placement of facilities in spp rate zones
TRANSCRIPT
SouthwestPowerPool SPPorg southwest-power-poolHelping our members work together to keep the lights on... today and in the future.
PLACEMENT OF FACILITIES IN SPP RATE ZONESJUNE 30, 2021
2
ATTACHMENT AI
• Above the voltage threshold (excluding transformer isolation equipment)
• Non-radial or multi-customer (wholesale) radial facilities• Open loops are considered radial
• Interconnections between zones or to another transmission provider
• Control and protection equipment
• DC ties owned by an SPP TO
• Seven-factor test with determination by FERC
3
ZONAL PLACEMENT PROCESS• Applicability to: 1) Integration of a potential SPP TO’s existing
facilities with resulting impact on Zonal ATRR under Schedule 9, or 2) Purchase by a current SPP TO of existing facilities that were not previously included in Zonal ATRR under Schedule 9
• Four-stage process: 1) Notification, 2) Information request from SPP, 3) Integration analysis including a rate impact assessment (45 days), 4) Affected parties’ negotiation (45 days)
• Data provided includes: Identification of facilities, Integration of facilities and operations in SPP, Reliability and comparability of the facilities, ATRR and its components, Loads served, Line miles and number of substations, Service area
• At the end of the process, a filing is submitted to FERC
4
ZONAL PLACEMENT CRITERIA
• FERC has stated that placement of facilities in a zone is a case-by-case determination
• Criteria applied by SPP in recent reviews include the following:• To determine whether to place the facilities in a new zone—
• (i) whether the ATRR is less than a minimum threshold based on a 3-year average. Recently, this has been around $13 million
• (ii) extent to which the facilities substantively increase the SPP regional footprint
• (iii) nature of transmission service to serve load prior to the facilities transfer date
5
ZONAL PLACEMENT CRITERIA
• If a new zone is not created, the determination of which existing zone the facilities are placed in is based on—
• (i) the extent to which the facilities are embedded in an existing zone
• (ii) the extent to which the facilities are integrated with an existing zone
• (iii) nature of transmission service to serve load prior to the facilities transfer date.
• Ultimately, FERC makes the determination as to whether the proposed zonal placement is just and reasonable
6
SECTION 30.9 CREDITS
• Provides that a network customer can offset its transmission service bill by the revenue requirement of transmission facilities it owns
• To qualify, the facilities must be integrated with the SPP transmission system as specified in Section 30.9. Among other things, the facilities should qualify under Attachment AI
• There is no credit over and above the customer’s network transmission service charge amount—i.e., no payment to customer
• The cost of the credit is included in the zonal revenue requirement paid by all customers in the zone
• SPP must submit filings to FERC in order to effectuate the crediting arrangement
SouthwestPowerPool SPPorg southwest-power-poolHelping our members work together to keep the lights on... today and in the future. 7
SPP RESOURCE ADEQUACY POWER PURCHASE AGREEMENT REQUIREMENTSCHRIS HALEY
8
WHO IS RESPONSIBLE FOR RESOURCE ADEQUACY?
• LRE is an asset owner with registered load in the SPP Integrated Marketplace
• Entities with load-serving obligations in the SPP Balancing Authority (BA) will be responsible for complying with SPP’s Resource Adequacy Requirement (RAR)
• Attachment AA requires a LRE to maintain capacity required to meet its load and planning reserve obligations.
• If an LRE serves load both internal and external to the SPP BA, compliance with the RAR does not affect an LRE’s obligation to maintain distinct and separate amounts of resources to cover planning reserve obligation for load external to the SPP BA
• Market Participant is responsible to ensure the LRE’s compliance
Load-responsible entity (LRE)
9
DEMAND TYPES
• The highest demand including a) transmission losses for energy, b) the projected impacts of non-controllable and non-dispatchable behind-the-meter generation, and c) the projected impacts of non-controllable and non-dispatchable demand response programs measured over a one clock hour period.
Peak demand
Net peak demand (NPD)• The forecasted peak demand less the a) projected impacts of a
demand response program and b) adjusted to reflect the contract amount of firm power with another entity as specified in section 8.2 of this Attachment AA.
• SPP’s RAR is applied to each LREs NPD.
10
CAPACITY AND POWER PURCHASE TYPES
• The accredited capacity of commercially operable generating units, or portions of generating units, adjusted to reflect purchases and sales of capacity with another party and is deliverable with firm transmission service to the LRE’s load.
Firm capacity
Firm power• Power purchases and sales deliverable with firm transmission
service to serve the LRE’s load with capacity, energy and planning reserves, which must be continuously available in a manner comparable to power delivered to native-load customers.
11
QUALIFICATION OF CAPACITY (ATTACHMENT AA, SECTION 7)
• Firm capacity/power from a resource(s) internal to the SPP BA must:• Demonstrate the resource(s) is:
• Registered in the Integrated Marketplace or• Listed as a designated resource in the Network Integration Transmission Service
Agreement• Submit current operational and capability test results as performed in accordance with
the SPP Planning Criteria• Demonstrate that there is firm transmission service from the internal resource(s) to the
LRE’s load• Firm capacity/power from a resource(s) external to the SPP BA must:
• Demonstrate ownership or contractual rights• Submit current operational test results per the requirements of the BA where the
resource(s) is located• Demonstrate firm transmission service from the external resource(s) to the LRE’s load• Attest that any external capacity identified is not otherwise being used as capacity in
any other BA or in another resource adequacy construct
Firm capacity and firm power requirements
12
QUALIFICATION AND VERIFICATION OF POWER PURCHASE AGREEMENTS (ATTACHMENT AA, SECTION 8)• (8.2) When a PPA qualifies as Firm Power and the purchaser and seller
are both LREs:• Purchaser deducts the contract amount from its Net Peak Demand • Seller adds the amount to its Net Peak Demand • The responsibility to maintain the RAR and the Winter Season
obligation transfers from the purchaser to the seller
• (8.3) When a PPA qualifies as Firm Power and the seller is not an LRE:• Purchaser cannot deduct the contract amount from its Net Peak
Demand• Purchaser remains responsible for the RAR and Winter Season
obligation for load served by the agreement• Purchaser reflects the contract amount plus the purchaser’s PRM
multiplied by the contract amount as Firm Capacity • Firm transmission service is only required for the contract amount
8.2: Contract is for 10 MWsPurchaser LRE 1: 100 MWs of NPD100(NPD)– 10 = 90 MW NPDSeller LRE 2: 100 MWs of NPD100(NPD) +10 = 110 MW NPD
8.3: Contract is for 10 MWsPurchaser LRE 1: 100 MWs of NPDCannot deduct = 100 MW obligationAdds the 10 MW plus reserve amount to their generation portfolio
13
QUALIFICATION AND VERIFICATION OF POWER PURCHASE AGREEMENTS (ATTACHMENT AA, SECTION 8)
• (8.4) When a PPA qualifies as Firm Power and the purchaser is not an LRE, seller is LRE• Seller cannot include the purchased contract
amount in its Net Peak Demand• Seller reflects the contract amount plus the
seller ’s PRM multiplied by the contract amount as Firm Capacity
• Firm transmission service is only required for the contract amount
Contract is for 10 MWsPurchaser is not an LRESeller LRE 1: 100 MWs of NPDSubtracts the 10 MW plus reserve amount from their generation portfolio
SouthwestPowerPool SPPorg southwest-power-poolHelping our members work together to keep the lights on... today and in the future. 14
SPP OPERATIONSOVERVIEW
15
16
Primary Control Center
17
Back-up Control Center
18
OperatingReserves Posted
0600
Bidding Closes
0930
DA Market Results Posted
1300
Re-Offer Period Closes
1345
DA RUC Results Posted
1615
DA MARKET TIMELINE
19
INPUTS INTO THE DA MARKET? Activated Flowgates
Instantaneous Load Capacity
Interchange Transactions
Load Forecast
Multi-Day Reliability Assessment (MDRA) Commitments
Resource and Transmission Outages
Virtual Bids and Offers
P.34
20
DA MARKET INPUTS AND OUTPUT
20
DA Market
Cleared OffersCommitment for Energy
Cleared Bids, OR, Virtuals, & Trans.
DA Market Prices
Bids & Offers (DA & Virtual)
MDRA Commitments
DA Confirmed Interchg. Trans.
SPP OR Requirements
Trans. System Topology
Trans. and Resource Outages
Activated Flowgates
Parallel Flow Forecasts
Instantaneous Load Capacity
21
PURPOSE OF RUC
Commit resources to meet forecasted RT capacity
requirement
Key inputs include RT offers, forecasts, & OR req.
Minimizes total commitment costs
22
A CLOSER LOOK
Bid-in Load and Operating Reserve (OR)
cleared in DA Market
Generation committed in DA Market
Hours
Load Forecast and OR Requirements (RUC Input)
Generation Committed in RUC
Generation De-committed
in RUC
Hours
23
Multi-Day Reliability
Assessment (MDRA)
Day-Ahead (DA) RUC
Intra-Day (ID) RUC
Short-Term RUC (ST-RUC)
RUC STUDIES
1 2
3 4
24
Issue start-up orders in advance
PURPOSE OF MDRA
24
Performed daily
At least three (3) days prior to OD
Assesses capacity adequacy
25
MDRA INPUTS: DAY BEFORE DA (DBDA) STUDY
25
DBDA:• Runs everyday at 2200 • Utilizes all algorithms, but focus is
constraint identification• Build new flowgates to enforce in
subsequent studies
26
MDRA INPUTS AND OUTPUT26
Real-Time (RT) Offers
Est. Interchange Transactions
Est. OR Requirements
Mid-Term Load Forecast
Trans. System Topology
Trans. and Resource Outages
Resource Output Forecast (Wind & Solar)
Activated Flowgates
MDRA Suggested Resources for Commitment
27
Multi-Day Reliability
Assessment (MDRA)
Day-Ahead (DA) RUC
RUC STUDIES
1 2
28
PURPOSE OF DA RUCAssesses capacity adequacy during DA period and remainder of current OD
28
Operating Day (OD) DA Market
NO Forecasts
Virtuals
DA RUC
Forecasts
NO Virtuals
29
DBDAResults
0300
DA Market Closes
0930
DA Market Results Posted
1300
Re-Offer Period Closes
1345
DA RUC Results Posted
1615
DA RUC TIMELINE All resources noton outage
30
DA RUC INPUTS AND OUTPUT30
Resource Commit/ Decommit
RT Offers & Existing Commit.
Confirmed Interchange Trans.
SPP OR Requirements
Instantaneous Load Capacity
Trans. System Topology
Trans. and Resource Outages
Mid-Term Load Forecast
Resource Output Forecast
Parallel Flow Forecasts
Activated Flowgates
DA RUC
31
DA RUC ANALYSIS & COMMITMENT
DA Operator analysis
Can the commitment
wait?
Resource(s) added to
COPNotification sent to MP
31
1 2 3 4
32
Multi-Day Reliability
Assessment (MDRA)
Day-Ahead (DA) RUC
Intra-Day (ID) RUC
RUC STUDIES
1 2
3
33
THE PURPOSE OF ID RUCAssesses capacity adequacy intra-OD
33
Operating Day (OD)
34
ID RUC TIMELINE
ID RUC 1ID RUC 2
ID RUC 3ID RUC 4
ID RUC 5
ID RUC 5
ID RUC 14 hr interval
ID RUC 24 hr interval
ID RUC 34 hr interval
ID RUC 44 hr interval
ID RUC 54 hr interval
ID RUC 64 hr interval
ID RUC 6
ID RUC 6
DBDA RUC 0000-0300
DA Market0930-1300
DA RUC1345-1615
35
ID RUC ANALYSIS & COMMITMENT
Algorithms run with updated
inputs and cleared RT OR
RUC Operator
analysis of potential
commitments
Can the commitment
wait?
Resource(s) added to COP
1 2 3 4
Notification send to MP
5
36
Multi-Day Reliability
Assessment (MDRA)
Day-Ahead (DA) RUC
Intra-Day (ID) RUC
Short-Term RUC (ST-RUC)
RUC STUDIES
1 2
3 4
37
PURPOSE OF ST-RUCLooks to extend or commit resource(s) that:
• Help smooth intra-hour transitions
• Reduce manual commitments
• Lower commitment of more costly resources
Designed to more frequently evaluate system conditions
38
ST-RUC PROCESS
Hour 1 Hour 2 Hour 3
Looks at 15-minute intervals over next 3 hours
00 15 30 45 00 15 30 45 00 15 30 45 00
Runs in about 10 minutes
In 3-hr. window, committed resource must:• Start up• Achieve its min. run time• Shut down
SCUC
39
Reliably operate grid; balance RT Demand and Generation
Determined by RT Offers, Load Forecast, and OR requirement
Minimizes total production costs
PURPOSE OF RTBM
40
RTBM INPUTS AND OUTPUT
40
RTBM
Resource Commitments
RT Offers
SPP OR Requirements
Approved/Tagged Inter. Trans.& DC Tie Schedules
Short-Term Load Forecast
State Estimator Data
Current Resource Output & Control Status
Manual or Auto-Activated Flowgates
Regulation-selected Resources Dispatch Instructions
Cleared Operating Reserve (OR)
RT Prices
41
Short-Term Load Forecast (10 minutes out)
System Conditions
RT Resource Data
RTBM runs/solves (interval 0105-0110)
Dispatch Instructions
RT Prices
10 MW
30 MW
0100 0105 01100110 0115
Cleared OR
42
System Conditions
RT Resource Data
RTBM runs/solves (interval 0110-0115)
Dispatch Instructions
RT Prices
25 MW
30 MW
0100 0105 01100110 0115
Cleared OR
Short-Term Load Forecast (10 minutes out)
43
Dispatch Instruction & Cleared OR
Snapshot Data
SetpointInstruction
Control Status
1
23
Market Participant / Asset Owner
Dispatch and Cleared OR
Offer Data
2
5
Indicates ability to follow Setpoint Instructions
4
44
WHAT IS CONGESTION?
• Congestion or “bottlenecks” happen when you can’t get energy to customers along a certain path• Desired electricity flows exceed physical capability
• Congestion caused by:• Lack of transmission, often due to load growth• Line and generator maintenance outages• Unplanned outages such as storms or trees on lines• Too much generation pushed to grid in a particular location• Preferred energy source located far from customers
• Results in inability to use least-cost electricity to meet demand
Flowgate
A transmission facility or transmission element(s) that has been identified as limiting the amount of power that can be reliably transferred over the bulk transmission system.
Shift Factor
A percentage that represents how much
impact an injection (e.g. from a Generator)
or withdrawal at a node causes on a flowgate.
Shadow Price47
How much it costs to reduce
flow on a flowgate
(per megawatt of flow)
Market Clearing Engine (MCE)
An optimization-based application that includes two core algorithms: SCUC and SCED.
Security Constrained Unit Commitment (SCUC)
An algorithm that determines which units are committed.
Security Constrained Economic Dispatch (SCED)
An algorithm that determines unit dispatch andLMP at each node.
Linear Programming (LP)
A mathematical optimization technique used in the Day-Ahead (DA) Market and Real-Time Balancing Market (RTBM)
to determine the dispatch of committed units.
LP Problem
52
LP P
robl
emObjective Function
Parameters to minimize or maximize
ConstraintsThings that should not be violated
Decision VariablesAdjustable parameters
MCCiMLCiMECLMPi
LMP Decomposition – Basic
Marginal cost of Energy
Marginal cost of losses at PNode irelative to Reference Bus
Marginal cost of congestion at PNode i relative to Reference Bus
MCCiMLCiMECLMPi
1. Shift Factors
Sub-component of MCC
1. Shift Factors – Defined
55
How much impact does an injection… or a withdrawal at a node…
cause on Flowgate Y?
Generator: Injection Load: Withdrawal
MCCiMLCiMECLMPi
3. Shadow Price
Sub-component of MCC
MEC is also Shadow Price of balancing power
3. Shadow Price – Defined57
How much it costs to reduce
flow on a flowgate
(per megawatt of flow)
3. Shadow Price – Illustration
Gen 1:250 Max$6/MWh
Load = 200 MW
Gen 2:250 Max
$10/MWhFlowgate YTransfer Limit = 150 MW
Total Cost: ($6 * 150MW) + ($10 * 50MW) = $1,400
150MW
50 MW
Let’s increase the transfer limit on Flowgate Y by 1 MW.
3. Shadow Price – Illustration (cont’d.)
Gen 1:250 MW$6/MWh
Load = 200 MW
Gen 2:250 MW
$10/MWhFlowgate YTransfer Limit = 151 MW151
MW49
MWWhat is the likely change in
output for Gen 1 and Gen 2?
3. Shadow Price – Illustration (cont’d.)
Gen 1:250 MW$6/MWh
Load = 200 MW
Gen 2:250 MW
$10/MWhFlowgate YTransfer Limit = 151 MW
NEW Total Cost: ($6 * 151MW) + ($10 * 49MW) = $1,396
151MW
49 MW
3. Shadow Price – Illustration (cont’d.)
Gen 1:250 MW$6/MWh
Load = 200 MW
Gen 2:250 MW
$10/MWhFlowgate YTransfer Limit = 151 MW
Shadow Price (SP): $1,396 - $1,400 = -$4
151MW
49 MW
3. LMP – Illustration No Congestion
Gen 1:250 Max$6/MWh
Load = 200 MW
Gen 2:250 Max
$10/MWh
Load Pays : ($6 * 200MW) = $1,800
200MW
0 MW
Gen 1: ($6 * 200MW) = $1,800 Revenue
($6 * 200MW) = $1,800 Cost
MCCiMLCiMECLMPi
LMP Decomposition – Advanced
LMPi MEC -LossSens MEC SPSFΣ
𝑳𝑳𝑳𝑳𝑳𝑳𝒊𝒊 = 𝑀𝑀𝑀𝑀𝑀𝑀 + (−𝜕𝜕(𝑆𝑆𝑆𝑆𝑆𝑆 𝐿𝐿𝐿𝐿𝐿𝐿𝐿𝐿𝐿𝐿𝐿𝐿)𝜕𝜕𝑆𝑆𝑖𝑖
𝑀𝑀𝑀𝑀𝑀𝑀) + (∑𝑘𝑘=1𝐾𝐾 𝑆𝑆𝑆𝑆𝑆𝑆𝑆𝑆𝑆 𝐹𝐹𝐹𝐹𝐹𝐹𝑆𝑆𝐹𝐹𝐹𝐹𝑖𝑖𝑘𝑘 ∗ 𝑆𝑆𝑆𝑆𝑘𝑘)
64
DANIEL BAKERSPP RC OperationsPlease feel free to contact me at [email protected]