Mock-Up – Impact Test Summary 044 Safety Aspects of Polyurethane Core 045 SPS Compact Double Side-shell Fendering for FPSOs 046 Fire Resistance of SPS 047 Effect of Creep on SPS Plates 048 Transverse Welded Connections 049 Ballistic and Blast Resistance of SPS Plates (MOD restricted) 050 Renewal of a Structural Member Welded to SPS Plate 051 SPS Pipe Penetration Fire Test 052 Bond Strength Resistance Summary 053 Buckling Capacity of SPS Plates for SPS Overlay Reinstatement 054 Terms for Combustion of Volatile Organic Compounds 055 Surface Preparation for SPS Plates 056 Material Characteristic Test Data and Determination of Material Properties 057 Curing Behaviour of Polyurethane Core 058 Shear Stresses at Bond Interface from Plate Distortions 059 Characteristic Material Properties of Elastomer Core 060 Comparison of Surface Temperature and Radiating Heat: SPS vs Concrete Terraces 061 Recommended Fasteners for SPS Plates 062 Fire Resistance of SPS Terraces 063 Cold Cutting Procedure for SPS Plates 064 Protective Coatings for SPS Plates 065 Thermal Transmittance of SPS Plates 066 SPS Terrace Slip Resistance 067 Stadium Terrace Noise Comparison Study 068 SPS Repair Procedure – Terraces 069 Safety Data Sheet for SPS Polyurethane Core 070 Chemical Resistance of Elastomer 071 Heat Transfer and Condensation – SPS Terraces

Page 84: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | SPS Technical Documents | May 2015 | page 5 of 5 Registered in England 3184851 | A member of the IE Group of Companies

Method Statements

# Title

SPS Floors

001 Cold Cutting Penetrations

002 Shipping and Site Storage

003 Lifting Procedure

004 Installation Procedure

SPS Terraces

100 Demounting Procedures

101 Coating Application and Repair

102 Shipping and Site Storage

103 Lifting Procedures

104 Installation Procedures

105 Aisle Step Installation

106 Joint Seal Installation

107 Movement Joint Cover Installation for SPS Terraces

108 Bolt Cover Plate Installation for SPS Terraces

109 High Contrast Nosing Strip Installation for SPS Terraces

110 Group Assembly of SPS Terraces

111 Connection of Concrete Members to SPS Terraces

112 On-Site Holes for Seat Bracket Connection to SPS Terraces

Page 85: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Project Portfolio | June 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

CONTENTS RECENT PROJECTS 1. Stadia 2. Buildings 3. Bridges 4. Industrial 5. Maritime OTHER INFORMATION 6. Engineering 7. Production 8. Publications 9. Company Profile

June 2015

Page 86: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Dongkuk | February 2015| page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Production Plant Pohang, Korea February 2015

The new SPS production facility at Dongkuk Steel commenced production in February 2015. First on its order book were the SPS Terraces, Floors and Walls for Melco Crown Entertainment, Studio City Magic Theatres, Macau. It is the overflow production facility for all SPS products.

Page 87: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Gwangyang Plant | March 2014 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Production Plant

Gwangyang, Korea

• overflow facility

• 3 bays - 25m x 150m

• 5-10 tonnes overhead cranes

• painting facilities

• convenient to ports

• photographs below show SPS terraces in production

Page 88: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Production Process | March 2014| page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

SPS Production Process

Steel plate surface preparation Fast low heat robotic welding

Injecting PU CNC drilling of bolt holes

Panels stacked Panels loaded for shipment

Page 89: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Shipment | September 2013 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

Shipment

Loads 77 to 79 to Philippine Arena, Manila, Philippines

Total 64,471 kgs of longest SPS Terraces fabricated to date (up to 12,183mm)

Big R Demo Bridge to Greeley, Colorado, USA 3 concept bridge deck panels with innovative connection details - Total 4,370 kgs

Load 73 to Philippine Arena, Manila 22,112 kgs wide back of bowl

terraces

Loads 3 & 4 to Q204 Escape tunnel Mokpo, Korea Total 22,670 kgs of flat, large radius outer tunnel & small

radius inner tunnel panels up to 4,925mm long

Page 90: Project Portfolio Web Version June 10 2015

jkfeofs

fn

Intelligent Engineering (UK) Limited | Project Portfolio | June 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

CONTENTS RECENT PROJECTS 1. Stadia 2. Buildings 3. Bridges 4. Industrial 5. Maritime OTHER INFORMATION 6. Engineering 7. Production 8. Publications 9. Company Profile

June 2015

Page 91: Project Portfolio Web Version June 10 2015

Intelligent Engineering (UK) Limited | | June 2015 | page 1 of 1 Registered in England 3184851 | A member of the IE Group of Companies

jkfeofsfn

8. PUBLICATIONS

i. Mettlach Bridge

Ernst&Sohn 14 / Award - Ulrich Finsterwalder Ingenieurbaupreis – May 2015

ii. Georgia Tech Structure Magazine / Spotlight – January 2014

iii. Mettlach Bridge Ernst&Sohn / Stahlbau 11 – November 2012

iv. Dawson Bridge Modern Steel Construction (MSC) – March 2011

v. BASF / Global PUR Magazine SPS Bridges Issue 24 – 2013 SPS Terraces Issue 23 – 2012 SPS Bridges Issue 21 – 2011 SPS Floors Issue 18 – 2010

Page 92: Project Portfolio Web Version June 10 2015

Awards

Submitter/responsible engineers: Eiffel Deutschland Stahltechnologie GmbH, Hanover Client/architect: Landesbetrieb für Straßenbau (LFS) Saarland, Neunkirchen Contractor: Eiffel Deutschland Stahltechnologie GmbH, Hanover Photographs/drawings: Eiffel Deutschland Stahltechnologie GmbH, Hanover

Saar River Bridge, Mettlach, remediation and repair

The judges' reasoning The sandwich plate system (SpS) steel-elastomer-steel composite plate (integral plate) is an innovative development by Stephan J. Kennedy (Canada), which is used in a variety of engineering disciplines (shipbuilding, offshore, civil engineering). As a result of the operating strength problems associated with orthotropic deck slabs and concrete or steel composite decks, Eiffel Deutschland Stahltechnologie GmbH (Hanover) reconfigured the SPS to meet today's demands and standards and developed it further. This creative adaptation was

managed in cooperation with major research centres and by employing extensive test series. Following initial prototypes, a remediation and refurbishment project has now been successfully implemented on the operational Saar River Bridge at Mettlach, Germany. Under running traffic conditions, the concrete deck was significantly lightened using SPS. This allowed the existing stays to be retained without reinforcement and thus the traffic load capacity to be substantially increased (upgrading). The intelligent installation concept should be emphasised. As a pilot scheme, the awarded structure is of strategic relevance to the maintenance and refurbishment of operational bridges.

Remit

Remediation of the Mettlach suspension bridge became necessary because the concrete deck was displaying serious damage and fractures were identified on one of the stays. The bridge needed to be lightened in order to increase the capacity of the stays and allow upgrading from bridge loading classification BKL 30/30 to 60/30. The remediation measures comprised two construction stages. During the first stage the concrete deck is replaced by the

innovative SPS (steel-elastomer-steel composite plate). This measure allowed the deck weight to be reduced from 500 t to 200 t. During the second construction stage the footpaths and corrosion protection were renewed. Cracks in the primary structure were identified at this stage. The main girder flanges and web connections therefore needed to be successively replaced by new assemblies. The cross girders were refurbished by means of bolted reinforcing assemblies.

Description of the main bearing structure The Mettlach bridge is a two-lane suspension bridge with a span of 108 m and footpaths attached on both sides. The primary bearing structure consists of two stays with 12 suspender ropes each, two main girders and 51 cross girders. The original main bearing structure was divided into 12 segments with riveted connecting joints. The existing reinforced concrete composite system carriageway was replaced by 104 steel-elastomer-steel composite system (SPS) deck panels. The downstream footpath was widened by 1.5 m and now also includes a cycle path.

Ulrich Finsterwalder Ingenieurbaupreis 2015

Page 93: Project Portfolio Web Version June 10 2015

Awards

Key to the figure Bestandstragwerk = Existing bearing structure Neukonstruktion SPS-Fahrbahn/Gehweg = Reconfigured SPS carriageway/footpath Instandsetzung und Ertüchtigung Tragwerk = Repaired and refurbished bearing structure

Design The SPS carriageway, newly designed for the first construction stage, consists of 104 panels. They are bolted to the existing cross girders using a supporting framework, which is designed as an elastic rod joint. The innovative SPS construction method was licensed for use in Mettlach by an individual case approval process. In order to repair the main bearing structure a stiffer welded structure, comprising 60 mm flanges with 20 mm web plate stubs, was integrated in the existing structure of main girders consisting of a combination of rolled sections and plates. To achieve this, approximately 50 t of old, S235 structure was replaced by 120 t of new, S355J2 structure. In addition, the cross girders and cantilever brackets were refurbished using additional web reinforcements and bracket clamps to relieve the load on the structure and as corner bracing. Material selection

The 24 cm thick reinforced concrete composite carriageway slab was replaced by the sandwich plate system (SPS), a mere 4.5 cm thick, in a combination of steel panels with an elastomer core. A double layer of melted asphalt was applied to form the bridge surface. The footpaths are executed as pure steel structures with thin reactive resin surfaces. All reinforcing and new structures consist of S355J2 steel. Special engineering achievement To facilitate remediation of the bearing structure an installation concept was developed in which the elements of the main bearing structure, consisting of the supporting carriageway and the main girder flanges, were removed piece by piece, temporarily replaced and subsequently exchanged for a new construction. The entire measure was implemented under running traffic conditions. The adopted solutions, developed at short notice, needed to be suitable for the specific bearing response of the Mettlach

suspension bridge in terms of stresses and form compatibility. Despite the very limited accessibility it was possible to integrate the additional and complex remediation of the bearing structure in the footpath and corrosion protection renewal works. What positive effects does the special engineering achievement have? Using the adopted innovative carriageway design and installation technology it was possible to reduce disturbances to the regionally important transport route to a minimum. Successful remediation has reduced the weight of the carriageway from 500 t to 200 t. As a result of this the bridge loading classification was increased to BKL 60/30, thus eliminating the previous heavy traffic restriction. Remediation of the Saar River Bridge at Mettlach is a good example of sustainable construction. It was possible to upgrade the listed structure to meet today's traffic requirements.

Ulrich Finsterwalder Ingenieurbaupreis 2015

Page 94: Project Portfolio Web Version June 10 2015

Transforming the Fan Experience A New Arena for the Yellow Jackets By john M Hann, P.E., LEED AP

KSi/Structural Engineers was an Award Winner for the McCamish Pavilion project in the 2013 NCSEA Annual Excellence in Structural Engineering awards program {Category - Forensic/Renovation/Retrofit/Rehabilitation Structures).

The McCamish Pavilion is the industry. The SPS system includes home of the Georgia Tech Yellow two \4-inch steel plates at the Jacket basketball program and has top and bottom of the assembly been a part of the Georgia Tech infilled with a polymer resin layer

Community since 1956. The original facility on the order of I-inch thick. The included a 50-foot tall, 270-foot diameter, McCamish Pavilion installation is 32 rib structural steel Schwedler dome over a the first onshore ~ of the SPS mat ri · 25 foot deep, cast-in-place, circular concrete the western ~~tll,'here. seco,!!.dacy, roof members were modified to bowl. Several renovations and additions have The SPS system.-cannot b\ field cut 011 resist increased tension loads, converting the been performed over the life of the facility. welded; it has to fit perfecdy\ he first tim secondary members into tension rings. In Georgia Tech's goal for this renovation was Innov.ativw oint cloud technol,~ was used ~ review of the existing documentation, it simply to improve the fan experience in the in th desi~n, fabri ation and installatio!},-0£ ~ me evident the existing facility had no arena. Desired improvements included ber, the upger de k structm_al steel:ffn ~S~ A\ discrete lateral load resisting system. To bring sight lines, increased seating row dep1h fro · ree di~ ensional map of the u · r deck the existing structure into compliance with front to back, a circulation concow-se open as devel opecI by~·ns rt~ l er scanned the current building code, a new lateral load to the court, modern ucho visual equip- e010:t clou~ ~ of , ~ sting steel into resisting system within the existing dome

:e7:;~:!ni~:;;~t:~ st::~: ;e~ =~J~.~l fr~: ~;r:c:r~cts~:~ ~:::~::::: :~~i::!·~~~:::s~:~;:~~ circulation concourse and ~ liance with an<l\sPS components were fabricated from the least intrusive applicable system. The new current building codes. this model. The method was so precise that frames were "woven" through existing steel, To improve sight lines and address seating all pieces fit without shimming, trimming or changing the planar angle of the brace at each

row depth issues, a new octagonal seating other modification upon installation. level to reduce impacts to seating counts and bowl design was developed. The original The raker beams supporting the SPS are sight lines. bowl was demolished and a new cast-in-place attached to the existing Schwedler dome for To limit lateral bracing locations, supporting concrete bowl installed at grade. The new lateral stability, and balanced on curved struts the need for unobstructed site lines, all lateral octagonal bowl design eliminated approxi- to limit the gravity load introduced to the loads were transferred from the new circula­mately 2,000 seats. To replace these lost seats, existing framing. New foundation systems tion concourse to the dome bracing through a new upper deck was installed within the to support the struts were also challenging. the use of roof diaphragms and collector ele­existing Schwedler dome. The upper deck uti- The location of the facility over an abandoned men ts. Conversely, the amount of gravity load lizes elevated flooring supported on structural landfill, and thrust loads from the new upper the new concourse framing transferred to the steel raker beams which are in turn supported deck, required the use of battered deep foun- existing structure had to be limited to avoid on curved structural steel struts. dations. These deep foundations were installed overstressed conditions in the existing dome Traditional materials for elevated arena seat- from the sloped side of the existing bowl ribs. The layout of the concourse framing was

ing floors include precast concrete and folded underneath the existing steel ribs, resulting developed to achieve these goals. steel plate, but neither of these materials was in a low headroom condition on a working The look and feel of the arena was completely optimal due to the capacity of the existing platform sloped at 30 degrees. Because of the changed by the renovation, transforming an structure. The precast concrete option was installation conditions, steel pipe micro piles aging facility from the 1950s into a twenty­simply too heavy and overstressed the existing were utilized for this application. first century arena. The renovation would steel dome ribs. The layout of the upper deck The addition of the other fan amenities not have been possible without the inno­made it desirable to span the upper deck riser also posed structural challenges for the proj- vative structural materials, assemblies, and system from existing rib to existing rib, on ect. The audio visual, lighting, and HVAC construction techniques developed by the the order of25 feet. Folded steel plate could components all added significant load to project team.• not span this far without the addition of sig- the Schwedler dome. A three dimensional nificant secondary framing. A new material, analytical model of the facility was devel­the Sandwich Plate System, SPS, was inves- oped to study the effects of added loads tigated and selected for the flooring system. from new audio, visual, lighting and HVAC This composite flooring system was originally components. The added load significantly developed for the offshore and shipbuilding overstressed the existing building ribs. To

STRUCTURE magazine • Jonuory 2014

John ,\1. H,111n. PE.. LEED AP. i, a

Princip,,! at KSi!Stmctum! Enginl'l'r., in Atf1111t,1, GA. John m11 he l't'ached ,It [email protected].

Page 95: Project Portfolio Web Version June 10 2015

11 Stahlbau

– Beulverhalten längsausgesteifter Platten – skywalk allgäu – Baumwipfelpfad– Heißbemessung ungeschützter Stahlprofile – Erforderliche Einspanntiefen von I-förmigen Stahlquerschnitten – Tragwerksertüchtigung am Beispiel einer Verbundbrücke – Ermüdungssicherheit von Brücken (Teil 2)– Untersuchungen zu nichtrostenden Stahllegierungen – Tragfähigkeit von Kehlnahtverbindungen höherfester Baustähle– Weihnachtspreisaufgabe 2012

81. JahrgangNovember 2012ISSN 0038-9145A 6449

Page 96: Project Portfolio Web Version June 10 2015

1Bautechnik 81 (2004), Heft 1

Inhalt

Stahlbau11

Editorial

819 Jan Vette, Matthias Kraus Prof. Dr.-Ing. Rolf Kindmann wird 65!

Fachthemen

820 Ulrike Kuhlmann, Darko Beg, Antonio Zizza, Franc Sinur Beulverhalten längsausgesteifter Platten unter Inter aktion von Biegung und Querkraft – Experimentelle und numerische Untersuchungen

828 Jörg Frickel skywalk allgäu – Baumwipfelpfad

833 Marco Bergmann, Gerhard Hanswille Näherungsverfahren für die Brandbemessung von Hohlprofilverbundstützen

840 Manuel Krahwinkel, Tobias Petersen, Christian Gehmert Bemessungshilfen für die Heißbemessung ungeschützter Stahlprofile auf Basis des

Eurocode 3 Teil 1-2

850 Jörg Laumann, Stefan Mainz Direkte Ermittlung der erforderlichen Einspanntiefe von I-förmigen

Stahlquerschnitten in Betonkonstruktionen

861 Matthias Kraus, Jan Vette, Hans Joachim Niebuhr, Michael Jostmann Tragwerksertüchtigung am Beispiel einer Verbundbrücke

868 Max Bosshard, Pirmin Steck, Christian Meyer, Eugen Brühwiler, Marcel Tschumi, Senta Haldimann Ermüdungssicherheit von Brücken – Teil 2: Nachweis basierend auf den Messwerten

des Monitoring-Projekts „Bahnbrücke Eglisau“

875 Andreas Burkert, Jens Lehmann, Annette Burkert, Jürgen Mietz, Paul Gümpel Technische und wirtschaftliche Alternativen zu den klassischen nichtrostenden,

austenitischen Stählen unter atmosphärischen Einsatzbedingungen

889 Christina Rasche, Ulrike Kuhlmann Zur Bestimmung der Tragfähigkeit von Kehlnahtverbindungen höherfester Baustähle

Rubriken

827 Aktuell (s. a. S. 860, 888, 901)849 Weihnachtspreisaufgabe898 Persönliches903 Rezensionen904 Termine Stellenmarkt

Produkte & Objekte

A4 aktuell

Die Saarbrücke in Mettlach war in den 1950er Jahren ein Pionierprojekt für leichte Brückenarchitektur – mit einer der ersten Fahrbahntafeln in Stahl-Verbundbauweise. Nachdem der Beton nun große Schäden aufweist und die Tragkabel an Tragfähigkeit verloren haben, kommt eine neue Innovation für das erhaltenswerte Bauwerk zum Einsatz: das Sandwich-Plate-System (SPS) als neue Stahlleichtfahrbahn.Eiffel Deutschland Stahltechnologie (EDS) hat seit 2003 gemeinsam mit der kanadi-schen Intelligent Engineering und mit Unterstützung der RWTH Aachen eine Reihe von Konstruktionsdetails in SPS-Bauweise für Brückenkonstruktionen auf Basis der aktuellen Eurocodes entwickelt und baut jetzt die dritte Anwendung für eine SPS-Straßenbrücke in Deutschland. (Foto: EDS; siehe Bericht Seite A 4)

81. JahrgangNovember 2012, Heft 11ISSN 0038-9145 (print)ISSN 1437-1049 (online)

Wilhelm Ernst & SohnVerlag für Architektur und technische Wissenschaften GmbH & Co. KGwww.ernst-und-sohn.de

Aus Wiley InterScience wird Wiley Online Library

www.wileyonlinelibrary.com, die Plattformfür das Stahlbau Online-Abonnement

Peer-reviewed journalStahlbau ist ab Jahrgang 2007 bei Thomson Reuters ISI Web of Scienceakkreditiert

Impact-Faktor 2011: 0,252

Page 97: Project Portfolio Web Version June 10 2015
Page 98: Project Portfolio Web Version June 10 2015

MODERN STEEL CONSTRUCTION

IN THIS ISSUE

The Legal Side of Green

AISC’s Steel Solutions Center Turns 10

Steel Centurion: The Eads Bridge

Three-Part Perfection

MSC March 2011

Page 99: Project Portfolio Web Version June 10 2015

40 MODERN STEEL CONSTRUCTION MARCH 2011

C

Lightweight composite steel plate and elastomer deck shaves months off project schedule and millions off budget.

CITY OFFICIALS RECENTLY were able to both save a his-toric Edmonton bridge and avoid massive structural repairs and upgrades by opting for a lightweight steel deck system over-laid with asphalt instead of the traditional concrete replacement deck. The system uses composite panels consisting of steel plates with a solid elastomeric core. Although the material has been used in shipbuilding for years, its use in bridge construc-tion is relatively new. In addition to providing an effective and economical solution, using this steel deck system also cut con-struction time signifi cantly.

Bridge HistoryThe North Saskatchewan River winds its way from the Rocky

Mountains, across Alberta, and through the heart of Edmonton on its way toward Lake Winnipeg. Its shores have been popu-lated at Edmonton by aboriginal peoples for millennia, with the fi rst European infl uence appearing in the late 18th century. During World War II, Edmonton acted as a staging area for construction of the Alaska Highway, and today is the capital of Alberta with a regional population of over one million.

Historic Dawson Bridge has been a vital link for the people of Edmonton for generations, entering its 100th year of service in 2011. Originally known as the East End Bridge, it is a fi ve-span riveted steel through-truss with a clear width of 26 ft, 8 in.

and a total length of 776 ft: three spans of 142 ft, a navigation span of 250 ft, and an east approach span of 100 ft.

Originally constructed to carry horse-drawn wagons and electric trains to the Dawson Coal Company mine located on the east bank, the bridge opened on October 8, 1912 with a construction cost of $145,000. Only the second bridge to cross the North Saskatchewan River at Edmonton, Dawson Bridge quickly became a vital link for the city’s growth, allowing coal to be transported quickly into the heart of the city for industry and home heating.

After closure of the Dawson Mine in 1944, the bridge was converted to carry only highway vehicles. Today, the bridge has one lane of traffi c in each direction and accommodates about 17,000 vehicles each weekday. As a link to Edmonton’s extensive multi-use river valley trail system, the two sidewalks on Dawson Bridge serve many pedestrians and cyclists.

Condition AssessmentIn 2007 the city of Edmonton commissioned Dialog to con-

duct a condition assessment for Dawson Bridge. Field inspec-tion revealed the nearly 100-year-old superstructure in need of signifi cant repair, including total replacement of the bridge deck and complete recoating of all steelwork. Structural analysis also identifi ed numerous truss members requiring strengthening or

BY JEFF DIBATTISTA, P.ENG., PH.D., KRIS LIMA, P.ENG., AND SHIRAZ KANJI, P.ENG.

The Dawson Bridge’sQuick Rehab

Photos: Dialog

Page 100: Project Portfolio Web Version June 10 2015

MARCH 2011 MODERN STEEL CONSTRUCTION 41

replacement in order to increase the service life of the bridge and meet the target reliability indices of the Canadian Highway Bridge Design Code 2006. In addition, the original narrow side-walks—only 5 ft wide—caused safety problems due to mixed use by pedestrians and cyclists.

Especially problematic was the existing 6½ -in. steel-fi ber reinforced semi-lightweight concrete deck, cast in 1986 on top of old timber subdecking from the 1940s. Though its relative light weight was benefi cial for limiting dead loads, the thin concrete deck was too fl exible to resist cracking. In particular, the city had continual maintenance problems with the methyl

Jeff DiBattista, P.Eng., Ph.D., is a principal and Kris Lima, P.Eng., is an associate with Dialog, an integrated design fi rm specializ-ing in engineering and architecture. Shiraz Kanji, P.Eng., is chief bridge engineer for the City of Edmonton.

General plan from 1913 of the East End Bridge, now known as the Dawson Bridge, in Edmonton, Alberta, Canada.

With an overall length of 776 ft, the Dawson Bridge consists of fi ve simply supported trusses that cross the North Saskatch-ewan River on the east side of Edmonton.

The Dawson Bridge rehabilitation included upgrading critical con-nections by replacing the original rivets with high-strength bolts.

A hydraulic jacking system was used to relieve the load on truss members in need of strengthening or replacement as the work was performed.

methacrylate membrane wearing surface at details where the concrete deck passed over the transverse fl oor beams. The con-crete deck section was reduced to only 2½ in. thick to clear the top fl ange of the fl oor beams, making it nearly impossible to control cracking.

As part of the assessment, a load rating of Dawson Bridge was conducted using a 4-axle, 63.5 ton Alberta CS3 rating vehi-cle, the largest vehicle that might practically access the bridge considering its vertical clearance restrictions and location. That assessment concluded that numerous truss members required strengthening or replacement to meet the required level of safety and to extend the life of the bridge.

As options for rehabilitation were developed, it became clear that the bridge could be rehabilitated economically only if a lightweight deck replaced the existing deteriorated deck. A traditional concrete deck would require costly replacement or strengthening of many truss members along with diffi cult

City of Edmonton

Page 101: Project Portfolio Web Version June 10 2015

42 MODERN STEEL CONSTRUCTION MARCH 2011

upgrading of existing connections. Additionally, it might over-load the piers, abutments, and foundations. The design team concluded that replacing the existing semi-lightweight concrete deck with a lightweight steel deck would allow the dead load savings to be applied to carrying additional live load and wid-ening the sidewalks. Only steel offered viable lightweight deck options: grating, orthotropic deck, or an innovative composite steel plate and elastomer system called the Sandwich Plate Sys-tem (SPS) developed by Intelligent Engineering (Canada) Ltd.

Grating was quickly eliminated as an option for the deck because increased road noise would be detrimental to the nearby Riverdale community. Orthotropic steel deck was judged a suit-able option, but detailing would be challenging where the deck had to clear the tops of the floor beams without raising the grade line. There also were concerns about its susceptibility to fatigue cracking. After considerable research, the design team recommended the patented SPS solution, judging that SPS technology offered the best combination of light weight, thin profile, and ease of erection for the Dawson Bridge Rehabilita-tion project.

Innovation and Risk ControlThe SPS composite steel plate and elastomer system was

originally developed by UK-based firm Intelligent Engineering Ltd. for ship hulls and decks in the marine industry. Application of this technology in the bridge industry began about a decade ago. After its use on several bridges around the world, SPS tech-nology is gradually gaining acceptance by bridge engineers.

SPS makes use of two relatively thin steel face plates con-nected by an injected thermosetting elastomer core. The final product is a composite panel with high stiffness and strength, but relatively low weight.

Deck panels are fabricated in the shop using conventional steel fabrication techniques. First, solid “perimeter bars” are welded along each edge of the bottom plate using a continuous fillet weld. The top plate is then lowered onto the perimeter

bars and fillet welded all around forming a panel with a sealed void. The liquid elastomer, which cures into solid form within an hour, is injected through a port to form the core. For Daw-son Bridge, the 3⁄8-in. steel face plates sandwich a 1-in. elasto-mer core, forming a composite deck panel with a total thickness of only 1¾ in. These prefabricated panels are typically 6 ft, 1 in. wide and 28 ft long.

Risk is inherent in the application of all new technologies in all industries. Perceived risk and its associated liability often dissuade engineers from trying innovations that might advance the state of the art in their area of practice. Potential liabil-ity places a constriction on the pace of innovation that, in the long run, is most often a disservice to society. Striking the right balance between innovation and risk control is the key to suc-cess. Thus, when Dialog recommended SPS—a relatively new technology—to the City of Edmonton, that recommendation came with the proviso that an intensive risk control program must be implemented, especially because Dawson Bridge is an important and expensive asset. As a progressive bridge owner, the city welcomed that innovation and directed the design team to proceed with SPS as the basis of design for the deck.

The risk control plan developed for the deck comprised six key elements:

Extensive background research in the available literature;Site visits by the design team to other bridges with SPS

decks, and interviews with the bridge authority managing those structures;Development of improved connection details in consulta-tion with Intelligent Engineering;Fatigue testing of full-scale sample connections in the

laboratory;Enhanced quality control and quality assurance programs during deck fabrication and erection; and,Monitoring of deck performance over the lifetime of the bridge as part of the Edmonton’s bridge maintenance program.

Dialog judged the most important aspect of the risk control

The old, deteriorated concrete deck was sawcut and removed in March 2010.

Top left and inset: All members were blast cleaned in preparation for applying a three-part zinc/epoxy/urethane coating system, providing protection well into the bridge’s next century of service.

Fabrication of the SPS components, which consist of two 3∕8-in. steel plates connected with perimeter bars and con-tinuous fillet welds then filled with a liq-uid elastomer that quickly solidifies.

Page 102: Project Portfolio Web Version June 10 2015

MARCH 2011 MODERN STEEL CONSTRUCTION 43

plan to be the development of new connection details between adjacent SPS deck panels. Of the handful of bridges around the world built using SPS technology, all have involved significant field welding—a method that is costly and makes quality control difficult. Risks associated with field welding include fit-up out-of-tolerance, the potential for excessive heat input that might debond the elastomer from the steel, and undesirable weld flaws that might inadvertently result in premature fatigue cracking.

Taking to heart the golden rule “shop weld and field bolt,” the Dialog design team developed unique bolted details for connecting the SPS deck panels that completely eliminate the need for field welding. Bolted connections drastically increase speed of erection, significantly reduce cost, and improve fatigue performance from Detail Category D (depending on the spe-cifics of the weld geometry) to Detail Category B when using slip-critical connections.

To connect adjacent SPS deck panels, a top splice plate is fastened by a single row of countersunk pretensioned ¾-in. ASTM A325 bolts. Countersunk bolts provide a flat surface for the finished deck, except for the thickness of the splice plate itself. This surface, once grit blasted, is prepared to receive a waterproof membrane and asphalt.

Longitudinal deck splices are designed to align with floor stringers below. This arrangement enables the top flange of the stringers to act as the bottom splice plate for the connection, saving both weight and complexity. The new stringers chosen—W18×50—are larger than required for flexural strength but offer a flange wide enough to accept a row of bolts on each side of the web. At transverse deck joints, located away from floor beams to avoid clashes, bolted splice plates are used both top and bottom. In all cases enough bolts are used so that sealing requirements are met and negative moments in the deck can be transferred across the supporting stringers. This very simple approach to connections makes the deck very easy to fabricate and simple to erect. Using similar bolting details, the traffic barriers along the length of the bridge are also bolted down through the deck to the edge stringer.

Also as part of the risk control plan, three small 1:1-scale samples of the longitudinal bolted deck connection detail were built and tested under fatigue loading at the University of Alberta with the assistance of professor Gilbert Grondin, P.Eng., Ph.D. Those tests demonstrated that the new connec-tion detail can withstand fatigue loads nearly double in magni-tude to those expected in actual in-service conditions.

Reaping the Benefits of InnovationBecause the composite steel deck panels could be fabricated

entirely in the shop and bolted quickly into position on the bridge, erection of the deck was completed in only six weeks during July and August 2010. This speed allowed the $17 mil-lion rehabilitation to be finished in only 12 months: the bridge closed to traffic on January 4, 2010, and reopened on December 20, 2010. A traditional concrete deck would have extended the project schedule to at least 18 months, added millions of dollars of extra truss strengthening work, and caused numerous other technical issues.

The Dawson Bridge project has successfully advanced the state of the art in bridge technology and has achieved cost sav-ings for the City of Edmonton, while allowing the rehabilita-tion work to be completed within a single construction season. Today, Dawson Bridge is fully rehabilitated with the world’s largest SPS deck—the only installation built entirely without field welding—and it stands prepared to serve Edmontonians for many generations to come.

OwnerCity of Edmonton, Alberta, Canada

Structural EngineerDialog, Edmonton, Alberta, Canada

Steel DetailingEmpire Iron Works Ltd., Edmonton, Alberta, Canada (NISD Member)

General ContractorConCreate USL Ltd., Crossfield, Alberta, Canada

Laboratory sample of a typical steel plate and elasto-mer connection detail for the Sandwich Plate System.

SPS deck construction sequence: A) Steel deck in place; B) The surface is grit blasted; C) The steel is covered with a waterproof membrane; D) The asphalt wearing course is placed.

Deck connection detail, showing A325 bolts coun-tersunk into the top connection plate while the beam flange serves as the lower connection plate.

Placement of one of the SPS 6 ft by 28 ft deck pieces on the Dawson Bridge in August 2010.

Page 103: Project Portfolio Web Version June 10 2015
Page 104: Project Portfolio Web Version June 10 2015
Page 105: Project Portfolio Web Version June 10 2015
Page 106: Project Portfolio Web Version June 10 2015
Page 107: Project Portfolio Web Version June 10 2015
Page 108: Project Portfolio Web Version June 10 2015
Page 109: Project Portfolio Web Version June 10 2015
Page 110: Project Portfolio Web Version June 10 2015
Page 111: Project Portfolio Web Version June 10 2015

PUR Customer Magazine . Edi t ion 2.2011 . No. 21G

lobal

Perfection in every detail. Polyurethane in Scania trucks.

100 years of BASF in Brazil. A South American success story.

Magnificent mannequins. Display dummies made of polyurethane.

A smooth ride all over the world.50 years of Cellasto in cars.

PUR_02_2011_EN_02.indd 1 05.10.11 10:50

Page 112: Project Portfolio Web Version June 10 2015

32

Edmonton, capital of the Canadian province of Alberta, has a population of over a million. The historic Dawson Bridge today carries an import-ant traffic artery that was so important for the city’s industrial growth in the last century. Built in

1912 and initially used for the transportation of coal, the two-lane bridge today handles some 17,000 vehicles per day.

In 2007, a detailed structural examination commissioned by the city revealed that the entire almost century-old deck had to be replaced along with some of the members of the steel trusses. The steel structure was in need of repainting, and the very narrow sidewalks were a source of safety prob lems as well.

ConstructionSandwich Plate System (SPS)

Clearing the deck.

With an impressive SPS deck rehabilitation project, the City of Edmonton in Canada restored its historic Dawson Bridge to its former glory.

Dawson Bridge project has won the CISC Steel Design

Award 2011.

PUR_02_2011_EN_02.indd 32 05.10.11 10:54

Page 113: Project Portfolio Web Version June 10 2015

33

Making light work of a burdensome problem.

After an examination of all options, it soon became clear that the best rehabilitation approach was to limit the bridge’s dead load with a lightweight deck – a traditional concrete deck would have been too costly and too heavy for the aging existing steel structure. The design team therefore recom-mended an entirely new, lightweight sol ution, the Sandwich Plate System (SPS) from Intelligent Engineering Ltd. This re- presented the best possible combination of weight savings, a thin profile and simple and above all swift execution of the job. As this is a pretty new technology, the city was also recommended an extensive risk control package, which SPS effortlessly satisfied on all counts.

New lease on life for an old bridge – achieved with 70 percent less weight than with reinforced concrete.

Originally developed for the marine industry, SPS technol-ogy is now also finding applications in the construction of bridges and of stands in stadiums. 776 ft long and 26.8 ft wide, the Dawson Bridge is so far the first major bridge project to have made use of SPS technology. No less remarkable is that it does entirely without welding.

SPS itself consists of two steel face plates sandwiching a core of polyurethane. The finished product is a composite panel of high rigidity and strength. Thanks to the elastomer core, the PU system Elastocore ®, SPS also absorbs vibra-tion and displays high tolerance to jolts and impacts. SPS panels weigh up to 70 percent less than reinforced con-crete while being at least as strong and more durable in addition. Consequently, today’s bridges with SPS panels may yet be used by our grandchildren.

Faster construction, less stress and lower costs – SPS is the best solution in every respect.

SPS panels can be prefabricated off-site and are then bolted together on the bridge. The overall rehabilitation of this bridge was accomplished at high speed – without time-consuming welding and without annoying, long-term closures to traffic.

The bridge deck was replaced in just six weeks, in July and August 2010. The entire project was com-pleted in only 12 months from January to December 2010. A trad-itional bridge repair would have taken at least 18 months and have been much more expensive be-cause of the additional steel mem-

ber replacements. Michael Kennedy, CEO of Intelligent Engin eering, was delighted that the project has won the CISC Award for excellence in steel structures: “To have success fully completed this project in the city where the three founders of IE went to college and where SPS was initially developed makes it a special achieve-ment.”

Further information: www.ie-sps.com

Workers fit an SPS panel on the Dawson Bridge in summer 2010. SPS has now been used in 180 projects on six continents.

Pho

to: S

mac

kaay

( Wik

iped

ia)

Michael Kennedy, e-mail: [email protected]

Call our number: Gunther Lukat,

Technical Sales Elastomers,

Germany, +49 5443 12 4190

or send an e-mail to:

[email protected]

PUR_02_2011_EN_02.indd 33 05.10.11 10:54

Page 114: Project Portfolio Web Version June 10 2015
Page 115: Project Portfolio Web Version June 10 2015
Page 116: Project Portfolio Web Version June 10 2015
Page 117: Project Portfolio Web Version June 10 2015
Page 118: Project Portfolio Web Version June 10 2015
Page 119: Project Portfolio Web Version June 10 2015
Page 120: Project Portfolio Web Version June 10 2015
Page 121: Project Portfolio Web Version June 10 2015

intelligent engineering company profile

Page 122: Project Portfolio Web Version June 10 2015

SPS Overlay being applied to the tank top (bottom of cargo hold) on a bulk carrier

Page 123: Project Portfolio Web Version June 10 2015

1

on the threshold of a new era

We established Intelligent Engineering more than 10 years ago to develop and commercialise what we call SPS. Others have called SPS “the first new materials technology for heavy engineering in150 years” and described it as “bringing the maritime and civil engineering industries to the thresholdof a new era”.

In the decade since, we have spent more than 500 professional man-years and more than $100mconducting thousands of tests, proving and re-proving every aspect of the performance, economics,safety and sustainability of SPS. Together with our partners at BASF, the world’s largest chemicalcompany, we have developed 84 different groups of patents. We have built up a team of more than60 professionals working out of offices in Europe, North America and Asia, supported by an AdvisoryBoard of leading experts and businessmen.

We have completed more than 440 projects and have more than 280,000m2 of our product inservice. We have secured the approval of key regulatory authorities around the world and we havedemonstrated, by example, that SPS makes maritime and civil engineering structures, such as ships,offshore platforms, bridges and buildings, stronger, lighter, faster to build, longer lasting, safer, moreenvironmentally friendly and less expensive. What next?

In the decade to come, we will roll out SPS through a series of strategic partnerships, such as ourjoint venture with DSME, the world’s second largest shipbuilder. We will provide new applications, suchas blast and ballistics protection for those young men who may still be in harm’s way. We will provideeconomic and sustainable solutions in new markets, such as India and China. We will continue toinvest and to advance the frontiers of SPS.

When you take your son to a football match or your daughter takes you to a rock concert or whenyou take a lift in a tall building or a bridge or a ship across a river or an ocean, SPS will be there.

Michael KennedyChairman, Intelligent Engineering.

Page 124: Project Portfolio Web Version June 10 2015

summary

Intelligent Engineering (IE) has developed and commercialised SPS.

> SPS offers substantial performance, economics, safety and sustainability advantages over steel and concrete for two major world markets: maritime and civil construction

> The technical capabilities of SPS have been proven by an extensive programme of tests conducted over the last ten years by IE in partnership with BASF and leading research institutions under the guidance of major regulatory bodies

> SPS is approved by the main maritime regulators and similar approvals have been granted for civil engineering applications in North America and the EU

> IE has completed over 440 commercial SPS projects across six continents. There are more than 280,000m² of SPS in demanding applications around the world

> SPS is protected by a portfolio of 84 different groups of patents filed in 80 jurisdictions which is jointly defended by IE, its partners and licensees

> IE works with leading architects, engineers and builders to design and integrate SPS solutions into construction programmes. SPS designs and prefabricated SPS products are available through a growing network of licensees

2

SPS Overlay showing placement of new top plate

The Norcape was the 20th SPS Overlay project for P&O

Page 125: Project Portfolio Web Version June 10 2015

what is SPS?

SPS is a structural composite comprising two metal plates bonded with a polyurethane elastomer core.

SPS is much simpler and more robust than stiffened steel plate and much lighter and faster to erect than reinforced concrete.

SPS is used in a wide variety of applications including structural flooring, stadia and arena terraces, ship repair, shipbuilding and bridges.

3

Conventional Concrete and Steel Structure

SPS Structure

Conventional Stiffened Steel

Page 126: Project Portfolio Web Version June 10 2015

benefits of SPS

4

Maritime applications

In maritime structures, such as the hulls and bulkheads of ships,load-bearing plates are usually made from steel, which is heavilystiffened to prevent buckling. SPS eliminates the stiffeningelements, making these structures much less complicated andmuch less prone to fatigue and corrosion.

Civil applications

In civil engineering structures, such as the decks of bridges andfloors in buildings, load-bearing plates are usually made fromreinforced concrete. This is because it is difficult to control fatigueand vibration using steel and, with the exception of long-spanbridges, the weight penalty of using concrete is tolerated. SPScontrols fatigue and vibration and is much lighter than concrete.In addition, SPS plates are prefabricated to a high degree ofdimensional accuracy. Using SPS plates reduces ‘wet-work’ onsite and de-risks and accelerates the build programme.

Repair and conversion

SPS can also be used to reinstate or strengthen existing platestructures, such as the cargo holds of ships and the decks ofbridges, in a process called SPS Overlay. Here again, the benefitsare a much reduced schedule and a very robust and longlasting solution. Across the full range of applications, thecomposite properties of SPS give rise to a number of othervaluable benefits. In summary, SPS offers:

Simpler, faster fabrication

> Elimination of stiffeners simplifies structures

> Prefabrication and ease of erection shortens and de-risks construction schedules

> Eliminating ‘cropping’ makes SPS Overlay a much faster and less risky method of reinstatement and strengthening

Improved designs and in-service performance

> Less susceptible to fatigue and corrosion, local buckling and the formation and propagation of cracks, compared to conventional stiffened steel structures

> Reduces weight and thickness and allows increased spans compared to conventional reinforced concrete structures

Cost savings and economic benefits

> Reduces build cost

> Reduces construction schedule and risk

> Reduces maintenance cost

> Increases service life

> Increases cargo capacity

> Increases rentable floor area

Enhanced protection and safety

> Greater resistance to accidental or extreme impact loads

> Built-in structural fire protection

> Built-in blast and ballistics protection

> Built-in acoustic insulation

Improved environmental sustainability

> Fully recyclable and reusable gives reduced carbon footprint

> Reduced weight results in less materials, less waste and fewer truck loads

> Faster construction means less disruption and public inconvenienceLifting a pre-assembled triple unit of SPS Terraces

SPS is a structural material used to make the load-bearing plates found in a wide variety of maritime and civil structures. SPS offers benefits in performance, economics, sustainability and safety.

Page 127: Project Portfolio Web Version June 10 2015

5

markets

> New construction for full range of ship types including components such as: • Hatch covers • Vehicle decks • Tank tops • Bulkheads • Hull plating • Citadel protection

> Repair and conversion of: • Offshore vessels and structures • Bulk carriers and tankers • RoRos, ferries and passenger vessels • A wide variety of other applications

> Stadia and arena terraces • New venues • Reprofiling • Extensions

> Structural floors • High rise • Concourses • Low rise • Car parks

> Bridge decks including: • New bridges • Bridge replacement • Deck reinstatement

> Naval vessels with particular benefits for: • Blast belts • Flight decks

> Construction including: • Crash decks • Blast walls

> Industrial applications: • Transformer casings • Turbine enclosures • Heavy machinery

SPS Floors eliminate the need for concrete at height

The Silver Bell tank tops reinstated with SPS Overlay

Page 128: Project Portfolio Web Version June 10 2015

6

SPS Overlay

SPS Overlay has set a new standard for ship repair and conversion, delivering a faster, less disruptive alternative to traditional ‘crop and replace’ techniques.

SPS Overlay uses existing plating as one side of a steel composite panel formed by a new top plate and an elastomer core. The results fully restore or enhance the strength of the original structure to deliver high impact resistance and permanently flatter surfaces that improve performance and cargo handling.

The benefits of SPS Overlay include:

> Faster repair schedules, minimal labour and reduced downtime

> Non-disruptive, safe, permanent improvements

> Reduced repair costs, lower operating costs and increased revenue potential

Over 270 commercial SPS Overlay projects have been completed. These fall into four categories:

> Offshore vessels and structures including FPSOs and FSOs, drilling rigs, semi-submersibles, and LNGs

> Bulk carriers and tankers including Capesize and Panamax vessels

> RoRos, car carriers, freight and passenger ferries

> A wide variety of other vessels from barges, dredgers and floating pontoons to helidecks and side shell protection

Page 129: Project Portfolio Web Version June 10 2015

7

SPS Overlay has been used for extensive deck reinstatement of six Stena Line ferries.

The non-intrusive nature of SPS Overlay contributed to significant schedule savings and ensured the vessels were back in service quickly.

“The original programme of repairing 10,000m² of deck on three ships back to back in 70 days was the most demanding schedule that I have overseen as technical superintendent. The project would not have been possible with conventional repair techniques.”

Nigel Baalham, Technical Superintendent, Stena Line

>

Transocean Legend, Helideck StrengtheningC A S E S T U D Y

The helideck of the Transocean Legend needed strengthening to accommodate heavier helicopters. The SPS Overlay solution was completed in 17 days.

“We are delighted with the end result and the speed with which the strengthening took place.”

Guy Cantwell, Transocean

>

Stena Line, Deck ReinstatementC A S E S T U D Y

Illustrative cross section showing new top plate and elastomer core of SPS Overlay. In spite of diminution and ‘dishing’, the original deck plate can be retained to form the bottom plate of

the sandwich. New lashing pots are integrated during process.

Page 130: Project Portfolio Web Version June 10 2015

8

The Capesize Docebay had 1,932m² of tank tops, hopper sides and stools reinstated with SPS Overlay in Cosco Nantong, China.

The “dishing” of the tank tops has been eliminated, which will lead to better cargo handling and reduced turnaround times.

“Using SPS Overlay rather than conventional crop and replace methods reduced our repair schedule by 40%.”

Atle Paulsen, Superintendent, V.Ships

>

Docebay, Tank topsC A S E S T U D Y

Page 131: Project Portfolio Web Version June 10 2015

9

Wear and tear had resulted in steel diminution to the FPSO Conkouati’s side and bottom shell.

SPS Overlay was used to reinstate the structural strength of the hull. Areas of side shell, which are vulnerable to impact damage from offloading tankers, were strengthened externally, while the bottom shell was strengthened intercostally below the waterline without the need for dry docking.

“SPS Overlay was an obvious choice for us. The repairs were not intrusive and were carried out on-station whilst normal operations continued on board. The equipment used for the job was small and portable and meant that its movement did not cause major inconvenience or involve many people. The work was finished with excellent results.”

Klervi Keryhuel, Marine Engineer, Perenco

>

Conkouati, Side and Bottom Shell RepairC A S E S T U D Y

SPS Overlay was used as side impact protection in the conversion of an FPSO to satisfy IMO MEP139 (53) “Guidelines for the application of MARPOL Annex 1 Requirements for FPSOs and FSUs”. It is also Class and Flag State approved.

“Keppel Singapore, Intelligent Engineering’s licensee of SPS Overlay continues to provide innovative, proven solutions for FPSO customers. The adoption of SPS Overlay offers the ideal side shell protection for FPSOs and we are pleased to be instrumental in this first application.”

Louis Chow, General Manager Commercial

(Conversions) Keppel Shipyard Ltd

>

FPSO, Side Shell ProtectionC A S E S T U D Y

Page 132: Project Portfolio Web Version June 10 2015

10

IE and DSME (Daewoo Shipbuilding and Marine Engineering Co Ltd) have established a joint venture, SPS Marine Technologies Ltd, to bring SPS into mainstream shipbuilding. The company provides SPS solutions and licences the technology to other shipyards around the world. A wide variety of applications have been developed including hatch covers, vehicle decks, tank tops, bulkheads and hull plating.

Benefits include:

> Simplified more robust structures

> Up to 40% reduction in labour, 50% less welding and 20% less surface area

> Superior in-service performance and reduced through-life maintenance

> Prefabrication guarantees quality and efficiency in construction

“Lloyd’s Register was the first to approve SPS for ship repair and now that this is well established we’re delighted to be supporting IE and DSME in their joint venture to bring SPS into new ship construction.”

Richard Sadler CEO, Lloyd’s Register

SPS hatch cover at DSME shipyard

maritime new construction

Page 133: Project Portfolio Web Version June 10 2015

11

Through the MTL partnership, DSME constructs and supplies SPS hatch covers for containerships. The advanced design uses SPS panels to replace the stiffened steel plating of a conventional hatch cover, eliminating all secondary stiffeners and greatly simplifying the structure. SPS hatch covers are functionally identical to the standard steel items, but possess greatly enhanced strength and resistance to impact and puncture from dropped or mishandled containers.

Hatch covers are obvious applications for SPS, not just for containerships, but also for bulk carriers and general cargo vessels. The simplified structure and inherent puncture resistance reduce maintenance costs, enhance lifetime performance and minimise the risk of costly delays due to accidental damage.

>

SPS Hatch CoversC A S E S T U D Y

Rhine Tanker (Type C)C A S E S T U D Y

IE designed a Type C Tanker for the Rhine River to meet ADNR and Germanischer Lloyd requirements. A mock-up structure was built in Hanover, Germany. This verified the construction and assembly processes, confirmed the construction quality standards and demonstrated the simplicity resulting from the use of SPS.

>

MV “Bow Hunter” was one of the first vessels built by DSME. In 2011 DSME converted her into a floating company museum or “Storium”. DSME selected SPS panels for the newly installed decks to provide high performance control of noise and vibration and allow fast installation in confined working areas.

“In the conversion of MV Bow Hunter, SPS gives installation and performance benefits over a normal steel deck. The innovation contained in SPS technology captures the spirit of DSME and is symbolic of DSME’s past and future.”

ManSoo Kim, Vice President, Head of Hull Design, DSME

>

DSME “Storium”C A S E S T U D Y

Page 134: Project Portfolio Web Version June 10 2015

SPS Terraces

SPS Terraces save weight, time and cost in the construction of high quality stadia and arenas:

> SPS Terraces weigh less than 25% of concrete terraces. This enables a 25% reduction in structural frame weights and 15% lighter foundations

> SPS Terraces can be erected quickly, with 6-10 times more units being transported per truck and 3-4 times more units lifted per hoist than concrete alternatives

> Project cost savings of over 20% are achieved using SPS Terraces

> At the end of a venue’s life SPS Terraces can be readily demounted and reused on future venues

Integrated steel rises

High quality coated faces

Connected in factory, or on site, to create integrated bank

Safe non-slip surface

12

Page 135: Project Portfolio Web Version June 10 2015

Zaha Hadid’s Aquatics Centre for the London 2012 Olympics is the iconic structure of the games. SPS Terraces helped to deliver a uniquely demountable structure with the feel of a permanent venue with the opportunity for the whole structure to be resold after the games. A breakthrough in sustainable construction and a valuable legacy.

“If it was up to me, I’d choose SPS Terraces over prefab concrete slabs every time. We threw them up onto the steelwork much faster than I’d first imagined possible, and with a schedule as tight and important as the Aquatics Centre build, that makes all the difference.”

Steve Burley, Site Manager, Watson Steel Structures

>

The Aquatics CentreC A S E S T U D Y

13

SPS Terraces delivered a lightweight, long span, cantilevered bowl with minimal supporting columns – allowing more of the audience to be closer to the stage and maximizing the venue’s capacity and versatility.

“We designed the arena bowl with SPS Terraces in mind; nothing else could have delivered the solution we wanted.

I am delighted with the quality of finish we have achieved using SPS Terraces – they are the future.”

Damon Lavelle, Architect, Populous

>

Winner of BEX 2009 International Award for Best Use of Architectural or Structural Design

O2 DublinC A S E S T U D Y

LG ArenaC A S E S T U D Y

The LG Arena at The NEC, Birmingham has been redesigned, enlarged and completely refitted. SPS Terraces were used to create 8,000 permanent seats, of the total 16,000 capacity at the new venue.

“Using SPS Terraces helped to ensure that our new arena was ready for the start of our season, the Horse of the Year show, in October and has created more space for concessions and services under the new stands.”

Phil Mead, Managing Director of Arenas at The NEC Group

>

Page 136: Project Portfolio Web Version June 10 2015

SPS Floors

> SPS Floors weigh one quarter of comparable concrete flooring; they are supported by lighter frames and foundations

> They are delivered to site finished to the highest tolerances ready to be assembled using standard steel working practices

> Using SPS Floors reduces construction schedules. They are installed quickly and predictably with panels of SPS Floors being lifted at the same time as the structural frame

> They provide 100% working load capacity as soon as they are fixed in position and with no wet-work above ground level

work can start earlier and be completed faster

> SPS Floors reduce health and safety risks by providing increased protection against falling objects and minimizing a range of on site hazards

> Using SPS Floors reduces contractors’ costs associated with time on site and project risk

> They provide increased revenue for developers from earlier project completion and extra floors on tall buildings

SPS Floors enable significantly lighter structures with shorter, safer construction programmes.

A full-scale 9m x 9m bay, fitted out with M&E, suspended ceilings and raised access floors has been fully tested at the UK Building Research Establishment (BRE). Inset pictureshows Techniks ceramic raised floor system installed on SPS panels

14

Page 137: Project Portfolio Web Version June 10 2015

Residential BuildingC A S E S T U D Y

It is proposed to use SPS Floors on a 27 storey residential building in London.

“SPS panel system is the step change we have been waiting for in off-site construction. The system finally enables us to bring precision manufacturing and assembly to the site eliminating multiple trades to deliver the building faster and ultimately cheaper than conventional techniques.”

David Glover, Global Head of Building Engineering, AECOM

>

15

Weston-super-Mare Grand PierC A S E S T U D Y

SPS Floors have been used to rebuild the main structural floor of the Grand Pier in Weston-super-Mare. The pier, which was gutted by fire in 2008, was being rebuilt on the existing 105 year old structure and extends 400m into the Bristol Channel.

The picture on the right, taken at low tide, shows work in progress on the superstructure and the SPS deck about 75% complete. Note the crane barge alongside.

“SPS Floors were key to meeting the challenges of rebuilding on an old and damaged structure with limitations onweight, restricted access and a demanding schedule. Intelligent Engineering has gone the extra mile in supporting us from design to installation to ensure the success of the project.”

Andy McGoldrick, Project Director, John Sisk & Son Ltd

>

SPS Floors formed part of the improvements to Carnegie Hall, which is a 120 year old heritage structure and a New York City landmark. They were used for the renovation of a mezzanine floor in the South Tower and floor additions in the North Tower, which resulted in minimal disruption to the music hall, provision of immediate load capacity on installation and an easy installation in a site restricted area.

For the South Tower, the SPS Floor forms office space that is suspended at mid-height between top and bottom flanges of an existing truss. In the North Tower, the floors add lounge areas to existing rehearsal halls.

>

Carnegie HallC A S E S T U D Y

Page 138: Project Portfolio Web Version June 10 2015

SPS Bridge Decks

SPS Bridge Decks are much lighter and less complicated than conventional concrete and steel structures. New construction, replacement and repair can be carried out much faster and with less disruption. SPS Bridge Decks are less vulnerable to fatigue and corrosion and have a longer service life.

Installation of new SPS Bridge Deck

16

New bridge decks

Prefabricated SPS Bridge Deck panels make new bridges moreeconomic. As an alternative to concrete decks, the 70% lighter,prefabricated SPS Bridge Decks enable shallower, longer, lighterspans to be constructed faster and with less disruption to traffic.As an alternative to orthotropic steel decks SPS Bridge Decksoffer a lighter solution with simple surfaces that are much lessprone to fatigue and corrosion.

Replacement decks

The replacement of old concrete decks with SPS Bridge Deckscan take days rather than weeks and bridges can often remain

operational throughout the procedure. Load restrictions can be removed and extra lanes added without the need for additionalsubstructure.

Deck reinstatement

SPS Overlay is used to reinstate or strengthen steel bridge decks.This process does not require the removal of existing structureand is therefore much faster and less disruptive. SPS Overlayimproves the distribution of wheel loads, decreasing deflectionsand increasing the life of the bridge.

Page 139: Project Portfolio Web Version June 10 2015

17

Prefabricated SPS Bridge Deck panels were used to replace concrete panels in four pedestrian bridges across the M6 motorway in England. The installation process required the motorway to be closed for just a few hours overnight, keeping disruption to a minimum.

“The Highways Agency is always on the lookout for new ways to get the job done and SPS is one of them.”

Peter Harner, Project Manager, UK Highways Agency

>

M6 FootbridgesC A S E S T U D Y

Schönwasserpark BridgeC A S E S T U D Y

The Schönwasserpark Bridge is an orthotropic steel bridge spanning a busy state motorway in Germany. Using SPS Overlay to strengthen the bridge deck ensured the existing structure was retained and additional work on the superstructure was avoided. Disruption to traffic was kept to a minimum and the whole bridge deck was reinstated in just five weeks.

“SPS Overlay technology has proved to be an effective refurbishment measure to make steel deck bridges fit for modern traffic.”

Prof. Dr.-Ing Markus Feldmann, RWTH Aachen University

>

The Dawson Bridge is a 100 year old, 5 span truss bridge that forms an important link across the North Saskatchewan River running through the centre of Edmonton, Canada. SPS Bridge Decks were selected as the alternative that offered the simplest, quickest installation that minimized truss strengthening and provided another 100 years life for the bridge deck.

“The SPS Bridge Deck allowed the entire project to be completed months faster and millions of dollars less expensively than a traditional concrete deck.”

Jeff DiBattista, Principal, Dialog

>

Dawson BridgeC A S E S T U D Y

Page 140: Project Portfolio Web Version June 10 2015

Tests carried out at the UK MoD’s Defence Evaluation Research Agency (QinetiQ)showed that SPS stops projectiles at shorter strike ranges and higher angles ofattack. SPS reduced risk of penetration by 75% compared with equivalent all steelstructure.

Blast tests carried out at US Navy’s Naval Surface Warfare Center (NSWC)demonstrate how SPS absorbs more blast energy, reduces risk of prematurerupture and limits fragment penetration. The conventional steel panel (left) isruptured by the blast while the SPS panel (right) absorbs the energy and deformswithout rupture.

18

The benefits of using SPS include:

> Lighter, stiffer, simpler structures with improved fatigue and corrosion resistance, more internal space and permanently smooth external surfaces

> Superior blast protection, transferring less energy to supporting structures and reducing risk of rupture

> Increased protection from projectiles at shorter ranges and higher angles of attack

> Built-in fire protection

> Reduced structure-borne noise and vibration signature

> Greater resistance to high energy impacts including groundings, collisions and falling objects

Example applications:

SPS protection can be incorporated into new designs, prefabricated for on-site installation or retrofitted as an SPS Overlay to existing structures.

> New build designs automatically incorporate full range of protection benefits wherever SPS is used as structural material

> Optimised designs where structures have specific requirements, e.g. high point loads on flight decks; reduced vulnerability on amphibious craft

> Retrofitted blast belt applied as additional protection above and below water-line or to provide impact protection for side shells of offshore structures

> Blast walls in refineries or vulnerable public buildings

> Crash decks (during construction) and permanent blast and impact resistant flooring structures

SPS can be used in military and civil applications to reduce vulnerability and to increase survivability and safety. SPS is a lightweight alternative to stiffened plate and reinforced concrete with built-in fire protection and vibration damping as well as energy absorbing properties that enhance the blast, ballistics and impact resistance of structures.

protection and defence

Page 141: Project Portfolio Web Version June 10 2015

19

protection and defence

SPS impact test dropping 2 tonne rocks from 3 metres onto a section of SPSdeck. SPS sustained no damage; the all-steel equivalent was destroyed.

SPS Overlay for pontoons of drilling rig is able to absorb impact of 3 tonne drillcollar falling from height of 37 metres without rupture.

Tests carried out at the Danish Institute of Fire Technology (DIFT) show un-insulated steel structure red hot (left) after 60 minutes at 945°C vs. maximum temperature for SPS of 38°C (note the bare feet).

SPS impact test - sharp point-load on a 2 tonne sled striking SPS plate at 5m persecond. SPS sustained minor indentation; the all-steel alternative was punctured through.

Citadel protection is a proven concept that has a successful track record for protecting ships and crew from piracy. The internationally recognized Best Management Practice to Deter Piracy in the Gulf of Aden and off the Coast of Somalia recommends that a “Citadel is designated and lock-down procedures rehearsed to delay access to ship controls and buy time”.

SPS Citadel Access Protection delays and deters entry to the safe refuge. Once installed, the SPS barrier creates a detail free surface that can be rapidly deployed within 2 minutes. When closed, the SPS panels create an extremely strong barrier that can withstand far higher impact loads than equivalent steel structures with superb blast protection against ballistics and shrapnel damage.

>

SPS Citadel Access ProtectionC A S E S T U D Y

Page 142: Project Portfolio Web Version June 10 2015

20

sustainability

SPS products offer important benefits in sustainability and thereduction of environmental risk in the construction and shipbuilding industries. These include increased structural efficiency andreduced use of materials and resources in construction. In serviceSPS structures are less vulnerable to damage, require lessmaintenance and have a longer service-life. SPS is easily recycledand, unusually for heavy engineering materials, SPS is easilyreused. This means that SPS structures can also yield lowerthrough-life emissions and a smaller carbon footprint thanconventional concrete and steel structures.

> Potential for 100% reuse or recycling of all SPS materials

> Reduction in other construction materials and resources

> Off-site prefabrication reduces on-site disruption

> Reduced maintenance and increased service-life

> Increased safety and reduced environmental risk

Shipbuilding

SPS can improve sustainability and reduce the environmentalimpact of the construction and operation of ships in several ways. SPS requires less steel, welding and coatings to produce. SPSstructures are less susceptible to fatigue and corrosion therebyincreasing service-life. They are less vulnerable to accidentaland extreme impact events thereby reducing the risk ofenvironmental damage. SPS designs have the potential to allowfor increased cargo volumes, resulting in proportionally fewervessel movements, less fuel consumed and reduced risk.

SPS delivers a more sustainable, long term alternative to conventional steel and concrete when measured against key indicators including environmental, social and economic impact.

The steel and PU components of SPS can be readily recycled into high grade materials

Page 143: Project Portfolio Web Version June 10 2015

21

Construction

Incorporating SPS in a building can improve its sustainabilityperformance and rating with BREEAM and LEED. SPS Terracesand SPS Floors have been developed for 100% reuse. At the end of a structure’s life SPS Terraces and SPS Floors can bedemounted and, unlike comparable concrete products, canbe reused in new buildings without any additional processing.Alternatively at the end of their life the SPS panels can be recycledinto new SPS and other high grade materials.

An independent study completed by Decarbonize concluded thatreusing SPS can reduce the carbon footprint of a whole buildingby 10-20% compared with using concrete. Using SPS also contributes to:

> 25% reduction in the overall weight of materials used in a structure

> 70% reduction in truck movements

> A reduction in site waste

> Safer on-site working practices resulting in fewer accidents and injuries

Reinstatement and Conversion

In the repair or strengthening of ships and bridges, SPS Overlayincorporates – rather than cutting out and replacing – the existingstructure, thereby reducing the quantity of new steel used byup to 75%. The process uses much less welding and is much less labour intensive in what are typically hazardous conditions. SPS Overlay requires a fraction of the time needed for conventional repairs and, in the case of bridges, can be completed with onlypartial closure, thereby substantially reducing the disruption to traffic.

Ongoing initiatives

IE continues to explore opportunities to further develop thesustainability benefits of SPS, including:

> Minimizing the full life emissions of a building

> Working with architects and engineers to design structures that capitalise on the potential to reuse SPS products

> Working with suppliers to maximize the recycled content in all SPS products and applications

SPS Floor panels are bolted into position and can be as easily unbolted for reuse at the end of a structure’s life

Building with SPS can reduce truck movements by 70%

Page 144: Project Portfolio Web Version June 10 2015

intellectual property and approvals

Intellectual property

> The SPS intellectual property (IP) pool currently comprises 84 different groups of patents filed across 80 jurisdictions

> The scope and effective life of the IP pool are regularly expanded and increased. New patents added by IE, BASF and licensees presently extend the life of the pool to 2030

> IE and its partners and licensees, including BASF and DSME, are jointly responsible for maintaining and defending the SPS

IP pool

> ‘SPS’ is a registered trademark of Intelligent Engineering

Regulatory approvals

> SPS applications have been granted approvals by Lloyd’s Register, Det Norske Veritas, Germanischer Lloyd, Bureau Veritas, China Classification Society, American Bureau of Shipping, Russian Maritime Register, Korean Register of Shipping, Indian Register of Shipping and ClassNK. These classification societies account for over 80% of the global fleet

> Lloyd’s Register published the first rules for the design of SPS structures, which are now being refined in collaboration with DSME. China Class has also published design assessment standards. Similar programmes are underway with other classification societies including DNV and GL. These allow owners and designers to specify SPS for repair and construction and enable SPS to be used directly by the global community of naval architects and marine engineers

> SPS Overlay is accepted by RightShip as a means of repair that meets their Condition Assessment Program (CAP) requirements

> SPS Bridges have been approved and are in use in Germany, Canada, the USA, China and the UK

> In 2009 SPS Terraces were Certified by BRE (BPS 7007), UL Listed and “Code-prescribed” under the New York City Construction Codes

> SPS Floors have completed certification testing at the UK’s Building Research Establishment (BRE) and have UL Listed fire ratings. Equivalent approvals are pending in other jurisdictions

Offshore/in-situ repairs

Individual projects

2-4 projects

5-9 projects

10-29 projects

30+ projects

22

Page 145: Project Portfolio Web Version June 10 2015

intellectual property and approvals

Global Reach – more than 280,000m², 440+ projects and approved by the major classification societies

23

Page 146: Project Portfolio Web Version June 10 2015

industry partners

SPS technology has been developed and commercialised in collaboration with leading designers, fabricators and regulatory authorities in the maritime and civil engineering sectors. These long term partners provide the platform for SPS increasing its profits, activities and projects in many international markets.

The continuing support of these parties is secured through partnership agreements and a network of licensees. These agreements deliver market access and capacity for the fabrication of SPS plates, in addition to technical expertise and the reliability of execution of SPS projects in the field. SPS licences ensure that both current and future SPS patents are controlled by IE and are available to all licensees. This network of strategic partnerships is being extended by application and by region.

BASF

IE and BASF jointly developed the core material for the SPS technology. An exclusive agreement provides for continuing collaboration in research and development and the joint prosecution and maintenance of intellectual property rights.

Daewoo Shipbuilding and Marine EngineeringCo Ltd (DSME)

In keeping with a strategy of partnering with the market leaders capable of transforming industries, IE has formed a joint venture, SPS Marine Technologies Ltd, with DSME to bring SPS technology into mainstream shipbuilding.

> AECOM

> Arup

> BIGR

> Bovis Lend Lease

> Buro Happold

> Franklin Sports Business

> Gardiner and Theobald

> John Sisk

> Mace

> Mott MacDonald

> Populous

> Thornton Tomasetti

> Tishman

> Walls

> Walter P Moore

> Wates

> WSP

SPS in Construction

IE is working with market leading architects, engineers andspecialists including:

SPS Customers

SPS is used by market leading companies:

> BP

> Exxon Mobil

> MWNY

> P&O

> Petrobras

> Prosafe

> SBM

> Schuff

> Shell

> Siemens

> Starbulk S.A.

> Stena

> Southern Bleacher

> Clarkson Technical Services

> Dongkuk

> DSME

> Eiffel Deutschland Stahltechnologie GmbH

> Harris Pye

> Keppel

> SMT

> SRC

> Supreme

> Walters Inc

SPS Partners and Licensees

IE has licensed a number of service providers to deliver SPS, while continuing to maintain an IE field team to support the execution of specialist projects.

These include:

24

Page 147: Project Portfolio Web Version June 10 2015

company information

SPS was invented by Dr Stephen Kennedy following years of primary research in the field of ice-strengthened structures. Intelligent Engineering was established to develop and commercialise SPS technology and now licenses the use of SPS to market leaders by application and by region.

IE’s team of over 60 professional staff work from offices in Europe, North America and Asia. Supervised by IE Holdings Ltd, the management team is supported by an operating board of directors and Advisory Board made up of leading experts and businessmen.

Operating Management Team and Directors

Michael Kennedy Chairman

Dr Stephen Kennedy Chief Technical Officer

Paul BradfordChief Financial Officer

Scott KentDirector, Civil Engineering (UK)

Dr Neil LittleDirector, Materials &Intellectual Property

Dr David WilbrahamChairman of Advisory Board

Sir Bruce MacPhailNon-executive Director

Jen GeddesNon-executive Director

Martin Brooking Director, SPS Shipbuilding

Tim Kennedy Director, Operations

25

David GloverChief Executive Officer

Steve SegarraPresident, SPS North America

Jonny LimGeneral Manager, SPS Asia

Andreas ChungCommercial Director, Korea

Page 148: Project Portfolio Web Version June 10 2015

advisory board

Advisory Board Members

George BlakeFormer EVP of Maritime Overseas Corporation

Professor Yingqiu ChenExecutive Vice Chairman of the Technical Consultation & Appraisal Committee of the China Classification Society (CCS)

Dr Peter ChengMember of ABS, Lloyd’s and NK Hong Kong Committees and Chinese SNAME

Dr Roger DortonFormer VP of the International Association of Bridge andStructural Engineering

John FergusonFormer Deputy MD of Lloyd’s Register

Professor Chengi KuoResearch Professor at the University of Strathclyde

Nicholas LykiardopuloFellow of the Institute of Chartered Shipbrokers

Sir Bruce MacPhailNon-executive Director of IE Ltd and former Managing Director of P&O and Chairman of P&O Property Holdings

Dr Tom MurrayInaugural Montague-Betts Professor of Structural Steel Design at Virginia Tech

Sir John Parker Chairman of Anglo American plc, Vice Chairman of DP World Dubaiand non-exec Director of Camival Corporation. Past President of RINA

Rt Hon John Redwood MPFormer Cabinet Minister. Former Director of NM Rothschild and Chairman of Norcross plc

Dr Harlan UllmanSenior Advisor to NATO’s Supreme Allied Commander Europe and former professor of military strategy at US National Defense University

Jake Ulrich MD of Centrica Energy and founding partner of Dynergy

Ton Voorham Founder of SMT Ship Management & Transport and partner in Cemilas BV which operates the SPS production plant in Holland

Dr David WilbrahamChairman of IE Advisory Board. Former roles include CEO andChairman of Hickson International plc, Chairman of Akers Bioscience Inc, Governor of Imperial College

Anthony WilliamsPartner in McKenna Long & Aldridge LLP and former Chairman of Coudert Brothers

Dr Douglas WrightPresident Emeritus of University of Waterloo

26

IE Management Team and Advisory Board pictured on the new terrace at Ascot Racecourse (2007) - Left to Right: Dr. Neil Little, John Ferguson, Dr Stephen Kennedy, Dr Roger Dorton, Sir Frank Lampl, Martin Brooking, Stuart Rolland, Jake Ulrich, John Redwood, Denis Welch, Prof Chengi Kuo, Dr Tom Murray, Dr Laurie Kennedy, Jeremy Lloyd, Guy Turner, Dr David Wilbraham, Dr Doug Wright, Sir Bruce MacPhail, Dr Peter Cheng, Michael Kennedy. Absent: George Blake, Tim Kennedy, Nicholas Lykiardopulo, Sir John Parker, Anthony Williams. New Members: Professor Yingqiu Chen, Dr Harlan Ullman.

Page 149: Project Portfolio Web Version June 10 2015

SPS Bridge Deck panel in production

Page 150: Project Portfolio Web Version June 10 2015

Intelligent Engineering (UK) Ltd Shire House, West CommonGerrards CrossBuckinghamshire SL9 7QNUnited KingdomTel: +44 1753 890575Fax: +44 1753 899056

Intelligent Engineering (Canada) Ltd14 Chamberlain Avenue (Suite 300)Ottawa Ontario Canada K1S 1V9Tel: +1 613 569 3111Fax: +1 613 569 3222

SPS Overlay Asia Pte LtdSPS Marine Technologies Ltd460 Alexandra Road #34-04A PSA BuildingSingapore 119963Tel: +65 6513 2782Fax: +65 6513 2784

[email protected]

SPS is a registered trademark of Intelligent Engineering

June 2015

PO Box 83Ordnance House31 Pier RoadSt HelierJersey JE4 8PW