procurement and subcontractors

23
Pacific Business & Law Institute April 29, 2015 CONSIDERATIONS UNIQUE TO SUBCONTRACTORS Presented by: Seema Lal David Mckenzie

Upload: shklaw

Post on 06-Aug-2015

99 views

Category:

Business


0 download

TRANSCRIPT

Pacific Business & Law InstituteApril 29, 2015

CONSIDERATIONS UNIQUE TO SUBCONTRACTORS

Presented by:

Seema Lal David Mckenzie

CONTRACT A - CONTRACT B

The fundamental principle of the law of tendering for construction in Canada is that that method of contract procurement involves two stages of contractual relationships:

a) Contract A, which arises between the tendering authority and each “materially compliant” bidder, the terms of which are generally as set out in the tendering documents; and

b) Contract B, which is the tendered contract entered into between the tendering authority and the successful bidder.

SUBCONTRACT TENDERS

Law of tender (Contract A/Contract B) can apply to subcontractors submitting bids to general contractors

General Contractor must stick with subcontract bid if it is expressly included in GC’s tender (Naylor Group v. Ellis-Don Construction, [2001] 2 SCR 943)

Conversely, Subcontractor is obligated to enter into a Contract B with GC if subcontract bid is included in GC’s tender and GC’s tender is accepted by the Owner (Civil Construction Co. v. Advanced Steel Structures, 2011 BCSC 1341)

SUBCONTRACT TENDERS (cont.)

Acceptance of subcontractor’s bid likely occurs when general contractor carries subcontractor’s bid or price in its own bid

If Subcontractor states a time for acceptance in its bid/quote, then that statement will be taken to mean the time in which the GC has to insert that bid/quote into its own bid to the Owner

• No need for GC to expressly advise subcontractor that has occurred

SUBCONTRACT TENDERS (cont.)

An Owner in a tendering process does not owe a duty of care to subcontractors (Martel Building v. Canada, 2000 SCC 60; Design Services v. Canada, 2008 SCC 22)

SUBCONTRACT TENDERS (cont.)

GC may be obligated to only seek resubmissions from subcontractors it originally carried, even if another subcontractor can offer a lower price (G&S Electric v. Devlan Construction, 2008 CANLII 24538 (OnSC))

GC is obligated to “carry” subcontractors through any bid resubmission process, unless there is an express clause in the bid documents that says otherwise

PRACTICE POINTS FOR GCs

If you expressly name a subcontractor in your bid documents, you are obligated to use that subcontractor if your bid is accepted by the Owner

Same may hold even if you use subcontractor’s bid amount but don’t expressly name subcontractor

You are not entitled to renegotiate a subcontractor’s bid if it has been included in your bid documents and your bid is accepted by the Owner

You have an overriding duty to treat all subcontractors fairly

PRACTICE POINTS FOR SUBCONTRACTORS Ensure your quotes to GCs are accurate as you will be

obligated to adhere to the quote if it is expressly incorporated into GC’s tender documents

You have no ability to make a claim against the Owner if the Owner accepts another bidder’s non-compliant bid or otherwise breaches its obligations to the GC

PROTECTING GCs (AND OWNERS) FROM INCREASED COSTS

■Subcontractor tender process is usually a much less formal process than general contractor tender process

■Potential issues for GCs (and, indirectly, owners) with less formal process:

• Where no formal tender documents are prepared, it may be that

the form of invitation is so lacking in terms and conditions as to

not amount to an offer capable of acceptance – so no Contract A

PROTECTING GCs FROM INCREASED COSTS

■Potential issues with less formal process:

• Bids may be more likely to contain exclusions and potentially be

materially non-compliant

» Creates potential risk of liability of general contractors to compliant

bidders

PROTECTING GCs FROM INCREASED COSTS

■Potential issues for GCs with less formal process:

– Rules of tender process may not be as clear:

• The terms of the owner’s tender may apply to the

subcontractor on the following basis

» through implication;

» through sub’s actions in reviewing the tender documents then

submitting a bid; or

» as a result of the wording of sub’s bid document.

PROTECTING GCs FROM INCREASED COSTS

■Potential issues for GCs with less formal process:

– Raises additional potential problems with negotiation after the fact:

• May be permissible where tender expressly allows GC to

negotiate with low bidder,

• Where tender does not expressly allow for negotiation, what

if negotiations begin and parties cannot then agree?

• Legal position likely to be less clear with less formal process

PROTECTING GCs FROM INCREASED COSTS

■Potential issues for GCs with less formal process:

– Form of Contract B is not always specified by general contractor during tender.

– This can lead to further disagreement when negotiating terms of subcontract later on – can lead to legal limbo

• Where parties cannot agree on form of contract, subcontractor likely

bound to do the work it bid on for the price it bid - Civil Construction

Co. v. Advanced Steel Structures, 2011 BCSC 1341 – but what exactly

does that mean?

PROTECTING GCs FROM INCREASED COSTS

■Potential issues for GCs:

– Incorporation by reference clause contained in specified Contract B, but no access to prime contract given during tendering?

– May lead to claims of negligent misrepresentation if prime contract not provided:

• Online Constructors Ltd. v. Speers Construction Inc., 2012

ABCA 132

PROTECTING GCs FROM INCREASED COSTS

■Potential issues for GCs:

– Post-bid negotiation a reality and a risk:

• GCs not permitted to uses the bids submitted to it as a

negotiating tool, whether expressly or in a more clandestine

way, before the construction contract has been awarded to it,

with a view to obtaining a better price or other contractual

advantage from that particular subcontractor or any of the

others

PROTECTING GCs FROM INCREASED COSTS

■Potential issues for GCs:

– Post-bid negotiation a reality and a risk:

• If negotiations do take place between a general contractor

and subcontractor, the courts will examine them with a view

to determining whether they constitute a termination of the

tender process through the making of a counter-offer by the

general contractor to the subcontractor, or a request for a

modification to the bid submitted by the subcontractor

PROTECTING GCs FROM INCREASED COSTS

■GCs can protect themselves by:

– Using a more formal bid process

– Specifying Contract B form up front

– Refusing to negotiate after bid closing/tender award (except in accordance with express tender terms)

– Use terms which insulate them from liability to bidders for any misconduct during the tender process

PROTECTING OWNERS FROM INCREASED COSTS

■Potential issues for Owners:

– Project disputes may arise where there is a gap in the tendering process

• one item is in GC’s scope of work, but has not been carried

through to any subcontractor’s scope

– Owner can require more formal process (through bid depository, for example) or mandate owner oversight in trade selection

• Potentially higher initial costs, but less likelihood of gaps

ISSUES FOR SUBCONTRACTORS

■Subcontractors must read tender documents carefully to understand rights, obligations and risks

■If pertinent information (such as the prime contract) is available, subcontractors should obtain it, as otherwise they may be stuck with a bargain they did not expect

ISSUES FOR SUBCONTRACTORS

■Where there are onerous clauses in Contract B, subcontractor must decide whether it will:

– refuse to bid,

– increase its price to account for same, or

– amend Contract B wording, which may mean its bid is now non-compliant

ISSUES FOR SUBCONTRACTORS

■Non-compliance may less of a concern depending on formality of tender process:

– Where GC carries non-compliant bid in its price to owner, likely some sort of contract akin to Contract A will be formed

– GC may be required to award Contract B, as amended by terms of bid, to subcontractor

SHK LAW CORPORATION

Seema Lal604.408.2026([email protected])

David Mckenzie

[email protected]

604 895 3155