pmi63 analyzing risk
TRANSCRIPT
-
7/23/2019 PMI63 Analyzing Risk
1/12
EuroProjex [email protected] jrt/epm/mar06
EuroProjex
Project and Programme Management
Session 3:Analyzing Risk
Professor Rodney Turner
Co-author, Project Oriented Leadership
Gower, 2010
EuroProjex [email protected] jrt/epm/mar06
-
7/23/2019 PMI63 Analyzing Risk
2/12
EuroProjex [email protected] jrt/epm/mar06
Getting earlier completion
Cummulative
Probability
Outcome
100%
30%
10%
DecJun
EuroProjex [email protected] jrt/epm/mar06
Analyzing Risk
Simple example
Sensitivity analysis
Three point estimating
Monte-Carlo analysis
-
7/23/2019 PMI63 Analyzing Risk
3/12
EuroProjex [email protected] jrt/epm/mar06
Precedence network for constructing awarehouse
0 3 3
0 0 3
Design buildingand foundations
1 2 3
3 2 5
Prepare site andfoundations
3 2 5
3 0 5
Procuresteelwork
5 2 7
5 0 7
Erect Steelwork
-2
EuroProjex [email protected] jrt/epm/mar06
Three point estimating- without lead
Activity Min Med Max
Design 2 3 4
Procure 1 2 3
Foundation 2 3 5
Erect 2 3 5
Top path 6 9 14
Bottom path 5 8 11
Result 6 9 14
-
7/23/2019 PMI63 Analyzing Risk
4/12
EuroProjex [email protected] jrt/epm/mar06
Three point estimating- with lead
Activity Min Med Max
Design 2 3 4
Procure 1 2 3
Foundation 2 3 5
Erect 2 3 5
Top path 4 7 12
Bottom path 5 8 11
Result 5 7 12
EuroProjex [email protected] jrt/epm/mar06
Monte Carlo analysis
Duration (months)
100%
80%
60%
40%
20%
100%
80%
60%
40%
20%5%
13%
31%41%
8%2%
6 7 8 9 10 11
Probabilty
theduration
will equaloutcome
Probabiltytheduration isless thanoutcome
-
7/23/2019 PMI63 Analyzing Risk
5/12
EuroProjex [email protected] jrt/epm/mar06
Analyzing Risk
Simple example
Sensitivity analysis
Three point estimating
Monte-Carlo analysis
EuroProjex [email protected] jrt/epm/mar06
Sensitivity analysis
Determine the response of the project as oneor more key parameters varies
Determine the value that flips the decision
-
7/23/2019 PMI63 Analyzing Risk
6/12
EuroProjex [email protected] jrt/epm/mar06
Value vs Discount factor
2% 4% 6% 8%
2000
-2000
-4000
-6000
-8000
-1000
EuroProjex [email protected] jrt/epm/mar06
Plot of two parameters
Terminal Value
Fuel Cost
135
10
12
15
2 Payback, years
-
7/23/2019 PMI63 Analyzing Risk
7/12
EuroProjex [email protected] jrt/epm/mar06
Analyzing Risk
Simple example
Sensitivity analysis
Three point estimating
Monte-Carlo analysis
EuroProjex [email protected] jrt/epm/mar06
Projects are bound to fail
Work Pack Min ML Exp Max
70 100 105 150
P00 P40 P60 P99
Project Th Mn Min Est Exp Budgt Max Th Mx
700 950 1000 1050 1000 1200 1500
P00 P00 P05 P60 P80 P99 P100
Common assumption: Mode of Sum = Sum of Modes wrong
Actual: Mean of Sum = Sum of Means correct
Guess at Expected = Most optimistic + 4 x Mode + Most pessimistic
6
-
7/23/2019 PMI63 Analyzing Risk
8/12
EuroProjex [email protected] jrt/epm/mar06
ProbabilityofAchievingEstimate
Project Cost
Base Cost
Stretch Target
Target Cost
Sanction Cost
Benchmark or Historical Cost
Economic Feasibility Limit
Alliance Target Savings
Alliance Contingency
Client Contingency
Ex-ante Alliance Saving
0%
100%
Cost probability curve
EuroProjex [email protected] jrt/epm/mar06
Planned Value
Min
MLMax
Three point estimates
Start with planned value (Usually includes contingency)
min = plan - contingency (best case)
max = min + all risks + real contingency (worst case)
Most-Likely depends on probabilities & responses Calculate in simple cases
Otherwise use best guess / expert judgement
If possible use previous experience
-
7/23/2019 PMI63 Analyzing Risk
9/12
EuroProjex [email protected] jrt/epm/mar06
Analyzing Risk
Simple example
Sensitivity analysis
Three point estimating
Monte-Carlo analysis
EuroProjex [email protected] jrt/epm/mar06
}=TOTAL DURATION
DISTRIBUTION
%PROBABILITYDISTRIBUTIONS
(3 point
estimates)
TASKS ACTIVITY
1
ACTIVITY
2
ACTIVITY
3
+ +
Et
cincidence
How does Monte Carlo work?
Apply three point estimates
Run model randomly sampling values
Calculate outturns with those values
Repeat a large number of times (1,000-10,000)
Sum to produce probability distributions
-
7/23/2019 PMI63 Analyzing Risk
10/12
EuroProjex [email protected] jrt/epm/mar06
EuroProjex [email protected] jrt/epm/mar06
-
7/23/2019 PMI63 Analyzing Risk
11/12
EuroProjex [email protected] jrt/epm/mar06
EuroProjex [email protected] jrt/epm/mar06
-
7/23/2019 PMI63 Analyzing Risk
12/12
EuroProjex [email protected] jrt/epm/mar06
EuroProjex [email protected] jrt/epm/mar06
END of SESSION 6 3