PERT:Programme Evaluation and Review Technique”.
And
CPM : Critical Path Method
![Page 2: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/2.jpg)
PERT was developed by US Navy Engineers to plan and control the huge Polaris Submarine Programme. AND Du Pont and Remington Rand Companies CPM to help the process of scheduling
![Page 3: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/3.jpg)
1.When is each individual phase of the project scheduled to start and finish?
2.How soon will the project be completed?
3.Which are the independent activities?
4.Which are inter-related activities?
5.What is total project time?
PERT AND CPM ????
![Page 4: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/4.jpg)
7.Which are the critical phases of the project to be finished on time and required close managerial attention to avoid delay?
8.Can project time be curtailed?
9.At what cost?
10.Can resources reduced and then the cost?
6.What are different resources required for completion of the project?
![Page 5: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/5.jpg)
2 TERMINOLOGY USED IN PERT AND CPM
ACTIVITY :
At HEAD / RHSTAIL / LHS
TYPES
1. PARALLEL / CONCURRENT / INDEPENDENT ACTIVITY
2, PRECEEDING ACTIVITY
3.SUCCEEDING ACTIVITY
CONSUME RESOURCES AND TIME
![Page 6: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/6.jpg)
EVENT / NODE
DO NOT CONSUME RESOUCES AND TIME
![Page 7: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/7.jpg)
2
AB
C
DE
F
BURSTING EVENT
MERGING EVENT
4
![Page 8: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/8.jpg)
Rules of Network Construction
1.In network diagram, arrows represent activities and circles (or nodes) the events. The length of an arrow is of no significance.
2.Each activity must start and end in a node The tail of an activity represents the start and head, the completion of work.
3.The event numbered 0 or 1 denotes start of the project and is acted initial node (or event). All activities emerging (or taking off) from event 1 should not be preceded by any other activity or activities Events carrying the highest number denote the completion event.
![Page 9: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/9.jpg)
4.Events should be numbered such that for each activity (i, J), i < j
5.An event number should not get repeated or duplicated,
6.The same starting and completion events should not identify two activities.
7.The logical sequence (or inter relationship) between activities must follow the following rules:
i)An event cannot occur until all the incoming activities into it have been completed.
ii)An activity cannot start unless all the proceeding activities, on which it depends, have been completed.
![Page 10: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/10.jpg)
DUMMY ACTIVITY
1 2
A
B
NOT ALLOWED
LOOP / LOOPING
![Page 11: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/11.jpg)
Though a dummy activity does not consume either resources or time, even then it has to follow the rules (1) and 7(ii).
![Page 12: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/12.jpg)
Activity Immediate Predecessors
A -
B -
C A
D A
E C, B
![Page 13: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/13.jpg)
Activity Immediate Predecessors
A -
B -
C A
D B
![Page 14: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/14.jpg)
Activity Immediate Predecessors
A -
B -
C A
D B
E C, D
F D
G E
H F
![Page 15: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/15.jpg)
![Page 16: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/16.jpg)
1
2
3
5
4
6
7
8
A
B
C
D
E
F
G
H
Dummy Activity
![Page 17: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/17.jpg)
Beginning Event
Ending Event Activity
1 2 1-2
1 3 1-3
2 4 2-4
3 4 3-4
3 5 3-5
4 6 4-6
5 6 5-6
![Page 18: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/18.jpg)
![Page 19: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/19.jpg)
Q1.Draw the network for the following activities.
Acitivity Duration( Days)
1-2 20
1-3 25
2-3 10
2-4 12
3-4 5
4-5 10
![Page 20: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/20.jpg)
Activity Time Activity Time
1-2 4 5-6 4
1-3 1 5-7 8
2-4 1 6-8 1
3-4 1 7-8 2
3-5 6 8-10 5
4-9 5 9-10 7
![Page 21: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/21.jpg)
![Page 22: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/22.jpg)
Q2.Draw the network for the following activities.
Acitivity Duration( Days)
1-2 13
2-3 8
3-4 10
3-5 11
4-6
9
5-6 10
5-7 6
6-8 8
7-8 7
8-9 14
9-10 18
![Page 23: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/23.jpg)
Q3.Draw the network for the following activities.
Activity Duration
1-2 10
1-3 4
1-4 6
2-3 5
2-5 12
2-6 9
3-7 12
4-5 15
5-6 6
6-7 5
6-8 4
![Page 24: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/24.jpg)
Activity Predecessor Activity
A Open work order None
B Get material for a A
C Get material for B A
D Turn A on lathe B
E Turn B on lathe B, C
F Polish B E
G Assemble A and B D, F
H pack G
An assembly is to be made from two parts A and B. Both parts must be turned on a lathe and B must be polished whereas, A need not be polished The sequence of activities together with their predecessors is given below. Construct a PERT diagram.
![Page 25: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/25.jpg)
![Page 26: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/26.jpg)
Optimistic Time (a)– The shortest possible time for completion of activity is called as Optimistic time. This is represented as ‘a’.
Pessimistic Time (b) – The longest of maximum possible time for completion of an activity is called as Pessimistic time and denoted as ‘b’.
Most likely Time (m) - If the same activity is done repeatedly then the most repeated time taken to complete the activity is called as Most likely time and it is denoted by ‘m’.
TIME ESTIMATES
![Page 27: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/27.jpg)
Expected Time (te) - This is practical workable time for completion of a activity & calculated as:
a + 4m + b te = -------------------
6
![Page 28: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/28.jpg)
VARIANCES OF ACTIVITIES ON CRITICAL PATH
=
![Page 29: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/29.jpg)
CRITICAL PATH
THE LONGEST TIME PATH THROUGH A NETWORK IS CALLED THE CRITCAL PATH.IT IS DENOTED BY DOUBLE LINES IN THE NETWORK.
1.IDENTIFIES SET OF ACTIVITIES AND EVENTS WHICH ARE CRITICAL AND HENCE NEED TO CONTROLL AND MONITOR.
2.TO SHRTEN PROJECT TIME,SOME OF THE ACTIVITIES ON THE CRITICAL PATH MUST BE SHORTENED.
3.CRITICAL PATH IDENTIFIES ACTIVIES FOR PREFERNCES IN RESOURCE ALLOCATION.
4.CRITICAL PATH IMPLIES “CONTROL BY EXCEPTION”
![Page 30: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/30.jpg)
Esj = Efj + tij
Forward pass computation:
BACKWARD PASS COMPUTATION
Efi = Efj – tis
![Page 31: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/31.jpg)
EARLIST START ( Es ) AND FINISH TIMES (Ef)
LET ZERO BE THE STRATING TIME FOR THE PROJECT.THEN THIS WILL BE THE EARLIEST START TIME,Es,FOR THIS ACTIVITY.
GIVEN Es FOR AN ACTIVITY,THE EARLIST FINISH TIME. Ef, OF THAT ACTIVITY IS Es PLUS THE ACTIVITY TIME t.
Ef = Es + t
LATEST START ( Ls ) AND FINISH TIMES (Lf)
SUPPOSE A TARGET TIME IS GIVEN FOR COMPLETING A PROJECT THEN THIS TIME IS CALLED THE LATEST FINISH TIME (Lf) FOR THE FINAL ACTIVITY.
THE LATEST START TIME (Ls) IS THE LATEST TIME AT WHICH AN ACTIVITY CAN START IF THE TARGET IS TO BE MAINTAINED.
Ls = Lf - t
![Page 32: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/32.jpg)
FOR CRITICAL PATH
Es = Ef
![Page 33: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/33.jpg)
a) Draw networkb) Calculate expected time of each activityc) Identify Critical Pathd) State Project Duratione)Find variances of activities on critical path and its standard deviation
Activity Optimistic Most Likely Pessimistic
1-2 6 7 8
1-3 4 5 12
1-4 2 10 12
2-5 3 7 11
3-6 10 20 48
3-7 6 9 18
4-6 3 3 9
5-8 3 3 9
6-9 8 18 40
7-8 2 6 10
8-9 2 5 14
![Page 34: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/34.jpg)
a) Draw networkb) Calculate expected time of each activityc) Identify Critical Pathd) State Project Duratione)Find variances of activities on critical path and its standard deviation
ActivityOptimistic Most Likely Pessimistic
1-2 2 5 8
1-3 4 10 16
1-4 1 7 13
2-5 5 8 11
3-5 2 8 14
4-6 6 9 12
5-6 4 7 10
![Page 35: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/35.jpg)
a) Draw networkb) Calculate expected time of each activityc) Identify Critical Pathd) State Project Duration
Activity Optimistic Most Likely Pessimistic
1-2 2 5 8
1-3 6 6 6
1-4 1 7 13
2-5 3 9 13
3-5 2 8 14
4-6 6 9 12
5-6 4 7 10
![Page 36: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/36.jpg)
Activity Predecessor activity Time (weeks)A - 2B - 6
C - 4D A 6E B 8F C 7
![Page 37: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/37.jpg)
![Page 38: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/38.jpg)
![Page 39: PERT:Programme Evaluation and Review Technique”. and CPM](https://reader033.vdocuments.mx/reader033/viewer/2022061201/546a4db1b4af9f817d8b4710/html5/thumbnails/39.jpg)