pfos and pfoa mitigation plan
TRANSCRIPT
Stewart Air National Guard Base
PFOS AND PFOA MITIGATION PLAN
Final
PFOS/PFOA Interim Mitigation Stewart Air National Guard Base, New York
Contract No. W9128F-14-D-0009 Delivery Order: W9128F19F0079
September 2019
Prepared by:
US Army Corps of Engineers Omaha District Special Projects Program Management Office
With Support From:
Bristol Environmental Remediation Services, LLC 720 Corporate Circle, Suite D
Golden, CO 80401
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 i Final
TABLE OF CONTENTS
SECTION PAGE
ACRONYMS AND ABBREVIATIONS .................................................................................. iii
1.0 INTRODUCTION ............................................................................................................... 1
1.1 Site Location and Project Background ...................................................................... 1
1.2 Stormwater Quality and Flow Data ........................................................................... 3
1.3 Project Planning and Reports .................................................................................... 3
1.4 Procurement ............................................................................................................... 4
1.5 Mobilization Activities ............................................................................................... 5
1.6 Health and Safety ........................................................................................................ 6
2.0 PROPOSED REDEVELOPMENT ..................................................................................... 8
2.1 Temporary Water Treatment System ........................................................................ 8
2.1.1 Recreational Pond Water Intake and TWTS Feed Pump .............................. 10
2.1.2 Pre-Treatment Enclosure ................................................................................ 11
2.1.3 Treatment System Enclosures ......................................................................... 13
2.1.4 General TWTS System Requirements and Controls ...................................... 14
2.1.5 Conex Enclosures ............................................................................................. 16
2.1.6 TWTS Electrical Service .................................................................................. 17
2.1.7 Interconnecting Process Piping ...................................................................... 17
2.1.8 TWTS Effluent Outfall .................................................................................... 18
2.1.9 Weather Protection Plan ................................................................................. 18
2.1.10 TWTS System Commissioning and Start-up .................................................. 19
2.2 Recreational Pond Storage ....................................................................................... 19
2.2.1 Stormwater Condition Assessment ................................................................. 20
2.2.2 Outlet Structure ............................................................................................... 21
2.2.3 Other Activities ................................................................................................ 23
3.0 AREAS OF ENVIRONMENTAL CONCERN ................................................................. 25
4.0 PERMITS .......................................................................................................................... 27
4.1 Electrical .................................................................................................................... 27
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 ii Final
4.2 SPDES Permit ........................................................................................................... 27
4.3 Stormwater and Earth Disturbance ......................................................................... 27
5.0 SITE MANAGEMENT ACTIVITIES ............................................................................... 29
5.1 Environmental Protection Plan ............................................................................... 29
5.2 Spill Contingency Plan ............................................................................................. 29
5.3 Management of Excavated Soils ............................................................................... 29
5.4 Dewatering ................................................................................................................ 29
5.5 Dust Control .............................................................................................................. 30
5.6 Air Monitoring .......................................................................................................... 30
5.7 Security ...................................................................................................................... 30
6.0 TRAINING PROCEDURES ............................................................................................. 32
7.0 DOCUMENTATION AND REPORTING ....................................................................... 34
ATTACHMENTS
Attachment 1 Site Location Map
Attachment 2 Outfall 010 Stormwater Quality and Flow Data from DMR Records
Attachment 3 Outfall 010 Recreational Pond and Outfall 002 Storm Drain Water Quality Sample Results
Attachment 4 Recreation Pond Outfall Stage Discharge Curves
Attachment 5 –Stormwater Review Technical Memorandum
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 iii Final
ACRONYMS AND ABBREVIATIONS
AFFF Aqueous Film Forming Foam APP Accident Prevention Plan BWS BERS-Weston Services JVA, LLC CAD Computer Aided Design CFR Code of Federal Regulations CWA Clean Water Act DMR discharge monitoring records EPP Environmental Protection Plan FAA Federal Aviation Administration FAR Federal Acquisition Regulations ft feet GAC granular activated carbon gpm gallons per minute HDPE high density polyethylene kW kilowatt LHA Lifetime Health Advisory MCLs Maximum Contaminate Levels mg/L milligrams per liter NY New York NYDOT New York Department of Transportation NYNJPA New York and New Jersey Port Authority OEC Onion Equipment Company OSHA Occupational Safety & Health Administration PDT Project Delivery Team PFAS per-and polyfluoroalkyl substances PFOA perfluorooctanoic acid PFOS perfluorooctanesulfonic acid PLC programmable logic controller ppt parts per trillion psi pounds per square inch PSIG Pounds per Square Inch Gauge QA/QC Quality Assurance/Quality Control
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 iv Final
QC Quality Control SANGB Stewart Air National Guard Base SSHP Site-Specific Safety and Health Plan SPDES State Pollutant Discharge Elimination System TAA Tennant Alteration Application TWTS Temporary Water Treatment System UPS uninterrupted power supply USACE United States Army Corps of Engineers VFD variable frequency drive
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 1 Final
1.0 INTRODUCTION
1.1 SITE LOCATION AND PROJECT BACKGROUND
BERS-Weston Services JVA, LLC (BWS), under Contract W9128F-14-D-0009 with the
United States Army Corps of Engineers (USACE), is required to provide time-sensitive
response actions for Stewart Air National Guard Base (SANGB), Newburgh, New York (NY)
whose stormwater discharge is contaminated with perfluorooctanesulfonic acid (PFOS) and
perfluorooctanoic acid (PFOA). PFOS and PFOA are two constituents of aqueous film
forming foam (AFFF), that have been detected above the U.S. Environmental Protection
Agency (EPA) drinking water lifetime health advisory (LHA) standard of 70 parts per trillion
(ppt) (individually or combined) in the off-base stormwater discharge into the Recreational
Pond. Flow out of the Recreational Pond is through a weir outfall, which then flows into
Silver Stream, which flows into Moodna Creek and eventually the Hudson River. A
diversionary channel could also direct Silver Stream to Lake Washington, which is the
drinking water reservoir for the City of Newburgh, NY. This diversionary channel was
closed in 2016 when per- and polyfluoroalkyl substances (PFAS) contamination was
detected. This action is being undertaken by SANGB to protect drinking water under the
Clean Water Act (CWA). A site location map is included as Attachment 1.
As part of the response actions under this Contract, BWS is required to develop and
implement interim mitigation measures for the treatment of stormwater runoff by reducing
PFOS/PFOA concentrations to acceptable levels. A Temporary Water Treatment System
(TWTS) will be mobilized to withdraw waters from the Recreational Pond, reduce
PFOS/PFOA, and discharge treated water to the existing pond outfall location.
The TWTS described in this mitigation plan is just one of several initiatives being undertaken by
the Air National Guard (ANG) to mitigate PFAS from being discharged to the Recreational
Pond. Other ANG activities not part of this current project include stormwater drainage
monitoring, sampling and modeling of PFAS contributions into the pond, and collection of data
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 2 Final
that will allow for evaluating long term strategies to mitigate or remediate PFAS from
stormwater discharges.
Stormwater runoff from the SANGB is diverted to the Recreational Pond, located at the
south side of the base via four main storm drains commonly referred to as Outfall’s A, 002,
003, and the 17K outfall. The existing detention pond is approximately 2.5 acres and the
pond depth to the top of sediment is believed to range between 3 to 8.3 feet deep with an
average pond depth of approximately 5.5 feet deep. The Recreational Pond has an average of
approximately 1.8 feet of sediment in the bottom based on 2017 soundings completed by
Aqua Survey, Inc. The detention pond outfall consists of an overflow structure equipped
with a 15’-6” crest width concrete trapezoidal weir that is approximately 7-feet high
measured from the water surface.
Interim mitigation shall include drawing down the dry weather pond level in order to
provide storage in the pond for rain events that exceed a determined runoff quantity. The
stored volume will then be treated and discharged at the existing overflow weir via a new
outfall structure. This Mitigation Plan clarifies proposed implementation methods for the
interim response actions.
Services required to successfully execute this task order will include but are not limited to:
development and installation of the approved PFOA & PFOS mitigation system, including an
interim TWTS; complete with needed ancillary infrastructure required for start-up,
operation, maintenance, and monitoring of the system.
Mitigation measures shall result in the discharge of treated water that is below the 70 ppt
lifetime health advisory (LHA) standard, in drinking water, for PFOS and PFOA
(individually or combined). Discharge water shall also meet local and state standards and be
in accordance with the CWA, and the conditions set forth in the existing State Pollutant
Discharge Elimination System (SPDES) Permit as it relates to the water quality requirements.
Concurrently with implementation of this interim mitigation, the State of New York is
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 3 Final
working on establishing more stringent Maximum Contaminant Levels (MCLs) for PFOS and
PFOA compounds at 10 ppt respectively. Although the current system has not been
Contracted or designed for these future standards, the TWTS should have the ability to
comply with the proposed lower state standards for PFOS and PFOA.
1.2 STORMWATER QUALITY AND FLOW DATA
Available discharge monitoring records (DMRs) including historical flow and water quality
data for stormwater overflowing the outfall structure are included in Attachment 2. This
outfall location is referred to as Outfall 010. There is limited water quality data available for
PFAS at Outfall 010. However the available data confirms the presence of PFAS compounds
at the outfall between 300 and 700 ppt, which exceed the 70 ppt LHA. BWS collected
additional stormwater quality samples in early April 2019 for PFAS, along with SPDES water
quality parameters and other wet chemistry parameters that will help confirm the interim
TWTS design requirements. These samples were collected at the existing Outfall 010 weir
structure as well as Outfall 002 entering the pond. These locations were selected to provide
additional water quality data that can be used for TWTS design purposes and verify the
limited available data set. The BWS sample results are included and summarized in
Attachment 3. As part of other concurrent initiatives being undertaken by SANGB,
additional sampling and monitoring is being performed by SANGB to further define the
concentrations and sources of PFAS contamination throughout the overall drainage system
including the Recreational Pond and outfall 010.
1.3 PROJECT PLANNING AND REPORTS
In addition to this Mitigation Plan, the following plans and planning activities have been or
are planned to be performed:
• Right of Entry (ROE) access agreements will be obtained for access to the Recreational Pond for both planning and construction purposes.
• BWS has prepared and submitted the following plans prior to mobilization: Uniform Federal Policy Quality Assurance Project Plan (UFP-QAPP), Contractor Quality
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 4 Final
Control Plan (CQCP), Accident Prevention Plan (APP)/Site-Specific Health and Safety Plan (SSHP), Environmental Protection Plan (EPP), Waste Handling/Management Plan, Community Involvement Plan, and a Restoration Advisory Committee Development Plan prior to mobilization.
• The TWTS and existing outfall structure are located on land owned by the New York Department of Transportation (NYDOT) and leased to New York and New Jersey Port Authority (NYNJPA). BWS and the Project Delivery Team (PDT) will coordinate the project activities with the NYNJPA and SANGB as the property tenant. The BWS team has submitted a Tenant Alteration Application (TAA) for implementation of the TWTS to the NYNJPA for review and approval. This TAA was prepared by a licensed engineer in the State of New York, referred to as the Engineer of Record (EOR) and submitted to the NYNJPA for approval. It is anticipated that TAA approval by NYNJPA will be provided in advance of mobilization.
• BWS has prepared and submitted a Work Plan for this project. The Work Plan further describes the procedures and work required to implement construction and operation of the TWTS.
• A project schedule will be submitted and updated weekly during planning and construction.
• Prior to TWTS operation, the following additional plans will be prepared and submitted for approval: Weatherization Plan, Startup and Maintenance Plan, Operations and Maintenance (O&M) Manual and a Transition Plan,
• BWS is procuring required site supplies and subcontractor services needed to implement this project.
• A submittal register and project submittals are on-going and being prepared and approved for all materials incorporated into the work.
• BWS will, set-up a field office, and conduct a Project Kickoff meeting with all PDT members.
• BWS will monitor the effectiveness of the stormwater interception and treatment measures to determine if additional mitigation measures are needed.
• A completion report will be prepared at the end of the project.
1.4 PROCUREMENT
Procurement of the following equipment and subcontractors will be necessary to implement
this project:
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 5 Final
• Site facilities (trailer, restroom, hand wash station, site security, and temporary power);
• Private underground utility locating survey services for all areas to be disturbed;
• Civil works services including; erosion and sediment controls installation, gravel pad construction, access road improvements, utility trenching/backfill, TWTS equipment rigging and installation/testing of interconnecting piping.;
• Pre-manufactured TWTS treatment system;
• Temporary outfall structure installed at the existing Recreation Pond overflow weir;
• Site power connection to the SANGB electrical system;
• Electrical services including 3-phase transformer, electrical distribution, and interconnecting communications and
• Operations subcontractor services during operations and maintenance (O&M).
All procurement activities are performed and administered in accordance with the Service
Contract Act, Federal Acquisition Regulations (FAR), and the Defense Federal Acquisition
Regulations Supplement (DFARS).
1.5 MOBILIZATION ACTIVITIES
Mobilization will commence after Prior to initiating any subsurface work on any site, Dig
Safely of NY will be contacted to mark-out utilities for each applicable work area. BWS will
also retain an independent underground utility locating firm utilizing ground penetrating
radar equipment to locate on-site utilities in disturbed areas. Mobilization/setup includes set-
up of a temporary job trailer; sanitary facilities and a portable generator for temporary power
to job trailer.
Placement of the TWTS enclosures will require use of a crane. BWS has received a Federal
Aviation Administration (FAA) determination (ASN 2019-AEA-7292-OE) allowing
operation of a temporary 120 ton crane with a maximum height of 100 feet above ground
level at the Recreation pond area. BWS and the Crane operator will perform the required
notifications prior to mobilization and when the crane is dismantled in accordance with the
determination.
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 6 Final
1.6 HEALTH AND SAFETY
An SSHP and APP has been prepared and approved for this project. The SSHP and APP
contains health and safety criteria, procedures, and work practices sufficient to protect on-
site personnel and the environment.
BWS will utilize qualified personnel, including a field dedicated Site Safety and Health
Officer (SSHO) to oversee the development and implementation of required safety and
health documents and all activities will comply with the following:
• Federal Acquisition Regulation, F.A.R. Clause 52.236 13: Accident Prevention.
• U.S. Army Corps of Engineers (USACE), Safety and Health Requirements Manual, EM 385 1 1 (Nov 2014).
• Occupational Safety & Health Administration (OSHA) Construction Industry Standards, Title 29 Code of Federal Regulations Chapter 1926 (29 CFR 1926), and General Industry Standards, 29 CFR 1910.
• Other applicable Federal, State, and local safety and health requirements.
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 7 Final
(Intentionally blank)
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 8 Final
2.0 PROPOSED REDEVELOPMENT
2.1 TEMPORARY WATER TREATMENT SYSTEM
BWS has procured and will install, test, and make fully operational Pre-manufactured
containerized mitigation systems for temporary treatment of stormwater for PFOS/PFOA
prior to discharge from the Recreational Pond to include pretreatment (screening/filtration),
granular activated carbon (GAC), followed by PFAS adsorption using ion exchange media.
The TWTS will be located in the open area south east of the existing overflow structure at
the approximate location shown on Figure 1.
The TWTS will be pre-engineered to treat water up to 500 gallons per minute (gpm). The
TWTS is to be housed in three (3) Conex enclosures to provide protection from weather and
freezing temperatures. The first Conex will enclose the pretreatment filtration system and
controls. The other two enclosures will house parallel trains of one Pre-treatment GAC
vessel and two primary treatment of ion exchange media vessels arranged in a lead/lag series
configuration. The treatment system conceptual design is shown on Figure 2. The TWTS
shall be engineered and constructed by Onion Equipment Company (OEC) who
manufactures pre-engineered (modular) treatment equipment and experienced with PFAS
water treatment for surface water. OEC will engineer and manufacture the system and
support start-up and commissioning of the installed treatment system.
The TWTS Conex enclosures will be installed behind the Recreational Pond berm and
southeast of the weir structure outfall as depicted in Figure 1. To protect against syphoning
of Recreational Pond, a vented high point will be provided in the effluent discharge line
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 9 Final
Figure 1 TWTS System Location
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 10 Final
Figure 2 TWTS Conceptual Diagram
2.1.1 Recreational Pond Water Intake and TWTS Feed Pump
Water will be drawn from the Recreational Pond via a submerged suction pump, which will
be mounted to a floating or temporary dock in a portion of the pond selected to maximize
usable volume and minimize exposure to damage and erosion. The intake will be submerged
and screened to prevent entry of floating debris, but off the bottom to minimize entrainment
of sediments. The screen will be sized to have a low intake velocity to reduce the likelihood
of collecting debris and adequately protect the pump. The screen will be accessible from the
floating or fixed dock for maintenance and cleaning if necessary. Water will be transferred
from the pump via flexible suction hose and high density polyethylene (HDPE) pipe to the
TWTS. The above ground line between the pond and the enclosure will be protected from
freezing. The pump will supply up to five-hundred (500) gpm to the TWTS. The pump will
be driven by a variable frequency drive (VFD) to maintain a flow processing rate under
variable TWTS back pressure. The pump will be controlled on/off by maintaining a target
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 11 Final
level in the pond that is below the overflow level. A level transducer will be installed in the
pond to monitor and document the water level during system operation and control the
TWTS.
2.1.2 Pre-Treatment Enclosure
The first Conex enclosure will house the pre-treatment system. Pre-treatment is required to
remove solids that may enter the TWTS and prematurely foul the treatment media. The pre-
treatment system will consist of 1 centrifugal separator and bag filtration. The centrifugal
separator will be a carbon steel separator manufactured by Rosedale as shown in Figure 3.
The separator shall be designed for 500 gpm with less than 15 pounds per square inch (psi)
pressure drop. The separator shall remove solids contained in the pond water via centrifugal
action. The separation systems have a timed solenoid valve that opens and flushes out the
accumulated solids automatically. Flush water will be returned to the Recreational Pond.
Figure 3 Pretreatment Separator
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 12 Final
Following the separator, the water will enter a second filtration system. The filtration system
consists of Rosedale multi-bag, two stage, No. 2 size bag filtration system constructed of
carbon steel. Each stage will have 6 filters in order to process 500 gallons per minute. The
first stage will have coarse bag filters (approximately 25 micron). The second stage will have
fine bag filters (approximately 10 micron). Figure 4 shows a Rosedale multiple bag filter
housing that could serve as either the coarse or fine filtration. The bag filter housings will
have pressure gauges and pressure transmitters located on the inlets and outlets, to
continuously monitor operating pressure during system operation. The pressure transmitter
will continuously document differential pressure at the control system and notify operations
staff when high differential pressure occurs indicating the bags will require change out.
Figure 4 Multi Bag Filter Skid
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 13 Final
2.1.3 Treatment System Enclosures
After pre-treatment, process water will be divided into two streams and process forward flow
will be sent to two identical and independent treatment system enclosures installed in
parallel. Each independent treatment system will be configured with two (2) total treatment
trains housed in a single Conex enclosure for a total of four (4) treatment trains running in
parallel within two (2) Conex enclosures.
Each treatment train shall contain GAC pretreatment, primary ion exchange and polishing
ion exchange. The GAC pretreatment system will be comprised of two (2) GAC vessels,
running in parallel, for the removal of organic compounds that could impact the long term
performance of the ion exchange media for PFOS/PFOA removal. Each GAC vessel will be
approximately five (5) foot diameter, and contain approximately 2,500 lbs. of carbon.
Between the two (2) Conex enclosures there will be a total of four (4) GAC treatment vessels,
each containing approximately 2,500 pounds of GAC media. The GAC vessels will initially be
filled with 8x30 Calgon Filtrasorb 300 granular activated carbon media. When GAC is
exhausted and requires to be replaced during system operation, it will be profiled and
properly disposed at a landfill following incineration. Each GAC vessel will have an air vent,
drain and inlet/outlet valves, sample ports and pressure gauges in order to monitor their
performance and control their operation. Provisions will be made to allow for manually
backwashing the vessels if premature fouling occurs. If backwashing is performed backwash
water would be returned to the Recreational Pond away from the pump intake and in a
manner that does not disturb the pond or cause erosion.
In each enclosure after passing through the two GAC pretreatment vessels, the flow will
then be directed into the primary ion-exchange resin treatment vessels (two located within
each Conex enclosure) followed by the polishing ion exchange resin treatment vessels (two
located within each Conex enclosure) for the removal of PFOS/PFOA from the water. Each
vessel will contain approximately 70 cubic feet of Purolite® PFA694 ion-exchange media (or
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 14 Final
equal). The eight ion exchange vessels will contain a total media volume of 560 cubic feet.
Four (4) ion-exchange treatment vessels will be installed in each parallel Conex enclosure.
Each vessel will be approximately five (5) foot diameter and have six (6) foot sidewalls. With
this configuration, there will be four (4) total treatment trains running in parallel (two
within each Conex enclosure). A manifold or flexible hoses with quick disconnects will be
provided to allow bypass of the primary vessels when they are exhausted and swapping the
primary and polishing vessels when media is replaced. The manifold will be equipped with
pressure gauges and sample ports to allow for monitoring the performance of each skid. Each
individual ion exchange vessel will have isolation valves to be able to service each unit
independently. Each ion exchange vessel will have an air vent, drain and inlet/outlet valves,
sample ports and pressure gauges in order to monitor their performance and control their
operation. During system operation when ion exchange media becomes exhausted and
requires to be replaced, it will be profiled and properly disposed at a landfill following
incineration.
The treated water will be combined and will exit both Conex treatment enclosures via a
single effluent line. The two effluent lines (one from each enclosure) will then be combined
and a single effluent flow meter will be installed to monitor the overall flow rate (gpm) and
total gallons treated. Discharge control valves are installed downstream of the flow meter
that will divert treated effluent either back to the Recreational pond (e.g. recycle) or direct
treated water adjacent to the outfall structure located adjacent to the overflow weir. Each
gravity discharge line will have a constructed high point and be vented.
2.1.4 General TWTS System Requirements and Controls
The treatment systems will contain sample ports on the influent (raw water), after each
pretreatment stage, and after each GAC and each ion exchange media stage as well as the
combined treated effluent. Intra-process monitoring is important to evaluate each process
stage and confirm breakthrough of PFOS/PFOA on the primary ion exchange media. Once
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 15 Final
breakthrough of PFOS/PFOA are detected on the primary ion exchange at concentrations
exceeding one-half the HAL (35 ppt) the resin in the primary vessels will be replaced.
Following media replacement, the polishing vessels will then become the primary vessels and
the newly serviced primary vessels will become the polishing vessels. Water samples will be
collected approximately on a weekly basis during the first month and monthly thereafter.
More frequent sampling will be performed if raw water quality changes or observed or if
treatment system performance warrants more frequent monitoring. The sampling schedule
will be adjusted appropriately to ensure that ion exchange media change outs are conducted
in advance of PFAS breakthrough in the polishing effluent to ensure that the systems are
serviced in a timely manner to meet treatment objectives.
Pressure gauges and pressure transducers will be installed on the influent and effluent of
each treatment stage to monitor for pressure differentials, which could indicate the need for
system servicing or backwashing. The treatment system will have automated controls that
will allow local monitoring of system performance from a single location.
The controls will include a programmable logic controller (PLC) with a touch screen panel,
similar to one shown in Figure 5. A cellular modem with a static IP address will be installed
to allow for remote access and monitoring of the system on computers and smart phones.
Access will be password protected and secure. The control system will monitor; equipment
run status, system flows, system pressures, pond level, and alarms. If an alarm occurs the
system will be equipped with an alarm dialer or alarm management system that can be
custom configured to notify operations personnel of an alarm. Operations personnel will be
available to address any operations and maintenance concerns, 24 hours/day, 7 days a week.
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 16 Final
Figure 5 Typical Control Panel
2.1.5 Conex Enclosures
Each Conex enclosure will be approximately eight (8) feet wide by forty (40) feet long by
nine (9) feet high. The enclosure will be insulated and will have electric heaters to protect
the systems from freezing. The enclosures will be constructed with interior lighting,
ventilation, personnel doors, fire extinguishers and double doors to allow for access to the
systems for servicing. These containers are not considered “confined space” under OSHA.
The systems and controls will come pre-fabricated within each Conex enclosure, minimizing
on-site time required for the erection of the systems and start-up.
The Conex enclosures will be installed on a level, gravel laydown pad that will be
constructed prior to delivery to the site. The Conex enclosure will arrive at the site via
flatbed truck and will be offloaded at the site using a crane. Interconnecting piping and
electrical for the treatment systems will then be constructed once the Conex enclosures are
situated on the laydown pad. A Conex enclosure similar to the enclosures envisioned at
SANGB is shown in Figure 6.
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 17 Final
Figure 6 Typical Conex Enclosed TWTS
2.1.6 TWTS Electrical Service
Because of the remote location of the Recreational Pond and TWTS, no local, secondary
electrical power is readily available. Site reconnaissance has confirmed that high voltage
power (13,200 volts) is available at a nearby substation operated by SANGB. A temporary
high voltage electrical service will be installed through a combination of new and existing
spare underground raceways between the substation and the TWTS. At the TWTS area a
300 kVA, 3 phase, 460 volt, pad mounted transformer will be installed. The electrical service
will have a main fused service switch, a manual transfer switch, and all necessary secondary
distribution equipment and low voltage transformers to power the supply pump, equipment,
heat tracing, heaters, lighting, instrumentation and system controls needed to operate and
maintain the TWTS. The manual transfer switch will allow for connection of a temporary
generator to power the TWTS if an extended power outage occurs.
2.1.7 Interconnecting Process Piping
As discussed herein the TWTS will be mobilized as pre-engineered fabricated skids to reduce
construction field effort. Field fabrication and assembly of interconnecting process piping
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 18 Final
will be required. Interconnecting piping will be comprised of PVC Pipe, HDPE Pipe, and
Suction Rated Flexible Hose. All exterior piping not subject to submergence or fully
drainable will also be insulated and heat traced for freeze protection.
2.1.8 TWTS Effluent Outfall The TWTS will be able to discharge treated water to both the existing outfall and recirculate
treated effluent back to the Recreational Pond via a central return line. The treated effluent
will normally be diverted to the existing overflow weir. The 8-inch HDPE line will be a
gravity return. It will discharge treated effluent to a temporary outfall structure situated
directly upstream of the existing overflow weir. Dam Safety flow curves were prepared by
BWS and submitted to NYSDEC to document estimated hydraulic impacts to the existing
overflow weir as a result of the temporarily outfall structure. These calculations are included
in Attachment 4. NYSDEC reviewed the temporary outfall drawings and calculations and
confirmed that the proposed outfall structure hydraulic impact is within acceptable limits
and no dam safety permit would be required. The temporary outfall structure will be a pre-
cast concrete chamber, equipped with an overflow installed at the same elevation as the
existing weir. The outfall structure will dissipate energy before flowing over the existing
weir. A 3-foot wide overflow spill way will be used to convey treated water to the existing
outfall weir. The temporary structure will be designed to resist buoyant forces.
2.1.9 Weather Protection Plan
A separate Weather Protection Plan will be submitted prior to mobilization. In general the
treatment systems will be housed in an insulated/heated enclosure, designed to protect the
system from freezing. Process piping (e.g., influent suction line, effluent piping and,
interconnecting Conex enclosure process lines) that are external from the enclosures shall be
placed on ground surface, insulated and heat traced to protect against freezing. The gravity
effluent lines will be sloped to fully drain so they do not require freeze protection. If a loss
of power occurs, the PLC based control system shall be provided with an uninterruptable
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 19 Final
power supply (UPS) and configured to notify operations staff of a loss of power condition. In
addition, each enclosure should be equipped with a temperature transmitter and
automatically notify staff of a potential freezing condition. If an extended power outage
occurs during cold weather operations staff will need to either drain the system, provide
temporary heat and power to protect the system from freezing or mobilize a generator to
temporarily power the system. Additional specific weather protection details will be
submitted in a follow-up submittal.
2.1.10 TWTS System Commissioning and Start-up
After the TWTS is constructed, the treatment system be commissioned and started up in
accordance with the individual equipment O&M manuals, and the TWTS system supplier
O&M manual.
Following system commissioning, initial samples will be collected from the influent, GAC
pretreatment effluent, primary ion exchange media effluent, and overall effluent and sent to
the approved analytical laboratory for analysis of PFOS/PFOA and other applicable SPDES
parameters. After confirmation that effluent quality is acceptable, effluent will be diverted to
its normal discharge at the new outfall structure and over the existing overflow weir.
Following startup, sampling will be performed as needed to monitor system performance.
2.2 RECREATIONAL POND STORAGE
In order to reduce discharge of untreated stormwater off site, the existing Recreational Pond
will be lowered approximately 2-feet to create approximately 1.86 million gallons of storage
capacity. This stored water will allow treatment and eventual discharge as described in
Section 2.1. As previously indicated the existing Recreational Pond is approximately 2.5 acres
and the pond depth to the top of sediment is believed to range between 3 to 8.3 feet deep
with an average pond depth of approximately 5.5 feet deep. The Recreational Pond has an
average of approximately 1.8 feet of sediment in the bottom based on 2017 soundings
completed by Aqua Survey, Inc.
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 20 Final
Stormwater storage will be created by operating the TWTS and lowering the water level in
the pond. See the Stormwater Review Technical Memorandum issued 17 June 2019 included
as Attachment 5 for additional information. This storage approach does not require
modifications to the existing Recreational Pond outfall structure, which would take
significant time to evaluate and implement modifications that allow for raising the pond
level and increasing storage.
If the volume created by lowering the pond water level were determined to be insufficient or
if the estimated volumes are impacted by either increased groundwater infiltration or
sediments in the bottom of the pond, modifications to the outfall structure may be required
to increase storage by increasing the weir elevation. The modifications to the pond outfall
structure (if required) would raise the wet weather pool elevation while maintaining the dry
weather pool elevation through pumping of stored water to the TWTS. In order to evaluate
the optimal storage capacity and ensure stability of the stormwater system, a complete
geotechnical investigation and modeling of the facility-wide and of site stormwater
conveyance system would be necessary. This effort would be completed as part of the
CERCLA process and implemented, if necessary, as part of the final selected remedy. All
future modifications to the outfall structure will be coordinated by the NGB with the NY
DOT and NYNJPA, the lessee and owner of the outfall, and the NYDEC who regulates the
outfall structure.
2.2.1 Stormwater Condition Assessment
Limited stormwater condition assessments have been performed based on the minimal
stormwater flow dataset and information available for the existing stormwater system to
determine statistical returns and anticipated performance metrics for the proposed TWTS.
Since the weir outfall structure is not being substantially modified as part of the interim
mitigation a more robust analysis is not necessary at this time to support TWTS
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 21 Final
implementation. However, data collection is on-going and a more in depth analysis will be
prepared as part of the CERCLA process to determine the appropriate final remedy.
The stormwater condition assessment will be a critical component to determining the final
remedy and will determine the feasibility of temporarily retaining stormwater in the
Recreational Pond above the existing dry water elevation by constraining flow through the
existing outlet structure. Weir stability, earthen embankment stability, and pond area
stability all depend on the results and findings of the stormwater condition, and require
supporting information from a geotechnical investigation, structural investigation, and
engineering assessment to fully quantify the ability to control the system utilizing structural
modifications to the outlet structure.
The stormwater condition assessment will additionally determine up to what storm event, or
series of events, will be able to be retained in the pond without overflow of the outlet
structure. It will consider continuous withdraw from the pond to the TWTS to a specified
maximum drawdown elevation, as well as event based stormwater runoff in determining
inflow into the pond and staged elevations if modifications to the weir are determined to be
necessary.
2.2.2 Outlet Structure
The existing outlet structure consists of a trapezoidal shaped broad crested weir built into an
earthen berm with wing walls on both the upstream and downstream sides. Dry weather
flow through the weir is continuous due to suspected groundwater influence and the
combined flow from the four outfalls previously described. It is reported that these water
sources provide a near constant flow depth of less than one inch to flow over the structure as
shown in Figure 7. A rock lined channel is downstream of the outlet structure as shown in
Figure 8. As discussed, BWS will install a temporary outfall structure just upstream of the
weir. The proposed temporary outfall structure will be a pre-cast concrete chamber,
equipped with an overflow installed at the same elevation as the existing weir. The outfall
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 22 Final
structure will dissipate energy before flowing over the existing weir. A 3-foot wide overflow
spill way will be used to convey treated water to the existing outfall weir.
Figure 7 Existing Outlet Structure (Upstream)
Figure 8 Downstream of Outlet Structure
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 23 Final
2.2.3 Other Activities
As previously discussed, the TWTS is just one of several initiatives being undertaken by the Air
National Guard (ANG) to mitigate PFAS from being discharged to the Recreational Pond. Other
ANG activities not part of this current project include stormwater drainage monitoring, sampling
and modeling of PFAS contributions into the pond, and collection of data that will allow for
evaluating long term strategies to mitigate or remediate PFAS from stormwater discharges.
The results of these studies will likely be completed prior to considering potential, modifications
such as drainage infrastructure modifications, or outfall structure modifications that could
be considered to increase storage volume by raising the water level. Any further
modifications would be evaluating through the CERCLA process.
This TWTS is being installed as an interim mitigation system, in order to reduce the
contamination level in the recreational pond outfall, while the site proceeds through the
CERCLA process. The site is currently at the Site Investigation (SI) phase within the
CERCLA process. The next phase in the CERCLA process is the remedial investigation phase.
During that phase a complete CSM and risk assessment are completed. Following the
CERLCA process a feasibility study, in which remedy alternative are evaluated for
consideration, will be undertaken. After remedy evaluation, a final remedy is chosen and
will be implemented as, required under the CERCLA process, to achieve New York state
and/or federal cleanup standards once those standards are properly promulgated.
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 24 Final
(Intentionally blank)
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 25 Final
3.0 AREAS OF ENVIRONMENTAL CONCERN
The only known or suspected contamination with the work area is the PFOS and PFOA
contaminants contained in the stormwater and groundwater. The presence of this
contamination is not expected to impact construction activities.
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 26 Final
(Intentionally blank)
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 27 Final
4.0 PERMITS
The proposed work will include electrical construction, installation of TWTS, modifications
to the existing Recreational Pond outlet structure, and earth disturbance activities associated
with establishing site access and construction of the proposed features.
The NYNJPA TAA process will require design and application submittal from SANGB and a
licensed engineer in the State of New York.
4.1 ELECTRICAL
All work associated with the electrical interconnection will follow all applicable codes and
regulations, however, no permits are expected to be obtained to complete the electrical
connection. Work will be performed by licensed electricians familiar with the type of work.
4.2 SPDES PERMIT
The ANG currently holds an expired discharge permit and is coordinating the continued use
of this SPDES Permit, with the New York State Department of Environmental Conservation
(NYSDEC). The system will be operated in and monitored in accordance with the
requirements set forth in the permit. In addition to the existing SPDES permit, PFAS
compounds will be monitored as discussed in Section 2.1 of this Plan.
4.3 STORMWATER AND EARTH DISTURBANCE
Prior to excavation or earth disturbance work Dig Safely New York will be contacted to
acquire state required utility clearances. Additionally, it is expected SANGB and NYNJPA
will require dig permitting to perform all earth disturbance activities.
Although a separate Stormwater Pollution Prevention Plan and SPDES permit for discharges
related to construction activities are not required for construction sites disturbing less than
one acre, an Environmental Protection Plan (EPP) will be prepared to depict the locations
and purpose of erosion and sediment control devices as well as depict the construction
activities and site development plan.
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 28 Final
(Intentionally blank)
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 29 Final
5.0 SITE MANAGEMENT ACTIVITIES
5.1 ENVIRONMENTAL PROTECTION PLAN
The EPP will be implemented by BWS personnel and involve the installation of a stabilized
construction entrance, silt fence, and disturbance area mulch and seed. Inspection of the site
will be completed monthly and after every significant rain event. A log of site inspections,
findings, and corrective actions will be kept on site.
5.2 SPILL CONTINGENCY PLAN
The nature of the work includes the potential for the spilling of small quantities of
construction equipment related fluids and TWTS operational fluids. BWS on site personnel
and contractors will be trained in the response for construction and TWTS operation related
spills and maintain adequate spill kits containing booms, absorbent pads, and containment on
site at all times. Spills will be recorded and reported in accordance with Federal, State, and
Local requirements. A detailed spill control plan is provided in the EPP.
5.3 MANAGEMENT OF EXCAVATED SOILS
Soils will only be excavated while installing the electrical conduit to the TWTS. No
contaminated soils are expected to be encountered and no off-site disposal of soils will be
performed. Any excess soils will be placed below the TWTS gravel pad in support of leveling
off that area.
Electrical Service raceways will be bedded in sand. No trenching is anticipated to be greater
than 4-feet deep. However, if deeper trenching was required, workers will not enter an
unsupported trench deeper than 4 feet and all other applicable OSHA and HASP
requirements will be maintained.
5.4 DEWATERING
Due to the shallow groundwater condition expected at the site, dewatering of the trench
excavations is anticipated. Excavation dewatering fluids will be directed to the Recreational
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 30 Final
Pond after passing through a sedimentation device such as a filter bag or settling tank to
remove any fines or silts and discharged to the Recreational Pond in a manner that will not
cause erosion or disturb the pond sediments.
5.5 DUST CONTROL
Dust will be policed on site by maintaining stable, dust free work surfaces such as gravel pads
and adding erosion controls to areas as soon as earth disturbances are complete.
5.6 AIR MONITORING
No air monitoring is required for this mitigation activity.
5.7 SECURITY
The TWTS location is installed in a secure area but in a remote location. Access to the job
site will be controlled with locked perimeter entry gates. All TWTS Conex enclosures are
lockable and secure. No additional local security fencing or security measures are anticipated.
However, additional temporary fencing or video surveillance around the TWTS enclosures
could be provided if deemed necessary following construction.
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 31 Final
(Intentionally blank)
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 32 Final
6.0 TRAINING PROCEDURES
The TWTS Equipment Supplier (Onion Equipment Company, Inc.) is responsible for
leadings commissioning, start-up and training of the Pre-engineered TWTS. BWS personnel
will assist with commissioning, start-up and have hands-on training on system operations
and provide initial operation of the system. BWS will also perform all required system
monitoring as part of the Start-up and operations.
Hazard communication and documentation will be provided in accordance with Federal,
State, and Local requirements. All personnel entering the work areas will be provided with
site specific training and hazard communication.
Upon turnover of the TWTS, BWS will provide training to the future TWTS operator.
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 33 Final
(Intentionally blank)
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 34 Final
7.0 DOCUMENTATION AND REPORTING
A Completion Report will be prepared for the facility following completion of the final
maintenance period at that facility. The final Completion Report will contain: an executive
summary, a summary for completed work, schedule, a signed or certified statement by the
contractor that the system complied with all relevant standards during the project execution,
as-builts, warranties, certifications, testing, samples and analyses results, validation, and
points of contact for completed work.
PFOS/PFOA Mitigation Plan Stewart Air National Guard Base Contract No. W9128F-14-D-0009, DO W9128F19F0079 Bristol Project No. 34190046
September 2019 35 Final
(Intentionally blank)
ATTACHMENT 1
Site Location Map
ATTACHMENT 2
Outfall 010 – Stormwater Quality and Flow Data from DMR Records
Attachment 2 - Outfall 010 Storm water Quality and Flow Data
1 of 1
Month 2016 2017 2018January No Data 3,570,320 4,865,070 February 1,898,560 No Data No DataMarch 1,769,890 1,481,170 10,659,100 April 1,808,240 6,001,870 9,587,740 May 6,906,790 5,405,350 No DataJune No Data 5,580,890 4,696,920 July 303,598 1,411,670 3,801,720 August No Data No Data No DataSeptember 616,100 No Data 6,553,550 October 46,115 3,538,927 No DataNovember 2,191,550 No Data 4,348,690 December 1,151,190 No Data 6,139,710 Minimum 46,115 1,411,670 3,801,720 Average 1,854,670 3,855,742 6,331,563 Maximum 6,906,790 6,001,870 10,659,100 1Flow Data source - Flow Data & Outfall 010 DMR Records in PWS Attachment G
MonthBOD, 5 day
(mg/L)pH
(s.u.)Oil & Grease
(mg/L)Glycol (mg/L)
January-18 7.8 7.0 <5.2 <5March-18 21 7.4 <5 9.6
April-18 <6 7.2 <5 <5June-18 <4 7.2 <5 <5July-18 <6 7.5 <5 <5
September-18 <6 7.2 <5 <5November-18 <6 7.1 <5 <5December-18 <6 7.1 <5 <5
2Sample results - Outfall 010 DMR Records in PWS Attachment G
Date Analyte
Upstream outfall 010
RP-SW-20 (ppt)
Downstream Outfall 010 - RP-SW-21
(ppt) Average (ppt)PFOS 601 607 604PFOA 63 79 71PFOS+PFOA 664 686 675PFOS NS 322 322PFOA NS 36 36PFOS+PFOA NS 358 358
3Sample result source - Wood Environment & Infrastructure Services, Inc. Abbreviationsppt - Parts per Trillion mg/L - milligrams per liter SU - standard unit
10/18/2017
5/18/2018
Recreation Pond - PFOS & PFOA Surface Water Sample Results (3)
Estimated Maximum Daily Flow During the MonthGallons per Day (GPD) (1)
SPDES Sample Results (2)
ATTACHMENT 3
Outfall 010 Recreation Pond and Outfall 002 Storm Drain Water Quality Sample Results
Parameter Result Units Parameter Result UnitsPerfluoroheptanoic Acid (PFHpA) 35 ng/L Perfluoroheptanoic Acid (PFHpA) 36 ng/LPerfluorooctaoic Acid (PFOA) 46 ng/L Perfluorooctaoic Acid (PFOA) 50 ng/LPerfluorononanoic Acid (PFNA) 14 ng/L Perfluorononanoic Acid (PFNA) 13 ng/LPerfluorobutanesulfonic Acid (PFBS) 17 ng/L Perfluorobutanesulfonic Acid (PFBS) 11 ng/LPerfluorhexanesulfonic Acid (PFHxS) 120 ng/L Perfluorhexanesulfonic Acid (PFHxS) 94 ng/LPerfluoroocatnesulfonic Acid (PFOS) 490 ng/L Perfluoroocatnesulfonic Acid (PFOS) 380 ng/LTotal PFOA/PFOS 536 ng/L Total PFOA/PFOS 430 ng/L
TSS 1.79 J mg/LT. Alkalinity 164 mg/L Note: Current Health Advisory is 70 parts per trillion for PFOA/PFOS Bicarbonate Alk. 164 mg/L Individually or Combined.Carbonate Alk. 4.0 U mg/LBOD 3.05 mg/LO/G HEM 4.0 U mg/LBTEX No Detections NASVOCS No Detections NAGlycols No Detections NAN as No3 0.090 U mg/LP as PO4 0.30 U mg/LTOC 2.9 mg/L
BOD - Biochemical Oxygen DemandBTEX - Benzene, toluene, ethylebenzene and xylenes mg/L - milligrams per liter or parts per millionng/L - nanograms per liter or parts per trillionNO3 - NitratePO4 - PhospateSVOC - Semi-volatile Organic CompoundsTOC - Total Organic CarbonTSS - total suspended solidsA full list of SVOCs and glyclols is available on request
SANG-EFF010-04042019
Stewart ANG Sample Results
Sample Date 04/04/2019
SANG-RPOND-04042019
ATTACHMENT 4
Recreation Pond Outfall Stage Discharge Curves
23 August 2019
CALCULATION COVER SHEET
PROJECT: Stewart ANGB
WORK ORDER NO. 15254.002.037.0003
CALC NO. 1
SHEET 1 of_7__
SUBJECT: Recreation Pond – Stage Discharge Curves
DISCIPLINE (Civil, Mech. Process, Elect.): Civil
PREPARED BY: H. Nathanson DATE:08/20/2019
CALCULATION STATUS ISSUED FOR REVIEW
FINAL
CONFIRMED
SUPERCEDED
VOIDED
COMPUTER PROGRAMS USED:
Yes No DESCRIPTION/VERSION: Microsoft Excel 2013
REFERENCE SPECIFICATIONS:
REFERENCE DRAWINGS:
SOURCES OF DATA: 1. HydroCAD Software Solutions LLC. HydroCAD Stormwater Modeling System: Owner’s Manual Version 10. HydroCAD
Software Solutions LLC, 2011. 2. Weston Solutions, Inc. (August 12, 2019). Temporary Water Treatment System (TWTS) Outfall Alternatives.
SUMMARY OF RESULTS: Weston Solutions, Inc. (WESTON) performed an analysis to determine the hydraulic impacts associated with placement of a precast outfall structure against the existing weir in Recreation Pond, to facilitate a Temporary Water Treatment System (TWTS). The precast outfall would behave as a six inch (6”) tall, five foot (5’) wide obstruction on the weir crest. WESTON’S analysis of the hydraulic impacts associated with partially obstructing the existing weir in Recreation Pond indicated that the restriction will increase the stage height to achieve the same discharge flowrate as that over the unrestricted weir. WESTON estimates that the restricted weir will have an increased stage height (head) over the unrestricted weir of approximately three to four inches (3 to 4”), dependent on actual flow. For example, at a discharge rate of 500 CFS, the TWTS restricted weir indicates an increased stage height (head) over the weir of approximately three-and-a-half inches (3.5”). Based on limited available flow data, weir flows have peaked at approximately 400 CFS in response to a 1.69" rain event, with a peak precipitation rate of 1.1 in/hr. WESTON’S calculations estimate the unrestricted weir capacity is in excess of 900 CFS with a maximum height of six feet (6’) with one foot (1’) of freeboard. Based on the calculated capacity compared to the available storm response data, the increase in stage height (e.g. approximately 4”) is expected to have de minimus impacts on the performance and safety of the existing weir structure. Please note that WESTON has not been provided design data for the existing weir, and it should it be made available, WESTON may utilize this data to further evaluate the findings.
RECORD OF REVISIONS NO. REASON FOR REVISION TOTAL NO.
OF SHEETS LAST SHEET
NO. BY CHECKED APPROVED/
ACCEPTED DATE
0 Issued for Review 7 HN CS AB 8/20/19 1 Response to Comments 7 HN CS AB 8/23/19
SHEET 2 OF 7 _
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Recreation Pond – Stage Discharge Curves TASK NO 0003 .
PREPARED BY H. Nathanson DEPT 2118 DATE 8/19/2019 . APPROVED BY
MATH CHECK BY C. Sembera DEPT 2118 DATE 8/19/2019 .
METHOD REV. BY A. Brown DEPT 2118 DATE 8/20/2019 .DEPT_ DATE_
File Name: 2-Stewart_ANGB_Rec_Pond_Stage Discharge Curve.docx Print date: 08/23/19 11:19 AM
Objective:
Determine the increase in relative stage height associated with placement of a precast outfall structure
against the existing weir in Recreation Pond, in conjunction with a temporary water treatment system
(TWTS).
References:
HydroCAD Software Solutions LLC. HydroCAD Stormwater Modeling System: Owner’s Manual Version 10. HydroCAD Software Solutions LLC, 2011.
Weston Solutions, Inc. (August 12, 2019). Temporary Water Treatment System (TWTS) Outfall Alternatives.
Attachments:
Attachment A – Stage Discharge Curve Temporary Water Treatment System Outfall Alternative 1.
Attachment B – Sheet C-5: Outfall Structure Plans and Sections.
SHEET 3 OF 7 _
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Recreation Pond – Stage Discharge Curves TASK NO 0003 .
PREPARED BY H. Nathanson DEPT 2118 DATE 8/19/2019 . APPROVED BY
MATH CHECK BY C. Sembera DEPT 2118 DATE 8/19/2019 .
METHOD REV. BY A. Brown DEPT 2118 DATE 8/20/2019 .DEPT_ DATE_
File Name: 2-Stewart_ANGB_Rec_Pond_Stage Discharge Curve.docx Print date: 08/23/19 11:19 AM
Assumptions:
• The weir is asymmetrical, and therefore divided into rectangular and half-v sections, which are
then summed, to determine the flow through the weir.
• A half-v weir is equivalent to half of a triangular or v-notch weir.
• The base of the existing weir is 15.5 feet long, and comprised of rectangles and right triangles.
• The existing weir has one foot (1’) of freeboard, and flows will not exceed a stage height over six
feet (6’) above the weir.
• A weir coefficient value of 2.95 corresponds to the rectangular portions of the weir.
• A weir coefficient value of 0.593 corresponds to the half-v portions of the weir, and represents a
90 degree angle.
• Approach velocity is negligible.
• The precast outfall partially blocks the weir and is expected to behave as a six inch (6”) tall, five
foot (5’) wide obstruction on the weir crest.
Discussion:
Weston Solutions, Inc. (WESTON) performed an analysis to determine the hydraulic impacts associated
with placement of a precast outfall structure against the existing weir in Recreation Pond to facilitate the
TWTS. The precast structure would extend five feet (5’) along the length and six inches (6”) above the
existing weir crest (Attachment B). The analysis compared the flows over the existing unrestricted weir to
those over an obstructed weir to determine the difference in head at varying stage levels.
Analysis:
Adding a partial obstruction to the existing weir would result in an asymmetrical weir; therefore flows
over the weir were calculated by dividing the opening into rectangular and half-v sections (HydroCAD
Software Solutions LLC, page 93). This methodology was utilized for both the unrestricted and TWTS
restricted weir for consistency in comparison. Figure 1 below shows the divided cross-sections of either
scenario, in which V represents a half-v weir and R designates a rectangular weir.
SHEET 4 OF 7 _
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Recreation Pond – Stage Discharge Curves TASK NO 0003 .
PREPARED BY H. Nathanson DEPT 2118 DATE 8/19/2019 . APPROVED BY
MATH CHECK BY C. Sembera DEPT 2118 DATE 8/19/2019 .
METHOD REV. BY A. Brown DEPT 2118 DATE 8/20/2019 .DEPT_ DATE_
File Name: 2-Stewart_ANGB_Rec_Pond_Stage Discharge Curve.docx Print date: 08/23/19 11:19 AM
Figure 1 - Cross-sections of Asymmetrical Weirs
The total flow (QT) over the weir, in cubic feet per second (cfs), is represented by the summation of flows
over each divided section, as designated in Equation 1:
Equation 1:
𝑄𝑄𝑇𝑇 = ∑𝑄𝑄𝑉𝑉𝑉𝑉 + 𝑄𝑄𝑅𝑅𝑉𝑉
The flow for a triangular weir and rectangular weir are calculated by Equation 2 and Equation 3,
respectfully.
Equation 2:
𝑄𝑄𝑉𝑉 =12𝐶𝐶1 �
815
tan𝜃𝜃2�
(𝐻𝐻5 2⁄ )�2𝑔𝑔 Equation 3:
𝑄𝑄𝑅𝑅 = 𝐶𝐶2𝑏𝑏𝐻𝐻32�
Where:
• C1 = Triangular weir coefficient; 0.593 for 90° • H = water surface elevation upstream of weir crest (ft) • g = gravitational constant (32.2 ft/sec) • b = weir length (ft) • C2 = Rectangular weir coefficient; 2.95 average
These equations were applied to each cross-sectional weir area to obtain a flow, which was summed for
various stage heights above the weir crest (H).
SHEET 5 OF 7 _
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Recreation Pond – Stage Discharge Curves TASK NO 0003 .
PREPARED BY H. Nathanson DEPT 2118 DATE 8/19/2019 . APPROVED BY
MATH CHECK BY C. Sembera DEPT 2118 DATE 8/19/2019 .
METHOD REV. BY A. Brown DEPT 2118 DATE 8/20/2019 .DEPT_ DATE_
File Name: 2-Stewart_ANGB_Rec_Pond_Stage Discharge Curve.docx Print date: 08/23/19 11:19 AM
For the unrestricted weir, total flow is calculated using:
𝑄𝑄𝑉𝑉1 =12
(0.593) �8
15tan
1.572 � (𝐻𝐻5 2⁄ )�2(32.3)
𝑄𝑄𝑅𝑅1 = (2.95)(15.5′)𝐻𝐻32�
𝑄𝑄𝑇𝑇 = 2𝑄𝑄𝑉𝑉1 + 𝑄𝑄𝑅𝑅1
For the TWTS restricted weir, total flow is calculated using:
𝑄𝑄𝑉𝑉1 =12
(0.593) �8
15tan
1.572 � (𝐻𝐻5 2⁄ )�2(32.3)
𝑄𝑄𝑅𝑅1 = (2.95)(15.5′ − 5′)𝐻𝐻32�
𝑄𝑄𝑉𝑉2 = 12
(0.593) � 815
tan 1.572� (𝐻𝐻 − 0.5)5 2⁄ �2(32.3) for values of H above six inches (6”)1
𝑄𝑄𝑅𝑅2 = (2.95)(5′)(𝐻𝐻 − 0.5)3 2� for values of H above six inches (6”)1
𝑄𝑄𝑇𝑇 = 𝑄𝑄𝑉𝑉1 + 𝑄𝑄𝑅𝑅1 + 𝑄𝑄𝑅𝑅2 + 𝑄𝑄𝑉𝑉2
The resultant stage discharge curves for both scenarios are depicted in Figure 2.
1 Flow is obstructed in this portion of the weir until the stage height exceeds six inches (6”). Therefore the stage height above these potions of the weir is equivalent to the original stage height less six inches (6”).
SHEET 6 OF 7 _
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Recreation Pond – Stage Discharge Curves TASK NO 0003 .
PREPARED BY H. Nathanson DEPT 2118 DATE 8/19/2019 . APPROVED BY
MATH CHECK BY C. Sembera DEPT 2118 DATE 8/19/2019 .
METHOD REV. BY A. Brown DEPT 2118 DATE 8/20/2019 .DEPT_ DATE_
File Name: 2-Stewart_ANGB_Rec_Pond_Stage Discharge Curve.docx Print date: 08/23/19 11:19 AM
Figure 2 - Stage Discharge Curves for the Unrestricted Weir and TWTS Restricted Weir
Conclusion:
WESTON’S analysis of the hydraulic impacts associated with partially obstructing the existing weir in
Recreation Pond indicated that the restriction will increase the stage height to achieve the same discharge
flowrate as that over the unrestricted weir. WESTON estimates that the restricted weir will have an
increased stage height (head) over the unrestricted weir of approximately three to four inches (3 to 4”),
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
5.5
6
0 100 200 300 400 500 600 700 800 900 1000
Stag
e He
ight
(fee
t)
Discharge (cfs)
Unrestricted Weir TWTS Restricted Weir
SHEET 7 OF 7 _
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Recreation Pond – Stage Discharge Curves TASK NO 0003 .
PREPARED BY H. Nathanson DEPT 2118 DATE 8/19/2019 . APPROVED BY
MATH CHECK BY C. Sembera DEPT 2118 DATE 8/19/2019 .
METHOD REV. BY A. Brown DEPT 2118 DATE 8/20/2019 .DEPT_ DATE_
File Name: 2-Stewart_ANGB_Rec_Pond_Stage Discharge Curve.docx Print date: 08/23/19 11:19 AM
dependent on actual flow. For example, at a discharge rate of 500 CFS, the TWTS restricted weir
indicates an increased stage height (head) over the weir of approximately three-and-a-half inches (3.5”).
Based on limited available flow data we have reviewed from the fall of 2017, WESTON understands that
weir flows have peaked at approximately 400 CFS in response to a 1.69" rain event, with a peak
precipitation rate of 1.1 in/hr, (i.e. an intense storm event). WESTON’S calculations estimate the
unrestricted weir capacity is in excess of 900 CFS with a maximum height of six feet (6’) with one foot
(1’) of freeboard. Based on the calculated capacity compared to the available storm response data, the
increase in stage height (e.g. approximately 4”) is expected to have de minimus impacts on the
performance and safety of the existing weir structure.
WESTON has not been provided design data for the existing weir. Should NYDEC or the Dam Safety
Section provide applicable information for the existing weir, WESTON may utilize this data to further
evaluate the findings.
Limitations:
Conclusions stated or referenced in this analysis are limited by several assumptions made. WESTON has
not been provided design data for the existing weir. The weir data utilized was based on field
measurements and assumes that the weir is consistently leveled and sloped; any variations in the
construction of the weir were not accounted for. The weir coefficients selected represent average values,
and actual conditions may vary.
The representation of the stage discharge curve is for comparison purposes only and does not take in to
account, among other parameters, tail water, velocity, and bed slope conditions.
ATTACHMENT A
WEIR STAGE CALCULATIONS
QV1
QR1
QT
C1 0.593
Ɵ 1.570796 radians (90 degrees)
g 32.2 ft/sec
b 15.5 ft
C2 2.95
Water Surface
Elevation (H) ft 2*QV1 QR1 QT
0 0 0 0
0.1 0.008026 1.445951 1.45397741
0.2 0.045402 4.089768 4.13516995
0.3 0.125112 7.513384 7.63849633
0.4 0.25683 11.56761 11.824442
0.5 0.448664 16.16623 16.6148929
0.6 0.707741 21.25106 21.9588008
0.7 1.040498 26.7794 27.8198943
0.8 1.452852 32.71815 34.1709985
0.9 1.950305 39.04069 40.9909948
1 2.538028 45.725 48.2630277
1.1 3.220906 52.75246 55.9733692
1.2 4.003589 60.10707 64.1106623
1.3 4.890517 67.77488 72.6653943
1.4 5.885948 75.74357 81.6295178
1.5 6.993982 84.00219 90.9961707
1.6 8.218571 92.54089 100.759464
1.7 9.56354 101.3508 110.91432
1.8 11.03259 110.4237 121.456338
1.9 12.62933 119.7524 132.381701
2 14.35725 129.3298 143.687083
2.1 16.21977 139.1498 155.369589
2.2 18.2202 149.2065 167.426694
2.3 20.36179 159.4944 179.8562
2.4 22.64772 170.0085 192.656196
1/2 of a v‐notch weir
Sharp Crested ‐ assumed approach
velocity negligable
=QV1+QR1+QR2+QV2
Unrestricted Weir Flow Calculations
Water Surface
Elevation (H) ft 2*QV1 QR1 QT
Unrestricted Weir Flow Calculations
2.5 25.08109 180.7439 205.825021
2.6 27.66494 191.6963 219.361242
2.7 30.40225 202.8614 233.263626
2.8 33.29595 214.2352 247.531118
2.9 36.34891 225.8139 262.162827
3 39.56394 237.5941 277.158006
3.1 42.94381 249.5722 292.516039
3.2 46.49126 261.7452 308.236431
3.3 50.20896 274.1098 324.318796
3.4 54.09955 286.6633 340.762845
3.5 58.16563 299.4027 357.568381
3.6 62.40977 312.3255 374.735289
3.7 66.83449 325.429 392.263531
3.8 71.44229 338.7109 410.153137
3.9 76.23561 352.1686 428.404204
4 81.21689 365.8 447.016886
4.1 86.38851 379.6029 465.991393
4.2 91.75285 393.5751 485.327986
4.3 97.31225 407.7147 505.026971
4.4 103.069 422.0197 525.0887
4.5 109.0254 436.4882 545.513565
4.6 115.1837 451.1183 566.301993
4.7 121.5461 465.9084 587.45445
4.8 128.1148 480.8566 608.971431
4.9 134.8921 495.9614 630.853463
5 141.8801 511.221 653.101102
5.1 149.0808 526.6341 675.71493
5.2 156.4965 542.199 698.695552
5.3 164.1293 557.9143 722.043599
5.4 171.9811 573.7786 745.759722
5.5 180.0541 589.7905 769.844593
5.6 188.3503 605.9486 794.298902
5.7 196.8718 622.2516 819.123357
5.8 205.6205 638.6982 844.318684
5.9 214.5984 655.2873 869.885623
6 223.8074 672.0175 895.824931
QV1
QV2
QR1
QR2
QT
C1 0.593
Ɵ 1.570796 radians (90 degrees)
g 32.2 ft/sec
b1 15.5 ft
b2 5 ft
C2 2.95
Water Surface
Elevation (H) ft QV1 QR1 QR2 QV2 QT
0 0 0 0 0 0
0.1 0.004013 0.979516 0 0 0.983528
0.2 0.022701 2.770488 0 0 2.793189
0.3 0.062556 5.089712 0 0 5.152268
0.4 0.128415 7.836124 0 0 7.964539
0.5 0.224332 10.95132 0 0 11.17565
0.6 0.353871 14.39588 0.466436 0.004013 15.2202
0.7 0.520249 18.14088 1.31928 0.022701 20.00311
0.8 0.726426 22.16391 2.423672 0.062556 25.37656
0.9 0.975153 26.44692 3.731488 0.128415 31.28197
1 1.269014 30.975 5.214913 0.224332 37.68326
1.1 1.610453 35.73554 6.855181 0.353871 44.55504
1.2 2.001794 40.71769 8.638515 0.520249 51.87825
1.3 2.445258 45.91201 10.55424 0.726426 59.63794
1.4 2.942974 51.31016 12.59377 0.975153 67.82206
1.5 3.496991 56.90471 14.75 1.269014 76.42071
1.6 4.109286 62.68899 17.01692 1.610453 85.42565
1.7 4.78177 68.65698 19.38938 2.001794 94.82992
1.8 5.516297 74.80318 21.86286 2.445258 104.6276
TWTS Restricted Weir Flow Calculations
1/2 of a v‐notch weir
1/2 of a v‐notch weir (Partially Obstructed)
Sharp Crested ‐ assumed approach velocity negligable
Sharp Crested ‐ assumed approach velocity negligable
(Partially Obstructed)
=QV1+QR1+QR2+QV2
Water Surface
Elevation (H) ft QV1 QR1 QR2 QV2 QT
TWTS Restricted Weir Flow Calculations
1.9 6.314666 81.12257 24.43341 2.942974 114.8136
2 7.178626 87.61053 27.09748 3.496991 125.3836
2.1 8.109883 94.26278 29.8519 4.109286 136.3339
2.2 9.110098 101.0754 32.6938 4.78177 147.661
2.3 10.18089 108.0446 35.62056 5.516297 159.3624
2.4 11.32386 115.167 38.6298 6.314666 171.4354
2.5 12.54054 122.4394 41.7193 7.178626 183.8779
2.6 13.83247 129.8588 44.88704 8.109883 196.6882
2.7 15.20113 137.4222 48.13113 9.110098 209.8646
2.8 16.64798 145.127 51.44981 10.18089 223.4057
2.9 18.17445 152.9707 54.84144 11.32386 237.3105
3 19.78197 160.9508 58.30449 12.54054 251.5778
3.1 21.47191 169.0651 61.83752 13.83247 266.2069
3.2 23.24563 177.3112 65.43915 15.20113 281.1972
3.3 25.10448 185.6873 69.10812 16.64798 296.5479
3.4 27.04977 194.1913 72.8432 18.17445 312.2587
3.5 29.08282 202.8212 76.64325 19.78197 328.3292
3.6 31.20489 211.5753 80.50717 21.47191 344.7593
3.7 33.41725 220.4519 84.43393 23.24563 361.5487
3.8 35.72114 229.4493 88.42253 25.10448 378.6974
3.9 38.1178 238.5658 92.47203 27.04977 396.2054
4 40.60844 247.8 96.58153 29.08282 414.0728
4.1 43.19426 257.1503 100.7502 31.20489 432.2996
4.2 45.87643 266.6154 104.9771 33.41725 450.8862
4.3 48.65612 276.1938 109.2616 35.72114 469.8327
4.4 51.5345 285.8843 113.6028 38.1178 489.1394
4.5 54.51269 295.6855 118 40.60844 508.8067
4.6 57.59184 305.5963 122.4525 43.19426 528.8349
4.7 60.77305 315.6153 126.9597 45.87643 549.2245
4.8 64.05742 325.7416 131.5209 48.65612 569.976
4.9 67.44606 335.9738 136.1354 51.5345 591.0898
5 70.94003 346.311 140.8026 54.51269 612.5664
5.1 74.54041 356.7521 145.522 57.59184 634.4064
5.2 78.24827 367.2961 150.293 60.77305 656.6104
5.3 82.06463 377.942 155.115 64.05742 679.1791
5.4 85.99056 388.6887 159.9875 67.44606 702.1129
5.5 90.02706 399.5355 164.91 70.94003 725.4126
5.6 94.17517 410.4813 169.882 74.54041 749.0788
5.7 98.4359 421.5253 174.9029 78.24827 773.1123
5.8 102.8102 432.6665 179.9724 82.06463 797.5138
5.9 107.2992 443.9043 185.0899 85.99056 822.2839
6 111.9037 455.2377 190.255 90.02706 847.4234
ATTACHMENT B
SHEET C-5: OUTFALL STRUCTURE PLANS AND SECTIONS
PROGRESS PRINT
ATTACHMENT 5
Stormwater Review Technical Memorandum 17 June 2019
Technical Memo - Stormwater Review and Analysis - Final - Stormwater Review and
Analysis Page 1 of 4
June 17, 2019
TECHNICAL MEMORANDUM
TO: Michelle Lordemann, Project Manager, USACE
Cc: PFOS/PFOA Interim Mitigation Project Delivery Team Members
From: Adam Brown, P.E Date: June 17, 2019
NY License No. 097396
RE: PFOS/PFOA Interim Mitigation Project
Stormwater Review and Analysis
INTRODUCTION
Weston Solutions, Inc. (WESTON) has reviewed and analyzed available stormwater and survey data for
the Recreation Pond, including draft and progress datasets provided by the John Wood Group (Wood), to
better characterize the Pond’s response to storm events and determine its ability to be utilized for storing
stormwater runoff for treatment prior to discharge. The project Performance Work Statement defines the
objective of these analyses stating, “Measures are to be implemented to limit overflow during storm events,”
which can be achieved by, “…raising the height of the outfall weir structure, approximately three feet.”
This Technical Memorandum is supported by two calculation packages that analyze both the stormwater
flows experienced by Recreation Pond and the Pond’s storage capacity, and are and included as the
following attachments:
Attachment A - Recreation Pond Water Retention Analysis
Attachment B - Pond Storage Volume Analysis
BOTTOM LINE UP FRONT
WESTON recommends artificially reducing the pond elevation by two feet, and maintaining this elevation
between storm events through artificial drawdown via pumping stormwater to the treatment plant for
discharge. WESTON does not recommend making modifications to the weir at this time. WESTON
considered the following facts, either determined by our analysis or presentation by others, in our review:
PFOS/PFOA Interim Mitigation Project
Stormwater Review and Analysis
Technical Memo - Stormwater Review and Analysis -
Final Page 2 of 4
June 7, 2019
1. There are roughly five-million gallons of water storage within the pond below the existing weir
elevation, without dredging sediment.
2. Raising the weir discharge elevation or drawing down the Pond will result in the additional storage
of approximately one-million gallons of storage per foot raised or lowered. Therefore, a three foot
increase in weir elevation would result in roughly three-million gallons of additional storage in
Recreation Pond.
3. A total flow volume of three-million gallons equates to a 0.44 inch rainfall event in the Pond’s
drainage area. For approximately every 0.13 inches of rainfall, one-million gallons of runoff can
be expected, after considering an initial depression storage of 0.05 inches.
4. Two feet of draw-down should result in approximately 1.86 million gallons of additional storage,
without requiring modifications to the existing weir.
5. During a 24-hour period, the proposed treatment plant is preliminarily designed to withdraw
approximately 720,000 gallons of water from the Pond, treat it, and ultimately discharge it to the
downstream watercourses beyond the weir.
6. A majority of the Pond’s water surface area will remain with up to three feet of drawdown.
Drawdown beyond that will cause areas of the Pond to become dry.
7. The Pond depth, away from the shoreline, ranges from 3.0 to 8.3 feet deep, as measured from the
weir to the top of soft sediments on the Pond’s bottom.
ANALYSIS DISCUSSION
A full discussion of each analysis and its sources of data are presented in the two aforementioned
attachments. A high level summary of these analyses is discussed below.
The storm analysis and relationships developed in Attachment A demonstrated that no extreme storm events
were experienced within the Pond’s drainage area during the approximate two month period of previously
monitored data. The largest event experienced during the period of monitoring consisted of 1.7 inches over
a period of four hours. This modest storm event resulted in the production of 13-million gallons of
stormwater flow to Recreation Pond, over a course of 48 hours, before returning to base-flow rates. A
relationship developed as part of this analysis determined that the difference between two-million and three-
million gallons stormwater flow is only the difference between a 0.31 inch and 0.44 inch storm event,
respectively.
Attachment 2 determined that roughly six-million gallons of water storage could be available within the
Recreation Pond if it were to be dredged of its soft sediments. The dredging or excavation of loose
sediments introduces challenges associated with habitat destruction, sedimentation, erosion, and increasing
hydrodynamic forces on the inlet pipes. Furthermore, any alteration of the Pond’s elevation that would
PFOS/PFOA Interim Mitigation Project
Stormwater Review and Analysis
Technical Memo - Stormwater Review and Analysis -
Final Page 3 of 4
June 7, 2019
result in reducing the tail water depth of the inlet pipes to less than six inches would require additional
armament, and energy dissipation devices, to avoid advanced scour and redeposition of the Pond’s
sediments. This potential exists both within the Recreation Pond, and in the case of changing Pond outlet
dynamics, in the downstream waterbodies. The analysis also established that the Pond water elevation could
be lowered by slightly less than three feet before significant portions of the Pond would be rendered dry.
However, lowering the Pond by this quantity would expose the inlet pipe at the outfalls, and would require
additional stabilization.
A reduction of Pond’s dry water depth by two feet is not expected to have significant impacts on
sedimentation and erosion in the Pond. This reduction is expected to result in an additional storage volume
of 1.86 million gallons. This storage volume, coupled with the a 500 gallon per minute pumping rate to the
treatment plant, is equivalent to a 0.4 inch storm event within a 24-hour period, without the need for
operational contingencies or monitoring of the weir structure. This strategy provides nearly the same 24-
period storage capacity as raising the weir structure by three feet without artificial drawdown or pumping.
PFOS/PFOA Interim Mitigation Project
Stormwater Review and Analysis
Technical Memo - Stormwater Review and Analysis - Final - Stormwater Review and
Analysis Page 4 of 4
June 17, 2019
RECOMMENDATION
From the established relationship between rainfall and stormwater flow to Recreation Pond, it is apparent
that creating a storage feature at the confluence of this large drainage area will require daily weather
monitoring and operation. A failure in management, unexpectedly large storm event, or human error could
result in overtopping of any weir modifications made to raise the dry-weather Pond elevation, and
potentially the berm itself, with the potential consequence for a catastrophic collapse of both. Given the
magnitudes of unknowns and diminishing returns with regards to storm event protection, modifications to
the weir structure are not recommended without a more in depth analysis and monitoring of the drainage
area. Prior to making modifications, it is highly recommended that a storm response model, calibrated to
actual events, be generated to predict potential exceedances of storage capacity.
Reducing the dry weather pond elevation by two feet, via drawdown, is therefore recommended.
LIMITATIONS
Analysis limitations to this technical memo are discussed in more detail within each of the attachments.
The overarching concept is that there is a limited dataset available for the basis of this recommendation.
Due to this, a somewhat conservative approach was made to maintain a stable environment within the Pond,
as well as prevent detrimental impacts to the berm and/or weir structure. As more information is made
available, and observations are made in the field, a more aggressive approach may be determined, if it
should be deemed necessary.
Attachments:
Attachment A - Recreation Pond Water Retention Analysis
Attachment B - Pond Storage Volume Analysis
ATTACHMENT A
CALCULATION COVER SHEET
PROJECT: Stewart ANGB
WORK ORDER NO. 15254.002.037.0003
CALC NO.
1 SHEET 1 of_7__
SUBJECT: Recreation Pond – Precipitation vs. Volume Analysis
DISCIPLINE (Civil, Mech. Process, Elect.): Civil
PREPARED BY: M. Mardenov DATE:06/17/19
CALCULATION STATUS ISSUED FOR REVIEW
FINAL
CONFIRMED
SUPERCEDED
VOIDED
COMPUTER PROGRAMS USED:
Yes No DESCRIPTION/VERSION: PCSWMM 7.2
REFERENCE SPECIFICATIONS:
REFERENCE DRAWINGS:
SOURCES OF DATA:
1. HDR, Inc. (November 17, 2017). Melissa E. LaMacchia to Tony Palumbo. New York Air National Guard Base, Stewart International Airport, Newburgh, Orange County, New York, Recreation Pond Pre-Design Investigation [Letter].
2. John Wood Group, PLC (October 29, 2018). Preliminary Estimate of Rec Pond Base Flow and Storm Flow Treatment Stewart Air National Guard Base, Newburgh, Orange County, New York [Draft Memorandum].
3. John Wood Group, PLC (May 21, 2019). Rich Niles to Adam Brown. Rec Pond Flow Data [Email]. 4. New York State Department of Environmental Conservation (January 2015). New York State Stormwater
Management Design Manual. Albany, NY. Retrieved from https://www.dec.ny.gov/docs/water_pdf/swdm2015entire.pdf 5. PCSWMM Professional 2D, Version 7.2.
SUMMARY OF RESULTS:
Weston evaluated the data collected by HDR, developed a linear relationship and yielded a storm depth of 0.44 inches that can be retained within a 3.0 million gallon storage volume. WESTON also determined a water quality volume for Outfalls 02, 03, 14 per the requirements of the New York State Stormwater Manual. This water quality volume was compared to the observed flow and precipitation data collected by HDR on August 2nd, 2017, to determine an estimate for discharge associated with the unknown watershed contributing to Outfall 17K.
RECORD OF REVISIONS
NO. REASON FOR REVISION TOTAL NO. OF SHEETS
LAST SHEET NO.
BY CHECKED APPROVED/ ACCEPTED
DATE
0 Issued for Review 7 MM DB AB 6/07/2019
1 Final 7 AB HN AB 6/17/2019
SHEET 2 OF 7 _
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Recreation Pond – Precipitation vs. Volume Analysis TASK NO 0003 .
PREPARED BY M. Mardenov DEPT 2118 DATE 6/07/2019 . APPROVED BY
MATH CHECK BY D. Borger DEPT 2118 DATE 6/07/2019 .
METHOD REV. BY D. Borger DEPT 2118 DATE 6/07/2019 .DEPT_ DATE_
File Name: 2-Stewart_ANGB_Rec_Pond_Volume_Evaluation_Rev5_mm Print date: 06/17/19 11:24 PM
Objective:
Determine the relationship between stormwater discharge to Recreation Pond and rainfall event total
precipitation quantities. Additionally quantify storage requirements for runoff dictated by The New York
Department of Environmental Conservation.
References:
HDR, Inc. (November 17, 2017). Melissa E. LaMacchia to Tony Palumbo. New York Air National Guard
Base, Stewart International Airport, Newburgh, Orange County, New York, Recreation Pond Pre-
Design Investigation [Letter].
John Wood Group, PLC (October 29, 2018). Preliminary Estimate of Rec Pond Base Flow and Storm
Flow Treatment Stewart Air National Guard Base, Newburgh, Orange County, New York [Draft
Memorandum].
John Wood Group, PLC (May 21, 2019). Rich Niles to Adam Brown. Rec Pond Flow Data [Email].
New York State Department of Environmental Conservation (January 2015). New York State Stormwater
Management Design Manual. Albany, NY. Retrieved from
https://www.dec.ny.gov/docs/water_pdf/swdm2015entire.pdf
PCSWMM Professional 2D, Version 7.2.
Attachments:
Attachment A – Site Layout
Attachment B – PCSWMM Drainage Area Measurements
Assumptions:
The stormwater discharge flow is the summation of metered flow from Outfalls 02, 03, 14, and
17K. Additional flow from local contributors is considered negligible.
The stormwater flows were assumed to begin at the start of a precipitation event and end when the
last outfall (typically Outfall 17K) ceased discharging into Recreation Pond.
SHEET 3 OF 7 _
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Recreation Pond – Precipitation vs. Volume Analysis TASK NO 0003 .
PREPARED BY M. Mardenov DEPT 2118 DATE 6/07/2019 . APPROVED BY
MATH CHECK BY D. Borger DEPT 2118 DATE 6/07/2019 .
METHOD REV. BY D. Borger DEPT 2118 DATE 6/07/2019 .DEPT_ DATE_
File Name: 2-Stewart_ANGB_Rec_Pond_Volume_Evaluation_Rev5_mm Print date: 06/17/19 11:24 PM
The calculated volumes do not include inflow associated from groundwater that may enter
Recreation Pond.
Inflow and infiltration from other sources in the collection system are included in the metered flow
data.
Linear relationship exists between precipitation depth and stormwater runoff volume for storms
events.
Discussion:
Weston Solutions, Inc. (Weston) performed an analysis to determine the relationship between stormwater
discharge and rainfall events. The analysis utilized metered flow data obtained from outfalls that
discharge to Recreation Pond (Outfalls 02, 03, 14, and 17K), and recorded precipitation depths, collected
during a previous study completed by HDR, Inc. (HDR, 2017). Weston generated a linear relationship
between the total summed outfall discharges produced from their respective storm events, from the data
collected during seven recorded storm events during the HDR study. The precipitation values were plotted
against the summation of the metered stormwater discharge volumes entering Recreation Pond (for
Outfalls 02, 03, 14, and 17K), for which the results are indicated in Figure 1.
This information was compared to a draft memorandum, dated October 29th, 2018 and prepared by the
John Wood Group, PLC (Wood, 2018), which also developed a ratio of outfall runoff volume per depth of
rainfall. However, this memorandum only utilized the data from two storm events (9/2/2017 and
9/6/2017), so the results differ slightly. Weston’s analysis described herein is an attempt to develop a
linear relationship using all of the observed precipitation and flow data collected by HDR, Inc. (HDR,
2017).
Weston also evaluated the Water Quality Volume (WQv) for the site. A WQv is a New York State
Department of Environmental Conservation ([NYSDEC], 2015) defined storage requirement intended to
SHEET 4 OF 7 _
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Recreation Pond – Precipitation vs. Volume Analysis TASK NO 0003 .
PREPARED BY M. Mardenov DEPT 2118 DATE 6/07/2019 . APPROVED BY
MATH CHECK BY D. Borger DEPT 2118 DATE 6/07/2019 .
METHOD REV. BY D. Borger DEPT 2118 DATE 6/07/2019 .DEPT_ DATE_
File Name: 2-Stewart_ANGB_Rec_Pond_Volume_Evaluation_Rev5_mm Print date: 06/17/19 11:24 PM
identify the storage volume necessary to capture and treat runoff from 90 percent of the average annual
rainfall events that are to be expected to fall on the site. Weston calculated this value to provide a frame of
reference to the evaluated storms and established relationship.
The WQv was calculated for areas contributing to Outfalls 02, 03, and 14 based on aerial photography of
the contributing areas. Outfall 17K was not included in this calculation due to the unknown
characteristics, location, and size of the watershed contributing to this outfall. Instead, a ratio was
developed between the cumulative summed volumes of Outfalls 02, 03, and 14, and the cumulative
volume of Outfall 17K alone. The total WQv estimated from the cumulative discharge sum from Outfalls
02, 03, 14 and 17K was then determined.
Analysis:
The precipitation depths from the seven recorded storm events and their associated stormwater runoff
flow volumes from Outfalls 02, 03, 14 and 17K were plotted against one another. The results
demonstrated that a linear relationship was the best fit for the comparison of precipitation and summed
outfall discharge volumes (Figure 1 – Linear Relationship), and a trend line equation was developed using
Microsoft Excel’s best fit algorithms. A y-intercept of 0.05 inches was assigned to the equation to
represent depression storage within the watershed.
SHEET 5 OF 7 _
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Recreation Pond – Precipitation vs. Volume Analysis TASK NO 0003 .
PREPARED BY M. Mardenov DEPT 2118 DATE 6/07/2019 . APPROVED BY
MATH CHECK BY D. Borger DEPT 2118 DATE 6/07/2019 .
METHOD REV. BY D. Borger DEPT 2118 DATE 6/07/2019 .DEPT_ DATE_
File Name: 2-Stewart_ANGB_Rec_Pond_Volume_Evaluation_Rev5_mm Print date: 06/17/19 11:24 PM
Figure 1 Linear Relationship
Utilizing this linear relationship, a storm precipitation depth can be calculated from a corresponding
stormwater volume that would discharge to Recreation Pond. Equation 1 (below) yields the total
precipitation determined from the linear regression equations of Figure 1.
An example below demonstrates that a given three MG discharge volume corresponds to a precipitation
depth of 0.44 inches as determined by the linear relationship.
Equation 1:
𝑦 = (1.3093 ∗ 10−7)𝑥 + 0.05
𝑦 = (1.3093 ∗ 10−7) ∗ (3,000,000 𝑔𝑎𝑙𝑙𝑜𝑛𝑠) + 0.05
𝑦 = 0.44 𝑖𝑛𝑐ℎ𝑒𝑠
Where:
y = the precipitation depth in inches.
x = the discharge volume in gallons.
The following equation (Equation 2) calculates the aforementioned WQv. This calculated WQv accounts
for runoff from Outfalls 02, 03, and 14. As previously discussed, Outfall 17K and the associated
y = 1E-07x + 0.05R² = 0.959
0
0.5
1
1.5
2
2.5
Pre
cip
itat
ion
(in
ches
)
Discharge Volume (gallons)
Linear Relationship
SHEET 6 OF 7 _
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Recreation Pond – Precipitation vs. Volume Analysis TASK NO 0003 .
PREPARED BY M. Mardenov DEPT 2118 DATE 6/07/2019 . APPROVED BY
MATH CHECK BY D. Borger DEPT 2118 DATE 6/07/2019 .
METHOD REV. BY D. Borger DEPT 2118 DATE 6/07/2019 .DEPT_ DATE_
File Name: 2-Stewart_ANGB_Rec_Pond_Volume_Evaluation_Rev5_mm Print date: 06/17/19 11:24 PM
watershed was excluded from the Equation 2 calculation, due to the unknown characteristics of the
watershed.
Equation 2:
𝑊𝑄𝑣 = 𝑃 ∗ (0.05 + 0.009(𝐼)) ∗ 𝐴
12
𝑊𝑄𝑣 =(1.4 𝑖𝑛𝑐ℎ𝑒𝑠) ∗ (0.05 + 0.009(70.2 %)) ∗ (509.4 𝑎𝑐𝑟𝑒𝑠)
12
𝑊𝑄𝑣 = 40.5 acre-feet
𝑊𝑄𝑣 = 13.2 𝑀𝐺
Where:
P = the 90 percent rainfall event number from Figure 4.1 of the NYS SWDM in inches.
A = the contributing area in acres that was measured from Attachment A – Site Layout as well as
from measurements based on aerial imagery made in PCSWMM from Attachment B – PCSWMM
Drainage Area Measurements.
I = the percent impervious cover that was measured in PCSWMM.
Weston further evaluated the metered flow data to determine what portion of the total inflow to
Recreation Pond was from Outfall 17K to estimate the WQv for all four outfalls, rather than the three (3)
discussed above. Adding the observed stormwater volumes from Outfall 17K and comparing them to
Outfalls 02, 03, and 14, results in a total stormwater volume percent increase between 50 to 70 percent.
When this ratio is added to the WQv (Equation 2), it is expected that the water quality volume for all four
outfalls (02, 03, 14 and 17K) would result in a total calculated WQv range between 19.8 MG and 22.4
MG.
SHEET 7 OF 7 _
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Recreation Pond – Precipitation vs. Volume Analysis TASK NO 0003 .
PREPARED BY M. Mardenov DEPT 2118 DATE 6/07/2019 . APPROVED BY
MATH CHECK BY D. Borger DEPT 2118 DATE 6/07/2019 .
METHOD REV. BY D. Borger DEPT 2118 DATE 6/07/2019 .DEPT_ DATE_
File Name: 2-Stewart_ANGB_Rec_Pond_Volume_Evaluation_Rev5_mm Print date: 06/17/19 11:24 PM
Conclusion:
Weston’s analysis of the previously collected data yielded a linear relationship (Equation 1) that predicts
storm depth given a discharge volume. An example calculation for a 3.0 MG discharge volume yields a
0.44 inch precipitation event.
Limitations:
Conclusions stated or referenced in this analysis are limited to the precipitation and flow metering data
provided by HDR, Inc. (HDR, 2017). The dataset was concise, but not complete with many data gaps and
interpretation was necessary to create complete storm responses. This interpretation can affect the total
runoff volumes calculated. For instance, the HDR report interpreted the duration of discharge over a
shorter period than interpreted by WESTON using the same dataset. Interpretations can vary for a number
of reasons depending on the analysis goals.
Additionally, the metered flow data and precipitation measurements occurred over a limited time spanning
from July 20, 2017 to September 11, 2017. Therefore, the data collection does not account for seasonal
variations or statistical normalization from data collection spanning multiple years. Variability in storm
duration and intensities also cause variation in final runoff volumes as compared to those describe herein.
An analysis relying on a small number of storm events (seven (7) storm events were utilized for this
analysis) inhibits the accuracy of the trends generated.
Lastly, the WQv calculation relies solely on precipitation and impervious area acreage, and does not
account for all watershed characteristics (e.g. conveyance routing, soil types, etc.). These characteristics
would normally be captured in a site wide conceptual model that, when calibrated, would allow more
accurate discharge predictions.
OUTFALL 010DISCHARGE POINT
OUTFALL 002
OUTFALL A
WEIR
RECREATIONPOND
17K OUTFALL
OUTFALL 003
0
OUTFALL A
OUTFALL 002
OUTFALL 003
17K OUTFALL
RECREATION POND
LEGEND
SCALE (ft)
400 ft
Recreation PondStewart International Airport - Air National Guard Base
Newburgh, NY
Site Layout
\\mah
pi-fi
le01
\Mar
ketin
g\G
raph
ics\
Proj
ects
\100
1955
8_St
ewar
tAP\
Task
39\F
2_Si
teLa
yout
.ai
PCSWMM Professional 2D Version 7.2 – Drainage Area Measurements for Outfalls 02, 03, and 14
ATTACHMENT B
CALCULATION COVER SHEET
PROJECT: Stewart ANGB
WORK ORDER NO. 15254.002.037.0003
CALC NO.
1 SHEET 1 of_12__
SUBJECT: Pond Storage Volume
DISCIPLINE (Civil, Mech. Process, Elect.): Civil
PREPARED BY: A. Brown DATE:06/06/19
CALCULATION STATUS ISSUED FOR REVIEW
FINAL
CONFIRMED
SUPERCEDED
VOIDED
COMPUTER PROGRAMS USED:
Yes No DESCRIPTION/VERSION:
REFERENCE SPECIFICATIONS:
REFERENCE DRAWINGS:
SOURCES OF DATA: 1. HDR, Inc. (November 17, 2017). Melissa E. LaMacchia to Tony Palumbo. New York Air National Guard Base, Stewart
International Airport, Newburgh, Orange County, New York, Recreation Pond Pre-Design Investigation [Letter]. 2. John Wood Group, PLC (October 29, 2018). Preliminary Estimate of Rec Pond Base Flow and Storm Flow Treatment
Stewart Air National Guard Base, Newburgh, Orange County, New York [Draft Memorandum]. SUMMARY OF RESULTS:
Weston evaluated the bathymetry data available for the Recreation Pond and determined a relationship of storage volume versus depth of artificial drawdown and/or raising the weird overflow elevation. One foot of drawdown or weir elevation increase results in roughly one million gallons of additional storage capacity. After three feet of drawdown, significant portions of the Pond will start to dry up, thereby reducing the increase in storage for every foot of additional drawdown.
RECORD OF REVISIONS
NO. REASON FOR REVISION TOTAL NO. OF SHEETS
LAST SHEET NO.
BY CHECKED APPROVED/ ACCEPTED
DATE
0 Issued for Review 12 AB HN/CS AB 6/6/2019
1 Final 12 AB HN AB 6/17/2019
SHEET 2 OF 12
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Pond Storage Volume TASK NO 0003 .
PREPARED BY A. Brown DEPT 2118 DATE 6/6/2019 . APPROVED BY
MATH CHECK BY C. Sembera DEPT 2118 DATE 6/6/2019 .
METHOD REV. BY H. Nathanson DEPT 2118 DATE 6/6/2019 .DEPT_ DATE_
File Name: Stewart ANG Pond Volume Analysis - Final Print date: 06/17/19 11:42 PM
Objective:
Determine the potential storage volume within the Recreation Pond at Stewart Air National Guard Base
(ANGB). Calculate the amount of artificially increased storage volume of the Pond via drawn down for
various drawdown depths as well as increase in dry weather storage by modifying the weir outlet
structure.
References:
Attachment A – Site Layout
Attachment B – Stewart Airport Pond Depth 1, July 2017, Sheet 1 of 1, ASI Project #: 37-133
Attachment C – Stewart Airport Pond Depth 2, July 2017, Sheet 1 of 1, ASI Project #: 37-133
HDR, Inc. (November 17, 2017). Melissa E. LaMacchia to Tony Palumbo. New York Air National
Guard Base, Stewart International Airport, Newburgh, Orange County, New York, Recreation
Pond Pre-Design Investigation [Letter].
John Wood Group, PLC (October 29, 2018). Preliminary Estimate of Rec Pond Base Flow and
Storm Flow Treatment Stewart Air National Guard Base, Newburgh, Orange County, New
York [Memorandum to Kerry Tull, from Rich Niles, James Barbis, and Sarah Dickert] (Not
attached)
Assumptions:
Elevation datum for all referenced reports (Wood Memorandum and Aqua Survey, Inc. (ASI)) is
NAD 88.
The Recreation Pond weir elevation is 376.24 feet NAD 88.
Recreation Pond can be divided into 39 equal areas (sectors) that comprise the total area of the
Pond.
The bathymetry elevations, shot by Aqua Survey, Inc. (ASI), represent an average depth within the
area of the corresponding sector.
SHEET 3 OF 12
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Pond Storage Volume TASK NO 0003 .
PREPARED BY A. Brown DEPT 2118 DATE 6/6/2019 . APPROVED BY
MATH CHECK BY C. Sembera DEPT 2118 DATE 6/6/2019 .
METHOD REV. BY H. Nathanson DEPT 2118 DATE 6/6/2019 .DEPT_ DATE_
File Name: Stewart ANG Pond Volume Analysis - Final Print date: 06/17/19 11:42 PM
Discussion:
The existing Recreation Pond (Pond), located at the southern edge of the Stewart Air National Guard Base
(ANGB), receives stormwater drainage from four (4) outfalls (Outfalls 02, 03, 14, and 17K) and local
overland flow. A trapezoidal weir, located at Outlet 10, controls outflow from the Pond. A site layout
indicating the locations of these items is included in Attachment A.
The following volumes will be calculated to determine the amount of storage the Recreation Pond can
provide, prior to discharging via Outfall 10 to the receiving watercourse:
1. Free Water Volume – the volume of water below the weir elevation;
2. Dredge Volume – the additional volume below the weir elevation that could be gained if soft
sediments at the bottom of the Pond were removed or dredged;
3. Gate Volume – volume of storage available if the discharge weir elevation was raised from its
current elevation, by modifying the weir using permanent or temporary structures, such as a sluice
gate or stop logs; and,
4. Additional Storage Volume – the volume of additional storage that could be obtained by
artificially drawing down water levels in the Pond to make room for additional flows.
To calculate the Free Water Volume and Dredge Volume, the total area of the pond was subdivided into
39 equal sectors. The depth of each sector was then determined via a bathymetry survey, completed by
ASI (HDR, Inc., 2017), by subtracting measured values from a reference elevation. In the case of the Free
Water Volume, depth was calculated by subtracting the elevation of the sediment (Pond bottom) at each
sector (shown in Attachment A) from the weir crest elevation. The Dredge Volume depth was calculated
SHEET 4 OF 12
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Pond Storage Volume TASK NO 0003 .
PREPARED BY A. Brown DEPT 2118 DATE 6/6/2019 . APPROVED BY
MATH CHECK BY C. Sembera DEPT 2118 DATE 6/6/2019 .
METHOD REV. BY H. Nathanson DEPT 2118 DATE 6/6/2019 .DEPT_ DATE_
File Name: Stewart ANG Pond Volume Analysis - Final Print date: 06/17/19 11:42 PM
by subtracting the elevation of the bottom of the soft sediment at each sector (Attachment B) from the
corresponding sector’s top of soft sediment, or Pond bottom (Attachment A).
To calculate the Gate Volume, the total Pond area was measured using aerial imagery, as exhibited in
Figure 1 below. The total Pond area (approximately 124,000 square feet) was then multiplied by an
increase in elevation that could be generated by weir modifications.
Figure 1 - Recreation Pond Area
To artificially increase the storage volume of Recreation Pond, one proposed method is to create a volume
of water could be drawn down to create airspace for new stormwater flows to enter the Pond. This would
be an intermediate measure, similar to the Free Water Volume, that would prevent the need to fully drain
the Pond. To calculate this Additional Storage Volume available, the height of the weir is “adjusted” by a
drawdown depth, and calculated in the same manner as the Free Water Volume at the reduced elevation.
SHEET 5 OF 12
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Pond Storage Volume TASK NO 0003 .
PREPARED BY A. Brown DEPT 2118 DATE 6/6/2019 . APPROVED BY
MATH CHECK BY C. Sembera DEPT 2118 DATE 6/6/2019 .
METHOD REV. BY H. Nathanson DEPT 2118 DATE 6/6/2019 .DEPT_ DATE_
File Name: Stewart ANG Pond Volume Analysis - Final Print date: 06/17/19 11:42 PM
The difference between the original Free Water Volume and the adjusted Free Water Volume represents
the Additional Storage Volume. This volume generally follows the trend of the Gate Volume until sectors
of the Pond no longer have water available, which are reflected as zero or negative volumes as the
artificial weir elevation exceeds the water depth.
Analysis:
Equation 1 – Free Water Volume:
𝐹𝑊𝑉 = 𝐴 × (𝐸𝑤 − 𝐸𝑠)
Where:
𝐹𝑊𝑉 = 𝐹𝑟𝑒𝑒 𝑊𝑎𝑡𝑒𝑟 𝑉𝑜𝑙𝑢𝑚𝑒 (𝑓𝑡3)
𝐴 = 𝑆𝑒𝑐𝑡𝑜𝑟 𝐴𝑟𝑒𝑎 = 𝑇𝑜𝑡𝑎𝑙 𝑃𝑜𝑛𝑑 𝐴𝑟𝑒𝑎
𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑆𝑒𝑐𝑡𝑜𝑟𝑠=
124,000 (𝑓𝑡2)
39= 3,179.5 (𝑓𝑡2 𝑝𝑒𝑟 𝑠𝑒𝑐𝑡𝑜𝑟)
𝐸𝑤 = 𝑊𝑒𝑖𝑟 𝐸𝑙𝑒𝑣𝑎𝑡𝑖𝑜𝑛 (𝑓𝑡)
𝐸𝑠 = 𝐸𝑙𝑒𝑣𝑎𝑡𝑖𝑜𝑛 𝑜𝑓 𝑇𝑜𝑝 𝑜𝑓 𝑆𝑒𝑑𝑖𝑚𝑒𝑛𝑡 𝑑𝑒𝑝𝑖𝑐𝑡𝑒𝑑 𝑖𝑛 𝐴𝑡𝑡𝑎𝑐ℎ𝑚𝑒𝑛𝑡 𝐵 (𝑓𝑡)
Example (Sector 2.2):
𝐹𝑊𝑉 = 𝐴 × (𝐸𝑤 − 𝐸𝑠) = 3,179.5 𝑓𝑡2 × (376.2 𝑓𝑡 − 368.0 𝑓𝑡) = 26,071.9 𝑓𝑡3
Please note that the calculations for all sectors are presented in Table 1. Summing the calculated
values for all 39 sectors resulted in a total Free Water Volume of 5,122,764 gallons.
Equation 2 – Dredge Volume:
𝐷𝑉 = 𝐴 × (𝐸𝑠 − 𝐸𝐵)
Where:
𝐷𝑉 = 𝐷𝑟𝑒𝑑𝑔𝑒 𝑉𝑜𝑙𝑢𝑚𝑒 (𝑓𝑡3)
𝐴 = 𝑆𝑒𝑐𝑡𝑜𝑟 𝐴𝑟𝑒𝑎 = 𝑇𝑜𝑡𝑎𝑙 𝑃𝑜𝑛𝑑 𝐴𝑟𝑒𝑎
𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑆𝑒𝑐𝑡𝑜𝑟𝑠=
124,000 (𝑓𝑡2)
39= 3,179.5 (𝑓𝑡2 𝑝𝑒𝑟 𝑠𝑒𝑐𝑡𝑜𝑟)
SHEET 6 OF 12
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Pond Storage Volume TASK NO 0003 .
PREPARED BY A. Brown DEPT 2118 DATE 6/6/2019 . APPROVED BY
MATH CHECK BY C. Sembera DEPT 2118 DATE 6/6/2019 .
METHOD REV. BY H. Nathanson DEPT 2118 DATE 6/6/2019 .DEPT_ DATE_
File Name: Stewart ANG Pond Volume Analysis - Final Print date: 06/17/19 11:42 PM
𝐸𝑠 = 𝐸𝑙𝑒𝑣𝑎𝑡𝑖𝑜𝑛 𝑜𝑓 𝑇𝑜𝑝 𝑜𝑓 𝑆𝑒𝑑𝑖𝑚𝑒𝑛𝑡 𝑑𝑒𝑝𝑖𝑐𝑡𝑒𝑑 𝑖𝑛 𝐴𝑡𝑡𝑎𝑐ℎ𝑚𝑒𝑛𝑡 𝐵 (𝑓𝑡)
𝐸𝐵 = 𝐸𝑙𝑒𝑣𝑎𝑡𝑖𝑜𝑛 𝑜𝑓 𝐵𝑜𝑡𝑡𝑜𝑚 𝑜𝑓 𝑆𝑜𝑓𝑡 𝑆𝑒𝑑𝑖𝑚𝑒𝑛𝑡 𝑑𝑒𝑝𝑖𝑐𝑡𝑒𝑑 𝑖𝑛 𝐴𝑡𝑡𝑎𝑐ℎ𝑚𝑒𝑛𝑡 𝐶 (𝑓𝑡)
Example (Sector 2.2):
𝐹𝑊𝑉 = 𝐴 × (𝐸𝑆 − 𝐸𝐵) = 3,179.5 𝑓𝑡2 × (368.0 𝑓𝑡 − 364.9 𝑓𝑡) = 9,856.5 𝑓𝑡3
Please note that the calculations for all sectors are presented in Table 2. Summing the
calculated values for all 39 sectors resulted in a total Dredge Volume of 1,626,727 gallons.
Equation 3 – Gate Volume:
𝐺𝑉 = 𝐴𝑃 × 𝐻𝑤
Where:
𝐺𝑉 = 𝐺𝑎𝑡𝑒 𝑉𝑜𝑙𝑢𝑚𝑒 (𝑓𝑡3)
𝐴𝑝 = 𝑇𝑜𝑡𝑎𝑙 𝑃𝑜𝑛𝑑 𝐴𝑟𝑒𝑎 = 124,000 (𝑓𝑡2)
𝐻𝑤 = 𝐶ℎ𝑎𝑛𝑔𝑒 𝑖𝑛 𝑊𝑒𝑖𝑟 𝐻𝑒𝑖𝑔ℎ𝑡 (𝑓𝑡) = 𝑁𝑒𝑤 𝑊𝑒𝑖𝑟 𝐸𝑙𝑒𝑣𝑎𝑡𝑖𝑜𝑛 (𝑓𝑡) − 𝐸𝑊 (𝑓𝑡)
Example – One (1’) Foot Increase in Weir Elevation:
𝐺𝑉 = 𝐴 × 𝐻𝑤 = 124,000 𝑓𝑡2 × 1 𝑓𝑡 = 124,000 𝑓𝑡3 = 927,520 𝑔𝑎𝑙𝑙𝑜𝑛𝑠
Equation 4 – Additional Storage Volume:
𝐴𝑆𝑉 = 𝐴 × (𝐸𝑤 − 𝐷 − 𝐸𝑠)
Where:
𝐴𝑆𝑉 = 𝐴𝑑𝑑𝑖𝑡𝑖𝑜𝑛𝑎𝑙 𝑆𝑡𝑜𝑟𝑎𝑔𝑒 𝑉𝑜𝑙𝑢𝑚𝑒 (𝑓𝑡3)
𝐴 = 𝑆𝑒𝑐𝑡𝑜𝑟 𝐴𝑟𝑒𝑎 = 𝑇𝑜𝑡𝑎𝑙 𝑃𝑜𝑛𝑑 𝐴𝑟𝑒𝑎
𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑆𝑒𝑐𝑡𝑜𝑟𝑠=
124,000 (𝑓𝑡2)
39= 3,179.5 (𝑓𝑡2 𝑝𝑒𝑟 𝑠𝑒𝑐𝑡𝑜𝑟)
𝐸𝑤 = 𝑊𝑒𝑖𝑟 𝐸𝑙𝑒𝑣𝑎𝑡𝑖𝑜𝑛 (𝑓𝑡)
SHEET 7 OF 12
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Pond Storage Volume TASK NO 0003 .
PREPARED BY A. Brown DEPT 2118 DATE 6/6/2019 . APPROVED BY
MATH CHECK BY C. Sembera DEPT 2118 DATE 6/6/2019 .
METHOD REV. BY H. Nathanson DEPT 2118 DATE 6/6/2019 .DEPT_ DATE_
File Name: Stewart ANG Pond Volume Analysis - Final Print date: 06/17/19 11:42 PM
𝐷 = 𝐷𝑒𝑝𝑡ℎ 𝑜𝑓 𝐷𝑟𝑎𝑤𝑑𝑜𝑤𝑛 (𝑓𝑡)
𝐸𝑠 = 𝐸𝑙𝑒𝑣𝑎𝑡𝑖𝑜𝑛 𝑜𝑓 𝑇𝑜𝑝 𝑜𝑓 𝑆𝑒𝑑𝑖𝑚𝑒𝑛𝑡 𝑑𝑒𝑝𝑖𝑐𝑡𝑒𝑑 𝑖𝑛 𝐴𝑡𝑡𝑎𝑐ℎ𝑚𝑒𝑛𝑡 𝐴 (𝑓𝑡)
The total Additional Storage Volume is calculated at different depths for each sector as well as for the
entire Pond in Table 3.
SHEET 8 OF 12
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Pond Storage Volume TASK NO 0003 .
PREPARED BY A. Brown DEPT 2118 DATE 6/6/2019 . APPROVED BY
MATH CHECK BY C. Sembera DEPT 2118 DATE 6/6/2019 .
METHOD REV. BY H. Nathanson DEPT 2118 DATE 6/6/2019 .DEPT_ DATE_
File Name: Stewart ANG Pond Volume Analysis - Final Print date: 06/17/19 11:42 PM
Table 1 - Free Water Volume Calculations
Cross
Section
Node
FWV (cf) = Area (ft2) X (
Ew
Estimated Weir
Elevation
-
Es
Depth 1 - Top of
Sediment
)
1.1 13989.7 3179.5 376.2 371.8
1.2 17487.2 3179.5 376.2 370.7
1.3 23846.2 3179.5 376.2 368.7
1.4 20348.7 3179.5 376.2 369.8
2.1 13671.8 3179.5 376.2 371.9
2.2 26071.8 3179.5 376.2 368.0
2.3 26071.8 3179.5 376.2 368.0
2.4 26389.7 3179.5 376.2 367.9
3.1 15897.4 3179.5 376.2 371.2
3.2 24482.1 3179.5 376.2 368.5
3.3 20984.6 3179.5 376.2 369.6
3.4 22892.3 3179.5 376.2 369.0
3.5 14307.7 3179.5 376.2 371.7
4.1 19712.8 3179.5 376.2 370.0
4.2 14943.6 3179.5 376.2 371.5
4.3 18759.0 3179.5 376.2 370.3
4.4 25435.9 3179.5 376.2 368.2
4.5 15897.4 3179.5 376.2 371.2
5.1 19394.9 3179.5 376.2 370.1
5.2 16851.3 3179.5 376.2 370.9
6.1 11446.2 3179.5 376.2 372.6
6.2 14307.7 3179.5 376.2 371.7
6.3 18441.0 3179.5 376.2 370.4
6.4 18759.0 3179.5 376.2 370.3
6.5 15897.4 3179.5 376.2 371.2
7.1 12717.9 3179.5 376.2 372.2
7.2 13035.9 3179.5 376.2 372.1
7.3 18759.0 3179.5 376.2 370.3
7.4 17805.1 3179.5 376.2 370.6
7.5 15897.4 3179.5 376.2 371.2
8.1 15261.5 3179.5 376.2 371.4
8.2 12717.9 3179.5 376.2 372.2
8.3 17487.2 3179.5 376.2 370.7
8.4 13035.9 3179.5 376.2 372.1
9.1 12717.9 3179.5 376.2 372.2
9.2 11128.2 3179.5 376.2 372.7
9.3 19076.9 3179.5 376.2 370.2
9.4 9538.5 3179.5 376.2 373.2
9.5 19394.9 3179.5 376.2 370.1
Total : 684861.5 cubic feet
5122764 gallons
SHEET 9 OF 12
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Pond Storage Volume TASK NO 0003 .
PREPARED BY A. Brown DEPT 2118 DATE 6/6/2019 . APPROVED BY
MATH CHECK BY C. Sembera DEPT 2118 DATE 6/6/2019 .
METHOD REV. BY H. Nathanson DEPT 2118 DATE 6/6/2019 .DEPT_ DATE_
File Name: Stewart ANG Pond Volume Analysis - Final Print date: 06/17/19 11:42 PM
Table 2 - Dredge Volume Calculations
Cross
Section
Sector
DV = Area (ft2) X (
Es
Depth 1 -
Top of
Sediment
-
Eb
Depth 2 -
Bottom of
Pond
)
1.1 1271.8 3179.5 371.8 371.4
1.2 4769.2 3179.5 370.7 369.2
1.3 4769.2 3179.5 368.7 367.2
1.4 7948.7 3179.5 369.8 367.3
2.1 953.8 3179.5 371.9 371.6
2.2 9856.4 3179.5 368.0 364.9
2.3 12082.1 3179.5 368.0 364.2
2.4 4451.3 3179.5 367.9 366.5
3.1 6359.0 3179.5 371.2 369.2
3.2 7312.8 3179.5 368.5 366.2
3.3 9538.5 3179.5 369.6 366.6
3.4 6359.0 3179.5 369.0 367.0
3.5 317.9 3179.5 371.7 371.6
4.1 5723.1 3179.5 370.0 368.2
4.2 6359.0 3179.5 371.5 369.5
4.3 6041.0 3179.5 370.3 368.4
4.4 11128.2 3179.5 368.2 364.7
4.5 1589.7 3179.5 371.2 370.7
5.1 9538.5 3179.5 370.1 367.1
5.2 3179.5 3179.5 370.9 369.9
6.1 5087.2 3179.5 372.6 371.0
6.2 4451.3 3179.5 371.7 370.3
6.3 7630.8 3179.5 370.4 368.0
6.4 9856.4 3179.5 370.3 367.2
6.5 6359.0 3179.5 371.2 369.2
7.1 6359.0 3179.5 372.2 370.2
7.2 3179.5 3179.5 372.1 371.1
7.3 9856.4 3179.5 370.3 367.2
7.4 6359.0 3179.5 370.6 368.6
7.5 6359.0 3179.5 371.2 369.2
8.1 2543.6 3179.5 371.4 370.6
8.2 8902.6 3179.5 372.2 369.4
8.3 7630.8 3179.5 370.7 368.3
8.4 3497.4 3179.5 372.1 371.0
9.1 3179.5 3179.5 372.2 371.2
9.2 635.9 3179.5 372.7 372.5
9.3 4769.2 3179.5 370.2 368.7
9.4 953.8 3179.5 373.2 372.9
9.5 317.9 3179.5 370.1 370.0
Total : 217476.9
1,626,727.38
cubic feet
gallons
SHEET 10 OF 12
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Pond Storage Volume TASK NO 0003 .
PREPARED BY A. Brown DEPT 2118 DATE 6/6/2019 . APPROVED BY
MATH CHECK BY C. Sembera DEPT 2118 DATE 6/6/2019 .
METHOD REV. BY H. Nathanson DEPT 2118 DATE 6/6/2019 .DEPT_ DATE_
File Name: Stewart ANG Pond Volume Analysis - Final Print date: 06/17/19 11:42 PM
Table 3 - Storage Volume Calculations
Cross
Section
Sector
SV1 (cf) SV2 (cf) SV3 (cf) SV4 (cf) FWV (cf) = Area (ft2) X (
Ew
Estimated
Weir Elev.
-
Es
Depth 1 -
Top of
Sediment
)
Drawdown
(ft)1 ft 2 ft 3 ft 4 ft Total
1.1 10810.3 7630.8 4451.3 1271.8 13989.7 3179.5 376.2 371.8
1.2 14307.7 11128.2 7948.7 4769.2 17487.2 3179.5 376.2 370.7
1.3 20666.7 17487.2 14307.7 11128.2 23846.2 3179.5 376.2 368.7
1.4 17169.2 13989.7 10810.3 7630.8 20348.7 3179.5 376.2 369.8
2.1 10492.3 7312.8 4133.3 953.8 13671.8 3179.5 376.2 371.9
2.2 22892.3 19712.8 16533.3 13353.8 26071.8 3179.5 376.2 368.0
2.3 22892.3 19712.8 16533.3 13353.8 26071.8 3179.5 376.2 368.0
2.4 23210.3 20030.8 16851.3 13671.8 26389.7 3179.5 376.2 367.9
3.1 12717.9 9538.5 6359.0 3179.5 15897.4 3179.5 376.2 371.2
3.2 21302.6 18123.1 14943.6 11764.1 24482.1 3179.5 376.2 368.5
3.3 17805.1 14625.6 11446.2 8266.7 20984.6 3179.5 376.2 369.6
3.4 19712.8 16533.3 13353.8 10174.4 22892.3 3179.5 376.2 369.0
3.5 11128.2 7948.7 4769.2 1589.7 14307.7 3179.5 376.2 371.7
4.1 16533.3 13353.8 10174.4 6994.9 19712.8 3179.5 376.2 370.0
4.2 11764.1 8584.6 5405.1 2225.6 14943.6 3179.5 376.2 371.5
4.3 15579.5 12400.0 9220.5 6041.0 18759.0 3179.5 376.2 370.3
4.4 22256.4 19076.9 15897.4 12717.9 25435.9 3179.5 376.2 368.2
4.5 12717.9 9538.5 6359.0 3179.5 15897.4 3179.5 376.2 371.2
5.1 16215.4 13035.9 9856.4 6676.9 19394.9 3179.5 376.2 370.1
5.2 13671.8 10492.3 7312.8 4133.3 16851.3 3179.5 376.2 370.9
6.1 8266.7 5087.2 1907.7 0.0 11446.2 3179.5 376.2 372.6
6.2 11128.2 7948.7 4769.2 1589.7 14307.7 3179.5 376.2 371.7
6.3 15261.5 12082.1 8902.6 5723.1 18441.0 3179.5 376.2 370.4
6.4 15579.5 12400.0 9220.5 6041.0 18759.0 3179.5 376.2 370.3
6.5 12717.9 9538.5 6359.0 3179.5 15897.4 3179.5 376.2 371.2
7.1 9538.5 6359.0 3179.5 0.0 12717.9 3179.5 376.2 372.2
7.2 9856.4 6676.9 3497.4 317.9 13035.9 3179.5 376.2 372.1
7.3 15579.5 12400.0 9220.5 6041.0 18759.0 3179.5 376.2 370.3
7.4 14625.6 11446.2 8266.7 5087.2 17805.1 3179.5 376.2 370.6
7.5 12717.9 9538.5 6359.0 3179.5 15897.4 3179.5 376.2 371.2
8.1 12082.1 8902.6 5723.1 2543.6 15261.5 3179.5 376.2 371.4
8.2 9538.5 6359.0 3179.5 0.0 12717.9 3179.5 376.2 372.2
8.3 14307.7 11128.2 7948.7 4769.2 17487.2 3179.5 376.2 370.7
8.4 9856.4 6676.9 3497.4 317.9 13035.9 3179.5 376.2 372.1
9.1 9538.5 6359.0 3179.5 0.0 12717.9 3179.5 376.2 372.2
9.2 7948.7 4769.2 1589.7 0.0 11128.2 3179.5 376.2 372.7
9.3 15897.4 12717.9 9538.5 6359.0 19076.9 3179.5 376.2 370.2
9.4 6359.0 3179.5 0.0 0.0 9538.5 3179.5 376.2 373.2
9.5 16215.4 13035.9 9856.4 6676.9 19394.9 3179.5 376.2 370.1
Totals : 124000 248000 372000 489959 684862
927,520 1,855,040 2,782,560 3,664,893 5,122,764
cubic feet
gallons
SHEET 11 OF 12
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Pond Storage Volume TASK NO 0003 .
PREPARED BY A. Brown DEPT 2118 DATE 6/6/2019 . APPROVED BY
MATH CHECK BY C. Sembera DEPT 2118 DATE 6/6/2019 .
METHOD REV. BY H. Nathanson DEPT 2118 DATE 6/6/2019 .DEPT_ DATE_
File Name: Stewart ANG Pond Volume Analysis - Final Print date: 06/17/19 11:42 PM
Conclusion:
The storage available in Recreation Pond is approximately 5,122,000 gallons. An additional storage
volume of approximately 1,626,000 gallons could be gained by dredging the soft sediment material from
the Pond.
The storage in the pond can be increased by roughly one-million gallons per foot of additional structure
height installed in the weir outlet or foot of drawdown. The available storage in the Pond through artificial
drawdown alone is depicted in the below figure:
Figure 2 - Drawdown Storage Available
927,520
1,855,040
2,782,560
3,664,893
5,122,764
-
1,000,000
2,000,000
3,000,000
4,000,000
5,000,000
6,000,000
1 ft 2 ft 3 ft 4 ft Total
Drawdown Storage Available
SHEET 12 OF 12
CLIENT/SUBJECT Stewart ANGB W.O. NO 15254.002.037 .
TASK DESCRIPTION Pond Storage Volume TASK NO 0003 .
PREPARED BY A. Brown DEPT 2118 DATE 6/6/2019 . APPROVED BY
MATH CHECK BY C. Sembera DEPT 2118 DATE 6/6/2019 .
METHOD REV. BY M. Mardenov DEPT 2118 DATE 6/6/2019 .DEPT_ DATE_
File Name: Stewart ANG Pond Volume Analysis - Final Print date: 06/17/19 11:42 PM
Limitations:
As previously mentioned, it is assumed that Recreation Pond can be divided into 39 equal sectors, and the
bathymetry elevation at each sector represents an average depth within that sector’s area. This averaging
may not fully encompass the changing topography and depth of the Pond at all locations, nor does it
account for sidewalls or shoreline characteristics. The varying geometry of the pond cannot be accounted
for without additional data, and so the calculation is as accurate as can reasonably be assumed. A more
completed bathymetry, with increased data collection in transition areas (shorelines), would increase the
accuracy of the analysis.
Additionally, a concise survey that encompasses both the land and bathymetry below the weir elevation
was not completed. Coupling two or more data sources may lead to errors in measurements used in
determining sizes and depths of the Pond. Additionally, the data sources that were used, while accurate,
have limited coverage and may not completely represent the Pond bottom due to the spacing of the
recorded bathymetry.
The values presented should be considered accurate up to a half order of magnitude. For instance, a value
of 3,000,000 may vary as much as 500,000 from actual values that could be calculated or measured given
a more complete dataset and survey.
OUTFALL 010DISCHARGE POINT
OUTFALL 002
OUTFALL A
WEIR
RECREATIONPOND
17K OUTFALL
OUTFALL 003
0
OUTFALL A
OUTFALL 002
OUTFALL 003
17K OUTFALL
RECREATION POND
LEGEND
SCALE (ft)
400 ft
Recreation PondStewart International Airport - Air National Guard Base
Newburgh, NY
Site Layout
\\mah
pi-fi
le01
\Mar
ketin
g\G
raph
ics\
Proj
ects
\100
1955
8_St
ewar
tAP\
Task
39\F
2_Si
teLa
yout
.ai