    SIMPROJECT AProjectManagementSimulationforClassroomInstruction

    PLAYERQUICKSTARTMANUAL

    Version2.5

    InstructorsManualforusewithSIMPROJECT

    JeffreyK.Pinto,Ph.D.andDianeH.Parente,Ph.D.

    ISBN:9781615843176

    Published by SimProfessionals LLC. Copyright 2009

    Copyright McGraw Hill Irwin 2000-2009. All rights reserved.No part of this publication may be reproduced or distributed in any form or by any means, or stored in a database or retrieval

    system, without the prior written consent of SimProfessionals, LLC, including, but not limited to, in any network or otherelectronic storage or transmission, or broadcast for distance learning.

    www.simprofessionals.com

    www.simprojectonline.com

  • 7/31/2019 Player Quick Start

    2/24

    PLAYERUSE

    i

    PrefaceSimProject

    TMisawebbasedcomputersimulationthatisintendedtoteachthe

    principlesofprojectmanagement. Itallowsaninstructortosetupasimulation,formteams

    ofstudents

    (or

    allow

    them

    to

    play

    individually),

    and

    to

    illustrate

    and

    practice

    project

    management.

    Thismanualisaprimerforplayerstosupplementtheinstructorslectures. A

    completeversionofthePlayersManualiscurrentlyunderdevelopment.

    Toomanycurrentprojectmanagerscontinuetolearntheircraftthroughbaptisms

    byfire,withminimaladvancepreparation. Thisapproachisexpensivetotheircompanies

    anddiscouragingtotheseindividuals. Inthepast,thisapproachwasnecessarybecause

    formalprojectmanagementtrainingwasoftenlackingandoptionssuchasproject

    simulationsnonexistent. Fortunately,thisisnolongerthereality. SimProjectisavaluable

    toolfortrainingsuccessfulgenerationsoffutureprojectmanagers. Wegenuinelyhopethat

    youfind

    SimProject

    avaluable,

    thought

    provoking,

    and

    useful

    component

    for

    learning

    projectmanagement. Wewishyouthebestofluckandsuccesswithallyourprojects!

  • 7/31/2019 Player Quick Start

    3/24

    PLAYERUSE

    ii

    Contents

    Preface..................................................................................................................................................... i

    Tableof

    Figures

    .....................................................................................................................................

    iii

    1 QuickReferenceGuide................................................................................................................... 1

    1.1 OverviewofSimProject.......................................................................................................... 1

    1.1.1 Whatarethetechnicalrequirementsofthesimulation?.............................................. 1

    1.1.2 Howisthesimulationstructured?................................................................................. 2

    1.2 Players.................................................................................................................................... 3

    1.2.1 RegisteringasaPlayer.................................................................................................... 3

    1.2.2 MakingDecisions............................................................................................................ 5

    1.2.3 InterpretingtheResults................................................................................................ 14

    1.3 Summary............................................................................................................................... 19

    2 INDEX............................................................................................................................................ 20

  • 7/31/2019 Player Quick Start

    4/24

    PLAYERUSE

    iii

    TableofFiguresFigure1BrowserProcedureInstructions............................................................................................... 2

    Figure2New

    Player

    Registration

    ...........................................................................................................

    3

    Figure3RegistrationCodeScreen......................................................................................................... 4

    Figure4Security/ProfileInformation..................................................................................................... 5

    Figure5PlayerDecisionScreen............................................................................................................. 6

    Figure6PeriodDecisionMakingScreen................................................................................................ 6

    Figure7ResourcePage.......................................................................................................................... 7

    Figure8ResourceSelection................................................................................................................... 7

    Figure9Addingaresource..................................................................................................................... 8

    Figure10ResourceBidding.................................................................................................................... 8

    Figure11TrainingCatalog...................................................................................................................... 9

    Figure12

    Training

    Assignment

    Screen

    ...................................................................................................

    9

    Figure13ManagerialActionsCatalog.................................................................................................. 10

    Figure14ManagerialActionAssignment............................................................................................. 11

    Figure15PeriodTasks.......................................................................................................................... 11

    Figure16ResourceAssignmenttoTask............................................................................................... 12

    Figure17ResourceAssignmentPercentage........................................................................................ 12

    Figure18TaskAssignmentResults...................................................................................................... 13

    Figure19PeriodTaskScreen............................................................................................................... 13

    Figure20SubmitDecisionScreen........................................................................................................ 14

    Figure21TeamResultsInterpretation................................................................................................. 15

    Figure22PeriodResultsInterpretation............................................................................................... 17

  • 7/31/2019 Player Quick Start

    5/24

    1

    1 QuickReferenceGuide1.1 OverviewofSimProject

    Conceptually,players

    manage

    aproject.

    The

    project

    Gantt

    chart

    is

    the

    foundation

    forasimulation. YoumaythinkoftheprojectGanttchartasresidingwithinSimProject.

    Playersmakedecisionsastowhichresourcetohireorfire,whethertotrainaresourceto

    improvetheirindividualattributes,whentoinvokeavarietyofmanagerialactionsfor

    motivation(e.g.holdapizzaparty),andwhichresourcetoassigntoeachofthetasks.

    Duringprocessing,SimProjecttakesthedecisionsmadeandcalculatestheactualtime

    andcostforeachtaskbasedonthedecisions. SimProjecttheninteractswithMicrosoft

    ProjectTM

    tocreatetheprojectfile(.mppfile)includingtheactualresultsfromeachround

    asitisplayed.

    One

    common

    problem

    with

    computer

    simulations

    is

    that

    students

    may

    obtain

    informationfrompriorstudentsthatwillallowcurrentstudentstohaveacompetitiveedge.

    Wecallthissimulationcarryover. Inordertominimizethisphenomenon,SimProjectsets

    upsimulationsthatareasdifferentfromeachotherasinstandardpractice. Anewand

    differentsimulationisgeneratedbySimProjecteachtimeaninstructorcreatesasimulation

    foraclass.Therearealmostaninfinitenumberofvariationsonthesimulationsbasic

    templates.

    1.1.1 Whatarethetechnicalrequirementsofthesimulation?SimProjectisawebbasedcomputersimulationusedtoenhanceinstructionof

    projectmanagement.

    SimProject

    works

    with

    MS

    Project

    in

    aWindows

    environment.

    Please

    notethatMSProjectmustbeinstalledonthecomputeraccessingSimProjectorbe

    availableoncomputerlabmachinesifstudentsareusingalabenvironment. MSProject

    neednotbeopenasSimProjectwillcallandopenMSProjectasitisneeded. Thisiswhy

    SimProjectfunctionalityisenhancedwithInternetExplorer. (PleasenotethatSimProject

    willworkinabrowserotherthanInternetExplorerbuttheMSProjectplanmaynotbe

    viewablefromanotherbrowser.) Withrespecttotheplatform,thewebapplication,

    SimProject,canbeviewedinanonWindowsplatformbutcannotcallMSProject. Running

    inanonWindowsplatformseverelylimitsthefunctionalityoftheprogram.

    SimProjectwas

    designed

    to

    work

    with

    Internet

    Explorer

    versions

    prior

    to

    IE

    8.0.

    SinceIE8.0hasimplementedenhancedsecurityfeaturesandmayblocksomewebsites,the

    simpleprocesslistedbelowwillhandlethesesecurityissues. Thisprocessisalsogivenat

    http://www.simprojectonline.com/cookies.aspx .

  • 7/31/2019 Player Quick Start

    6/24

    2

    Figure1BrowserProcedureInstructions

    StudentsmayviewandinteractwiththeSimProjectwebsitefromanybrowseron

    anyplatform. However,MSProjectisonlyavailablefortheWindowsplatform. Therefore,

    thestudentcannotuseanonWindowsplatformwithSimProjectandexpecttoexperience

    thefullimpactofthesoftware.

    1.1.2 Howisthesimulationstructured?SimProject

    TMisorganizedintwoparts.ThefirstpartiscalledPrePlayinwhich

    resourcebiddingtakesplace. ThesecondisPeriodPlayorRoundPlay. Thisistheformal

    partoftheprojectfromtheStartnodetotheFinishnode.

    Simulationprojectsarestructuredintwoparts;preplayandplay. Theportionof

    thesimulationthatoccursbeforetheStartnodeontheGanttchartiscalledpreplay. The

    onlydecisionsthatcanbemadeinPrePlayaretheselectionofresources. Playersmaybid

    forvirtualresourcesduringthepreplayperiods.Yourinstructormayrunasmanypreplay

    roundsashe/shechoosespriortobeginningplay. (Notethatinstructorsmayalsochooseto

    beginthesimulationwithPlayandnotparticipateinresourcebiddingandselectionrounds.

    Thesimulationwillautomaticallypopulateeachteamwithresourcesifthatoptionis

    chosen.)

  • 7/31/2019 Player Quick Start

    7/24

    3

    ThevirtualprojectbeginsduringPlayorattheStartnodeontheGanttchart.The

    underlyingGanttchartoftheprojectisdividedinto12periods. Oncethesimulationplay

    begins,theteamscompeteagainsteachother,periodbyperiod.

    1.2 PlayersAlthough

    detailed

    information

    will

    be

    given

    in

    the

    full

    version

    Players

    Manual,

    an

    overviewispresentedinthepagesthatfollow.

    1.2.1 RegisteringasaPlayerOnthewebsiteatwww.simprojectonline.comintheareaforNewUser,playersclick

    onregisternowasshowninFigure2.

    Figure2NewPlayerRegistration

    1. Aregistration(oraccess)codeisaunique9digitcodethateachplayeris

    requiredtohavetoparticipateinthesim. Generally,schoolswillarrangefor

    theirbookstorestocarrythecodes. Thecodesmayalsobeavailablefrom

    variousonlinesites. However,besurethatthecodeacquired(from

    whateversource)isISBN9781615843176. OnlycodeswiththisISBNwill

    besupported. The9digitcodeshouldbeenteredintotheboxesmarkedby

    theredarrowinFigure3.

    2. TheinstructorwillprovidetheentireclasswiththeSimulationCodethatwas

    generatedforyourspecificclass.Playersenterthe7digitSimulationCode

    intotheboxesmarkedbythegreenarrowinFigure3.

  • 7/31/2019 Player Quick Start

    8/24

    4

    3. PlayersthenclickonNewUserasindicatedbythebluedashedarrowin

    Figure3.

    Figure3RegistrationCodeScreen

    4. YouwillthenbepresentedwiththeSecurity/ProfileInformationinFigure4.

    Onceyoucompleteallinformationrequested,youwillcreateaUserIDand

    passwordto

    enter

    SimProject.

    You

    will

    not

    need

    the

    Registration

    Code

    or

    the

    SimulationCodeagain. Justincaseyoucannotrememberyourinformation,

    theinstructorcanaccessitforyou. However,youshouldwriteitdownso

    thatyouhaveimmediateaccesstowhatyoucreated.

  • 7/31/2019 Player Quick Start

    9/24

    5

    Figure4Security/ProfileInformation

    Onceplayersregister,yourinstructorwillassignyoutoteams. Youmustbe

    assignedtoateambeforeyouareabletoseethesimulation. Onceyouareassignedtoa

    team,youcanuseyourusernameandpasswordtoentertheclasssimulationandtomake

    decisions.

    1.2.2 MakingDecisionsPlayersmaymakefourtypesofdecisions:

    Resourcedecisionsaddorremoveresourcesfromtheproject

    Trainingdecisionssendresourcestotrainingclasses

    Managerialactionstakemanagementactionstoinfluenceresources

    Periodtasks

    assign

    one

    or

    more

    resources

    to

    each

    task

    for

    the

    period

    Whenplayersselectthesimulation,theyarepresentedwiththeProjectInformation

    asshowninFigure5. TheycanclickonMakePeriodDecisionsasshownbytheredarrow.

  • 7/31/2019 Player Quick Start

    10/24

    6

    Figure5PlayerDecisionScreen

    AfterselectingMakePeriodDecisions,playersarepresentedwiththePeriod

    DecisionMakingScreeninFigure6. Inthenextsections,wewillwalkthroughthe

    selectionsforResourceDecisions,TrainingDecisions,ManagerialActions,andPeriodTasks.

    ProjectTasksarethelastselectionandpresenttheplayerswiththeopportunitytoviewall

    projecttasksandtosortbytaskgroup,period,hours,andalsotoviewtheMSProjectplan

    forthe

    entire

    project.

    Figure6PeriodDecisionMakingScreen

    1.2.2.1MakingResourceDecisionsResourcedecisionsaremadebyclickingontheResourceDecisionsinFigure6. You

    willthenbetakentotheTeamResourcespageasshowninFigure7. Thenextstepin

    selectingresourcesistoseewhoisinthepoolbyclickingonViewResourcePoolasshown

    by

    the

    red

    arrow

    in

    Figure

    7.

  • 7/31/2019 Player Quick Start

    11/24

    7

    Figure7ResourcePage

    TheResourcePoolwillbepresentedtotheplayerasshowninFigure8. Youmaysee

    additionalattributesofaparticularresourcebyclickingononeofthenamesinthe

    ResourcePool,

    say

    for

    example

    selecting

    the

    resource

    shown

    by

    the

    red

    arrow

    in

    Figure

    8.

    Figure8ResourceSelection

    MorespecificinformationonthatresourcewillappearasnotedinFigure9. Ifthe

    playerdecidestobidonthatresource,theyclickonAddResourceasshownbythered

    arrow.

  • 7/31/2019 Player Quick Start

    12/24

    8

    Figure9Addingaresource

    ThentheplayerwillseethescreeninFigure10. Theplayerwillthentypeinthe

    hourlyrateofferintheboxshownbytheredarrowandsubmittheofferbyclickingthe

    buttonnearthegreenarrow.

    Figure10ResourceBidding

    Theofferswillbenotedontheplayersscreensasofferedbutwillnotbeplaced

    onaparticularteamuntiltheinstructorprocessesthebidsineitherPrePlayorPlay. Itis

    duringthe

    processing

    that

    the

    resolution

    of

    which

    team

    wins

    the

    bid

    for

    aspecific

    virtual

    playerisdetermined. PlayersareadvisedintheViewPeriodResultssectionastowhether

    theyobtainedtheresourcesinthecompetitivebiddingand,ifnot,whynot.

    ResourceDecisionsmaybemadeineitherPrePlayorPlay. However,only

    ResourceDecisionsmaybemadeinPrePlayrounds.

  • 7/31/2019 Player Quick Start

    13/24

    9

    1.2.2.2MakingTrainingDecisionsTrainingDecisionsmaybemadeinPlayrounds.PlayersmayviewtheTraining

    catalogasshowninFigure11. Inthisgraphic,theycanseethedurationandcostofthe

    specifictrainingeventinadditiontothetotalnumberofslotsavailableandthenumber

    remaining. Finally,thegraphicwillshowhowmanypersonsontheirteamareassignedto

    thetrainingevent.

    Figure11TrainingCatalog

    WhentheplayerclicksontheclassasshownbytheredarrowinFigure11,more

    informationappearsinadditiontotheassignmentscreenshowninFigure12.

    Figure12TrainingAssignmentScreen

  • 7/31/2019 Player Quick Start

    14/24

    10

    Aplayermayassignavirtualresourcetotrainingbyhighlightingthenameinthe

    right,asshownbyredarrow#1inFigure12,thenclickingontheAddbuttonasshownby

    redarrow#2,andmovingthenametotheleftmostboxasshownbyredarrow#3. When

    playersassignresourcestotraining,theymustplanforthetimeandcostofthetraining.

    They

    also

    must

    remember

    that

    training

    occurs

    first

    in

    a

    period.

    Therefore,

    assigning

    any

    resourcetotrainingandtothefirstactivityinaperiodwill,bydefinition,delaythe

    completionoftheperiod.

    1.2.2.3MakingManagerialActionDecisionsManagerialActiondecisionsmaybemadeinPlayrounds.Playersmayviewthe

    ManagerialActionsavailableasshowninFigure13. Inthisgraphic,theycanseethename

    ofthemanagerialactionandthecostperresource. Theycanalsoseehowmanyresources

    havebeenassignedtoeachManagerialAction.

    Figure13ManagerialActionsCatalog

    Playersmay

    select

    aManagerial

    Action

    by

    clicking

    on

    the

    name

    of

    the

    action

    as

    shownbytheredarrowinFigure14.Playerscanviewadditionalinformationaboutthe

    ManagerialAction. AvirtualresourcemaybeassignedtotheManagerialActionby

    highlightingthenameintherighthandboxshownbyredarrow#1,clickingtheAddbutton

    shownbyredarrow#2,andthenamewillthenappearintherightmostboxshownbyred

    arrow#3.

  • 7/31/2019 Player Quick Start

    15/24

    11

    Figure14ManagerialActionAssignment

    1.2.2.4MakingPeriodTaskDecisionsThelastofthefourpossibledecisionsthatmaybemadebyplayersisthePeriod

    TaskDecisionortheassignmentofvirtualresourcestotasksfortheperiod. Whenclicking

    onPeriodTaskinFigure6,thescreeninFigure15isdisplayed.Inordertoassignresources

    toatask,playersmustfirstselectthetask.IntheexampleshowninFigure15,theplayer

    clicksonIdentifyVendors(asshownbytheredarrow)toassignaresourcetothetaskfor

    thisperiod.

    Figure15PeriodTasks

    When

    the

    player

    clicks

    on

    a

    task,

    such

    as

    Identify

    Vendors,

    the

    Resource

    Assignment

    screenappearsasshowninFigure16. Additionalinformationonthetaskisshownunder

    TaskInformation. Playerscanseetheestimatedorbudgetedhoursandcost,task

    description,andtaskdependenciesatthepointwhentheyareassigningresources.

  • 7/31/2019 Player Quick Start

    16/24

  • 7/31/2019 Player Quick Start

    17/24

    13

    Oncethetaskassignmentismade,playersclicktheAssignbuttonasshowninFigure

    17andthescreenshowninFigure18appears. Aftercheckingtheassignmentforthetask,

    playersclickOKatthebottomofthescreenasshownbytheredarrowinFigure18.

    Figure18TaskAssignmentResults

    ThesystemreturnsplayerstothePeriodTaskscreenasshowninFigure19where

    playerscanproceedtoassignresourcestoeachtask. Whenalltaskshavebeenassigned

    resources,theplayerclicksDoneatthebottomofthescreenasshowninFigure19.

    Figure19PeriodTaskScreen

    WhentheplayerclicksDoneinFigure19,theSubmitDecisionScreeninFigure20

    appears. ThentheplayersthenclickontheSubmitDecisionsbuttonasshownbythered

    arrowinFigure20tocompletetheprocessandrecordthetimeanddatethatdecisions

    weresubmitted. Thus,yourinstructorissurethatyouhavemetthesubmissiondeadline.

  • 7/31/2019 Player Quick Start

    18/24

    14

    Figure20SubmitDecisionScreen

    AllfourofthedecisionstypesmaybemadeinPlayrounds,althoughtheonly

    requireddecisiontypeisPeriodTasksorassigningresourcestotasks. Ifresourcesarenot

    assignedbytheteam,thesimulationwillassignresourcestotasksinanonoptimalway.

    1.2.3 InterpretingtheResults1.) TheTEAMSTANDINGSCHARTisshownnearthetopoftheViewPeriodResultspage

    (seeFigure

    21).

    The

    results

    are

    displayed

    for

    each

    of

    the

    four

    key

    factors:

    Cost,

    Time,

    FunctionalityandStakeholderSatisfaction.Inaddition,theOverallscoreisprovided(see

    arrow1inFigure21).Theoverallrankisthecalculatedpercentilefortheteamswith100as

    thebestand0astheworstoftheset. ThiscalculationisillustratedintheReferenceSection

    ofthefullversionofthePlayerManual.

  • 7/31/2019 Player Quick Start

    19/24

    15

    Figure

    21

    Team

    Results

    Interpretation

    RememberthatthescoresaredisplayedonaPERCENTILEbasis. Oneadvantageof

    usingpercentilescoringisthatitprovidesteamswitharelativescorecomparedto

    theotherteams. Theteamwiththebestmetricwillbeshownwithascoreof100%,

    whiletheteamwiththeworstmetricwillbeshownwithascoreof0%. (Itdoesnot

    meanthattheteamhasa"score"of0%.)

    Theauthorssuggestthatyoulookatthefourfactors(Cost,Time,

    Functionality,andStakeholderSatisfaction)separately.

    Cost

    Thecostmetricismeasuredbyadeviationfrombudgetthatrewardsateam

    thatisclosesttothebudget.

    ThePeriodResultspageprovidesthebudgetstatus,aswellasthedetail

    behindthebudgetchargesfortheperiod. Youcanalsogobacktoanyprevious

    periodbyclickingonthe"PeriodRanks"section. Additionally,MSProjectprovides

    manyreportsthatcanbeusedtoanalyzetheteam'sCostperformance.

    Time

    Thesimulationcalculatestheactualtimeforeachtaskbaseduponthe

    decisionsmadeandthensendsthedatatoMSProject. MSProjectperformsthe

    loadlevelingtaskandreturnstheelapsedtimefortheperiodtoSimProject. The

    FinishDateisthendisplayedinthePeriodMilestonesectionofthepage.MSProject

    hasmanyreportsthatcanbeusedtoanalyzetheTimeperformanceoftheteam.

  • 7/31/2019 Player Quick Start

    20/24

    16

    Functionality

    Functionalityisameasureofwhetherthesimulationprojectdoeswhatit

    wasintendedtodo.

    Thesimulation

    cannot

    measure

    asubjective

    factor

    such

    as

    whether

    aproject

    achieveswhatitismeanttodo. Theproxyforscoringpurposesiswhethertheteam

    ismeetingtheprojectmilestones. Youshouldaskyourselfifyouareassigningthe

    rightcategoryofresourceandifthoseresourcesarecompletingthetaskson

    budget.

    StakeholderSatisfaction

    LikeFunctionality,StakeholderSatisfactionisarathersubjectfactor.

    Satisfyingstakeholdersonarealprojectisafunctionofwhetherthestakeholders

    arepleased.

    This

    should

    be

    aresult

    of

    whether

    the

    project

    is

    coming

    in

    on

    time

    and

    iftheinteractionswiththeprojectteamarepositive. Therefore,themetricfor

    StakeholderSatisfactionwillbeacombinationofmilestonesmetandacompositeof

    theteammembers'interpersonaltraitssuchasInterpersonalskills,Flexibilityand

    PublicRelationsskills.

    2.) MSProjectfilesfortheperiodareaccessedbyclickingonViewMSProjectPlan(as

    shownbyarrow2inFigure21). MSProjectprovidesawidevarietyofreportsincludinga

    budgetvarianceonataskbytaskbasis. AllofthereportsthatareprovidedbyMSProject

    providetheteam'svirtualprojectdata. Thereportswillprovideinformationtodiagnose

    projectperformance.

    3.) Inthefollowingsection,wediscussadditionalinformation/reportingareasonView

    PeriodResultsPagewhichisillustratedinFigure22.

  • 7/31/2019 Player Quick Start

    21/24

    17

    Figure22PeriodResultsInterpretation

    TeamEfficiency(a)

    Inarealworldscenario,TeamEfficiencywouldbeameasureofanumberof

    factors. Theseincludehowwelltheteamisperformingintermsofmeetingthe

    milestones,aswellashowwelltheyaremanagingtheprocess. Thiswouldinclude

    suchfactorsashowwelltheteamgetsalong(cohesion),themanagerialstyle

    developedwithintheteam,theteamcomposition(e.g.diversityofskills,age,

    experience,gender,

    and

    ethnicity),

    the

    movement

    of

    personnel

    on

    and

    off

    the

    team

    (longevityofcore),andhowwelltheteamimplementsrewardsanddiscipline

    (managerialactions). ThescoreforTeamEfficiencyisgivenasapercentageand

    displayedonthePeriodResultspageintheFinancialsandStatisticsportionofthe

    page.

    PeriodMilestoneachieved(b)

    Intherealworldateamwouldeitherachieveornotachieveamilestone.

    Thesimulationgivescreditinthescoringtoateamforcomingclosetotheir

    milestone. ThecutoffforcreditissetbytheInstructorwhentheycreatetheclass

    simulation. ThatcutoffpercentagemaybeseenonthePeriodResultspageunder

    periodMilestone.

    UnallocatedResources(c)

  • 7/31/2019 Player Quick Start

    22/24

    18

    Ifyouhirearesourceintherealworld,yourbudgetischargedfortheirrate

    whetheryouassignthemtoataskornot. Thesimulationreflectsthis"bench

    penalty"withanUnallocatedResourcescharge. Ifyoudonotassignaresourcetoa

    taskortrainingforatleast25%oftheelapsedtimefortheperiod,theteamwillbe

    charged

    the

    difference

    between

    the

    actual

    assignment

    time

    and

    25%

    of

    the

    elapsed

    timefortheperiod. ThischargewillappearinthePeriodCostsectionofthePeriod

    Resultspage.

    Effectivenessrating(d)

    Effectivenessreferstotheassignmentofthebestcategoryofresourcetoa

    task(e.g.Didyouassignaplumbertoperformplumbingwork?). Whileallvirtual

    resourcescanperformalltasks,thereisasinglebestcategoryforeachtask. The

    highertheEffectivenessisforatask,thecloseryouweretoassigningtheright

    category

    for

    the

    task

    and

    the

    better

    your

    overall

    score.

    Efficiencyrating(e)

    Whileitisimportanttoassignthecorrectcategoryofresource,allresources

    inthesamecategoryarenotequal. Inotherwords,allengineersarenotcreated

    equallyinthesimortherealworld. Thevirtualresourcesallhavedifferent

    individualattributescores. Notall(say)engineersworkthesame. Somearemore

    efficientthanothers. Toincreasethescoreinthisarea,considerTrainingor

    ManagerialActionsthatmayincreaseefficiency.

    AllocatedHours(f)

    Whenaresourceisassignedtoatask,thesimaskswhatpercentofthetime

    ofthatresourceistobeallocated. Iftheteamassignstheresourcefor100%,that

    meanstheresourcewillworkonthetaskforeight(8)hoursadayuntilthetaskis

    complete.

    Thisrevealstheconceptofworkormanhoursandelapsedhoursor

    duration. Thesimcalculatestheworkhoursneededforataskandtheelapsed

    hoursitwilltaketheactualpersonassignedtocomeupwiththeelapsedhoursor

    duration. Then,theelapsedtimeitwilltaketofinishthejobwillbebasedonthe

    numberofhoursperdaywillbeputonthetask.

    IftheteamisnotdoingwellintheTIMEmetric,itmaybethattheyare

    allocatingresourcesonalowerpercentage. Assuch,itwilltakelongertocomplete

    thetask.

  • 7/31/2019 Player Quick Start

    23/24

    19

    1.3 SummaryWhiletheQuickstartManualshouldhelpyoutonavigatethebasicdecisionsofthe

    simulation,afullversionofthePlayerManualisavailable.

  • 7/31/2019 Player Quick Start

    24/24

    20

    2 INDEXGantt

    chart,

    1,

    3,

    12

    individualattributes,1

    managementaction,5,Seemanagerialaction

    Managerialaction,5

    managerialactions,1

    MicrosoftProjectTM,1

    MSProject,

    1,

    2,

    6,

    SeeMS

    Project,

    See

    MicrosoftProject

    PeriodResults,8,17

    Periodtask,5

    preplay,

    2

    register,3,5

    ResourceAllocation,12

    Resourcedecision,5

    simulationcarryover,1

    taskassignment.Seeresourceallocation

    taskdependencies,

    11

    taskdescription,11

    Trainingdecision,5