predicting the unpredictable? - fplotnick.com sequence duration. case study #3 - - discussing risk...
TRANSCRIPT
Colin ThriftColin Thrift
2014 Construction CPM 2014 Construction CPM Conference Conference Orlando, FlOrlando, FlJanuary 23January 23rdrd, 2014, 2014
Predicting the Unpredictable? Predicting the Unpredictable? ……..a ..a CMCM’’ss point of point of
view view
Founded in 1873, 140 Years Continuously Family Owned and Managed
4th Generation Family Member in Leadership
$4 Billion in Revenue in 2009 update
2,000 Employees
5th Largest CM at Risk (as ranked by ENR)
GilbaneGilbane OverviewOverview
Understand the Schedule Risk Analysis process
How SRA can help you mitigate impacts to your project schedule & cost
Understand why a critical path analysis is not enough
Seminar Goal Today Seminar Goal Today
Schedule risk are unpredictable events and time constraints that put the on time completion of your project at in jeopardy.
Schedule risk can dramatically increase the chances of a timely, cost-efficient project completion
Schedule risk threatens the schedule and cost throughout the life of the project
What is Schedule Risk?What is Schedule Risk?
Industry ChangesIndustry Changes
• BIM & Virtual Design • Client expectations • Accessible risk software• The new norm –
ENR (56% of construction)
Have you ever asked yourself the following?
Why should I conduct a Schedule Risk Analysis when I already have a great critical path schedule?
How do I replace my “gut-feeling” about the outcome of the project?
Why do I lack confidence that the monthly report does not capture the true health of the project?
Should I be worried that the team is overlooking a potential risk, and that it will be identified too late to mitigate?
How can I get a true schedule assessment of the change request?
Why SRA Why SRA -- Reason #2 YOU!Reason #2 YOU!
What is Risk?What is Risk?
There are known knowns. These are things we know that we know. There are known unknowns. That is to say, there are things that we know we don't know. But there are also unknown unknowns. There are things we don't know we don't know.
Donald Rumsfeld
Finding RiskFinding Risk
The greater the uncertainties and constraints, the greater the risk to the successful outcome of a project.
Risks in constructionRisks in construction
long lead procurement, permits, budget vs. design constraints, program changes, value engineering
weather, resources, site remediation
escalation, customs
legislation, legal issues
Trade disputes, personalities, new technology
………………..and on and on
The SRA ProcessThe SRA Process
Step 1 – Schedule scope review + quality review
Step 2 – Identifying project risk
Step 3 – Mitigation of risk
– Typical time to do SRA is 1-2 days
When:
Program - Design Phase
Construction GMP Baseline
Quarterly
The Project
Expansion and renovation of an existing clinical manufacturing facility to comply with various federal and manufacturing bio safety and security guidelines.
SRA conducted at CM Baseline submission
Case study #1 Case study #1 -- Manufacturing FacilityManufacturing Facility
Project Schedule Assessment:
The first step is the assessment of the project schedule to determine if the plan accurately represents the scope of work, and necessary adjustments
Sample of adjustments made:
Long Lead Equipment activities did not have successors.
Inaccurate assumptions – piping follows ceiling install
No equipment startup / permanent power relationship
Start of Test and Balancing was inaccurate
Case study #1 Case study #1 -- Schedule AssessmentSchedule Assessment
Results:
CPM schedule showed an on-time completion
Adjusted CPM had 2 weeks overrun
SRA predicted 4 weeks overrun
Team Risk Discussion:
Installation of HVAC rough-in interstitial duct
Clean room ceiling framing
Chicago ceiling > light fixtures
Door security trim > test & balance
Case study #1 Case study #1 -- Discussing RiskDiscussing Risk
Recommendations
Project contingency approach vs. aggressive schedule
Enhanced schedule – Work Areas/ Phasing / Systems
Question schedule assumptions/ ties & resources
Commissioning/ validation approach
Handling changes and issues – TIA
Outcome
CM implemented all recommendations
Open client/ CM risk discussions
Project did complete on time
Case study #1 Case study #1 -- RecommendationsRecommendations
First SRA at GMP Baseline (18 months remaining)
– Foundations were 50% completed– CPM had an on-time completion– SRA predicted 3-4 week over-run
– Risk Identified:o Achieving “building tight”o Steel erection sequenceo Auditorium & Gymnasium detail
Case Study #2 Case Study #2 -- High SchoolHigh School
Replace generic submittal procurement with specific façade components.
Clarify the definition of “building tight” & approach
Expand façade sequence, identify key locations where building tight can be achieved earlier than
Case Study #2 Case Study #2 -- SRA RecommendationsSRA Recommendations
Accelerate steel - benefits versus cost
Focus on deck “turn-over” and not steel erection
Mitigate roof mechanical/steel detailing coordination
Consider 4D steel erection/façade model
Case study #2 Case study #2 -- RecommendationsRecommendations
Team to confirm perimeter CMU / SOG logic.
Conduct focused Auditorium & Gymnasium IPS
Breakdown gymnasium floor installation (receive/store/installation)
Add interior climate control approach
SRA Conclusion at Baseline– Potential 3-4 week over-run– Three primary risk area (Steel, Building Tight,
Gym/Auditorium)– Focused recommendations & action plan
Case Study #2 Case Study #2 -- RecommendationsRecommendations
Follow-up SRA – Conducted 5 months later– Steel was almost at completion– SRA focused on evaluating scenarios
Case study #2 Case study #2 –– FollowFollow--up SRAup SRA
Scenario 1 – All schedule activities assumed “realistic”
Scenario 2 – All schedule activities assumed “aggressive”
Scenario 3 – Façade assumed “very aggressive”
Scenario 4 – Plumbing & Electrical activities assumed “very aggressive”
Scenario 5 – Area B (Gymnasium) activities assumed “very aggressive”
Case Study #2 Case Study #2 -- The SRA ScenariosThe SRA Scenarios
Action – team implemented all recommendations
Zero cost to project $$$$
Potential 3-4 week early completion
6-8 weeks improvement
Note: CPM remained at zero float through-out
Case study #2 Case study #2 -- Outcome to dateOutcome to date
PROJECT DESCRIPTION
Medical Center is an 11-story, 1,200,000-square-foot
This facility has 28 operating rooms, 176 medical/surgical and ICU beds, 128 recovery rooms, interventional radiology, procedure rooms, staff training facilities, main kitchen, ancillary departments, clinical offices, support office, sterile processing, and pharmacy and public areas.
Case study #3 Case study #3 -- Medical CenterMedical Center
Project in the last 8 months of construction
Current CPM schedule shows two-weeks over-run
SRA predicted 2 months over-run
Risk Found:
Punchlist > City Inspections > Substantial Completion
Life Safety Inspections > Substantial Completion
Hot Water Systems > HW Balancing > HW Owner Testing > Substantial Completion
Air TAB (AHU’s) > AHU Owner Testing > Substantial Completion
Case study #3 Case study #3 -- Predicting the outcomePredicting the outcome
Team buy-in of closeout procedure/ sequence
Confirm City Inspections approach
Determine A/E punch list approach
Mitigating “owner” risk
Mechanical contractor bonding performance issues
Balancing schedule required accelerated 6-8 weeks representing almost a 40% acceleration in the overall balancing sequence duration.
Case study #3 Case study #3 -- Discussing RiskDiscussing Risk
Outcome– Team on same page– Team assigned specific action– Action plan on risk– Removed “unkowns”– Identified risk outside our control > focus action plans
(unkown unkowns?)
Project Completed on-time
16 hours to do SRA (one day on site, one day doing report)
Case study #3 Case study #3 -- OutcomeOutcome
Explain why & how Schedule Risk Analysis helps mitigate the impact of unpredicted threats to your project schedule.
Demonstrate, through case-studies, the benefits of following specific steps to proactively manage schedule risk and dramatically increase the chances of a timely, cost-efficient project completion.
Our Seminar Goal Today Our Seminar Goal Today
HOWThree step process (Quality/Risk/Mitigate)
WHYChanging World, good business practice, software……Risk exists need a proactive approach not reactive
SRA
Improves confidence by identifying risk
Asks the right questions
Team conversations
ALL ABOUT THE DIALOGUE - NOT STATISTICAL CURVE
ConclusionConclusion