project cost management paper 27 may09

16
Enhancing project team roles and responsibilities in project cost management by Pascal Martin-Daguet, Civil Engineer INSA Rennes (France) Freyssinet International and Company (www.freyssinet.com) [email protected] Singapore, 27 th May 2009 Introduction In most construction projects “cost control”, if any, consists of asking an accounting department to code each invoice using pre-defined cost codes, and to dedicate a quantity surveyor to sum-up, on a regular basis, the amounts accrued on each of these codes. With this biased information the project management team (Project Manager and Construction Manager) are consequently restricted in their ability to attain efficient cost management. In short this paradigm is “cost following” rather than “cost controlling” “Project cost management” or “Cost-driven project management” has two main goals: 1. To secure the projected profitability, success and sustainability of the Project by reducing the risks 2. To find areas of cost optimization in order to further improve profitability In order to achieve the aforementioned the whole Projects organisation must be structured, selected, organised but also effectively managed and lead to achieve these aims. 1 of 16 Project Management Operations Customer Learning & growth Financial

Upload: pascal109

Post on 05-Dec-2014

1.248 views

Category:

Business


0 download

DESCRIPTION

Enhancing project team roles and responsibilities in project cost management

TRANSCRIPT

Page 1: Project Cost Management Paper   27 May09

Enhancing project team roles and responsibilitiesin project cost management

by Pascal Martin-Daguet, Civil Engineer INSA Rennes (France)Freyssinet International and Company (www.freyssinet.com)

[email protected], 27th May 2009

IntroductionIn most construction projects “cost control”, if any, consists of asking an accounting

department to code each invoice using pre-defined cost codes, and to dedicate a quantity

surveyor to sum-up, on a regular basis, the amounts accrued on each of these codes. With

this biased information the project management team (Project Manager and Construction

Manager) are consequently restricted in their ability to attain efficient cost management.

In short this paradigm is “cost following” rather than “cost controlling”

“Project cost management” or “Cost-driven project management” has two main goals:

1. To secure the projected profitability, success and sustainability of the Project by

reducing the risks

2. To find areas of cost optimization in order to further improve profitability

In order to achieve the aforementioned the whole Projects organisation must be

structured, selected, organised but also effectively managed and lead to achieve these

aims.

1 of 16

ProjectManagement

Operations

Customer Learning& growth

Financial

Page 2: Project Cost Management Paper   27 May09

Planning the strategy

In order to manage the cost, the organisation has first to set out its strategy. This can be

first formulated in a vision and mission statement. The next step is to develop a

sustainable plan which is communicated and socialised throughout the whole organisation.

Risk management must be one of the fundamentals of this strategy. Risk management is a

systematic approach to minimizing the organisation exposure to risk. A risk management

system includes various policies, plans, procedures and practices that work in unison to

identify, analyse, control, monitor, measure and record risks.

The project management team need will need to prepare the following documents:

• Risk Register/Risk Assessment

• Safety & Security Policies & Plans & Procedures

• Quality Assurance, Quality Control, policy, Plan & Procedures

• Administrative policy , plans and procedures

• Human Resources , policy , plans and procedures

• Crisis/Emergency Management Response Plan and Procedures

Very often, the project management team is rushing to start the project and neglects these

strong pillars of a cost-driven organisation, or delegate them to lower rank staff, often a

trainee. This is a severe mistake as these documents are the architecture of the

organisation. Without them, members of the organisation will not efficiently execute the

strategic plan.

Throughout the life cycle of the project, regular reviews of the strategy must be

undertaken. This will facilitate the continual improvements of the organization as it moves

thought the various phases of the project: For example

• Management review : every 6 months

• Quality review : every 6 months

• Risk register review : every 2 months

2 of 16

Page 3: Project Cost Management Paper   27 May09

The execution of the strategy must also be made measurable as it provides the

organisation with measurements of actual performance against its perceived performance.

These measurements can take various forms and should be kept simple and in graphical

format to be more easily understood.

Safety Number of accidents (AFR)

Severity of accident (ASR)Quality Non Conformance Reports (NCR)Engineering Number of documents to be issued,

issued, approvedWorks Percentage work done, scheduled; and

any other linear indicator (number of

beams, m3 of concrete...)Financial Amounts invoiced, paid; costCost control Budget, cost accrued, cost to spend,

works value, cost at completion, daily

running costHR Absenteism

Project team organisation

An organisation that manages cost is an organisation that manages risks. Traditionally,

safety and quality are the two major risks in the construction industry. The corresponding

two departments should therefore have an important position in the organisation chart,

they should be a service to the other departments, and they should be directly connected

to the Project Manager as they are some of his main control levers (other control levers

being: planning, budget/cost control, HR).

3 of 16

Page 4: Project Cost Management Paper   27 May09

Cost-driven project organisation

Traditionally, projects are late from the very first day, and recruitment is done in a rush.

Staffs normally are hired with little know of their qualifications, competency and suitability

to the project (job description, work environment, capability to cope with stress, ethics...).

While most of people adapt well to their new environment, there is usually a small number

of people wrongly selected that don't fit the organisation. In best cases, these people don't

produce the expected results; in worse cases they produce counter-productive results and

damage the entire organisation, limiting the execution of the plan and adding avoidable

costs.

It is therefore important that the whole the organisation be clear on the projects goals,

mission and values. This can be achieved through strategic HR policy where the right

person is selected for the right job, in alignment with the project's goals.

To achieve this important target, the following should be put in place:

• Assign/recruit a trained HR manager

• Forecast HR requirements for the whole project

• Prepare an organisation chart at an early stage of the project, and keep it regularly

updated

• Define the required job positions, do a job analysis in order to clearly define what

the employee is expected to do.

4 of 16

Production

Project Manager

Safety Quality

Engineering Contract/QSCost control Accounts Procurement HR

Page 5: Project Cost Management Paper   27 May09

• Contact recruitment agencies, advertise in newspapers (although 75% of

recruitment is usually done through “people who know people who know people”)

• Use Human Resource information management systems to assist in making

people the most powerful organisation assets [ HRIMS]

• Ensure time is built into the plan for regular group or one-on-one worker

management consultation sessions.

• Use performance appraisals and link rewards (bonuses, salary increments) to

Projects goals.

Job interviews should be conducted not only to verify the competencies of the candidate,

but also to determine whether the candidate will fit the organisation (be in alignment with

the project's goals and values). The interviewer should use pre-defined questionnaires to

assess the candidate's values: ambition, assertiveness, competence, courtesy,

cheerfulness, dependability, forgiveness, helpfulness, honesty, imagination, independence,

rationality, openness, self-control. Finally, the interviewer could use online tests

(personality, team playing) to ensure that the future staff will be comfortable in the

organisation and produce positive results.

Cost control organisation

Cost control is a tool that must be used by senior management to monitor the profitability

of the project, to report to a corporate level, to make strategic decisions, to get the

production teams to be responsible of their works.

The most important point of an efficient cost controlling system is to have a senior

manager with a good technical knowledge of the project (“what” has to be built) to define

the cost codes. It would be typically the project manager, the construction manager or a

senior engineer. In no cases should the definition of cost codes be left to an accounting

department as they would not have the required big picture.

Cost codes should be defined so that they provide monitoring of the critical parts of the

project, representing amounts of money that are relatively high or in the same range. It

makes no sense, for example, to create a specific code to monitor purchase of stamps that

would represent 0.002% of the cost of the project.

5 of 16

Page 6: Project Cost Management Paper   27 May09

Cost codes should be of two types, organised in a matrix system, in order to represent the

two different aspects of cost: its destination (which part of the site) and its nature (what

kind of material, equipment or service):

Cost centres : typically one per team so that each foreman is responsible of his own

budget. It is recommended to use letters for cost centres. There should always be a cost

centre for “general items” where all the administrative and running costs (general staff,

office...) can be allocated.

For example, for a bridge construction:

Centre ActivityA General itemsB FoundationC ColumnsD PiersE Beams prefabricationF DeckG Finishes

Analytical codes (also called, global ledger code, accounting code...) : a series of codes

representing the nature of the cost, defined in main categories and sub-categories. It is

recommended to use 4-digits code, the first two digits for the main category, the following

two for the sub-category. There should no more than 50 to 100 analytical codes.

An example of chart of accounts (sub-categories have been shown here only for the first

category for easy reading):

Code Nature010001010102011001110112

Labour (main category)Direct labourSub-contracted labourLabour medical expensesLabour transportationLabour other expenses

0200 Materials and products0300 Plant and equipment0400 Consumables

6 of 16

Page 7: Project Cost Management Paper   27 May09

0500 Design, Testing, sub0600 Staff0700 Running cost0800 Administrative and financial charges0900 Fixed assets

On smaller projects, cost centres can be omitted as long as analytical codes don't actually

comprise of a mix of cost centres and analytical codes (for example: labour for

foundations, labour for columns...) as this would create confusion in the coding process.

Once the chart of accounts has been created, the first budget can be prepared; each item

of the budget should then be coded according to the charts of accounts, and the cost

displayed in the form of a matrix so that each team (corresponding to each cost centre) is

aware of its available budget in each category:

A B C D E F G0100 - $ $ $ $ $ $0101 - $ $ $ $ $ $0102 - $ $ $ $ $ $0110 - $ - $ - - -0111 - $ $ $ $ $ $0112 - - $ - $ $ -0200 - $ $ - $ - -0300 - $ $ $ $ $ $0400 - $ $ $ $ $ -0500 - $ $ $ $ $ $0600 $ $ $ $ $ $ $0700 $ - - - - - -0800 $ - - - - - -0900 - $ $ - $ $ -

During the course of the project, each site team will specify ts cost centre on the

requisition for purchase of material, equipment..., and the accounting department will code

each invoice according to the analytical nature of the cost. Purchase orders, delivery notes

and invoices should be input in a computer system, and the cost reconciled in a matrix

7 of 16

Page 8: Project Cost Management Paper   27 May09

form, similar to the budget one, for easy comparison.

On a regular basis (monthly), the cost controller should compare the “cost to date” + “cost

accrued” (spent but not yet paid) to the “works value” (cost that should have been spent

considering the present progress of the works). The budget should be updated at least

every 6 months.

The typical organisation chart for this kind of system should be as follows.

PlanningThe Five P rule : “Proper Planning Prevents Poor Performance”

The main program of works should be prepared at the beginning of the project in the form

of a Gantt chart showing the main activities and sub-activities, using a specialised

software. Dates in a Gantt chart should never be fixed except for the first task as futures

modifications of the program would be rendered very difficult. Tasks should be linked to

each other, and the calendar should include rest days, bank holidays and a few days

8 of 16

Store keeper

Steering Committee

Project Manager

Construction Manager

Accountant

Purchaser

Cost controller

Foreman 1

Foreman 2

Foreman 3

Commercial Manager

Page 9: Project Cost Management Paper   27 May09

immobilized for bad weather. The actual progress of works should be checked against the

main program of works on a monthly basis, and the main program of works should be

revised every 6 months.

A “weekly 5 weeks rolling program” should be prepared at the end of each week to show

the activities programmed for the 4 weeks to come, and the actual works done against the

programmed tasks of the past week.

A program of procurement of the main items to be ordered should also be prepared in

accordance with the main program of works and reviewed on a regular basis. This is

particularly important for items that have to be procured from overseas to allow fabrication

time, shipping and custom clearance. Indeed, many project suffer delays because of bad

procurement planning.

if you fail to plan, you plan to fail

Finally, a program of staff and labour (in the form of a bar chart) will allow the HR

department to anticipate the recruitment needs.

9 of 16

Page 10: Project Cost Management Paper   27 May09

Leadership

The best way to manage the cost of a project is to make sure that the whole team is

aligned on a same vision, a same goal, so that all the energies are focussed in the same

direction (towards a successful completion of the project) rather than to fight against each

other. It is widely recognized that a team behaves similarly to its leader. Besides finding

the right people for the right job, it is therefore paramount to the team to lead by example

in an environment where each person feels empowered, respected, listened to,

responsible. In such circumstances, no energy is lost in conflicts, everybody works

efficiently which, eventually, helps managing cost (conflicts creating intangible cost).

Creating such an environment is entirely up to the project manager, and it takes years of

practice and a good dose of psychology to achieve it. There are countless books and

training methods available (see in the references section), and here are some of the

qualities that a good leader should develop:

10 of 16

Page 11: Project Cost Management Paper   27 May09

Think big picture Set realistic targetsBe completely committed Hold effective meetingsWork harder than everybody Make meetings funBe prepared to sacrifice Encourage peopleBe mentally tough Give creditLead with integrity CelebrateBuild team spirit Fight for your teamBuild confidence Inspire loyaltyRespect legitimate authority Respect individual differencesBe proactive, not reactive Listen to ideas from othersKeep it simple Don't always have the last wordChase perfection Be ready to say yesLearn from mistakes Set standards/expectationsHave a plan B, and a plan C Be creativeBe flexible and ready to move on Keep learningDon't bad-mouth your boss Don't bad-mouth your teamDon't play politics Don't intimidateDon't cut corners Be in command and take charge

Relationships with Client and subcontractors

Remember why you are working of this project: because of the Client, your customer.

Although the Client has the same goal as the contractor (finishing the project on time, with

the required level of quality, with high safety standards and within its budget) he has

different problems to solve: funding the project, dealing with Authorities or stakeholders,

dealing with the Public...

Although most contracts contain all the necessary weapons to go to war with the Client (or

vice-versa) this should be envisaged as a last recourse only. All win-loose situations

actually lead to loose-loose situations!

Maintaining good relationships with the Client from the very first day of the project and

more particularly in difficult moments, will be beneficial to both the Client and the

Contractor; in other words to the Project. This requires to work in partnering with the Client

to solve problems as they come, to propose solutions adapted to the problems, to discuss

11 of 16

Page 12: Project Cost Management Paper   27 May09

openly and on a regular basis contractual and commercial issues. In all circumstances,

leaving problems aside until the end of the project, hoping that they will be solved then, is

an open door to endless conflicts and financial losses.

In some cases, Contractors realising that their price offer was too low will start a

contractual battle with the client and produce unreasonable variation orders. They should

rather consider the option of “managing the cost of the project” through the implementation

of an appropriate organisation and opting for cost optimization. Blaming the Client for

everything is, in the end, counter-productive as a lot of energy (and therefore cost) is lost

in the process. It also damaged the image of the company for future projects.

Compromising and opting for a win-win settlement of problems will, once again, avoid

intangible costs.

The same principles apply to sub-contractors that main contractors often tend to

pressurize to “squeeze” cost. Ensure the sub-contractors are selected not only on their

cost both also their ability to align themselves with projects goals. There should be time

allocated to sufficiently orient them to the expectation levels. Early identification of sub-

contractors' weakness through audits and through a formal appraisal system, will guide

these sub-contractors to improve themselves. Not blaming “bad” subcontractors, but

instead helping them to develop, will help create strong and durable relationships between

parties, reducing delays and ultimately cost. Changing sub-contractors “as they are not

good” would again produce intangible costs and is often a result of poor planning and

selection policies.

Training

Most project-based organisations don't see the value of training their project staff. After all,

they will be with the company for only a few months or a few years; so why spending

money for their development?

The first reason for adopting a learning and development policy is to be able to fill the gaps

in people's competencies and make them more efficient in their present position. They

work better, produce better results for the benefit of the project which has the long-term

effect of optimizing the cost of the project.

12 of 16

Page 13: Project Cost Management Paper   27 May09

The second reason is that, thanks to continuous training, people can be internally

promoted to higher levels of responsibilities, which is of great advantage to the company

as there is no need to spend time and money recruiting external staff that could possibly

be unsuitable for the job.

Finally, being exposed to external experiences different from the daily routine job, helps

the team to bond together and to work better together, especially when they are under

pressure.

In conclusion, adopting a learning and development program helps to stabilize the staff,

reduces turnover , improves work efficiency and avoids intangible costs.

Communication

Communication is the giving, receiving, processing and interpretation of information.

Information can be conveyed verbally, non-verbally, actively, passively, formally, informally,

consciously or unconsciously. Effective communication is fundamental to project

management as it helps to gain common understanding (what are the objectives and how

to attain them). Unclear communication can quickly lead to misunderstanding among the

projects team, which can invariably degenerate into friction and conflicts as everybody

may think they have understood the expectations levels when in fact they may have not.

The organisation may also be a multi ethnic team where multiple languages and different

cultural norms exist. If each member is not recognized and understood by the

management, there can be misunderstanding, frustration, conflict and reduction in

efficiency. Ideally all managers should be trained in cultural awareness and effective

communications before they start to work on a project.

In other words, “seek first to understand then to be understood “(Covey, 1989). Effective

communication helps maintaining energy levels and enthusiasm, builds teamwork and

ensures that the organisation is focused towards a common goal which, in turn, reduces

the intangible costs incurred.

13 of 16

Page 14: Project Cost Management Paper   27 May09

My suggestion is to have, at least, one weekly meeting with the management personnel

(15 to 20 participants maximum). This meeting should be held within the office building,

preferably towards the end of the week (my personal experience is that Friday morning

9am is a good time). The meeting should be held in the form of a forum where each

participant is invited to expose the challenges or problems that he faces so that the other

members of the team can actively participate and suggest solutions. The chairman of the

meeting (the Project Manager) should limit the meeting to 1h-1.5h, make it a dynamic and

fun moment and prepare short minutes of meeting in the form of an action list (who does

what by when). A weekly coordination meeting should not be a lengthy, sterile moment

where each participant waits his turn to give a report of what he has done during the week.

I also suggest to have a 2-3 hours meeting with the senior staff only (5 to 10 people) every

6 months, outside of the office (preferably in a hotel or in a restaurant so that it can be

followed by a dinner and a fellowship session) for the Project Manager to remind the

objectives of the project, share the strategy and important information.

Finally, Key Performance Indicators (KPI), newsletters, website, multilingual posters

should be used when appropriate to communicate with the whole team.

Cost optimisation

Once the above-described organisation has been put in place and is working efficiently, a

cost-optimisation exercise can be envisaged. It is pointless, and sometimes counter-

productive, to start a cost-optimisation exercise when the cost-management structure is

not fully-functioning and stable. There are several ways to optimise cost:

1. Planning optimisation: consist of looking for ways to reduce the project time by

overlapping tasks, modifying resources on specific tasks, reducing float using the

Critical Path Method.

2. Value engineering: is the action of being creative to modify parts of the structure to

be build, to change methods of construction or materials in order to reduce cost.

Value engineering usually requires the prior approval of the Client.

3. Budget optimization: consist of reducing “cost to spend” of specific areas in the

budget that had been over-estimated. The cost centre / nature of cost matrix

defined earlier is particularly useful here.

14 of 16

Page 15: Project Cost Management Paper   27 May09

4. Six Sigma: is a performance based methodology that uses metrics and statistical

analysis to detect inefficient parts of a working process, to reduce defects, to

improve performance and productivity, and to ultimately reduce cost. The Six Sigma

methodology is widely used in the manufacturing industry to drastically improve

profitability, but is under-used in the construction industry although it is easy to set-

up and can generate substantial savings (10% and above) as it tackles intangible

costs : the Cost Of Poor Quality (COPQ). Six Sigma uses the DMAIC concept:

Define, Measure, Analyse, Improve, Control to produce durable cost savings.

Conclusion

Cost-Managing projects is far more than cost-controlling projects. It relates to cost-driving

projects to tackle the intangible costs by putting in place a strong organisation united

toward a same goal: completing the project safely, on time, with the required quality, in

budget and to the satisfaction of the Client. Cost-managing projects not only helps to

stabilise costs (avoiding cost overrun) but also gives opportunity to improve profitability by

improving productivity and efficiency, therefore further reducing cost. Finally, it enhances

the image of the company, builds sustainability and improves marketability.

15 of 16

Page 16: Project Cost Management Paper   27 May09

References

Association for Project Management (APM), http://apm.org.uk , viewed 12th May 2009

APM Body of Knowledge 5th Edition, 2006, Association for Project Management, UK ,

Covey , S , 1989 , The 7 Habits of Highly Effective People , Simon and Schuster , NY

Free online personality test, http://www.goddessflight.com/per/passess.htm, viewed 12th

May 2009

Free online team player test, http://www.testcafe.com/team/team.html, viewed 12th May

2009

Lombardi , V , 2003, The Lombardi Rules, Mc Graw-Hill, USA

Project management tools : http://www.method123.com/, viewed 12th May 2009

Stone, R, J , 2008 ,Human Resource Management 6th Edition, John Wiley and Sons

Australia Ltd.

Templar, R, 2005, The rules of Management, Pearson Books, Pearson Books , UK

Understanding Six Sigma, Neville Clarke Malaysia Sdn Bhd, www.nevilleclarke.com

16 of 16