pmi63 analyzing risk

Upload: dragana-jovanovic

Post on 14-Feb-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/23/2019 PMI63 Analyzing Risk

    1/12

    EuroProjex [email protected] jrt/epm/mar06

    EuroProjex

    Project and Programme Management

    Session 3:Analyzing Risk

    Professor Rodney Turner

    Co-author, Project Oriented Leadership

    Gower, 2010

    EuroProjex [email protected] jrt/epm/mar06

  • 7/23/2019 PMI63 Analyzing Risk

    2/12

    EuroProjex [email protected] jrt/epm/mar06

    Getting earlier completion

    Cummulative

    Probability

    Outcome

    100%

    30%

    10%

    DecJun

    EuroProjex [email protected] jrt/epm/mar06

    Analyzing Risk

    Simple example

    Sensitivity analysis

    Three point estimating

    Monte-Carlo analysis

  • 7/23/2019 PMI63 Analyzing Risk

    3/12

    EuroProjex [email protected] jrt/epm/mar06

    Precedence network for constructing awarehouse

    0 3 3

    0 0 3

    Design buildingand foundations

    1 2 3

    3 2 5

    Prepare site andfoundations

    3 2 5

    3 0 5

    Procuresteelwork

    5 2 7

    5 0 7

    Erect Steelwork

    -2

    EuroProjex [email protected] jrt/epm/mar06

    Three point estimating- without lead

    Activity Min Med Max

    Design 2 3 4

    Procure 1 2 3

    Foundation 2 3 5

    Erect 2 3 5

    Top path 6 9 14

    Bottom path 5 8 11

    Result 6 9 14

  • 7/23/2019 PMI63 Analyzing Risk

    4/12

    EuroProjex [email protected] jrt/epm/mar06

    Three point estimating- with lead

    Activity Min Med Max

    Design 2 3 4

    Procure 1 2 3

    Foundation 2 3 5

    Erect 2 3 5

    Top path 4 7 12

    Bottom path 5 8 11

    Result 5 7 12

    EuroProjex [email protected] jrt/epm/mar06

    Monte Carlo analysis

    Duration (months)

    100%

    80%

    60%

    40%

    20%

    100%

    80%

    60%

    40%

    20%5%

    13%

    31%41%

    8%2%

    6 7 8 9 10 11

    Probabilty

    theduration

    will equaloutcome

    Probabiltytheduration isless thanoutcome

  • 7/23/2019 PMI63 Analyzing Risk

    5/12

    EuroProjex [email protected] jrt/epm/mar06

    Analyzing Risk

    Simple example

    Sensitivity analysis

    Three point estimating

    Monte-Carlo analysis

    EuroProjex [email protected] jrt/epm/mar06

    Sensitivity analysis

    Determine the response of the project as oneor more key parameters varies

    Determine the value that flips the decision

  • 7/23/2019 PMI63 Analyzing Risk

    6/12

    EuroProjex [email protected] jrt/epm/mar06

    Value vs Discount factor

    2% 4% 6% 8%

    2000

    -2000

    -4000

    -6000

    -8000

    -1000

    EuroProjex [email protected] jrt/epm/mar06

    Plot of two parameters

    Terminal Value

    Fuel Cost

    135

    10

    12

    15

    2 Payback, years

  • 7/23/2019 PMI63 Analyzing Risk

    7/12

    EuroProjex [email protected] jrt/epm/mar06

    Analyzing Risk

    Simple example

    Sensitivity analysis

    Three point estimating

    Monte-Carlo analysis

    EuroProjex [email protected] jrt/epm/mar06

    Projects are bound to fail

    Work Pack Min ML Exp Max

    70 100 105 150

    P00 P40 P60 P99

    Project Th Mn Min Est Exp Budgt Max Th Mx

    700 950 1000 1050 1000 1200 1500

    P00 P00 P05 P60 P80 P99 P100

    Common assumption: Mode of Sum = Sum of Modes wrong

    Actual: Mean of Sum = Sum of Means correct

    Guess at Expected = Most optimistic + 4 x Mode + Most pessimistic

    6

  • 7/23/2019 PMI63 Analyzing Risk

    8/12

    EuroProjex [email protected] jrt/epm/mar06

    ProbabilityofAchievingEstimate

    Project Cost

    Base Cost

    Stretch Target

    Target Cost

    Sanction Cost

    Benchmark or Historical Cost

    Economic Feasibility Limit

    Alliance Target Savings

    Alliance Contingency

    Client Contingency

    Ex-ante Alliance Saving

    0%

    100%

    Cost probability curve

    EuroProjex [email protected] jrt/epm/mar06

    Planned Value

    Min

    MLMax

    Three point estimates

    Start with planned value (Usually includes contingency)

    min = plan - contingency (best case)

    max = min + all risks + real contingency (worst case)

    Most-Likely depends on probabilities & responses Calculate in simple cases

    Otherwise use best guess / expert judgement

    If possible use previous experience

  • 7/23/2019 PMI63 Analyzing Risk

    9/12

    EuroProjex [email protected] jrt/epm/mar06

    Analyzing Risk

    Simple example

    Sensitivity analysis

    Three point estimating

    Monte-Carlo analysis

    EuroProjex [email protected] jrt/epm/mar06

    }=TOTAL DURATION

    DISTRIBUTION

    %PROBABILITYDISTRIBUTIONS

    (3 point

    estimates)

    TASKS ACTIVITY

    1

    ACTIVITY

    2

    ACTIVITY

    3

    + +

    Et

    cincidence

    How does Monte Carlo work?

    Apply three point estimates

    Run model randomly sampling values

    Calculate outturns with those values

    Repeat a large number of times (1,000-10,000)

    Sum to produce probability distributions

  • 7/23/2019 PMI63 Analyzing Risk

    10/12

    EuroProjex [email protected] jrt/epm/mar06

    EuroProjex [email protected] jrt/epm/mar06

  • 7/23/2019 PMI63 Analyzing Risk

    11/12

    EuroProjex [email protected] jrt/epm/mar06

    EuroProjex [email protected] jrt/epm/mar06

  • 7/23/2019 PMI63 Analyzing Risk

    12/12

    EuroProjex [email protected] jrt/epm/mar06

    EuroProjex [email protected] jrt/epm/mar06

    END of SESSION 6 3

    [email protected]

    [email protected]