pre-feasibility report - welcome to...
TRANSCRIPT
PRE-FEASIBILITY REPORT
of
EXPANSION AND NEW UNIT
for
MANUFACTURING OF SPONGE IRON, FERRO
ALLOYS, M.S.& ALLOY STEEL BILLETS AND
ROLLING MILL UNITS
at
M/s. TOPWORTH URJA & METALS LTD. NAGPUR
Village – Heti, Mouza Ukkerwahi, P O – Udasa,Tehsil – Umred, District
– Nagpur
EIA EIA EIA EIA Consultant:Consultant:Consultant:Consultant:Pollution Pollution Pollution Pollution and and and and Ecology Control Ecology Control Ecology Control Ecology Control Services (Services (Services (Services (PECS), Nagpur.PECS), Nagpur.PECS), Nagpur.PECS), Nagpur. Accredited vide letter no. NABET/EIA/02/12/47 dated 27/02/2012.Accredited vide letter no. NABET/EIA/02/12/47 dated 27/02/2012.Accredited vide letter no. NABET/EIA/02/12/47 dated 27/02/2012.Accredited vide letter no. NABET/EIA/02/12/47 dated 27/02/2012.
PRE-FEASIBILITY REPORT
2
1.0 INTRODUCTION
1.1 PREAMBLE:
Ferro-alloys are among the essential inputs required for steelmaking. It improves the
quality of steel, by controlling the harmful impurities and at the same time improves the
mechanical properties of steel through alloying. Growth in Global as well as domestic
steel industry directly drives the demand of Ferro-alloys. Since Indian steel industry is
under massive expansion, there is a tremendous potential for investment in Ferro-alloy
production.
Steel being a basic commodity for all industrial activities, quantum of its consumption is
considered an index of industrial prosperity. Since independence, there has been a
substantial growth in the steel sector in India from 1.5 Million Tons in 1950-51 to about
31 Million Tons at present. Additional steelmaking capacity of about 8 to 10 Million Tons
/year exists in the secondary steel sector. Despite the above growth in the steel sector,
the per capita steel consumption continues to remain at a level of about 27 kg only,
compared to about 350 to 450 kg in the developed countries and 40 to 100 kg in some
of the developing countries. Further, with nearly 20% of the world population, India’s
contribution is only of the order of 3.4% of world steel production. Hence, short-term
and long-term strategies are necessary in planning the development of the steel
industry in the country to improve the level of per capita steel consumption. It is
expected that with the measures taken by Govt. of India for promotion consumption of
iron and steel and expected growth of Indian economy the requirement of steel will
significantly increase and accordingly the domestic manufacturing capacity needs to be
increase.
The specification covers the design, manufacture, shop testing, supply, erection and of
Steel Melt Shop (SMS) Equipment, i.e., Electric Arc Furnace (EAF), Ladle Refining Furnace
(LRF), called Ladle Furnace (LF), and Continuous Casting Machine (CCM) for 400,000 TPA
PRE-FEASIBILITY REPORT
3
Alloy Steel Complex, 3 Lac TPA Alloy Steel Bars/Wire Rods & TMT Bars Mill, Light &
Medium Section Mill of 1.5 Lac TPA, Heavy Section Mill of 2.5 Lac TPA Capacity,
Expansion of existing capacity of Sponge Iron Division from 60000 TPA to 2.91 Lac TPA
by installing 2 x 350 TPD Sponge Iron Kilns to produce 2.31 Lac TPA Sponge Iron, 50000
TPA Ferro Alloys Unit, Expansion of existing capacities of Steel Billets from 240 TPD to
480 TPD and TMT Bars from 66000 to 1.5 Lac TPA for Topworth Urja & Metals Ltd. at
Nagpur, Maharashtra.
1.2 PROJECT DESCRIPTION:
The existing Plant site of Topworth Urja & Metals Limited (TUML), Nagpur has been
selected for the expansion by installation of proposed:
• Enhancement of capacity of existing Sponge Iron Plant from 60,000 TPA to
291000TPA by installing additional 2 X 350 TPD Rotary Kilns for production of
231000TPA Sponge Iron.
• Enhancement of Capacity of Existing TMT Bar Mill from 66,000 TPA to 1, 50,000
TPA.
• Enhancement Of Capacity of Existing Billet Plant From 240 TPD To 480 TPD Steel
Billets By Installing Additional 2 X 12 Ton Induction Furnaces And also Installation
Of Ladle Refining Furnace For Production Of Better Quality Of Steel.
• 2 X 16.5 MVA Submerged Arc Furnaces Based 50000 TPA Ferro Alloys Plant.
• 400,000 TPA Alloy Steel Melt Shop for Production of Alloy Steel Billets.
• 300000 TPA Bar Mill for rolling of Alloy Steel Bars & wire rods and TMT Bars .
• 1.5 Lac TPA Section Mill for Rolling of Light & Medium Steel Sections like Angles,
Channels and Beams.
• 2.5 Lac TPA Heavy Section Mill for Rolling of Structural Steel Heavy Sections.
Proposed units for the project are given below along with existing capacity and proposed
expansion.
PRE-FEASIBILITY REPORT
4
1.2.1 RAW MATERIAL REQUIREMENT
S.
N
NAME OF UNITS
EXISTING
CPACITY
PROPOSED
EXPANSION/
NEW UNITS
AFTER EXPANSION
AND AS PER TOR
ISSUED BY VIDE
LETTER NO.F.NO.J-
11011/283/2013-IA-
II (I) DATED30TH
APRIL 14
AS PER
PROPOSED
AMENDMENT IN
PROJECT
CONFIGURATION
1 Sponge Iron 60000TPA 231000TPA 291000TPA 291000TPA
2 Steel Billets 240 TPD 240 TPD 480 TPD 480 TPD
3 TMT Bar 66,000TPA 84,000 TPA 1,50,000 TPA 1,50,000 TPA
4 Captive power plant 100MW -- 100MW 100MW
5 Ferro Alloys Plant, -- 50000 TPA 50000 TPA 50000 TPA
6 Alloy Steel melt shop -- 200000 TPA 200000 TPA 400000 TPA
7 Alloy Steel Bar/Wire
Rod/TMT Bar Mill
(Stainless Steel, Alloy
Steel, Carbon Steel &
Wire Rods)
-- 200000 TPA 200000 TPA 300000 TPA
8 Section Mill For
Rolling of Steel
Sections
-- 100000 TPA 100000 TPA 150000 TPA
9. Heavy Section Mill For
Rolling of Structural
Steel Heavy Sections
- 250000 TPA - 250000 TPA
Sr.
No
RAW MATERIAL
REQUIREMENT
PRODUCTS
Existing
Requirement
Proposed
Expansion
Total
Requirement
After expansion
As per
Amendment
requested
1. Manganese Ore ------------- 7050 MT/M 7050 MT/M 7050 MT/M
2. Ferro Alloy 100 MT/M 350 MT/M 450 MT/M 700 MT/M
3. Pig Iron ----------- 3500 MT/M 3500 MT/M 3500 MT/M
4. Billets 5850 MT/M 34235 MT/M 40085 MT/M 76125 MT/M
5. M. S. Scrap 1140 MT/M 2895 MT/M 4035 MT/M 7545 MT/M
6. Sponge Iron 7200 MT/M 21000 MT/M 28200 MT/M 41850 MT/M
7. Coal (DRI+ Power
plant+ Rolling mill) 69300 MT/M 28875 MT/M 98175 MT/M 69300 MT/M
PRE-FEASIBILITY REPORT
5
1.2.2 WATER REQUIREMENT AND ITS SOURCE:
The water requirement will be supplied by Paradgaon dam. The makeup water and
other requirement for the proposed expansion project will be 3009 m3/day. Water is
basically required for cooling water and the make-up, domestic and other miscellaneous
requirements.
1.2.3 POWER REQUIREMENT AND ITSSOURCE:
The power requirement will be 92.5 MW/Hr for the proposed project Source will be
Captive Power Plant which is in operation.
Sr.
No.
Energy required for Existing Power
Consumption
Proposed Power
Consumption
Total Power
Consumption in
MW
1 Induction furnaces based SMS 8.5 MW 8.5 MW 17 MW
2 Rotary kilns / Sponge Iron
Plant
1 MW 2.5 MW 3.5 MW
3 All Rolling mills 2 MW 8.5 MW 10.5 MW
4 Submerged arc furnace based
Ferro Alloys Unit
---------------- 23.5 MW 23.5 MW
5 Electric Arc Furnace / LRF /
VD / AODbasedSteel melting
shop for Alloy Steel Billets
---------------- 25 MW 25 MW
6 Power Plant Home Load for
auxiliary consumption
08 MW ----------------- 08 MW
6 Pollution control equipment 1.5 MW 2 MW 3.5 MW
7 Plant lighting 0.75 MW 0.75 MW 1.5 MW
Total 21.75 MW 70.75 MW 92.5 MW
8 Iron Ore/Pellets 7500 MT/M 28875 MT/M 36375 MT/M 36375 MT/M
9. Dolomite 825 MT/M 3170 MT/M 3995 MT/M 3638 MT/M
PRE-FEASIBILITY REPORT
6
N
0 1 2 3 4 5 6 7Metres 1000Km.
STREAMS
RIVER / NALA
ROAD
HABITATION
INDEX
FOREST BOUNDARY
POND
RAILWAY
79°10'
21°55'
21°0'
Pendhri
Phukeahwar
Dudha
Makaedhokra
Dahegoon Amb NadiHewri
DawhaSayaki
Sirpur
Kursapar
Paradgoon
Masaikkund
Bhiwapur
UtiHaladgoon
ParsodiTikhadiUmra
Sukli Khurd
Champa Chanpa
Mangli
Undri
Khapri
KHAPRI TALAV
Sonegaon
Knetapur
Sonegaon Talav
Kolarmet
Talav
Takli Kalan
Kolarmet
Kalandri
BorgaonKalandri Talav
Khairi
Nirwah
WaregaonBarwa
Pipra
Canal
Ukharwahi Talav
HetiAkola
UkharwahiWirli
Aptur
Welsakhra
Udasa
Rajulwari
Thomra
Ganpaoli
Gangapur
Kanhwa
Can
al
Can
al
Canal
Canal
Amb Nadi
79°15'
BHIWAPUR R.F
Dense Mixed Jungle
Dense Mixed Jungle
BHIWAPUR R.F
Open mixed jungle
Open mixed jungle
Open mixed jungle
10 km.
79°15' 79°20'
21°55'
21°0'
TOPOSHEET NO : 55- P/1,P/5 & 55- O/4, O/8
1.3 SITE DESCRIPTION:Topworth Urja & Metals Ltd. Nagpur, Village Heti, Mouza –
Ukkerwahi, P O – Udasa, Tehsil: Umred, District Nagpur, Maharashtra.
1.3.1 SITE LOCATION:
The proposed site is about 35 km south east of Nagpur city and about 12 km North East
of Umred Tehsil. Sponge Iron Mini Steel Plant and Rolling Mill are present in the existing
premises of Topworth group and Captive Power Plant is proposed. Topworth Urja and
Metals Ltd (TUML), located on Umred road, Village Heti, Mouza Ukkerwahi, P O- Udasa,
Tehsil Umred, Distt. Nagpur (MH). The terrain of the land is almost flat and low lying.
The location of the TUML is given below in the Study Area (10 Km. radius).
M/s TOPWORTH URJA
AND METALS LTD.
PRE-FEASIBILITY REPORT
7
Source: Toposheet of GOI
Fig-1: Study Area Map (10 Km Radius)
Source: NRSC Hyderabad
Fig -2: Satellite
Image
PRE-FEASIBILITY REPORT
8
Fig -3: Land Use
PHOTOGRAPHS OF EXISTING UNITS:
PRE-FEASIBILITY REPORT
9
PRE-FEASIBILITY REPORT
10
PRE-FEASIBILITY REPORT
11
PRE-FEASIBILITY REPORT
12
1.3.2 ENVIRONMENTAL SETTING OF THE SITE:
1.3.4 CONNECTIVITY:
Road
The proposed site is located on State Highway No.9 and is well connected with National
Highway No. 7 via Nagpur. This gives a sound connectivity to the raw material source,
nearest port at Vishakapatanam and nearest market/Mines area of Maharashtra,
Chattishgarh and Odisha.
SR. NO. FEATURES PARTICULARS
1. Location At Village : Heti
Mouza : Ukkerwahi
PO : Udasa
Tehsil : Umred
District : Nagpur
State : Maharashtra.
2. Nearest major road National Highway – 7 : 24.21kms
State Highway– MSH9 : 0.5 kms
3. Coordinates Latitude : 20°55'39.10"N
Longitude : 79°14'47.96"E
4. Nearest railway station Butibori Railway Station : 32kms
5. Nearest village Welsakhara : 2 kms
6. Nearest major city Nagpur : 35 kms
7. Nearest water body Ukkerwahi lake : 0.5kms : N
Amb River : 10 kms: SE
Paradgaon Lake : 3.0 Km : SW
8. Sensitive locations Archaeological structures, Historical
places, Sanctuaries and Biosphere are
not present within 10 km
9. Nearest forest Bhivapur R.F. : 1.0kms : N
PRE-FEASIBILITY REPORT
13
Rail
TUML is sourcing iron ore for existing units from Bellary / Orissa region which is received
at Butibori Railway station this station is 32 Km away from the plant site & Nagpur
railway station is 35 Km. Trucks are used for further transportation to the site. Similarly
raw material for the Ferro alloy plant and other projects envisaged can also be sourced
similarly.
1.3.5 COMMON FACILITIES:
In order to meet the repair and maintenance needs of the various plant units, the
following facilities would he provided.
— Repair shop
— Servicing garage
The common facilities such as Administrative Building, Laboratory, Fire Water Reservoir
and Fire Water Pump house, Workshop Building, Water Storage Reservoir, and Raw
Water Pump House have already been provided in the existing plant.
1.3.6 SOURCE & AVAILABILITY OF WATER:
Water will be sourced from Paradgaon dam and the total water requirement will be
3009 m3/day.
1.3.7 POLLUTION CONTROL MEASURES:
The pollutants in the form of solids, liquids and gases are generated from various
technological units and, if let out as such, will have hazardous effects on the
environment. Pollution of the environment, not only adversely affects the flora and
fauna, but also shortens the life of plant and equipment. This vital aspect, therefore, has
been taken into account while planning the plant and equipment and adequate
PRE-FEASIBILITY REPORT
14
measures have been proposed to limit the emission pollutants within the stipulations of
statutory norms.
However, before starting the plant, the detailed Environmental Management Plan
(EMP) needs to be prepared based on the findings of an Environmental Impact
Assessment study which will cover monitoring of existing environment at site,
assessment of pollution likely to be caused by the proposed plant and its impact on the
socioeconomic, flora & fauna, demography, land use, etc.
2.1. IDENTIFICATION OF PROJECT AND PROJECT PROPONENT:
Acquired by the Topworth group in April 2006, Topworth Urja & Metal Ltd. (TUML)
(erstwhile Shree Virangana Steels Ltd) is a wholly-owned subsidiary of Crest Steel &
Power Pvt Ltd (CSPL, rated CARE BBB/A3). The Topworth group has presence in metals,
mining and power sectors and is led by Mr. Abhay Lodha (Chairman), who has adequate
experience in steel trading and manufacturing.
TUML is engaged in manufacturing of billets with a captive production of sponge iron
along with captive power generation at its plant located at Tehsil Umred, near Nagpur
(Maharashtra). In addition, the company is engaged in trading of iron and steel
products, mainly hot rolled (HR) coil. The site layout plan of TUML is given in Fig 2 on
next page:
Fig
PRE
15
Fig-2: Site Layout Plan
PRE-FEASIBILITY REPORT
PRE-FEASIBILITY REPORT
16
2.2 BRIEF DESCRIPTION OF PROJECT
The existing Plant site of Topworth Urja & Metals Limited (TUML), Nagpur has been
selected for the expansion by installation of proposed:
• Enhancement of capacity of existing Sponge Iron Plant from 60,000 TPA to
291000TPA by installing additional 2 X 350 TPD Rotary Kilns for production of
231000TPA Sponge Iron.
• Enhancement of Capacity of Existing TMT Bar Mill from 66,000 TPA to 1, 50,000
TPA.
• Enhancement Of Capacity of Existing Billet Plant From 240 TPD To 480 TPD Steel
Billets By Installing Additional 2 X 12 Ton Induction Furnaces And also Installation
Of Ladle Refining Furnace For Production Of Better Quality Of Steel.
• 2 X 16.5 MVA Submerged Arc Furnaces Based 50000 TPA Ferro Alloys Plant.
• 400,000 TPA Alloy Steel Melt Shop for Production of Alloy Steel Billets.
• 300000 TPA Bar Mills for rolling of Alloy Steel Bars & wire rods and TMT Bars .
• 1.5 Lac TPA Section Mill for Rolling of Light & Medium Steel Sections like Angles,
Channels and Beams.
• 2.5 Lac TPA Heavy Section Mill for Rolling of Structural Steel Heavy Sections.
2.3 NEED FOR THE PROJECT AND IMPORTANCE TO THE REGION:
2.3.1 GLOBAL STEEL SCENARIO
Global steel production grew enormously in the 20th century from a mere 28 million
tons at the beginning of the century to 1011 million tonnes at the end of 2005. That was
the period when the steel industry developed in Western Europe and the USA followed
by the Soviet Union, Eastern Europe and Japan. However, steel consumption in the
developed countries has reached a high stable level and growth has tapered off.
Towards the end of the last century, growth of steel production was in the developing
countries such as China, South Korea, Brazil and India. Steel production and
consumption grew steadily in China in the initial years but later it picked up momentum
PRE-FEASIBILITY REPORT
17
China produced 220.1 million tons in 2003, 272.2 million tons in 2004 and 349.36 million
tons in 2005. That is much above the production of Japan at 112.47 million tonnes, the
USA at 93.90 million tons, Russia at 66.15 million tones and India around 42 million tons
in 2005.
2.3.2 STEEL PRODUCTION IN INDIA
India is one of the few countries where the steel industry is poised for rapid growth.
India's share in world production of crude steel increased from 1.5% in 1981 to around
3.5 % in 2004. While plant closures and privatization are rare in India, the private sector
is considered to be the engine of growth in the steel industry and technological changes
and modernization are taking place in both the public and the private sector integrated
steel plants in India. Steel production of India accounted for 14.33 million tons in 1990-
91, which gradually increased to 36.12 million tons in 2003-04, as shown in Table below.
The Indian steel industry got a giant importance in the recent past when the Tata Steel
purchased the Corus steel. Today India plays a significant role in the production of steel
in the world. The Indian steel industry is growing at 8.74 % of CAGR.
2.3.3 STEEL BIILET INDUSTRY
Steel billets are manufactured either by ingot casting and rolling through blooming &
billet mills or by forging or by continuous-casting of billets directly from liquid steel.
Billets manufactured by forging are mostly alloy or special steels. Pencil ingots of smaller
sizes, manufactured in mini steel plants are also used as substitute of billets. Due to
better yield, less energy consumption and capital investment, continuous-casting is
being practiced even for production levels of 25,000-30,000 TPA of billets. The billet
being a semi-finished product is used for further processing for production of suitable
products. It is used as a feedstock to rolling mills for production of long products like
wire rods, bars/rods and light structural. Billet is also used extensively in forge shops
and machine shops for production of engineering goods and also as feedstock for
seamless tubes.
PRE-FEASIBILITY REPORT
18
While projecting all-India demand for steel billets, the requirement of the same for
integrated steel plants (primary producers) has not been considered, since their captive
requirement goes for finished steel production. The anticipated production of mild steel
bars and rods and structural from secondary producers during 2006-07 is of the order of
11.8 million tons. Billet requirement for producing the above products will be around
12.5 million tons. The production of pencil ingots/billets from secondary sector during
2006-07 is likely to be about 10 million tons, which includes mild steel, medium/high
carbon steel, alloy steels etc.
In view of the above, demand for steel billets excluding the captive requirement of
integrated steel plants is mainly dependent on production levels of bars and rods and
structural by secondary producers.
EMPLOYMENT GENERATION (DIRECT & INDIRECT)
The proposed expansion project creates employment to 570 people. The total no. of the
people after expansion will be 965.
3.0 PROJECT AT GLANCE
1. Name of the proposed unit : Topworth Urja & Metals Limited (TUML)
2. Location of the proposed unit: Village : Heti
Mouza : Ukkerwahi
P O : Udasa
Tehsil : Umred
District : Nagpur
3. Units to be installed : Submerged Arc Furnaces
Electric Arc Furnace
Induction Furnaces
Ladle Refining Furnaces
Rotary Kilns
TMT Bar Rolling Mills
Alloy Steel Bar / Wire rods & TMT Bar Mills
PRE-FEASIBILITY REPORT
19
Light & Medium Section Mills
Heavy Section Mills
4. Products to be manufactured: Sponge Iron - 231000TPA
Ferro Alloys - 50,000 TPA
TMT Bar - 84000TPA
Steel Billets - 240 TPD
Alloy Steel Billets - 4,00,000 TPA
Alloy Steel Bars &
Wire rods, TMT Bars - 3,00,000 TPA
Steel sections like Angles,
Channels and Beams - 1,50,000 TPA
Heavy Section Mill for Rolling of Structural
Steel Heavy Sections - 2,50,000 TPA
5. Meteorological Site Condition: Air Temperature
Ambient Temperature Max 50 oC
Dry Bulb Temperature 40 oC
Wet Bulb Temp 27 oC
Relative Humidity
Average relative humidity 60%
Rainfall
Average annual rainfall 250 mm
Wind:
Predominant Wind Directions From North
West to South East Max. Wind Speed: 114
Km/hr
6. Cost of Project : 1637.55 Cr.
3.2 PROCESS DETAILS:
• EXPANSION OF EXISTING SPONGE IRON PLANT CAPACITY FROM
60000 TPA TO 2,91,000 TPA BY INSTALLING 2 X 350 TPD ROTARY
KILNS AND OTHER ANCILLIARY UNITS
The proponent has decided to enhance the capacity of existing Sponge Iron Plant from
60,000 TPA to 291000TPA by installing additional 2 X 350 TPD Rotary Kilns for
production of 231000TPA Sponge Iron. The char produced from the rotary kiln will be
used in power plant.
PRE-FEASIBILITY REPORT
20
Waste Heat Recovery Boilers will be installed for flue gas heat recovery of 2 x 48 Tons/hr
Steam generation capacity. The steam so generated from these new Waste Heat
Recovery Boilers (WHRB’s) will be sent to the existing 30 or 35 MW Power Plant turbines
(by providing a new steam pipeline) and one of the existing fossil fuel based
Atmospheric Fluidized Bed Combustion Boilers (AFBC Boiler) of 70 or 80 TPH capacity
will be shutdown. This will not only save the fuel costs incurred in the existing Power
Plants but will also contribute positively by reducing the green house effects and other
environmental hazards caused due to combustion of the fossil fuels.
• FERRO ALLOYS PLANT OF 50000 TPA CAPACITY.
A) SUBMERGED ARC FURNACES (SAF)
Submerged Arc Furnaces (SAF) is the heart of Ferro-alloy plant wherein oxides of
manganese, silicon, iron, phosphorous etc contained in feed ore are reduced by coke/
carbon. These SAFs are located inside the Ferro Alloys Plant.
B) SINTER PLANT FOR MANGANESE ORE FINES:
A sinter Plant will be installed for production of sinter feed material of Manganese
Ore to the Ferro Alloys Submerged Arc Furnaces by using the Manganese Ore fines
available nearby.
• ELECTRIC ARC FURNACE / LRF / VD / AOD BASED ALLOY STEEL BILLET
PLANT OF 4 LAC TPA CAPACITY
In Electric Arc Furnace recycled steel scrap and DRI is melted and converted into high
quality steel by using high power electric Arcs. Modern EAF is a tool to convert solid raw
materials such as Steel Scrap and Sponge Iron into liquid crude steel as fast as possible
and then refine further in secondary steel refining processes such as Ladle Refining
Furnaces, Argon Oxygen Decarburization(AOD) and Vacuum Degassing (VD) Units.
PRE-FEASIBILITY REPORT
21
The Electric Arc furnace consists of a circular bath with a moveable roof, through which
three graphite electrodes can be raised or lowered.
At the start of the process, the electrodes are withdrawn and the roof swung clear. The
steel scrap is then charges into the furnace from a large steel basket lowered from an
overhead crane.
When charging is complete, the roof is swung back into position and the electrodes are
lowered into the furnace. A powerful electric current is passed through the charge, an
arc is created and the heat generated melts the scrap. Sponge Iron is continuously
charged to the liquid metal pool to get the required size of the liquid metal heat. Lime
and fluorspar are added as fluxes, and usually carbon and oxygen are blown into the
melt. As a result, impurities in the metal combine to from a liquid slag.
Samples of the steel are taken and analyzed to check composition and, when the correct
composition and temperature have been achieved, the furnace is tapped rapidly into a
ladle. Final adjustments to customer specification can be made by adding alloys during
tapping or later in a secondary Steelmaking unit.
Refining the Liquid Steel
The Liquid Steel from the EAF is tapped into a pre heated ladle. The ladle is taken to
Ladle Refining Furnace for carrying out refining operations. The ladle is fitted with
porous plug and an inert gas is purged through the steel bath during entire refining
operation. The steel is deoxidized and desulphurised by treating under basic reducing
slag which is rendered fluid by arc heating and also by adding fluorspar to it. For
making/ reducing & desulphurising slag, burnt lime, fluorspar, ferro-silicon and
powdered coke are normally added. The reducing slag reduces the oxides in the bath
and assists in the removal of sulphur as calcium sulphates. The desulphurization is also
promoted in presence of sufficient quantity of manganese in the bath, high basicity of
slag and high bath temperature. By blowing with the inert gas, the metal in the ladle is
stirred and as a result of purging its temperature and composition are equalized and
PRE-FEASIBILITY REPORT
22
non- metallic inclusions would float up to the surface. Necessary ferro-alloys are added
to the liquid steel through a port on the ladle cover after the bath has been fully
deoxidized. A sample is, thereafter, drawn out and sent to the laboratory for final
analysis. Further arc power may be applied to increase the temperature to the desired
level, if necessary. As soon as the final analysis conforms to the desired composition
and proper temperature has been attained, the ready metal is transferred to vacuum
degasser.
Vacuum Degassing
A ladle of liquid is transferred by overhead crane from the LRF unit to the vacuum
degasser. The ladle is placed in a cylindrical tank and is supported inside the tank. The
tank is constructed with the steel plate and is lined with refractory.
When the ladle has been located in the tank and inert gas supply is connected to one or
more porous plugs located in the refractory lining in the bottom of the ladle. Inert gas is
blown through the plug at control rate to stir the liquid metal in the ladle and expose
the surface of the liquid steel by pushing aside the slag layer on the surface.
The tank equipped with a flange around the upper periphery of the tank side wall is
then sealed by a cover which is located in self-propelled car. The car drives over the tank
and then covered is lowered until the flange around the lower edge of the cover is
connected with the tank flange.
An “O” ring seal between the two flanges creates a vacuum tight seal. The volume
enclosed by the tank and the cover is then evacuated by a set of vacuum pumps
connected to the tank. As the pressure in the tank falls, the flow of inert gas through
porous plug in the bottom of the ladle can be adjusted to create the required degree of
turbulence in the ladle. The dissolved gases like hydrogen, oxygen etc are removed by
effusion from the surface of steel to the low negative pressure surrounding atmosphere.
PRE-FEASIBILITY REPORT
23
Argon Oxygen Decarburization (AOD) Converter
Converter process of Argon Oxygen Decarburization (AOD) was introduced in early
1970s, andis now the preferred route for specialty electrical steel and stainless
steels.Secondary refining equipment mainly used in final refining step for stainless
production includesAOD furnace. Stainless steel contains a large amount of chromium
as a basic component.
Since chromium is a strong oxides forming element, during normal refining it is difficult
todecarburize stainless steel to a sufficiently low carbon level while preventing loss of
chromiumthrough oxidation to slag phase.Thus low carbon levels are achieved by
decreasing the partialpressure of carbon mono oxide in the refining atmosphere to
ensure preferential decarburizationin the presence of chromium.
In practice this is in done in AOD furnace by dilution with argon and in VOD furnace by
reducingthe pressure.The AOD Converter Plant shall be located near the furnace. The
Steel scrap/DRI will be melteddown in the Furnaces. The molten metal at temperature
of 1600°-1650°C will be transferred tothe AOD Converter Vessel via overhead crane to
refine to the desired chemical composition byaddition of required Alloys/Fluxes and use
of various gases.
The gases media such as Oxygen, Nitrogen, Argon& Compressed Air is injected into AOD
Converter through High Blowing rate Tuyers for good mixing effect and excellent heat
efficiency.
Continuous Casting of Billets
Liquid metal from VD / AOD or some from LRF directly is transferred to the continuous
casting machine for casting into billets.
The main operations involved in the whole process of turning out billets are:
i) Checking the individual major components of the casting machine and their
synchronized operation;
PRE-FEASIBILITY REPORT
24
ii) Insertion of a dummy bar to close the bottom end of the mould;
iii) Accurate centering of the tundish over the mould;
iv) Transferring the ladle to the casting aisle and placing it on the ladle stand of the
casting machine;
v) Pouring of liquid steel from the ladle through a slide gate mechanism into the lined
tundish;
vi) Pouring of liquid steel into the water cooled mould through tundish;
vii) Passage of liquid steel through water cooled mould tubes initiated by withdrawing
dummy bar;
viii) Oscillation of the mould;
ix) Maintaining a constant level of liquid steel in the mould and introducing lubricants
into the mouldthroughout the casting process;
x) Controlling the intensity of cooling of the emerging billets in the primary and
secondary cooling areas; and
xi) Straightening and cutting of billets.
The most important component of a casting machine is the bottomless water cooled
copper mould. The internal shape and size of the mould tube is the same as that of the
cross section of the billet / blooms to be cast. To initiate casting, a dummy bar is
inserted to the bottom end of each mould, while the other end of the dummy bar is
held by withdrawal/ straightening rolls. Molten steel at the correct temperature is
poured into the mould and when it reaches the stipulated level, the withdrawal rolls,
mould reciprocation unit are operated; cooling water circulation through the mould and
in the secondary circuit is started few minutes earlier the actual casting operation is
started. The dummy bar is withdrawn, followed by hot solidified billet. The cooling
water circulating around the mould has carried away enough heat from the liquid steel
to produce a solid outer skin of sufficient strength to safely envelop the still liquid
portion at the interior that too will be solidified by a secondary cooling. The rates of
solidification and withdrawal are obviously inter linked. Before beginning to withdraw
PRE-FEASIBILITY REPORT
25
the dummy bar it must be ensured that the outer casting of the billet is strong enough
for the process to continue. An error in this regard will cause “break out” of the strand,
which will then remain inoperative for the rest of that heat into casting. For obtaining
satisfactory surface quality of billets and for satisfactory performance in general, the
liquid steel temperature, casting speed, the rates of primary and secondary cooling
must be controlled and matched. Usually this harmonization is developed on the basis
of practice in the particular plant. If the casting speed is increased to raise output, the
quality of the central zone of the billet may suffer because of increase in unsoundness,
chemical heterogeneity and prone to internal cracking.
Billet Processing
The billets from a particular cast are lifted from the cooling bank and stored separately.
When cooled, they are inspected on each face for defects; surface defects are normally
removed by a swing frame grinder, etc. These billets will then be fed to the new Alloy
Steel/Wire Rods/TMT Bar Mill or the Light Section Mills for rolling into long products for
onward sale to the market.
• ALLOY STEEL BARS / WIRE RODS & TMT BARS MILL OF 3 LAC TPA
Billets after heating in Reheating Furnace will be pushed out and taken on Roller Table
to feed into Bar Mill. Coal Gasifiers will be installed to provide Producer Gas to the
Reheating Furnace as fuel for heating. In the Roughing Mills the size of Billet will be
reduced to desired size to feed into Continuous Mill. Before feeding to Continuous Mill
the front end of the bar will be at cut in a crop cum cobble shear.
After Rolling in Continuous Mill, the desired section will be achieved and the Bar will be
divided into multiples of marked length and pushed to Automatic Cooling Bed. These
Bars will be either plain round bars of Alloy Steel or Stainless steel or even TMT Bars
depending upon the market demand.
PRE-FEASIBILITY REPORT
26
Bars on Automatic cooling bed will be aligned by aligning Rollers and the bars will be
taken on outgoing Roller Table.
Bars will be cut to market lengths by cold shear. Cut bars will be handled by Bar
Handling System and made into bundles. Bundles will be lifted by crane and stored in
Finishing Bay and from there loaded onto trucks/trailers for onward dispatches to the
customers.
Just after the bars rolling mills, a separate line having the Wire Rod Block along with the
quenching system and laying head, bundling unit etc will be installed for production of
wire rods from the bars.
This rolling Mill will be of 3 Lac TPA capacity with a provision to roll Alloy Steel and
Stainless Steel Bars/rods or Wire Rods and TMT Bars also. The total production capacity
will be 3 Lac TPA and the different products such as Alloy Steel and Stainless Steel
Bars/rods or Wire Roads and TMT Bars will be rolled as per market demand.
• EXPANSION OF INDUCTION FURNACE BASED STEEL BILLET PLANT FROM
240 TO 480 TPD AND INSTALLATION OF LADLE REFINING FURNACE.
Melting process
2 X 12 Ton capacity Induction furnaces will be installed in the existing sheds. Induction
Furnace crucible is first filled with MS Scrap with the help of Electromagnet installed on
the crane along with CPC (to obtain required carbon percentage in metal). Furnace is
then switched on for heating. MS scrap gets heated when power in Furnace is increased.
MS scrap gets heated and scrap and CPC start to melt. Approx 20% of the total charge
weight comprises of MS Scrap and rest 80% sponge iron of the total charge Weight is
fed into furnace in a small batches for melting through weigh feeder which is installed
on Furnace platform. Slag (molten non – metallic impurities present in the charge)
generated during melting is being continuously removed manually by de-slagging spoon.
Finally, sample is drawn from liquid metal to check the chemical composition in
PRE-FEASIBILITY REPORT
27
Laboratory. Required qty of alloys (silico manganese & ferro silicon is added in metal at
suitable temperature (1610º-1640º Celsius).
The Ladle Refining furnace will be installed for further refining and reduction of Sulphur
and Phosphorus from the Steel as per the market requirements.
The existing Continuous Casting Machine will be used to cast the liquid Steel into Steel
billets.
• EXPANSION OF THE EXISTING TMT BARS ROLLING MILLS FROM 66000 TPA
TO 150000 TPA.
The existing 66000 TPA TMT Bar Mills is having One No of Coal Gasifer, One Reheating
Furnace for heating the Steel Billets and its capacity will be augmented.
The TMT Bars Rolling Mills are comprising of Roughing Mill, Intermediate and Finishing
Mills and Cooling Bed. The capacities of these equipment will be enhanced by adding a
few Intermediate and Finishing Mills and building in considerable amount of
Automation to make the final capacity of the existing TMT Bars Mill of 1.5 Lac TPA.
The final nomenclature of the 1.5 Lac TPA TMT Bar Mill will be generally asbelow:
Reheating Furnace & Producer Gas Plant:
The Steel Billets from The Billet Plant shall be fed into the Reheating Furnace of 25 TPH
capacity. The Reheating Furnace will be refractory lined from inside with burners
arranged for heating the Steel Billets inside the furnace. A provision for either 2 row
charging (billet length of max. 3 meters) or single row charging (billet length of max. 6
meters) will be available. The Billet of Cross section sizes 100 x 100 mm Square upto 130
x 130 Sq. mm and max. 6 meters length will be charged in the Reheating Furnace by
Pusher mechanism.
These Billets will be properly heated and soaked upto a temperature of 1200 Deg Celsius
(Max.). The heated billets will be discharged from the Furnace by Ejector facilitated by
Pinch Rollers at the furnace outlet.
PRE-FEASIBILITY REPORT
28
1 No of Producer Gas Plant will be there for gasification of coal to generate Producer gas
and this producer gas will be fired in the Reheating Furnace to maintain the required
temperature inside the furnace. The entire producer gas from the PG Plant will be fired
in the Reheating Furnace and the Furnace will be equipped with Low SOx/NOx emission
burners and Furnace will be designed such that the SOx/NOx and SPM levels will be
within the prescribed limits. The Furnace Flue gases will be at slightly higher
temperatures i.e. about 650 to 700 Deg C and high efficiency special design Heat
Recuperator will be installed in the flue gas path to heat the combustion air upto 600
Deg C required for the Reheating Furnace and the flue gas temperature will come down
upto 120 Deg C before releasing them to the atmosphere through a 30 M tall stack.
Roughing Mills:
The Hot billets will be transferred to the Roughing Mills of 18” size via Skid transfer and
Roller Tables. Roughing Mill train will consist of 2 Nos 3 Hi / 2 Hi Mill Stands of 460 mm
(18”) size arranged in one line and will be driven at required fixed rpm by a 1250 HP
Electric motor, Fly Wheel, gearbox and pinion stand. Solid Steel Mill rolls of Cast Steel
with passes cut into these rolls will be installed inside these Mill stands and these Rolls
will be driven by the pinion stand by wobblers/spindles. The Hot billets/metal will be
passed through the Roughing Mill stand roll passes many times depending upon the
Rolling pass design.
Repeaters/Tilting Tables/Lifting Roller Tables/Straight Roller Tables will be arranged at
the entry and exit side of the Roughing Mills for enabling the entry and exit of the hot
metal from the Mill Stand passes and for shifting the metal from one pass to the other
pass.
After completing the required Roughing Mill passes, the hot metal will be transferred to
the Intermediate stands of TMT Bars rolling line via Roller Tables.
PRE-FEASIBILITY REPORT
29
TMT Bars Rolling Line:
Intermediate Mills:
This shall comprise of 2 Nos of 360 mm (14”) & 4 Nos of 310 mm (12”) size Intermediate
Mill Stands in which the size of the hot metal will be further reduced.
Intermediate Mill train will consist of 2 Nos 2 Hi Mill Stands of 360 mm (14”) & 4 Nos 2
Hi Mill Stands of 310 mm (12”) size arranged in one line (Tandem Mills) and each of the
Mill stand will be driven at required rpm by a 350 KW DC Electric motor, Fly Wheel,
gearbox cum pinion stand. Solid Steel Mill rolls of Cast Steel with passes cut into these
rolls will be installed inside these Mill stands and these Rolls will be driven by the pinion
stand by wobblers/spindles. The Hot metal will be passed through these Intermediate
Mill stand roll passes depending upon the Rolling pass design.
Bigger size of the TMT Bars i.e. 16 mm upto 32 mm will be finished in these
Intermediate Stands only and Finishing Mill passes will not be required for the same.
Finishing Mills:
This shall comprise of 6 Nos 10” (260 mm) size Finishing Mill Stands in which the size of
the hot metal will be further reduced and final product i.e. TMT Bars of sizes 8, 10 and
12 mm diameter will be rolled.
Finishing Mill train will consist of Continuous 6 Nos 2 Hi Mill Stands of 260 mm (10”)
size arranged in tandem one after the other and will be driven at required variable rpm
by a 250 KW DC Electric motor, gearbox cum pinion stand. Solid Steel Mill rolls of
hardened Steel with passes cut into these rolls will be installed inside these Mill stands
and these Rolls will be driven by the pinion stand by wobblers/spindles. The Hot metal
will be passed through these Continuous Finishing Mill stand roll passes depending upon
the Rolling pass design. Loopers will be provided between these Finishing Mill Stands for
speed variation compensation.
Smaller size of the TMT Bars i.e. 8 mm upto12 mm will be finished in these finishing Mill
passes.
PRE-FEASIBILITY REPORT
30
Once the TMT Bars of the required size are rolled, they are passed through the TMT
quenching line for rapid cooling of these hot bars for enhancing the mechanical
properties of these TMT Bars and imparting higher strength to them. The TMT
Quenching line is designed & supplied by H & K Rolling Mill Engineers Pvt. Ltd. under
license from “Thermex” Germany. Pinch Rolls before & after the TMT Quenching Box
are provided for precise speed control.
After passing through the TMT Quenching line, the TMT Bars are cut online into 60
meters length by the Rotary Flying Shear and conveyed to the Cooling Bed for cooling.
Tail Break Pinch Rolls are provided after Flying Shear but before Cooling Bed for precise
speed control. These bars of 60 meters length travel from one side of the Cooling Bed to
the other side and get cooled by natural heat transfer. These bars are then collected on
the exit roller tables in lots of 10-12 bars and are then cut to commercial lengths varying
from 6 to 12 meters by online Cold Shear as per the customers requirement and are
then bundled and strapped. The Bundles of the finished TMT bars are stacked/stored in
the stockyard and dispatched by trucks/trailers.
Stringent Quality Control Checks are ensured and a elaborate Quality Control (QC)
laboratory is set up for checking the physical and chemical properties of the TMT Bars
rolled in the Rolling Mill.
EOT Cranes of 10 Tons capacity will be installed in the Mill Bay for maintenance and also
in the Stockyard bay for handling the Steel finished TMT Bars.
As the hot metal temperature is about 800 to 1000 Deg C in the Rolling Mill, a elaborate
Roll pass cooling water arrangement will be provided and the same water will be
collected in the scale pit and recycled. The Mill Scale collected in the Scale Pit, which is a
waste by product, will be sold in the market.
A cooling water circuit with water pumps, cooling towers for cooling the return water,
water collection and recycling tanks, flume tunnels for conveying the return water to
PRE-FEASIBILITY REPORT
31
the hot well will be constructed/installed. For the TMT Quenching Box water
contamination is not envisaged and water will be recycled.
• LIGHT & MEDIUM SECTIONROLLING MILLS OF 150000 TPA.
The Nomenclature of the Section Mills for the rolling of Light and Medium sections such
as Angles/Channels and Beams will comprise of the following:
1. Coal Gasifier: A coal Gasifier will be installed for generation of producer gas from
coal which will be fed into the reheating furnace of the Rolling Mill for heating
the billets.
2. Reheating Furnace: A adequate size of the reheating Furnace will be installed for
reheating of the Steel Billets to the required rolling temperatures. These heated
and soaked steel billets will then be fed into the roughing mills for hot rolling.
3. Roughing Mills, Intermediate and Finishing Mills: Adequate number of these
Mills in cross country and tandem arrangement will be provided for hot rolling of
the steel billets into light and medium sections such as Angles / channels and I
beams. The rolled sections will then be cut onto Hot circular saws to get the
required commercial lengths.
4. Cooling Bed: The cooling bed will be installed for cooling of the rolled light and
medium sections in ambient air for further transfer to the Storage cum dispatch
area.
The detailed configuration of the above Mill will be worked out after engaging an expert
Consultant for carrying out the detailed engineering and design. Due care will be taken
at the design and detail engineering stage to provide the required Air and Water
pollution abatement provisions to keep the emission levels within the specified limits.
• HEAVY SECTIONROLLING MILLS OF 250000 TPA.
The Nomenclature of the Section Mills for the rolling of heavy steel sections such as
Angles/Channels and Beams will comprise of the following:
PRE-FEASIBILITY REPORT
32
5. Coal Gasifier: A coal Gasifier will be installed for generation of producer gas from
coal which will be fed into the reheating furnace of the Rolling Mill for heating
the billets.
6. Reheating Furnace: A adequate size of the reheating Furnace will be installed for
reheating of the Steel Billets to the required rolling temperatures. These heated
and soaked steel billets will then be fed into the roughing mills for hot rolling.
7. Roughing Mills, Intermediate and Finishing Mills: Adequate number of these
Mills in cross country and tandem arrangement will be provided for hot rolling of
the steel billets into light and medium sections such as Angles / channels and I
beams. The rolled sections will then be cut onto Hot circular saws to get the
required commercial lengths.
8. Cooling Bed: The cooling bed will be installed for cooling of the rolled light and
medium sections in ambient air for further transfer to the Storage cum dispatch
area.
The detailed configuration of the above Mill will be worked out after engaging an expert
Consultant for carrying out the detailed engineering and design. Due care will be taken
at the design and detail engineering stage to provide the required Air and Water
pollution abatement provisions to keep the emission levels within the specified limits.
4.0 SELECTION OF SITE & LOCATION OF PLANT
Selection of the site for any project is the most important aspect for it’s successful
operation & better economic viability. Proximity to Raw material source, assured supply
of fuel and other infrastructural support are required to be essentially examined while
selecting the site of the plant. The following basic requirements are necessarily required
to be fulfilled.
i. Identified land is in industrial use
ii. Easy access to Raw Material source.
iii. Confirmed water source.
iv. Dedicated power supply
PRE-FEASIBILITY REPORT
33
v. Availability of existing infrastructure.
4.1 SITE ANALYSIS
LAND USE: - The existing land is industrial land.
TOPOGRAPHY: - The topography of the land is plain.
EXISTING LAND USE PATTERN: - The existing land is in industrial use.
EXISTING INFRASTRUCTURE: -All required infrastructure is prevailing in the site.
4.2 Availability of Utilities
For successful running of any unit most important factor is the availability of Raw
Materials, as well as Utilities & Power, Water Connectivity which are required to
efficiently run the Equipment.
5.0 Water System & Plant Utilities:
5.1 Source of Water
Water required for the plant will be drawn from Paradgaon dam sources. Permission will
be taken from concerned authority in due course.
5.2 Water Consumption
Total water requirement for the project will be about 3009 cum/day for the process.
5.3 Fire Protection System
The firefighting system will be designed in conformity with the recommendations of the
Tariff Advisory Committee (TAC) of Insurance Association of India. While designing the
fire protection systems for proposed facilities its extreme ambient conditions need
special attention. Codes and Standards of National Fire Protection Association (NFPA)
will be followed, as applicable.
PRE-FEASIBILITY REPORT
34
6.0 ENVIRONEMENTAL MANAGEMENT PLAN
6.1 Sources of Pollution
The major sources of pollution from proposed units can be classified under the following
heads:
• Pollutants in the waste gases namely, suspended particulate matter (SPM),
sulphur dioxide, NOX and Carbon monoxide, etc.
• Fugitive dust generated during vehicular movement
• Noise pollution
• Waste water and sewage
• Solid Waste Generation
The various measures proposed to mitigate the impact of these pollution sources on the
environment are discussed below:
UTILITY REQUIREMENT (AS PER AMENDMENT REQUEST)
Sr. No. ITEM QTY
EXISTING
REQUIREMENT
PROPOSED
EXPANSION
TOTAL
1. Power 21.75 MW/Hr 70.75 MW/Hr 92.5 MW/Hr
2. Compressed Air 7648 Cu.Mtr/Hr 5981 Cu.Mtr/Hr 13629Cu.Mtr/Hr
3. Water 606Cu.Mtr/Day 2403Cu.Mtr/Day 3009Cu.Mtr/Day
4. Manpower 395 persons 570 persons 965 Man/Day
PRE-FEASIBILITY REPORT
35
6.2 Pollution Control Measures
6.2.1 Air Pollution
Following are the Air pollution control measures proposed:
1. Sponge Iron Plant : Installation of ESP and WHRB
2. Induction furnace : Fume extraction system with Bag Filters followed by stack.
3. Ferro Alloys : Fume Extraction system with Bag Filters followed by stack.
4. All Rolling Mills : Efficient Low Sox/NOx burners with Heat Recuperator followed
by stack. Suitable water treatment system will be provided to
maintain the cooling water quality.
5.Alloy Steel Melt Shop : Fume Extraction System with Bag Filters followed by stack.
6.For control of fugitive dust emissions due to vehicular movement: Water sprinkling
and spraying system will be installed. Internal roads will be asphalted or concreted.
6.2.2 Water Pollution
Requirement of water for proposed unit is only for cooling & domestic purpose; the
same will be recycled for cooling purpose through closed cooling circuit and there will
not be any effluent generation. However domestic effluent will be treated through well
designed septic tanks and soak pits.
6.2.3 Noise Pollution
There will no such high noise generate due to operation of proposed units, however
Noise generation is due to handling of raw materials and finished products. Ear plugs/
ear muff will be provided to the workers working in noisy areas such as the Furnace
floors.
PRE-FEASIBILITY REPORT
36
6.2.4 Solid Waste Management
Following are the solid waste generation due to operation of proposed units:
a. Slag from Electric Arc Furnace, induction furnace / Submerged Arc Furnaces
b. Crop and cobbles from Rolling Mill.
c. Char andDolocharfrom sponge iron plant.
Disposal of Slag from Ferro Alloys:
The Ferro silicon slag produced from the proposed plant shall be dumped in the area
earmarked for solid waste management site within the plant.
The slag can be used for manufacture of Silico-manganese, bricks, etc.
Mill scale generated in the Bar Mill is collected in the mill scale pit and sold in the
market.
The slag generated in M.S. Billets plant and Alloy Steel Billet Plant will be
processed/crushed inhouse in slag granulation plant for recovery of magnetic and the
balance granulated slag will be sold to cement, brick manufacturers and the process
waste will be sold to recyclers along with use for filling of low lying areas.
Char &Dolochar generated in the 2 x 350 TPD Sponge Iron Plant will be mixed with the
fuel mix and burnt efficiently in the AFBC Boilers of the Power Plants.
6.2.6 Plantation
Apart from the aforesaid pollution control measures the management has decided to
develop green belt covering more than 33% of total acquired area. During plantation
landscaping pattern will be considered. The plantation scheme covers the plantation of
ornamentals plants and some local fruit bearing species. At present TUML has planted
over 25000 no. of trees/saplings.
PRE-FEASIBILITY REPORT
37
Selection Criteria of plant species for Green Development Plant
The selection of plant species for the development depends on various factors such as
climate, elevation and soil. Area falls under the tropical region and thus the plants that
area adapted to this condition should be selected. The plant should exhibit following
characteristics in order to be selected for plantation.
1. The species should be fast growing and providing optimum penetrability.
2. The species should be wind firm and deep rooted
3. The species should form a dense canopy.
4. As far as possible, the species will be locally available
5. Species tolerance to air pollutants like PM, SO2, and NOx should be preferred.
6. The species should be permeable to help create air turbulence and mixing within the
belt.
7. There should be no large gaps for the air to spill through.
8. Tree with high foliage density, leaves with larger leaf area and hairy on both the
surface.
9. Ability to withstand conditions like inundation and drought.
10. Soil improving plants (Nitrogen fixing, rapidly decomposable leaf litter).
11. Attractive appearance with good flowering and fruit bearing.
12. Bird and insect attracting tree spacing.
7.0 PROJECT SCHEDULE & COST ESTIMATE(AS PER AMENDMENT REQUEST)
The following is the breakup cost of the proposed expansion project.
PRE-FEASIBILITY REPORT
38
Sr.
No.
Plant Description Estimated
Cost in (Cr.)
1. Expansion of existing Sponge Iron Plant from 60000 to 2.91 Lac
TPA by installing 2 X 350 TPD Rotary Kilns and ancillary
equipment.
150.00
2. Expansion of existing M.S. Billet Plant from 240 TPD to 480 TPD
with Ladle Refining Furnace
51.36
3. Expansion of TMT Steel Bar Rolling Mill from 66000 TPA to 1.5
Lac TPA
132.95
4. 2 X 16.5 MVA Submerged Arc Furnaces (SAF) Based 50000 TPA
Ferro Alloys Plant with sinter plant for making Manganese ore
sinter feed for the SAF.
315.24
5. Electric Arc Furnace/LRF/AOD/VDbased 4 Lac TPA Alloy Steel
Billet Plant
248.55
6. 3 Lac TPA Alloy Steel Bar/Wire Rod/TMT Bar Rolling Mill 251.35
7. 1.5 Lac TPA Light & Medium Section Mill for Rolling of Steel
sections like Angles, Channels And Beams.
162.25
8. 2.5 Lac TPA Heavy Section Mill for Rolling of Structural Steel
Heavy sections like Angles, Channels And Beams.
325.85
Total Estimated Cost in Rs. 1637.55