power system restoration using dfig-based wind …

113
The Pennsylvania State University The Graduate School College of Engineering POWER SYSTEM RESTORATION USING DFIG-BASED WIND FARMS AND VSC-HVDC LINKS A Thesis in Electrical Engineering by Pooyan Moradi Farsani © 2018 Pooyan Moradi Farsani Submitted in Partial Fulfillment of the Requirements for the Degree of Master of Science August 2018

Upload: others

Post on 05-Dec-2021

16 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

The Pennsylvania State University

The Graduate School

College of Engineering

POWER SYSTEM RESTORATION USING DFIG-BASED WIND

FARMS AND VSC-HVDC LINKS

A Thesis in

Electrical Engineering

by

Pooyan Moradi Farsani

© 2018 Pooyan Moradi Farsani

Submitted in Partial Fulfillment

of the Requirements

for the Degree of

Master of Science

August 2018

Page 2: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

The thesis of Pooyan Moradi Farsani was reviewed and approved∗ by the following:

Nilanjan Ray Chaudhuri

Assistant Professor of Electrical Engineering

Thesis Advisor

Mehdi Kiani

Assistant Professor of Electrical Engineering

Kultegin Aydin

Professor of Electrical Engineering

Head of Electrical Engineering Department

∗Signatures are on file in the Graduate School.

ii

Page 3: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Abstract

Application of Voltage Sourced Converter High Voltage DC (VSC-HVDC) linksin power system restoration has been demonstrated in literature through detailedElectromagnetic Transient (EMT)-type models of very small-scale systems. How-ever, studying restoration of large power systems using such detailed models iscomputationally prohibitive. In this thesis, a hybrid simulation platform is proposedfor such studies in which a significant portion of the system, for which developing adetailed three phase model is not necessary, is modelled in a phasor framework andis co-simulated with a detailed EMT-type model of a smaller portion containingVSC-HVDC link. Moreover, in this thesis an innovative restoration strategy isproposed using Doubly-Fed Induction Generator-based wind farms. The strategyinvolves retention of charge in the DC bus following a blackout, thereby avoidingthe need for energy storage, and ‘Hot-Swapping’ between direct flux control modeand conventional grid-connected mode, which does not require resetting of anycontroller dynamic states. An autonomous synchronization mechanism enabled byremote synchrophasors is also proposed. In this black-start strategy a wind farmand a VSC-HVDC connected to a network unaffected by blackout, conduct line andtransformer charging and load pickup for two separate parts of a blacked out area.The proposed ‘Hot-Swapping’ and synchronization approach are applied to connectthe two parts of the grid and switch the wind farm to grid connected mode ofoperation. This approach is verified using the aforementioned hybrid co-simulationplatform for a test system. One shortcoming of DC bus charge retention method isthat the DC bus capacitors gradually discharge and hence, the restoration processhas to begin within a reasonable time frame. In the last part of this thesis it isshown that a DFIG-based wind farm operating in isolated flux control mode, cankeep its DC-bus charged even with an open terminal.

iii

Page 4: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Table of Contents

List of Figures vi

List of Tables x

List of Symbols xi

Acknowledgments xiii

Chapter 1Introduction 11.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11.2 General approach for power system restoration . . . . . . . . . . . . 3

1.2.1 Bottom-up approach . . . . . . . . . . . . . . . . . . . . . . 41.2.2 Top-down approach . . . . . . . . . . . . . . . . . . . . . . . 51.2.3 Combination approach . . . . . . . . . . . . . . . . . . . . . 5

1.3 Role of HVDC links in system restoration . . . . . . . . . . . . . . 61.4 Novel DFIG-based wind farm-assisted power system restoration

method . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71.5 New hybrid simulation platform for power system restoration studies 8

Chapter 2VSC-HVDC link and its control scheme 102.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102.2 Comparison between VSC and LCC technologies . . . . . . . . . . . 112.3 Overall structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . 122.4 VSC: The building block . . . . . . . . . . . . . . . . . . . . . . . . 13

2.4.1 Ideal VSC . . . . . . . . . . . . . . . . . . . . . . . . . . . . 132.4.2 VSC topologies . . . . . . . . . . . . . . . . . . . . . . . . . 172.4.3 Two-level VSC . . . . . . . . . . . . . . . . . . . . . . . . . 22

2.5 VSC controls . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24

iv

Page 5: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

2.5.1 Control of real and reactive power . . . . . . . . . . . . . . . 242.5.1.1 Design and implementation of control . . . . . . . 252.5.1.2 Current control in rotating frame . . . . . . . . . . 26

2.5.2 Phase-locked loop . . . . . . . . . . . . . . . . . . . . . . . . 292.5.3 Control of DC-side voltage . . . . . . . . . . . . . . . . . . . 312.5.4 Control of AC-side voltage . . . . . . . . . . . . . . . . . . . 33

2.6 Voltage/frequency control in islanded mode . . . . . . . . . . . . . 342.7 Summary and conclusion . . . . . . . . . . . . . . . . . . . . . . . . 35

Chapter 3DFIG-based wind farms and their control scheme 373.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 373.2 DFIG-based wind energy system . . . . . . . . . . . . . . . . . . . . 39

3.2.1 Wind turbine model and characteristics . . . . . . . . . . . . 403.2.2 Doubly-fed induction generator model . . . . . . . . . . . . 423.2.3 Pitch control . . . . . . . . . . . . . . . . . . . . . . . . . . 44

3.3 Control strategy of DFIGs . . . . . . . . . . . . . . . . . . . . . . . 443.3.1 Grid-connected mode of control . . . . . . . . . . . . . . . . 45

3.3.1.1 RSC control . . . . . . . . . . . . . . . . . . . . . . 453.3.1.2 GSC control . . . . . . . . . . . . . . . . . . . . . . 47

3.3.2 Isolated mode of control . . . . . . . . . . . . . . . . . . . . 483.3.2.1 RSC control . . . . . . . . . . . . . . . . . . . . . . 483.3.2.2 GSC control . . . . . . . . . . . . . . . . . . . . . . 50

3.4 Summary and conclusion . . . . . . . . . . . . . . . . . . . . . . . . 51

Chapter 4Novel hybrid simulation platform in VSC-HVDC-assisted power

system restoration studies 524.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 524.2 Need for hybrid co-simulation . . . . . . . . . . . . . . . . . . . . . 534.3 Hybrid simulation architecture . . . . . . . . . . . . . . . . . . . . . 54

4.3.1 PSSE-side changes . . . . . . . . . . . . . . . . . . . . . . . 564.3.2 PSCAD-side changes . . . . . . . . . . . . . . . . . . . . . . 57

4.4 Simulation studies: hybrid vs non-hybrid . . . . . . . . . . . . . . . 594.4.1 VSC-HVDC model and controls . . . . . . . . . . . . . . . . 594.4.2 Non-hybrid model . . . . . . . . . . . . . . . . . . . . . . . . 604.4.3 Hybrid model . . . . . . . . . . . . . . . . . . . . . . . . . . 60

4.5 Simulation results . . . . . . . . . . . . . . . . . . . . . . . . . . . . 604.5.1 System restoration: hybrid vs non-hybrid . . . . . . . . . . . 624.5.2 Additional load pick up: hybrid simulation . . . . . . . . . . 64

v

Page 6: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

4.6 Summary and conclusion . . . . . . . . . . . . . . . . . . . . . . . . 65

Chapter 5Novel power system restoration strategy using DFIG-based wind

farms and VSC-HVDC links 675.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 675.2 Proposed black-start process using wind farms . . . . . . . . . . . . 68

5.2.1 Step I: DC-bus pre-charging controls . . . . . . . . . . . . . 695.2.2 Step II: Line charging and load pickup . . . . . . . . . . . . 715.2.3 Step III: PMU-enabled autonomous synchronization . . . . . 725.2.4 Step IV: Hot-swapping . . . . . . . . . . . . . . . . . . . . . 73

5.2.4.1 Notable points regarding ‘hot-swapping’ . . . . . . 745.3 VSC-HVDC controls for black-start . . . . . . . . . . . . . . . . . . 745.4 Simulation study . . . . . . . . . . . . . . . . . . . . . . . . . . . . 75

5.4.1 System configuration . . . . . . . . . . . . . . . . . . . . . . 755.4.2 Cold load effect . . . . . . . . . . . . . . . . . . . . . . . . . 755.4.3 Simulation results . . . . . . . . . . . . . . . . . . . . . . . . 76

5.5 A self-supporting DC-bus scheme for DFIG-based wind farms . . . 835.5.1 Proposed approach . . . . . . . . . . . . . . . . . . . . . . . 845.5.2 Case study and results . . . . . . . . . . . . . . . . . . . . . 86

5.6 Summary and conclusion . . . . . . . . . . . . . . . . . . . . . . . . 87

Appendix ASpace phasor and dq reference frame 89A.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 89A.2 Space phasor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 89

A.2.1 dq-frame representation of a space phasor . . . . . . . . . . . 90

Appendix BLine-commutated HVDC 92B.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 92B.2 Overview on LCC-HVDC . . . . . . . . . . . . . . . . . . . . . . . 92

Bibliography 94

vi

Page 7: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

List of Figures

1.1 Sequence of events during a power system blackout. . . . . . . . . . 3

2.1 AC and DC transmission cost by length. . . . . . . . . . . . . . . . 112.2 Configuration VSC-HVDC system with its control structure. . . . . 142.3 Configuration of a bipolar VSC-HVDC system with metallic return. 152.4 Ideal VSC interfacing DC and AC systems . . . . . . . . . . . . . . 152.5 VSC interfacing DC and AC systems through LC filters . . . . . . . 182.6 Schematic of a half-bridge, single-phase, two-level VSC . . . . . . . 192.7 Schematic of a H-bridge . . . . . . . . . . . . . . . . . . . . . . . . 202.8 Schematic of a three phase three-level VSC . . . . . . . . . . . . . . 202.9 Schematic showing one leg of a three-phase MMC . . . . . . . . . . 212.10 Simplified schematic of the two-level three phase VSC . . . . . . . . 222.11 Signal flow diagram of PWM strategy . . . . . . . . . . . . . . . . . 232.12 Waveforms of the modulating signal (m), carrier signal, and AC-side

terminal voltage, based on the SPWM switching strategy . . . . . . 232.13 Block diagram of the control plant describing the dynamics of the

AC side current in a general dq frame . . . . . . . . . . . . . . . . . 272.14 Block diagram of the current-control scheme for control plant . . . . 282.15 A space phasor and dq rotating frame . . . . . . . . . . . . . . . . . 292.16 Block diagram of a PLL. . . . . . . . . . . . . . . . . . . . . . . . . 302.17 Control block diagram of the PLL. . . . . . . . . . . . . . . . . . . 312.18 Block diagram of the control plant describing DC voltage control. . 332.19 Block diagram illustrating the process of DC voltage control . . . . 342.20 Block diagram illustrating the process of AC voltage regulation at

the coupling point . . . . . . . . . . . . . . . . . . . . . . . . . . . . 342.21 Block diagram of voltage/frequency control of VSC in islanded mode. 36

vii

Page 8: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

3.1 (a) Schematic of constant-speed wind power system. Schematic ofvariable-speed wind power system based on (b) wound rotor induc-tion generator without power electronic converters, (c) doubly-fedinduction generator and power electronic converter, (d) synchronousand asynchronous generator and full power electronics conversion. . 38

3.2 Typical performance-coefficient versus tip-speed-ratio characteristiccurve of a wind turbine. . . . . . . . . . . . . . . . . . . . . . . . . 41

3.3 Block diagram of turbine pitch control (Active only when ωr crossesa threshold). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44

3.4 Grid-connected DFIG-based wind farm control scheme. . . . . . . . 463.5 Isolated DFIG-based wind farm control scheme. . . . . . . . . . . . 49

4.1 (a) Proposed hybrid simulation architecture. The updation of datafrom PSCAD/EMTDC to PSSE and vice-versa takes place at asampling rate, which is equal to the integration time step that islarger among the two platforms. ETRAN library components: (b)‘ETRANPlus-Com,’ (c) ‘AutoLaunch,’ (d) ‘chan-import.’ . . . . . . 55

4.2 VSC-HVDC controls for the positive pole of the inverter. . . . . . . 604.3 Hybrid simulation setup for a 8-machine, 31-bus 4-area power system

with a bipolar VSC-HVDC link with metallic return connecting areas#3 and #4. Individual circuit breakers and the time of operationof those are shown. A portion of area #3 is modeled as detailed3-phase network in EMTDC/PSCAD. The rest of the model is builtin phasor domain in PSSE software. . . . . . . . . . . . . . . . . . . 61

4.4 Dynamic response during system restoration from: (a),(c),(e) non-hybrid and, (b),(d)(f) hybrid simulation platforms. . . . . . . . . . 63

4.5 (a)-(b) Comparison of dynamic behavior of frequency at bus 6interfacing the detailed and the equivalent/phasor model for non-hybrid and hybrid simulations , and (c) a zoomed view of thefrequency comparing responses from non-hybrid (black trace), andhybrid (grey trace) simulations. . . . . . . . . . . . . . . . . . . . . 63

4.6 Hybrid simulation: dynamic response for simulating additional loadpickup in 22-bus test system shown in Fig. 4.3(a). . . . . . . . . . . 64

5.1 DFIG control scheme for black-start: ‘Hot-Swapping’ and autonomoussynchronization are shown. . . . . . . . . . . . . . . . . . . . . . . 69

viii

Page 9: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

5.2 The DFIG-based wind farm is disconnected from the grid at t = 7.0sfollowed by the application of DC-bus pre-charging control. (a)Rotor power input equivalent to power flow from GSC to RSC. (b)DC-link voltage: zoomed views show the instant of stopping GSCand RSC, respectively. . . . . . . . . . . . . . . . . . . . . . . . . . 70

5.3 DC link voltage magnitude when the DFIG-based wind farm operatesin isolated mode with open terminal. . . . . . . . . . . . . . . . . . 71

5.4 Proposed PMU-enabled Autonomous Synchronization. . . . . . . . 735.5 Test system configuration consisting of a 3-area, 6-machine, 27-bus

network including a DFIG-based wind farm connected to a remotegrid through a point-to-point bi-polar VSC-HVDC link. A portionof the 3-area system is under blackout while the remote grid ishealthy. Light grey: model in PSSE. Dark grey: model in PSCAD. . 74

5.6 (a) Wind speed profile. (b) Variation in wind turbine pitch angle. . 765.7 Build up of (a) magnetizing current and (b) terminal voltage of

DFIG-based wind farm during line charging and simultaneous remoteload pickup. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 77

5.8 (a) DC-link voltage of the DFIG-based wind farm and (b) the powerconsumed by the remote loads at bus 8 picked up by the wind farm. 77

5.9 Comparison of voltage build up in phase a at (a) bus 8 from the windfarm and (b) at bus 7 from VSC-HVDC. (c) Overlapping zoomedview. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 78

5.10 Power flow: (a) from 20-bus system to bus 6, (b) out of positivepole VSC station, (c) out of generator G2, (d) from bus 153 to bus3006, (e) from bus 152 to bus 3004, and (f) from bus 205 to bus 154. 80

5.11 Dynamic performance while connecting the breaker BR4 withoutproposed synchronization process: (a) Phase difference betweenvoltages in both sides of breaker BR4. (b) DC-link voltage of DFIG.(c) GSC modulating signals. . . . . . . . . . . . . . . . . . . . . . . 80

5.12 Dynamic performance while connecting the breaker BR4 followingproposed synchronization process: (a) Phase difference betweenvoltages and (b) Frequency from both sides of breaker BR4. . . . . 81

5.13 Frequency of two sides of breaker BR4 (a) before breaker closureand (b) after breaker closure. . . . . . . . . . . . . . . . . . . . . . 81

5.14 Phase a voltages at two sides of breaker BR4 during auto-synchronization.v8a is instantaneous voltage at bus 8 and v7a is instantaneous voltageat bus 7. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82

5.15 (a) DFIG GSC d-axis current and (b) DC-link voltage during closureof BR4 at t = 14.0s and Hot-Swapping. . . . . . . . . . . . . . . . . 82

ix

Page 10: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

5.16 DFIG RSC currents in d and q reference frames during closure ofBR4 at t = 14.0s and Hot-Swapping. . . . . . . . . . . . . . . . . . 83

5.17 (a) Test system configuration consisting of DFIG-based wind farmand its controls, step up transformers, grid, transmission line andremote loads. (b) Flow chart showing the sequence of events in casestudy. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84

5.18 (a) Real and reactive power fed to remote loads. (b) Power outputof the DFIG-based wind farm. (c) DC-bus voltage. (d) DFIG-basedwind farm terminal rms voltage. . . . . . . . . . . . . . . . . . . . . 85

5.19 (a) Rotor power input equivalent to power flow from RSC to GSC,and (b) DC-link voltage, when the DFIG-based wind farm is dis-connected from the grid at t = 7.0s followed by the application ofDC-bus charge retaining process. (c) DC-link voltage between 8sand 24s. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85

5.20 DFIG-based wind farm’s instantaneous terminal voltage (one phase)when operating in: (a) grid-connected mode, (b) isolated modewith open terminal, (c) isolated mode serving 220MW and 45MVArremote load, and (d) isolated mode supplying an additional 90MWand 30MVAr remote load. . . . . . . . . . . . . . . . . . . . . . . . 87

B.1 Schematic of a Graetz bridge. . . . . . . . . . . . . . . . . . . . . . 93

x

Page 11: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

List of Tables

2.1 A comparison between VSC and LCC . . . . . . . . . . . . . . . . . 13

xi

Page 12: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

List of Symbols

ρ air mass density

r turbine radius

Vw wind speed

Cp performance coefficient

λ tip-speed ratio

λopt optimal tip-speed ratio

β turbine pitch angle

A turbine swept area

Cf blade design constant

ωtur rotational speed of turbine blades

ωturopt optimal rotational speed of turbine blades

Pturmax maximum power extracted by turbine

Cpmax maximum performance coefficient

Tturmax maximum turbine torque

ωo rotational speed of turbine blades

fo stator current frequency

fr rotor frequency

s machine slip

ωr rotor rotational speed

p number of pole pairs

λs stator flux linkage

xii

Page 13: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Lm mutual inductance

Ls stator leakage inductance

Lr rotor leakage inductance

Rs stator resistance

Rr rotor resistance

Pe electromagnetic power

Te electromagnetic torque

ims magnetizing current

ids d-axis stator current

iqs q-axis stator current

iαs α-axis stator current

iβs β-axis stator current

idr d-axis rotor current

iqr q-axis rotor current

λds d-axis stator flux

λqs q-axis stator flux

λdr d-axis rotor flux

λqr q-axis rotor flux

λαs α-axis stator flux

λβs β-axis stator flux

Jωt inertia constant of rotating mass

Tωt input mechanical torque applied to generator

vαt α-axis PCC voltage

vβt β-axis PCC voltage

θt angle of PCC voltage

θr rotor angle

θslip generator slip angle

Rfr rotor-side converter filter resistance

Lfr rotor-side converter filter inductance

xiii

Page 14: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Acknowledgments

First and foremost, I would like to thank my advisor Dr. Nilanjan Ray Chaudhurifor giving me the opportunity to be a member of his research group. I greatlyappreciate his guidance, support, and patience.

In addition, I would also like to thank Dr. Mehdi Kiani for accepting to be inmy thesis committee and taking on the responsibility.

Finally, I would like to thank my family. Without their love and support thiswork would not have been possible.

This work is partially supported by NSF under grant award # 1656983. Anyopinions, findings, and conclusions or recommendations expressed in this work arethose of the author and do not necessarily reflect the views of the NSF.

xiv

Page 15: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Chapter 1 |

Introduction

1.1 Introduction

Modern power grid is a very large and interconnected system that spreads over

countries and continents. System planners derive an operating envelop of the

grid by performing rigorous planning studies that take into account all credible

contingencies. Grid operators tend to remain within this envelop to ensure a reliable

operation. However, under certain extremely rare circumstances, faults in such a

large-scale system can lead to a cascaded outage, which in turn can expand rapidly

and cause massive blackouts. History of power grid blackouts have shown that

cascaded failures of such a large system has enormous impact on the socio-economic

aspects of a nation. Although infrequent, the cost of blackouts in the USA, e.g.

the Western Electricity Coordinating Council (WECC) blackout in 1996, the 2003

blackout in the Eastern Interconnection, and the massive blackouts that took place

in 2012 in India run into billions of dollars. In this context, there are two key

aspects of research that are being pursued: (a) research on system monitoring and

control that can prevent the spread of such blackouts, and (b) research on system

restoration that can reduce the downtime of a power grid when such a blackout

takes place. The topic of system restoration is the subject matter of this thesis.

High voltage DC (HVDC) links, especially Voltage Sourced Converter (VSC)-

HVDC, when interconnects two asynchronous AC systems - can act as a ‘firewall’

against the propagation of blackouts. This implies that the blackout taking place

in one AC-area cannot propagate into the other. During the North-East blackout

of 2003, the 330-MW VSC-HVDC link across Long Island Sound, also known as

1

Page 16: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Cross-Sound Cable (CSC), was started up under an emergency order from the US

Department of Energy [1] to facilitate the black-start process.

System planners designate certain generating units as ‘black-start’ units, which

are used during the early phase of the restoration process. Although a growing

portion of generation in modern power grid comes from wind farms, so far only

conventional generators have been considered as black-start units for power system

restoration [2]. In this thesis, it is shown that a Doubly-Fed Induction Generator

(DFIG)-based wind farm can be effectively used for such purpose by means of a

seamless control transition and autonomous synchronization approach without any

need for energy storage systems.

Application of VSC-HVDC links in power system restoration has been demon-

strated in literature through detailed Electromagnetic Transient (EMT)-type models

of very small-scale systems. However, studying restoration of large power systems

using such detailed models is computationally prohibitive. In this thesis, a hybrid

simulation platform is proposed for such studies in which a significant portion of

the system, for which developing a detailed three phase model is not necessary, is

modelled in a phasor framework and is co-simulated with a detailed EMT-type

model of a smaller portion containing DFIG and VSC-HVDC link.

The following are the salient contributions of this thesis -

1. A novel method of black-start using DFIG-based wind farms and VSC-HVDC

systems is proposed, and

2. A hybrid simulation platform for VSC-HVDC-assisted power system restora-

tion study is proposed.

The outline of the thesis is as follows - This chapter briefly discusses different

considerations in power system restoration and general approaches for black-start.

The history and advantages of HVDC-assisted black-start is also briefly discussed

in this chapter. Since one of the main topics in this thesis is VSC-HVDC-assisted

restoration, chapter 2 describes the structure and control scheme of voltage sourced

converters (VSCs), which are used in point-to-point VSC-HVDC systems. Chapter

3 describes the structure, characteristics and controls of doubly-fed induction

generator (DFIG)-based wind energy systems. Using the background information

from chapter 2 and chapter 3, chapter 5 proposes a novel method of power system

restoration using VSC-HVDC systems and DFIG-based wind farms simultaneously.

The effectiveness of this restoration method will be demonstrated by using a hybrid

2

Page 17: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Initiating

events

System

seperation

Formation of

islands

Load/

generator

imbalance in

islands

Islands

blackout

Begin

restoration

process

Figure 1.1. Sequence of events during a power system blackout.

co-simulation platform. This proposed platform, which is a useful tool in large-scale

restoration studies will be discussed in chapter 4.

1.2 General approach for power system restoration

There are several phenomena which could cause blackout in power systems including

system voltage collapse, large deviations in frequency and large imbalance in real

power demand and supply. Severe weather conditions such as hurricanes can also

result in blackouts by causing faults and damages in transmission system. Fig. 1.1

shows the common sequence of events resulting in a blackout. As it can be seen

from Fig. 1.1, any of the aforementioned events can cause the power grid to divide

into several separate so called ‘islands’ with supply/demand imbalance which results

in blackouts in each of these islands.

The methods and considerations for system restoration depend on several factors

including whether the blackout has happened on a local or system-wide scale and

also whether there is access to external support or not. Other factors that should

be brought into consideration include the availability of generating units and

equipments, restoration time, voltage control, transient overvoltages and dynamic

issues [1, 3]. Moreover, protection issues usually arise during restoration due to

high or low voltages, large rate of changes in frequency and excessive unbalance

in voltage or current, which need to be considered [4]. The final objective of

power system restoration is to bring the system to normal operating condition

with a fast and secure method, minimizing costs, losses and outage time. Hence,

3

Page 18: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

power system restoration is a multi-variable, multi-constraint, and multi-objective

optimization problem [5]. There are other constraints such as stability of system

during restoration which needs to be considered. This means that one should

make sure that the voltage and frequency are within the rated range during the

restoration process, and that these variables have small enough deviations as

each load is picked up. Several methods have been used to meet the objectives

and constraints of restoration problem and provide a solution such as case-based

reasoning [6]. Heuristic algorithms such as genetic algorithms [7] and fuzzy logic [8]

have also been applied to system restoration problem.

In case of a blackout, the black-start units start charging transmission lines

and transformers so that the non-black-start units could also start up and connect

to the grid. Based on North American Electric Reliability Corporation (NERC)

definition, black-start units (BSU) are generators with the ability to start without

any outer support from the grid like hydroelectric units [9]. Gas turbine-based

plants can also be profitably used in system restoration as black-start units [10].

Simultaneously, cold loads could be picked up by these generating units based on

related considerations including generation and transmission capacities, the priority

of loads to be picked up and stability considerations. There are general approaches

for system black-start which are employed based on the scale of blackout, and

availability of resources and outer support. These general approaches are briefly

described in the following subsections.

1.2.1 Bottom-up approach

This is the only method, which can be used in case of a full system shutdown with

no outside support available. In this method several islands are formed within the

large system where each island includes BSUs.

After starting up each BSU, transmission lines are charged and loads are picked

up in an area around that unit to form an island. These islands are expanded by

charging more lines and picking up more loads. After the restoration process has

been completed for all of these islands within the system, they are synchronized

and connected to complete the whole system black-start process. Naturally, the

transmission paths and loads are chosen in the optimal way in each island. This

method is referred to as multi-island method [11].

4

Page 19: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Another common approach is to have a core island rather than multiple ones [11].

In this case a larger island with more generating capacity is formed and expanded

gradually until the whole system is restored. It results is a shorter restoration time

besides the fact that it reduces the control effort since there is a single core island

instead of multiple ones. However, this method has several disadvantages. In case

of a failure in core island the black-start process should be restarted. Furthermore,

restoration of critical loads and generation located far from core island will be

delayed, which is undesirable. On the other hand in the multi-island method, if a

failure happens in one of the islands, restoration process can still proceed in others.

However, slower overall restoration and small inertia in islands, which has adverse

effect on stability are the main demerits of multi-island method.

1.2.2 Top-down approach

This approach is dependent on outer support and hence is only applicable in cases

when there is an outer source available to be used for black-start of collapsed

region. In this method a backbone transmission system is restored with support

from outside assistance to restore critical generation, substations and loads [11].

By starting more generation and picking up more loads the black-start process

proceeds. This method has the advantages of restoring critical auxiliary equipments

for generating units in a short time and no need for synchronization since we do

not have multiple islands. However, it is highly dependent on neighboring system’s

supplying capacity and transmission constraints which can limit the amount of

transmittable power from outer system.

1.2.3 Combination approach

In this method a combination of bottom-up and top-down approaches is used

simultaneously [11]. A backbone transmission system is formed with the support

of outer system and generation islands are built and expanded. It results in a

fast black-start process, which allows restoration of multiple areas of a system in

parallel. However, as it could be easily understood, it includes demerits of other

approaches including dependency on neighboring system supplying capacity, more

control efforts due to formation of multiple islands and synchronization needed

before merging them.

5

Page 20: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

1.3 Role of HVDC links in system restoration

High-Voltage DC (HVDC) transmission systems were developed primarily as the

more economical and feasible option for bulk power transmission in long distances.

The excessive line charging current in AC transmission lines in such distances makes

them unsuitable for long distance bulk power transmission; while, there is no such

limitation for underground DC lines [12]. However, since the power grid is still

operating dominantly on AC voltage, the HVDC links need AC/DC converters to

be connected to the rest of the grid. The two common technologies used in AC/DC

conversion in power system are the line-commutated converter (LCC) and the

voltage-sourced converter (VSC) technologies (The structure and control scheme of

these converters will be discussed in detail in chapter 2).

The first commercial HVDC transmission system was built in 1954 in Europe,

connecting Gotland in Baltic sea to mainland Sweden and has been expanding in

capacity since then [13]. The converter stations in this system use LCC technology

which was developed earlier than the VSC technology. Due to its earlier development,

LCC is now a mature technology compared to VSC, which was developed in late

90s and is still a developing technology [14]. Because of the same reason, only a

small portion (<10GW) of installed HVDC worldwide, which is over 100GW and

additional 200GW planned to be added by china [15], is of VSC technology [16].

Although LCC-HVDC systems can be used in black-start process depending on

the availability of other equipments, some of the unique features of VSC-HVDC

systems make them a preferred candidate for restoration purpose. LCC-HVDC

requires a source of AC voltage for operation. As a result, the LCC-HVDC systems

need synchronous condensers to be able to be used for black-start operation. During

restoration, the AC grid behaves as a ’weak’ system, which results in issues including

high dynamic over voltage, voltage instability, large voltage flicker, and harmonic

instability causing challenges for LCC-HVDC systems [16]. Some of these problems

can be solved by connecting synchronous condensers or static VAr compensators

(SVC) at the converter bus. On the contrary, the VSC-HVDC systems do not

need a stiff AC voltage source for operation due to their self-commutation property.

VSC-HVDC systems can independently control real and reactive power while LCC-

HVDC does not have any control over the consumption of reactive power [14].

Furthermore, VSC-HVDC can impose desired frequency and voltage magnitude on

6

Page 21: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

a blacked-out AC grid connected to it and does not need synchronous condensers

for restoration purpose. Besides these advantages, one of the main applications

of HVDC connections is in power transmission from remote resources such as

hydroelectric units. As mentioned earlier, hydroelectric plants are one of the

primary choices as black-start units. Hence, in case of a blackout, the favorable

black-start capabilities of VSC-HVDC systems can be utilized to restore the system

using hydroelectric sources [17].

In case of a blackout, a VSC-HVDC link, which is connected between two

asynchronous networks can act as a "firewall" and prevent the propagation of the

blackout to the system connected to its other end. When a blackout happens in

the AC system connected to one end of HVDC link, energy storage systems ensure

the necessary equipment like control and protection continue to operate for some

time. Later, the healthy system at the other end of the HVDC link can be used to

energize the DC link and charge the capacitors at the local station. This station

can then start operating in black-start mode to control AC voltage and frequency

in the blacked out system and initiate black-start process by transmission line

charging and cold load pickup. Details of principle of operation of VSC HVDC

and its controls are presented in chapter 2, and chapter 5 describes its black-start

features.

1.4 Novel DFIG-based wind farm-assisted power

system restoration method

The generation mix in the modern power grid is undergoing a significant change

as more renewable energy penetration, especially from wind energy takes place.

However, thus far, regulators have refrained from considering renewable energy

resources as resources in the system restoration process. In literature, several works

have studied restoration of microgrids using renewable sources, which is different

compared to transmission system restoration including [18–20]. The AC voltage

is first established by solar PV, battery storage, or diesel generation before the

wind resource is connected. This disqualifies the wind sources described in these

papers as aforementioned black-start unit per NERC definition [9] since they lack

the ability to be started without assistance from the system and energize a dead

7

Page 22: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

bus. Only a few papers [21–25] have proposed wind units for transmission system

restoration where [21], [22] presented very preliminary results; [23] utilized a diesel

generator before connecting the wind unit; [24] needs battery energy storage in the

DC link of the wind unit; and [25] is focused on the static aspects of restoration.

In this thesis a novel restoration strategy is proposed using DFIG-based wind

farms without any conflict with their normal operation or any major deviation

from current widely manufactured and used DIFG-based wind turbine systems. In

this proposed strategy, there is no need for energy storage equipments and hence it

complies with the NERC definition [9] of black-start unit.

Wind farms can generally be operated when connected to power grid or when

feeding isolated loads. There are different control schemes for the operation in these

two modes. Chapter 3 describes two widely-known control schemes for DFIG-based

wind farms in grid-connected and isolated modes of operation. In the proposed

strategy, one of the two control schemes is used to start up a DFIG-based wind

farm in isolated mode. In this mode the wind farm can energize transmission lines

and pick up local or remote loads, while the rest of the system is restored by other

sources. An ‘autonomous synchronization’ method, will be proposed in chapter

5, which can be utilized to connect the wind farm feeding the isolated load, to

the rest of the grid, and switch its control structure to grid-connected mode. The

details of this restoration approach are described in chapter 5 and nonlinear hybrid

simulation studies are presented to validate its performance.

1.5 New hybrid simulation platform for power sys-

tem restoration studies

The restoration process of a power grid involves phenomena that can be associated

with a wide range of time-constants. Phenomena like transformer inrush and

long line switching currents during this process require Electro-Magnetic Transient

(EMT)-type simulation. The EMT-type models are detailed three-phase models

and hence, running this type of simulations is significantly time consuming. Due

to this fact, running this type of three-phase simulation for large-scale systems

is computationally prohibitive. However, voltage, angle and stability issues can

be represented by phasor models in transient stability (TS) simulation, which are

8

Page 23: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

computationally much faster than EMT-type models.

In this thesis, the focus is on restoration assisted by DFIGs and VSC-HVDC.

The tasks performed by a VSC-HVDC link during system restoration include

transformer energization, line energization, generator synchronization, system

inertia and frequency control, cold load pickup, etc. DFIG-based wind farms will also

be used for transformer and line charging, load pickup, and synchronization. The

issues facing these operations include voltage fluctuations, low system damping in

absence of loads in the system, large inrush current during transformer energization,

resonance, and so on. To simulate these phenomena, an EMT-type model is needed.

However, as mentioned, the use of this type of model for simulating a large-scale

system is not feasible. To solve this problem, a hybrid co-simulation platform is

proposed in chapter 4 as a useful tool for large-scale system restoration studies

involving DFIG-based wind farms and VSC-HVDC links. In this platform, a portion

of the system including DFIG and VSC-HVDC link and their surroundings are

modeled in a three-phase EMT environment in EMTDC/PSCAD [26], while the

rest of the system including loads, generators and transmission lines is represented

by a phasor model in PSSE [27]. The exchange of data between the two models

is achieved via ETRAN-PLUS [28] which provides an interface between them. In

chapter 4, details of this hybrid co-simulation platform is presented. Finally, in

chapter 5 the effectiveness of the proposed restoration method is validated using this

platform for a reasonably large system consisting of multiple areas, a DFIG-based

wind farm and a VSC-HVDC link.

9

Page 24: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Chapter 2 |

VSC-HVDC link and its con-trol scheme

2.1 Introduction

Chapter 1 provided a background on the challenges of power system restoration and

general approaches of black-start. As mentioned, VSC-HVDC links can act as a

firewall to restrict the propagation of cascaded failures. Moreover, VSC-HVDC can

significantly improve system restoration. This chapter discusses the fundamentals

of operation and control of VSC-HVDC systems.

The main motivation for developing high voltage DC transmission lines was

their cost effectiveness in transmitting bulk power over long distances. Although

the installation costs are higher for the HVDC transmission system (because of

the needed converter stations and associated infrastructure), they become a more

economical option than AC lines beyond a certain distance. Figure 2.1 shows

variation in cost for an AC transmission compared to an HVDC transmission with

transmission distance. As it is shown in Fig 2.1, for over a certain distance, called

"break-even distance", HVDC transmission provides a lower cost. The break-even

distance is about 700 to 900 Km for overhead HVDC lines. For underground

or subsea cable transmission, this distance is much shorter (typically about 50

Km) [16]. However, this is not the only reason for using HVDC transmission

lines. For underground transmission, the high charging current in medium and long

distance AC cables disqualifies them for such transmission purposes. Moreover, the

losses in DC transmission are lower compared to their AC counterpart. [29].

10

Page 25: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

co

st

co

st

Transmission distanceTransmission distance

AC lineAC line

DC lineDC line

Break-even distanceBreak-even distance

Figure 2.1. AC and DC transmission cost by length.

Since the power grid is dominantly AC, AC/DC converters are needed to interface

HVDC transmission lines with the AC grid. There are three types of devices which

have been used in converters in HVDC transmission systems. Mercury arc valves

where used in the first LCC-HVDC system connecting Gotland to mainland Sweden

in 1954. They were in use until 1970, when thyristors started to be used in HVDC

converters [30]. In the late 90s, insulated gate bipolar transistors (IGBT) became

commercially available for high power ratings. IGBTs where later used to develop

the voltage sourced converter (VSC)-based HVDC systems. The LCC-HVDC and

VSC-HVDC, which are the two technologies currently in use in HVDC transmission

are compared briefly in the following section.

2.2 Comparison between VSC and LCC technolo-

gies

LCC was developed several decades earlier than VSC and hence is a more mature

technology widely used in HVDC systems around the world. As mentioned earlier,

LCC converter stations use thyristors as switching devices which are turned on by

gate pulses when they are forward biased. However, they can only be turned off

11

Page 26: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

when the commutating AC voltage becomes negative. Usually large reactors are

connected to the DC-side of these converters to smooth the voltage and current

ripples. The flow of current in the DC link is unidirectional and hence, the direction

of power flow is reversed by changing the DC voltage polarity. These type of

converters consume large amounts of reactive power. Usually large capacitor banks

are connected on the AC-side to supply the reactive power needed for converters.

Due to the requirement of large capacitor banks and harmonic filters, the footprint

of LCC-HVDC converters is large [16]. The basics of LCC-HVDC systems is briefly

described in Appendix B.

Unlike LCC, VSC is still a developing technology. This type of converters

typically use IGBTs with anti-parallel diodes. IGBTs offer both controlled turn-on

and turn-off capability. Both the magnitude and phase angle of the AC voltage can

be controlled by VSCs, which enables independent control of active and reactive

power exchange with the AC system at both ends. VSC-HVDC systems require

significantly less filtering and hence, the footprint of this type of stations is much

less than LCC. The polarity of DC voltage is fixed in VSC-HVDC links and the

direction of power flow can be changed by reversing the direction of current flow.

The LCC systems rely on AC system voltage for turning off the thyristors. This

means that they face serious challenges when connected to a weak grid. There

is no such restriction for a VSC HVDC link which can work even with weak or

isolated AC systems and offer black start capability. Some of the differences between

VSC-HVDC links and LCC-HVDC links are shown in Table 2.2. VSCs are discussed

in detail later in this chapter.

2.3 Overall structure

Figure 4.2 shows the structure of a VSC-HVDC system with the control scheme

of its converters. The VSCs are built using IGBTs and anti-parallel diodes. The

DC/AC voltage conversion is achieved by controlled turn on and turn off of these

IGBTs. The VSC can independently control the active and reactive power exchange

with the AC system by regulating the magnitude and phase angle of its AC terminal

voltage. The real power flow can be reversed by altering the DC current direction,

while keeping the DC-link voltage polarity the same. In a VSC-HVDC system, one

converter station controls the DC link voltage, while the other usually sets the

12

Page 27: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Table 2.1. A comparison between VSC and LCCLCC V SC

Thyristor base technology IGBT base technologyConstant current direction Current direction changes

with powerTurned on by a gate pulse Both turn on and off isbut rely on external circuit carried out without the

for its turn off help of an external circuitRequires stronger AC systems Operate well in weak

for excellent performance AC systemsRequires additional equipment Has black-start

for black-start operation capabilityReversal of power is done Reversal of power is doneby reversing the voltage by reversing the current

polarity flow direction

active power reference. Furthermore, each converter can independently control the

AC side voltage or reactive power at either end. The VSC-HVDC system shown in

Fig. 4.2 is a monopolar configuration. It is also possible to have a bipolar structure

in which there are two VSC stations at each end; positive pole and negative pole

station as shown in Fig. 2.3. In this case the HVDC link consists of a positive and

a negative pole cable and a metallic return.

The structure of VSCs and the details of their control scheme are the subject

matter of the following sections.

2.4 VSC: The building block

2.4.1 Ideal VSC

Consider Fig. 2.4 where a five-terminal device shown as ideal VSC operates as a

medium for energy transfer between DC and AC systems. This ideal VSC is a

system consisting of passive, memory-less and loss-less circuit elements including

ideal transformer, diode and switch. As shown in Fig. 2.4 the DC-side terminal

voltage and currents are denoted by vdc and idc, respectively. Here, a positive

current is assumed to be the current entering the DC-side port as it appears in

Fig. 2.4. The three remaining terminals identify the AC-side of the VSC and are

13

Page 28: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

ne

ga

tiv

e p

ole

()

vKs

*0

gsc

Q=

ext

P

/ /

L L

()

iKs ()

iKs

PW

M

()

iKs ()

iKs

L L

/ /*

0gsc

Q=

*P

po

siti

ve

po

le

G2

G1

Sy

ste

m #

1S

yst

em

#2

rec

tifi

er

inv

ert

er

inve

rte

r-si

de

co

ntr

ols

rect

ifie

r-si

de

co

ntr

ols

dcr

Vdci

V

tivtrv

* gdi

i

gdi

i * gqi

igqi

i

tdi

v tqi

v

* gdi

v * gqi

v* gqr

v* gdr

v

tdr

v tqr

v

* gdr

i gdr

i gqr

i

* gqr

i

()2

* dcrv (

)2dcrv

3 2tdi

v−

3 2tdr

v−

Figure 2.2. Configuration VSC-HVDC system with its control structure.

14

Page 29: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

G1G2

System #2

positive pole

negative pole

metallicReturn

System #1

Figure 2.3. Configuration of a bipolar VSC-HVDC system with metallic return.

DC

system

Ideal

VSC

AC

system

dcP

dci

dci

dcv0

/ 2dcv

/ 2dcv

gai

gbi

gci

gav

gbv

gcv

gP

gQ

Figure 2.4. Ideal VSC interfacing DC and AC systems

assumed to have voltages vga, vgb, and vgc with respect to a reference node indicated

in Fig. 2.4 as ‘0‘. This reference node is referred to as the DC-side midpoint of the

VSC. Typically, this is a virtual node used to simplify the analysis. The AC-side

voltages are three-phase balanced sinusoidal voltages whose magnitude and phase

angle are controllable. As indicated in Fig. 2.4, the currents iga, igb, and igc leave

the corresponding AC-side terminals of the VSC and enter the AC system.

15

Page 30: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Since AC side voltages are balanced sinusoidal, they can be represented as:

vga(t) = Vg(t) cos [ε(t)]

vgb(t) = Vg(t) cos[

ε(t)− 2π3

]

vgc(t) = Vg(t) cos[

ε(t)− 4π3

]

(2.1)

where, Vg(t) and ε(t) are voltage magnitude and angle of the AC side voltage

respectively. Usually ε(t) is not directly controlled, but it is related to frequency,

ω(t) by:

ε(t) = εo +

∫ t

0

ω(τ)dτ (2.2)

where, εo is the initial phase angle.

Assuming an undistorted sinusoidal Thevenin voltage for the AC grid at the

coupling point, a nonzero average energy transfer, i.e., a nonzero real-power flow,

can exist only if the VSC operates at the same frequency as that of the AC grid,

that is, if ω(t) is made equal to the power system frequency. Thus, if the power

system frequency is constant at a value ωs, then, based on (2.1) and (2.2), the

AC-side voltages assume the forms:

vga(t) = Vg(t) cos [ωst+ εo]

vgb(t) = Vg(t) cos[

ωst+ εo −2π3

]

vgb(t) = Vg(t) cos[

ωst+ εo −4π3

]

(2.3)

Due to the fact that we are assuming an ideal VSC here, the power drawn from

DC system by VSC, Pdc, is equal to the power flowing into the AC system, Pg.

This means:

vdcidc = vgaiga + vgbigb + vgcigc (2.4)

The left side of (2.4) corresponds to Pdc and the right side corresponds to Pg.

Solving (2.4) for idc we have:

idc =vgaiga + vgbigb + vgcigc

vdc(2.5)

The VSC controls result in the generation of a balanced three-phase AC-side

voltage, as shown in (2.3), whose magnitude Vg is also proportional to the DC-side

voltage vdc. This three-phase voltage generates a three phase current. These

16

Page 31: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

voltages and currents result in a power flow, which based on (2.5) translates into a

DC-side current, idc. A constant vdc is needed for the proper operation of the ideal

VSC. This means that the DC system should exhibit a small Thevenin impedance to

the DC-side port of the ideal VSC and the AC grid should exhibit a large Thevenin

impedance to the VSC from any of the coupling nodes. These requirements are

equivalent to stating that a proper operation of the VSC requires the host DC

and AC grids to be of the voltage source and current source nature, respectively.

The ideal VSC behaves as a controllable three-phase voltage source from its AC

side, and it acts as a dependent current source from its DC port. This point will

be further discussed later in this chapter. In practice, a VSC is never directly

connected to DC and AC systems. Rather, there are DC and AC filters connected

to its DC and AC side respectively. This is because the Thevenin equivalent of

the AC system cannot be counted on to ensure the current-source nature of the

AC grid. This is also true for the DC system. Another reason is that there are

harmonics in AC side voltages of the VSC due to its structure which uses switches

to generate these voltages. These voltage harmonics can also result in large current

harmonics if the Thevenin impedance of the AC system is small corresponding to

the harmonic frequencies. These harmonics do not contribute to power transfer

and stress the VSC and possibly the AC system. Hence, some impedance should

be used between the VSC AC-side and the AC system. This impedance acts as a

buffer and ensures a small distortion in currents. Figure 2.5 shows the same VSC

system shown in Fig. 2.4 with LC filters implemented between the VSC ports and

the AC and DC systems. The capacitance C provides a low impedance path for

current harmonics and prevents them from entering the AC system. The ohmic loss

of the inductors are represented by resistance R. On the DC-side, Cdc acts as open

circuit for the DC component of idc and should present a small impedance for the

harmonics in idc. An inductance Ldc might be included to ensure that the capacitor

remains effective regardless of the impedance that the DC system exhibits to the

VSC. Similar to the AC-side filter, Rdc represents the ohmic loss of Ldc.

2.4.2 VSC topologies

VSCs are built with three general topologies, which are called two-level, three-level

and multi-level depending upon how many levels of DC-side voltage they posses.

17

Page 32: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

DC

system

Ideal

VSC

AC

system

dcP

dci

dci

dcv

0

/2dcv

/2dcv

tai tbi tcitcvtbvtav

dc

Rdc

Lli

dc

C

DC-side

filter

RL

C

AC-side

filter

gai gbi gci

gav gbv

gcv

gP

gQ

tP tQ

Figure 2.5. VSC interfacing DC and AC systems through LC filters

18

Page 33: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

DC

sy

ste

m

p

2dcV

2dcV

n

AC system

Figure 2.6. Schematic of a half-bridge, single-phase, two-level VSC

Half-bridge two-level VSC consists of two semiconductor switches connected to

each other as shown in Fig. 2.6. The semiconductor switches should be turned on

and off in a controlled manner to generate an AC voltage in presence of DC voltage

on the other end of VSC. The capacitors act as filters to reduce the distortion in

the DC-side voltage. This type of VSCs can also be built with four switches as

full-bridge converters. The VSC shown in Fig. 2.6 is a single phase VSC. Three

phase VSC can also be built, which consists of three half-bridge converters for the

three phases (see Fig. 2.10). Such a two-level three-phase VSC topology is the focus

of this chapter and will be discussed in detail in the next section.

We can have less harmonics in terminal voltage by using more than two levels.

For example an H-bridge, shown in Fig. 2.7, can be used to synthesize three-level

VSCs. This structure is shown in Fig. 2.8. The three H-bridges are controlled using

three modulating signals which make a balanced three-phase set of waveforms. The

H-bridges are connected in parallel from their DC ports to identify the DC port

of the composite VSC, and their AC outputs are combined by three correspond-

ing single phase transformers whose grid-side windings are connected as a wye

configuration [16,31].

Increasing the number of levels beyond three can reduce the harmonic distortions

even further. One configuration of multi-level VSC, which has come to use in recent

years is known as the modular multi-level converter (MMC) [16, 32]. In this

configuration, multiple half-bridge converters are connected in series from their AC

19

Page 34: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

dci

dcv gv

gi

Hdcv

dci

tv

ti

Figure 2.7. Schematic of a H-bridge

H gav vgaN H Hdcv

gai gbi gci

gbv gcvvgbN vgcN

dcai dcbi dccinv

gAv gBv gCv

gCigAi gBi

dci

Figure 2.8. Schematic of a three phase three-level VSC

side terminals to generate a multi-level AC voltage waveform. The configuration of

one phase of a three phase MMC is shown in Fig. 2.9. This structure consists of

two so-called arms in each phase. In each of the arms there are n series-connected

half-bridge converters, which are each connected to a capacitor in the DC-side as

shown in Fig 2.9. Assume that the DC-side voltage, vdc, is externally supported

and each of the capacitors are charged with a voltage equal to vdc/n. The AC-side

terminal of each half-bridge converter can have 0 or vdc/n as their voltages and

hence, the voltage across each of the arms can be varied from 0 to vdc/2 in steps

equal to vdc/n. The AC-side voltage of MMC can vary in steps of vdc/n by varying

20

Page 35: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Half-

bridge1,1dcv

1,1dci

dcC

Half-

bridgedcC

1,2dci

1,2dcv

Half-

bridgedcC

1,dc ni

1,dc nv

1,1tv

1ti

1ti

1,2tv

1ti

1,t nv

1armv

gi

gv

armL

armL

Half-

bridgedcC

Half-

bridgedcC

Half-

bridgedcC

dcv 0

/ 2dcv

/ 2dcv4armv

4ti

4ti

4ti

4,1tv

4,2tv

4,t nv

4,1dci

4,2dci

4,dc ni

4,1dcv

4,2dcv

4,dc nv

Arm#1

Arm#2

Figure 2.9. Schematic showing one leg of a three-phase MMC

varm1 and varm2. Hence, by having a large number of half bridge converters the AC

side voltage of MMC becomes remarkably smooth. Two-level three phase VSCs,

which are the main focus of this chapter, are discussed in detail in the following

sections. The details of operation of three-level and multi-level VSCs are not

discussed here and can be found in [31,32].

21

Page 36: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

dci

dcv

gai

gbi

gci

gcv

gbv

gav

Figure 2.10. Simplified schematic of the two-level three phase VSC

2.4.3 Two-level VSC

Figure 2.10 shows the simplified schematic of a two-level three-phase VSC circuit.

The circuit consists of three half-bridge converters, one per AC-side terminal. Each

half-bridge converter consists of two controllable semiconductor switches. These

switches are turned on and off in a complimentary manner, which means when one

switch is in ‘on‘ mode the other switch should be ‘off‘. Hence, at each switching

instant, the terminal voltage of the half-bridge converter transitions from one of

the two possible levels, −vdc/2 and vdc/2, to the other one. If this switching action

is periodic, the terminal voltage has a fundamental component, which can be made

to have the desired frequency ωo. Thus we have:

〈vga〉1 (t) = Vg(t) cos [ε(t)]

〈vgb〉1 (t) = Vg(t) cos[

ε(t)− 2π3

]

〈vgc〉1 (t) = Vg(t) cos[

ε(t)− 4π3

]

(2.6)

where, ε(t) and ωo are related as shown in (2.2).

The most frequently used switching strategy for the two-level VSC is the carrier-

based, pulse-width modulation (PWM) strategy. In this strategy, the switching

22

Page 37: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

time

m

0

time0

1

-1

sT

Carrier

Modulating

signal0

1

S1

S4

Figure 2.11. Signal flow diagram of PWM strategy

-1

0

1

m mcarrier

time

-0.5

0

0.5

v t/v

dc

Figure 2.12. Waveforms of the modulating signal (m), carrier signal, and AC-sideterminal voltage, based on the SPWM switching strategy

instants of a constituting half-bridge converter are determined by comparing a

corresponding modulating signal, m(t), with a high frequency periodic triangular

carrier signal, as Fig. 2.11 illustrates. A special case of the PWM strategy, referred

to as the sinusoidal pulse-width modulation (SPWM) strategy, uses a sinusoidal

modulating signal. Figure 2.12 shows the typical waveforms in SPWM strategy.

In a three-phase VSC, there are three modulating signals, one per half-bridge

converter, which are compared with a common carrier signal, and they constitute

a balanced three-phase sinusoidal signal. Based on the SPWM strategy, the

fundamental components of the AC-side voltages are the amplified versions of their

23

Page 38: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

corresponding modulating signals, as:

〈vga〉1 (t) =12vdc(t)ma(t)

〈vgb〉1 (t) =12vdc(t)mb(t)

〈vgc〉1 (t) =12vdc(t)mc(t)

(2.7)

where ma(t), mb(t) and mc(t) are the modulating signals for the three phases.

Assuming:

ma(t) = M(t) cos [ε(t)]

mb(t) = M(t) cos[

ε(t)− 2π3

]

mc(t) = M(t) cos[

ε(t)− 4π3

]

(2.8)

and replacing for ma(t), mb(t), and mc(t) from 2.8 in 2.7 we obtain:

〈vga〉1 (t) =12vdc(t)M(t) cos [ε(t)]

〈vgb〉1 (t) =12vdc(t)M(t) cos

[

ε(t)− 2π3

]

〈vgc〉1 (t) =12vdc(t)M(t) cos

[

ε(t)− 4π3

]

(2.9)

Where M(t) is the magnitude of modulating signals and an independent control

variable. Furthermore, ε(t) is calculated from ωo, which is a control variable, based

on (2.2). Hence, if the DC-side voltage is constant, the fundamental components of

the AC-side terminal voltages constitute a balanced three-phase voltage. Also, if

the magnitude and frequency of the modulating signals are constants, say, M and

ωs, respectively, then the fundamental AC-side voltages take the forms:

〈vga〉1 (t) = vg cos [ωst+ εo]

〈vgb〉1 (t) = vg cos[

ωst+ εo −2π3

]

〈vgc〉1 (t) = vg cos[

ωst+ εo −4π3

]

(2.10)

where the constant vg =12vdcM is the magnitude of the AC side voltage.

2.5 VSC controls

2.5.1 Control of real and reactive power

The control of a VSC is based on the control of real and reactive power that it

exchanges with the AC system, which are shown as Pt and Qt in Fig. 2.5. The real

24

Page 39: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

power control can be employed for power-flow control or, indirectly, for controlling

the DC-side voltage of the VSC. Reactive power control can be directly employed

for ancillary services or, indirectly, for regulating AC voltage magnitude at the point

of common coupling (PCC). The real/reactive power can be controlled based on

voltage-mode or current-mode control strategy [33,34]. In the voltage-mode control

strategy, Pt and Qt are controlled directly by the phase angle and magnitude of

the terminal voltage of the VSC, vg, relative to those of the grid voltage vt. This

control mode is easy to implement, but it makes VSC vulnerable to the AC system

faults. Furthermore, in this control strategy power control through the control of

phase angle and magnitude is based on a steady-state relationship (model) and,

therefore, typically results in a fairly poor transient performance.

In the current-mode control strategy, Pg and Qg are controlled by the AC-side

current, ig, with reference to the AC system voltage vt. In turn, ig is regulated

through the AC side terminal voltage of the VSC, vg. The VSC is protected against

over-currents and external faults since the magnitude of it will be limited if the

magnitude of the reference current is constrained. This is the main reason for

choosing the current-mode control strategy over its voltage-mode counterpart. The

details of this control strategy are described in the following subsections.

2.5.1.1 Design and implementation of control

The VSC is best analyzed and controlled via the concept of space phasors. This

concept is described in appendix A and is used here to describe the VSC controls.

Consider the system shown in Fig. 2.5. The following equations show the

dynamics of AC-side currents of the VSC:

Ldigadt

= −Riga + vga − vta

Ldigbdt

= −Rigb + vgb − vtb

Ldigcdt

= −Rigc + vgc − vtc

(2.11)

Note that since the impedance of capacitors C in the AC-side filter shown in

Fig. 2.5 is high for the fundamental frequency, we have neglected them in writing

(2.11). Multiplying the two sides of equations in (2.11) by 23ej0, 2

3ej

2π3 and 2

3ej

4π3 ,

25

Page 40: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

respectively and adding the resulting equations, we can obtain:

LdIgdt

= −RIg + Vg − Vt (2.12)

The over bars in this equation denote space phasors. It can be seen from 2.12

that the space phasor of AC-side currents can be controlled by the space phasor

of the VSC terminal voltage. In this case the AC system voltage phasor acts as a

disturbance input.

2.5.1.2 Current control in rotating frame

If each space phasor in (2.12) is expressed in d−q frame components (see, Appendix

A), the AC side of the system in Fig 2.5 can be expressed in d− q frame. Thus, we

can obtain:L

dIgddt

= −RIgd + LωIgq + Vgd − Vtd

LdIgqdt

= −RIgq − LωIgd + Vgq − Vtq

(2.13)

From the rotating frame concept described in appendix A we have the following

relations for real and reactive power:

P (t) = Re{

32V (t)I

∗(t)

}

Q(t) = Im{

32V (t)I

∗(t)

} (2.14)

Replacing V t and Ig in (2.14) with (Vtd + jVtq) ejρ and (Igd + jIgq) e

jρ respectively,

we have:Pt(t) =

32(VtdIgd + VtqIgq)

Qt(t) =32(−VtdIgq + VtqIgd) +Qc(t)

(2.15)

where Qc(t) is the instantaneous reactive power generated by filter capacitors. It

can be understood that by knowing the AC system voltage components Vtd and

Vtq, it is possible to control Pt and Qt by controlling the VSC AC-side current

components Igd and Igq.

Equations in (2.13) represent a two input, two output dynamic system. For

this system, Vgd and Vgq are control inputs (which are produced through switching

strategy from other control inputs), Igd and Igq are the outputs and Vtd and Vtq

are the disturbance signals. This system is shown in Fig. 2.13. Here, the SPWM

switching method mentioned in section 2.4.3 is assumed. In this case Vgd and Vgq

26

Page 41: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

dm

qm

2dcV

gdv

gqv

1

Ls R

1

Ls R

L

L

tdv

tqv

AC current dynamics

gdi

gqi

Figure 2.13. Block diagram of the control plant describing the dynamics of the AC sidecurrent in a general dq frame

are proportional to the dq frame components of the three phase modulating signals,

md and mq.

The control purpose for the system shown in Fig. 2.13 is to keep Igd and Igq

at respective reference values, I∗gd and I∗gq, using Vgd and Vgq as control input. To

ensure that these signals are DC in steady state, we need to regulate ω at the

angular frequency of the AC system which is achieved by the action of a PLL. There

are some challenges in designing the control scheme. Igd and Igq are not decoupled

due to the existence of ωIgd and ωIgq terms as seen in (2.13). Furthermore, the

AC system voltage vt depends on the current contribution of the VSC, ig. This is

mostly because of the nonzero Thevenin impedance of the AC system.

Figure 2.14 shows the control scheme, which can mostly overcome these chal-

lenges. There are two decoupled sub-controllers controlling d and q channels. In the

d-axis controller, the error signal, ed = I∗gd − Igd, is passed through a compensator,

27

Page 42: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

*

gdi

gdi

*

gqi

gqi

L

L

( )iK sde

( )iK sqe

du

qu

tdv

tqv

*

gqv/

/

*

gdvdm

qm

0.5 dcv

Decoupling signals

Dq-frame current controller

Figure 2.14. Block diagram of the current-control scheme for control plant

Ki(s), to generate the signal, ud. Two signals Vtd and −LωIgq are added to ud to

generate v∗gd. Adding Vtd as a feed-forward signal mitigates the dependence of Igd

on Vtd, while adding −LωIgq decouples Igd from Igq. Similar process is used for the

q channel. Since we are assuming SPWM switching here, dividing V ∗gd and V ∗

gq by12vdc gives the modulating signals, md and mq.

As it can be seen in Fig. 2.13, the control plant is the same for both d and q

loops. Hence, we can have the same compensator, Ki(s) for both control loops.

The simplest compensator that ensures regulation with zero steady-state error is a

proportional-integral (PI) compensator, as:

Ki(s) =kps+ ki

s(2.16)

where kp and ki are proportional and integral gains, respectively. A set of propor-

28

Page 43: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

d

q

( )t

( )t

( )t t

( )t t

tdv

tqv

tv

Figure 2.15. A space phasor and dq rotating frame

tional gains is:

kp =Lτi

ki =Rτi

(2.17)

For this set of gains we get a first order transfer function as:

Igd(s)

I∗gd(s)=

Igq(s)

I∗gq(s)=

1

τis+ 1(2.18)

where τi is the desired time constant of the closed loop step response. The choice

of compensator parameters based on (2.17) corresponds to canceling the plant pole,

−RL, by the compensator zero, − ki

kp. This results in a first-order closed loop transfer

function which is shown in (2.18).

2.5.2 Phase-locked loop

The main advantage of control in dq reference frame is that it involves DC signals.

This is guaranteed if the angular speed of dq frame, ω(t), is equal to the angular

speed of the grid voltage phasor, ωt(t) (see Fig. 2.15). One can achieve this by forcing

angle ρ(t) to track θt(t). This can be done by the action of a phase-locked loop

(PLL). There are different methods of PLL design. This section briefly describes the

model and performance of a PLL. Figure 2.15 shows a case in which the dq frame

29

Page 44: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

abc

dq

tav

tbv

tcv

tdv

tqv( )H s

s

( )t 1

s( )t

Figure 2.16. Block diagram of a PLL.

is lagging the grid voltage phasor vt. This means ρ(t) is smaller than θt(t). Hence,

in this case ω(t) should be increased so that the dq frame reaches vt. The leading

or lagging of dq frame compared to the voltage phasor can be known by the sign of

vtq (see Fig. 2.15). If vtq is positive it can be understood that the frame is lagging

and ω(t) should be increased. On the other hand, a negative vtg indicates a leading

frame which means ω(t) should be decreased. Figure 2.16 shows the schematic of a

PLL, which can regulate ρ(t) at θt(t). As it can be seen from Fig. 2.16, the grid

voltage is transformed to dq frame using angle ρ (the transformation is described

in Appendix A). Then, vtq is driven to zero by a compensator shown as H(s) to

generate ω, which is then fed into an integrator producing ρ. In practice, the

frequency of grid voltage varies in a small region around the nominal value ωs.

Hence, ω is variable over a narrow range around ωs. To avoid the need for large

compensator output variations in situations with severe transients, the output of

compensator is limited to small positive upper and negative lower bound, and then

offset by a constant ωs to generate ω.

Characterizing H(s) needs development of a control block diagram for the PLL.

We can express vt(t) = vt(t)ejθt(t) in dq frame as:

vtd(t) + jvtq(t) = vt(t)ejθt(t)e−jρ(t) = vt(t)e

j(θt(t)−ρ(t)) (2.19)

Using Euler’s identity expressed as ej(.) = cos(.) + j sin(.) we have:

vtq(t) = vt(t) sin (θt(t)− ρ(t)) (2.20)

30

Page 45: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

( )t( )H s( )t t

( )e t

( )tv t

( )tqv t

s

( )t 1

s

Figure 2.17. Control block diagram of the PLL.

Assuming that ρ(t) is kept close to θt(t), (2.20) can be written as:

vtq(t) ≈ vt(t) (θt(t)− ρ(t)) = vt(t)e(t) (2.21)

Hence, the PLL can be represented by a unity-feedback control loop as shown

in Fig. 2.17. θt(t) is the reference and ρ(t) is the output signal. e(t) is the error

signal and the instantaneous peak of line to neutral grid voltage vt(t) is a time-

varying gain, and the integrator is the control plant. This objective is to design the

compensator H(s) of this control loop tunes the compensator H(s) such that ρ(t)

is tightly regulated at θt(t). Since the command signal θt(t) is a ramp function of

time, H(s) should have at least one pole at s = 0 to ensure that the controller is a

type 2 controller (i.e., overall open-loop gain includes at least two integrators.). In

the simplest case H(s) can be a proportional-integrator (PI) controller. However,

often a more complicated controller is used. In this thesis the PLL described in [35]

is used in study cases.

2.5.3 Control of DC-side voltage

Any imbalance in real power within the area between DC system and VSC shown

in Fig. 2.5 results in variations in DC voltage. Pdc should be controlled via the

VSC to ensure the power balance. Power balance can be formulated as follows in

this system:

Pext − Ploss −d

dt

(

1

2CV 2

dc

)

= Pdc (2.22)

where Pdc = Vdcidc and Pext = Vdcil and Ploss represents the losses in Rdc. The

31

Page 46: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

third term in the left hand side of equation (2.22) is equal to the rate of change of

stored energy in the dc bus capacitor. Lumping the converter losses into the Ploss

term, we can assume that Pdc = Pg and rewrite equation (2.22) as:

(

Cdc

2

)

dV 2dc

dt= Pext − Ploss − Pg (2.23)

where Pg is the VSC ac-side terminal power. Equation (2.23) shows a dynamic

system in which V 2dc is the state variable, Pg is the control input and Pext and Ploss

are the disturbance signals. Since the VSC system enables the control of Pt and

Qt we express the control input, Pg, in terms of Pt. It can be seen from Fig. 2.5,

neglecting C as before, that the dynamics of shown system can be expressed by the

below equation:

L

−→digdt

= −R−→i g +

−→Vg −

−→Vt (2.24)

Multiplying both sides of (2.24) by 32

−→i∗g , assuming

−→i g

−→i ∗

g = i2g and applying real

operator we get:

3L

2Re

{

d−→i g

dt

−→i∗g

}

= −3

2Ri2g + Re

{

3

2

−→Vg

−→i∗g

}

− Re

{

3

2

−→Vt

−→i∗g

}

(2.25)

The second and third terms in the right side of (2.25) are Pg and Pt respectively.

Hence we have:

3L

2Re

{

d−→i g

dt

−→i∗g

}

= −3

2Ri2g + Pg − Pt (2.26)

Solving 2.26 for Pg gives:

Pg = Pt +3

2Ri2g +

3L

2Re

{

d−→i g

dt

−→i∗g

}

(2.27)

The second term in the right side of (2.27) is the real power loss in the resistor

and the third term is the instantaneous real power consumed by the inductor shown

in Fig. 2.5. Hence, substituting Pg from (2.27) in (2.23) we obtain:

(

Cdc

2

)

dV 2dc

dt= Pext − P ′

loss − Pt (2.28)

32

Page 47: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

gdi

3

2tdV−

2

dcV

extP

tP−

lossP 2

dcsC

Figure 2.18. Block diagram of the control plant describing DC voltage control.

where, P ′loss

P ′loss = Ploss +

3

2Ri2g +

3L

2Re

{

d−→i g

dt

−→i∗g

}

(2.29)

Based on (2.28), V 2dc is the output, Pt is the control input and Pext and P ′

loss

are disturbance inputs. Figure 2.18 shows the diagram of plant described by (2.28).

Hence we can form the control scheme shown in Fig 2.19. In the outer loop of

GSC control shown in Fig. 2.19, V 2dc is compared with a reference value and the

error is fed to a compensator, Kv(s) to deliver reference current i∗dg to the inner

current control loop. Pext can be measured and used as a feed-forward signal to

the output of Kv(s) to mitigate its impact on V 2dc. We note that P ′

loss is a small

term compared to Pext. Also, Ploss can not be estimated with certainty and hence

we cannot mitigate its impact by a feed-forward term. Therefore, to eliminate the

steady state error of V 2dc due to changes in Ploss, Kv(s) should have an integrator.

Kv(s) is a PI controller designed by combining pole placement technique with

symmetrical optimum criterion described in [36].

2.5.4 Control of AC-side voltage

Independent of the objective of Pt control, Qt can be controlled as an intermediate

variable to regulate the voltage magnitude of the AC system, vt, at the PCC.

Figure 2.20 shows this control scheme. As it is shown, the difference between

vt and its reference value, v∗t , is fed to a compensator, KV ac. The output of the

compensator is added to Cωvt, which is a feed-forward signal for compensating

33

Page 48: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

dcV

*

dcV

2(.)

2(.)

( )vK s

extP

3

2tdV−

*

gdi/

Figure 2.19. Block diagram illustrating the process of DC voltage control

( )Vac sk− 1

1is +

*

gqI gqI 3

2−

tQ AC system

voltage model tv

( )2.3

2C

C

*

tv

Compensator Limiter

Closed current

control loop

Feed-forward compensation

Figure 2.20. Block diagram illustrating the process of AC voltage regulation at thecoupling point

reactive power produced by filter capacitors, to generate I∗gq. It can be shown that,

assuming a purely inductive AC system, vt is incrementally proportional to −Igq

, with the constant of proportionality being equal to the fundamental-frequency

Thevenin reactance seen from the point of coupling [16]. In practice, as shown in

Fig. 2.20, vt depends also on Pt and, therefore, on Igd due to the resistance of the

lines. However, this dependence is negligible at the transmission level voltage.

2.6 Voltage/frequency control in islanded mode

There are situations where VSCs are connected to small grids or islands, and should

control the voltage magnitude and frequency of the island. This application of

VSCs is very useful when they are connected to a blacked out system without any

reasonable voltage and frequency support. This mode is specifically discussed in

this section and will be applied for power system restoration using VSC-HVDC

systems, which will be discussed in chapter 4. There are different ways of achieving

34

Page 49: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

voltage/frequency (v/f) control. The method represented here is one that has been

used in the case studies of this thesis.

The three modulating signals used for the switching of the two-level three-phase

VSCs can be described as:

ma(t) = M(t) cos [2πfmt]

mb(t) = M(t) cos[

2πfmt−2π3

]

mc(t) = M(t) cos[

2πfmt−4π3

]

(2.30)

where, M(t) is the magnitude and fm is the frequency of the modulating signal.

As mentioned earlier, in this thesis, v/f control mode of VSC is utilized to control

voltage and frequency in a blacked out grid. In such a case, the frequency of the

system, which is connected to the VSC can be determined by the frequency of the

modulating signal, fm. Hence fm should be set as the nominal frequency of the

system, 60Hz. One can use the magnitude of the modulating signal to control the

magnitude of the AC terminal voltage. Figure 2.21 shows the mechanism of v/f

control. The actual AC voltage magnitude is compared with the desired reference

value; and the error is fed to a PI controller to generate the magnitude of the d-axis

component of modulating signal, Md. The q-axis component, Mq can be set equal

to zero. A free running integrator with 60Hz frequency can generate the angle of

d− q axis modulating signals. It results in generation of modulating signals as:

md(t) = Md cos [2πfmt]

mq(t) = Mq sin [2πfmt](2.31)

These signals can then be converted to abc frame based on relationships described

in Appendix A, and be used for converter switching.

2.7 Summary and conclusion

The focus of this chapter was on VSC-HVDC systems. As described, there are

different topologies of VSC systems which can be put in three categories; two-level,

three-level, and multilevel. The control of VSC systems was described based on a

real and reactive power control scheme. This scheme can be used, as elaborated, to

control DC and AC voltages by the VSC. The control design uses the decoupled

35

Page 50: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

dq

to

abc

1

s

0

-

acv*

acv PI

abcm

2 mf

dM

qM

Figure 2.21. Block diagram of voltage/frequency control of VSC in islanded mode.

current control strategy in which d and q axis current components can be used to

regulate the real and reactive powers independently.

The content of this chapter gives adequate background to understand the way

VSC-HVDC systems are used in power grid restoration, which is a key element of

this thesis. The last section of this chapter described how VSC can control the AC

voltage magnitude and frequency in an island or an area without any voltage and

frequency support (i.e. a blacked out area). It will be shown in chapters 4 and 5

that a VSC-HVDC link can perform restoration process in a blacked out system

connected to it.

36

Page 51: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Chapter 3 |

DFIG-based wind farms andtheir control scheme

3.1 Introduction

Chapter 2 described the structure and controls of VSC-HVDC systems. In this

chapter, the model and controls of doubly-fed induction generator (DFIG)-based

wind energy system is presented. This chapter along with chapter 2 provides the

background for, an innovative restoration method proposed in chapter 5.

Renewable energy consists a relatively significant portion of generation in modern

power grid, which is growing at a fast pace. Of all different renewable sources such

as solar, biomass, hydro, etc., wind power has the largest share in the generation

mix.

Different types of wind turbine-generator systems are in use, which can be

broadly classified as either constant-speed (Type 1) or variable-speed systems

(Type 2, 3, and 4). Figure 3.1(a) shows simplified schematic of a Type 1 wind power

system. It is composed of a wind turbine coupled with a squirrel-cage induction

generator via a gearbox. In this type of wind power system, the machine is directly

connected to grid without any power electronic interface. Since the asynchronous

machine consumes reactive power, it is equipped with shunt capacitors as it can

be seen in Fig. 3.1(a). It should be noted that, since the induction machine is

operating in generator mode, the rotor speed is higher than the synchronous speed.

The three dominant types of variable-speed wind energy systems are shown in figs

3.1(b)-(d). Figure 3.1(b) shows schematic of a Type 2 turbine-generator system

37

Page 52: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Doubly-fed

induction

generator

grid

AC/DC/AC

Converter System

PCC

rP

turP

Wind

turbine

WV

tP

tQ

sPGear

box

Wound rotor

induction

generator

grid

PCC

turP

Wind

turbine

WV

tP

tQ

sPGear

box

grid

PCC

turP

Wind

turbine

WV

tP

tQ

sPGear

box

gridAC/DC/AC

Converter System

PCC

tP

tQ

sP

Synchronous/

asynchronous

generator

Squirrel-cage

induction

generator

(a)

(b)

(c)

(d)

turP

Wind

turbine

WV

Gear

box

Figure 3.1. (a) Schematic of constant-speed wind power system. Schematic of variable-speed wind power system based on (b) wound rotor induction generator without powerelectronic converters, (c) doubly-fed induction generator and power electronic converter,(d) synchronous and asynchronous generator and full power electronics conversion.

38

Page 53: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

which is consisted of a wound rotor induction generator connected directly to the

grid. The rotor is connected to an external set of resistors and power electronics via

slip rings. The resistors and power electronics can also be mounted on the rotor to

eliminate the slip rings. These variable resistors are connected to rotor circuit softly

and can rapidly control currents in order to keep power constant during gusting

wind conditions. Figure 3.1(c) shows Type 3 wind generator, which is based on

DFIG. A power electronic converter system is used which allows bidirectional power

exchange between rotor and the grid. As it can be seen from Fig. 3.1(c), the stator

of DFIG is directly connected to grid and hence the stator frequency is determined

by the grid frequency. This type of wind power system will be described in more

detail later in this chapter. The schematic of a Type 4 wind energy system is

illustrated in Fig. 3.1(d). The used machine could be wound rotor synchronous

generator with high number of poles, permanent magnet synchronous generator, or

squirrel cage induction generator. The stator is connected to grid via a converter

system which adjusts the frequency of stator circuit excitation to allow a variable

rotor speed. In this type of system, the gearbox can be omitted so that the machine

spins at the slow turbine speed and generates an electrical frequency lower than

that of the grid.

Among these topologies, Type 3 turbines based on DFIGs (shown in Fig. 3.1(c))

are used in about 50% of variable speed wind farms [37]. The objective of this

chapter is to describe the structure and widely-used control strategies of DFIG-

based wind units. The other types of aforementioned wind turbine-generators are

not discussed in this work.

Later in chapter 5, an approach for power system black-start is proposed, which

uses these well-known modes of control commonly used in current wind energy

systems.

3.2 DFIG-based wind energy system

Figure 3.1(c) shows a schematic of a wind energy system based on DFIG. It can be

seen in Fig. 3.1(c), this structure consists of a wind turbine, a gearbox connecting

turbine and generator shaft, an induction generator, and a converter system. The

stator of the machine is directly connected to the power grid (or isolated loads) and

the rotor is connected to the AC/DC/AC converter system. The converter system

39

Page 54: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

consists of two 2-level, three-phase back-to-back VSCs connected via a common

DC-link.

3.2.1 Wind turbine model and characteristics

Operation of a wind turbine can be characterized by its mechanical power output

as a function of wind speed, which is given by the following equation:

Ptur = 0.5ρAV 3wCp(λ, β) (3.1)

where, ρ is the air mass density, A = πr2 is the turbine swept area, r is the turbine

radius, and Vw is the wind speed. Cp is a nonlinear function of λ and β referred

to as the performance coefficient or power efficiency and is smaller than 0.59 [38].

It can assume different forms. In this thesis it is considered to have the following

form [39]:

Cp = 0.5

[

rCf

λ− 0.022β − 2

]

e−0.255rCf

λ (3.2)

where, β is the turbine pitch angle [40], λ is the tip-speed ratio, and Cf is blade

design constant. λ is defined by:

λ =rωtur

Vw

(3.3)

where, ωtur is the rotational angular speed of turbine blades. Equations (3.1) and

(3.3) show that the mechanical power of wind turbine can be controlled via β and

ωtur. The pitch angle, β, is usually set based on the power output needed from wind

farm. If electrical power is below rated value and the purpose is to generate the

maximum available power, β is set to zero. It is set to 90◦ to stop power generation

in cases like extreme wind conditions and is actively controlled in case the power

generation needs to be regulated below the maximum power level. Figure 3.2 shows

the variation of Cp with respect to λ for two different values of β. As it can be seen,

the value of Cp increases by increasing λ, reaches a peak for an optimum value of

λ, and then decreases. It is usually desirable for wind turbine systems to harness

the maximum power possible from wind. For this purpose, pitch angle β should

be set to zero. Moreover, λ should be adjusted to the optimum value, λopt, which

maximizes Cp. Under this condition, based on (3.3) we have:

40

Page 55: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

0 2 4 6 8 10 12

λ

-0.05

0

0.05

0.1

0.15

0.2

0.25

0.3

0.35

0.4

0.45

Cp

β = 30o

β = 15o

loci of maximum

power point

Figure 3.2. Typical performance-coefficient versus tip-speed-ratio characteristic curve ofa wind turbine.

Vw =rωturopt

λopt

(3.4)

where, ωturopt is the turbine rotating speed corresponding to λopt. Substituting (3.4)

in (3.1) we obtain:

Pturmax =

(

0.5ρAr3Cpmax

λ3opt

)

ω3turopt (3.5)

where Cpmax is the maximum value of Cp corresponding to λopt and β=0.

Defining kopt =(

0.5ρAr3Cpmax

λ3opt

)

, equation (3.5) can be written as:

Pturmax = kopt ω3turopt (3.6)

(3.6) indicates that under a constant λ the maximum attainable turbine power

is proportional to the cube of turbine speed [41, 42]. We can also have a similar

equation for torque as:

Tturmax = kopt ω2turopt (3.7)

These relations are applied to achieve maximum power point tracking (MPPT).

The details of MPPT are descried in the following sections of this chapter along

41

Page 56: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

with other aspects of DFIG control.

3.2.2 Doubly-fed induction generator model

DFIG can be considered as a traditional induction generator with a nonzero rotor

voltage. As it can be seen in Fig. 3.1(c) this machine consists of rotor and stator

windings, which are connected to back-to-back VSCs. The stator windings are

connected to the grid, which imposes the stator frequency, fo. Stator currents

create a rotating magnetic field in the air gap. The rotational speed of this field,

ωo, is proportional to the grid frequency and is defined by:

ωo = 2πfo (3.8)

where, fo is equal to the grid nominal frequency of 60Hz. The induction machine

operates with the rotor rotating at a different speed from the rotational speed of

the magnetic field. This results in flow of current with a different frequency in rotor

windings. This frequency is related to the stator synchronous frequency by:

fr = sfo (3.9)

where, s, referred to as machine slip is defined by:

s =ωo − ωr

ωo

(3.10)

The governing equations of a DFIG can be written in a d-q reference frame

42

Page 57: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

rotating at angular speed ωo as follows [43]:

vds = Rsids +dλds

dt− ωoλqs

vqs = Rsiqs +dλqs

dt− ωoλds

vdr = Rridr +dλdr

dt− (ωo − ωr)λqr

vqr = Rriqr +dλqr

dt− (ωo − ωr)λdr

λds = Lsids + Lmidr

λqs = Lsiqs + Lmiqr

λdr = Lmids + Lridr

λqr = Lmiqs + Lriqr

Pe = λqridr − λdriqr = λdsiqs − λqsids

Te =pωoPe

(3.11)

where, p = number of pole pairs, Lss = Ls+Lm, Lrr = Lr +Lm, λs: stator flux

linkage, Lm: mutual inductance, Ls/Lr: stator/rotor leakage inductance, Rs/Rr:

stator/rotor resistance, Pe: electromagnetic power, Te: electromagnetic torque,

and ims: magnetizing current. All quantities are expressed in per unit (p.u.).

Equations in (3.11) will be used to design the control scheme of such machines,

which is described in detail in the next section.

As shown in Fig. 3.1(c) the generator is connected to the wind turbine via shafts

and gearbox. Another set of equations are needed to model the mechanical interface

between the turbine and the generator. This interface can be represented by six-

mass, three-mass, two-mass and lumped one-mass models [44]. In the one-mass

or lumped model, all types of wind turbine drive train components are lumped

together and work as a single rotating mass. These components include the blades,

hub, and shaft of wind turbine, gearbox and the generator shaft and rotating mass.

In this case the dynamic behavior can be described by:

dωr

dt=

Twt − Te

Jwt

(3.12)

In (3.12), ωr is the generator rotor speed, Jwt is the inertia constant of the rotating

mass, Twt is the input mechanical torque applied to the wind turbine rotor and Te

is the electromagnetic torque of the induction generator. This one-mass model has

been used in this work.

43

Page 58: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

*

r

r

Figure 3.3. Block diagram of turbine pitch control (Active only when ωr crosses athreshold).

3.2.3 Pitch control

Usually, a mechanism is needed to control the amount of wind energy captured by

the turbine. This is achieved via the pitch control mechanism. This mechanism is

also useful in protecting the turbine during extreme wind conditions. High wind

speeds or a reduction in the load demand in an isolated wind farm can result in the

turbine speeding up. As shown in Fig. 3.3, in the pitch angle control mechanism,

the rotational speed of the turbine is continuously measured and compared to a

pre-set threshold level. The error is fed to a PI controller which generates the pitch

angle, β. With this process in use, an increase in the rotational speed beyond the

threshold level causes β to increase, which results in less wind power input and

hence, a decrease in rotational speed.

3.3 Control strategy of DFIGs

This section discusses common control methods for DFIGs in two modes of their

operation when connected to power grid and when feeding isolated loads. As

mentioned earlier, two back-to-back VSCs are used for controlling DFIG, which

are switched based on sinusoidal PWM described in chapter 2. These include

the rotor-side converter (RSC), connected to induction machine rotor, and the

grid-side converter (GSC), connected to induction machine stator. The generator

is controlled via these converters, which is based on decoupled current control

strategy. As mentioned in chapter 2, in this commonly-used strategy, rotor and

44

Page 59: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

stator currents of the induction machine are converted to a rotating d− q frame

using transformations described in Appendix A. Each of these decoupled current

components can be used to control variables including AC and DC-link voltages,

and real and reactive powers. These control schemes are discussed in detail in the

following sections.

3.3.1 Grid-connected mode of control

In grid-connected mode of control, it is usually desirable to harness the maximum

available power from wind. Also, the AC voltage at the terminal of the DFIG needs

to be regulated. RSC control structure is designed to achieve these objectives. GSC

is designed to control DFIGs DC-bus voltage and the reactive power [45].

3.3.1.1 RSC control

Figure 3.4 shows the control scheme of a grid-connected DFIG-based wind turbine.

In this mode of operation, RSC is responsible for AC voltage control at PCC and

MPPT. For this purpose, the decoupled current control strategy is used. As shown

in Fig. 3.4 the d-axis rotor current idr can be used for AC voltage control, and

q-axis rotor current iqr can be used for MPPT. The AC voltage magnitude at the

PCC is regulated by droop control shown in Fig.3.4. Since the stator is connected

to grid and the effect of stator resistance is not significant, stator magnetizing

current, ims, can be considered to be constant.

The d-axis of the reference frame is aligned with the stator flux vector position.

This will give us the angle θo shown in Fig. 3.4. For this purpose, the stator flux

is estimated measuring the PCC voltage vt and the stator current is, see Fig.3.4,

and the d-axis is locked with the estimated flux vector using a phase locked loop

(PLL). The PLL model was described in section 2.5.2 in chapter 2. The following

relationship is used for flux estimation in a stationary α− β reference frame, which

can later be converted to a rotating d-q frame (see Appendix A).

λαs =∫

(vαt −Rsiαs)dt , λβs =∫

(vβt −Rsiβs)dt (3.13)

An encoder measures the rotor angle of DFIG, θr. Subtracting θr from θo gives

the slip angle θslip (see Fig. 3.4). Aligning the d-axis of reference frame with the

45

Page 60: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

()2

* dcv (

)2

dcv

()

vKs

* qgi

qgidgi

* dgi

dtv

qtv

* dri

dri

* qri

qri

r

dcv

C

dcI

frL

frR

fgR

fgL

WV

sP

sg

QQ

=

rigi

gv

*0

gsc

Q=

tv

msi

vcK

()2

•d dt

* tv

tv

oslip

t

t

r

ofgqg

Li

ofgdg

Li

2

{(

)}

mslip

rrfr

dr

ms

ss

LL

Li

iL

++

()

slip

rrfr

qr

LLi

+

rv

si

tv

si

* drv* qrv

* dgv

* qgv

ext

P

3 2dV

ext

I

r

* r

2

3

opt

mms

K

pLi

Figure 3.4. Grid-connected DFIG-based wind farm control scheme.

46

Page 61: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

stator flux vector position, the following equations are obtained for flux, current

and voltages:

λs = λds = Lmims = Lssids + Lmidr

iqs = −Lm

Lssiqr

vds = Rsids +dλds

dt− ωoλqs

vqs = Rsiqs +dλqs

dt+ ωoλds

vdr = (Rr +Rfr)idr + (σLrr + Lfr)didrdt

− ωslip(σLrr + Lfr)iqr

vqr = (Rr +Rfr)iqr + (σLrr + Lfr)diqrdt

+ ωslip{L2m

Lssims + (σLrr + Lfr)idr}

(3.14)

where, ωslip = ωo − ωr, σ = 1 − L2m

LssLrr, Lss = Ls + Lm, Lrr = Lr + Lm, λs:

stator flux linkage, Lm: mutual inductance, Ls/Lr: stator/rotor leakage induc-

tance, Rfr/Lfr: RSC filter resistance/inductance, Rs/Rr: stator/rotor resistance,

and ims: magnetizing current. These equations are basically the same general

equations of DFIG appearing in (3.11) with a specific alignment of the d-q frame,

and the impedance of rotor filters, Lfr and Rfr included.

As shown in Fig. 3.4, the d-axis current reference i∗dr is generated from a voltage

droop control with droop gain Kvc. The q-axis current reference i∗qr is determined

by MPPT control which is described by the following equations:

i∗qr =−2T ∗

e

3pLmims, T ∗

e = Koptω2r (3.15)

where, Te: generator’s electromagnetic torque, p: number of generator’s pole pairs

and Kopt holds the same expression as described in section 3.2.1.

The above equation shows that the optimal torque, T ∗e is proportional to iqr. It

is obvious from equation (3.14) that vqr can be used to control iqr. Furthermore,

vdr can be employed to regulate idr. The expressions for vdr and vqr shown in (3.14)

are used for control loop design. The first two terms on the right side of these

expressions could be used to design PI controllers as in equations (2.16) - (2.18),

while the third terms are feed-forward terms, see Fig. 3.4.

3.3.1.2 GSC control

The GSC is also regulated based on vector control strategy where the d-axis of the

rotating frame is aligned with the voltage−→Vt at PCC. Figure 3.4 shows GSC control

47

Page 62: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

scheme for a grid connected DFIG. The position of PCC voltage vector is estimated

using a PLL indicated as PLL2. The purpose is to maintain the voltage constant at

its rated value at the DC link between the two converters. The d-channel of GSC

current is used for this purpose while the q-channel is utilized for reactive power

control. Assuming that the stator supplies all of demanded reactive power, Q∗gsc is

usually set to zero as shown in Fig. 3.4. The control scheme for such purposes was

described in chapter 2 under DC voltage control discussion, which can be applied

here. Hence, the details of control implementation will not be repeated here.

3.3.2 Isolated mode of control

This is the other common mode of operation of wind farms. In this mode the wind

farm is connected to and feeds isolated loads in a microgrid. In this case, in absence

of any grid support, the voltage magnitude and frequency at the terminal depend

on wind farm. Unlike the grid-connected mode, in this case MPPT cannot be

followed due to the fact that the generated power by the wind farm should match

with the load demand. The GSC performs the same DC voltage and reactive power

control as in the previous mode, while the RSC is responsible for building up and

controlling the AC voltage at the PCC as described in the next section.

3.3.2.1 RSC control

The DFIG should supply a constant voltage and frequency at its terminal and since

it is not connected to power grid its flux is no longer determined by the grid voltage

and should be regulated by rotor excitation current. A common control strategy

for a DFIG-based wind farm feeding an isolated load is proposed in [43] and is

usually referred to as the direct flux control. The d-axis of rotating reference frame

is aligned with stator flux vector as in grid-connected mode. Thus the q-axis stator

flux, λqs, is equal to zero. Similar relationships hold for voltages, currents, and

fluxes as described in (3.14). Figure. 3.5 shows the control scheme of an isolated

load-feeding DFIG.

As shown in Fig. 3.5, using (3.14) and applying appropriate feed-forward

terms, two PI controllers in the inner current control loop are used to generate the

commands v∗dr and v∗qr for RSC. From (3.14) the q-axis reference current is given

48

Page 63: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

()2

* dcv (

)2

dcv

()

vKs

* qgi

qgidgi

* dgi

dtv

qtv

* dri

dri

* qri

qri

r

dcv

C

frL

frR

fgR

fgL

WV

sP

sg

QQ

=

rigi

gv

*0

gsc

Q=

tv

qsi

* tv

tv

* msi

msi

1 s0

2

oslip

t

r

* r

t

1s

dt

s

vR

+

/ss

mL

L−

ofgqg

Li

ofgdg

Li

2

{(

)}

mslip

rrfr

dr

ms

ss

LL

Li

iL

++

()

slip

rrfr

qr

LLi

+

rv

si

* drv* qrv

* dgv

* qgv

d

q

d q

ot

00

dcI

ext

I

3 2dV

ext

P

� �

Figure 3.5. Isolated DFIG-based wind farm control scheme.

49

Page 64: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

by the following relationship:

i∗qr = −Lss

Lm

iqs (3.16)

From equations (3.14) we can get:

(

Lss

Rs

)

dims

dt+ ims = idr +

1 + σs

Rs

vdt (3.17)

where, σs =Lss−Lm

Lm

Equation (3.17) shows that idr can be used to control ims. In Fig. 3.5, a PI

controller is shown, which controls ims and uses 1+σs

Rsvdt as a feed-forward term.

The outer loop of this controller maintains a desired terminal voltage magnitude.

As shown in Fig. 3.5, the stator flux angle θo is derived directly by integrating

demanded angular frequency ω0 = 2π60rad/s. Therefore, the angle needed for the

decoupled current controls in the RSC is derived from:

θslip =

ω0dt− θr (3.18)

where, θr is the rotor angle measured by an encoder as shown in Fig. 3.5.

3.3.2.2 GSC control

The control structure of GSC in DFIG’s isolated mode of control uses a rotating

frame in which the d-axis is oriented along the terminal voltage vector position and

is similar to the grid-connected mode which is described in section 3.3.1.2.

One of the complications in GSC-side control in direct flux control mode is

how to determine the terminal voltage vector position. In this mode, aligning the

voltage vector using PLL is not recommended due to the presence of harmonics

when there is no grid voltage support. As proposed in [43], the reference angle θt

to align terminal voltage vector−→Vt with the d-axis, see Fig. 3.5, could be derived

from:

θt = θ0 +π

2(3.19)

where, θ0 is the angle obtained from free running integrator described in RSC

control.

50

Page 65: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

3.4 Summary and conclusion

This chapter described the two common methods of control for a variable-speed

DFIG-based wind energy system. These systems are typically used in a grid

connected mode or an isolated-load feeding mode. Usually in grid connected mode,

the purpose is to harvest the maximum possible power and inject it into the power

grid via a method known as maximum power point tracking (MPPT). The rotor-

side converter controls are designed for this purpose as was described in details.

The terminal AC voltage is another variable being controlled by RSC using droop

control approach. The GSC is used to retain the DC-link voltage at rated level as

well as controlling the reactive power of the converter. One PLL is utilized to align

the d-axis of GSC rotating frame with the PCC voltage and another PLL is used

to align d-axis of RSC frame with stator flux.

In the isolated mode the DFIG is controlled based on direct flux control method.

In this mode the voltage at PCC is built up by DFIG through the control of

magnetizing current by RSC. Due to the lack of voltage support from the grid, it is

not practically possible to use PLLs and hence the d-axis of RSC is aligned with

an arbitrary angle generated by a free running integrator on rated frequency. The

GSC structure is the same as grid-connected mode.

Building on these common control schemes a novel method of power system

black-start is proposed in chapter 5. Such an approach facilitates the ease of

adoption in wind generation industry, which uses such common control techniques.

The detailed switched models that were described in chapters 2 and 3 are used

to perform EMT-type simulations in EMTDC/PSCAD platform. The objective of

these simulations is to study novel control strategies involving VSC-HVDC and

DFIG-based wind farms for black-start of power system. However, black-start is a

system level analysis. Hence, these detailed models cannot be used for simulations

of large systems for black-start studies. A hybrid co-simulation platform is proposed

in chapter 4, which retains fidelity of components like VSC-HVDC links and DFIG-

based wind farms, while ensuring that simulation is computationally manageable

for a large-scale system.

51

Page 66: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Chapter 4 |

Novel hybrid simulation plat-form in VSC-HVDC-assistedpower system restoration stud-ies

4.1 Introduction

Power system planners traditionally use software tools that are based on positive

sequence, fundamental frequency phasor models. Examples of a few commercial

power system planning software are PSLF [46], PSSE [27], and DIgSILENT [47].

However, traditional planning software tools may not be adequate for simulating

restoration of large systems. One of the reasons behind this is the wide range

of bandwidth of interest for the system restoration including phenomena with

small time constants like transformer inrush current, voltage fluctuations, long line

switching along with relatively slower phenomena including inertial and frequency

support, and different system stability challenges. This gets even more complicated

when we consider the black-start process assisted by VSC-HVDC links.

When an HVDC link, especially VSC-HVDC, interconnects two asynchronous

AC systems, it acts as a ‘firewall’ against the propagation of blackouts. This implies

that the blackout taking place in one AC-area cannot propagate into the other.

During the North-East blackout of 2003, the 330MW VSC-HVDC link across Long

Island Sound, also known as Cross-Sound Cable (CSC), was started up under an

52

Page 67: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

emergency order from the US Department of Energy [17]. The CSC was used

to restore service to Long Island, although it was not equipped with blackstart

controls. This link was also instrumental in stabilizing system voltage as lines,

transformers, etc. were energized, generators were synchronized and cold loads

were picked up. The dynamic voltage restoration capability was very important in

riding through these transients [17]. [48] studied black-start using VSC-HVDC for

a small system with two generators and three loads. The simulation was conducted

in EMTDC/PSCAD platform.

Simulating a large system in an EMT-type platform is computationally pro-

hibitive and unnecessary. In this chapter a ‘hybrid’ co-simulation platform for

system restoration application for large power grids is proposed that will have the

ability to capture faster transients in a certain region of the grid while the rest of

the system is modeled in the phasor-domain. The content of this chapter has been

reported in [49].

4.2 Need for hybrid co-simulation

Dynamic simulation of power grid restoration is essentially a ‘system-level’ problem.

However, it is unique in the sense that unlike traditional planning simulations, the

dynamic response of interest during restoration has a wide range of time-constants.

Challenges during restoration stem from (a) frequency, angle, and voltage stability

issues that can be represented by phasor models, and (b) faster transients like

transformer inrush and long line switching currents that demands EMTP-type

representation. None of the previous studies done on VSC-HVDC assisted sys-

tem restoration [48, 50, 51] have considered a medium or large system in their

simulation-based studies. The tasks performed by a VSC-HVDC link during system

restoration include transformer energization, line energization, generator synchro-

nization, system inertia and frequency control, cold load pickup, etc. Different

restoration functionalities of the HVDC system have been presented using EMT-

DC/PSCAD [26]-type models [48, 50, 51]. Although the simulation run-time of

such models is manageable in a small-scale system, it becomes unrealistic when

considering large power grids.

ETRAN [52] is a software that has been widely used by system planners under

such circumstances. The software converts a user-defined section of the large power

53

Page 68: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

system model in phasor domain in PSSE [27] into a detailed three-phase model in

EMTDC/PSCAD. It represents the rest of the power system by an ideal voltage

source behind an equivalent Ybus network that retains the short circuit capacity

(SCC) as viewed from the boundary nodes. Unfortunately, such a representation

has two drawbacks:

1. It does not have any dynamic representation of the rest of the power system

2. It can not allow the simulation of system restoration of the rest of the grid or

a portion thereof

Herein comes the motivation for a ‘hybrid ’ simulation for handling this problem

where the rest of the power grid in phasor-domain will be retained and co-simulated

along with the detailed three-phase model in EMTDC/PSCAD. Such a hybrid

simulation will be able to capture different time constants of interest. The hybrid

simulation architecture is described next in detail.

4.3 Hybrid simulation architecture

A hybrid simulation approach is proposed in which the HVDC link and a region

surrounding it is represented using a detailed three-phase EMT-type model. The

reason is that the influence of HVDC in initiating system restoration is limited

up to a certain boundary of the network, beyond which, the focus of research

is into optimal resource allocation subject to the system’s static and dynamic

constraints. The rest of the system is modeled by its phasor equivalent in which

the network will be represented by the algebraic model (Ybus) and the generators by

their subtransient dynamic models. In the boundary between these two regions, the

three-phase variables are converted into equivalent phasors and this information is

exchanged between the models.

The proposed hybrid simulation architecture is shown in Fig. 4.1(a). The

detailed three-phase model runs in EMTDC/PSCAD platform using time-step of

the order of micro-seconds, and the rest of the system runs with time-step of the

order of milliseconds in PSSE [27] platform - simultaneously. The interface between

these two platforms is provided by ETRAN-PLUS [28]. The interface is performed

in the following steps -

54

Page 69: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

ETRAN PLUS

PSCAD/EMTDC

Intel Visual Fortran Compiler

VSC-HVDC, DFIG, and

surrounding buses

(3-phase EMT model)

PSSE

.bat files

Large AC system

(phasor model)

ETRCOMPSCAD

boundary

bus

DFT+ve Seq

P, Q

Update

current

injection

PSSE

boundary

bus

Update

voltage

phase,

frequency • Map IP address

• Establish socket connection

INITAD

Hybrid Co-Simulation Platform

abc/

+,-,0funda

mental

dq/abc

E+

ETRAN PSSE -> PSCAD

ANGLE

Bus 1 ID Port

100 1 2000

E+

ETRAN Plus

Process AutoLaunch

E+

ETRAN Plus

Computer/Socket Mapping

Tstart (PSS/E Com) = 1.0

(a)

(b) (c) (d)

Figure 4.1. (a) Proposed hybrid simulation architecture. The updation of data fromPSCAD/EMTDC to PSSE and vice-versa takes place at a sampling rate, which is equalto the integration time step that is larger among the two platforms. ETRAN librarycomponents: (b) ‘ETRANPlus-Com,’ (c) ‘AutoLaunch,’ (d) ‘chan-import.’

• Creating boundary buses in PSCAD model: The boundary buses are user-

defined. From .raw loadflow files in PSSE, a Ybus matrix is created followed by

LDU reduction, which represents the network equivalent of the PSSE model

and is presented in a Network Equivalent sub-page of the PSCAD model.

The steady state short and open circuit response of this equivalent is identical

to that of the PSSE loadflow solution.

• Creating boundary buses in PSSE model: From the boundary buses of the

phasor model, the PSCAD side is modeled as dynamic loads and generators

in a positive sequence, fundamental frequency current injection framework,

Fig. 4.1(a).

• Data exchange - PSSE to PSCAD: At each integration time-step of the PSSE

case, the node voltages of the network equivalent are calculated from the

55

Page 70: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

phasor model and are converted to the equivalent abc frame quantities using

dq − abc transformation, see Appendix A. This is used to update the bus

voltages in PSCAD boundary buses as shown in Fig. 4.1(a).

• Data exchange - PSCAD to PSSE: The boundary buses in the PSSE model

needs to update the positive sequence fundamental frequency real and reactive

powers of the dynamic loads or generation at each sample of integration time

step, see Fig. 4.1(a). If vn,p, and in,p for p : a, b, c are the sampled voltages and

and currents in three phases in the PSCAD model, then a Discrete Fourier

Transform (DFT) is performed followed by calculation of the fundamental

frequency positive sequence voltage current phasors V+ and I+, respectively.

Thereafter, the required real and reactive power can be calculated as described

in equation (4.1).

Vk,p =N−1∑

n=0

vn,p{

cos(

−2πk nN

)

+ j sin(

−2πk nN

)}

, k ∈ Z, p : a, b, c

Ik,p =N−1∑

n=0

in,p{

cos(

−2πk nN

)

+ j sin(

−2πk nN

)}

, k ∈ Z, p : a, b, c

V+ = 13

(

Vr,a + αVr,b + α2Vr,c

)

, I+ = 13

(

Ir,a + αIr,b + α2Ir,c

)

α = 1∠120◦, α2 = 1∠240◦

P+ + jQ+ = V+I∗+

(4.1)

where, subscript ‘r′ corresponds to fundamental frequency components.

The models ‘talk’ to each other by establishing ‘socket’ connection through

the mapping of IP addresses. There are several modifications needed in both

PSCAD and PSSE models for the purpose of running a hybrid simulation using

ETRAN-PLUS, which is described next.

4.3.1 PSSE-side changes

Step I: A hybrid simulation case setup starts with conversion of either a small

or large portion of a system simulated in PSSE to a PSCAD model. The detailed

three-phase model, which is intended to be simulated in PSCAD should then be

added to this created PSCAD file. This conversion is performed using ETRAN

by selecting the desired buses. These selected buses are converted to PSCAD

model along with components attached to them. The portion of the network which

56

Page 71: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

has been converted to PSCAD using ETRAN should be removed from simulation

system built in PSSE.

Step II: The removed portion of network should be replaced by a generator

model at the boundary bus. This generator model is key for the interface to PSCAD

as the values of real and reactive power acquired from PSCAD at each time step

are used to modify this generator output. The generators’ initial real and reactive

power should be equal to the values derived by loadflow in original system in PSSE

so that the loadflow remains the same even after removing of converted portion

from PSSE simulated model.

Step III: There are three dynamic models, which should be defined in .dyr file

which includes dynamic details of all other system components for PSSE simulation.

The first model called ‘INITAD’ is intended to establish port number and IP

addresses for connection between PSSE and PSCAD. In the second model called

‘ETRCOM’ the mentioned port number is entered along with the bus number to

which the generator model is connected. This model transfers voltage magnitude

and angle data from PSSE simulation to PSCAD simulation. This transferred data

is used to update the equivalent voltage source which is representing the portion

of system modeled in PSSE. The positive sequence real and reactive power from

PSCAD simulation are calculated using DFT and the resulting data is transferred

to PSSE simulation as described in equations (4.1). The transferred data is used to

update the dynamic generator model. Since PSSE is a non-interactive software and

output channels can not be viewed during simulations, variables could be transferred

and plotted in PSCAD environment using a model called ‘CHOUT’. Details on the

dynamic definition of mentioned models is described in ETRAN-PLUS Manual [28].

4.3.2 PSCAD-side changes

Step I: An ETRAN source model called ‘Electranix-Gen’ is automatically

added to the boundary buses when ETRAN is used for the discussed conversion of

PSSE model to PSCAD which is one of the components needed to establish the

interface between two software. This source model is provided by ETRAN-PLUS

in an imported PSCAD library. It is essential that it is set to act as a dynamic

source model in its component settings.

Step II: Two components named ‘ETRANPlus-Com’ and ‘AutoLaunch’ [28]

57

Page 72: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

which could be found in a library provided by ETRAN-PLUS should be added at

the beginning of PSCAD simulation. These are shown in Fig. 4.1(b) and Fig. 4.1(c),

respectively. The number of ports should be entered in ‘ETRANPlus-Com’ setting

as they were defined in ‘ETRCOM’ model. A variable named ‘TStart’ should

also be set in this component’s setting. This variable indicates the exact time

when interface between two software begins and should be preferably set at a

moment after the PSCAD simulation reaches a steady state. Prior to this time

PSCAD and PSSE simulations run independently without any communication.

The ‘AutoLaunch’ component is used to start PSSE simulation at the same time

when PSCAD simulation in started. This is done by entering the address of batch

file which initiates PSSE case simulation in this component’s settings. Fig. 4.1(d)

shows a component called ‘chan-import’ which can be added optionally in PSCAD

simulation to import and plot PSSE simulation variables including voltages, angles

etc. provided that the dynamic model named ‘CHOUT’ has been defined in PSSE

case .dyr file as discussed in previous subsection.

Step III: The user can add new models from PSCAD library in the PSCAD file

to expand the model. For example, in our work, the VSC-HVDC and DFIG-based

wind farm was built using the components from the PSCAD library.

A few important points should be kept in mind while performing such hybrid

simulations. It should be noted that the generator, turbine, and exciter components,

which are converted to PSCAD from PSSE require a detailed dynamic model. These

dynamic models are specified in dynamic model file (i.e. the .dyr file), which includes

dynamic details of every component in a PSSE simulation case. User should refer

PSCAD to this file by adding it’s address in these components’ settings.

One complication in the process of preparing a hybrid simulation case arises

from choosing the proper bus to connect generator model in PSSE simulation

and problem of how to keep lines between boundary bus and other buses as they

are. When a portion of the system is converted from PSSE to PSCAD the lines

connected to the boundary bus are not converted to PSCAD and they will not

exist in PSSE simulation either. A practical approach is to create an additional

bus in PSSE simulation which connects to the boundary bus by a lossless line and

connect boundary bus-connected transmission lines to this new bus. The generator

model, which should be added to PSSE simulation after deleting the converted

58

Page 73: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

portion should also be connected to this additional bus. Such an approach solves

the discussed problems without making any practical change to the study case.

It should be noted that specific versions of Fortran compiler should be used by

PSCAD in order for this hybrid simulation platform to work. Intel Fortran V.15 [53]

has been used effectively in this work.

4.4 Simulation studies: hybrid vs non-hybrid

As shown in Fig. 4.3, a 31-bus 4-area power system with 8 generators is considered

for simulation study in this work. A bipolar VSC-HVDC link (see section 2.3 in

chapter 2) connects area #3 to area #4. A phasor model of area #1, #2, and #3

was built in PSSE software. A portion of area #3 was then converted to equivalent

PSCAD model using ETRAN, see Fig. 4.3. A detailed switched model of the VSC

HVDC link was built in PSCAD connecting area #4 to area #3, which is described

next.

4.4.1 VSC-HVDC model and controls

A PWM-controlled bipolar 2-level VSC-HVDC link is considered in this work and

the DC lines are represented by Bergeron models with rated voltage of 350kV. The

rectifier-side VSC controls the reactive power and the DC voltage using standard

current control scheme in d− q frame. During black start, the inverter-side VSC

works in AC voltage and frequency control mode to energize the system during

the initial phase. AC voltage is controlled using the magnitude of the modulating

signal. In this stage the reference for power control loop is the measured amount of

real power and hence the phase of the modulating signal comes from a free-running

oscillator. Later the control mode is shifted to AC voltage and real power control

mode. AC voltage is controlled in the same fashion and the phase of modulating

signal is used for power control. Figure 4.2 shows the VSC control mechanism for

the positive pole of the inverter. The rectifier of VSC system is in DC-bus voltage

and reactive power, Q, control mode. The details of VSC-HVDC system control

were described in chapter 2 and will not be repeated here.

59

Page 74: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Inveter-Side Control Diagram

dq

to

abc

-

1

s0p

dm

p

qm0

p

abcm

*p

iP

p

iP1

0

S

0

S

0 : V-f control mode

1 : V-P control mode

-

acv*

acvPI

PI

Figure 4.2. VSC-HVDC controls for the positive pole of the inverter.

4.4.2 Non-hybrid model

A non-hybrid simulation platform is considered where the system outside the

detailed three-phase model is represented by a voltage source behind an impedance

that retains the short circuit capacity (SCC) of the system model viewed from the

point of intersection. This is performed using the ETRAN [52] software. Since

the non-hybrid model does not have any representation of the dynamics of the

phasor model, it will not be adequate for dynamic simulation during the restoration

process.

4.4.3 Hybrid model

As mentioned in Section 4.3, in the hybrid model the dynamic representation of the

phasor model is retained. The phasor model in PSSE is interfaced with the detailed

three-phase model in PSCAD using the ETRAN-PLUS software. Figure 4.3 shows

the test system in a hybrid simulation platform.

4.5 Simulation results

In this study a scenario is considered where blackout occurred in a portion of area

#3 shown in Fig. 4.3. The goals are: (a) to restore that portion of the system

with the help of the VSC-HVDC link, and (b) to pick up an additional 200-MW

load connected to bus 154 (marked in red in Fig. 4.3) and supply a portion of the

60

Page 75: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

30113002

3001

3004

3003

3005

3020

3006

154

153

152

151

102101 211

201

202

203

205

206

Area3 Area2 Area1

Phasor model in PSSE

ETRAN PLUS

interface

V-f control Vdc – Q control

Vdc1

±350 kV

2 1

G3

converter station #2 converter station #1

Positive pole

Negative pole

MetallicReturn

Area 4

Load

BR1

t=2s

Line #1

G2Line #2

Load1

G1G1

3

45

Auxiliary

Euipment

BR2

t=25s

BR4

t=30s

BR5

t=6s

BR6

t=3s

BR7

t=3.8

s

BR8

t=3s

BR9

t=3s

6

7

8

9

T1

T2

T3

Part of Area 3:

system under

restoration

BR10

t=11.2s

Detailed 3-phase model in PSCAD

Additional

200MW load

Ptie3

Ptie1

Ptie2

Figure 4.3. Hybrid simulation setup for a 8-machine, 31-bus 4-area power system witha bipolar VSC-HVDC link with metallic return connecting areas #3 and #4. Individualcircuit breakers and the time of operation of those are shown. A portion of area #3 ismodeled as detailed 3-phase network in EMTDC/PSCAD. The rest of the model is builtin phasor domain in PSSE software.

load from generators G1 and G2 in the restored area. It was assumed that the

blackout could not propagate to area #4 since the DC link was acting as a ‘firewall.’

Initially all the breakers are assumed to be open. First, the dynamic behavior of

the non-hybrid and hybrid simulation are compared when the first objective (a) is

considered, which is described next.

61

Page 76: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

4.5.1 System restoration: hybrid vs non-hybrid

The same restoration sequence is used for both simulations and identical control

parameters are used. The results are shown in Figs 4.4 and 4.5. In these figures

Pvsc is the power output of one of the VSCs in converter station #2, P22−bus is the

power flowing through the line interfacing the phasor model and the detailed model,

f denotes the frequency measured at bus 6, and Vac is the AC voltage at bus 2.

The timing of the breaker reclosure are shown in Fig. 4.3. The steps followed for

the system restoration are described next:

Step I: Soft-start [t = 0.2s to 1s] During this stage converter #1 is in

Vdc−Q control and converter #2 is in Vac−f control mode. As shown in Fig. 4.4(a)

and (b), the AC voltage at bus 2 is ramped-up gradually using AC voltage control

illustrated in Fig. 4.3(b). This method of energization of long line and transformers

prevents inrush currents under no-load condition [48].

Step II: Pick-up auxiliary load of G1 [t = 3s] Auxiliary equipment of G1

which are modeled as a 56-MW load is picked up using the power flowing from area

#4 through the HVDC link.

Step III: Synchronizing generator G1 [t = 3.8s] Generator G1 is connected

to system after synchronization.

Step IV: Load 1 pick-up [t = 6s] Load 1, which is a 100MW load connected

to bus 6 is connected. This load is fed by VSC-HVDC and G1 is still a floating

source at this stage.

It could be seen that as expected, the non-hybrid and the hybrid models produce

same dynamic response up to this point since BR10 is open.

Step V: Closing BR10 [t = 11.2s] At this step the part of the system which

is modeled in PSSE in hybrid simulation and as a source in non-hybrid simulation is

connected to the rest by closing BR10 after synchronization. Significant oscilations

can be seen in power output of VSCs and power flow to bus 6 from bus 3020

(Fig. 4.3(a)). Figure 4.5(c) shows the zoomed view of frequency during this event.

It can be observed that the dynamic response of frequency substantially differ when

the hybrid simulation is considered. Figs 4.4(e) and (f) also show the direction and

the dynamic behavior of the power flowing into the detailed model is quite different

in the hybrid simulation from the non-hybrid simulation. Similar observations can

be made from Figs 4.4(c) and (d) for the power output of the VSC HVDC.

62

Page 77: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

0 5 10 15 20 25 30 350

0.5

1

vac[pu]

Non−Hybrid

0 5 10 15 20 25 30 350

0.5

1

vac[pu]

Hybrid

0 5 10 15 20 25 30 35−100

0100

Pvsc[M

W]

0 5 10 15 20 25 30 35−100

0100

Pvsc[M

W]

0 5 10 15 20 25 30 350

50

100

P22−bu

s[M

W]

time[s]0 5 10 15 20 25 30 35

0

200

400

P22−bu

s[M

W]

time[s]

[a] [b]

[c] [d]

[e] [f]

Figure 4.4. Dynamic response during system restoration from: (a),(c),(e) non-hybridand, (b),(d)(f) hybrid simulation platforms.

0 5 10 15 20 25 30 3559.9

60

60.1

f[H

z]

Non-Hybrid

time [s]

0 5 10 15 20 25 30 3559.9

60

60.1Hybrid

time [s]

f[H

z]

10 15 2059.95

60

60.05

f[H

z]

time [s]

[a]

[c]

[b]

Figure 4.5. (a)-(b) Comparison of dynamic behavior of frequency at bus 6 interfacingthe detailed and the equivalent/phasor model for non-hybrid and hybrid simulations , and(c) a zoomed view of the frequency comparing responses from non-hybrid (black trace),and hybrid (grey trace) simulations.

Step VI: HVDC mode switch [t = 20s] The control mode of converter

#2 VSCs, which was in AC voltage and frequency control mode is switched to AC

voltage and power control mode as described in Section 5.3.

Step VII: Power ramping [t = 21s to 24s] In this step the power output

of G1, which was primarily floating is ramped up to 40MWs and simultaneously the

power output of each of two VSCs in station #2 has been ramped down by 20MW.

Step VIII: Synchronizing generator G2 [t = 25s] G2 is connected to the

63

Page 78: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

25 30 35 40 45 50 550

100200300

P22−bus[M

W]

25 30 35 40 45 50 55100

150

Ptie1[M

W]

25 30 35 40 45 50 55−50

050

100

Pvsc[M

W]

25 30 35 40 45 50 55120130140150

Ptie2[M

W]

46 48 50 52 54 560

50100150

PG1[M

W]

time[s]46 48 50 52 54 560

204060

PG2[M

W]

time[s]

[a] [b]

[c] [d]

[e] [f]

Figure 4.6. Hybrid simulation: dynamic response for simulating additional load pickupin 22-bus test system shown in Fig. 4.3(a).

system after synchronization as a floating generator.

Step IX: Load 2 pickup [t = 30s] The 50-MW load at bus 2 is connected

to the system. Since VSCs are in power control mode at this stage this load is fed

from the rest of system.

Results from this section emphasize the importance of using a hybrid simulation

in such studies. Although the control schemes and parameters have resulted in a

desirable black start process, if the exact model of a large system is used in the

study, the outcome is significantly different.

In the next Section we focus on the other objective, i.e. load pickup at bus 154,

which cannot be studied using the non-hybrid model.

4.5.2 Additional load pick up: hybrid simulation

In this study a 200-MW load has been picked up at bus 154 at t = 30s. Prior to

picking up the load the sequence of events and their timing from Steps I - V are

identical to what was described in the previous section. The rest of the sequence is

described as follows:

Step VI: 200MW load pickup [t = 30s] At t = 30s the 200MW load is

connected at bus 154. As it is shown in Fig. 4.6(a) the power flow from the portion

of system modeled in PSSE is reduced following oscillations from around 230MWs

to 50MWs. At the same time the power output of each HVDC pole has increased

64

Page 79: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

to more than 50MW, see Fig. 4.6(c).

Step VII: HVDC mode switch [t = 38s] The control mode of converter

#2 VSCs, which was in AC voltage and frequency control mode is switched to AC

voltage and power control mode as described in Section 5.3.

Step VIII: [t = 39s to 42s] From t = 39s to 42s the same process of ramping

down the power output of HVDC and increasing power output of G1 is done as

described in previous section.

Step IX: Synchronizing generator G2 [t = 42.5s] G2 is connected to

network at t = 42.5s as a floating source.

Step X: Power ramping [t = 50s to 56s] In the last step from t = 50s

to 56s power output of G1 is increased by 80MW and G2 by 45MW as seen in

Fig. 4.6(e), (f) in order to supply the power needed for the 200MW load. During

this process the power output of each HVDC pole is also reduced by 20MWs using

power control. It is easily seen in Fig. 4.6(a) that through this process power

flow reverses and starts flowing into the PSSE-side segment of the system. The

power flow in two tie lines shown in Fig. 4.3 in the phasor model are highlighted

in Figs 4.6(b) and (d). This dynamic response observed in the hybrid simulation

paradigm cannot be simulated in the non-hybrid counterpart.

4.6 Summary and conclusion

Developing a detailed EMT-type model of a large-scale system for system restoration

studies is computationally prohibitive and hence, not a feasible approach. In this

chapter a hybrid co-simulation platform was proposed and described, which can be

a powerful tool in such studies where a detailed model of HVDC system is needed

besides the need for simulation of a large power system, which cannot be performed

in a three phase EMT environment like PSCAD.

In this approach a portion of the system including VSC-HVDC can be modeled

in a three phase EMT environment like PSCAD, while the rest of system is

represented by a phasor model in software like PSSE. ETRAN PLUS can be used as

a tool to establish a proper connection between the two models and simulate them

simultaneously. A case study was presented with VSC-HVDC assisted black-start

process in the presence of a reasonably large power system. Two simulations were

performed for the same case when a portion of system is represented as a source

65

Page 80: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

behind equivalent impedance and when the exact phasor model of that portion is

retained. It was shown that the dynamics of the large system impacts the process

of black start and the performance of control scheme used for the VSCs. With

the ETRAN PLUS-based hybrid simulation tool, the impact of load pickup or

disturbances in large system during the restoration can also be studied. This

platform will be used in chapter 5 where a novel method of black-start is proposed

using DFIG-based wind farms to assist VSC-HVDC links in the restoration process.

66

Page 81: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Chapter 5 |

Novel power system restora-tion strategy using DFIG-basedwind farms and VSC-HVDClinks

5.1 Introduction

Chapter 4 proposed a hybrid co-simulation platform for power system restoration

studies. This platform was shown to be a useful tool in a study where only the

detailed three phase model of a portion of system is needed like a VSC-HVDC link.

The platform was applied to a case to investigate VSC-HVDC assisted black-start

in a fairly large power system. In this chapter, the described platform is used to

analyze a proposed method of restoration, which uses DFIG-based wind farms in

conjunction with VSC-HVDC links.

Although a growing portion of generation in modern power grid comes from

wind farms, so far only conventional generators have been considered as black-start

units for power system restoration [2]. Operation of wind farms as black-start

units is a possibility when integrated with advanced wind forecasting tools, which

in turn can accelerate the restoration process. In this chapter, it is shown that

a DFIG-based wind farm can be effectively used for such purpose by means of a

seamless control transition and autonomous synchronization approach without any

need for energy storage systems.

67

Page 82: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

The following techniques and methods are proposed and discussed in this chapter

and are employed for system restoration using DFIG-based wind farms:

1. A DC-bus pre-charging control is proposed for DFIG-based wind farms,

which can retain the DC-bus voltage following a blackout. If wind energy is

available, this pre-charged DC bus is used to operate the wind farm in stator

flux control mode and build the terminal voltage, charge a transmission line,

and simultaneously pick up load at the remote end of the transmission line.

Picking up of loads of different compositions including constant impedance,

constant power and nonlinear rectifier load is demonstrated.

2. A novel autonomous synchronization enabled by a Phasor Measurement Unit

(PMU) is proposed to interconnect the isolated DFIG system to the rest

of the AC grid. This approach automatically adapts the phase of the AC

voltage vector at a remote bus connected to the DFIG by using the rotor-side

converter (RSC) controls and aligns it with the rest of the AC system voltage

before closing the circuit breaker.

3. Finally, a ‘Hot-Swapping’ approach is proposed, which does not lead to

any discontinuous resetting of the controller states of the wind farm. This

ensures a seamless transition from the flux control mode to the traditional

grid-connected mode.

Building on the hybrid co-simulation platform discussed in chapter 4, restoration

of a portion of a reasonably large system is demonstrated to show the effectiveness

of proposed black-start method. This portion of the system includes a DFIG-

based wind farm, a VSC-HVDC connection, a synchronous generator, multiple

transmission lines, transformers, different loads, and a remote grid, which are

represented by a EMT-type model in EMTDC/PSCAD [26]. The rest of the system

consisting a 20-bus 5-generator network is simulated as a phasor model in PSSE [27].

The content of this chapter has been reported in [54].

5.2 Proposed black-start process using wind farms

It is proposed that selected wind farms can be equipped with the control systems

presented here and be designated as black-start units. In addition to the considera-

tions mentioned in [25], it is envisioned that the wind farms used during restoration

68

Page 83: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

DC Link

GSCRSC

Wind turbine

PWM

DFIG

PLL2encoder

RSC Controls GSC Controls

-

-

--

-

( )2*

dcv

( )2dcv-

( )vK s

*

qgi

qgidgi

*

dgidtv

qtv

-

-

*

dri

dri

*

qri

qri

r

dcv C

dcIfrL frR fgR fgL

WVsP

s gQ Q=

ri gi

gv

* 0gscQ =

Rest of

AC Grid

tv

Transmission line

Remote

loads

Breaker

-

msivcK

( )2•d

dt

*

tv

tv

qsi

1

0 S2

-

*

tv

tv

PI

*

msi

msi

PI-

1

0

S2

0

1

1

s0

2

Flux

estimationPLL1 1

0

o slip-

tlg

gv lv

PMU

Co

mm

un

ica

tio

n C

han

ne

l

g

l

-

- 0

1

0

r*

r-

PI

Pitch angle control:

(Enabled if rotor speed

surpasses treshold level)

S2

S2S1

S2 : Hot-Swapping

0 : direct flux control mode

1 : grid-connected control mode

S1 : Autonomous synchronization

0 : inactive

1 : active

t

1 sdt

s

vR

+

r

/ss mL L−

o fg qgL i

o fg dgL i

2

{( ) }mslip rr fr dr ms

ss

LL L i i

L + +

( )slip rr fr qrL L i +

rv

si

tv

si

*

drv

*

qrv*

dgv

*

qgv

d

q

d

q

o t

0 0

PI

PI

PI

PI

3

2dV−

extP2

3

opt

m ms

K

pL i

� �

Figure 5.1. DFIG control scheme for black-start: ‘Hot-Swapping’ and autonomoussynchronization are shown.

will be a subset of those wind farms designated as black-start units in the planning

stage. During the restoration process, accurate wind forecast tools should be used

by the system operators to determine which units can be chosen for this purpose.

The proposed black-start process using wind farms is discussed in detail in the

following sections.

5.2.1 Step I: DC-bus pre-charging controls

A challenge in operating an isolated DFIG-based wind farm is that it requires a

charged DC bus. In absence of a grid, this can be ensured by installing a battery in

each wind turbine, which could be used to charge the DC bus capacitor in the start

69

Page 84: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

-20

-10

0

Protor[M

W]

rotor real power and DFIG DC-link voltage

6.98 7.0 7.1time [s]1.39

1.4

1.41

1.42

1.43

Vdc[kV]

[b]

[a]

[2]

GSC stops RSC stops

[1]

Figure 5.2. The DFIG-based wind farm is disconnected from the grid at t = 7.0s followedby the application of DC-bus pre-charging control. (a) Rotor power input equivalent topower flow from GSC to RSC. (b) DC-link voltage: zoomed views show the instant ofstopping GSC and RSC, respectively.

up stage. This will need additional investment and pose maintenance challenges.

To avoid this, a mechanism is proposed here to retain the charge in the DC bus

capacitor when the grid voltage support is lost following a blackout. Figure 5.1

shows the RSC and GSC of DFIG connected via the DC-link. Without loss of

generality, let us assume the flow of power in the DC-link is from RSC to GSC,

which can be determined from the direction of flow of the DC-link current Idc

in Fig. 5.1. When loss of grid voltage is sensed, switching of GSC is stopped.

This will cause an immediate rise in the DC-link voltage. However, switching in

RSC is continued to allow the capacitor to discharge through it, which causes a

gradual decrease in DC voltage. When the DC voltage comes back to its rated value,

switching of RSC is stopped. If power flows from GSC to RSC the described process

should be reversed. It can be observed from results in Fig. 5.2 that the proposed

strategy can successfully restore the voltage to its rated value within a short time

period and maintain a pre-charged DC bus. A fact which can adversely affect the

the charge retainment in capacitors is their internal losses. In fact the charge can be

retained in the capacitors for a specific period and they will discharge gradually by

time. However, another approach can be used which guarantees that the capacitors

are kept charged during the blackout, using the wind turbine-generator. As shown

in fig. 5.3, operating the DFIG-based wind farm in isolated mode using the control

scheme described in chapter 3, DC-link capacitors can be kept charged even if the

70

Page 85: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

0 2 4 6time [s]

1

1.5

2

Vdc[kV]

DFIG DC-link voltage

Figure 5.3. DC link voltage magnitude when the DFIG-based wind farm operates inisolated mode with open terminal.

PCC of wind farm is open-circuited. Although operating the wind farm in this

condition results is a very distorted voltage at the terminal, it fulfills our purpose to

keep the DC-link voltage at its rated value until the black-start process is initiated.

If wind energy is available, the DFIG-based wind farm designated as black-start

unit will start operating in the direct flux control mode to charge transmission line

and pickup remote loads, which is described next.

5.2.2 Step II: Line charging and load pickup

At the beginning of the restoration process, using the pre-charged DC bus in Step I,

the wind farm can perform line and transformer charging, and load pickup. These

loads are not necessarily local but can be located far from the wind farm as shown

in Fig. 5.1. In this step the DFIG-based wind farm operates in direct stator flux

control mode which is shown in fig. 5.1 and builds up the terminal voltage vt. As

shown in Fig. 5.1, in this control mode the switch S2 is in position ′0′.

The details of this control mode for GSC and RSC were described in details in

chapter 3 and hence, are not repeated here.

After building up the PCC voltage vt, the wind farm can charge the transmission

line and pick up remote loads shown in Fig. 5.1. Assuming that the rest of the

AC grid will also undergo restoration process in parallel, the objective now is to

synchronize the wind farm to the rest of the grid, which is described next.

71

Page 86: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

5.2.3 Step III: PMU-enabled autonomous synchronization

When the grid on the other side of the breaker shown in Fig. 5.1 is restored it is

likely that the voltage on each side of the breaker differ in phase. Therefore, a

synchronization method is necessary before this breaker is closed. Figure 5.4 shows

the proposed synchronization mechanism. In this context, the following points

should be noted:

• The phase of the voltage of the islanded system charged by the wind farm is

determined by integrating the rated frequency ω0 shown in Figs 5.1 and 5.4,

which is performed by digital control systems. Due to a finite resolution, its

frequency could be slightly different from the rest of the grid – we denote this

by ωo + ∆ω. As a result, there is a time-varying phase difference between

voltage vectors on the two sides of the breaker denoted by−→Vl and

−→Vg in Fig.

5.4.

• The goal is to align the voltage vector ~Vl with that of ~Vg using the controls of

the wind farm.

Since ~Vt and ~Vl have the same frequency ω0 +∆ω; their phase difference (θt − θl) is

constant, which depends on the transmission line impedance and the current iWF .

As shown in Fig. 5.4, before synchronization, the space vectors can be represented

with respect to a rotating voltage reference frame aligned with ~Vg. Mathematically,

~Vg = Vg

~Vl = Vl ej(θl−θg) = Vl e

jϕ(t)

~Vt = Vt ej(θt−θg) = Vt e

jγ(t)

(5.1)

We assume that PMUs are installed in the remote substation where the breaker is

located, which can measure the phase difference ϕ(t). All substations are equipped

with standby power supply for operating essential equipment during outages, which

will ensure PMUs operate under a blackout. As shown in Figs 5.1 and 5.4, it is

proposed that this phase difference ϕ(t) will be communicated to the wind farm

using dedicated fiber-optic channels, which in turn will be continuously subtracted

from the free running integrator angle θ0, eventually controlling θt. As shown in

Fig. 5.4, this process shifts ~Vt by a phase angle ϕ(t) and aligns vector ~Vl with ~Vg.

Let to be the time when synchronization begins and let Ts be the sampling time of

72

Page 87: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

AC Grid

g

transmission

line

DFIG

-

g

-

( )t( )t

Frequency

Before autonomous

synchronization

Before autonomous

synchronization

PMU

Frequency

g-

Communication channel

tV lV gV

o = + o=

tV

lV

gV

( ) ( ) t lt t − = −

1

s0

o

o

o + o +

d

q

After autonomous

synchronization

After autonomous

synchronization

tV

lV gV

oo +

o +

d

q

t l −

2

t

Breaker

WFi

( )t

( )t

ltl

l

Figure 5.4. Proposed PMU-enabled Autonomous Synchronization.

the PMU. After attaining steady state, we have,

~Vg = Vg

~Vl = Vl ej(∆ωs⌊(t−t0)/Ts⌋Ts)

~Vt = Vt ej(∆ωs⌊(t−t0)/Ts⌋Ts+θt−θl)

(5.2)

where, ⌊x⌋ represents floor of x. Since ∆ωsTs is quite small, ~Vg and ~Vl are almost

in-phase.

5.2.4 Step IV: Hot-swapping

When the autonomous synchronization process is complete and the voltages ~Vl and~Vg on two sides of the circuit breaker in the remote substation shown in Fig. 5.1 are

in the same phase, the breaker is closed. The breaker status is communicated to

the DFIG-based wind farm, which in turn performs the proposed ‘Hot-Swapping’

operation by changing the position of the switch ‘S2’ to position ‘1’ shown in

Fig. 5.1. This modifies the RSC and GSC controls to conventional grid-connected

mode which was described in detail in chapter 3.

73

Page 88: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

5.2.4.1 Notable points regarding ‘hot-swapping’

• PLL1 and PLL2 run from the beginning of the DFIG operation. Although

the output of the PLLs are used only after the ‘Hot-Swapping.’

• The proposed approach does not require switching of any dynamic states of

the controllers. This ensures a seamless transition.

5.3 VSC-HVDC controls for black-start

A bipolar VSC-HVDC system with metallic return is considered. The control mode

of VSC-HVDC system is identical to what described in chapter 4. It is assumed

that the rectifier is connected to a system unaffected by the blackout and operates

in reactive power and DC voltage control mode using traditional vector control [31].

V-f/V-P control Vdc – Q control

Vdc1

±350 kV

2 1

G3

converter station #2 converter station #1

Positive pole

Negative pole

Metallic Return

Load4

BR1

Line #1

G2Line #2

Load3

3

45

Load1

BR5

t=4.5s

BR7

t=6s

BR6

t=4s

6

7

T1

BR3

t=11s

Line #3

DFIG_based

wind farm

Load2

8

BR2

t=2s

BR4

t=14s

Blacked out area

Healthy

system

0.575/27.6 27.6/345

30113002

3001

3004

3003

3005

3020

3006

154

153

152

151

102101 211

201

202

203

205

206

Area2 Area1

3-area, 6-machine grid

Rest of

Area3

Part of

Area3

PSSE model

PSCAD model

Remote

grid

Healthy system

1tieP

20busP

vscP

Figure 5.5. Test system configuration consisting of a 3-area, 6-machine, 27-bus networkincluding a DFIG-based wind farm connected to a remote grid through a point-to-pointbi-polar VSC-HVDC link. A portion of the 3-area system is under blackout while theremote grid is healthy. Light grey: model in PSSE. Dark grey: model in PSCAD.

74

Page 89: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Initially, the inverter operates in AC voltage and frequency control mode to energize

the blacked-out system. After the AC system is synchronized with a generating

unit, the control mode is shifted to AC voltage and real power control mode. AC

voltage is controlled in the same fashion and the phase of the modulating signal is

used for power control. The details of VSC-HVDC control scheme were described

in chapter 2 and will not be repeated here.

5.4 Simulation study

5.4.1 System configuration

The test system shown in Fig. 5.5 consists of a 3-area, 6-machine, 27-bus network

including a DFIG-based wind farm connected to a remote grid, represented by an

ideal voltage source, through a point-to-point bi-polar VSC-HVDC link. Most of the

system is similar to the system used for simulation studies in chapter 4. A part of

area 3 in the 27-bus network is under blackout while the remote grid is healthy. The

portion of the blacked-out system connected to the remote healthy grid through the

HVDC transmission system is shown in dark grey, which is presented by a detailed

3-phase model in PSCAD [26]. The rest of the 3-area network, which is healthy, is

shown in light grey and is represented in a phasor framework in PSSE [27]. The

hybrid simulation is run using the ETRAN-PLUS [28] software.

5.4.2 Cold load effect

Cold load effect is a phenomenon appearing during system restoration in which

the loads consume significantly more power than their rated values when being

reconnected to grid after a period of disconnection. This phenomenon is the result

of a number of effects including inrush currents to cold lamp filaments, motor

starting currents, which can be up to 6 times the normal current, and motor

accelerating currents. The cold load model considered for the study in this thesis

follows reference [55]. At the beginning, the active power consumption is about

2.7 pu. The power consumption stays at that level for about 2 minutes and then

gradually decreases to 1.2 pu over a 20-minute time interval.

75

Page 90: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

5.4.3 Simulation results

Assuming that blackout occurred in the area shown in Fig. 5.5, the purpose is to

perform restoration process in this area using both the DFIG-based wind farm

and the VSC-HVDC link, simultaneously. The wind farm starts operating in the

flux control mode and picks up remote loads marked as Load 1. In parallel, the

VSC-HVDC link charges lines #1 and #2, and the transformers using the softstart

process described in [50] and picks up Load 2 followed by Loads 3 and 4. When

the two terminals of the circuit breaker BR4 are live, the process of autonomous

synchronization and Hot-Swapping are performed and the wind farm is connected

to the rest of the grid. The details of the restoration process are described next.

� Wind speed fluctuations: It is assumed that the wind energy is available based

on forecast at the location of the wind farm. Figure 5.6(a) shows the wind speed

profile during the period of system restoration. A slow decline, sharp reduction and

increase, and random fluctuations in the wind speed are considered to evaluate the

performance of the proposed restoration strategy under challenging circumstances.

12

14

16

18

Vw[m

/s]

wind speed and pitch angle

0 8 16 24 32time [s]

0

5

10

15

β[deg]

[a]

[b]

Figure 5.6. (a) Wind speed profile. (b) Variation in wind turbine pitch angle.

� Load composition: Different types of loads are considered for reflecting the

load diversity. These include constant impedance, constant power, and nonlinear

loads.

� Voltage buildup, line charging & load pickup by wind farm [t = 0.0s - 12.0s]:

The wind farm starts it’s operation in flux control mode using the pre-charged

DC bus and builds up the voltage at its terminal using the outer voltage control

loop in the RSC control shown in Fig. 5.1, which in turn generates i∗ms. Figure 5.7

76

Page 91: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

0

100

200

i ms[kA]

magnetizing current and wind farm voltage at PCC

ims

i∗ms

0 2 4 6 8 10time [s]

0

0.5

Vt[kV]

Vt

V ∗

t

[a]

[b]

Figure 5.7. Build up of (a) magnetizing current and (b) terminal voltage of DFIG-basedwind farm during line charging and simultaneous remote load pickup.

1.3

1.4

1.5

Vdc[kV]

DC link voltage and power consumption in remote loads

Vdc

V ∗

dc

0 2 4 6 8 10 12time [s]

0

200

PQ

load[M

W,M

VAr]

Pload

Qload

[a]

[b]

Figure 5.8. (a) DC-link voltage of the DFIG-based wind farm and (b) the powerconsumed by the remote loads at bus 8 picked up by the wind farm.

shows magnetizing current and terminal voltage build-up by the wind farm, while

charging the 345-kV, 50-km line (line #3) and simultaneously picking up a remote

load at bus 8 in Fig. 5.5. The load consists of three components: (a) a 100MW

and 35MVAr constant impedance load, (b) a 20MW and 10MVAr constant power

load, and (c) a 100MW nonlinear rectifier load. It can be seen from Fig. 5.7(b)

that the terminal voltage reaches its rated value in about 6.0s and the load power

consumption shown in Fig. 5.8(b) steadily increases, while the DC-link voltage

(Fig. 5.8(a)) is tightly regulated by the GSC controls.

Additional loads at bus 8 were picked up in the following sequence: (i) at

77

Page 92: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

-500

0

500

v8a[kV]

build up of phase-a voltage in both sides of BR4

1 4 8 12-500

0

500

v7a[kV]

0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 1.1 1.2 1.3

time [s]

-500

0

500

v7a,v8a[kV]

[c]

[b]

[a]

Figure 5.9. Comparison of voltage build up in phase a at (a) bus 8 from the wind farmand (b) at bus 7 from VSC-HVDC. (c) Overlapping zoomed view.

t = 8.5s: a 20MW resistive load, (ii) at t = 9.5s: a 20MW resistive load, (iii)

at t = 11.0s: a 10MW, 10MVAr constant impedance load, and finally (iv) at

t = 12.0s: a 20MW, 5MVAr constant power load. Figure 5.8 shows the load power

consumption increases in steps while the DC bus voltage controller demonstrates

good tracking performance. The wind speed profile throughout this process is

higher than the wind farm’s rated wind speed of 13.5m/s, which results in the

variation in pitch angle β as shown in Fig. 5.6(b).

� Voltage buildup, line charging & load pickup by VSC-HVDC [t = 0.2s -

12.0s]: Simultaneously, on the VSC-HVDC side, converter #1 starts operating in

Vdc −Q control and converter #2 in Vac − f control mode to build up rated voltage

with rated frequency is the blacked out area (details of Vac − f control mode of

VSCs was described in chapter 2 for islanded operation). The AC voltage at bus 2

is ramped-up gradually during 0.2s to 1.0s, while charging line #1, which is 190km

long and the transformers between buses 6 and 7, and 6 and 3. At t = 2.0s, a

constant power 56MW, 14MVAr load is picked up at bus 7 by closing BR2 followed

by the pickup of Load 3 at t = 4.0s, which is a constant power load consuming

50MW and 37MVAr. Figure 5.9 shows the comparison of voltage build up at bus

78

Page 93: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

8 from the wind farm and at bus 7 from VSC-HVDC. As it can be seen from fig.

5.9(b) the voltage built-up by VSC-HVDC has been performed in a soft startup

manner which has taken 1s to reach the rated voltage. Figure 5.9(b) also shows

a voltage drop at 4s at bus #7. This is a natural phenomenon for this system

since VSC is controlling the voltage at bus #2 and an increase in the loads causes

increased voltage drop across line #1 and transformers shown in fig. 5.5 (note that

we have a very weak system here).

� Synchronization and generation ramp up [t = 4.5s - 12.0s]: Synchronous

generator G2 which is a 120MVA machine, is synchronized and connected at

t = 4.5s and its power output is gradually ramped up to 100MW during t = 6.0s -

12.0s as shown in fig. 5.10. Also, the healthy portion of the 3-area 6-machine grid,

modeled in phasor framework in PSSE [27], is synchronized and connected to bus 6

of the blacked out portion modeled in PSCAD [26] by closing BR3 at t = 11.0s, see

Fig. 5.5. Figure 5.10 shows the power output of generator G2, the 20-bus system,

and the positive pole the VSC-HVDC station. This figure also shows power flow in

three tie lines inside the 20-bus system which are indicated in Fig. 5.5. It can be

seen from Fig. 5.10(b) that the power flowing through VSC-HVDC line reverses

during this phase. This can happen because the VSC is not controlling real power

flow at this stage. Moreover, when connecting the fairly large system (closing BR3)

the nature of the whole system and load flow solution determine the power flows in

the system. As it can be seen from fig. 5.10(a),(d),(e),(f) the 20-bus system injects

a significant amount of power into the rest of system and a large portion of this

power flows into the remote grid shown in fig. 5.5.

� Autonomous synchronization of DFIG [t = 10.0s - 14.0s]: Figure 5.11 shows

the dynamic response of the system when the proposed auto-synchronization is not

enabled and BR4 is closed at t = 14.0s when the phase difference ϕ(t) between

voltages v7a and v8a, shown in Fig. 5.14, is around 90deg. Over-modulation in

GSC and unacceptable transients in the DC-link voltage are observed as seen from

fig. 5.11(b),(c). This observation signifies the importance of proposed synchroniza-

tion method in this process.

Now, the proposed autonomous synchronization process is enabled at t = 10.0s,

which shows its effectiveness. Figure 5.12(a) shows that the phase difference between

voltages from both sides of BR4 changes slowly before t = 10.0s, which can be

explained by the wind farm-side frequency, which is slightly less than the grid-side

79

Page 94: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

0

200

400

P20bus[M

W]

-100

0

100

Pvsc[M

W]

1 5 10 15 20 25 30 35time [s]

050

100

PG2[M

W]

100

150

Ptie1[M

W]

1 5 10 15 20 25 30 35time [s]

300

400

500

Ptie3[M

W]

200

250

Ptie2[M

W]

[a]

[b]

[d]

[e]

[f][c]

Figure 5.10. Power flow: (a) from 20-bus system to bus 6, (b) out of positive pole VSCstation, (c) out of generator G2, (d) from bus 153 to bus 3006, (e) from bus 152 to bus3004, and (f) from bus 205 to bus 154.

0

50

100

ϕ(t)[deg]

phase difference between two sides of breaker BR4

0.51

1.52

2.5

Vdc[kV]

13 14 15 16time [s]

-5

0

5

mdqg mdg

mqg

[b]

[c]

[a]

Figure 5.11. Dynamic performance while connecting the breaker BR4 without proposedsynchronization process: (a) Phase difference between voltages in both sides of breakerBR4. (b) DC-link voltage of DFIG. (c) GSC modulating signals.

frequency due to the finite resolution of numerical integration as highlighted in

Fig. 5.13(a). It can be seen from Fig. 5.12(a) that this process can successfully

change the phase of voltage on DFIG side of BR4 so that the two voltages have same

phase. Figure 5.13(b) shows the dynamic response of DFIG-side frequency during

the autonomous synchronization process. As it can be seen during this process

there are fluctuations in this frequency when the phase is being shifted by large

values. However, as the voltage at the two sides of breaker BR4 become in phase,

80

Page 95: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

-50

0

50

100

ϕ(t)[deg]

phase difference and frequency of two sides of breaker BR4

4 6 8 10 12 14 16 18time [s]

59.8

60

60.2

f[H

z]

flfg

[b]

[a]

Figure 5.12. Dynamic performance while connecting the breaker BR4 following proposedsynchronization process: (a) Phase difference between voltages and (b) Frequency fromboth sides of breaker BR4.

6 8 10time [s]

59.99

59.995

60

60.005

60.01

f[H

z]

wind farmrest of grid

14 16 18time [s]

59.98

59.99

60

60.01

f[H

z]

wind farmrest of grid

[a] [b]

Figure 5.13. Frequency of two sides of breaker BR4 (a) before breaker closure and (b)after breaker closure.

the frequency fluctuations start decaying. Figure. 5.14 shows the two instantaneous

phase-a voltage waves at bus #7 and bus #8 during the synchronization process.

It is obvious that the proposed method can effectively synchronize the two voltages

in about 3 seconds.

� Breaker closure and hot-swapping [t = 14.0s]: At this stage the voltages at bus

#7 and bus #8 are perfectly synchronized. So, BR4 is closed and the DFIG-based

wind farm control is switched to grid connected mode. This control switching

is in a Hot-Swapping fashion which means there is no value presetting for PI

controllers. Figure 5.15(a) shows reference and actual value of GSC d-axis current

81

Page 96: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

9.99 10 10.01-400

-200

0

200

400

va[kV]

v8a

v7a

10.99 11 11.01-400

-200

0

200

400

va[kV]

12.99 13 13.01time [s]

-400

-200

0

200

400

va[kV]

11.99 12 12.01time [s]

-400

-200

0

200

400

va[kV]

[a]

[d] [c]

[b]

Figure 5.14. Phase a voltages at two sides of breaker BR4 during auto-synchronization.v8a is instantaneous voltage at bus 8 and v7a is instantaneous voltage at bus 7.

-20

0

20

40

60

80

i dg[kA]

GSC d-axis current and DC link voltage

idgi∗dg

13.83 14 14.17time [s]

1.38

1.4

1.42

Vdc[kV]

Vdc

V ∗

dc

[a]

[b]

Figure 5.15. (a) DFIG GSC d-axis current and (b) DC-link voltage during closure ofBR4 at t = 14.0s and Hot-Swapping.

before and after Hot-Swapping at 14s. Figure 5.16 illustrates the reference and

actual values of RSC decoupled currents. It is obvious that in both modes these

currents are controlled at their reference values and a seamless transition occurs

during mode switch at t = 14.0s. The DC-link voltage is shown in fig. 5.15(b)

before and after Hot-Swapping. It can be seen that the DC-link voltage is tightly

controlled during both control modes with a very fast and small transient at 14s

when the Hot-Swapping takes place.

� HVDC control mode swapping [t = 30.0s]: At t = 30.0s converter #2 of the

HVDC link, which was in AC voltage and frequency control mode to perform the

black-start process, is switched to AC voltage and real power control mode to fix

82

Page 97: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

100

150

i dr[kA]

RSC decoupled currents

idri∗dr

13.83 14 14.17time [s]

100

150

i qr[kA]

iqri∗qr

[b]

[a]

Figure 5.16. DFIG RSC currents in d and q reference frames during closure of BR4 att = 14.0s and Hot-Swapping.

the power flow through the HVDC link. The power control mode can also be used

to decrease or increase the power flow through HVDC link if desired as shown in

the studies in chapter 4. Figure 5.10(b) shows that the power flowing through

the HVDC transmission system is maintained at around 100MW flowing into the

remote grid.

5.5 A self-supporting DC-bus scheme for DFIG-

based wind farms

So far in this chapter, a restoration method using DFIG-based wind farms has

been proposed. One shortcoming in the pre-charged DC bus method discussed in

section 5.2.1 is the fact that the DC-bus capacitor will gradually discharge due

to the resistive losses. As a result of this fact, the black-start process should be

started within a specific time frame. However, the system operators might need

longer time to initiate the restoration sequence. Hence, we need a form of support

for the DC-bus voltage.

This section describes a proposed scheme for a self-supporting DC-bus in DFIG-

based wind farms, which equips the wind farm with the ability to keep its DC-bus

charged and continue the operation in absence of the grid support or any storage

system. It is shown that using the already described direct flux control and with

the availability of wind, a DFIG-based wind farm can retain the DC-bus charged

83

Page 98: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

DC Link

GSCRSC

Wind turbine

PWM

DFIG

PLL2encoder

RSC Controls GSC Controls

-

-

-- -

3

2−

( )2*

dcv

( )2dcv-

lossP

dcP

( )vK s

*

qgi

qgidgi

*

dgidtv

qtv

-

-

*

dri

dri

*

qri

qri

r

dcv C

dcIfrL frR fgR fgL

WVsP

s gQ Q=,WF WFP QG

SC

P0

GSC

Q=

GSC

P0

GSC

Q=

ri gi

gv

WFi

* 0gscQ =

tv

-

2

ss opt

m ms

L K

L i

msivcK

( )2•d

dt

*

tv

tv

qsi

1

0

S

-

*

tv

tv

PI

*

msi

msi

PI-

1

0

S

0

11

s 02

Flux

estimation PLL1

1

0 o slip-

r*

r-

PI Pitch angle control:

(Enabled if rotor speed

surpasses treshold level)

S

S

S : control mode switch

0 : grid-connected control

mode

1 : direct flux control mode

t

1 sdt

s

vR

+

r

/ss mL L−

o fg qgL i

o fg dgL i

2

{( ) }mslip rr fr dr ms

ss

LL L i i

L + +

( )slip rr fr qrL L i +

rv

si

tv

si

*

drv

*

qrv*

dgv

*

qgv

d

q

d

q

o t

0 0

PI

PI

PI

PI

AC Grid

Load 1 Load 2

Tra

nsm

issio

n

line

BR 1 BR 2

BR 3

Grid-connected

operationLoss of grid

Self-supporting

DC-bus operation

Isolated

operation with

open terminal

Isolated

operation with

load 1 picked up

Isolated

operation with

load 2 picked up

(a)

(b)

� �

Figure 5.17. (a) Test system configuration consisting of DFIG-based wind farm and itscontrols, step up transformers, grid, transmission line and remote loads. (b) Flow chartshowing the sequence of events in case study.

even with an open-terminal. The effectiveness of the proposed method has been

verified using PSCAD/EMTDC [26] simulation.

5.5.1 Proposed approach

The proposed approach is demonstrated in Fig. 5.17. In presence of a healthy AC

system, consider a DFIG-based wind farm operating in grid-connected mode [45] as

described in detail in chapter 3. In case of a disturbance, which results in the loss

of grid support (e.g. a blackout) operators can perform the charge retaining process

described in detail in section 5.2.1. This results in the isolation of the DC-bus and

keeps the capacitor charged for a specific amount of time. However, as mentioned,

it is obvious that the capacitor will gradually discharge. Hence, we need a form of

support for the DC-bus voltage. It is proposed that at this stage the DFIG can

start operating in the direct-flux control mode [56], as described in chapter 3, to

support its DC-bus voltage even with an open terminal.

Since there is no load connected to the wind farm, it only feeds the losses of

84

Page 99: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

-100

0

100

200

300

PQ

load[M

W,M

VAr]

Pload

Qload

-100

0

100

200

300

PQ

t[M

W,M

VAr]

Pterminal

Qterminal

0 5 10 15 20 24time[s]

1

1.5

VDC[kV]

0 5 10 15 20 24time[s]

0

0.5

1

Vt[pu]

[a] [b]

[c] [d]

Figure 5.18. (a) Real and reactive power fed to remote loads. (b) Power output of theDFIG-based wind farm. (c) DC-bus voltage. (d) DFIG-based wind farm terminal rmsvoltage.

6.98 7 7.05

1.4

1.41

1.42

VDC[kV]

8 10 12 14 16 18 20 22 24time [s]

1

1.5

VDC[kV]

[a]

[b] isolated modeoperation

Load1pickup

Load2pickup

GSC stops RSC stops

Figure 5.19. (a) Rotor power input equivalent to power flow from RSC to GSC, and(b) DC-link voltage, when the DFIG-based wind farm is disconnected from the grid att = 7.0s followed by the application of DC-bus charge retaining process. (c) DC-linkvoltage between 8s and 24s.

generators, converters and step-up transformers in this condition. This power is a

very small fraction of the wind farm capacity and hence, it is necessary to have pitch

angle control in order to prevent the rotational speed of turbines from increasing

beyond a certain limit. The method of pitch angle control was discussed in chapter

3 and will not be repeated here.

If a blackout occurs, the wind farm can keep its DC-bus charged and operate

in a no-load condition if wind is available. At the appropriate time, decided by

system operators, the wind farm, which is in an isolated control mode can perform

line charging and load pickup as part of the restoration process. The next section

85

Page 100: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

describes the test system used for simulation to verify the proposed idea.

5.5.2 Case study and results

Figure 5.17(a) shows the test system, which consists of the DFIG-based wind farm,

step-up transformers, the power grid, and the remote loads connected to point of

common coupling (PCC) by a 50km transmission line. The sequence of events,

shown in Fig 5.17(b), can be divided into the following stages:

� Loss of grid [t = 0.0s - 7.0s]: In the first stage the wind farm starts up and

operates in the grid-connected mode as described in sec 5.5.1. The grid is modeled

as an ideal source. Figure 5.18(b), (c), and (d) show power output of the wind

farm, DC-bus voltage, and terminal voltage, respectively.

� Self-supporting DC-bus operation [t = 7.0s - 17.0s]: At t=7.0s the wind farm

is disconnected from the grid and remote loads by opening the breakers BR1 and

BR2. The switching of the GSC stops immediately. This causes the DC-bus voltage

to increase as shown in Fig. 5.19(b). However, switching of RSC continues to reduce

the voltage. When the DC voltage is back at its rated value, RSC switching is

stopped. Figure 5.19(a) shows the DC-bus voltage during this charge retaining

process. After this process, the wind farm starts operating in isolated mode to

support the DC-bus and prevent its discharging. At t=10.0s the DFIG converters

start operating in direct flux control mode with an open terminal as described

in section 5.5.1. The angles for GSC and RSC are estimated based on flux angle

rather than PLL calculation (see Fig. 5.17(a)). It can be seen from Figs. 5.18(c)

and 5.19(b) that the wind farm can control the DC-bus voltage at its rated value.

Figure 5.18(b) shows the small amount of active and reactive power generated by

the wind farm to feed the losses in DFIGs and transformers. Figure 5.20(b) shows

the instantaneous phase-a voltage at the terminal of wind farm. As it can be seen,

this voltage is highly distorted due to the no-load operation of wind farm. However,

since the main purpose in this stage is for the wind farm to regulate its DC-bus

voltage, the distortion in terminal voltage is not of concern.

� Line charging and cold load pickup [t = 17.0s - 24.0s]: At t=17.0s the

transmission line and a portion of remote loads (indicated by Load 1 in Fig. 5.17(a)),

consisting a 100MW and 35MVAr constant impedance, a 20MW and 10MVAr

constant power, and a 100MW nonlinear load, are connected to the wind farm by

86

Page 101: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

4.92 4.94 4.96-400

-200

0

200

400

va[kV]

11.22 11.24 11.26-400

-200

0

200

400

va[kV]

19.22 19.24 19.26time[s]

-400

-200

0

200

400

va[kV]

23.22 23.24 23.26time[s]

-400

-200

0

200

400

va[kV]

[a] [b]

[c] [d]

Figure 5.20. DFIG-based wind farm’s instantaneous terminal voltage (one phase) whenoperating in: (a) grid-connected mode, (b) isolated mode with open terminal, (c) isolatedmode serving 220MW and 45MVAr remote load, and (d) isolated mode supplying anadditional 90MW and 30MVAr remote load.

closing BR1. Another 90MW and 30MVAr constant impedance load, indicated by

Load 2 in Fig 5.17(a), is picked up at 20s by closing BR3. The wind farm operating in

direct flux control mode feeds these loads as shown in figure 5.18(b). Figure 5.18(c)

shows the DC voltage being controlled during this stage with transients occurring

at load pickup instances - also see the zoomed view in Fig. 5.19(b). Figure 5.20

shows the reduction in voltage distortion after connecting the transmission line and

remote loads.

5.6 Summary and conclusion

In this chapter a new black-start method using DFIG-based wind farms and VSC-

HVDC links at the same time was proposed to have a faster restoration process.

It was shown that a wind farm equipped with both islanded and grid connected

control systems can start up in an isolated mode and pick up remote loads and

get connected to grid using an autonomous synchronization method. No energy

storage is needed to perform this process. The idea was successfully tested using

the hybrid co-simulation platform described in chapter 4, to simulate the partial

restoration process for a relatively large-scale system. There is no deviation from

what wind industry is currently developing in this proposed black-start method

since two commonly used control structures have been used. This method uses a

portion of wind farms which are designated as black-start units without any conflict

87

Page 102: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

with their normal operation.

88

Page 103: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Appendix A|

Space phasor and dq referenceframe

A.1 Introduction

This Appendix includes a brief description of space phasor and transformation

formulations used to transfer abc, αβ, and dq reference frames. An extensive

discussion about space phasors and two-dimensional frames can be found in [31].

A.2 Space phasor

A three-phase AC system can be represented, analyzed, and controlled using the

concept of space phasors. Assume that fa(t), fb(t), and fc(t) are three signals of

arbitrary waveforms that satisfy the following equation:

fa(t) + fb(t) + fc(t) = 0 (A.1)

Then their corresponding space phasor F (t) also known as space vector is defined

as:F (t) = Fα(t) + jFβ(t)

= 23

[

ej0fa(t) + ej2π3 fb(t) + ej

4π3 fc(t)

] (A.2)

89

Page 104: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

F (t) is a complex function of time and Fα(t) and Fβ(t) are the real and imaginary

components, respectively. In terms of real valued signals we can write:

[

Fα(t)

Fβ(t)

]

=2

3C

fa(t)

fb(t)

fc(t)

(A.3)

where, C is:

C =

[

1 −12

−12

0√32

−√32

]

(A.4)

In case the space phasor is known, one can find the corresponding three phase

signals by:

fa(t) = Re{

F (t)e−j0}

fb(t) = Re{

F (t)e−j 2π3

}

fc(t) = Re{

F (t)e−j 4π3

}

(A.5)

In terms of the real-valued components Fα(t) and Fβ(t) , the corresponding signals

are given by:

fa(t)

fb(t)

fc(t)

=

1 0

−12

√32

−12

−√32

[

Fα(t)

Fβ(t)

]

= CT

[

Fα(t)

Fβ(t)

]

(A.6)

where, CT is the transpose of C defined in (A.4).

A.2.1 dq-frame representation of a space phasor

Assuming a space phasor as F = Fα + jFβ, the αβ to dq-frame transformation is

defined as:

fd + jfq = (fα + jfβ) e−jε(t) (A.7)

The dq to αβ-frame transformation is achieved by multiplying both sides of (A.7)

by e−jε(t). Hence we have:

fα + jfβ = (fd + jfq) ejε(t) (A.8)

90

Page 105: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Based on Euler’s identity ej(.) = cos(.) + j sin(.), we can rewrite (A.7) as:

[

fd(t)

fq(t)

]

= R [ε(t)]

[

fα(t)

fβ(t)

]

(A.9)

where,

R [ε(t)] =

[

cos ε(t) sin ε(t)

− sin ε(t) cos ε(t)

]

(A.10)

Also, (A.8) can be rewritten as:

[

fα(t)

fβ(t)

]

= R−1 [ε(t)]

[

fd(t)

fq(t)

]

= R [−ε(t)]

[

fd(t)

fq(t)

]

(A.11)

where,

R−1 [ε(t)] = R [−ε(t)] =

[

cos ε(t) − sin ε(t)

sin ε(t) cos ε(t)

]

(A.12)

A direct transformation from the abc to dq-frame can be obtained by:

[

fd(t)

fq(t)

]

=2

3T [ε(t)]

fa(t)

fb(t)

fc(t)

(A.13)

where,

T [ε(t)] = R [ε(t)]C =

[

cos [ε(t)] cos[

ε(t)− 2π3

]

cos[

ε(t)− 4π3

]

sin [ε(t)] sin[

ε(t)− 2π3

]

sin[

ε(t)− 4π3

]

]

(A.14)

Similarly, direct transformation from dq to abc-frame can be obtained by:

fa(t)

fb(t)

fc(t)

= T [ε(t)]T

[

fd(t)

fq(t)

]

(A.15)

91

Page 106: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Appendix B|

Line-commutated HVDC

B.1 Introduction

Line-commutated converter HVDC (LCC-HVDC) technology was developed long

before VSC-HVDC systems and is a mature technology now. The majority of HVDC

links now in operation are of LCC type. The details on topology, characteristics

and control of LCC-HVDC systems can be found in [33, 57–60]. This Appendix

includes a very brief overview on LCC-HVDC systems.

B.2 Overview on LCC-HVDC

The overall structure of LCC-HVDC is similar to VSC-HVDC which is discussed in

chapter 2 and consists of rectifier and inverter-side converters, DC transmission line,

transformers, and DC and AC-side filters. LCCs are constructed using thyristor

valves instead of IGBTs which are used in VSCs. A thyristor valve can be turned

on when a positive voltage is applied across it and a gate signal is provided to it.

Unlike the IGBT which can be turned off by gate signal, thyristors can be turned

off only if a negative voltage is applied across them. One can build a so-called

Graetz bridge, which is a three-phase full-wave bridge, by arranging six thyristor

valves as in the configuration shown in fig. B.1. Graetz bridge is the basic building

block in LCCs. In this application each thyristor valve is comprised of a suitable

number of series-connected thyristors to achieve desired DC voltage rating.

The control of LCC stations is basically achieved by controlling the firing angle

of the thyristors. LCCs require a relatively strong synchronous voltage source in

92

Page 107: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

dcv

gcv

gbv

gav

Figure B.1. Schematic of a Graetz bridge.

order to commutate; which is the transfer of current from one phase to another in

a synchronized firing sequence of the thyristor valves. Hence, they cannot properly

operate when connected to a weak grid. As a result of this, unlike VSC-HVDC,

LCC-HVDC systems lack the black-start ability. LCCs can only operate with the

ac current lagging the voltage so the conversion process demands reactive power.

This is the reason for one of the demerits of LCCs which is their high consumption

of reactive power. Under full-load condition reactive power consumption is 50−60%

of the real power. However, the consumption of reactive power changes by the

load change. Large capacitor banks are installed to meet the reactive power need

of converters. Since the reactive power demand changes with loading condition

breakers are always connected to these banks to switch them on and off as needed.

The flow of DC current in this type of converters is uni-directional and hence, power

reversal from one station to other is done by reversing the polarity of DC voltage in

both stations. Furthermore, smoothing filters are needed to reduce the harmonics.

Tap-changing transformers are usually used to connect the converters’ AC-side to

the grid. These transformers are used to bring the firing angles of the converter

stations within the nominal operating range. The footprint of LCC-HVDC converter

stations is generally large due to the need for large filters, capacitor banks, and

transformers.

93

Page 108: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

Bibliography

[1] Feltes, J. W., C. Grande-Moran, P. Duggan, S. Kalinowsky, M. Za-mzam, V. C. Kotecha, and F. P. de Mello (2006) “Some considerations inthe development of restoration plans for electric utilities serving large metropoli-tan areas,” IEEE Transactions on Power Systems, 21(2), pp. 909–915.

[2] Adibi, M. M., J. N. Borkoski, and R. J. Kafka (1987) “Power SystemRestoration - The Second Task Force Report,” IEEE Transactions on PowerSystems, 2(4), pp. 927–932.

[3] Adibi, M. M. and N. Martins (2008) “Power system restoration dynamicsissues,” in 2008 IEEE Power and Energy Society General Meeting - Conversionand Delivery of Electrical Energy in the 21st Century, pp. 1–8.

[4] Apostolov, A., P. Mysore, T. Sidhu, and C. F. Henville (2012) “Anupdate to protection issues during system restoration,” in 2012 IEEE Powerand Energy Society General Meeting, pp. 1–4.

[5] LIU, Y., R. FAN, and V. TERZIJA (2016) “Power system restoration: aliterature review from 2006 to 2016,” Journal of Modern Power Systems andClean Energy, 4(3), pp. 332–341.

[6] Zhou, Y., X. Hu, and B. Luo (2007) “Design of a case-based reasoningsystem for power system restoration,” Automation of Electric Power Systems,31(18), pp. 87–90.

[7] WANG, H. and Y. LIU (2009) “Multi-objective Optimization of Power SystemReconstruction Based on NSGA-II [J],” Automation of Electric Power Systems,23, p. 005.

[8] Liu, W., Z. Lin, F. Wen, and G. Ledwich (2012) “Intuitionistic fuzzyChoquet integral operator-based approach for black-start decision-making,”IET generation, transmission & distribution, 6(5), pp. 378–386.

[9] Kafka, R. J. (2008) “Review of PJM restoration practices and NERC restora-tion standards,” in 2008 IEEE Power and Energy Society General Meeting -Conversion and Delivery of Electrical Energy in the 21st Century, pp. 1–5.

94

Page 109: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

[10] Barsali, S., D. Poli, A. Pratico, R. Salvati, M. Sforna, and R. Za-ottini (2008) “Restoration islands supplied by gas turbines,” Electric PowerSystems Research, 78(12), pp. 2004–2010.

[11] “PJM Manual 36: System Restoration. [Online]. available: www.pjm.com/,” .

[12] Bahrman, M. P. (2008) “HVDC transmission overview,” in 2008 IEEE/PESTransmission and Distribution Conference and Exposition, pp. 1–7.

[13] Bahrman, M. and P. E. Bjorklund (2014) “The New Black Start: SystemRestoration with Help from Voltage-Sourced Converters,” IEEE Power andEnergy Magazine, 12(1), pp. 44–53.

[14] Oni, O. E., I. E. Davidson, and K. N. I. Mbangula (2016) “A review ofLCC-HVDC and VSC-HVDC technologies and applications,” in 2016 IEEE16th International Conference on Environment and Electrical Engineering(EEEIC), pp. 1–7.

[15] projects in china. [Online]. available:www.siemens.com/energy/hvdc, P. H. .

[16] Chaudhuri, N. R., B. Chaudhuri, R. Majumder, and A. Yazdani (2014)Multi-terminal Direct-Current Grids: Modeling, Analysis, and Control, Wiley.

[17] Bahrman, M. and P. E. Bjorklund (2014) “The New Black Start: SystemRestoration with Help from Voltage-Sourced Converters,” IEEE Power andEnergy Magazine, 12(1), pp. 44–53.

[18] Thale, S. and V. Agarwal (2011) “A smart control strategy for the blackstart of a microgrid based on PV and other auxiliary sources under islandedcondition,” in 2011 37th IEEE Photovoltaic Specialists Conference.

[19] Li, J., J. Su, X. Yang, and T. Zhao (2011) “Study on microgrid operationcontrol and black start,” in 2011 4th International Conference on ElectricUtility Deregulation and Restructuring and Power Technologies (DRPT), pp.1652–1655.

[20] Dang, J. and R. G. Harley (2013) “Islanded microgrids black start pro-cedures with wind power integration,” in 2013 IEEE Power Energy SocietyGeneral Meeting, pp. 1–5.

[21] Zhu, H. and Y. Liu (2012) “Aspects of power system restoration consideringwind farms,” in International Conference on Sustainable Power Generationand Supply (SUPERGEN 2012), pp. 1–5.

95

Page 110: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

[22] Seca, L., H. Costa, C. L. Moreira, and J. A. P. Lopes (2013) “AnInnovative Strategy for Power System Restoration using Utility Scale WindParks,” in 2013 IREP Symposium-Bulk Power System Dynamics and Control(IREP), Rethymnon, Greece, pp. 1–8.

[23] Tang, Y., J. Dai, Q. Wang, and Y. Feng (2017) “Frequency ControlStrategy for Black Starts via PMSG-Based Wind Power Generation,” Energies,10(3).

[24] Aktarujjaman, M., M. Kashem, M. Negnevitsky, and G. Ledwich(2006) “Black start with DFIG based distributed generation after major emer-gencies,” in International Conference on Power Electronics, Drives and EnergySystems, 2006. PEDES ’06, pp. 1–6.

[25] Sun, W. and A. Golshani (2015) “Harnessing Renewables in Power SystemRestoration,” in 2015 IEEE PES General Meeting, Denver, USA, pp. 1–8.

[26] (PSCAD/EMTDC v. 4.2.1, Manitoba HVDC Research Centre, Winnipeg, MB,Canada) .

[27] (PSS/E, "Program Operation Manual," SIEMENS Power Technologies, Inc.,New York, USA) .

[28] (E-TRAN PLUS, ELECTRANIX Corporation, Winnipeg, Canada,http://www.electranix.com/software/e-tran-plus/) .

[29] Arrillaga, J. (1998) High Voltage Direct Current Transmission, The Insti-tution of Electrical Engineers.

[30] Peake, O. (2010) “The History of High Voltage Direct Current Transmission,”Australian Journal of Multi-Disciplinary Engineering, 8(1), pp. 47–55.

[31] Yazdani, A. and R. Iravani (2010) Voltage-sourced converters in powersystems : modeling, control, and applications, Wiley, Oxford.

[32] Sharifabadi, K., L. Harnefors, H. Nee, S. Norrga, and R. Teodor-escu (2016) Design, Control, and Application of Modular Multilevel Convertersfor HVDC Transmission Systems, Wiley.

[33] Arrillaga, J., Y. H. Liu, and N. R. Watson (2007) Flexible powertransmission: the HVDC options, Wiley.

[34] Padiyar, K. R. (2012) HVDC power Transmission Systems, New age inter-national.

[35] Chung, S.-K. (2000) “A phase tracking system for three phase utility interfaceinverters,” IEEE Transactions on Power Electronics, 15(3), pp. 431–438.

96

Page 111: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

[36] Nicolau, V. (2013) “On PID Controller Design by Combining Pole PlacementTechnique with Symmetrical Optimum Criterion,” in 2008 IEEE Power andEnergy Society General Meeting - Conversion and Delivery of Electrical Energyin the 21st Century, pp. 1–5.

[37] Liserre, M., R. Cardenas, M. Molinas, and J. Rodriguez (2011)“Overview of Multi-MW Wind Turbines and Wind Parks,” IEEE Transactionson Industrial Electronics, 58(4), pp. 1081–1095.

[38] Kazmierkowski, M. P., R. Krishnan, and F. Blaabjerg (2002) Controlin power electronics, selected propblems, Academic press.

[39] Anderson, P. M. and A. Bose (1983) “Stability Simulation Of Wind TurbineSystems,” IEEE Transactions on Power Apparatus and Systems, PAS-102(12),pp. 3791–3795.

[40] Heier, S. (2006) Grid integration of wind energy conversion systems, Wiley.

[41] Datta, R. and V. T. Ranganathan (2002) “Variable-speed wind powergeneration using doubly fed wound rotor induction machine-a comparison withalternative schemes,” IEEE Transactions on Energy Conversion, 17(3), pp.414–421.

[42] Song, Y. D. and B. Dhinakaran (1999) “Nonlinear variable speed controlof wind turbines,” in Proceedings of the 1999 IEEE International Conferenceon Control Applications (Cat. No.99CH36328), vol. 1, pp. 814–819 vol. 1.

[43] Pena, R., J. C. Clare, and G. M. Asher (1996) “A doubly fed inductiongenerator using back-to-back PWM converters supplying an isolated load froma variable speed wind turbine,” IEE Proceedings - Electric Power Applications,143(5), pp. 380–387.

[44] Muyeen, S. M., J. Tamura, and T. Murata (2009) Stability Augmentationof a Grid-connected Wind Farm, Springer.

[45] Pena, R., J. C. Clare, and G. M. Asher (1996) “Doubly fed induc-tion generator using back-to-back PWM converters and its application tovariable-speed wind-energy generation,” IEE Proceedings on Electric PowerApplications, 143(3), pp. 231–241.

[46] (GE PSLF: http://www.geenergyconsulting.com/practice-area/software-products/pslf) .

[47] “DIgSILENT,” .URL http://www.digsilent.de/

97

Page 112: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

[48] Li, S., M. Zhou, Z. Liu, J. Zhang, and Y. Li (2009) “A study on VSC-HVDCbased black start compared with traditional black start,” in SUPERGEN ’09.International Conference on Sustainable Power Generation and Supply, 2009,pp. 1–6.

[49] Farsani, P. M., N. R. Chaudhuri, and R. Majumder (2016) “Hybridsimulation platform for VSC-HVDC-assisted large-scale system restorationstudies,” in 2016 IEEE Power Energy Society Innovative Smart Grid Tech-nologies Conference (ISGT), pp. 1–5.

[50] Zhou, M., S. Li, J. Zhang, Z. Liu, and Y. Li (2009) “A study on theblack start capability of VSC-HVDC using soft-starting mode,” in IEEE 6thInternational Power Electronics and Motion Control Conference, 2009. IPEMC’09, pp. 910–914.

[51] Jiang-Hafner, Y., H. Duchen, M. Karlsson, L. Ronstrom, andB. Abrahamsson (2008) “HVDC with voltage source converters - a powerfulstandby black start facility,” in IEEE/PES Transmission and DistributionConference and Exposition, 2008. T&D, pp. 1–9.

[52] (E-TRAN, ELECTRANIX Corporation, Winnipeg, Canada,http://www.electranix.com/E-TRAN/) .

[53] “Intel Fortran V15,” .URL https://software.intel.com/

[54] Moradi Farsani, P., S. Gopal Vennelaganti, and N. Ray Chaudhuri“Synchrophasor-Enabled Power Grid Restoration with DFIG-Based WindFarms and VSC-HVDC Transmission System,” to appear in IET - Generation,Transmission and Distribution, pp. 1–7.

[55] (E. Angeholm, Cold Load Pickup, Department of Electric Power Engineering,Chalmers University of Technology, 1990) .

[56] Pena, R., J. C. Clare, and G. M. Asher (1996) “A Doubly fed inductiongenerator using back-to-back PWM converters supplying an isolated load froma variable-speed wind turbine,” IEE Proceedings on Electric Power Applications,143(5), pp. 380–387.

[57] Kimbark, E. (1971) direct current transmission, Wiley-Interscience.

[58] Adamson, C. and N. Hingorani (1960) High voltage direct current powertransmission, Garraway.

[59] Arrillaga, J. and B. D. Smith (1998) AC-DC power system analysis,Stevenage.

98

Page 113: POWER SYSTEM RESTORATION USING DFIG-BASED WIND …

[60] Padiyar, K. R. (1996) Power system dynamics : stability and control, JohnWiley ; Interline Publishing, Singapore Bangalore.

99