ENGINEERING FINDING REPORT
FINDING SUMMARY REPORT
PIPING STRUCTURE
ELECTRICAL INSTRUMENT
FINDING ITEM PIPING :
1. Total piping engineering documents received from detail engineering =171 documents.
2. To be revise during fabrication & construction phase 42 documents.Percentage piping engineering document to be revised 42 of 117(35.90%).
3. Piping material items refer to Exhibit I:
Additional new items = 54 Initial items = 105
FINDING REGISTER
CTR found that piping route on TP- 04, the
elevation for new route would clash with existing
lamp. Therefore, it is required to relocate the
Lamp (MWPN )
CTR Found that piping route on TP- 04, the elevation for new route would clash with
existing pipe. Therefore it is required to re-route the pipe ( WPN2 )
MWPS - POTENTIAL OBSTRUCTION DURING P/F INSTALLATION
2”2”- DIESEL OIL FROM TANK TO PUMPSUPPLY WAS NOT SHOWN IN DETAIL ENGINEERING DRAWING• CTR TO PERFORM SIMULATION PRIOR P/F INSTALLATION,• IMPACT : TO RE-ROUTE 2’-DIESEL OIL LINE • TO BE ASSESS POSSIBILITY TO INSTALL TEMPORARY GENSET DURING P/F INSTALLATION,
MWPS - POTENTIAL OBSTRUCTION DURING P/F INSTALLATION
2”-DO-B01-31088DIESEL OIL
OFFLOADING FACILILITIES P/F
DISCREPANCIES ITEM
ISO NO LINE NO DESC GS REQ (GS - EP- PVV 112)
REMARK
ID-SNB-MWPS-1080-551008
3”-L-G05S-31022 3/4”- 1500# WELDOFLANGE –RTJ A182 GR. F321
A105, ELBOWS, CUOPLINGS, TEES, SOCKOLETS, FLANGOLETS, SWAGE NIPPLES PE
TO BE SUBTITUTE TO A105
ID-SNB-MWPS-1080-551020
6”-L-G05S-31017 3/4”- 1500# WELDOFLANGE –RTJ A182 GR. F321
A105, ELBOWS, CUOPLINGS, TEES, SOCKOLETS, FLANGOLETS, SWAGE NIPPLES PE
TO BE SUBTITUTE TO A105
ID-SNB-MWPN-1080-551008
3”-L-G05S-41022 3/4”- 1500# WELDOFLANGE –RTJ A182 GR. F321
A105, ELBOWS, CUOPLINGS, TEES, SOCKOLETS, FLANGOLETS, SWAGE NIPPLES PE
TO BE SUBTITUTE TO A105
ID-SNB-MWPN-1080-551020
6”-L-G05S-41017 3/4”- 1500# WELDOFLANGE –RTJ A182 GR. F321
A105, ELBOWS, CUOPLINGS, TEES, SOCKOLETS, FLANGOLETS, SWAGE NIPPLES PE
TO BE SUBTITUTE TO A105
ID-SNB-WPN2-1080-551008
3”-L-G05S-42022 3/4”- 1500# WELDOFLANGE –RTJ A182 GR. F321
A105, ELBOWS, CUOPLINGS, TEES, SOCKOLETS, FLANGOLETS, SWAGE NIPPLES PE
TO BE SUBTITUTE TO A105
ID-SNB-WPN2-1080-551020
6”-L-G05S-42017 3/4”- 1500# WELDOFLANGE –RTJ A182 GR. F321
A105, ELBOWS, CUOPLINGS, TEES, SOCKOLETS, FLANGOLETS, SWAGE NIPPLES PE
TO BE SUBTITUTE TO A105
EFFECTED Drawing
D-SNB-MWPN-1080-551020ID-SNB-MWPS-1080-551020ID-SNB-WPN2-1080-551020
Problem Is: In drawing Number above this is line service is G05S if see in GS –EP‐PVV‐112 Should be use for material carbon steel but BOM we found material use Stainless steel total we found for three Platform is 9 ea of weldo flange SS.
GS EP PVV 112ID-SNB-WPN2-1080-551020
Problem Is: In drawing Number No ID-SNB-WPN2-1080-551013 line 3”-L-B48-42024 we found line spec class B 48 but in material elbow 2” Sch 40 use material Carbon steel if we compare with GS EP PVV 112 is unmatched
• Drain line from offloading pump elevation lower than existing tie in point• Liquid trap during offloading pump operation
• Drain line to be re-route to lower deck to avoid liquid trap during offloading pump operation •Re-route drain line shall be refer to pump vendor dwg
BASED ON P&ID, PROJECT MUST INSTALLSPECTACLE BLIND 6" - 900# SS : NO DRAWINGCONSTRUCTION IN DETAIL EINGINEERINGAND IMPACT TO ADDITIONAL MATERIALS
BACK TO THE LIST
FINDING ITEM STRUCTURAL:
1. Total structural engineering documents received from detail engineering = 32 documents.
2. To be revise during fabrication & construction phase 18 documents.Percentage structural engineering documents to be revised 18 of 32(56,25%).
3.Structural material items refer to Exhibit I: Additional new item = 8 Initial item = 35
FINDING REGISTER
Hook up connection Lower Deck FramingExtension not detailed in detailengineering for following issues:
• Row 2'B' Lower Deck MWPN• Row 2’C Lower Deck MWPS
ID-SNB-MWPN-1080-590003
ID-SNB-MWPS-1080-590003
ID‐SNB‐MWPS‐1080‐590005
ID‐SNB‐MWPS‐1080‐590007 sht. 3 of 3
Orientation of plating and H/R lay out T.O.P EL. (+) 16.146 (MWPS) and detail hatch cover framing plan is not matching, to be revise accordingly
Existing framing step landing clash with offloading frame extension deck module( MWPN & WPN2 )
Alternative solution :•Demolish the existing step landing frame to accommodate new frame offloading pump and rectify after new extension plaform installed.
Potential obstruction during Offloading Pump Installation : Cable trays, Lighting poles, Instrument stanchion
Connection at row 2’B’ to be detailed
Actual condition hook up connection Row2’B’ is different in detail engineering forfollowing issues:
• Row 2'B' Lower Deck MWPN
‐ Pump support/skid detail for mounting is not found ( all platforms ) in detail engineering, impact : additional material