photovoltaic training - session 2 - construction and start-up
DESCRIPTION
* Civil works. Preparation of infrastructure. * Mechanical assembly. * Electrical Installation: Ground‐mounted PV facilities. Rooftop installations. Wiring. Cabinets. Ground net. * Environmental aspects and waste management. * Quality. Critical aspects in the development of the installation. * Testing. Key issues. Inverter tests. Maximum power of the PV generator. Evaluation of the Performance Ratio real.TRANSCRIPT
Photovoltaic Systems Training
Session 2 ‐ Execution and Commissioning
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Javier Relancio & Luis RecueroGeneralia Group
September 16th 2010
PHOTOVOLTAIC SYSTEM
Design, Execution, Operation & Maintenance
EXECUTION AND COMMISSIONING
Javier Relancio. Generalia Group. 16/09/2010www.generalia.es
2 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
INDEX
Civil works. Infrastructure preparation
Mechanical works
Electrical works
Environmental issues
Quality. Critical issues during execution
Safety & Labor risks
Commissioning tests. Key points
3 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
INDEX
Civil works. Infrastructure preparation
Mechanical works
Electrical works
Environmental issues
Quality. Critical issues during execution
Safety & Labor risks
Commissioning tests. Key points
4 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
5
Rooftop projects
We may find little civil works, but it will be reduced to the trench
opening for the connection of the inverters and the meters
Ground projects
Civil works are very important
A good definition for the civil works could mean an important
saving in the project.
Main civil works are:
Terrain leveling
Accesses and inside roads/paths
Trench opening (AC & DC)
Civil Works: Infrastructure preparation
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
6
Terrain leveling
It might be avoided as much as possible in order to reduce the environmental impact
Only required works should be done:
Selecting a flat terrain may avoid its leveling
Selecting a structure type which can be fixed to the terrain by a “ground anchor”, instead
of a concrete base
Depending on the solution design, the choice between fixed or suntracking project can be
determinant
Source: QHOELET
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
7
Internal roads & paths
It is recommended to use already existing paths
We must take into account that the roads or paths have to allow the circulation of
trucks. Truck turning radius must be considered:
Vehicle Type Nomenclature Height Width LengthLength
between axis
Minimum radius for external front-
wheel
Minimum radius for internal back-
wheel
Light vehicle VL 1,30 2,10 5,80 3,40 7,30 4,20
2-Axis Omnibus B2 4,10 2,60 9,10 6,10 12,80 8,50
3-Axis Omnibus B3 4,10 2,60 12,10 7,60 12,80 7,40
2-Axis simple truck C2 4,10 2,60 9,10 6,10 12,80 8,50
3-Axis simple truck C3 / C4 4,10 2,60 12,20 7.6 12,80 7,40
Trailer (Semi) T2S1/ 2 / 3 4,10 * 2,60 15,20 4,00 / 7,00 12,20 5,80
Trailer (Semi) T3S1 / 2 / 3 4,10 2,60 16,70 4,90 / 7,90 13,70 5,90
2 Axis trailer + 1 Double C2 - R2 / 3 4,10 2,60 19,903,80 / 6,10 / 6,40
13,70 6,80
3 Axis trailer + 1 Double C3 - R2 / 3 / 4 4,10 2,60 19,90
3,80 / 6,10 /6,40
13,70 6,80
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
8
Once the installation has been commissioned, internal paths & roads will not be used too
much, so a 25 cm depth path of a mixture 75% gravel, 25 % river sand, may be enough.
Internal roads & paths
Minimal turning radius for B3/C3 vehicles
Accesses and roads/paths detail75% gravel, 25 % river sand
Natural terrain
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
9
Trenches
In a PV project, all the cable must be buried underground
Each 40 meters or each direction change, a manhole will be placed to ease the cable
laying
The project design might try to use the same section for all the trenches
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
10
Trenches
The trenches will have:
A river sand base
Space for the pipes
Backfill of sifted soil and soft sand
Cable caution tape
In the case it is a vehicle passing area, it will have a concrete layer at the top
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
INDEX
Civil works. Infrastructure preparation
Mechanical works
Electrical works
Environmental issues
Quality. Critical issues during execution
Safety & Labor risks
Commissioning tests. Key points
11 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
12
Mechanical works
Structure type Weight Anticorrosion protection Mechanical performance
Galvanized steel Resistant rooftops 8 years (non salty atmosphere) Good
Hot galvanized steel Resistant rooftops More than 25 years Good
Anodizing Aluminum Light rooftops More than 20 years Medium
No structure Light rooftops ‐ ‐
For fixed installations, the structure can be set parallel to the surface
where it is to be installed (flat), or with the optimum tilt for each
latitude (Tilted)
Flat Tilted
No wind action Important wind action
Worse cooling Best natural cooling
Lower cost (Both for structure & mounting)
Higher cost (Both for structure & mounting)
Photo: Krannich
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
13
Mechanical works
The structure anchor for a ground installation may
have the following possibilities:
Ground anchor
These screws have an average length
between 1 -1,6 meters
Easy to be dismounted
They can be adapted to the terrain orography
They can’t be used in a rocky terrain
Concrete basement
Above or under the ground
It requires a flat surface
Easy to be dismounted (if it is above the
ground)
Source: Conectavol
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
14
Roof anchorage
Metal roof anchors:
We have two options:
Direct to purlins anchorage
Specially designed anchors to be fixed directly to the roof
sheathing
It is recommended to use the direct to purlin anchorage. If
tilted structure is being used, other choice could be risky.
Tile roof anchorage:
A typical solution is using a “U” shaped piece which is
anchored directly to the roof, avoiding to drill the tile
It is necessary to move the tiles (danger of leaks)
With a special piece we can go through the tile
Danger to break the tileSource: SoportesSolares
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
15
Roof state:
The following aspects are to be evaluated:
Safety
We have to verify if the roof is safe. If not, we may install “lifeline”, “skylight
network”
Roof type
Asbestos (Uralita) roofs are the most difficult ones, as it may be cracked by
stepping on it, producing leaks, or it could even be broken, being really risky for
the installers. In this case, it is recommended to change the whole roof to metal
roof.
PV Roofs
Sealing
It is important to use the most indicated sealing to avoid
leaking. This sealers must have great elasticity and good
mechanical resistance. They may be complemented by
EPDM* bands
* a type of synthetic rubber (ethylene propylene diene Monomer)
16
Loads on the roof
Material weight (average weight by square meter)
Wind effect
During the design, both panel height and exposed surface must be considered
Extra loads during the execution: such us tools, workers, materials…
Accesses: The accesses will be distributed all along the roof surface, guaranteeing the
worker safety and allowing them to carry up small materials and tools
PV Roofs
Element Weight
Structure 2KG
Crystalline panels 15KG
Thin film glass‐glass panel 22KG
Thin film laminated panel 6KG
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
INDEX
Civil works. Infrastructure preparation
Mechanical works
Electrical works
Environmental issues
Quality. Critical issues during execution
Safety & Labor risks
Commissioning tests. Key points
17 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
18
Electrical works
Cable for the panel strings
• We usually use the cable included by the panel manufacturers.
Important to confirm with the manufacturer that this cable is included
• This cable are composed of copper: 4mm; 0,6/1kV
• This cables usually are ended in “fast connectors”: Multicontact,
Tyco, etc
Source: Eastech Solar
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
19
Electrical works
Roof installations
Cable canalization might be done under hot galvanized cable tray or tubular conduit
Cable tray canalization simplifies mounting works, and eases the maintenance tasks.
Indoor, plastic(or metallic) cable tray might be used, as well as halogen-free cable
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
20
Electrical works
Ground installations
Electrical works will be done in the trenches, so the cable must be designed for this use.
It is recommended to use anti-mice cable, inside a tubular conduit.
Cable trenches might be really long, so the
trench design, number of cables by pipeline,
extra space by pipeline, manholes, etc.. could
be decisive to optimize the electrical works
duration
The cable should be previously marked in order
to avoid connecting issues
It is important to avoid corners or any element
which may cause any damage in the cable
isolation.
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
21
Electrical cabinets
Depending on its location, a different IP may be required
• For outdoor installations, at least IP 65 will be required
• For indoor installations, IP 21 could be enough (except for special conditions: water,
powder…)
It is really important to pay attention at the element connections, and the
identification of each cable & component in the project documentation
The thermal study of the cabinet is also important, verifying the minimal required volume
for the heat dissipation, and raising additional solutions as the incorporation of a heat
resistance in case of outdoor installations in very cold zones
22
Earthing system
The following elements must be earth connected
PV panel frameworks
Structure
Metal cable tray
Metal elements in electrical cabinets
PV inverters
For small facilities, the earthing system would be quite
simple: 2 – 3 pegs, depending on the soil resistivity
For bigger facilities, a cable grid is usually implemented,
using the trench already opened for the energy cables, placing
an uncovered copper cable below the energy cables.
The section of this cable is to be calculated during the design
EARTH CABLE
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
INDEX
Civil works. Infrastructure preparation
Mechanical works
Electrical works
Environmental issues
Quality. Critical issues during execution
Safety & Labor risks
Commissioning tests. Key points
23 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Nowadays we can find
A change in the social sensibility for the environmental impacts. The society begins to
have a greater conscience and a harder implication.
This will be the real engine for the new environmental initiatives to be managed in a
suitable way.
The ISO Certification 14001, allows us to take and to show the others, our
environmental commitment.
For all this, the solar power companies should demonstrate the coherence with their
ecological message, developing a good environmental policy
24
Our solar facility and the environment
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
25
Definitions (ISO 14001):
Environmental aspect: Any element of the activities, products or services that is
causing some type of impact on the environment can be considered as an
environmental aspect.
Environmental impact: Any change in the environment, either adverse or beneficial,
resulting from the activities, products and services of an Organization.
Residue: Any substance or object from which his holder detaches or has the obligation
to become detached following the European rules & standards
Environmental aspects & impacts
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
We must take into account the environmental management of our solar facility
a. To know the in force legislation
b. To know the environmental aspects that concern our business
c. To evaluate the impact that has on the environment
d. To propose indicators that give us a tangible evidence about the measured aspects,
and their impacts, and to use them to develop new preventive and corrective
measures
e. To have an emergency plan derived from the knowledge of the different environmental
aspects
f. To do the suitable management of the generated residues
26
The environmental management becomes necessary in the execution, as well as the operation
of the solar plant, therefore, an individual analysis of every project will be required
Environmental aspects & impacts
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
27
1. List of aspects and impacts
2. Emergency classification
Activity Aspect N/E Impact
PV installations (and
Suntrackers, in case
of being used)
Electric energy consumption NAtmospheric contaminations
Visual Impacts
Fuel consumption N Atmospheric pollution
Powder generation N Atmospheric pollution
Residues generation N Space in the dumpsite
Fire EAtmospheric pollution
Impact on the fauna & flora.
N: Normal; E: Extraordinary
Example: Environmental management during the project execution
Aspect P S ASignificant
YES=Y; NO=N
Fire 2 4 8 Y
P: Probability; S: Seriousness; A: Assessment
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
3. Aspect classification (Normal aspects)
ASPECTS F S C ASIGNIFICANT
YES/ NO
Electrical energy consumption 5 2 2 20 YES
Dangerous residues generation 3 2 2 12 NO
Urban residues generation 4 1 2 12 NO
Noise generation 3 1 1 6 NO
Fuel consumption 3 2 2 12 NO
Powder generation 3 1 1 6 NO
Paper consumption 5 1 2 15 YES
Packages 4 1 2 12 NO
F: Frequency; S: Seriousness; C: Consequence; A: Assessment
28
Example: Environmental management during the project execution
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
EVENT/ EMERGENCY: FIRE
Preventive measures Adaptation to the electrical and construction regulations. Fire‐extinguishers.
Actuation plan
• The work manager is the person in charge of the extinction of fire.
• In case of non‐controllable emergency, the work manager will take charge of
warning the external emergency services.
• The work responsible is the person in charge of giving the alarm and
controlling the evacuation of the whole staff. He must check that the
evacuation has been completed
Practice Fire
Practice description
The response time will be measured for the following aspects:
• The fire warning.
• Staff evacuation.
• The checking that the evacuation has been completed.
Frequency Yearly
29
4. Emergency plan
Example: Environmental management during the project execution
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
5. Residue management general process:
In every moment, we must:
To develop a study of the residues that are being produced, in the execution and the
operation of the solar power facility;
To quantify the quantity of each one, and to do a management of the residue
according to its type.
30
Urban residues Dangerous residues
Paper Toner with metallic components
Plastic Batteries
Tins & Cans Fluorescents
Toner without metallic components Oils (Vehicles / Motors)
Example: Environmental management during the project execution
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
INDEX
Civil works. Infrastructure preparation
Mechanical works
Electrical works
Environmental issues
Quality. Critical issues during execution
Safety & Labor risks
Commissioning tests. Key points
31 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
32
Quality: Critical aspects
The critical aspects referred to quality in the phase of execution are:
Materials
Checking that we have received the goods that have been requested
Inspection of the goods at their arrival to check possible material faults/defects
This process will be developed for a certain number of samples previously defined by the
quality department
The checking of the electrical and mechanical parameters of the material, to avoid early
breakdowns
Work execution
Correct planning of the work: in order to avoid delays, dead times of the workers,
managing the activities in “critical way”
Updated documentation for the works: It is important to check that the workers have the
latest edition of the information
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
33
Work Manager
Quality: Critical aspects
Material Administration Material Reception
1.Checking that the items that have
arrived correspond to the items of
the delivery note
2.Visual checking
3.Checking of electrical and
mechanical characteristics
1.Checking that the items indicated in
the delivery notes corresponds with
the ordered ones
2. Checking any lacking item in the
order and claiming for it
3. Checking the payments
1.Checking that the ordered material fits
with the projects real requirements
2.Checking that the real project conditions
matched with the project design
3.Managing the material administration and
reception
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
34
Work Manager
Worker
1. Work execution according to the
work order
2. To notify incidents in the
accomplishment of the works
3. Accomplishment of the checking
indicated in the work order
1. Fulfillment of the planning deadlines
2. Checking the documentation of the
work orders
3. Checking the quality in the
intermediate milestones of the project
4. Checking the management of the
residues during and at the end of the
project
5. Final checking of the work
Quality: Critical aspects
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Samples selection
VISUAL ELECTRICAL THERMAL
Packages
PanelsOF
DETECTION OF
Panel arrays Panels
• Frame defects
• Glass defects
• Connection box defects
• Cable & connector defects
The electrical
characteristics differ from
the technical specs, used
for the design and they
are out of the required
range
Cell defects
Hot spots
Cell bubbles
35
Panel inspections
Although it might be true that the panels are the most expensive element in
the installation, a similar table should be done for the rest of the elements
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
The Thermography is a simple method to detect defaults in the solar panels
The checking of the installation is developed in a rapid and visual form
It saves time, as it identifies directly the problematic panel without having to do complex checks in the different strings
36
Thermography
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
INDEX
Civil works. Infrastructure preparation
Mechanical works
Electrical works
Environmental issues
Quality. Critical issues during execution
Safety & Labor risks
Commissioning tests. Key points
37 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
38
1. Introduction
Within every company it is obligatory to have a labor risk evaluation plan.
Even in the case that we subcontract other companies, it is necessary to check that each
company has its labor risk evaluation plan adapted to our activity.
Knowledge of the particularities of the company activities
Risk analysis for each activity
Actions depending on the risks
Labor risks evaluation plan
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
39
2. Activitie characteristics
PV on the roof PV on the ground (Fix) PV on the ground (Suntracking)
Small facilities: From 2‐3 KW to 100KW
(Or even more)Larger facilities: >100 KW Larger facilities: >100 KW
Working at great heights Working on the ground Working on the ground
Different types of roofs Earth movements Earth movements
Different tilts of roofs Trench openings Trench openings
Sharing the work with the industry
where our plant is locatedLarger number of workers Larger number of workers
Electrical cabling and inverter
commissioningPossibility of using cranes
Usage of cranes to fix the panel structure
to the Suntrackers
Electrical cabling and inverter
commissioning
Electrical cabling and inverter
commissioning
Labor risks evaluation plan
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
3. Activity risks
PV on the roof PV on the ground (Fix) PV on the ground (Suntracking)
Falls from the roof Falls into trenches Falls into trenches
Accidents due to material falling To be run over by working vehicles To be run over by working vehicles
Risk from the industry where the
plant is locatedElectrocution risk Electrocution risk
Electrocution risk Accidents due to material falling Accidents due to material falling
Accident due to collision with the suntracker
40
Labor risks evaluation plan
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
4. Activitie summary
To analyze the photovoltaic activities, to know and to evaluate the risks of every job
inside every activity.
To train the staff on the risks depending on their job or workstation
To distribute the equipments of individual protection adapted to every workstation
To designate a person in charge of checking the correct execution of the prevention
plans
To develop an emergency and evacuation plan
41
Labor risks evaluation plan
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
INDEX
Civil works. Infrastructure preparation
Mechanical works
Electrical works
Environmental issues
Quality. Critical issues during execution
Safety & Labor risks
Commissioning tests. Key points
42 http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Commissioning
Execution
Project design
Operation & Maintenance
PlansEngineeringTechnical datasheetsEquipment manualsSuntracker manual
Project modificationDone inspectionsElement identification
Preventive maintenance planCorrective maintenance planMonitoring system manual
Commissioning checklistPlant production checkingGenerator production checkingInverter production checking
Technical documentation
43
Project commissioning
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
As the aim that we pretend is to maximize the productive capacity of the photovoltaic solar
plant, we need to check, from time to time, a test of the plant productive capacity (i.e. every
three years)
If the plant is very large, it could be worthy to do a test every year
The plant performance can be measured up by the instantaneous response to:
Cell temperature (Depending on the outdoor temperature, wind, irradiance)
Irradiance
44
Plant production checking
We will evaluate:
The power, in alternating current at the plant output (meter)
Global and direct irradiance in a calibrated cell (from a similar technology to the one used
for the generator and parallel with it)
Cell temperature: sticking a thermal sensor to the calibrated cell
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
45
Source: Geonica
Plant production checking
Outdoor temperature
(Optional)
Irradiance
AC Power (at the meter output)
TEMP. PANEL FV
For the capture of the indicated
variables we will need to have:
A meteorological station
where the information of
Temperature and irradiance
will be registered
A meter (with integrated
communications) from which
we can read the output
power
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
46
In the case of using suntrackers, we have to verify the equipment performance every
hour by testing the shadow projected by a rod perpendicular to the plane of the
generator
Minimal measure period: 5 consecutive days dawn - dusk
Condition: The minimal period of irradiance over 600W/m2 must be at least 12 hours
Periodicity of the measure of output power - irradiance-temperature: 10 mins
The obtained measures of output power-irradiance-temperature are compared to the
expected ones and the deviations between both are analyzed
If the legislation allows it in the future, the modernization or extension of the plant for
repowering might be recommended
Plant production checking
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
47
I
V
Testing of PV Generator electrical characteristics
We obtain the C-V curve from the generator and the
one from a standard module, and both are compared
under the conditions above-mentioned
These tests have to be done two hours before and after
the local midday and the global irradiance has to be a
over 700W/m2
Nowadays we can find specific equipments to obtain the
C-V curve of a PV generator and move it into standard
conditions
Objective: To determine the electrical characteristics under the “Standard metering conditions”, defined by:
• Irradiance: G = 1000 W/m2 • Cell temperature: CT=25ºC.
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
48
Is the second most important element in a PV facility
The European efficiency of the inverter, has to be
verified with the measures commented in the previous
slides, attaching the power measure and the voltage
in the DC side
Furthermore, it must be verified the inverter capacity
to track the Maximum Power Point (MPP)
Testing of the inverter electrical characteristics
Source: SMA
Objective: To determine the characteristics which define the energetic performance of an inverter:
• Efficiency• Maximum Power Point Tracking
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
49
End of Session 2
http://www.leonardo-energy.org/training-pv-systems-design-construction-operation-and-maintenance
Thank you for attending