presented by: capital southeast connector joint powers authority tom zlotkowski executive director
DESCRIPTION
Presentation for. Presented by: Capital SouthEast Connector Joint Powers Authority Tom Zlotkowski Executive Director July 17, 2014. Connector Update - July, 2014. Location and General Information Project Description and History Project Implementation and Phasing - PowerPoint PPT PresentationTRANSCRIPT
Presented by:
Capital SouthEast Connector Joint Powers Authority
Tom ZlotkowskiExecutive DirectorJuly 17, 2014
Presentation for
Connector Update - July, 2014
Location and General Information
Project Description and History Project Implementation and
Phasing Recent Activity and
Accomplishments Anticipated Next Steps Scheduled Segment Milestones Opportunities and Challenges
Project Location
Selection of General Alignment
Elk Grove
Folsom
El Dorado County
Rancho Cordova Sacramento
County
Alignment Kammerer/Grant Line/White Rock Roads
Kammerer
Grant L
ine
White Rock
Length: 33.41 milesWidth: 4 to 6 lanesSignals: 25 + -
Interchanges: 10Speed Limit: 40-55 MPHSidewalk/Trail: Continuous
JPA SouthEast Connector:
From I-5 south of Elk Grove (Hood Franklin Road) through Rancho Cordova to Highway 50 in El Dorado County, just east of El Dorado Hills (Silva Valley Parkway
Project HistoryStudied by Caltrans in mid-90s
Studies abandoned due to cost and priorities
JPA History 2004 Sacramento County Sales Tax Extension
Studied extensively by SACOG (2005-2006) Selected Project Alignments/Governance recommended by SACOG Joint Powers Authority Formed (2007)
JPA MakeupSacramento CountyEl Dorado CountyCity of Elk Grove City of Rancho CordovaCity of Folsom(one vote format)
Selection of General Alignment
Elk Grove
Folsom El Dorado County
Rancho Cordova
Sacramento County
Activities of Significance 2011 Certification of PEIR and Selection of
Preferred Alignment (Amended and Re-certified March, 2012)
2012 Economic Impact Analysis (December, 2012)
2012/2013 Design Guidelines and Committee Work (initial adoption, March, 2013; Rev. 3.0 Nov. 2013)
2013 Initial Draft Plan of Finance (Initial adoption, March, 2013; Rev. 2.0 Jan. 2014)
2013 Design-Build Legislation AB 401 (September 2013)
2014 Environmental Phasing Strategy (May 2014)
2014 Sacramento County General Plan Amendment (May 2014)
Programmatic Environmental Impact Report
Programmatic Environmental Impact Report
SACOG Phase 1 Study
(November 2006)
Pre-scoping (2008-2010)
Public Input Opportunity
Notice of Preparation (February 2010)
Public Input Opportunity
Scoping Meetings(February/March 2010)
Public Input Opportunity
Technical StudiesDraft EIR Circulated (March –May, 2011)
Public Input Opportunity
Final EIR/responses to comments (Minimum 10
days) (Aug/September 2011)
Public Input Opportunity
Final PEIR Public Hearings and
Certification (2011)
Public Input Opportunity
Board adoption of Corridor Alignment
Notice of Determination
JPA Member Agencies amend General Plans to
align with adopted corridor
Project Level Environmental Analysis
Begin
PEIR Certified March 2012 Selection of General Alignment Identification of Mitigation Measures Adoption of MMRP ECOS settlement agreement on legal
challenge Current Related Activities Explore
Mitigation Strategies through SSHCP
Complete General Plan Amendments
Project Level Environmental Documents
NEPA Determination
Economic Impact Analysis
Economic Impact Analysis
Construction $830.9 Million in New Economic Output 5,448 New Full Time Jobs $23.03 Million in New Indirect Business
TaxesImportance of the Connector As Regional Accelerator and Catalyst
$2.5 Billion in New Output 25,015 New Jobs $1.06 Billion of new Labor Income $1.6 Billion of New Value Added (GRP) $182.2 Million in New Indirect Business
Taxes
Economic Impact Analysis
“This project has the SINGLE LARGEST OVERALL ECONOMIC IMPACT POTENTIAL compared to other projects (Airport, Downtown Arena) in terms of Increased Vibrancy and Overall Economic Prosperity for Region.”
Dr. Sanjay Varshney, Ph.D. Dean – CSUS Business
School
Project Design Guidelines
12
JPA Board
PDTProject Team TAC
SCC
SAC
Inpu
t
Ensures the Connector has the following characteristics: Uniform in character, appearance, and blends
with communities Effectively located access to maximize
efficiency of the corridor Integrated modes of travel Well-coordinated, efficient traffic operations Implements sustainable solutions Maintains integrity of regional transportation
systems Cost-effective implementation of the project
Project DesignGuidelines
Initial Plan of Finance
Includes: Cost Estimate
methodology and breakdown by segment
Project implementation and phasing
Funding and Finance mechanisms
SEGMENT DESCRIPTION
A4 laneexpressway, on Kammerer Rd from the I-5/Hood Franklin IC to Bruceville Rd & 6 lane Thoroughfare from Bruceville Rd to SR99
B 4 to 6 lane thoroughfare, from SR 99 to Bond Rd
C 4 lane roadway, on Grant Line Rd from Bond Rd to Calvine Rd (Sheldon Area)
D4 to 6 lane expressway, on Grant Line/White Rock Rd from Calvine Rd to the Sacramento‐El Dorado County line
E4 to 6 lane thoroughfare, on White Rock Rd from the County line to US 50/Silva Valley Pkwy IC
Project Segments
A1 A2B
C
D1
D2
D3 E1E2
Bruc
eville
Rd
Bond Rd
Calvine Rd
Jackson Hwy
White Rock Rd
Latrobe Rd
99
I-5
County Line
5 Major Categories Used
(Project Delivery, ROW, ROW Administration, Environmental, Construction)
Project Cost EstimatesCost Estimate Methodology
Major Segment Roadway Segment
Total Project Cost Estimate % of Total
A I-5 to State Route 99 $ 76,194,000 17%B State Route 99 to Bond Road $ 56,746,000 12%C Bond Road to Calvine Road $ 25,471,000 6%D Calvine Road to El Dorado County Line $275,635,000 60%
EEl Dorado County Line to US-50/Silva Valley Parkway $ 22,354,000 5%
456,400,000$ 100%
Project Delivery Costs; 14%
Right-of-Way; 6%
Right-of-Way Administration;
1%
Environmental Mitigation; 5%
Construction (includes sus-
tainability), 62%
Construction Con-tingency; 12% Consistent with Project
PEIR Project Delivery
Method: Design-Build/CMGC/?
Broken Down by Segment
Project Segmentation: Smaller Sub-Segments for flexibility - A1, A2, B,
C, D1, D2…
Two–Phased Approach:Phase 1: Construct “Backbone Facility” - capacity for between five to fifteen yearsPhase 2: Finish corridor for full buildout – six lane segments, interchange conversions
Project Implementation and Phasing
Major Segment Segment Roadway Segment
Phase 1 Cost Estimate
Phase 2 Cost Estimate Total Costs
A1 I-5 to Bruceville Road $ 44,444,304 $ 1,553,552 $ 45,997,856
A2 Bruceville Road to State Route 99 $ 24,099,838 $ 6,096,544 $ 30,196,382
B B State Route 99 to Bond Road $ 45,850,190 $ 10,896,296 $ 56,746,486
C C Bond Road to Calvine Road $ 24,810,822 $ 660,000 $ 25,470,822
D1 Calvine Road to Jackson Road $ 35,384,781 $ 15,336,192 $ 50,720,973
D2Jackson Road to White Rock/Grant Line Road $ 45,450,559 $ 61,139,733 $106,590,292
D3White Rock/Grant Line Road to Sacramento/El Dorado County Line $ 69,371,880 $ 48,951,704 $118,323,584
E1 El Dorado County Line to Latrobe $ 10,653,793 $ - $ 10,653,793 E2 Latrobe to US-50/Silva Valley Parkway $ 11,700,235 $ - $ 11,700,235
311,766,403$ 144,634,021$ 456,400,424$
A
D
E
Connector JPA Measure A Funds - $118.0M
Federal and State Regional Funds - $136.9M
Member Jurisdiction Developer Fees - $197.0M
Fair Share Contributions - $23.8M
Member Jurisdiction Direct Contributions - $2.3M
Potential Revenue Sources - $80M
Funding and Finance Mechanisms
Measure A; $118.00
Fed/State; $136.90 Dev. Fees;
$197.00
Other Contribu-tions ; $23.80
Member Direct; $2.30
Potential; $80.00
Measure A Fed/State Dev. FeesOther Contributions Member Direct Potential
Anticipated next steps
Discussion, Development, and Execution of Reciprocal Use and Funding Agreements to Address: Funding contributions Timing and Sequencing of segment
construction Future access requests Overall JPA authority
Refine Alignment Right of Way Assessment and
Acquisition Further Technical Development
Schedule for segment milestones
Segment
Segment A Kammerer Road
Segment D2Jackson to White Rock Road
Segment D3Prairie City to County Line
Segment ECounty Line to Latrobe
Schedule
Dec 2015 – certify NEPA document
Winter 2014 – Initiate PA/ED process: NEPA/CEQA
Fall 2014 – Initiate PA/ED process: CEQA
2014/2015 – Initiate PA/ED process w/ D3
Opportunities and Challenges
Opportunities Stated project transportation benefits Economic growth potential – Jobs!! Provides opportunities for other
necessary infrastructure Single largest local road project in
region will raise capabilities and capacities
Improved jurisdictional relations amongst members
Introduce design-build as procurement option
Opportunities and Challenges
Challenges Stakeholder Outreach and education Jurisdictional sovereignty and policy
sensitivity California enviro-political climate Project “Champion” vacancy Financing capacity and construction
cash flow Competing local government priorities Lack of perceived “immediacy of need” Advocacy deficiency
Questions