gantt chart critical path method (cpm) program evaluation and review technique (pert) project...

74
Gantt chart Critical Path Method (CPM) Program Evaluation and Review Technique (PERT) Project Management Techniques

Upload: brittany-dean

Post on 03-Jan-2016

292 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Gantt chart Critical Path Method

(CPM) Program Evaluation

and Review Technique (PERT)

Project Management Techniques

Page 2: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

A Simple Gantt Chart

TimeJ F M A M J J A S

Design

Prototype

Test

Revise

Production

Page 3: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Passengers

Baggage

Fueling

Cargo and mail

Galley servicing

Lavatory servicingDrinking water

Cabin cleaning

Cargo and mail

Flight services

Operating crewBaggagePassengers

DeplaningBaggage claimContainer offloadPumpingEngine injection waterContainer offloadMain cabin doorAft cabin doorAft, center, forwardLoadingFirst-class sectionEconomy sectionContainer/bulk loadingGalley/cabin checkReceive passengersAircraft checkLoadingBoarding

00 1515 3030 4545 6060MinutesMinutes

Service For A Delta Jet

Figure 3.4Figure 3.4

Page 4: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Project Control Reports

Detailed cost breakdowns for each task Total program labor curves Cost distribution tables Functional cost and hour summaries Raw materials and expenditure forecasts Variance reports Time analysis reports Work status reports

Page 5: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Network techniques Developed in 1950’s

CPM by DuPont for chemical plants (1957) PERT by Booz, Allen & Hamilton with the

U.S. Navy, for Polaris missile (1958)

Consider precedence relationships and interdependencies

Each uses a different estimate of activity times

PERT and CPM

Page 6: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Six Steps PERT & CPM

1. Define the project and prepare the work breakdown structure

2. Develop relationships among the activities - decide which activities must precede and which must follow others

3. Draw the network connecting all of the activities

Page 7: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Six Steps PERT & CPM

4. Assign time and/or cost estimates to each activity

5. Compute the longest time path through the network – this is called the critical path

6. Use the network to help plan, schedule, monitor, and control the project

Page 8: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

1. When will the entire project be completed?

2. What are the critical activities or tasks in the project?

3. Which are the noncritical activities?

4. What is the probability the project will be completed by a specific date?

Questions PERT & CPM Can Answer

Page 9: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

5. Is the project on schedule, behind schedule, or ahead of schedule?

6. Is the money spent equal to, less than, or greater than the budget?

7. Are there enough resources available to finish the project on time?

8. If the project must be finished in a shorter time, what is the way to accomplish this at least cost?

Questions PERT & CPM Can Answer

Page 10: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

A Comparison of AON and AOA Network ConventionsActivity on Activity Activity onNode (AON) Meaning Arrow (AOA)

A comes before B, which comes before C

(a) A B CBA C

A and B must both be completed before C can start

(b)

A

CC

B

A

B

B and C cannot begin until A is completed

(c)

B

A

CA

B

CFigure 3.5Figure 3.5

Page 11: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

A Comparison of AON and AOA Network ConventionsActivity on Activity Activity onNode (AON) Meaning Arrow (AOA)

C and D cannot begin until A and B have both been completed

(d)A

B

C

D B

A C

D

C cannot begin until both A and B are completed; D cannot begin until B is completed. A dummy activity is introduced in AOA

(e)CA

B D

Dummy activityA

B

C

D

Figure 3.5Figure 3.5

Page 12: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

A Comparison of AON and AOA Network ConventionsActivity on Activity Activity onNode (AON) Meaning Arrow (AOA)

B and C cannot begin until A is completed. D cannot begin until both B and C are completed. A dummy activity is again introduced in AOA.

(f)

A

C

DB A B

C

D

Dummy activity

Figure 3.5Figure 3.5

Page 13: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

AON Example

Activity DescriptionImmediate

Predecessors

A Build internal components —

B Modify roof and floor —

C Construct collection stack A

D Pour concrete and install frame A, B

E Build high-temperature burner C

F Install pollution control system C

G Install air pollution device D, E

H Inspect and test F, G

Milwaukee Paper Manufacturing'sMilwaukee Paper Manufacturing'sActivities and PredecessorsActivities and Predecessors

Table 3.1Table 3.1

Page 14: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

AON Network for Milwaukee Paper

A

Start

BStart Activity

Activity A(Build Internal Components)

Activity B(Modify Roof and Floor)

Figure 3.6Figure 3.6

Page 15: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

AON Network for Milwaukee Paper

Figure 3.7Figure 3.7

C

D

A

Start

B

Activity A Precedes Activity C

Activities A and B Precede Activity D

Page 16: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

AON Network for Milwaukee Paper

G

E

F

H

CA

Start

DB

Arrows Show Precedence Relationships

Figure 3.8Figure 3.8

Page 17: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

HH

(Inspect/ (Inspect/ Test)Test)

77Dummy Dummy ActivityActivity

AOA Network for Milwaukee Paper

66

FF(Install

(Install

Controls)

Controls)EE

(Bu

ild B

urn

er)(B

ui ld

Bu

rner)

GG

(Insta

ll

(Insta

ll

Pollutio

n

Pollutio

n

Device)

Device)

55DD

(Pour (Pour Concrete/ Concrete/

Install Frame)Install Frame)

44CC

(Construct (Construct Stack)Stack)

11

33

22

BB(Modify

(Modify

Roof/Floor)

Roof/Floor)

AA(B

uild In

tern

al

(Build

Inte

rnal

Componen

ts)

Componen

ts)

Figure 3.9Figure 3.9

Page 18: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Determining the Project Schedule

Perform a Critical Path AnalysisPerform a Critical Path Analysis

The critical path is the longest path The critical path is the longest path through the networkthrough the network

The critical path is the shortest time in The critical path is the shortest time in which the project can be completedwhich the project can be completed

Any delay in critical path activities Any delay in critical path activities delays the projectdelays the project

Critical path activities have no slack Critical path activities have no slack timetime

Page 19: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Determining the Project Schedule

Perform a Critical Path AnalysisPerform a Critical Path AnalysisActivity Description Time (weeks)

A Build internal components 2B Modify roof and floor 3C Construct collection stack 2D Pour concrete and install frame 4E Build high-temperature burner 4F Install pollution control system 3G Install air pollution device 5H Inspect and test 2

Total Time (weeks) 25Table 3.2Table 3.2

Page 20: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Determining the Project Schedule

Perform a Critical Path AnalysisPerform a Critical Path Analysis

Table 3.2Table 3.2

Activity Description Time (weeks)A Build internal components 2B Modify roof and floor 3C Construct collection stack 2D Pour concrete and install frame 4E Build high-temperature burner 4F Install pollution control system 3G Install air pollution device 5H Inspect and test 2

Total Time (weeks) 25

Earliest start (ES) =earliest time at which an activity can start, assuming all predecessors have been completed

Earliest finish (EF) =earliest time at which an activity can be finished

Latest start (LS) =latest time at which an activity can start so as to not delay the completion time of the entire project

Latest finish (LF) =latest time by which an activity has to be finished so as to not delay the completion time of the entire project

Page 21: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Determining the Project Schedule

Perform a Critical Path AnalysisPerform a Critical Path Analysis

Figure 3.10Figure 3.10

A

Activity Name or Symbol

Earliest Start ES

Earliest FinishEF

Latest Start

LS Latest Finish

LF

Activity Duration

2

Page 22: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Forward Pass

Begin at starting event and work forwardBegin at starting event and work forward

Earliest Start Time Rule:

If an activity has only one immediate predecessor, its ES equals the EF of the predecessor

If an activity has multiple immediate predecessors, its ES is the maximum of all the EF values of its predecessors

ES = Max (EF of all immediate predecessors)

Page 23: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Forward Pass

Begin at starting event and work forwardBegin at starting event and work forward

Earliest Finish Time Rule:

The earliest finish time (EF) of an activity is the sum of its earliest start time (ES) and its activity time

EF = ES + Activity time

Page 24: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

ES/EF Network for Milwaukee Paper

Start

0

0

ES

0

EF = ES + Activity time

Page 25: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

ES/EF Network for Milwaukee Paper

Start0

0

0

A

2

2

EF of A = ES of A + 2

0

ESof A

Page 26: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

B

3

ES/EF Network for Milwaukee Paper

Start0

0

0

A

2

20

3

EF of B = ES of B + 3

0

ESof B

Page 27: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

C

2

2 4

ES/EF Network for Milwaukee Paper

B

3

0 3

Start0

0

0

A

2

20

Page 28: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

C

2

2 4

ES/EF Network for Milwaukee Paper

B

3

0 3

Start0

0

0

A

2

20

D

4

73= Max (2, 3)

Page 29: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

D

4

3 7

C

2

2 4

ES/EF Network for Milwaukee Paper

B

3

0 3

Start0

0

0

A

2

20

Page 30: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

E

4

F

3

G

5

H

2

4 8 13 15

4

8 13

7

D

4

3 7

C

2

2 4

ES/EF Network for Milwaukee Paper

B

3

0 3

Start0

0

0

A

2

20

Figure 3.11Figure 3.11

Page 31: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Backward Pass

Begin with the last event and work backwardsBegin with the last event and work backwards

Latest Finish Time Rule:

If an activity is an immediate predecessor for just a single activity, its LF equals the LS of the activity that immediately follows it

If an activity is an immediate predecessor to more than one activity, its LF is the minimum of all LS values of all activities that immediately follow it

LF = Min (LS of all immediate following activities)

Page 32: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Backward Pass

Begin with the last event and work backwardsBegin with the last event and work backwards

Latest Start Time Rule:

The latest start time (LS) of an activity is the difference of its latest finish time (LF) and its activity time

LS = LF – Activity time

Page 33: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

LS/LF Times for Milwaukee Paper

E

4

F

3

G

5

H

2

4 8 13 15

4

8 13

7

D

4

3 7

C

2

2 4

B

3

0 3

Start0

0

0

A

2

20

Figure 3.12Figure 3.12

LF = EF of Project

1513

LS = LF – Activity time

Page 34: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

LS/LF Times for Milwaukee Paper

E

4

F

3

G

5

H

2

4 8 13 15

4

8 13

7

13 15

D

4

3 7

C

2

2 4

B

3

0 3

Start0

0

0

A

2

20

LF = Min(LS of following activity)

10 13

Figure 3.12Figure 3.12

Page 35: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

LS/LF Times for Milwaukee Paper

E

4

F

3

G

5

H

2

4 8 13 15

4

8 13

7

13 15

10 13

8 13

4 8

D

4

3 7

C

2

2 4

B

3

0 3

Start0

0

0

A

2

20

LF = Min(4, 10)

42

Figure 3.12Figure 3.12

Page 36: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

LS/LF Times for Milwaukee Paper

E

4

F

3

G

5

H

2

4 8 13 15

4

8 13

7

13 15

10 13

8 13

4 8

D

4

3 7

C

2

2 4

B

3

0 3

Start0

0

0

A

2

20

42

84

20

41

00

Figure 3.12Figure 3.12

Page 37: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Computing Slack Time

After computing the ES, EF, LS, and LF times After computing the ES, EF, LS, and LF times for all activities, compute the slack or free for all activities, compute the slack or free time for each activitytime for each activity

Slack is the length of time an activity can be delayed without delaying the entire project

Slack = LS – ES or Slack = LF – EF

Page 38: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Computing Slack Time

Earliest Earliest Latest Latest OnStart Finish Start Finish Slack Critical

Activity ES EF LS LF LS – ES Path

A 0 2 0 2 0 YesB 0 3 1 4 1 NoC 2 4 2 4 0 YesD 3 7 4 8 1 NoE 4 8 4 8 0 YesF 4 7 10 13 6 NoG 8 13 8 13 0 YesH 13 15 13 15 0 Yes

Table 3.3Table 3.3

Page 39: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Critical Path for Milwaukee Paper

Figure 3.13Figure 3.13

E

4

F

3

G

5

H

2

4 8 13 15

4

8 13

7

13 15

10 13

8 13

4 8

D

4

3 7

C

2

2 4

B

3

0 3

Start0

0

0

A

2

20

42

84

20

41

00

Page 40: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

ES – EF Gantt Chartfor Milwaukee Paper

AA Build internal Build internal componentscomponents

BB Modify roof and floorModify roof and floor

CC Construct collection Construct collection stackstack

DD Pour concrete and Pour concrete and install frameinstall frame

EE Build high-Build high-temperature burnertemperature burner

FF Install pollution Install pollution control systemcontrol system

GG Install air pollution Install air pollution devicedevice

HH Inspect and testInspect and test

11 22 33 44 55 66 77 88 99 1010 1111 1212 1313 1414 1515 1616

Page 41: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

LS – LF Gantt Chartfor Milwaukee Paper

AA Build internal Build internal componentscomponents

BB Modify roof and floorModify roof and floor

CC Construct collection Construct collection stackstack

DD Pour concrete and Pour concrete and install frameinstall frame

EE Build high-Build high-temperature burnertemperature burner

FF Install pollution Install pollution control systemcontrol system

GG Install air pollution Install air pollution devicedevice

HH Inspect and testInspect and test

11 22 33 44 55 66 77 88 99 1010 1111 1212 1313 1414 1515 1616

Page 42: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

CPM assumes we know a fixed time estimate for each activity and there is no variability in activity times

PERT uses a probability distribution for activity times to allow for variability

Variability in Activity Times

Page 43: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Three time estimates are requiredOptimistic time (a) – if everything goes

according to planMost–likely time (m) – most realistic

estimatePessimistic time (b) – assuming very

unfavorable conditions

Variability in Activity Times

Page 44: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Estimate follows beta distribution

Variability in Activity Times

Expected time: Expected time:

Variance of times: Variance of times: t = t = ((a + a + 44mm + + bb)/6)/6

v = v = [([(b b – – aa)/6])/6]22

Page 45: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Estimate follows beta distribution

Variability in Activity Times

Expected time: Expected time:

Variance of times: Variance of times: t = t = ((a + a + 44mm + + bb)/6)/6

v = v = [([(b b − − aa)/6]2)/6]2Probability of 1 in 100 of > b occurring

Probability of 1 in 100 of < a occurring

Pro

bab

ility

Optimistic Time (a)

Most Likely Time (m)

Pessimistic Time (b)

Activity Time

Page 46: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Computing Variance

Most ExpectedOptimistic Likely Pessimistic Time Variance

Activity a m b t = (a + 4m + b)/6 [(b – a)/6]2

A 1 2 3 2 .11B 2 3 4 3 .11C 1 2 3 2 .11D 2 4 6 4 .44E 1 4 7 4 1.00F 1 2 9 3 1.78G 3 4 11 5 1.78H 1 2 3 2 .11

Table 3.4Table 3.4

Page 47: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Probability of Project Completion

Project variance is computed by Project variance is computed by summing the variances of critical summing the variances of critical activitiesactivities

22 = Project variance = Project variance

= = ((variances of activities variances of activities on critical pathon critical path))

p

Page 48: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Probability of Project Completion

Project variance is computed by Project variance is computed by summing the variances of critical summing the variances of critical activitiesactivitiesProject variance

2 = .11 + .11 + 1.00 + 1.78 + .11 = 3.11

Project standard deviation

p = Project variance

= 3.11 = 1.76 weeks

p

Page 49: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Probability of Project Completion

PERT makes two more assumptions:PERT makes two more assumptions:

Total project completion times follow a Total project completion times follow a normal probability distributionnormal probability distribution

Activity times are statistically Activity times are statistically independentindependent

Page 50: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Probability of Project Completion

Standard deviation = 1.76 weeks

15 Weeks

(Expected Completion Time)Figure 3.15

Page 51: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Probability of Project Completion

What is the probability this project can What is the probability this project can be completed on or before the be completed on or before the 1616 week week deadline?deadline?

ZZ == –– //pp

= = (16 (16 wkswks –– 15 15 wkswks)/1.76)/1.76

= = 0.570.57

duedue expected dateexpected datedatedate of completionof completion

Where Z is the number of standard deviations the due

date lies from the mean

Page 52: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Probability of Project Completion

What is the probability this project can What is the probability this project can be completed on or before the 16 week be completed on or before the 16 week deadline?deadline?

ZZ == −− //pp

= = (16 (16 wkswks −− 15 15 wkswks)/1.76)/1.76

= = 0.570.57

due expected datedate of completion

Where Z is the number of standard deviations the due

date lies from the mean

.00 .01 .07 .08

.1 .50000 .50399 .52790 .53188

.2 .53983 .54380 .56749 .57142

.5 .69146 .69497 .71566 .71904

.6 .72575 .72907 .74857 .75175

From Appendix I

Page 53: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Probability of Project Completion

Time

Probability(T ≤ 16 weeks)is 71.57%

Figure 3.16

0.57 Standard deviations

15 16Weeks Weeks

Page 54: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Determining Project Completion Time

Probability of 0.01

Z

Figure 3.17

From Appendix I

Probability of 0.99

2.33 Standard deviations

0 2.33

Page 55: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Variability of Completion Time for Noncritical Paths

Variability of times for activities on noncritical paths must be considered when finding the probability of finishing in a specified time

Variation in noncritical activity may cause change in critical path

Page 56: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

What Project Management Has Provided So Far

The project’s expected completion time is 15 weeks

There is a 71.57% chance the equipment will be in place by the 16 week deadline

Five activities (A, C, E, G, and H) are on the critical path

Three activities (B, D, F) have slack time and are not on the critical path

A detailed schedule is available

Page 57: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Trade-Offs And Project Crashing

The project is behind schedule The completion time has been

moved forward

It is not uncommon to face the It is not uncommon to face the following situations:following situations:

Shortening the duration of the project is called project crashing

Page 58: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Factors to Consider When Crashing A Project

The amount by which an activity is crashed is, in fact, permissible

Taken together, the shortened activity durations will enable us to finish the project by the due date

The total cost of crashing is as small as possible

Page 59: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Steps in Project Crashing

1. Compute the crash cost per time period. If crash costs are linear over time:

Crash costCrash costper periodper period ==

(Crash cost – Normal cost)(Crash cost – Normal cost)

(Normal time – Crash time)(Normal time – Crash time)

2. Using current activity times, find the critical path and identify the critical activities

Page 60: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Steps in Project Crashing

3. If there is only one critical path, then select the activity on this critical path that (a) can still be crashed, and (b) has the smallest crash cost per period. If there is more than one critical path, then select one activity from each critical path such that (a) each selected activity can still be crashed, and (b) the total crash cost of all selected activities is the smallest. Note that a single activity may be common to more than one critical path.

Page 61: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Steps in Project Crashing

4. Update all activity times. If the desired due date has been reached, stop. If not, return to Step 2.

Page 62: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Crashing The Project

Time (Wks) Cost ($) Crash Cost CriticalActivity Normal Crash Normal Crash Per Wk ($) Path?

A 2 1 22,000 22,750 750 YesB 3 1 30,000 34,000 2,000 NoC 2 1 26,000 27,000 1,000 YesD 4 2 48,000 49,000 1,000 NoE 4 2 56,000 58,000 1,000 YesF 3 2 30,000 30,500 500 NoG 5 2 80,000 84,500 1,500 YesH 2 1 16,000 19,000 3,000 Yes

Table 3.5Table 3.5

Page 63: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Crash and Normal Times and Costs for Activity B

| | |11 22 33 Time (Weeks)Time (Weeks)

$34,000 $34,000 —

$33,000 $33,000 —

$32,000 $32,000 —

$31,000 $31,000 —

$30,000 $30,000 —

Activity Activity CostCost

CrashCrash

NormalNormal

Crash TimeCrash Time Normal TimeNormal Time

Crash Crash CostCost

Normal Normal CostCost

Crash Cost/WkCrash Cost/Wk = = Crash Cost – Normal CostCrash Cost – Normal CostNormal Time – Crash TimeNormal Time – Crash Time

==$34,000 $34,000 –– $30,000 $30,000

3 3 –– 1 1

= = $2,000/Wk= = $2,000/Wk$4,000$4,0002 Wks2 Wks

Figure 3.18Figure 3.18

Page 64: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Critical Path And Slack Times For Milwaukee Paper

Figure 3.19Figure 3.19

E

4

F

3

G

5

H

2

4 8 13 15

4

8 13

7

13 15

10 13

8 13

4 8

D

4

3 7

C

2

2 4

B

3

0 3

Start0

0

0

A

2

20

42

84

20

41

00

SlackSlack = 1 = 1 SlackSlack = 1 = 1

SlackSlack = 0 = 0 SlackSlack = 6 = 6

SlackSlack = 0 = 0

SlackSlack = 0 = 0

SlackSlack = 0 = 0

SlackSlack = 0 = 0

Page 65: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Advantages of PERT/CPM

1. Especially useful when scheduling and controlling large projects

2. Straightforward concept and not mathematically complex

3. Graphical networks help to perceive relationships among project activities

4. Critical path and slack time analyses help pinpoint activities that need to be closely watched

Page 66: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Advantages of PERT/CPM

5. Project documentation and graphics point out who is responsible for various activities

6. Applicable to a wide variety of projects

7. Useful in monitoring not only schedules but costs as well

Page 67: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

1. Project activities have to be clearly defined, independent, and stable in their relationships

2. Precedence relationships must be specified and networked together

3. Time estimates tend to be subjective and are subject to fudging by managers

4. There is an inherent danger of too much emphasis being placed on the longest, or critical, path

Limitations of PERT/CPM

Page 68: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Using Microsoft Project

Program 3.1

Page 69: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Using Microsoft Project

Program 3.2

Page 70: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Using Microsoft Project

Program 3.3

Page 71: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Using Microsoft Project

Program 3.4

Page 72: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Using Microsoft Project

Program 3.5

Page 73: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Using Microsoft Project

Program 3.6

Page 74: Gantt chart  Critical Path Method (CPM)  Program Evaluation and Review Technique (PERT) Project Management Techniques

Using Microsoft Project

Program 3.7