powermax [ˈpou (ə)r ˈmaks] noun: a system designed to ......2016/10/01  · niraj shah sps branch...

32
© SEL 2017 Copyright © SEL 2017 Niraj Shah SPS Branch of SEL Engineering Services Inc. POWERMAX ® [ˈpou (ə)r ˈmaks] noun: a system designed to maintain stability

Upload: others

Post on 29-Jan-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

  • © SEL 2017Copyright © SEL 2017

    Niraj ShahSPS Branch of SEL Engineering Services Inc.

    POWERMAX® [ˈpou (ə)r ˈmaks] noun: a system designed to maintain stability

  • • POWERMAX – Power Management System Introduction

    • POWERMAX – Functionalities (IDDS, LSP, GCS, A25A)

    • POWERMAX – Simulators

    • MOTORMAX – LV Motor Management System Introduction

    Agenda

  • • POWERMAX – Power Management System Introduction

    • POWERMAX – Functionalities (IDDS, LSP, GCS, A25A)

    • POWERMAX – Simulators

    • MOTORMAX – LV Motor Management System Introduction

    Agenda

  • What Is POWERMAX?

    HMI /SCADA

    IDDS GCS A25A andTie Flow

    High-SpeedLoad

    SheddingEngineering Management

  • Subcycle (Fast)

    Grid-Tied Operation

    Islanded Operation

    Synchronization Systems

    Automatic Decoupling

    Load Shedding

    Controller

    Relay

    Status Trip

    POWERMAX Operation

  • POWERMAX Applications and Goals

    Power Management System (PMS)

    Heavy Industries

    Blackout Prevention

    Process Survivability

    Remedial Action Scheme (RAS)

    Utilities

    Blackout Prevention

    Wide-Area Schemes

    Efficiency

    Security

    Microgrid

    Small Communities

    Resiliency

    Economics

    Renewables

    Speed of Operation

    Adaptive Protection

  • Controller Provides Many Features

    Hardware

    Dual Ethernet

    No Moving Parts

    Substation Graded

    Self-Diagnostics

    2 ms Scan

    Multithread Processing

    Linux OS

    Software

    IEC 61131 Interface

    MIRRORED BITS®

    Web HMI

    Modbus RTU / IP

    DNP3 / IP

    SEL Protocols

    IEC 61850

  • All High-Priority Controller Tasks Must Execute Each Operating Cycle

  • Fast and Scalable Architectures Are Required

    Controller Scan Time: 2 ms

    Controller Scan Time: 2 ms

    Controller Scan Time: 2 ms

    Central FEPScan Time: 2 ms

    20 RelaysScan Time: 2 ms

    200 RelaysScan Time: 2 ms

    1,000 RelaysScan Time: 2 ms

    Small (

  • Redundancy

    All dual systems can be hot, standby, or dual primary

    DependabilitySecurity

    Complexity and Cost

    Single Dual

    DualTMR

    TMR

  • RedundantHMI Servers

    RedundantGateways

    RedundantControllers

    Engineering Work Station

    HistorianServers

    HMIWorkstations / Clients

    Event / SOEServer

    SynchrophasorServerFirewall

    Corporate Networks

    Redundant PMS LAN

    SEL-3355SEL

    SEL-3530SEL

    SEL-3355SEL

    SEL-3530SEL

    SEL-3555SEL

    SEL-3555SEL

    SEL-2730MSEL SEL-2730MSEL

    SEL-2730MSEL SEL-2730MSEL

    SEL-3530SEL

    SEL-3530SEL

    AxionSEL

    Primary FEP

    Backup FEP

    Axion Field I/O

    SEL Relays

    SEL SEL-751ASEL SEL-751A

    SEL SEL-751A

    Substation A

    SEL-2730MSEL SEL-2730MSEL

    SEL-3530SEL

    SEL-3530SEL

    AxionSEL

    Primary FEP

    Backup FEP

    Axion Field I/O

    SEL Relays

    SEL SEL-751ASEL SEL-751A

    SEL SEL-751A

    Substation B

    SEL-2730MSEL SEL-2730MSEL

    SEL-3530SEL

    SEL-3530SEL

    AxionSEL

    Primary FEP

    Backup FEP

    Axion Field I/O

    SEL Relays

    SEL SEL-751ASEL SEL-751A

    SEL SEL-751A

    Substation ...n

  • • POWERMAX – Power Management System Introduction

    • POWERMAX – Functionalities (LSP)

    • POWERMAX – Simulators

    • MOTORMAX – LV Motor Management System Introduction

    Agenda

  • POWERMAX Functions

    HMI /SCADA

    IDDS GCS A25A andTie Flow

    High-SpeedLoad

    SheddingEngineering Management

  • • Power system frequency stability Shed the correct amount of load

    Quickly shed load

    • Process survivability Intelligently select loads that minimize the

    effect on the production process

    High-Speed Load SheddingObjectives

  • • Subcycle speed

    • Dual primary mechanism

    • Primary CLSP

    • Backup UFLSP / ICLT

    • Asset overload shedding• Multiple simultaneous

    contingencies• SOEs and event records• Backup Web HMI

    SEL Load SheddingFeatures

  • • System contingencies Tie line

    Bus tie

    Generator breaker

    Turbine trip

    Asset overload

    • Primary load shedding• Blackout prevention• Fastest – independent• Decision based on

    topology, contingency and load calculations

    Contingency Load Shedding

  • Contingency Breaker Opening Is Determined by 52A and 52B Limit Switches

    Closed

    Open52B52A

    52A 52B

    SPINDLE

    Limit Switch in “CLOSE”

    position

    Limit Switch in “OPEN” position

    Flow of Current

    Breaker in “CLOSE” condition

  • Contingency-Based Load-Shedding System

    Trigger SignalsTrigger Signals

    Load Trip Load Trip

    SignalsSignals

    Contingency BreakersContingency Breakers

    Load Load

    SelectionSelection

    Sheddable LoadsSheddable Loads

    Load PriorityLoad Priority

    5252 A and A and 5252 B B Contact StatusesContact Statuses

    Crosspoint Crosspoint

    SwitchSwitch

    Contingency Contingency Detection Detection

    Contingency Contingency

    Calculation Calculation

    ContingencyContingency

    MW ValueMW Value

    ContingencyContingencyBreaker Close StatusBreaker Close Status

    Breaker Close StatusBreaker Close Status Required to Required to

    Shed MWShed MW

    IRM Set Points IRM Set Points

    Breaker Close StatusBreaker Close Status

    MW ValueMW Value

    Bus TopologyBus Topology

    Load Topology TrackingLoad Topology Tracking

  • Required to Shed (kW)

    19

    n = contingency (event) number

    m = number of sources (generators) in system

    g = generator number, 1 through m

    Ln = amount of load selected for n event (kW)

    Pn = power disparity caused by n event (kW)

    IRMng = incremental reserve margin of all generators (sources) remaining after n event (kW)

    𝐿𝐿𝑛𝑛 = 𝑃𝑃𝑛𝑛 −� 𝐼𝐼𝐼𝐼𝐼𝐼𝑛𝑛𝑛𝑛

    𝑚𝑚

    𝑛𝑛=1

  • Typical CLSP Contingency Screen

  • SEL CLSP Crosspoint Switch Screen

  • SEL CLSP Load Screen

  • Operation Example – Multiple Contingencies

    23

  • Proactive Overload Load-Shedding Integrator

  • Proactive Overload Load-Shedding Screen

  • Backup – Underfrequency Load Shedding

    Why ?

  • Strategy: Keep Frequency at NominalBall in a Bowl Analogy

  • • Dynamically selects loads (only active loads to shed)• Incorporates load consumption (MW) into selection• Tracks power system topology• Selects correct amount of load to shed for every

    underfrequency threshold• Sheds less load with better impact• Easily changes priority of sheddable load

    Advantages of POWERMAX UFLSP

  • • Detection logic monitors frequency and asserts underfrequency trigger

    • Signal conditioning logic in UFLSP protects against chatter

    • Event calculation logic calculates load shed for each event

    • Crosspoint logic determines load trip signals

    UFLSP Algorithm

  • UFLSP Screen

  • 60

    58

    57

    59

    Frequency (F)

    Time

    Normal Operation

    Load Shed

    Blackout

    L3F2

    F2

    L2F1

    L1F1

    F1

    Macrogrid

    Complex Grid

    4

    Inertia-Compensated Load SheddingDo It Right!

    Traditional Failure

    Inertia-Compensated Success

    Load Shed ~ H • DFDT = 4 • 2 = 8 MWLoad Shed ~ H • DFDT = 8 • 1 = 8 MW

    MW Load to Shed

    DFDTF 59

    4 8

    58

    < 0.5

    1280.5–1.0

    > 1.0 12 16

    2 4

    8

    8 12

    Microgrid

  • Questions?

    Slide Number 1AgendaAgendaWhat Is powerMAX?powerMAX OperationPOWERMAX Applications and GoalsController Provides Many FeaturesAll High-Priority Controller Tasks Must Execute Each Operating CycleFast and Scalable Architectures Are Required�RedundancySlide Number 11AgendapowerMAX FunctionsHigh-Speed Load Shedding�Objectives SEL Load Shedding�Features Contingency Load SheddingContingency Breaker Opening Is Determined by 52A and 52B Limit SwitchesSlide Number 18Required to Shed (kW)Typical CLSP Contingency ScreenSEL CLSP Crosspoint Switch ScreenSEL CLSP Load ScreenOperation Example – Multiple ContingenciesProactive Overload Load-Shedding IntegratorProactive Overload Load-Shedding ScreenBackup – Underfrequency Load SheddingStrategy: Keep Frequency at Nominal�Ball in a Bowl AnalogyAdvantages of POWERMAX UFLSPUFLSP AlgorithmUFLSP ScreenInertia-Compensated Load Shedding�Do It Right!Questions?