physical planning - technical manual - ufs

32
Physical Planning Quarterly Revised Manual Edition 1

Upload: others

Post on 10-Apr-2022

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Physical Planning - Technical Manual - UFS

Physical PlanningQuarterly Revised Manual

Edition 1

Page 2: Physical Planning - Technical Manual - UFS
Page 3: Physical Planning - Technical Manual - UFS

This document is of utmost importance for the correct implimentation of technical guide-

lines and was designed to address specific and unique needs as compiled by the Depart-

ment of Physical Planning, University of the Free State. This guideline manual is directed

specifically at problemsolving as a preventative informational guideline within the Univer-

sity and took time and knowledge to compile and may not be copied/altered/re-designed or

provided/introduced to a third party, unless under specific direction (in writing) from the

Department of Physical Planning.

Page 4: Physical Planning - Technical Manual - UFS

10.2.2 Magnetic locks 10.2.3 Auto door closers 10.2.3.1 Overhead type 10.2.3.2 Floor type11. Structural Steelwork12. Aluminium work13. Plastering14. Plumbing and drainage 14.1 General 14.2 Inside buildings 14.3 Outside buildings 14.4 Stop taps 14.5 Fire equipment 14.6 Bathroom equipment15. Electrical installation 15.1 General 15.2 Disabeling of electricity/ aircons 15.2.1 Internal procedure 15.2.2 External procedure 15.2.3 Maintenancespecifications for installation16. Mechanical installations 16.1 General 16.2 Maintenance manuals17. Telephone and data installations18. Paintwork 18.1 General19. External Work 19.1 Booms 19.2 Landscaping 19.2.1 General 19.2.2 Irrigation 19.2.2.1 Repairwork to irrigation 19.2.3 Planting 19.2.3.1 Planting in beds 19.2.3.2 Planting of trees 19.2.3.3 Planting of grass 19.3 Parking and paving

INDEX

Introduction1. Generalspecifications 1.1 Drawings2. Earthworks3. Concrete, formwork and reinforcement4. Masonry5. Waterproofing6. Roof covering 6.1 Metal 6.2 Tiles 6.3 Fascia boards7. Carpentry and joinery 7.1 Skirtings 7.2 Doors 7.2.1 Internal doors 7.2.2 External doors (wooden) 7.2.3 Door stops 7.3 Cupboards8. Ceilings,partitionsandaccessflooring9. Floor coverings 9.1 Tiling10. Ironmongery 10.1 Signage 10.1.1 External signs 10.1.1.1 Building names 10.1.1.2 Directional road signs 10.1.2 Internal signs 10.1.2.1 Door numbering 10.1.2.2 Officedoors 10.1.2.3 Directional wall signs 10.1.2.4 Suspended signs 10.1.3 Safety signage 10.1.3.1 Escape route signs 10.1.3.2 Fire signs 10.1.3.3 Electrical distribution points 10.2 Locks 10.2.1 Deadlocks

Page 5: Physical Planning - Technical Manual - UFS

19.4 Pedestrian routes & Speed bumps20. Cleaning Services 20.1 Items to be included when undertaking new building/ upgrading projects 20.1.1 Buildings: General 20.1.2 Lecture halls/rooms 20.1.3 Store Rooms 20.1.4 Rest rooms for cleaning personnel 20.1.5 Rest rooms/bathrooms in buildings 20.1.6 Courtyards

PP = Physical Planning

DO = Drawing office

PA = Principal Agent

PM = Maintenance

Page 6: Physical Planning - Technical Manual - UFS

1

INtroDuctIoN

This document is an overview of the key elements of the material and/or methods to be used in all UFS facilities, representing all preceding directives. It has been compiled to establish principles while at the same time endeavouring to promote uniformity in regard to the usage of materials and regulations.Buildingmaterialsandmethodsgivenpreferencetowouldbeeconomicallyjustifiableand suitable for long-term usage and implementation in order to reduce maintenance and repair work.

The guidelines in this manual will be updated regularly.

If for any reason there should be a deviation from regulations laid down in this document, this deviation will have to be cleared with PP prior to any action begin taken.

The descriptions of the different products/items/materials in this document only serve as the re-quired bases and all items must be clearly and meticulously described when drawings are made and bills of quantities are drawn up, so that no doubt can arise in respect to intended meanings.

Page 7: Physical Planning - Technical Manual - UFS

Down

Staircase

UP

2

1. GENErAL SPEcIFIcAtIoNS

• Itisconsideredthatifaprofessionalser-vice is being rendered, the service pro-vider is aware of national legislation and provincial and municipal regulations and will adhere to such requirements. All in-spections, etc. applicable in this respect remain the responsibility of the PA to see that it is adhered to.

• It is the responsibility of the PA or hisdelegates to obtain all relevant service plansandexistingfixtures fromPMbe-fore planning and that it must be pointed out on site before actual construction.

• Contractors toconsidercurrentongoingactivities associated with the UFS.

• Rubbletoberemovedonaweeklybasiswith the least amount of disruption.

• It will be regarded the Contractor’s re-sponsibility to timeously prepare, submit and obtain the specified designs andguaranteecertificatesapplicabletoeachproject as well as all the necessary ser-vice drawings eg: sewerage, low- and high voltage cabling, water, etc.

• Allbillsofquantitiestobesubmittedforapproval by PP prior to tender invitation.

• Only selected sub-contractors to beused for electrical and mechanical instal-lations.

• AllBillsofquantitiesaboveR1milliontocontain targeted procurement.

• Public reliability to be provided by thecontractor.

• Nopaymentguaranteeswillbeissuedbythe UFS.

• Escalation to be excluded at all times.(Fixed sum contracts).

• Thecontractorwillnotbeallowedtousethe option of retention as guarantee.

• Applicable Municipal inspections mustbe adhered to at all times.

• Healthandsafetyrequirementstobein-cluded in tender documents. Safety re-quirements must be clearly stipulated in this document.

• JBCC principal building agreement tobe used as contract. Deviations to be in-cludedasspecifiedbyPP.

• ABuildingLifeCycleMaintenancedocu-menttobehandedovertoPPuponfirstdelivery. Consultants must aquaint them-selves with the required content.

• No construction above or over existinginfrastructure without prior written ap-proval of PM.

• Colour schemes and finishes must bepresented to PP as a complete presen-tation and to be approved before issuing any instructions to contractor.

• Staff Quarters to be provided at eachbuilding.

• Professional cleaning of building to beincluded in bill of quantities.

• All ground floors of buildings to be ac-cess able for persons with disabilities.

• AllworkmustcomplywithNBR(NationalBuilding regulations) and SABS (South African Bureau of Standards).

1.1 Drawings

• Drawingsmustcomplywiththelocalau-thorityandPPspecifications.

• Drawings to be submitted electronicallyto PP on site handover date by e-mail and on CD-Rom and hard copies, deliv-eredtothePPoffice.

• The electronic format of drawingsmustbe in CAD format (Caddie or Autocad) - thus drw, cex, dwg or dxf format.

Page 8: Physical Planning - Technical Manual - UFS

3

- If caddie format is used, edition 9-16 is acceptable - If Autocad format is used, up to edition

2008 is acceptable because Autocad is not generally used by UFS. - When using Model Space (when making sketches, etc.) in Autocad,

each drawing must be layered separately on the relevant A0 or A1

size paper.• Eachdrawingsubmittedmustbe to the

scale of 1:100 and the Title Block must contain all the necessary information re-gardingtheNameoftheArchitect,draw-ing particulars and the specific drawingnumber. Revisions to be indicated clear-ly.

• Ifdetaildrawings(egbathrooms,toilets,cabinets, etc.) are submitted according to another scale as mentioned above, (eg 1:50) it must be clearly mentioned/indicated.

• Ifworkingwithprogramlayerstheymustnot be locked or hidden but must be open and accessible.

• As-built-drawingsshouldbesubmitted: - upon practical completion. - Municipal approved drawings to form part of contract documentation and

kept at PP.• NoFinalDrawings in .pdf formatwillbe

accepted.• As-builtdrawingsmustconsistof: - Foundations - Electrical - Mechanical - Water - Groundfloorlayout - Elevations - Roofinglayout

- Ceiling - All schedules: Doors, windows - Cabinet and other detail drawings

2. EArtHWorKS

• Poison the foil/filling of foundationsand under floorswith soil insecticide toeliminatetermiteinfestation.Acertificateshould be obtained from the contractor.

3. coNcrEtE, FormWorK AND rEINForcEmENt

• Tobedoneinaccordancewithengineersspecifications.

4. mASoNry

• Nocementbrickstobeused• Lintelstobeinstalledabovedoors,arch-

es and windows. • Brickforce to be minimum every third

course and above lintel height every sec-ond course.

• Only prior approved face bricks to beused.

• The cavity between the wall and thesidesofsteeldoorframesmustbefilled.

5. WAtErProoFING

• Dampproofmembranemust be placedunderneathconcretefloorsuptotheout-side end of the brickwork at all times

• Only prior approved products may beused.

• Waterproofingmustcarrya10yearwrit-ten guarantee

• Dampproofcoursetobeinstalledunderwindowsill.

Page 9: Physical Planning - Technical Manual - UFS

4

6. rooF covErING

• Rainwatergoodstobeomittedandonlyused by exceptions. Provision must be made for run-off water.

• Ifguttersanddownpipesareused(theexception), it must be sealed off with wa-terproofingmaterial.Alldownpipestobeat least 100mm diameter.

• Plasticdownpipesandguttersisnotal-lowed.

• Outletsanddownpipes insideconcretecolumns are not allowed.

• Outletsmustbeeasilyaccessible.• Only45-degreebendsmaybeused for

down pipes.• Roofslopestobesufficient.

6.1 Metal

• Corrugated roof iron to be minimum0.6mm thick.

6.2 Tiles

• Plastic damp proof membrane to beplaced over trusses before battens are installed.

• Everysecondtileontheridgeoftheroofto be secured with nails.

• Thebottom3rowsofroof tilesmustbenailed to the battens and thereafter, eve-ryconsecutive row.Thefinal rowat theridge, regardless of the subsequent row of tiles, must also be nailed to the bat-tens.

6.3 Fascia boards

• Fasciaboardstobefixedtotrusses/pur-lins with screws and not with nails and

joinedwith0.5mmthickH-profilegalva-nised sheet metal cover strips.

7. cArPENtry AND joINEry

• Supawoodtobeusedasfaraspossibleand no chipboard. Solid wood at request of the customer.

• All wall plates, including areas wherebuilding work around trusses etc. are required, must be treated with Carbo-linium.

• Trussesmust be fixed with wire ties tobrickwork and then secured with hoop iron roof ties to wall plates.

• Allpurlinsmustbefixedinaccordancetoengineersspecifications.

7.1 Skirtings

• AllskirtingsmustbepriorapprovedandfixedwithHiltinails.

7.2 Doors

7.2.1 Internal doors

• All internaldoorsmustbesemi-solidorsolid wood.

7.2.2 External doors (wooden)

• Mustbefrommerantiorsaligna.WhereFLB doors are used, braces must be ap-plied.

7.2.3 Door stops

• Alldoorsmusthavedoorstops.

Page 10: Physical Planning - Technical Manual - UFS

5

7.3 Cupboards

• Shouldhaveabasetomatchskirtings.• Impactedgingtobeused.• Where doors exceed 700mm, 3 hinges

must be used.• Tops of cupboards should be prior ap-

proved.

8. cEILINGS, PArtItIoNS AND AccESS FLoorING

• Minimumceilingheight tobediscussedwith PP.

• Brandering to be tampered screwed totrusses.

• Noplasteredceilings,bulkheadsordec-orative ceilings without prior approval of PP.

• Accesstoceilingstobesufficient.• 38mmx38mmBranderingmaynot ex-

ceed300mmcentreswhenfixedtobear-ers.

• Fixbrandering,joistsorrunnerswiththelarger dimension in the vertical position.

• Installsupportingbranderingwherelightfittingsaretobesuspended.

• No decorative cornices and should beprior approved.

9. FLoor covErINGS

• Vinyl tiles to be used generally andshould be prior approved by PP.

• Vinyl covering should be stripped andsealed by specialists with a relevant guarantee.

• 500x500mmFlortimeBerberPoint920carpettiletobeusedinoffices.Colourtobe approved by PR.

• Wooden laminatedflooringoranyotherfloorcoveringmustbeapprovedpriortospecified,byPR.

• Entrancestohavedusttrappers.

9.1 Tiling

• Uselocallyavailabletilesasfaraspos-sible.

• A-gradetilestobeused.• Alltilesmustbenonskid.• Usesufficientexpansionjoints.• Expansion joints to be lined with mov-

able joint strip with synthetic rubber in-serts.

• Ceramicandporcelaintilesarepreferredin areas of high frequency.

10. IroNmoNGEry

• A Presentation regarding Ironmongerymust be presented to PP and approved beforebeingspecified.

• Onlygenerallyknowntradenamestobeused.

10.1 Signage

10.1.1 External signage

10.1.1.1 Building names

• Building names attached to exterior ofbuilding.

• Cut-out lettering in “Optima font” to beused.

• Sizeofbuildingname-320mmhighlet-ters. (any other size must be submitted for approval to PP).

Page 11: Physical Planning - Technical Manual - UFS

6

• 2/3mm laser-cut mild steel with5mm/6mm machine screw pins welded on. Powder coated and duco sprayed to required colour.

• Usedrillingtemplate,drillholestoallowfor required stand-off distance

• Mountusingchemicalepoxycement• Distancefromwall: 35mm to 80mm letters - 10mm standoff

100mm to 200mm letters - 15mm stand-off 200mm to 300mm letters - 20/25mm standoff

10.1.1.2 Directional road signs

• Use reflective vinyl for lettering, frameand symbols.

• Board: 1mm Chromadec sheet, re-in-forced at the back.

• Framework:Roundtubing,whitepaintedwith 2k paint.

• 2/50x3x300 longplateswelded toCHS,installed 600x600x500 Concrete base

• Lettering:Helvetica,100mmhigh,Upperand lower case.

• Frame:20mmwitharadiusof100mm• Arrow: 222mmwide when directing left

of right.• Letteringtobeapplied315mmfromthe

left of the board (minimum starting point) and 70mm from the right of the board (ending point).

• Spacing between end of arrow to theleft and starting point of lettering to be 238mm.

• Afulldetaileddrawingisavailableonre-quest from PP.

10.1.2 Internal signage

• Tobevistaortomatchexisting.

10.1.2.1 Door numbering

• Door numbering – Drawings to be for-warded to DO for the allocation of door numbers and approval of size and font

• Door numbers to be screwed to doorframes.

10.1.2.2Officedoors

• Vista(V150x400mm).• Mount 50mm from left door frame,

1600mmfromfloor.Ifnotpossible,thenright of door, if not possible, then above door. Only on door at customers request.

• Fastenwithmirrortapeandadhesive. 10.1.2.3 Directional wall sign

• Vista(V500x1600portrait).• With full colour bubble jet, large format

printedinsert&clear,nonreflectiveplas-tic coating.

• Mount as per architectural layout andcustomers requirements.

• FastenwithHiltiorsimilarfasteners.

10.1.2.4 Suspended signs

• VLseries,landscape. Size will depend on building layout and

quantity of information, normally 150 x 600 (landscape)

• Mountwithcablesprovidedbysupplier.Ceilingmounted2.5mfromfloor.

• Installwithceilinghooks.

Page 12: Physical Planning - Technical Manual - UFS

7

10.1.3 Safety signage

10.1.3.1 Escape route signs

• Photoluminescent(SANSapproved)• Sizeofsign190mmx380mmor 190mm x 570mm

10.1.3.2 Fire signage

• Photoluminescent(SANSapproved)• Sizeofsign190mmx380mmor 190mm x 570mm

10.1.3.3 Electrical distribution points

• PhotoluminescentWW7 (SANSapproved)• Sizeofsign190mmx190

10.2 Locks

• MinimumTwo keys to every door to bemarked and handed to PP

10.2.1 Doorlocks

• Internal doors must be fitted with mini-mum 2-lever locks. Use well-known brands such as Esco, Union, Yale or BBL.

• Externaldoorsmustbefittedwithmini-mum 4-lever locks. Use well-known brands such as Esco, Union, Yale or BBL.

10.2.2 Magnetic locks

• Fittednottoreducedooropening.• Installtopandbottombarrelbolts.

10.2.3 Automatic door closers

10.2.3.1 Overhead type

• Wheninstalledontoaluminiumdoors,in-stall 2 hinges at the top of the door.

10.2.3.2 Floor type

• Installonfloorlevel.

11. StructurAL StEELWorK

• Strictlyaccordingtoengineerdetailandspecification.

12. ALumINIum WorK

• All aluminium doors, windows, shopfronts, etc. are to be manufactured, sup-plied and installed complete by an ap-provedfirmofSpecialistsandshallcom-ply with AAAMSA design criteria.

• Anodizing or powder coating has beenprocessedinaccordancewithSANS999andSANS1796respectively.

• Glazing to be installed in accordancewithSANS0137

13. PLAStErING

• Nodoubleplasteredwalls• Screedthicknessonfloors,casttomini-

mum of 25mm, with 1:4 ration sand/ce-ment.

Page 13: Physical Planning - Technical Manual - UFS

8

14. PLumbING AND DrAINAGE

14.1 General

• Separate booster pumps must be in-stalledforfire-andhouseholdpurposeswhere necessary.

• Allnewwaterpipes thatare installed inwalls must be pressured tested and in-spected.

• Usegoodquality,heavydutymaterialasa basic principle. Eg. Cobra heavy duty taps with the code starting with 1.

• IfotherPVCpipingisused,makeuseofClass 12 pipes.

• Make use of Hilti clamps to fasten pip-ing against walls and ceilings. The use of wire is not acceptable.

• Wherepipingstops, itmustnotbebentover but must be sealed with stoppers.

• WheninstallingPVCorseweragepiping,avoid sharp 90-degree bends. Rather make use of 2 x 45-degree bends where applicable.

14.2 Inside buildings

• Use class 2 copper pipes with Conexconnections. (Soldering material not al-lowed).

• Nostopcocks, -valves, inspectioneyes,etc. may be installed behind any cup-board, etc.

• Allnewwaterpipesinceilingstobeinsu-lated with Thermo Flex.

• All PVC and Plythene piping in shaftsand labs must be clamped and support-ed well against walls.

• Geysersmustbe installedsecurelyandin such a way that the electrical heating elements can be easily removed.

• Pressuretapsareforuseinlowpressurepiping and is not suitable for high pres-sure piping. A pressure reducing valve must be installed.

14.3 Outside buildings

• Warmwaterpipestobeinsulatedtore-duce heat loss.

• Use class 2 copper pipes with Conexconnections. (Soldering material not al-lowed).

• Use galvanised pipes class B. (classAnot allowed).

• Use class 12 Duroflo pipes with castiron fittings or class 10/12 HDPE Plas-sonpipeswithPlassonfittingsforsubsoilcold water installations.

• All underground water pipes with nothread must be fastened with strong metal pins at the back of all bends and T-pieces, then mortar must be poured around the bends and T-pieces.

• Thread on pipes should be as short aspossible, exposed thread to be painted with a rust resistant Epoxy paint.

• Pipesmustbefittedwithgalvanisedcon-nections (preferably Unions) for easy disconnection.

• Allwaterpipesshouldbecleaned,rinsedand pressure-tested before installing taps or valves.

• Gulliesshouldbefittedwithagrid.• AllPVCandPlythenepipesinshaftsand

labs must be thoroughly clamped and supported.

• Sewerageinspectioneyesmustbebuiltabove ground and be covered with a cast iron lid.

Page 14: Physical Planning - Technical Manual - UFS

9

• Stormwaterpipesmustbebigenoughtoaccommodate bigger than usual water run-off.

14.4 Stop taps

• Stoptapmustbeeasyaccessible, if in-stalled behind a panel, the panel should have hinges.

• OnevisibleandeasyaccessibleCPLe-ver Ballcock stop tap must be installed on main pipeline that leads to each bath-room.

• Additionaltothemainwatersupplystoptap, (code: 1060-15) Fullway CP Ball cocks must be installed on warm and cold water pipes under taps of basins, sinks and lab basins, etc., as well as toi-let ball valves.Note that ballcocksmaynot be coupled directly to existing pipes.

• Install Stop taps on both sides of thecompression valves on a geyser. Ball-o-Fix taps are allowed.

14.5 Fire equipment

• Fire hose valves (preferably SaundersValves)mustbeclearlyvisibleandeasyaccessible and must not be locked.

• Connection point of fire hosesmust beeasy accessible.

• Sealallexposedwater&drainagepipesduring construction to ensure no rubble will block the pipes and make sure that there are no stoppages before complet-ing the work.

14.6 Bathroom equipment

• Inspectioneyestobeinstalledwitheverybend/junction.

• Installagoodqualityclosabledoorattheside of a bath.

• Plastic toilet bowls, basins, etc.will notbe allowed.

• Stretch-jointinpipeatexpansionjointisneeded.

15. ELEctrIcAL INStALLAtIoN

15.1 General

• All cable ends should be insulated byheat shrinking.

• All light fittings to be prior approved byPM.

• All light fittings to be fitted with energysaving bulbs.

• Aspartofenergysaving,nodecorativelighting is allowed. This however is open for discussion with PM.

• Examplesoflightsandlampsshouldbesubmitted to PM by the electrical contrac-tor before installation, for the purpose of updating the maintenance database.

• All light switchesandsocketoutlets (orother outlets) should be numbered with the appropriate circuit number on the distribution board. A Label printer would besufficientforthispurpose.

• UseonlySchneiderCircuitbreakers fornew buildings or installations and not CBI.

• Allcabletrenchesmustbeinspectedbythe Consultant and/or PM before they are filledup.Aphotomustbetakenthereof.

• Service Coordination for spacing be-

Page 15: Physical Planning - Technical Manual - UFS

10

tween power / data / water / sewerage / storm water / gas / fuel leads must be signedoff byPM.Someflexibility is al-lowed.

• Luminaires in bathrooms: 1x9/18W PLinstead of 2x26W/

• PR has an EnergyManagement Policywhereby all existing 1.8m fluorescentRapid Start luminaires is to be replaced with 1.5m luminaires (ELB). This re-placement must be included in projects.

• Emergency power machines: supplyhand controlled bypass switches. (By-passSocomecType>150kVA.AnySABSapproved bypass switch.

• Emergency power: Plinth Spec and re-habilitate the environment profession-ally.

• Nonewsurfacewiringisallowed.Allex-isting surface wiring to be chased into wall.

• PVCconduitinsideandgalvanisedcon-duit outside.

• Only Energy saving lighting (Electroniccontrol gear CLASS A2). Even in case of a double lamp luminaire, one lamp must continue to work even i the other lamp is defective.

• Allow Mechanical installations to con-nect toexistingBMS(JohnsonControlsEnergy Management). Flow diagrams and graphic layouts must be supplied to PM

• Givespecialattentiontothewaterproof-ing of roofs of substations. Waterproof-ing on the roofs of substations must be repaired by professionals when cable routes are planned through them. A wa-terproofing test will be done after com-

pletion.• Existingtransformerloadingislimitedto

a maximum of 75% of nameplate capac-ity. Provide additional transformers per projectasneeded.Loadprofilesshouldbe provided as support documentation.

• Drawings per project: Schematic linediagrams / reticulation drawings must be presented at design and completion stage to PM.

• Photocells: Only Royce Thompson orNational(mountedinanexternalweath-erproof enclosure) A BYPASS green le-ver isolator (63A), to distinguish it from adjacent circuit breakers, must be in-stalled in the relevant distribution board. Agreement must be reached per project over the necessity of a contactor (AC3).

• Luminaires in toilets/bathrooms/passag-es/stairways: Must be energy saving in nature and adhere to minimum levels as prescribed inOHSAct (not productivityindex).

15.2 Disabling of electricity and/or air conditioning:

15.2.1 Internal Procedure:

• Anconsultantisappointedbythedepart-ment to do electrical work on campus that has the potential to cause an inter-ruption to power supply.

• The consultant/contractor informs theDepartment of Physical Resources in writing, at least three days beforehand about the planned and controlled power outage. It would however be preferable if aweek’snoticecouldbegiven.

Page 16: Physical Planning - Technical Manual - UFS

11

• The time of advance notice varies ac-cordingtotheactivitiesinspecificbuild-ings and PM will negotiate this with the contractor/consultant.

• Thetimeofshutdownmustbeanabso-lute minimum.

• Ifnototherwisearranged,shuttingdownof power should take place during week-ends.

• The precise date, time and duration ofthe power outage must be arranged be-forehand with the client and PM.

• TheDepartment of Physical Resourcesgives written notice to the inhabitants of the building/buildings about planned power outages, and if it is not suitable, alternative dates and times are negoti-ated

• Where needed consultants/contractorsshould be helpful to provide alternative means of power supply. This will be com-municated to them by PM as soon as the request is received.

15.2.2 External Procedures:

• AconsultantisappointedbytheDepart-ment to do electrical work on campus that has the potential to cause an inter-ruption to the power supply.

• Theelectrical contractorgivesnotice tothe electrical consultant that there will be apoweroutageonaspecificdayatanappointed time.

• The electrical consultant gives writtennotice to the project leader (Architect, Quantity Surveyor, or engineer appoint-ed by the University) or directly to the University (PM/PP) if the consultant is appointed individually.

• Theprearrangedtimeframeschangeac-cordingtotheactivitiesinspecificbuild-ings and will be discussed/arranged with the contractor/project leader.

• The period of interruptions shouldbe restricted to the minimum.

• Asfaraspossibletheinterruptionsshouldbe scheduled over weekends.

• Theexactdate,timeanddurationoftheplanned power outage must be arranged in writing to the project leader, tak-ing into account that the project leader needs the opportunity to give the infor-mation to the appropriate campus per-sonnel at least three days in advance. It would however be better if notice could be given a week in advance. It is there-fore necessary that PM be given no-tice of ten days in advance.

• Whereneededtheconsultant/contractorshould help to provide alternative means of power supply.

• Ifthepoweroutageisinconvenientornotpossible, the University (PM) will contact the project leader and alternative times and dates can be arranged.

• Afterthistheprocessrepeatsasofpointnumber 2.

15.2.3Maintenancespecificationsfor Electrical installations:

• Examplesofluminaires(andenergysav-ing lamps 840) must be presented by an electrical consultant/contractor to PM be-fore installation. For projects where aes-thetics are important, examples of lumi-naires to PM is crucial before installation and after approval from the Architect as well as Physical Resources, the instal-

Page 17: Physical Planning - Technical Manual - UFS

12

lation can commence. If a certain type of light is technically approved once, it is not later necessary to give a physical sample on another project. A photo and specifications from the catalogue willsuffice.

• All light switches and socket outlets(or other outlets) should be numbered with the appropriate circuit number and switchboard name. A “Brother” labelprinter is sufficient for this. Emergencylight luminaires should also be marked like this. All socket circuits should be clearly identifiablebymeansof the leg-end on the switchboard. If the legend does not give clear indications, the sock-et outlets of the installation should be clearly marked with the circuit reference.

• Circuitbreakers fornewbuildingsor in-stallations must as far as possible be from the same supplier as the nearest upstream circuit breaker. Example: a new small installation feed from a distribution box with an old Fuchs circuit breaker as the main breaker and this box then feeds from a substation where an M&G circuit breaker is the main, then CBI is used. The board manufacturer states the type on the quotation. In principle only Schneider Circuit breakers and not CBI must be used for new buildings or instal-lations.

• Allcoverplatesonpanelsmustbepow-der coated and must adapt to the exist-ing colour, where appropriate. Cover plates from normal boards should be White. Red for Emergency power, Purple for UPS. (SABS 1091). There is some flexibilityregardingtheshadesofcolour,

but this should be cleared with PM be-fore manufacturing commences.

• Emergencypowerandminisubpedestalspecifications will be provided. Pleaseallow area around pedestal to be profes-sionally rehabilitated. Leave 1.5m paving around to give personnel admission for maintenance purposes.

• Forplannedpoweroutages,theRiskAs-sessment should be done seven days before by the contractor. For large-scale power outages, 10 days notice from contractor is needed otherwise a 7 day notice is sufficient. Contractor providesswitch instructions and risk assessment to consultant before power outages. Af-ter completion of project, it is important that the contractor complete the Stand-ard Authorization, Switch Instructions, Risk Assessment and Permit forms and submit to UFS Competent Person by next working day.

• Allow to integrate ALL new HVAC me-chanical installations, including electri-cal heater panels in hostel rooms and all buildings to the existingBMS (JohnsonControls) as part of the Energy Man-agement Policy. Where geysers are in-stalled, a load management device that can integratewith the existing JohnsonControls BMS, must be provided. Flow diagrams and graphic layouts must be agreeduponatdesignstageandreflect-ed in the tender amount. Updating the existing Main Workstation PC graphics forms part of the scope of works.

• Tails tonewcircuitbreakersonexistingdistribution boards should be fed from the bus bars with conductors that have

Page 18: Physical Planning - Technical Manual - UFS

13

the similar current carrying capacity than the new circuit breaker.

• Cablesaremarkedonbothends:Cable-and earth conductor size in mm2 and DB name where/from where fed. Profession-al labelling system to be used.

• Factory acceptance testing is requiredon all Emergency power, 11kV equip-ment and switchboards 10kA and larger. Factory Testing Certificate and then 1hour load test on terrain. 11kV equip-ment: Factory Testing Certificate, nophysical testing by consultant in factory.

• The streetlight cabinet should be sup-plied separate from the Main switch-board. Get clearance from the University Electrical Engineer before construction. New Street- / terrain light cable feedsshould have a bypass switch in the di-vider cabinet for maintenance during the day.

• AllcontactorsshouldbeselectedforanAC3 application, no matter in which ap-plication. All contactors to be similar and equal to Telemechanique.

• ELSTERA1700Energymeterwithasso-ciatedGSMmodem(v117xfirmware),3months web hosting by SDG Technolo-gies per building/transformer must be al-lowed for.

• Phase/Flash barriers are required onboth the line and the load sides of circuit breakers. Any moulded case type circuit breaker that can accommodate phase barriers should have it.

• Switchboards 10kA and larger shouldcomply with SABS TTA. The board man-ufacturer shouldprovideCertificateandprovide a TTA label on the switchboard.

• Sparecapacityof30%shouldbeallowedon all new distribution and switchboards aswellassparecircuitbreakersfitted.

• Cable jointmarkers should be suppliedon top of all Cable joints.

• Transformer/substation room doorsshould have removable ventilation pan-elsthatcontainfilters.

• All new panels ( Pillar box, Emergencypower generators, Mini substations, Sub station doors, etc.) that by law should be equipped with a locking mechanism, must be supplied with padlocks that are on the UFS Master lock system. The Project must allow for these locks. The Contractor will be authorized by UFS to approach the supplier of locks to UFS as directed by PM, who will in turn get the master key from UFS and produce the padlocks. Barrel locks on substation doors to match ELECTRICAL master se-ries on UFS campus.

• Drawingsshouldcontainaccurate infor-mation for example; Cable routes and markers that in future projects help with the layout of services. There is some flexibility to this- but special requestsshouldbeclearedbytheuniversityfirst.

• UniversityPMshouldbepresentwiththeofficial Practical Completion inspectionthat is organized by the consultant. This ensures that Maintenance personnel have the opportunity to observe the new installation and can effectively maintain it in future. It is accepted that the con-tractor has already completed the quality control inspection at this time. Polarity and earth-leak test can be requested, and instruments should be available.

Page 19: Physical Planning - Technical Manual - UFS

14

• DATAPACK: During the Practical Com-pletioninspectiontheDATAPACKisgiv-en to PM. It contains the following;

• OperatingandMaintenanceManuals• Manualsofinstallation• Electricalcompliancecertificate• EarthingCertificate• WorkshopdrawingsofallDB’s.• Record of Contractor’s Quality Control

Inspection.• An Electrical compliance Certificate is

required from the moment that an elec-trical Installation is in operation. Even if it is before the Practical Completion In-spection.

• Allnewdistributionboardsinnewbuild-ings/alterations to existing buildings, should be accessible to Maintenance staff at all times. Thus avoid placing DB in store area, etc.

• All existing and new LV andMV powercables, are deemed to be situated in a 2 metre wide servitude. Application must be made for any possible encroachment of the servitude by building purposes and must be accompanied by the neces-sary plans.

• 11kVsubstations:SELprotectionrelayswith Ethernet connection to UFS network displayingthepowerflowperpanel.

• Power trunking size to be designed sothat only 70% of space is occupied by theinitialproject’swiring.

• Maintenance guarantee period label onallnewDB’s.

• Supply padlock and keys to all trans-former tap changers.

• Substationfloorstobepaintedandspec-ifiedbyArchitech.

• Circuit breaker settings to be indicated

on single line drawing.• EmergencypowergeneratorsandUPS’:

Maintenance contract included in tender for the maintenance liability period.

• Trenchesinsubstations:Coverstore-cessflushwithfloor.

• Trenchesinsubstations:Fire&oilleak-age sealed off.

• Flexiblepowercable(“weldingcable”)toconformtoSABS1574(1000V)

• Where socket outlets SSO (plugs) areprovided, a maximum of 2 rooms and /or 4 SSO’s are to share a 20A circuitbreaker.

• SupplycablestothemainLVdistributionboard per building, must be designed to have 20% additional capacity bearing in mind the agreed upon utilization factor.

• The centralized hot water systems inhostels and large buildings are to be metered separately with regards to elec-tricity ( ELSTER A1700 ) and water con-sumption.

• SSO’s inhostel roomsare tobe limitedto 5A per student or otherwise as re-questedfromHRA.

• Noscalingdownoftherequirementslaiddown for new Electrical and Mechanical Infrastructure without prior consultation with Physical Resources.

• OnlySchneidercircuitbreakersmustbespecifiedandsuppliedinallElectricalIn-stallations.

• Allboominstallationstobeprovidedwithexternal cabinet containing isolator fed from distribution board.

Page 20: Physical Planning - Technical Manual - UFS

15

16. mEcHANIcAL INStALLAtIoNS

16.1 General

• AMechanical engineer to be appointedwitheach large installationand “DesignandSupply”bycontractorisprohibited.

• Tradenamesofairconditioningunitsin-cludedchillers,tobeconfirmedwithPMbefore specification thereof in spite ofthe following requirements:

Mid Wall, Window Shaker (Only in excep-tional cases), Console Units, Cassettes, Under Ceiling must be: LG, Mitsubishi, Daiken, Panasonic, Carrier, Dunham Bush

Hideaway, Package and Rooftop mustbe of the type: LG, Mitsubishi, Daiken,

Panasonic, Carrier, Dunham Bush

Chillers must be of the make: Carrier, Daiken, Trane, Dunham Bush, Mitsubishi

Cooling Towers must be of the type: BAC (Baltimore Air Coil Company)

• All installations to be compatible withthe existing BMS (Building Management System)namely: JohnsonControls, us-ingBacNetIPprotocol.

• The complete mechanical installationand procedure must be discussed and approved by the PM Engineer and Sec-tion Head of Air conditioning beforespecificationthereof.

• HailGuardson thecondensers isa re-quirement where the condenser coil will be exposed to the elements and vandal-ism.

• Powder coated canter-lever bracketsmust be supplied for the condenser: Bolt-

ed to the wall with M2 rawl bolts 600mm long and complete with M10 spring nuts and washers.

• Theserialandmodelnumbersmustbesupplied to PM.

• AllremovedAirConditionerswillremainthe property of the UFS and must be de-livered to PM.

• All air conditioning units must be heat-ing and cooling, preferably heat pumps. Units with electric heat shall only be used if nothing else is available.

• Where under ceiling and cassette unitshave been removed, the ceiling must be repaired, replaced and painted to match the existing.

• Where Mid Wall, Window Shaker andConsole units have been removed or replaced, the wall must be repaired to match the existing surface as well as the glassfittedtomatch.

• Armaflexmust have awall of¼ inch&must be installed on the suction & dis-charge piping

• All exposedArmaflex must be dressedwithwaterproofingmembraneandpaint-edwithwaterproofing

• Copper tubing for refrigerant circuitsmust be hard or soft drawn refrigeration grade.

• Drainpipingmusthaveaminimumouterdiameterof25mmandbluePVC irriga-tionpipingmustbeused.Nodrainpip-ing shall be chased into walls. If surface mounting is not possible all pipes shall be installed in steel trunking with remov-able lids. If wall thickness permits, trunk-ing may be chased into walls with the removablelidsflushwithwallfinish.

Page 21: Physical Planning - Technical Manual - UFS

16

• Once a tender for air conditioning hasclosedandanOrderNumberhasbeenissued to a contractor, a Letter of Ap-pointment must be signed by the con-tractor that stipulates for eg. the date of commencement and day of completion.

Page 22: Physical Planning - Technical Manual - UFS

17

16.2 Maintenance Manuals

• Aftercompletionofeachmajormechanicalinstallation,PMmustbesuppliedwithacompre-hensive Maintenance Manual. The contents of the manual must be as follow. (Compiled by PMmechanicalengineer,Mr.KoosUys).

1. SECTION 1: DETAILS OF RESPONSIBLE BODIES

1.1 Consulting Engineer :

NameofConsultingEngineer: Address:

TelephoneNumber: NameofEngineerincharge: ECSARegistrationNumber:

1.2 Contractor

NameofContractor: Address:

TelephoneNumber:

EmergencyTel.Numbers:

1.3 Completion Date:

1.4 Guarantee Period start date:

1.5 Guarantee Period end date:

1.6 Expected Service Life: (List applicable)

Water chiller(s) Cooling Tower(s) AirHandlingunits Pumps Packaged units Room type a/c units VRVsystem

Page 23: Physical Planning - Technical Manual - UFS

18

2. SECTION 2: SUMMARY OF SPECIFICATION FOR MAIN PLANT AND EQUIPMENT INSTALLED

ITEM SPECIFIED ACTUALLY INSTALLED Water chiller: Make Model number Cooling cap (kW) Chilledwaterflow(l/s) Condenserwaterflow(l/s) CHWT(in/out°C) CondWT(in/out°C) SerialNumber Cooling Tower Make Model number Cooling cap (kW) Condenserwaterflow(l/s) Serial number Pumps (list each pump separately) Service(e.g.CHW/CONDW) Make Model number Impeller diameter (mm) Suction pressure (kPa) Headpressure(kPa) Motor kW Serial number Airhandlingunits(listeachAHUseparately) Areaserved(e.g.“OfficesNorth”)Roomno: Make Model number Supply air (l/s) Return air (l/s) Fresh Air (l/s) Coilon(°CDB/°CWB) Coiloff(°CDB/°CWB) SerialNumber

Page 24: Physical Planning - Technical Manual - UFS

19

VRVSystem(s) Make ModelNumberOutdoorunit Cooling Capacity Refrigerant Serial number Indoor units: Area served Type Sens. Cooling Cap (kW) Serial number Packaged Units Areaserved(e.g.“OfficesNorth”)RoomNo Make Model number Supply air (l/s) Return air (l/s) Fresh Air (l/s) Coilon(°CDB/°CWB) Coiloff(°CDB/°CWB) Total Cooling (kW) Sens. Cooling (kW) SerialNumber Room Type A/C Units Areaserved(OfficeNumber)RoomNo Make Type Model number NominalCooling(kW) SerialNumberIndoor SerialNumberOutdoor ElectricHotwaterBoilers Make Type Heatingcapacity(kW) Numberofheatingsteps StorageVolume(Litresorm3) Test Pressure (kPa) Max. working pressure (kPa)

Page 25: Physical Planning - Technical Manual - UFS

20

3. SECTION 3: SUPPLIERS’ DOCU-MENTATION PERTAINING INSTALLED EQUIPMENT

Insert all relevant suppliers’ documentation inPDF format. Information shall cover all installed equipment.(Users’manuals,commissioningpro-cedures,start-upprocedures,faultfindingproce-dures, etc.)All relevant mechanical drawings must be deliv-ered to DA. See also 1.2

4. SECTION 4: COMMISSIONING DATA

• Suction&headpressuresofcompressors(heat pumps included)

• Runningcurrents• Suction&headpressuresofpumps• Runningcurrents• Waterin&outtemperatures:Chilled,con-

denser, hot water• CoilAiron/offtemperatures• Waterflows(l/s)• Airflows(l/s)(Airflowsatdiffusersshallbe

shown on drawings)• Filterdetails(Type,Make,modelnumber,

numberforeachAHU)• Mapping data of all electronic plant con-

trollers• Complete electrical wiring diagram for

each control board (with terminal, conduc-tor, contactor and relay numbers indicat-ed)

• Sizesofelectricalsupplycables

5. SECTION 5: MAINTENANCE

• Completemaintenanceschedule

• Detailed maintenance tasks and proce-dures

• Replacement schedule of maintenancespares

6. SECTION 6: REPLACEMENT SPARES

List of maintenance items (complete with part numbers) required for normal maintenance:• Airfilters• Refrigerantdriers• Waterstrainers• Chemicals• Contactors• Circuitbreakers• Relays• Fanbelts• Lubricants

List of recommended replacement (complete with part numbers) spares to be kept in stock

Page 26: Physical Planning - Technical Manual - UFS

21

17. tELEPHoNE AND DAtA INStALLAtIoN

• AccordingtoICTstandards

18. PAINtWorK

18.1 General

• Paint Brands to be used on Campus:Plascon and Dulux only.

• Application according to manufacturersspecifications

• Representativeofpaintmanufacturer toinspect each stage and approve work.

19. EXtErNAL WorK

• All buildings to have concrete/paving apron along the outside perimeter.

19.1 Booms

• Seespecificationforpedestalontheat-tached according to Turnstar 4 x 10mm. Galvanised Bolts should be fastened into the concrete where the cupboard is fas-tened. There should also be 3 x 25mm PVC Conveyer pipes in the concretewhere the electric wiring can go.

• Additionaltocupboard:• 1x15A2.5kacircuitbreaker• 1xMTDTimeswitch• 1x220v–12VDCEnergySource• 1x1000chSentryreceiver• 3Buttonc/HoppRemoteControls• 1xTubularKeySwitchonexistingseries

of university

• NB: Electric wiring should be done insuch a way that the power of the entire cupboard can be shut down when the cir-cuit breaker is turned off. This includes the power source and time switch.

19.2 Landscaping

19.2.1 General

• Itisthecontractor’sresponsibilitytoob-tain all relevant requirements, service plansandexistingfixtures fromMainte-nance before quotation.

19.2.2 Irrigation

• The area shall be levelled to facilitateuniform drainage of the site. Such level-ling shall conform to facilitate to the natu-ral fall of land and the contractor shall insurethatthegeneralshape,profileandlevels of the area is in keeping with the context.

• Adjustable bubblers should be usedwhere trees are planted in parking areas. Bubblers may not be higher than 50mm above the soil level.

• Otherbeds, lawnswithorwithout treesshould also receive sufficient irrigation.Pop up sprayers with nozzles are recom-mended. Exceptions on standpipes with nozzles are made with the necessary permission from the horticulturist. The use of the same fabrication of sprayers ornozzlesisimportant;preferablyHunt-er, as used on the rest of the campus.

• Norotarynozzlesmaybeused.UseonlystandardUorPSU17’nozzles.

Page 27: Physical Planning - Technical Manual - UFS

22

• Round/ circular feed system is recom-mended where possible.

• Fixed nozzle and rotary sprayers maynot be used on the same station.

• Anti-theft sockets are used on pop upsprayers and standpipes to minimize theft.

• Theuseofacheckvalvesealdeviceinall pop up sprayers to prevent low head drainage.

• Only PVC pipewith a diameter greaterthan 25mm may be used on campus.

• Trenches that have to be dug for irri-gation pipes should be at least 300mm deep. Pipes of 40mm and larger should be placed 450mm deep.

• Apressureandflowtestshouldbedoneto decide on the thickness and class of the pipe that should be used for the area according to specifications used in theindustry.

• Battery or electric controllerswith elec-tric valves are recommended for use to regulate and save water usage on cam-pus.

• Approved suitable gravelwill beplacedbeneath all valves to provide drainage.

• Nogardenbedor lawnareamaymakeuse of the same station as the require-ment for water is different.

• The sprayer according to the spray arcshould be spaced to overlap no less than 80% in order to prevent dry patches and to shorten watering time.

• Thesettingofthenozzlesandarcshouldbe completed after installation by the contractor.

• Thecontrollerandpowersupplyshouldbe mounted securely to an outside wall in a lockable durable weather resistant

unit. Supply the key to the unit to ground servicesafterfinalhandover.

• Where needed, sleeves 110mm shouldbe placed 100mm under paving or road services, the repair must be done imme-diately after insertion of sleeve.

• Beforefinaltakeoverfromthecontractorto the university, a representative from Physical Planning and the horticulturist shouldbeinvitedtodoafinalinspection.

19.2.3 Planting

19.2.3.1 Planting in beds

• Plantingcanonlybedoneuponcomple-tion of irrigation installation.

• Allloosestonesexceeding30mm,debrisand building rubble should be removed from site.

• The beds shall be leveled to facilitateuniform drainage of the site. Such lev-eling shall conform to facilitate to the nat-ural fall of land and the contractor shall insurethatthegeneralshape,profileandlevels of the area is in keeping with the context.

• Bedsshouldbeprepared thoroughlybyloosening the soil up to 250mm deep - cultivated mechanical or by hand. A layer of compost 50mm thick should be spread over the area and worked into the soil. Fertilizer 2:3:2 should be used at least 60gram per square meter and gently forked into the soil. Area is then raked even before planting.

• Plantsarethenplacedandafterinspec-tion by Ground services, planted. Black bags to be removed before planting!

Page 28: Physical Planning - Technical Manual - UFS

23

Plants to be planted with the roots under the soil level.

• After planting the soil should again beloosened and raked even. This can be achieved by gently forking and raking through it.

• Plants are then watered to at least300mm deep. The plant should be kept moistuntilthefinalinspectionandhandover is completed.

• Rosebedswhereapplicable,musthavea mulching layer of coarse bark of 40mm.

• Beforefinaltakeoverfromthecontractorto the University a representative from Physical Planning and the horticulturist shouldbeinvitedtodofinalinspection.

19.2.3.2 Planting of trees

• Holes for planting of trees should besquare. Measurements in comparison to a 20 liter tree: 500mm x 500mm x 750mm deep.

• Compost should be mixed with soil. Atleast 30dm (one bag) or one third of total soil that is to be placed back in the hole of the tree should be compost.

• Superphosphate, 60 gram per tree,should be mixed with the above men-tionedsoilbeforebackfilling.

• Absorbsiongranulesmaybeapplicable,as determined by the soil composition and area where the tree is going to be planted.

• Becertainthattreesareplantedwithouttheir black bags and roots are just under the soil level.

• On grass areas, trees should be sup-plied with a tree ring 350mm for protec-tion against machine damage.

• Where bubblers are being used to wa-ter trees, a tree ring of 500mm should be placed around the tree base. This will be used as watering area.

• All trees shall be staked. Two stakesshall be driven into the pit, one on either side of the centre position of the pit, prior to placing the tree. The stakes shall be ofroundtimber,40–50mmindiameter,exceeding 2000 mm in height. The tree shall be attached to stakes using ap-proved tree ties and ensuring that stakes does not chafe the tree. Two tree ties shall be placed approximately 600mm above ground level and 2 within the crown of the tree approximately 300mm below the top of the stake.

• Supports in the form of Y droppers(2.1m) should be placed to keep the trees upright. The poles should be uni-form, the same height above the ground and planted deep enough to prevent theft. Wire with hose, at least 2 bonds should be used to fasten the tree in an upright position to the Y dropper.

• Plantsarethenwateredtoadepthofatleast 300mm. The plant should be kept moistuntilthefinalinspectionandhandover is completed.

• Beforefinaltakeoverfromthecontractorto the University a representative from Physical Planning and the horticulturist shouldbeinvitedtodofinalinspection.

19.2.3.3 Planting of grass

• Makeuseofonlyinstantlawn.• Plantingcanonlybedoneuponcomple-

tion of irrigation installation.• Asiteplanoftheareawillbesuppliedby

Page 29: Physical Planning - Technical Manual - UFS

24

Physical planning for use to determine the size of the area to be planted with grass.

• Preparation of the site involves the re-moval of boulders, stones and building ruble.

• Theareashallbeleveledtofacilitateuni-form drainage of the site. Such levelling shall conform to facilitate to the natural fall of land and the contractor shall in-sure that thegeneralshape,profileandlevels of the area is in keeping with the context.

• Prepare the soil by cultivation up to30mm and levelling the area before planting.

• Grasslevelshouldnotbehigherthanthecurbing surrounding the area. Prepare soil level at 25mm under the curbing lev-el before planting.

• Applyfertilizer3:2:1or3:2:3at5kg/100m².• Compact instant lawn with a roller and

apply water.• Theplantshouldbekeptmoistuntil the

final inspection and hand over is com-pleted.

• Beforefinaltakeoverfromthecontractorto the university, a representative from Physical Planning and the horticulturist shouldbeinvitedtodofinalinspection.

19.3 Parking and paving

• Treatgroundunderneathpavingwithanapproved weed killer.

• Concreteblockpavingmustbereplacedwith paving brick that is locally available.

• Pedestrianpaving-50mm Vehiclepaving-80mm• Paving must be at the same level as

manholes.

• Reinforcerestrainwithbrickforcetore-duce cracking.

19.4 Pedestrian Routes & Speed bumps

• Install largerdrainagepipesofapproxi-mately 150mm underneath bumps and pedestrian routes

• Wherearoutecrossesaroad,use80mmpaving stones.

20. cLEANING SErvIcES

20.1 Items to be included when undertaking new projects (New building/upgrading)

20.1.1 Buildings: General

• Whenplanninganewbuilding it is cru-cial to provide as much information with regardtotypeofflooring,thesquareme-tersofflooring,etc.

• Whenusingcarpetsasatypeofflooring,make use of carpet blocks and not the wall-to-wall carpeting

• Whenuseofvinylflooringcannotbepre-vented,thesealingofthefloormustformpart of the cost of the project and should be done by maintenance upon practical completion.

20.1.2 Lecture halls/rooms

• Lecture halls/roomsmust preferably beequippedwithfixedbenches/seatingex-cept in the case of Tutor Rooms.

• Prominentsignsregardingtheforbiddingof eating, drinking and smoking must be put up in lecture halls

Page 30: Physical Planning - Technical Manual - UFS

25

• Doorsoflectureroomsmustbeequippedwith a coded door lock as already in-stalled in existing buildings

20.1.3 Store room(s)

• Storagespacemustbeasnearaspossi-ble to the rest room of workers and must be big enough for storage of cleaning equipment and cleaning supplies.

• Shelves must be erected against thewalls and provisioning must be made for a broom cupboard

20.1.4 Rest rooms for cleaning personnel

• Theentrancetoarestroommustprefer-ably be on the outside of a building

• Windows must be ample size with anoutside view

• Standard shelves, lockers, a basin forcutlery, a wall mounted platform for kitch-en equipment must be provided accord-ing to the existing standard on campus

• Flooring must preferably be of ceramictiles with loose carpets otherwise plain concrete with a loose carpet.

• At least one double electric wall outletmust be provided near the table top for a two plate stove, a kettle, a fan, etc. and also a double electric wall outlet for eg a heater elsewhere in the room

20.1.5 Rest rooms/bathrooms in buildings

• Wallsmustpreferablybe tiledup to theceiling and if not, then at least to the top of a door

• wallsmustbepaintedwithanoilbasedpaint

• Donotmakeuseofautomaticwaterdis-pensers at urinals but rather make use of auto-janitors

• Provision must be made for fluid soapdispensers next to washbasins. The type of dispenser must be approved by Cleaning Services

• Provide5rolltoiletpaperholdersasfaras possible. However some rest roomsdo not need such a holder and if there is uncertainty, it can be discussed with Cleaning Services.

• Alwaysprovideelectrichandblowers inrest rooms and not any paper towel hold-ers.

• Doors inrestroomsmusthaveaspaceof at least 100mm at the bottom.

• Alwaysmake use of the “bowl” type ofurinal and not the long stainless steel va-riety

• Ifinanywaypossible,makeprovisionforawateroutletinthefloorincaseofanyfloodingofwashbasins,etc.

20.1.6 Courtyards

• No treesmust be planted in courtyardsas far as possible. Can be discussed with Maintenance and Cleaning Services

• Provisionmustbemadeforawatertapin a courtyard from which a hose may be connected

• Water drainage outlets must be big inorder to accommodate the accumulation of leaves, bird droppings, etc. and metal rosters must also have wide openings.

Page 31: Physical Planning - Technical Manual - UFS
Page 32: Physical Planning - Technical Manual - UFS

205NelsonMandelaDrive/RylaanPark West / Parkwes

Bloemfontein 9301South Africa / Suid-Afrika

P.O Box / Posbus 339Bloemfontein 9300

South Africa / Suid-AfrikaT: +27(0)51 401 9111

www.ufs.ac.za