project appraisal report - african … · project appraisal report date: september 2012 ... william...

30
Language: ENGLISH Original: French AFRICAN DEVELOPMENT BANK PROJECT : MARRAKECH REGION WATER SUPPLY PROJECT COUNTRY : KINGDOM OF MOROCCO PROJECT APPRAISAL REPORT Date: September 2012 Team Leader Belgacem BEN SASSI, Principal Water and Sanitation Engineer OWAS.2 William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal Officer GECL.1 Laurette DADE, Regional Financial Management Coordinator ORPF.2 Habib KAMOUN, Consultant, Financial Analyst OWAS.2 Team Members Idrissa SAMBA, Consultant, Environmental Expert OWAS.2 Appraisal Team Mohamed ELOUAHABI, Water and Sanitation Specialist OWAS.2/MAFO Mohamed EL ARKOUBI, Procurement Officer ORPF.1/MAFO Leila KILANI JAAFOR, Social Development Specialist OSHD/MAFO Iman SERROKH, Disbursement Assistant FFCO.3/MAFO Sector Division Manager Osward M. CHANDA OWAS.2 Resident Representative Amani ABOU-ZEID MAFO Sector Director Sering JALLOW OWAS Regional Director Nono MATONDO FUNDANI ORNB Mahib CISSE, Chief Investment Officer OPSM.3 Mouldi TARHOUNI, Chief Irrigation Engineer OSAN.2 Ibrahima KONATE, Principal Energy Engineer ONEC.1 Peer Reviewers Francis Daniel BOUGAIRE, Principal Water and Sanitation Engineer FAE Jean-Noel ILBOUDO, Infrastructure Engineer OITC.1 Patrice HORUGAVYE, Socio-Economist OWAS.1

Upload: vocong

Post on 18-Aug-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

Language: ENGLISH Original: French

AFRICAN DEVELOPMENT BANK

PROJECT : MARRAKECH REGION WATER SUPPLY PROJECT COUNTRY : KINGDOM OF MOROCCO

PROJECT APPRAISAL REPORT Date: September 2012

Team Leader Belgacem BEN SASSI, Principal Water and Sanitation Engineer

OWAS.2

William DAKPO, Regional Procurement Coordinator

ORPF.1

Félix BAUDIN, Chief Legal Officer GECL.1

Laurette DADE, Regional Financial Management Coordinator

ORPF.2

Habib KAMOUN, Consultant, Financial Analyst

OWAS.2

Team Members Idrissa SAMBA, Consultant, Environmental Expert

OWAS.2

Appraisal Team Mohamed ELOUAHABI, Water and Sanitation Specialist

OWAS.2/MAFO

Mohamed EL ARKOUBI, Procurement Officer

ORPF.1/MAFO

Leila KILANI JAAFOR, Social Development Specialist

OSHD/MAFO

Iman SERROKH, Disbursement Assistant

FFCO.3/MAFO

Sector Division Manager Osward M. CHANDA OWAS.2

Resident Representative Amani ABOU-ZEID MAFO

Sector Director Sering JALLOW OWAS

Regional Director Nono MATONDO FUNDANI ORNB

Mahib CISSE, Chief Investment Officer OPSM.3

Mouldi TARHOUNI, Chief Irrigation Engineer OSAN.2

Ibrahima KONATE, Principal Energy Engineer ONEC.1

Peer Reviewers Francis Daniel BOUGAIRE, Principal Water and Sanitation Engineer

FAE

Jean-Noel ILBOUDO, Infrastructure Engineer OITC.1

Patrice HORUGAVYE, Socio-Economist OWAS.1

Page 2: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

TABLE OF CONTENTS

Currency Equivalents, Fiscal Year, Weights and Measures, Acronyms and Abbreviations,

Project Information Sheet, Project Summary, Logical Framework, Project Implementation

Schedule. i - v

I – Strategic Thrust and Rationale .............................................................................................. 1

1.1. Project Linkages with the Country Strategy and Objectives ....................................... 1

1.2. Rationale for Bank’s Involvement .............................................................................. 2

1.3. Aid Coordination ......................................................................................................... 2

II – Project Description .......................................................................................................... 3

2.1. Project Components .................................................................................................... 3

2.2. Technical Options Retained and Other Alternatives Explored ................................... 3

2.3 Project Type / Instrument ............................................................................................ 4

2.4. Project Cost and Financing Arrangements .................................................................. 4

2.5. Project Area and Beneficiaries .................................................................................... 5

2.6. Participatory Approach for Project Identification, Design and Implementation…… 6

2.7. Bank Group Experience and Lessons Reflected in Project Design............................ 6

2.8. Key Performance Indicators ........................................................................................ 7

III – Project Feasibility .............................................................................................................. 8

3.1. Economic and Financial Performance ......................................................................... 8

3.2. Environmental and Social Impact ............................................................................... 9

IV –Implementation ................................................................................................................. 12

4.1. Implementation Arrangements .................................................................................. 12

4.2. Monitoring ................................................................................................................. 15

4.3. Governance ................................................................................................................ 15

4.4. Sustainability ............................................................................................................. 16

4.5. Risk Management ...................................................................................................... 16

4.6. Knowledge Building.................................................................................................. 17

V – Legal Framework .............................................................................................................. 18

5.1. Legal Instrument........................................................................................................ 18

5.2. Conditions Associated with Bank’s Intervention ..................................................... 18

5.3. Compliance with Bank Policies ................................................................................ 19

VI – Recommendation ............................................................................................................. 19

Annex I. Country’s Development Indicators .................................................................. 1

Annexe II. Table of ADB Active Portfolio in the Country (as at 31 January 2010) .......... 1

Annex III. Key Related Projects Financed by the Bank and Other Development

Partners of the Country .............................................................................................................. 1

Annex IV. Map of Project Area ...................................................................................... 1

The information and data in this report were collected by the project team led by Mr. Belgacem BEN SASSI, Principal Water and Sanitation Engineer, Task Manager, after a pre-appraisal mission carried out in Morocco from 23 October to 5 November 2011 and an appraisal mission from

6 to 11 February 2012.

Page 3: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

i

Currency Equivalents August 2012

UA 1 = MAD 13.5054

UA 1 = EUR 1.22788

UA 1 = USD 1.50833

Fiscal Year 1 January – 31 December

Weights and Measures

1 km = kilometre = 1,000 m

1 km2 = square kilometre = 1,000 m

2

1 ha = hectare = 10,000 m2

1 ml = linear metre

1 m3 = cubic metre

1 m3/d = cubic metre per day

1 hm3 = million cubic metres

l/s = litres per second

inh/ha = inhabitants per hectare

lpd = litre per person per day

Acronyms and Abbreviations

ABH Water Basin Agency

AFD French Development Agency

CSP Country Strategy Paper

DEPP Directorate of Public Enterprises and

Privatization

DWS Drinking Water Supply

DWSS Drinking Water Supply and Sanitation

ESMP Environmental and Social Management Plan

ERR Economic Rate of Return

EU European Union

FIRR Financial Internal Rate of Return

GTZ German Technical Cooperation Agency

for Development

IWRMMP Integrated Water Resource Management

Master Plan

KFW Kreditanstalt für Wiederaufbau (German

Development Bank)

MAD Moroccan Dirham

MDG Millennium Development Goal

MEMEE Ministry of Energy, Mines, Water

and Environment

NHDI National Human Development Initiative

OCP Office chérifien de phosphates

(Moroccan Phosphates Authority)

ONE Office national de l’électricité

(National Electricity Authority)

ONEE Office national de l’électricité et

de l’eau potable (National Electricity

and Drinking Water Authority)

ONEP Office national de l'eau potable

(National Drinking Water Authority)

SME Small and Medium-Size Enterprise

RADEEMA Marrakech Autonomous Water and

Electricity Distribution Board

Water SAP Water Sector Adjustment

Programme

WHO World Health Organization

Page 4: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

ii

Project Information Sheet

Client

BORROWER : National Electricity and Drinking Water Authority (ONEE)

EXECUTING AGENCY : National Electricity and Drinking Water Authority (ONEE)

GUARANTOR : Government of Morocco (Ministry of Economy and Finance)

Financing Plan

Source Amount (UA) Instrument

ADB

122.20 million

ADB Loan

AFD 45.60 million Loan

ONEE and OCP 44.30 million -

TOTAL COST 212.10 million -

Important ADB Financing Information

Loan Currency

EUR (80%) and USD (20%)

Interest Type* Enhanced variable spread

loan

Interest rate spread* EURIBOR / LIBOR

Commitment fee* Nil

Other charges* Nil

Grace period 60 months

FIRR, NPV (baseline scenario) 7.1%

MAD 577 million

ERR (baseline scenario) 10.7%

MAD 684 million

*where applicable

Time Frame – Main Milestones (expected)

Concept Note Approval

December 2011

Project Approval November 2012

Effectiveness March 2013

Completion December 2017

Last Disbursement December 2018

Last Repayment -

Page 5: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

iii

PROJECT SUMMARY

Project Overview

1. The Marrakech Region Water Supply Project in Morocco consists in ensuring the secure

supply of drinking water to the city of Marrakech and its neighbouring urban centres from the Al

Massira dam and meeting the industrial water needs of the country’s Phosphates Authority (Office

chérifien de Phosphates – OCP). This area has three poles (Marrakech, Al Haouz and Al Kelaa)

which are experiencing significant urban, tourism and industrial development. The project aims to

meet drinking and industrial water demand in these areas by 2030. The project, at an estimated cost

of UA 212.1 million will be implemented over a 60-month period (2013-2017).

2. The project will prioritize the populations of the towns and cities concerned and

neighbouring urban and rural centres. In terms of supply, it will strengthen and improve the quantity

and quality of the drinking water supply of about 2 million people as from 2017 and provide both

ONEE (Water Branch) as producer and distributor, and the Marrakech Autonomous Water and

Electricity Distribution Board (RADEEMA) as distributor with the resources to sustain growing

demand in the areas concerned until 2030 – when the area’s population will reach about 3 million,

with over one million in in rural areas. It will also help to supply the industrial water needs of the

Phosphates Authority (Office chérifien de Phosphates – OCP) for its Ben Guerir site.

Needs Assessment

3. The project’s design was based on the priority needs outlined by ONEE (Water Branch) in

its Programme Contract with the Moroccan State for the 2012-2016 period. The urgent need to

implement the project now stems from the large volume of water to be mobilized (about 96 million

m3/year by 2030) to meet the future drinking water needs of the Marrakech region and the industrial

water needs of OCP given that surface and ground water resources currently available are saturated.

The solution retained to mobilize the waters of the Al Massira dam is the best option and is in line

with the national policy of transferring water from basins with surplus water to those with a deficit.

Bank’s Added Value

4. ONEE (Water Branch) was chosen to propose to the Bank to participate in financing this

project because of its proven comparative advantage in implementing this kind of project (with

fairly urgent operations affecting medium-and large urban centres). This is well illustrated in recent

Bank-financed water and sanitation sector projects in Morocco – the most recent being the Project

to Upgrade Drinking Water Supply in the Rabat-Casablanca Coastal Area, approved in 2010.

5. This operation will provide an opportunity for the Bank to foster its cooperation with a

major water sector partner in Morocco, the French Development Agency, which will participate in

financing the project.

Knowledge Building

6. The project will contribute to enrich ONEE’s (Water Branch) experience in terms of

implementing and managing urban and rural drinking water supply and sanitation projects. OCP’s

involvement will strengthen the integrated project approach in Morocco and partnership with

various water sector beneficiaries, contributing to the promotion of integrated water resource

management.

Page 6: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

iv

RESULTS-BASED LOGICAL FRAMEWORK

Project Country and Name: Morocco – Marrakech Region Water Supply Project.

Project Goal: To strengthen and secure the drinking water production and supply system of the city of Marrakech and neighbouring centres and meet OCP’s raw water needs

RESULTS CHAIN PERFORMANCE INDICATORS MEANS OF VERIFICATION RISKS AND MITIGATION MEASURES

Indicator (including CSI) Baseline Scenario Target

IMP

AC

T The socio-economic and health

conditions of the population are

improved through a secure supply of

drinking water to urban and rural

centres.

1. Access rate to drinking water in urban areas

2. Access rate to drinking water in rural areas.

100% in 2011

92% in 2011

100% in 20301

100% in 2030 (95% in 2016)

Reports and statistics of ONEE, MEMEE

and other Ministries concerned

EF

FE

CT

S

1. The drinking water production and

supply system for the city of

Marrakech and neighbouring centres is

secure and strengthened.

2. OCP’s pre-treated water needs

assured.

1.1. Rate of access to drinking water for the urban

population of the towns concerned.

1.2. Rate of access to drinking water for the rural

populations of the provinces concerned.

1.3. Infant mortality rate (caused by water-borne

diseases).

1.4. Maternal mortality rate (caused by water-borne

diseases).

1.5. Percentage of households’ spending on health

(caused by the quality of water)

2.1. Pre-treated (de-silted) water needs of the Ben

Guerir mining industry (OCP) assured.

100% in 2011

79% in Rehamna, 84% in Al Haouz

and 94% in Marrakech in 2011

29 deaths for 1,000 people in 2011

112 deaths for 1,000 people in 2011

57.4% in 2011

-

100% in 2020

95% in Rehamna, 91% in Al Haouz

and 96% in Marrakech in 2020

15 deaths for 1,000 people in 2020

50 deaths for 1,000 people in 2020

25% in 2020

100% in 2020

ONEE reports and statistics

Reports and statistics of Boards

National statistics

Risks

- Preservation and availability of water

resources and their integrated and optimal

management.

Mitigation Measures

- Implementation of the Water SAP

measures, the National Water Strategy

action plans and Integrated Water

Resource Management Master Plan

(IWRMMP) of Oum Rbia Water Basin

Agency (ABH).

O

UT

PU

TS

1.1. Water intake structure built on

the Al Massira dam.

1.2. A 48km pre-treated water

pipeline laid.

1.3. One treatment station constructed

in Guerir .

1.4. A 65-km pre-treated water

pipeline laid.

1.5. Pumping stations constructed.

1.6. Loading and storage reservoirs

constructed.

1. Flow rate of pumped water on the Al Massira dam.

2. Flow rate of pre-treated water distributed.

3. Treated water flow rate.

4. Treated water flow rate.

5. Number of pumping stations completed.

6. Number of reservoirs completed.

- Non applicable (NA)

- NA

- NA

- NA

- NA

- NA

7 m3/s in 2017 (for 1st and 2nd

phases)

3.5 m3/s in 2017 (1st phase)

2.5 m3/s in 2017 (1st phase)

2.5 m3/s in 2017 (1st phase)

3 stations in 2017 (1st phase)

2 reservoirs in 2017 (1st phase)

Quarterly project monitoring reports

submitted by ONEE, Bank supervision

reports

Reports and statistics of MENEE and

other Ministries concerned

Mid-term Review Report and Project

Completion Report (PCR)

Risks

- Grouping of ONE and ONEP into a single

entity.

- Significant delay in procuring the

necessary land.

- Failure to maintain and renew water

distribution and sanitation networks.

Mitigation Measures

- Mitigation measure stated in Act No. 40-

09 related to continuity of activity.

- Choice of itinerary of pipes and location

of works (outside urban centres, low-value

land).

2.1. One pre-treatment station

constructed downstream from the Al

Massira dam.

1. 2. Flow of pre-treated water.

- NA

3.5 m3/s in 2017 (including 0.7 m3/s

for OCP’s needs).

- Implementation of the DWSS sector

stakeholders’ (ONEE (Water Branch) and

Board) action plans for extending the

water distribution and sanitation networks

and improving the management conditions

of this infrastructure.

KE

Y A

CT

IVIT

IES

COMPONENTS RESOURCES

1. Strengthening of the DWSS of the city of Marrakech and neighbouring urban centres

1.1 Construction of a water intake structure.

1.2 Construction of a pre-treatment station (de-silting).

1.3 Construction of a treatment station.

1.4 Construction of 3 pumping stations and 2 loading and storage reservoirs.

1.5 Laying of about 113 kms of water supply conduit (pre-treated and treated water).

2. Technical support

2.1 Contractors’ working design validated.

2.2 Acceptance reports signed, attachments of works completed validated and monitoring reports drafted.

RESOURCES (in UA Million)

- ADB Loan: UA 122.2 M.

- AFD Loan: UA 45.6 M.

- Moroccan part (ONEE & OCP): UA 44.3 M.

1 To maintain a 100% access rate in urban areas, more has to be done to satisfy the water needs of the additional population and the water needs of new tourist and industrial activities programmed by 2030.

Page 7: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

v

PROJECT IMPLEMENTATION SCHEDULE

1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12

Loan approval by the Board

Signature of the loan agreement

Effectiveness of the loan agreement

1- TECHNICAL SUPPORT

Preselection of consulting firms

Consultation of consulting firms selectedBid appraisal

Contract award

Execution of services

Preparation of the completion report

2-STRENGTHENING OF DWSS SYSTEMS

Raw water intake

Consultation of contractors

Bid appraisal

Contract award

Works execution

Works acceptance

De-silting plant

Consultation of contractors

Bid assessment

Contract award

Works execution

Works acceptance

Equipment and GC (de-silted water)

Consultation of contractors

Bid appraisal

Contract award

Works execution

Works acceptance

De-silted water piping

Consultation of contractors

Bid appraisal

Contract award

Works execution

Works acceptance

Treatment plant + PS

Consultation of contractors

Bid appraisal

Contract award

Works execution

Works acceptance

Treated water piping

consultation of contractors

Bid appraisal

Contract award

Works execution

Works acceptance

Equipment and GC treated water)

Consultation of contractors

Bid appraisal

Contract award

Works execution

Works acceptance

Remote management

Consultation of contractors

Bid appraisal

Contract award

Works execution

Works acceptance

Electric line

Consultation of contractors

Bid appraisal

Contract award

Works execution

Works acceptance

3- PROJECT COMPLETION

ONEP's completion report

Bank's completion report

20172012 2013

Item2014 2015 2016

Page 8: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

1

REPORT AND RECOMMENDATION OF MANAGEMENT TO THE BOARD OF DIRECTORS

CONCERNING A PROPOSAL TO AWARD A LOAN TO MOROCCO FOR THE MARRAKECH

REGION DRINKING WATER SUPPLY PROJECT

Management submits the following reports and recommendations concerning a proposal to award a

loan of EUR 120 million and USD 37 million (about UA 122.2 million) to the National Electricity and

Drinking Water Authority (ONEE) for the financing of the Marrakech Region Water Supply Project in

Morocco.

I. Strategic Thrust and Rationale

1.1. Project Linkages with the Country Strategy and Objectives

1.1.1 The new national water strategy in Morocco (Annex A) is based on three thrusts: (i) meeting

water needs and supporting the socio-economic development of the country; (ii) appropriate use and

management of water resources; and (iii) sustainable use of water. This strategy seeks to strengthen

the national water sector policy, by focusing on: (i) far more ambitious objectives for sustainably

meeting the country’s water needs and offsetting the effects of global warming; (ii) a radical change in

behaviour concerning the use and management of the resource through an integrated management of

demand and the resource; and (iii) fostering genuine long-term management of water (national

visibility, political commitment, public and private financing). This new water strategy will help to

support Morocco’s long-term development by meeting the requirements of economic growth and

accompanying major projects initiated while protecting the country from the effects of global

warming.

1.1.2 The projects recommended in this national strategy include the North-South Water Transfer

Project to Support the Socio-economic Development of the Central and South Basins which aims to:

(i) strengthen the spirit of solidarity among the Kingdom’s basins by harnessing the unused excess

waters of the northern basins; (ii) guarantee and ensure secure drinking water supply of strategic

towns such as Marrakech (one of the country’s main tourist destinations); (iii) restore the water

balance of certain basins especially the Oum Er Rbia basin and (iv) enhance the region’s developed

agricultural zones.

1.1.3 The Marrakech region, targeted by this project, is situated in the Tensift basin which benefits

from water transfers from the Oum Er Rbia basin. Water is now transferred through the Rocade canal

which, although chiefly intended for agricultural needs, also contributes to the drinking water supply

of Marrakech city. This transfer of water from the Oum Er Rbia water basin to the Tensift basin will

be strengthened under this project by the construction of the pipeline from the Al Massira dam. This

complementary input from the Oum Er Rbia basin was validated by the Oum Er Rbia Water Basin

Agency (ABH) during preparation of the Water Resource Development Master Plan (IWRMMP),

approved in 2011.

1.1.4 In line with the national strategy and the IWRMMPs of the relevant water basin, the strategic

plan of ONEE (Water Branch), the main actor in drinking water and sanitation infrastructure, focuses

especially on the following three thrusts: (i) ensuring widespread access to drinking water for the

population as a whole; (ii) active intervention in the liquid sanitation sector; and (iii) sustainability and

safeguarding of existing infrastructure. The project is consistent with the third thrust of ONEE’s

(Water Branch) strategy relating to the sustainability and safeguarding of existing infrastructure.

1.1.5 The safeguarding of water resources is also among the priorities of the OCP strategy. This

major concern led the Authority to establish a policy to, among others, optimize its use of water

resources. Optimizing the use of water resources entails not only optimizing water consumption

specifically but also preserving ground water resources and replacing them with surface water or even

non-conventional resources.

Page 9: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

2

1.1.6 The project is aligned with Pillar II of the Bank’s assistance strategy in Morocco for the

2012-2016 period aimed at supporting the development of green infrastructure. It is also in keeping

with the Bank’s medium-term strategy (2008-2012) which prioritizes the infrastructure sector the

Bank’s Integrated Water Resource Management Strategy and its draft long-term strategy for 2013-

2022.

1.2. Justification for Bank Intervention

1.2.1 The Marrakech region is experiencing significant economic development and has tremendous

potential (tourism, phosphates, etc.). However, the lack of water impedes its economic and social

development. The project addresses this concern by providing supplementary resources that can meet

the region’s drinking and industrial water needs up to 2030, while ensuring for Marrakech additional

secure supplies of drinking water, which is currently obtained from a single arrival point.

1.2.2 The project was designed to meet the priority needs expressed by ONEE (Water Branch) in

its draft Programme Contract with the Moroccan State for the 2012-2016 period in view of the

imminent saturation of the water production and supply system of the towns concerned (2017). The

Bank was selected to participate in the financing of the project mainly because of its proven

comparative advantage in implementing this type of project (with fairly urgent operations covering

medium and large urban centres). This advantage is well- illustrated by recent projects financed by the

Bank in the drinking water and sanitation sector in Morocco. In recent years, its performance for

completed projects improved significantly with sustained coordination from the Bank’s Country

Office in Morocco (MAFO).

1.2.3 Primarily, the project will benefit the people of Marrakech, particularly the underprivileged

residents of peri-urban areas and the population of nearby urban and rural centres. In terms of water

supply, it will enhance and improve the quantity and quality of the drinking water supply of about 3

million people in Marrakech and nearby centres, and enable ONEE (Water Branch) to meet the

increase in demand induced by the natural growth and living standards of the population of the areas

concerned by 2030. Furthermore, the project will help to meet the Morocco Phosphates Authority’s

pre-treated (de-silted) water needs for its Béni Guérir production site (located on the road between the

Al Massira dam and Marrakech). It will also contribute to the achievement of Millennium

Development Goals Indicator 7 related to access to safe drinking water, since the rate of access to

drinking water in rural areas in Morocco will exceed 95% by 2016 compared to 92% in 2011.

1.3. Aid Coordination

1.3.1 The Moroccan Government has made significant efforts to ensure aid coordination. It intends

to set up a Geographic Information System (GIS) to monitor in real time the interventions of the

different Technical and Financial Partners (TFP) by geographic zone, sector and amount. Donor aid is

fairly well aligned with the Government’s strategic priorities and no parallel project implementation

unit exists. Several bilateral and multilateral donors are involved in the drinking water and sanitation

sector in Morocco. The key ones are the African Development Bank (ADB), World Bank (WB),

European Investment Bank (EIB), European Union (EU), French Development Agency (AFD),

German Development Agency (KFW), German Cooperation Agency (GIZ), Belgium, Spain, Italy,

Japanese International Cooperation Agency (JICA), the Islamic Development Bank (IsDB), AFESD

and FSD.

1.3.2 Moreover, ONEE (Water Branch) has an investment programme under its Programme

Contract with the Moroccan State for the 2012-2016 period. It finances this programme with the

assistance of its traditional donors. Donor coordination is done through a thematic group co-chaired

by AFD and EU. This thematic group meets regularly (2 to 4 times per year) in Rabat to, among

others, discuss sector trends, especially the country’s policy and strategy and each donor’s

Page 10: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

3

intervention strategy and programme of activities so as to better coordinate and harmonize their

respective assistance in the drinking water and sanitation sectors. The Bank regularly participates in

these meetings since MAFO was opened in 2006.

II. Project Description

2.1. Project Components

The project will help to meet the drinking water and industrial water needs of the Marrakech region by

2030 by tapping surface water from the Al Massira dam. The project components are presented in the

following table. Table 2.1

Project Components and Costs

Name of Component / Sub

Component

Estimated Cost

(UA Million)

Description of Components

1 Development of water

production, storage and supply

infrastructure

Sub-component 1.1 : “de-silted

Water” part

108.00 Construction of a raw water intake structure from the

Al Massira dam (capacity = 7 m3/s) ;

Laying of raw water supply conduit (diametre 2,000

mm, linear distance about 3 kms) ;

Construction of a de-silting plant (capacity = 3.5

m3/s) ;

Laying of a desilted water conduit (diameter: 1,600 to

2,000 mm, linear distance of about 45 kms) ;

Construction of 2 reservoirs (R1, RMC1) ;

Construction of 2 pumping stations (SR1 and SR2).

Sub-component 1.2: “Treated

Water” part

100.85 Construction of a treatment station (capacity = 2.5

m3/s);

Laying of a treated water aqueduct (diametre of 1,300

to 1,800 mm, linear distance of about 65 kms);

Construction of 3 reservoirs (R2, RMC2 and North

reservoir);

Construction of an SR3 pumping station.

2 Technical support 3.25 Studies, works control and supervision

Total including contingencies 212.10

2.2. Technical Solutions Retained and Other Alternatives Explored

2.2.1 The water needs of the project zone are currently supplied from the Hassan 1st – Sidi

Driss and Wirgane – Lalla Takerkoust dams located in the south-west of the town of Marrakech and

ground water in the Haouz and Bahira water tables. A 2,100 l/s treatment station treats surface water;

its rated capacity can be increased to 2,400 l/s (overload capacity). After extension works, to be

completed at end-2012 (under the 10th

DWS Project financed by the Bank) the rated capacity of the

treatment station will rise to 3,100 l/s with an overload capacity of 3,400 l/s. Ground water resources,

for their part, are tapped through a series of boreholes whose current flow rate of 320 l/s will

eventually fall to 160 l/s, based on projections made.

2.2.2 Water balance estimates show a deficit in the project area from 2015. It has, therefore,

become essential to mobilize new resources to support this region’s development, ensure widespread

access to drinking water in urban and rural areas and meet OCP’s industrial water needs. An

additional annual volume of about 96 million m3 will be needed to meet the region’s needs by 2030.

2.2.3 Considering the volume of water needed to address drinking water needs in the project area

and the absence of sufficient water in the Tensift basin, the different departments concerned by the

Page 11: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

4

issue (MEMEE, ONEE (Water Branch), ABH, OCP, etc) weighed all possible options and concluded

that the regulated waters of the Al Massira dam (Oum Er Rbia water basin) should be mobilized as

part of the project to transfer water from basins in the North to those in the Centre and South (see

paragraph 1.2 above). Thus, volumes of 100 million m3 and 18 million m

3 from the Al Massira dam

were allocated each year for the region’s drinking water needs and OCP’s industrial water needs

respectively (see map attached as Annex IV).

2.2.4 This solution and the other actions retained (improving distribution network yields, re-using

recycled wastewater to water green spaces and golf courses, limiting the tapping of ground water and

making it a strategic reserve) are fully in line with the national water strategy. This solution also

offers an additional guarantee of water supply to Marrakech city since it creates a second water

arrival point (to the North of the city) in addition to the existing one in the South (at the existing

treatment station).

2.2.5 The alternative solution explored concerns strengthening the current treatment station which

has been extended twice already and is supplied by the “Rocade” canal primarily intended for

irrigation. This solution was rejected for three reasons: (i) the drinking water quota from the canal has

been exceeded; (ii) the existing station cannot be further extended because the land is in an area of

high urban and tourism development; and (iii) it would be risky to concentrate all Marrakech’s water

resources in a single point (the existing station), in case of accident.

2.2.6 Once the decision to transfer water from the El Massira dam was taken, the preliminary and

detailed design studies and environmental impact assessment of the project were prepared by

independent consulting firms and approved by ONEE (Water Branch) and OCP. The solutions

retained were based on these studies and represent rational and optimal technical solutions to cover

the deficits at least cost. These technical solutions are detailed in Annex C.3.

2.3 Project Type /Instrument

This is an investment project to be financed with ADB, AFD, ONEE and OCP resources.

2.4. Project Cost and Financing Mechanisms

2.4.1 The total project cost, net of taxes and customs duties, is estimated at UA 212.10 million,

comprising UA 155.50 million in foreign exchange and UA 56.60 million in local currency. It

includes a provision of 7% for physical contingencies, 2% for foreign exchange price escalation and

3% for local currency price escalation. This estimated cost is based on the preliminary design studies

dated September 2011.

Table 2.2 Estimated Cost by Component (in UA million, net of taxes and customs duties)

Components Foreign

Exchange Cost

Local

Currency Cost

Total Cost %

Foreign

Exchange

DWS of Marrakech and nearby urban

centres

139.90 51.50 191.40 73.1

Technical support 3.00 0.00 3.00 100

Total base cost 142.90 51.50 194.40 73.5

Provision for physical contingencies 9.80 3.60 13.40 -

Provision for price escalation 2.80 1.50 4.30 -

Total Project Cost 155.50 56.60 212.10 73.3

Page 12: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

5

2.4.2 The project will be jointly financed by the Bank, AFD, ONEE and OCP2. The Bank’s

financing will be EUR 150 million, or about UA 122.20 million (the exchange rate in August

2012 was UA 1 = EUR 1.22788). This amount represents about 57.6% of the estimated project cost

ADF’s contribution will be EUR 56.00 million, or 21.5%, while ONEE and OCP will finance 20.9%

of the total project cost. Mobilization of the financing to be provided by AFD will be a condition of

the Bank loan, based on the fact that the project can only achieve its development objectives if all

expected works are completed.

Table 2.3 Sources of Financing (in UA million)

Sources of Financing Foreign Exchange

Costs

Local Currency

Costs

Total Cost % total

ADB 122.20 0.00 122.20 57.6

AFD 33.30 12.30 45.60 21.5

ONEE and OCP 0.00 44.30 44.30 20.9

Total Project Cost 155.50 56.60 212.10 100

Table 2.4 Project Cost by Expenditure Category (in UA million)

Expenditure Categories Foreign

Exchange

Cost

Local

Currency Cost

Total Cost % Foreign

Exchange

Goods 47.90 5.30 53.20 90.1

Works 92.00 33.70 125.70 73.2

Services 3.00 0.30 3.30 88.9

Miscellaneous costs (*) 0.00 12.20 12.20 0.0

Total base cost 142.90 51.50 194.40 73.5

Provision for physical

contingencies

9.80 3.60 13.40 73.2

Provision for price escalation 2.80 1.50 4.30 64.6

Total Project cost 155.50 56.60 212.10 73.3

(*) Procurement of the necessary land for works and laying of conduits.

Table 2.5 Expenditure Schedule by Component (in UA million)

Components 2013 2014 2015 2016 2017

DWS for Marrakech and nearby

urban centres

9.60 38.30 57.40 57.40 28.70

Technical support 0.10 0.60 0.90 0.90 0.50

Total base cost 9.70 38.90 58.30 58.30 29.20

Provision for physical

contingencies 0.70 2.70 4.00 4.00 2.00

Provision for price escalation 0.20 0.90 1.30 1.30 0.60

Total Project Cost 10.60 42.50 63.60 63.60 31.80

2.5. Project Area and Beneficiaries

2.5.1 The project area covers three poles: (i) the Marrakech pole comprising the city of Marrakech

and the centres of Tamnsourt, Tameslouht, Tnine Loudaya, Kettara, Sid Zouin, as well as the rural

population of Marrakech Prefecture; (ii) the Al Haouz pole comprising the centres of Aït Ourir,

Amezmiz, My Brahim, Tahannout, Lalla Takarkoust, Ghmate and sidi Abdellah Ghiate, and the rural

population of Al Haouz province; and (iii) the Rehamna pole comprising the towns of Ben Guerir and

Sidi Bou Othmane, the Skhour Rhamna centre and the rural population of the Sidi Bou Othmane and

Rhamna administrative circles.

2 The Moroccan Party’s (ONEE + OCP) share of financing is estimated at about 21% of the project cost, net of taxes. After adding taxes estimated at

20% of the project cost, the financing to be borne by the Moroccan Party stands at about 34% of the project cost, inclusive of taxes.

Page 13: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

6

2.5.2 Administratively, the project area comprises 5 districts, 3 municipalities, 12 urban centres, 74

rural communes and 1,640 douars3. Marrakech city, considered as the core of the project area, is

experiencing an unprecedented tourism and urban boom whose impact is reflected, among others, in a

6.5% annual increase in drinking water consumption compared to a national average of 2%.

2.5.3 The project beneficiaries, about 2 million people in 2015, will increase to about 3 million by

2030, over one-third of whom will live in rural areas. They will be mainly concentrated around the

city of Marrakech (over 50%) and distributed among the three above-mentioned geographic poles.

The main socio-economic characteristics of beneficiaries are given in Annex B8 (Social Analysis).

2.6. Participatory Approach for Project Identification, Design and Implementation

2.6.1 During Bank preparation and appraisal missions, several meetings were held at central and

local level, involving all stakeholders – ONEE (Water Branch), OCP, RADEEMA, ABH, and the

MEMEE Water Department to note their respective concerns and take them into account in the project

design and implementation.

2.6.2 In addition to the different sensitization and communication campaigns organized by ONEE

(Water Branch) and RADEEMA (as part of the preparation of its master plan) and through which

people were informed about the project characteristics and objectives, ONEE (Water Branch) will also

ensure, prior to works start-up, that the local residents are informed through their communes and/or

local authorities, about the nature of works, possible damages and the corresponding compensation

and about the need to organize themselves in order to enjoy benefits (part-time jobs, etc.).

Consequently, contractors must maintain the same level of consultation with the local communities

throughout the duration of works (a mandatory works contract clause. The communication focus

mainly on: (i) the nature and period of works; and (ii) precautions to be taken regarding the movement

of machines.

2.6.3 Information, education and sensitization campaigns are also necessary to avoid water wastage

and pollution. These campaigns will focus on: (i) promoting a culture of respect of water and positive

behaviour towards water use; and (ii) fostering positive attitudes and behaviour towards hygiene.

Direct on-site actions aimed at different target groups constitute a preferred method by while

communicating the following messages: “Drinking water is necessary for good health, it is a common

right; use it but don’t waste it”. Target groups are: (i) children and youth (schools, summer camps, site

visits) ; (ii) women (women’s centres, associations, youth centres) ; (iii) subscribers (subscriber’s

guide) ; (iv) press agents (press day, dispatch of brochures) ; (v) public and private stakeholders; and

(vi) decision-makers, elected officials and other partners (information day). This sensitization

campaign will factor in a variety of socio-cultural data including people’s manners, customs and

habits and their propensity to take part in community actions.

2.7. Bank Group Experience Reflected in Project Design

2.7.1 The implementation performance of recent projects with ONEE (Water Branch) is deemed

satisfactory overall. ONEE (Water Branch) clearly understands Bank policies and procedures and the

Authority conducted quality studies. The key recommendations of previous project completion

reports, especially the last four (5th, 6th, 7th and 8th), are summarized as follows: (i) strengthen

technical support and make relevant provisions before the commencement of works right to project

completion; and (ii) strengthen project supervision missions (especially in terms of number of experts)

and guarantee better project oversight. These recommendations were taken into account in the most

recent projects being financed by the Bank in the sector (9th

and 10th

DWSS Project and the Rabat-

3 Douar: ‘Official’ local administrative unit, comprising a group of individuals actually or potentially having the same territory (used in official

censuses). The average size of a douar is about 500 inhabitants.

Page 14: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

7

Casablanca DWS Project). This will also be the case for this project with the assistance of the Bank’s

Country Office in Morocco (MAFO). In 2005, the Bank’s Evaluation Department conducted a post

review of the performance of operations in Morocco for the period 1996-2004, concluding that loan

operations performed well (physical investments). Unlike some autonomous electricity and drinking

water distribution boards which still have uncontrolled costs, ONEE (Water Branch) projects,

especially those concerning drinking water production and supply of major urban centres (the case of

this project), experience no return-on-investment problems

2.7.2 The eleven Bank-financed projects (eight have been completed while three are ongoing) have

contributed to improve drinking water mobilization, supply and distribution as well as sanitation and

wastewater treatment services. The Water Sector Adjustment Programme (Water SAP) helped to

establish an institutional and regulatory framework of integrated water resource management to

address the challenges of ensuring secure supplies of drinking water throughout the country. These

projects target key towns in the Kingdom distributed nationwide (Rabat, Casablanca, Marrakech,

Tanger, Tetouan, Béni Mellal, Settat, Kénitra, Essaouira, Ouarzazate, Khouribga, Tan Tan) and have

contributed to safeguarding drinking water access in rural areas, which rose from 14% in 1990 to

about 92% at end-2011, and the sanitation access rate which rose from under 50% in 1990 to over

65% currently.

2.7.3 Based on these achievements, the main lessons learned from the partnership between the

Bank and ONEE (Water Branch) concern the need to build the project monitoring/evaluation and

post-evaluation capacity of ONEE staff (water branch) especially those in regional directorates. In that

context, a partnership project between OPEV and the Audit and Organization Directorate of ONEE

(Water Branch) was initiated after OPEV’s mission in December 2009 which led to the adoption of an

action plan. The proposed actions of that plan aim to assist ONEE (Water Branch) to design an

evaluation policy and a system of internal organization and management of review missions, and to

build monitoring/evaluation and post-review capacity.

2.8. Key Performance Indicators

2.8.1 In the short-term (2017), the project outcomes will be toguarantee an additional flow of 3.5

m3/s of raw water (2.5 m

3/s treated) pumped, treated and supplied to the Marrakech region from the Al

Massira dam in the first phase, with possibility of extension to 7 m3/s in the post-project period.

2.8.2 In the medium term (2020), the project will help to maintain the drinking water access rate at

100% in urban areas (towns concerned) and increase it in rural areas (provinces concerned) from 79%

to 95% (Rehamna), from 84% to 91% (AL Haouz) and from 94% to 96% (Marrakech). The project

will maintain the drinking water access rate at 100% in urban areas by supplying an additional

quantity of drinking water that matches the rising needs in the Marrakech region. In other words, if the

project is not implemented, the drinking water access rate in the area concerned will drop by a few

points. The project will also contribute to significantly reduce the rate of infant mortality (caused by

water-borne diseases) from 40 deaths per 1,000 infants currently to 15 deaths per 1,000 in 2020.

Lastly, the project will guarantee the industrial water needs of OCP’s Ben Guerir site, which will not

only ensure the proper operation of the site but also enhance the region’s economic development

(through the mining industry).

2.8.3 In the long run (2030), the project’s key performance indicator is the rate of access to

drinking water in urban and rural areas, and particularly in the project area. While the urban access

rate at national level will be maintained at 100%, the rural access rate will increase from 92%

currently to 100% in 2030.

Page 15: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

8

III. Project Feasibility

3.1. Economic and Financial Performance

Table 3.1: Key Economic and Financial Data

IRR : 7.1% - NPV: MAD 577 million

ERR: 10.7% - NPV: MAD 684 million

Note: See Annex B7 for detailed calculations

3.1.1 This is an anchor project aimed at strengthening existing facilities for the production and

supply of drinking water to the urban and rural populations of Marrakech region (Marrakech, Al

Haouz and Rehamna provinces) and supply of pre-treated water to Morocco’s Phosphates Company

(OCP). Apart from the expected value added of an original sharing of the ONEE-OCP financing

package, the project will generate many financial and economic benefits. It will enable ONEE (Water

Branch) to improve its productive base and financial indicators, implement its development strategy

aimed at ensuring secure drinking water supply to Marrakech city and nearby areas (one of the largest

development poles in the Kingdom in terms of tourism) and meet at least cost the drinking water

needs of rural communities along the water conduit route and the pre-treated water needs of OCP.

This confirms the synergy among national economic entities and generates economies of scale with

immediate impact on the profitability of the Authorities. There are many project externalities: creation

of part-time and full-time jobs, catalytic role in new tourist, agricultural and industrial projects

(mining industries), generation of economic activities in rural areas, optimization of mining activities,

and improvement of the living environment and conditions of urban and rural populations.

3.1.2 The project financial internal rate oif return (FIRR) is 7.1% and the net present value

estimated at MAD 577 million. Sensitivity tests were conducted based on the following situations:

Table 3.2: Sensitivity Tests of Financial Internal Rate of Return

Event Impact on FIRR IRR NPV

(in MAD million)

10% increase in investment cost : 6.7 % 438

10% drop in demand : 6.8 % 470

10% increase in energy cost : 6.9 % 494

Combination of the three events : 6.4 % 343

10% increase in demand : 7.7 % 791

3.1.3 The different IRR sensitivity tests for poor performance scenarios show levels that are

above the weighted average investment rate estimated at 5.5%. A combination of three events – 10%

increase in investment cost, 10% drop in demand and 10% increase in energy cost – causes a

reduction of the IRR by 6.4%. Where performance matches project expectations and demand

increases by 10%, the IRR rises to 7.7%.

3.1.4 The project financial rate of return is acceptable, helping to service the debt and generate a

surplus. It appears fair for a project intended mainly for urban consumers. However, this return is

lowered by the fact that the project primarily constitutes a back-up and security basis for the part

reserved for Marrakech city. The project’s rated capacity will be used gradually manner and optimized

in 2020/2025. This is a capital-intensive project. Its components are inextricably linked, which

precludes partial or gradual implementation. The return is therefore diffuse and spread over time.

3.1.5 The economic rate of return (ERR) is 10.7 %. It is calculated on the basis of the same

financial return data after a 0.9% correction of local currency costs, application of the same foreign

exchange investment costs, 1.2% correction of the economic value of water, taking into account of

quantifiable benefits represented by the value of work-days generated during project implementation

Page 16: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

9

and the water-fetching chore in terms of hours saved and used for more useful purposes (particularly

in rural areas) and lastly, health budget savings.

3.1.6 The economic rate of return is also satisfactory considering the nature of the project. The fact

that due consideration was given to several hard-to-quantify benefits confirms this rate of return. The

project will contribute to consolidate the structural foundations and financial and economic

management parameters of ONEE (Water Branch). It is financially sound and economically viable as

refelected in the above rates of return and the trend of ONEE’s (Water Branch) structure and financial

management parameters.

3.2. Environmental and Social Impact

Environment

3.2.1 The project is classified under the Bank’s environmental and social category 2. It was the

subject of an Environmental Impact Study (EIS) in January 2011 and an Environmental and Social

Management Plan (ESMP) that was published on the Bank’s website on 30 March 2012. Thus, it will

not lead to any significant irreversible and negative environmental and social impact or one that

might significantly affect environmental and social components considered as sensitive by the Bank

and the country. Indeed, the project only has specific impacts on project sites which have been

minimized by applying appropriate mitigation measures”. The analysis of project components and

activities, especially earthworks, civil engineering works, and the putting in place of a suitable sludge

management system at the station show that the project has no significant negative impact. Added to

that is the project’s expected positive impact both from a social and public health standpoint. It was

agreed that the Environment Division under ONEE’s Water and Sanitation Directorate will implement

the planned mitigation measures, in collaboration with the works supervision officials of the Technical

and Engineering Directorate (DTI).

Climate Change

3.2.2 Climate change in Morocco mainly affects already scarce water resources owing to the semi-

arid climate of the region, characterized by very low rainfall that is also very irregular in time and

space. Climate change, exacerbated by extreme phenomena, has resulted in increasingly longer dry

spells interspersed with episodes of brief and violent rains that have weakened water resources. In the

last three decades, the Kingdom has experienced 20 dry years with 3 dry spells each lasting four

consecutive years resulting in an overall drop of water resources of about 10 to 20%.

3.2.3 This aspect was taken into account in the project by first ensuring that the Water Basin

Agency (ABH) efficiently manages the available water of the Al Massira dam from which the

Marrakech region DWS will be enhanced and which offers the guarantee of project sustainability. The

ABH manages a series of dams4 upstream Al Massira intended to regulate all water resources and

guarantee a fixed reserve for drinking water needs (representing an absolute priority over other water

uses). Second, some project activities incorporate water saving processes such as water recycling in

the treatment station. Apart from the project, the country has an adaptation strategy being

implemented in zones of high water stress which, among other things, is based on the treatment and

re-use of wastewater to water golf courses; the promotion of drip irrigation; the improvement of the

efficiency of the drinking water distribution system with a national output objective of 75% in 2015 so

as to preserve substantial volumes of treated water.

4 My Youssef, Tioughza, Ait Segmine, Amsfrane, El Ouidane, Bou Inougoudane, Tagzirt, Ait Messaoud, Dcher El Oued,Taskdert, Tajemout,

Imezdelfane dams.

Page 17: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

10

Gender

3.2.4 The project seeks to improve the living conditions of the population, particularly those of

women (51%). Gender mainstreaming in this project is aimed at ensuring that the needs and interests

of various social groups are taken into account and that the latter are involved in managing certain

structures. Gender has to do with social relations and the distribution of roles between men and

women. Since the two social groups are homogenous, gender mainstreaming takes into account the

diversity of project stakeholders. Lastly, to comply with the Moroccan Government’s policy

guidelines and Bank’s guidelines, the project will adopt a gender-based approach to ensure that the

needs and interests of various groups are taken into account during the project implementation phase

and beyond.

3.2.5 The availability of water in sufficient quantity and on a continuous basis will enable women

to seize opportunities offered by new projects in the tourism, industry and trade sectors or to create

their own income-generating activities (IGA) in synergy with other programmes (for example, the

National Human Development Initiative – NHDI). This will contribute to increase the number of

active women and thus bridge gender disparities in economic activities. The project area has major

tourism projects that are growing (the region accounts for 35.2% of the total number of hotel stays in

the country) and many business enterprises and services developing around these activities, known to

use high levels of female labour. This provides great opportunities to effectively contribute to the

advancement of gender equality (GE) in targeted zones in terms of involvement in economic life.

3.2.6 On the institutional front, Morocco has several instruments on equitable and sustainable

human development: (i) the National Strategy for Gender Equity and Equality by mainstreaming

gender in development policies and programmes, prepared by the Ministry of Social Development and

the Family and, (ii) the National Human Development Initiative (NHDI). These instruments provide

the project with a very favourable framework to give women and men equitable access to benefits and

reduce gender disparities.

Social

3.2.7 By virtue of its location and its key objective of safeguarding the water supply of the

Marrakech region, the project targets an area that is densely populated, especially during the tourist

season. It will contribute to improve the living conditions of the people, reduce poverty and provide

sufficient quantities of water to industrial and tourism enterprises for their activities. The project area

is a key tourism zone in the country and hosts one of the largest sites of the mining industry (OCP’s

Ben Guerir site which benefits directly from the project). It will help to create 43,935 direct and

indirect jobs in the tourism, construction, handicrafts and industrial sectors.

Poverty

3.2.8 With regard to poverty reduction, the project will contribute to improve the living conditions

of the population (mostly in peripheral neighbourhoods and nearby rural areas). The region has five of

the poorest provinces in the country. Except for the city of Marrakech (3.5%), the poverty index is

about 11.1% in El Kelâa des Saghna province and 14.9% in El Haouz province, whereas the national

average does not exceed 8.9%. Pockets of poverty persist in these provinces, with wide inter-

neighbourhood disparities (rates higher than the national average). Rural-urban migration is high in

the region and these job-seekers have settled on the outskirts of the city or in certain intra-urban

districts. The region lacks sufficient basic infrastructure for drinking water supply. By 2020, the

project will help to raise the drinking water access rate to 95% on average.

Page 18: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

11

Health

3.2.9 On the health front, although drinking safe water prevents diseases such as cholera, this has a

marginal effect on endemic diseases which are transmitted by contaminated water and dirty hands.

The safeguarding of drinking water supply will provide households with sufficient quantities of water

to enable each to at least wash their hands before eating and after going to the toilet.

3.2.10 This project will procure several health benefits in the region: (i) better conditions of hygiene:

the time saved from water-fetching chores enables women to devote more time to their children; (ii)

fewer water-borne diseases: washing of hands with soap can reduce by about 40% the incidence of

diarrhea-related diseases, a major cause of infant morbidity and mortality. Currently, 16.3% of under-

five children suffer diarrhea attacks at least twice each year. There are still many cases of waterborne

gastro-enteritis in the region (241 cases in 2010), with several cases of typhoid and hepatitis A. This

health improvement will be greater if water is brought to homes; (iii) drop in the infant mortality rate

to 15/1000 live births by 2020 against 29/1000 currently; (iv) drop in maternal mortality by 2020 to

50/100,000 against 112/100,000 currently. Having water and better hygiene during pregnancy and

delivery means that the chances of post-natal infections are reduced and in the long run, women’s

reproductive health improves; (v) drop in the mortality and morbidity rates of the elderly, disabled

and HIV/AIDS carriers: they are more sensitive than others to disease and it is often difficult for them

to have access to water; and (vi) households’ spending on health drops to 25% in 2020 compared to

57.4% at present.

Education

3.2.11 When children spend hours helping their mothers to look for water, they often no longer have

time for education. Furthermore, if their parents become ill, girls often stay at home to look after

them. This project will help to halve the school drop-out rate in the region.

3.2.12 The absence of water and sanitary facilities in schools and the failure to build separate

gender-specific facilities are determining factors in girls dropping out of school. Access to adequate

sanitary facilities has a direct impact on their schooling and safety. This project will help to raise

school enrolment rates in the region to 100% for primary education in 2020 (97.2% currently) and

85% for secondary school (62% in 2011).

Millennium Development Goals (MDG)

3.2.13 The project will help greatly not only to improve the local population’s hygiene and living

conditions but also to achieve the MDGs. The 3rd

report of the Planning High Commission on the

MDGs concluded that Morocco has to speed up the current implementation of the following goals: (i)

control of make-shift housing; (ii) school enrolments; and (iii) access to drinking water.

Expropriation and Involuntary Resettlement

3.2.14 No resettlement operation is planned for this project. Procedures for expropriation for public

utility are already in progress for the private land identified for the treatment station and raw water

conduit (the landowners are already informed and are being sensitized to sell their land the cost of

which will be included in the project cost). This is in accordance with Act No. 7-81 promulgated by

Dahir No.1-81-254 of 11 Rajeb 1402 (6/05/1982) relating to expropriation for public utility and

temporary occupancy (see Annex B8) that governs expropriation procedure in Morocco and that was

deemed consistent with the relevant Bank requirements5.

5 Act No. 7-81 promulgated by Dahir No.1-81-254 of 11 Rajeb 1402 (6/05/1982) relating to expropriation for public utility and temporary occupation

were also enforced during recent DWSS projects in Morocco.

Page 19: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

12

IV. Implementation

4.1. Implementation Arrangements

National Electricity and Drinking Water Authority (ONEE)

4.1.1 The grouping of ONE and ONEP into a single public establishment called “National Electricity

and Drinking Water Authority” (ONEE), subject of Act No. 40-09, sought to harmonize the new water

and energy strategies and ensure the continuity and rational management of the water and electricity

public service by adopting action plans to guarantee their availability.

4.1.2 Act No. 40-09 became effective on 24 April 2012 after expiry of the six-month period as from

the date of its publication in the Official Gazette of 24 October 2011. Decree No. 2-12-89 of 5 April 2012

to implement the above law specified the composition of the Board of Directors and headquarters of

ONEE (published in Official Gazette No. 6040 of 19 April 2012). The General Manager of ONEE will be

appointed by dahir, pursuant to the regulations in force (organic law No. 02-12 promulgated by Dahir

No.1-12-20 of 17 July 2012 and published in Official Gazette No. 6066 of 19 July 2012)..

4.1.3 Act No. 40-09 set up mechanisms and guarantees to ensure continuity of activity given the

importance of the services managed by ONE and ONEP. In that regard, the law provides as follows:

- Subrogation : Section 15 of the law stipulates that ONEE shall be ‘subrogated to the rights

and obligations of ONE and ONEP pertaining to works, supplies and service contracts

and for all other agreements and conventions, especially financial ones, signed by ONE

and ONEP before the effective date of this law and not finally paid on that date. ONEE

shall pay for such contracts and conventions in the forms and conditions stipulated

therein”.

- Continuity of activity: This principle is enshrined in Section 16 of the law which provides

that “the establishment of ONEE after grouping ONE and ONEP into a single entity shall

not lead to the suspension of activities. This grouping in no way calls into question the

assets, rights, obligations, conventions and contracts, including those signed with staff

members, their representatives and third parties, as well as authorizations of any nature in

and out of Morocco and shall in particular have no incidence on third-party contracts

signed by ONE and ONEP, their subsidiaries and companies in which they have equity

participation with third parties”.

- Discharge by ONEE of the same missions and activities as the two merged

establishments: Act No. 40-09 repealed the instruments instituting ONE (dahir of 5

August 1963) and ONEP (dahir of 3 April 1972), except for sections related to the

missions of the two merged entities and their respective areas of intervention.

4.1.4 Furthermore, the Moroccan authorities indicated that to ensure the smooth performance of its

duties and implementation of the projects, ONEE will adopt a separate operational management by

specialty, that is, either electricity or drinking water. Thus, the operational departments (engineering,

procurement, finance, etc) of the former entities (ONEP and ONE) will continue to implement all existing

and programmed projects in their respective spheres (water or electricity).

Institutional Arrangements

4.1.5 ONEE (Water Branch) is the project executing agency.. It is very familiar with the Bank’s

procedures, having successfully implemented several Bank-financed projects. The Development Pole

Central Directorate implements and monitors the project through the Technical and Engineering

Directorate. It has sufficient material and human resources to implement the project on schedule. This

Page 20: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

13

Directorate will closely manage all technical aspects of the project in association with the Supplies

and Procurement Directorate for the procurement of goods, services and works, the Finance

Directorate for project accounts and financial management and general coordination with the Bank

and the Sanitation and Environment Directorate for monitoring measures to mitigate the project’s

impact on the environment. The Regional Directorate at Marrakech will provide support for the day-

to-day management of the project.

4.1.6 The Technical and Engineering Directorate, which oversees project technical management,

will designate a project coordinator who will implement and manage all components of the project.

Further, a consulting engineer will be recruited to supervise and inspect works under the component

related to project technical support.

Procurement Arrangements

4.1.7 All goods, works and consultancy services financed with Bank resources will be procured in

accordance with the Bank’s Rules of Procedure for the Procurement of Goods and Works (May 2008

version as revised in July 2012) or, as the case may be, its Rules of Procedure for the Use of

Consultants (May 2008 version as revised in July 2012) using the standard bidding documents of the

Bank. Through “Water Pole” structures namely, the Supplies and Procurement Directorate, ONEP

will be responsible for all procurements as described in detail in Annex B5. The resources, capacity,

expertise and experience of ONEE (Water Branch) are presented in detail as Annex B5. The

procurement plan was prepared and discussed with ONEE and will be finalized and adopted during

negotiations of the loan agreement.

4.1.8 Given the scope and nature of contracts to be financed by the Bank under this project, the

parties have agreed that all bidding procedures will be submitted for the prior opinion of the Bank.

The Borrower requested and obtained the Bank’s approval for advance procurement action (APA) for

consultancy services for technical support. This action will help to guarantee the presence of the

Consulting Engineer (CE) at project start-up and particularly during the evaluation of works-related bids

(especially for the water intake structure and treatment station that require proven expertise).

Disbursement Arrangements

4.1.9 Disbursements of the ADB loan will be made in accordance with the applicable provisions of

the Bank’s disbursement manual (2012 version). ONEE (Water Branch) will use the different

disbursement methods specified in that manual. During negotiation of loan and guarantee agreements, a

disbursement letter will be reviewed by both parties and forwarded to ONEE (Water Branch) once the

Bank approves the project.

Financial Management

4.1.10 ONEE (Water Branch) has a financial management system deemed highly reliable for all the

projects it implements. However, the Bank recommends measures for improving the periodic and

annual reporting of project financial information and audit opinions produced in line with the relevant

general conditions and specific requirements of the Bank and taking into account the Authority’s

accounting and financial procedures. Thus, the fiduciary risk assessment conducted in line with Bank

guidelines on project financial management concluded that initial fiduciary risk was moderate for the

Bank mainly because of financial reporting to the Bank. The satisfactory implementation of the

priority action plan for financial management detailed in Annex B4 (not a loan condition), will help to

achieve a low-level residual risk. Furthermore, since the ONE/ONEP merger can impact projects

financial management, the Bank asked to be notified of any re-organization of accounts/financial

services or change of procedures because it may undertake a supervision mission to ensure the

reliability of new arrangements in place for the financial management of projects financed.

Page 21: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

14

4.1.11 The project’s financial management will be based on the financial system of ONEE (Water

Branch) as a whole and, especially, the relative organization of the Finance Directorate and other key

Directorates or positions involved in resource management or supervision (Planning, Supplies and

Contracts, Management Supervision and Information System, Operations Oversight Agency, Internal

Audit and Organization). These Directorates have adequate, qualified and experienced staff. Since

ONEE is a public establishment endowed with moral personality and administrative and financial

autonomy, it is managed autonomously and subject to the principles and obligations of the

Commercial Code and the Finance Minister’s order on privatization of 20 December 2005 laying

down the management instruments of public establishments that are eligible to support supervision.

Thus, during project implementation, the public financial management system will not be used, except

for the timeliness of internal and external audits undertaken by other State audit bodies. Each year,

ONEE (Water Branch) implements a programme of activities budgeted for and approved by its Board

of Directors. It will also forward to the Bank an annual investment budget note, highlighting Bank-

financed projects.

4.1.12 ONEE (Water Branch) maintains the financial accounting (in accordance with Moroccan

accounting standards) and the cost and budgetary accounting of the entity integrated in the SAP CFI

module, whose principles and procedures are documented. Although ONEE (Water Branch) does not

keep separate accounts for each project, some items of information that can be reconstituted from

financial accounting and the cost and budgetary charges of ONEE will serve to compile (outside the

accounting framework) the project’s financial statement whose residual funds will be backed by

verifiable accounting data. ONEE (Water Branch) has a collection of detailed, documented and

updated procedures for all its operational activities (purchases, accounts-finance, human resources,

commercial, operation, stock, management oversight, etc.). If implemented, they will guarantee a

reliable control of expenditure commitment and justification, financial transactions, accounting entries

and safeguard financial data and ONEE (Water Branch) and project assets. The recent study to map

the risks of ONEE (Water Branch) and the measures considered by the Directorate will lead to a better

rationalization of the expenditure control chain. Internal audit will be performed both by the Internal

Audit Division based on its charter and procedures, and the Audit Committee. Being a public

establishment, ONEE is subject to the control of the Ministry of Economy and Finance (through the

Directorate of Public Enterprises and Privatization) or other authorized public auditors and State audit

institutions (IGF, Court of Auditors, etc.). A project technical and financial activity report will be

prepared quarterly based on the usual format. The financial part of the report will be backed by the

statements indicated in Annex B4. The project will be subject to financial management oversight both

on and off the project sites.

Audit Mechanisms

4.1.13 The financial statements of ONEE (Water Branch) and those of projects implemented with

ADB resources are currently audited by an external audit firm recruited by ONEE (Water Branch).

Projects will be audited according to international audit standards and taking into account procedures

outlined in TORs agreed with the Bank. TORs for FY2011-2013 have already been discussed and

approved by the Bank. The report on the audit of project financial statements and those of ONEE

(Water Branch) will be submitted to the Bank along with the letter to the Directorate on the internal

audit of the project, no later than six (6) months after the close of the relevant fiscal year. ONEE

(Water Branch) will also submit to the Bank an extract summarizing the key remarks and

recommended measures of the internal audit report of ONEE (Water Pole). Further, ONEE (Water

Branch) can also be audited by the Court of Auditors of Morocco.

Page 22: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

15

4.2. Monitoring

4.2.1 The physical implementation of the project will cover a period of 60 months, from 2013 to

2017. This time-frame is considered reasonable, taking into account the nature of the works and

ONEE’s (Water Branch) experience in similar works.

4.2.2 ONEE (Water Branch), the project executing agency, will assume prime responsibility for

monitoring the project and will prepare, in accordance with the method of presentation recommended

by the Bank, quarterly status reports of project implementation covering all aspects of its outputs. In

particular, the reports will assess the project implementation status, the expenditure, commitments and

disbursements by component, expenditure category and source of financing, the major problems

encountered as well as the recommended solutions. Beyond the implementation period and during the

operation phase, ONEE (Water Branch) has appropriate structures for monitoring the project impact;

it will establish a database, references and statistics for monitoring and evaluating various

performance indicators, in accordance with ONEE’s (Water Branch) standard models.

4.2.3 The Bank will monitor project implementation through supervision missions, ONEE (Water

Branch) activity reports and financial statements. The assistance of the Country Office in Morocco

(MAFO) will help to improve project implementation management and monitoring, especially as

regards the project’s technical, procurements, disbursements and financial management. Thereafter,

the Bank will prepare the project completion report and the project performance review report.

4.2.4 The detailed project implementation schedule is presented at the beginning of this report. The

completion of the project is scheduled for December 2017. The proposed project implementation

schedule is summarized below:

Period Stages Monitoring Activities / Feedback Loop

2010 – 2012 Detailed designs Validation of studies by ONEE (Water Branch)

2nd

half 2012 Consultation of CE Launch of consultation by APA

November 2012 Approval of project Bank Board of Directors

4th

quarter 2012 – 2nd

quarter 2013

Issue of BD for goods and

works

Preparation by ONEE (Water Branch) and Bank’s non-

objection

2013 – 2014 Bid evaluation Preparation by ONEE (Water Branch) and Bank’s non-

objection

2013 – 2014 Award of contracts Preparation by ONEE (Water Branch) and Bank’s non-

objection

2013 – 2017 Works Implementation Implementation by contractors and acceptance by ONEE

(Water Branch)

2013 – 2017 Works Monitoring Performed by CE and accepted by ONEE (Water Branch)

December 2018 Completion report Joint preparation by the Bank and ONEE (Water Branch)

4.3. Governance

4.3.1 ONEE (Water Branch) pays special attention to strengthening management and

organizational procedures, as seen in the new organization put in place to gradually decentralize its

activities and give broad autonomy to regions. The first measures concerned the devolution of

essential functions such as studies, works, partial human resource management and management

control by separating production and service-related tasks to foster greater proximity and visibility in

terms investment and commercial management.

4.3.2 In light of the reliability and efficiency of strategic and operational management tools

available at the ONEE (Water Branch) level (State-ONEE Programme Contract, internal management

contract, management control, SIONEP system, post-evaluation and quality management system,

etc.), the governance-related risks are low. Similarly, the reliability and efficiency of the control,

organization and, internal and external audit system has earned ONEE (Water Branch) the privilege of

Page 23: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

16

moving in April 2006 from an a priori control by the State to support control, reserved for entities

with proven competence in internal auditing, optimal management of resources and budget

implementation, and regularity of expenditure. In June 2009, ONEE (Water Branch) initiated a study

to strengthen its internal audit system and put in place an overall risk management strategy. This study

culminated in the mapping of risks ( curative and preventive risks).

4.4. Sustainability

4.4.1 Project sustainability depends mainly on ONEE’s (Water Branch) capacity to implement the

project as well as monitor and maintain the facilities that will be put in place. ONEE (Water Branch)

has an appropriate set-up as well as sufficient qualified technical staff who can operate and maintain

the drinking water production and supply systems of the cities concerned. In addition and as reflected

in ONEE’s (Water Branch) financial projections, adequate financial resources will be generated and

will cover the recurrent operating and maintenance costs of each of the structures to be put in place.

4.4.2 The sustainability of drinking water supply from the Al Massira dam depends on several

factors: the preservation of water quality, the right balance between abstraction (water removal and

losses from infiltration and evaporation, and the useful volume of the lake) and supply (which depends

on rainfall and climate change) and regulated transfer between basins of the North, Centre and South.

All these factors are managed by the Oum Er Rbia Water Basin Agency (ABH) in order to ensure the

sustainability of the resources of the storage dam (see Annex C1) and that the different water needs

of the Oum Er Rbia basin are satisfied.

4.4.3 Project sustainability also depends on the sound management of water distribution systems

by the Marrakech Autonomous Water and Electricity Distribution Agency (RADEEMA) for the city

of Marrakech and ONEE (Water Branch) for the other smaller urban and rural centres. This

management is reflected in the performance indicators of networks mentioned in annual reports of

RADEEMA and ONEE (Water Branch) and the two operators as well as the level of satisfaction of

their clients (Annex C2). The water tariff policy seeks to reconcile the interests of consumers and

those of stakeholders in order to guarantee service sustainability. The tariffs are based on a national

equalization system that makes it possible to establish social equity. The progressive rate system

accommodates low income-earners and incites the big consumers to use drinking water more

economically. Under a draft State-ONEE (Water Branch) Programme Contract revised periodically

which entrenches the objective of service sustainability, the DWS in rural areas and sanitation benefit

from targeted subsidies to maintain the financial balance of ONEE (Water Branch).

4.4.4 Finally, project sustainability is guaranteed by the reforms and programmes initiated by the

Government of Morocco particularly through the Water Sector Adjustment Programme (Water SAP) co-

financed by the Bank, the World Bank, the European Union, the National Irrigation Water Saving

Programme (PNEEI) and the National Sanitation Programme (PNA). These reforms, most of which have

already been implemented, will lead to integrated water resource management, watershed erosion control,

rehabilitation of DWS distribution and irrigation systems to reduce losses, the promotion of new

irrigation techniques to save water, the development of an adequate sanitation service, the reduction of

pollution and lastly, the introduction of adequate tariffs based on economic cost.

4.5. Risk Management

4.5.1 Possible project risks concern (i) the preservation and sustained availability of water

resources and the integrated and optimal management of these resources; (ii) the grouping of ONE

and ONEP into a single entity; (iii) delays in the procurement of the necessary land for building

structures; and (iv) failure to maintain and renew water distribution and sanitation networks.

Page 24: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

17

4.5.2 The conservation, sustained availability and integrated and optimal management of water

resources is one of the major concerns of the Water SAP measures co-financed by the Bank, the

European Union and the World Bank. These measures define quality standards for surface water and

water intended for DWS. These standards fix the threshold values for water discharged into the

sanitation systems and the natural environment as well as the values for liquid discharged from

different industrial and handicraft sectors. Furthermore, implementation of the action plans of the

national water strategy and PADAIREs contribute to ensuring integrated water resource management.

4.5.3 The grouping of ONE and ONEP could represent a risk for project implementation

(organizational aspect) as well as for the financial balance of the Authority (financial aspect).

However, this risk is low because Act No. 40-09 relating to this merger provided for the continuity of

business. In that regard, the operational departments (engineering, procurement, finance, etc) of the

former ONEP will continue to implement existing and programmed projects which concern them

(drinking water and sanitation). This separation by specialty will also be extended to financial aspects.

Separate financial statements will be prepared, to be consolidated later, as well as a Programme Contract

with the State in two parts (one for drinking water and sanitation and the other for electricity) that will

seek to preserve the financial balance of ONEE.

4.5.4 The sometimes fairly long time required to acquire the necessary land for laying pipes and

building structures could represent a risk for the timely implementation of the project. However, the

preliminary designs and environmental impact study have shown that the land parcels to be acquired

are either: (i) public land (public works, municipalities, etc); or (ii) have a low market value

(unfarmed arable land). In determining the planned route of the pipelines and location of structures, all

the existing urban centres were by-passed and, consequently, no construction will be affected.

Moreover, in order to take into account lessons learned from projects being implemented with ONEE,

it was agreed that officials of the Central Directorate in charge of legal affairs should assume

responsibility for the land acquisition file before the start of works and undertake on-site missions to

better identify possible land tenure constraints the project might face. Lastly, the Directorate in charge

of legal affairs will be backed by a legal expert during the technical support mission.

4.5.5 Failure to maintain and renew water distribution and sanitation networks is a risk that will be

mitigated by implementing the networks extension action plans of DWSS sector stakeholders (ONEE

(Water Branch) and Boards) and improving the infrastructure management conditions (see Annex

C2).

4.6. Knowledge Building

4.6.1 Project implementation will help to enrich ONEE’s (Water Branch) experience in carrying

out and operating drinking water supply and sanitation projects in urban and rural areas. The

involvement of ONEE (Water Branch) in integrated water resource management and the people’s

participation in the various components and their sensitization on the choice of projects are obvious

assets for the project.

4.6.2 The project implementation approach will seek the involvement of the maximum number of

staff members in the design and application of technical options, optimization of investments and the

rational use of water, adoption of technical options adapted to the environment of the different project

components and reconciling environmental, financial and socio-economic interests. The experience of

micro-enterprises for outsourcing certain functions and generating jobs locally especially for young

diploma-holders can also be an opportunity for the project

4.6.3 ONEE (Water Branch), through its website, will share its experience within the country and

beyond its borders. Its training centre will play a knowledge dissemination and research role, as

recognized by the WHO. The dissemination of experience will further confirm the status of ONEE as

a DWSS sector benchmark in Africa having close links with universities, research centres and similar

Page 25: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

18

bodies throughout the Continent and beyond, and collaboration geared towards sharing knowledge

and know-how. (ONEE already operates in some fifteen African countries). The Bank will definitely

benefit from it for the future direction of its DWSS sector operations, and will share the experience

from this project with its other units.

4.6.4 Technical support will be an instrument of assistance and transfer of knowledge and lessons

learnt in monitoring and supervising the environmental and social aspects. Technical support will

include an environmentalist who will help ONEE to properly monitor and evaluate environmental and

social indicators. It will facilitate the transfer of knowledge through the design of a monitoring and

surveillance guide and the necessary tools for this work which is new to ONEE (Water Branch). All

the documents and tools produced for the environmental and social component will be disseminated

on the ONEE (Water Branch) website.

V. Legal Framework

5.1. Legal Instrument

This is an ADB loan agreement.

5.2. Conditions Associated with the Bank’s Intervention

The granting of the ADB loan shall be subject to the following conditions:

Conditions precedent to effectiveness

Effectiveness of the loan agreement shall be subject to its signature.

Conditions precedent to first disbursement

Provide the Bank with evidence of the appointment of the Project Coordinator whose qualification and

experience shall have been deemed acceptable beforehand by the Bank.

Other conditions

i) Submit to the Bank, before commencement of the works on each structure, justification

for the occupancy of each plot of land concerned;

ii) Submit to the Bank, at the end of each quarter, a quarterly environmental and social

monitoring report based on the implementation of the environmental and social

management plan approved by the Bank. The report could form part of the quarterly

project implementation report.

Page 26: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

19

5.3. Compliance with Bank Policies

5.3.1 A waiver of the Policy on Expenditure Eligible for Bank Group Financing approved by the

Board on 19 March 2008 was requested to enable the Bank to finance over 50% of the total cost, net

of taxes and customs duties, of the Marrakech Region Drinking Water Supply Project. The

justification note, prepared in line with the provisions of Section 4.2.2 of the Policy, obtained the non-

objection of the relevant Bank services.

5.3.2 The project complies with all other applicable policies, in particular the Bank’s policies,

guidelines and procedures on environmental and social management. It is a category 2 project. The

ESMP summary was prepared and the cost of implementing mitigation measures was included in the

project cost.

VI. Recommendation

It is recommended that an ADB loan not exceeding a total amount of EUR 120.0 million and USD 37

million (about UA 122.2 million) be awarded to ONEE with a State guarantee. The loan will be used

to finance 57.6% of the total project cost, net of taxes and customs duties.

Page 27: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

Annex I

Page 1/1

Country Development Indicators

1990 2011 *

Superficie ( 000 Km² ) 30 323 80 976

Population totale (millions) 24,8 32,3 1 044,3 5 732,2

Croissance annuelle de la population (%) 1,9 1,0 2,3 1,3

Espérance de vie à la naissance -Total (années) 64,1 71,8 56,0 67,1

Taux de mortalité infantile (pour 1000) 64,6 32,2 78,6 46,9

Nombre de médecins (pour 100000 habitants) … 62,0 58,3 109,5

Naissances assistées par un personnel de santé qualifié (%) … … 50,2 64,1

Taux de vac. contre rougeole (% d'enfants de 12-23 mois) 79,0 98,0 77,9 80,7

Taux de scolarisation au primaire (% brut) 68,3 113,7 100,4 107,2

Ratio Filles/Garçons au primaire (%) 67,6 94,3 90,9 100,0

Taux d'alphabétisation (% de la population >15 ans) … 56,1 65,1 80,3

Accès à l'eau salubre (% de la population) 75,0 81,0 64,5 84,3

Accès aux services sanitaires (% de la population) 52,0 69,0 41,0 53,6

Valeur de l'IDH (Rang sur 187 pays) … 130,0 n.a n.a

Indice de pauvreté humaine  (IPH-1) (% de la Population) … 31,1 34,7 …

Indicateurs macroéconomiques 2000 2009 2010 2011

RNB par habitant, méthode Atlas ($ courant) 1 312 2 832 2 939 …

PIB (Million de dollars courant) 37 060 90 907 90 803 100 865

Croissance du PIB réel (% annuel) 1,8 4,8 3,7 5,0

Croissance du PIB réel par habitant (% annuel) 0,6 3,6 2,7 4,0

Investissement intéreur brut (% du PIB) 25,5 35,6 35,1 36,0

Inflation (% annuel) 1,9 1,0 0,9 0,9

Solde budgétaire (% du PIB) -5,5 -2,2 -4,7 -6,1

Commerce, Dette extérieure & Flux financiers 2000 2009 2010 2011

Variation en valeur des exportations (%) 3,3 -27,4 32,4 14,3

Variation en valeur des importations (%) 3,6 -19,0 12,9 19,6

Variation des termes de l'échange -7,4 5,7 -32,2 -4,8

Balance commerciale ( Million de dollars E.U.) -3234,9 -16279,2 -20010,7 -23833,6

Balance commerciale (% du PIB) -8,7 -17,9 -21,1 -22,7

Solde des comptes courants ( Million de dollars E.U.) -477,9 -4909,0 -4086,1 -6556,2

Solde des comptes courants (% du PIB) -1,3 -5,4 -4,5 -6,5

Service de la dette (% des exportations) 32,4 7,5 6,6 6,1

Dette extérieure totale (% du PIB) 48,6 23,3 23,6 24,0

Flux financiers nets totaux ( Million de dollars E.U.) 600,7 2082,4 … …

Aide publique au développement nette ( Mn de dollars E.U.) 418,8 911,6 … …

Investissements nets directs ( Million de dollars E.U.) 422,2 1951,7 1303,7 …

Réserves internationales (mois d'importations) 3,6 7,7 6,8 5,2

Développement du secteur privé et infrastructures 2000 2005 2010 2011

Temps requis pour demarrer une affaire (jours) … 12 12 12

Indice de protection des investisseurs (0-10) … 3,0 3,3 5,0

Abonnés aux téléphones fixes (pour 1000 hab.) 49,5 44,1 117,3 …

Utilisateurs d'internet (pour 1000 hab.) 81,3 407,8 1001,0 …

Routes asphaltées (% du total des routes) 54,6 59,6 … …

Ferroviaire, Marchandises transportées (million ton-km) 4576,0 5919,0 … …

* Année la plus récente. Dernière mise à jour : février 2012

Maroc

Source: Département de la statistique de la BAD, à partir de sources nationales et internationales.

Indicateurs sociauxMaroc

AfriquePays en dévelo-

ppement

711

Page 28: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

Annex II

Page 1/1

Table of ADB Active Portfolio in the Country (August 2012)

Taux

d'

exec.

Phys.

(%)

SECTEUR AGRICOLE 1.9 0.6 3.5 139,139,051 160,374,880 2,263,606 158,111,274 1.4% 18.6% 7.3%

1 Projet d'ap. tech. prom. jeunes entrepreneurs - DON PRI 12-janv.-12 4-May-12 4-May-12 30-juin-14 0.6 0.1 UC 497,200 497,200 0 497,200 0.0% 100.0%

2 Projet d'ap. au Prog. nat. d' eco. d'eau d'Irrig. (PNEEI) 14-déc.-09 04-mars-10 2-Jul-10 31-Dec-15 2.7 0.4 6.7 EUR 47,651,651 53,590,000 1,609,400 51,980,600 3.0% 17.0%

3Ass. Tech. progr. Protec. sauvegarde des oasis du Sud du Maroc

(POS) - DON PRI28-avr.-09 31-juil.-09 31-juil.-09 30-juin-13 3.3 0.8 3.1 UC 496,000 496,000 386,338 109,662 77.9% 77.9%

4 Appui tech. dév. Infrastr. d’irrigation - DON PRI 21-févr.-11 17-mars-11 17-mars-11 31-déc.-12 1.5 0.8 0.8 UC 494,200 494,200 158,834 335,366 32.1% 62.1%

5 Programme d' appui au Plan Maroc Vert (PAPMV) 18-juil.-12 0.1 EUR 90,000,000 105,000,000 105,000,000 57.1%

SECTEUR TRANSPORTS 3.1 0.6 7.7 510,263,406 585,720,000 51,733,548 533,986,452 8.8% 17.4% 26.9%

6 2è phase Progr. Nation. de routes rurales (PNRR 2) 5-sept.-07 23-nov.-07 8-mars-08 31-déc.-13 4.9 0.8 6.2 EUR 41,754,428 45,000,000 45,000,000 0 100.0% 100.0%

7 3ème Projet aéroportuaire 16-avr.-09 8-mai-09 22-oct.-09 31-déc.-13 3.3 0.7 6.3 EUR 214,456,130 240,000,000 5,940,008 234,059,992 2.5% 11.0%

8 Réparation ouvrages 7 ports - DON PRI * 01-avr.-10 17-mars-11 17-Mar-11 31-août-12 2.4 1.0 11.7 UC 600,000 600,000 12,675 587,325 2.1% 100.0%

9 Projet d'augm. de capa. Ferrov. Tanger-Marrakech 17-déc.-10 17-mars-11 30-Jun-11 31-déc.-16 1.6 0.2 6.5 EUR 253,452,847 300,000,000 778,528 299,221,472 0.3% 10.0%

SECTEUR ENERGIE 1.0 0.5 4.9 559,688,984 650,820,000 12,811,146 265,008,854 2.0% 29.0% 29.5%

10 Progr. déve. réseau transp. et réparti. élect. 02-déc.-09 11-déc.-09 29-Apr-10 31-déc.-14 2.7 0.5 4.9 EUR 101,830,388 109,820,000 12,811,146 97,008,854 11.7% 29.0%

11 Projet de la centrale solaire de Ouarzazate 16-mai-12 31-déc.-16 0.2 EUR 137,858,596 168,000,000 168,000,000

12 Programme intégré éolien et PERG 13-juin-12 31-déc.-16 0.2 EUR 320,000,000 373,000,000

SECTEUR SOCIAL 1.4 0.8 0.2 470,406 544,942 544,942 0 100.0% 100.0% 0.0%

13 Appui strat. dével. enseig. Privés - DON PRI 11-mars-11 17-mars-11 17-mars-11 31-déc.-12 1.4 0.8 0.2 UC 470,406 470,406 470,406 0 100.0% 100.0%

SECTEUR EAU ET ASSAINISSEMENT 3.6 0.7 7.7 309,565,848 369,375,833 89,517,146 275,557,100 24.2% 41.5% 16.3%

14 Neuvième Projet d'AEPA 21-juil.-06 18-déc.-06 16-mai-07 30-juin-13 6.1 0.9 10.0 EUR 70,666,446 81,000,000 63,900,423 17,099,577 78.9% 90.0%

15 Dixième Projet d'AEP 16-nov.-08 26-déc.-08 17-juil.-09 31-déc.-13 3.7 0.7 8.1 EUR 30,702,510 33,840,000 11,247,016 22,592,984 33.2% 60.0%

16 Dixième Projet d'AEP 16-nov.-08 26-déc.-08 17-juil.-09 31-déc.-13 3.7 0.7 8.1 USD 34,540,816 53,340,000 12,918,748 40,421,252 24.2% 60.0%

17 Onzième Projet d'AEPA Rabat-Casa 12-mai-10 19-août-10 13-janv.-11 31-déc.-14 2.2 0.4 8.2 EUR 135,258,333 162,310,000 0 162,310,000 0.0% 12.0%

18 Onzième Projet d'AEPA Rabat-Casa 12-mai-10 19-août-10 13-janv.-11 31-déc.-14 2.2 0.4 8.2 USD 36,706,667 55,060,000 3,123,581 51,936,419 5.7% 12.0%

19 Projet recharge artificiel. nappe du Haouz - DON FAE ** 12-janv.-09 8-mai-09 8-mai-09 30-nov.-12 3.6 0.9 3.9 EUR 1,691,076 1,892,500 1,637,700 254,800 86.5% 100.0%

SECTEUR MULTISECTEUR 1.5 0.7 1.6 201,445,338 227,027,046 224,529,840 2,497,206 98.9% 99.3% 10.6%

20 Projet d'améliorat. du syst. de garantie - DON PRI 19-janv.-11 17-mars-11 17-mars-11 31-déc.-13 1.6 0.5 1.9 UC 464,988 464,988 159,388 305,600 34.3% 76.5%

21 Projet de renf. du contr. marché. fin. - DON PRI 13-déc.-10 17-mars-11 17-mars-11 31-déc.-12 1.7 0.8 3.1 UC 480,350 480,350 171,410 308,940 35.7% 100.0%

22 Projet de dévelop. du Secteur Financier II (PADESFI-II) 23-nov.-11 23-Nov-11 6-déc.-11 31-déc.-12 0.7 0.6 0.4 EUR 200,000,000 224,000,000 224,000,000 0 100.0% 100.0%

23 Appui inst. SG UMA ( Multinational) - DON PRI 30-avr.-09 28-mai-09 28-mai-09 30-déc.-12 3.3 0.9 0.9 UC 500,000 500,000 110,735 389,265 22.1% 100.0%

24 Statistical Capacity Building II - DON PRI /ψ 15-mars-11 1.4 UC 490,000 490,000 490,000 100.0%

25 Etude sur la croissance et l' emploi au Maroc - DON PRI /ψ 2-juil.-12 0.1 EUR 587,200 704,640 704,640 100.0%

SECTEUR PRIVE 1.8 0.2 7.8 179,094,963 223,333,333 208,942,333 14,391,000 93.6% 93.5% 9.4%

26 Fond Argan pour le développement des infrast. 17-févr.-10 21-juil.-10 21-juil.-10 31-déc.-18 2.5 0.2 5.1 EUR 14,000,000 15,000,000 609,000 14,391,000 4.1% 3.0%

27 Prêt à l'Office Chérifien des Phosphates 29-juin-11 10-mai-12 10-mai-12 10-mai-15 1.1 0.1 10.5 USD 165,094,963 250,000,000 250,000,000 100.0% 100.0%

Récapitulatif: Répartition sectorielle des opérations Approbations (millions EUR) Situation des décaissements

Montant du portefeuille Total %

En Unités de compte 1,899,667,996 100.0%

Prêts (16 projets) 1,892,896,576 99.6%

Dons (11 projets) 6,771,420 0.4%

En Euros 2,217,196,034

Actuel Proj. 2012

Montant des approbations en 2012 542,301,280 903,830,500

Montant Total des décaissements en Euros 590,342,561 772,592,754

Prêts 587,453,031

Dons 2,889,530

Taux de décaissement global 37.6% 34.8%

Prêts 43.5% Dons 52.7%Montant moyen par prêt (en UC) 126,193,105

Delai moyen de mise en vigeur (mois) 4.8 Prêts 6.4 Dons 3.1Age relatif du portefeuille (an) *** 0.6

Age moyen du portefeuille (an) 2.0 Prêts 2.7 Dons 1.7

Note: Les zones gisée correspondent à des opérations non encore en vigueur ( ψ): Projet non encore en vigueur et par conséquent non inclus dans la détermination du taux de décaissement global du portefeuille.* PRI: Pays à revenu intermédiaire

* PRI: Pays à revenu intermédiaire ** FAE : Facilité africaine de l'eau *** Age relatif (ratio < ou = à 1): Age du projet depuis sa mise en vigueur rapporté à la période entre la date de mise en vigueur et la date de clôture telle que prévue à l'évaluation du projet.

Part

dans

le

portef

euille

Montant approuvé Décaissement

cumulé en

monnaie du prêt

par projet / en

euro par

secteur

Annulatio

n en

monnaie

du prêt

Montant non

décaissé en

monnaie du prêt

par projet /en

EUR par secteur

Taux décaissements

cumulés (en %)Nom

breNom du Projet

Date

d'approbation

Date de

signature

Date de

mise en

vigueur

Date de

clôture

Age

moyen

projet

(an)

Age

relatif

du

projet

(an)

delai

mise en

vigeur

(mois) en Unités de

compte

en monnaie du

prêt (total par

sect. en EUR)

ActuelProject.

2012

Monnaie

du prêt

Agric Transp. Energ. Social Eau/ass. Multisect. Sect. privé Moyenne

6%

17%

5%

100%

42%

99%

3%

30%

1%9%

2%

100%

24%

40%

52%

24%

Tx déc. prév. fin 2012 Tx de décais. fin juin 2012

158

643 634

476

646

904

2008 2009 2010 2011 act.2012

proj.2012

Agric7.3%

Transp26.9%

Energ29.5%

Eau/as16.3%

Multisec.10.6%

Privé 9.4%

Page 29: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

Annex III

Page 1/1

Key Related Projects Financed by the Bank and Other Development Partners of the Country

1. The list of the main projects financed by the Bank and and the other development partners in the DWSS sector is given in Annex-A.

2. The distribution of the main donors’ operations in Morocco’s DWSS sector in March 2012 is presented below (un EUR million).

Main Water Sector

Donors

ADB KFW AFD World

Bank

EIB JICA EU Belgian

Coop.

IsDB Spanish

Coop.

Total

Total (EUR Million) 555.17 504.64 414.50 272.98 253.50 188.00 165.66 79.40 72.40 10.00 2,521.91

% 22.01 20.01 16.44 10.82 10.05 7.45 6.57 3.15 2.87 0.40 100.00

Page 30: PROJECT APPRAISAL REPORT - African … · PROJECT APPRAISAL REPORT Date: September 2012 ... William DAKPO, Regional Procurement Coordinator ORPF.1 Félix BAUDIN, Chief Legal ... Key

Annex IV

Page 1/1

Map of Project Area

Project area