p2011 - the analysis and valuation of disruption - derek nelson

Upload: pameswara

Post on 03-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    1/31

    TheAnalysisandValuationofDisruption

    byDerekNelson,SeniorVicePresident&RegionalManagingDirectorAsia

    HillInternational,Inc

    25January2011

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    2/31

    TheAnalysisandValuationofDisruption

    Page|2

    TableofContents

    Introduction 3

    WhatisDisruption? 3WhatisProductivity? 4

    WhyisProductivityImportant? 4

    Background 5

    FactorsAffectingLabourProductivity 5

    ProjectChange 7

    ExtentofProjectChange 8

    DisruptionsandCumulativeImpacts 9

    MethodsofQuantifyingLostProductivity 10

    ProjectPracticeBasedMethods 13

    MeasuredMileAnalysis 13

    BaselineProductivityAnalysis 16SystemDynamicsModelling 17

    EarnedValueAnalysis 22

    SamplingMethods 23

    ComparisonStudies 24

    IndustryBasedMethods 24

    CostBasedMethods 24

    OtherQuantifyingMethods 25

    MatchingtheQuantifyingMethodswithProjectPractice 26

    Conclusions 27

    Attachment 31

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    3/31

    TheAnalysisandValuationofDisruption

    Page|3

    Introduction

    Complaintsof disruptionandadditionalcostsareroutinelymadeduringthecourseofaconstruction

    projectyettheyremainnotoriouslydifficulttoprove.

    Oneofthemainreasonsforthisisthatproductivitylossesareoftendifficulttoidentifyanddistinguish

    atthetimetheyarise,asopposedtoothermoneyclaimswhicharemoredirectlyconcernedwiththe

    occurrenceofadistinctandcompensableeventtogetherwithadistinctanddirectconsequence,such

    as an instruction for a discreet variation during the progress of the works or a properly notified

    compensationevent.

    Assuch,mostclaimsfordisruptionaredealtwithretrospectivelyandtheclaimant isforcedtorelyon

    contemporaryrecordstotryandestablishacausalnexusforidentified losses(causeandeffect)which

    are all too often inadequate for the purposes of sufficiently evidencing a loss of productivity claim.

    Whenthishappenstheclaimant isoften forced intothesituationwhere itadvancesaweakglobalor

    totalcostclaimofsortstotryandrecoversomeofitslosses.

    Thecauseandeffectburdenofproof isthesame foraclaim for lossofproductivityas foranyother

    claiminsofarastheclaimingpartymustfirstestablishthattheeventorfactorcausingthedisruptionisa

    compensable risk event under the contract. To do this, the contract needs to be reviewed to

    understand thebasisof theagreementascertainproductivity issuesmayhavebeen foreseeableand

    thereforeaccountedforwithintheclaimantsproductivityallowances. Thecontractmayalsoidentifyif

    apartyexpresslyacceptedcertainproductivityrisks.

    Where courts and tribunalshave a clear focuson linking cause and effect, claims fordisruptionwill

    comeundergreaterscrutiny. Itisunlikelythatcontractorsandsubcontractorswillsucceedwheretheir

    claims fordisruptionarebased simplyonaglobaloverspendon labourorplant for thewholeof thecontractworkingperiod. Sufficientdetailisrequiredtoisolatethecauseofthedisruptioncomplained

    ofandevaluatetheeffectsofthatdisruption.

    WhatisDisruption?

    Disruption is loss of productivity, disturbance, hindrance or interruption to a Contractors normal

    workingmethods,resultinginlowerefficiency. Intheconstructioncontext,disruptedworkisworkthat

    iscarriedoutlessefficientlythanitwouldhavebeen,haditnotbeenforthecauseofthedisruption. IfcausedbytheEmployer, itmaygiverisetoarighttocompensationeitherunderthecontractorasa

    breachofcontract.1

    Constructioncontractshavetwomajortypesofcostsassociatedwiththem:fixedandvariable.

    Fixedcostsarethosecoststhatthecontractorprocuresonafixedpricesubcontractorpurchaseorder.

    Fixedcostsareinherentlylowerinrisk,becausethecontractorhasfixedthemthroughacontract. Risks

    doexist,suchasthefinancialfailureordefaultofeitheravendororsubcontractorortheinstallationof

    defective or faultywork by a subcontractor or vendor,but the risks aremuch less than the risks in

    variablecostitems.

    1SCLDelayandDisruptionProtocol:October2002.

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    4/31

    TheAnalysisandValuationofDisruption

    Page|4

    Variable costs are items such as the contractor's labour, equipment, and site overhead. Extensive

    literaturehasbeenpublishedaboutdelayclaims,whichprincipallyareclaimsrelatedtotheextended

    durationof thejobandthe resultingextendedsiteoverheadcosts. However,themajorvariable risk

    component on a construction project is labour, not extended site overhead. Equipment, on certain

    types of construction such as utility, heavy, and highway construction, can be a significant cost;

    however,equipmentcoststendtobeproportionaltolabourcosts. It isuncommontohavesignificantincreasesinequipmentcostswithoutsignificantincreasesinlabourcosts.

    Onmany constructionprojects, the largest single areaof costoverrun is in labour costs. This isnot

    surprisinggiventhatlabourisfrequentlythelargestvariablecostforacontractor. Claimsinvolvinglost

    productivityarefrequentlyreferredtoasdisruptionclaims.

    WhatisProductivity?

    Productivity = ProductionOutput/ResourceInput

    = 4mof4pipe/labourhour

    ProductivityRatio = ActualProductivity/PlannedProductivity

    = 3mperhr/4mperhr

    = 0.75

    WhyisProductivityImportant?

    HypotheticalProject

    Cost

    Components

    Labour 40% Oftenthelargestcostcomponent;

    Mostvolatilecostcomponent

    MostcriticalcosttocontrolMaterials 40%

    GeneralConditionsandIndirectCosts 10%

    Overhead 5%

    Profit 5%

    Total 100%

    Shouldtheaboveprojectsuffera12.5%overrunonthelabourcostcomponent:

    HypotheticalProjectCostComponents

    Labour 40% 45% Arisingfroma12.5%overrunon

    labourcontent

    Materials 40%

    GeneralConditionsandIndirectCosts 10%

    Overhead 5%

    Profit 5% 0%

    A12.5%

    overrun

    on

    labour

    content

    Wipesoutallprofitontheproject

    Total 100%

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    5/31

    TheAnalysisandValuationofDisruption

    Page|5

    Theexistenceofalabourcostoverrunisnotproofthatanevententitlingacontractortodamageshas

    occurred. Clearly labour cost overruns can occur for a variety of reasons,not allofwhichentitle a

    contractortocompensation.

    One of the most contentious areas in construction claims is the calculation or estimation of lost

    productivity. Unlikedirectcosts,lostproductivityisoftennottrackedorcannotbediscernedseparatelyandcontemporaneously. Asa result,bothcausationandentitlementconcerning the recoveryof lost

    productivitycanbedifficulttosatisfactorilyestablish.

    Compounding this situation, there are numerous ways to calculate lost productivity and no uniform

    agreement within the construction industry as to a preferred methodology of calculating lost

    productivity. Many methods of calculation are open to challenge with respect to their validity and

    applicabilitytoparticularcases,thusmakingsettlementofthe issueonaparticularprojectpotentially

    problematic.2

    Withinthepast20years,therehasbeensignificantresearchinconstruction labourproductivitywhich

    providesan

    increasing

    body

    ofempirical

    data

    astothe

    effects

    ofvarious

    factors

    on

    construction

    labour

    productivity. Someofthedifficultiesinapplyingthatdatatoaspecificprojectisoutlinedherein.

    Background

    Projectchanges,disruptions,cumulative impacts,andfactorsaffecting labourproductivityhavestrong

    interrelationships. Theyalsoplayavitalroleinestablishingliability,causation,andresultantlossinlost

    productivityclaims. Change isonecrucial factor ina rangeof factors influencing labourproductivity.

    Thefollowingisabriefdiscussionoftheseconcepts.

    FactorsAffectingLabourProductivity

    Labour productivity is a function of various controllable and uncontrollable factors. Schwartzkopf3

    listedthesefactorsundersixgroupscomprising:

    (1) Scheduleacceleration;

    (2) Changeinwork;

    (3) Managementcharacteristics;

    (4) Projectcharacteristics;(5) Labourandmorale;and

    (6) Projectlocation/externalconditions.

    2ConstructionIndustryInstitute,AnAnalysisoftheMethodsforMeasuringConstructionProductivity,SD13,Austin,Texas,

    1984.3Schwartzkopf,W.(1995).Calculatinglostlaborproductivityinconstructionclaims,Wiley,NewYork.

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    6/31

    TheAnalysisandValuationofDisruption

    Page|6

    Borcherding and Alarcon4 present a comprehensive review of quantitative information on factors

    influencing productivity. In addition, they categorised themajor components ofproductivity loss as

    waitingoridle,travelling,workingslowly,doingineffectivework,anddoingrework.5

    As noted previously, a number of factors may influence the actual productivity achieved on a given

    project:

    Figure:Examplefactorsaffectingproductivity6

    Clearly not all disruption attracts the paymentof compensation. The contractormay beentitled to

    compensationfortheeffectsoflostproductivitytotheextentthatabreachofobligationexists,acausal

    linktotheoffendingpartycanbeestablishedandtheeffectsofthatdisruptioncalculatedappropriately.

    Moststandardformsofcontractdonotdealexpresslywithdisruption. Iftheydonot,thendisruption

    maybeclaimedasbeingabreachofthetermgenerallyimpliedintoconstructioncontracts,namelythat

    theEmployerwillnotpreventorhindertheContractorintheexecutionofitswork.7

    4Borcherding,J.D.,andAlarcon,L.F.(1991).Quantitativeeffectsonproductivity.Constr.Lawyer,11(1).

    5SpecificfactorsandtheirdescriptionsareavailableinBorcherding,J.D.,andAlarcon,L.F.(1991).Quantitativeeffectson

    productivity.Constr.Lawyer,11(1),MechanicalContractorsAssociationofAmerica(MCAA)(1994).Factorsaffectinglabor

    productivity.Laborestimatingmanual,bulletinNo.PD2,Rockville,Md.,13,Schwartzkopf,W.(1995).Calculatinglostlabor

    productivityinconstructionclaims,Wiley,NewYork,andAssociationfortheAdvancementofCostEngineering(AACE)

    International,Inc.(2004).Estimatinglostlaborproductivityinconstructionclaims.AACEInternationalRecommended

    PracticeNo.25R03.6Thefigurepresentedisintendedasillustrativeonlyofthetypeofmattersthatmayinfluenceproductivityonagivensite.

    AdaptedfromapresentationbyDr.IbbsMeasuringProductivityforImprovedProjectPerformance,2009.7SCLDelayandDisruptionProtocol:October2002.

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    7/31

    TheAnalysisandValuationofDisruption

    Page|7

    ProjectChange

    Whilstanumberofthefactorsimpactingonlabourproductivityonaprojectarereadilyidentifiable,the

    consequencesofchangeareoftenunderestimatedandthereforespecificallyreferencedhere.

    Change isnormallydefinedasanyeventthatresults inamodificationoftheoriginalscope,execution

    time,cost,and/orqualityofwork8. Therearegenerallyfivetypesofchanges,namely:

    Changeinscope; Differingsiteconditions; Delays; Suspensions;and Acceleration.

    Thecostsofperformingchangedworkconsistofboth:

    (1) Thosecostsdirectlyrelatedtotheaccomplishmentofthechangedwork;and

    (2) Thosecostsarisingfromtheinteractionbetweenthechangedworkandunchangedwork9.

    Notwithstandingthatmostformsofcontractrecogniseandprovideforthevaluationofworkrelativeto

    the circumstances under which it is being executed, this second aspect is often significantly

    underestimatedorundervaluedbybothContractorsorEmployersandtheirRepresentatives.

    Thecostsandscheduleimpactsofachangeoccurinfourphases:

    PhaseOne is the time prior to the recognition of the change. An example would be a tradesman

    determining that the plans do not fit the situation encountered. The tradesman first attempts to

    determine if he is misreading the plans, then will seek direction from the supervisor who, if the

    supervisorcannotresolvetheproblem,willthenseekdirectionfromtheengineerortheowner. Aftersomeperiodoftime,aclarificationmaybeissued. Itmaybedeterminedthatachangeisnecessaryto

    deal with the situation. During the period before a change is recognised, costs and delays can be

    incurred. The process of finding a problem and implementing the solution is outlined in summary

    below10.

    8Ibbs,C.W.,andAllen,W.E.(1995).Quantitativeimpactsofprojectchange.;Revay,S.O.(2003).Copingwithchanges.AACEInt.Transactions,CDR.25,17.9TripleASouth,ASBCANo.46866,943BCA27,194,at135,523.

    10DevelopedfromWilliamSchwartzkopf,CalculatingLostLabourProductivityinConstructionClaims,2

    ndEdition,Aspen.

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    8/31

    TheAnalysisandValuationofDisruption

    Page|8

    Attachment1presentsalargerscaleoftheaboveprocessdiagramme.

    PhaseTwooccurs after theneed tomakea change is recognised. During thisperiod,materials are

    procured and the work is scheduled. Tradesmen may either be doing other work while waiting to

    performthechangeorworkingaroundthechange. Eitheroftheseactionscancauseinefficiencies.

    PhaseThree is the actualexecutionof the changedwork. The costs incurredduring thisphase are

    generallyreferredtoasthedirectcostofthechange. Thesecostsrepresentthetimerequiredandcost

    toperformthechangedwork.

    PhaseFourrepresentstheworkperformedafterthechangedworkhasbeenperformed. Thecostand

    scheduleeffectsduringthisphaseandthefirstphaseare indirectandareoftenreferredtoas impact

    costs. The amount of these impact costs is often the subject of considerable disagreement. By

    comparison,thedirectcostsduringthethirdphasecanfrequentlybemeasuredand,therefore,thecost

    of the labour,materials,equipment,andother itemscanbedetermined. Ifaproject is impactedby

    multiplechanges,itmaybenecessarytoanalysetheeffectofallofthechangessimultaneouslybecause

    oftheinteractionofthevariouschanges.

    ExtentofProjectChange

    The degree of project change varies according to each project but can be significant. Among 24

    constructionprojectsinwesternCanada,projectcostsincreasedbyatleast30%formorethanhalfand

    60%onathirdofprojects11. Severalprojectssuffereddelaysover100%. AstudyoftheJointLegislative

    AuditandReviewCommission12onapproximately300 roadconstructionprojects inVirginia revealed

    thattheaveragefinancialprojectchangewasmorethan11%.

    The amount and timing of change are also significant factors affecting productivity. Analysis of 90

    constructiondisputesin57independentprojects13showedthattherewasasignificantdirectcorrelation

    11Semple,C.,Hartman,F.T.,andJergeas,G.(1994).Constructionclaimsanddisputes:Causesandcost/timeoverruns.J.

    Constr.Eng.Manage.,120(4),785795.12JointLegislativeAuditandReviewCommission(JLARC).(2001).ReviewofconstructioncostsandtimeschedulesforVirginia

    highwayprojects.HouseDocumentNo.31,CommonwealthofVirginia.13Leonard,C.A.(1987).Theeffectofchangeordersonproductivity.RevayRep.,6(2),14.

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    9/31

    TheAnalysisandValuationofDisruption

    Page|9

    between the percentage of change order hours to contract hours and the percentage of lost

    productivity. Ibbs14foundthat:

    (1) Thegreatertheamountofchange,thelesstheefficiencyis;and

    (2) Lateprojectchangemoreadverselyaffectslabourproductivitythanearlychange.

    Thisfindingwasalsoconfirmedbylaterstudies

    15

    .

    DisruptionsandCumulativeImpacts

    InCoastalDryDock&RepairCorp.,disruptionisnotedasthecosteffectupon,ortheincreasedcostof

    performing, the unchanged work due to a change in contract16. In some studies17, disruptions are

    definedastheoccurrenceofeventsthatareacknowledgedtonegativelyimpactonlabourproductivity.

    Morebroadly,theAACE;RecommendedPracticestandard18definesdisruptionsasanactionorevent

    whichhindersaparty fromproceedingwith theworkor someportionof theworkasplannedoras

    scheduled.

    As noted previously, disruptions can be caused by change. These changes can reduce labour

    productivityandextendtheprojectduration19. Disruptionscausedbychangecanbebothforeseeable

    andunforeseeable. Theforeseeableorlocaldisruptionscanoccuratthesametimeandeitherthesame

    place or within the same resource as the changed work, whereas unforeseeable or cumulative

    disruptionscanalsooccurata timeorplace,orwithinresources,different from thechangedwork20.

    Thewordscumulativedisruptionandcumulativeimpactcanbeusedinterchangeably.

    Cumulativeimpacthasbeendescribedasbeingtheunforeseeabledisruptionofproductivityresulting

    fromthesynergisticeffectofanundifferentiatedgroupofchanges. Cumulativeimpact isreferredto

    asthe rippleeffectofchangesonunchangedwork thatcausesadecrease inproductivityand isnot

    analysed in termsof spatialor temporal relationships21. Jones22argued thatwhen theBoard states

    thatcumulative impactcannotbeanalysed intermsofspatialortemporalrelationships, itmeansthat

    cumulativeimpactcostscannotbesecuredwithinindividualcontractchanges.

    Pricing of the direct impact due to local disruptions and cumulative impacts due to cumulative

    disruptionsisdifferent. Thedirectimpactcostsarepreparedonaforwardpricingbasis. Thecumulative

    impact costs,on theother hand, aremore oftenpricedon abackwardpricingbasis as a contractor

    cannotforeseeorreadilyquantifytheimpact. Inotherwords,acumulativeimpactclaimaddressesthe

    14Ibbs,C.W.(1997).Quantitativeimpactsofprojectchange:Sizeissues.J.Constr.Eng.Manage.,123(3),308311,Ibbs,W.

    (2005).Impactofchangestimingonlaborproductivity.J.Constr.Eng.Manage.,131(11),12191223.15E.g.,Hanna,A.S.,Russell,J.S.,Gotzion,T.W.,andNordheim,E.V.(1999).Impactofchangeordersonlaborefficiencyfor

    mechanicalconstruction.J.Constr.Eng.Manage.,125(3),176184.16CoastalDryDock&RepairCorp.,ASBCANo.36754,911BCA23,324,at116,989,1990.

    17Thomas,H.R.,andNapolitan,C.L.(1995).Quantitativeeffectsofconstructionchangesonlaborproductivity.J.Constr.Eng.

    Manage.,121(3),290296.;Thomas,H.R.,andRaynar,K.A.(1997).Scheduleovertimeandlaborproductivity:Quantitative

    analysis.J.Constr.Eng.Manage.,123(2),181188.18AssociationfortheAdvancementofCostEngineering(AACE)International,Inc.(2004).Estimatinglostlaborproductivityin

    constructionclaims.AACEInternationalRecommendedPracticeNo.25R03.19Hanna,A.S.,Lotfallah,W.B.,andLee,M.J.(2002).Statisticalfuzzyapproachtoquantifycumulativeimpactofchange

    orders.J.Comput.Civ.Eng.,16(4),252258.

    20Finke,M.R.(1998).Abetterwaytoestimateandmitigatedisruption.J.Constr.Eng.Manage.,124(6),490497.21CentexBatesonConstructionCo.,VABCANo.4613,991BCA30,153,at149,259,1998.

    22Jones,R.M.(2001).Lostproductivity:Claimsforcumulativeimpactofmultiplechangeorders.PublicContractLawJ.,31(1),

    146.

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    10/31

    TheAnalysisandValuationofDisruption

    Page|10

    changedworkseffectonworkingconditionsthatwillindirectlyinfluencetheunchangedwork,whereas

    adirectimpactclaimcoverstheimpactofchangedworkonunchangedwork23.

    TheAACERecommendedPractice24notes:contractorstendtoblamesuchlossesonownersandaskto

    becompensated. Owners,ontheotherhand,oftenblameabadbidorpoorprojectmanagementand

    thus deny additional compensation for lost productivity. Given this situation the root cause of lostproductivityisfrequentlyamatterindisputebetweenowners,contractorsandsubcontractors.

    This paper seeks to set out appropriate approaches and recognised practices designed to overcome

    thoseinherentobstaclesinanalysingandquantifyingtheeffectsofsuchdisruption.

    MethodsofQuantifyingLostProductivity

    Theconstructionindustryhasdevelopedandemployedanumberofmethodologiesforestimating lost

    labourproductivity. Basedon theappropriatedata input, thesemethodscanbeclassified intothree

    majorgroups;namely:

    (1) Projectpracticebased;

    (2) Industrybased;and

    (3) Costbasedmethods.

    The detailed data requirements and corresponding judicial acceptance generally increase as the

    approachadoptedmovesfromcostbasedtoprojectpracticebasedmethods.

    23Jones,R.M.(2001).Lostproductivity:Claimsforcumulativeimpactofmultiplechangeorders.PublicContractLawJ.,31(1),146.24AssociationfortheAdvancementofCostEngineering(AACE)International,Inc.(2004).Estimatinglostlaborproductivityin

    constructionclaims.AACEInternationalRecommendedPracticeNo.25R03.

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    11/31

    TheAnalysisandValuationofDisruption

    Page|11

    The above figure25 outlines the relationships between the availability, quality and providence of the

    contemporaneousprojectdocumentation,thereliabilityofthemethodsofquantifyinglostproductivity

    and the cost and expertise generally required to record, prepare, and document the quantum of

    damagesderivedthereby.

    Thehorizontalaxisreferstotheattributesoftheprojectdata. Thetwoverticalaxesrefertoattributes

    ofthemethodsavailableforcalculatinglostproductivity.

    Themethodslistedtypicallyincreaseinprecisionastheymovefromthetoptothebottominthegraph

    andfromlefttoright,i.e.fromatotalcostapproachtoameasuredmileapproach. Thisalsoreflectsthe

    orderofpreferenceintheresearchliterature26.

    The cost,effort,andexpertise required forquantifying the lossnormally increases from left to right.

    Horizontallytheavailabilityandqualityofcontemporaneousdocumentationrequired increasesasthe

    moredetailedmethodsareused.

    Beforeembarkingonaproductivitylossanalysis,theclaimantshouldcarefullyconsiderwhethertheloss

    canberecastasanimpactofspecificallydefinableextrawork. Ifthatisthecase,thenthatproductivity

    lossshouldbeincorporatedintotheestimatefortheextraworkandresolvedinthatmanner.

    25AdaptedfromQuantifiedImpactsofProjectChange,Ibbs,Long,NguyenandLee,JournalofProfessionalIssuesinEngineeringEducationandPractice2007.26AssociationfortheAdvancementofCostEngineering(AACE)International,Inc.(2004).Estimatinglostlaborproductivityin

    constructionclaims.AACEInternationalRecommendedPracticeNo.25R03.

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    12/31

    TheAnalysisandValuationofDisruption

    Page|12

    Tribunalsappeartobemorefavourablyimpressedbydamagecalculationsrelateddirectlytotheproject

    in dispute and supported by contemporaneous project documentation.27 Therefore, recommended

    practiceforpreparingalostproductivitycalculationistoutilise,ifpossible,oneofthetechniqueslisted

    inthecategoryofProjectPracticeBasedMethodssetoutbelow.

    Thesemethodologiesareprojectspecificandsupportedbypeopleandrecordsdirectlyinvolvedatthetime of the dispute or the disputed work. That direct relationship to the work and the events in

    question are what gives the approach its appeal to a tribunal in favour of a more theoretical or

    generalistapproach.

    Ifthere is insufficient informationavailable fromcontemporaneousprojectdocumentationtosupport

    oneof these techniques, recommendedpractice then is touseoneof themethods listedunder the

    category ProjectComparison Studies. These methodologies, too, are project specific but rely upon

    differentformsofcontemporaneousdocumentation.

    Unfortunatelyappropriatecontemporaneousprojectdocumentationisnotalwaysavailable. Estimated

    costs

    are,

    of

    course,

    recognised

    as

    a

    legitimate

    way

    to

    calculate

    damages

    once

    entitlement

    and

    causation are sufficiently proven. Legal systems generally recognise that damages cannot always be

    calculatedwithmathematical certainty. Further, it is recognised that contractors frequentlyhave to

    prepareand livewithcostestimates. Therefore, intheabsenceofotherproofofdamages,the legal

    systemmayallowestimatestoestablishdamages.28

    Estimated damages may be acceptable, under appropriate circumstances, but are more subject to

    challenge than direct project costs. Of the damage calculation and estimating methods available,

    recommended practice is to use first, one of the studies listed in the Specialty Industry Studies

    category. These are specialty studies of specific types of problems and are, generally, based on a

    numberofactualconstructionprojects. Ofcourse,toutiliseoneofthesestudies,thecausationofthe

    lostproductivityshouldbeappropriatefortheparticularproblemstudied.

    Ifnoneofthespecialisedstudiesareapplicabletothesituationinquestionrecommendedpracticeisto

    utiliseoneofthestudieslistedintheGeneralIndustryStudiescategories.

    Thesestudiesaresubjecttogreaterchallengebecausetheyareindustrywideandnotsubjectorproject

    specific. Inaddition,thebasicdataissometimesderivedfromanonconstructionenvironment. Finally,

    thesestudieswere largely intendedasforwardpricingguides,assuch, their intendedpurposewas

    distinctlydifferent.

    Notwithstanding these criticisms, in the absence of more reliable techniques, claimants have been

    allowedtousethesestudiesonceentitlementandcausationhavebeensufficientlyproven.

    If the contractorpreparing a lostproductivitydamages calculation candemonstrateentitlementand

    causationbutisunabletoutiliseoneofthetechniquespreviouslynoted,recommendedpracticeisthen

    touseoneofthemethodslistedintheCostBasiscategory.

    Tosuccessfullyutiliseoneof these techniques, theclaimantgenerallyhas toovercomesomedifficult

    legalhurdles,discussedinmoredetailbelow.But,ifthesechallengescanbemet,thenthesetechniques

    maybeallowedasameasureoflostproductivity.

    27ForamorethoroughdiscussionofthispointseeSchwartzkopf,WilliamandJohnJ.McNamara,CalculatingConstruction

    Damages,2ndEdition,AspenLaw&Business,NewYork,2001,1.03.Seealso,Wickwire,JonM.,ThomasJ.Driscoll,StephenB.

    HurlbuttandScottB.Hillman,ConstructionScheduling:

    Preparation,

    Liability

    and

    Claims,

    2ndEdition,AspenLaw&Business,

    NewYork,2003,12.04et.seq.Seealso,RoyS.Cohen,SurveyofCourtsReactionstoClaimsforLossofProductivityand

    Inefficiency,Session612,ABAPublicConstructionSuperconference,December10,1998.28Schwartzkopf,ibid,1.03[B].

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    13/31

    TheAnalysisandValuationofDisruption

    Page|13

    ProjectPracticeBasedMethods

    Measured mile analysis, baseline productivity analysis, system dynamics modelling, earned value

    analysis, sampling studies, and comparison studies are all project practice based approaches whose

    calculationsaredrawnfromtheprojectrecords.

    Assuch,theyareexpectedtobemorecrediblethanalternativegeneralapproaches. Courtsandother

    tribunalsthereforepreferestimationsofdamages thataredirectly linked to thedisputedprojectand

    supported by its contemporaneous documentation29. The types of contemporaneous documentation

    requiredaregenerallydifferentfromonemethodtoanother.That is,themostsuitablemethod fora

    givenprojectcanonlybedeterminedbasedupontheavailableprojectdata.

    MeasuredMileAnalysis

    Themeasuredmileapproach30

    iswidelyacknowledgedasthemostacceptablemethod forcalculatinglostproductivitycosts.

    Theanalysiscomparesidenticaltasksinimpactedandnonimpactedperiodsoftheprojecttoestimate

    theproductivitylosscausedbytheimpactofaknownseriesofevents31. Itisbasedonanextrapolation

    ofactualworkhoursspent32. Themeasuredmilecalculationmightincludecomparisonofsimilarwork

    activities and achieve court acceptance33. The attraction of the measured mile is that the actual

    contractperformanceratherthanthe initialestimate isusedforthecalculations. Assuchitcompares

    actualperformanceonsitewithactualperformance,notsometheoreticalplannedperformance.

    29AssociationfortheAdvancementofCostEngineering(AACE)International,Inc.(2004).Estimatinglostlaborproductivityin

    constructionclaims.AACEInternationalRecommendedPracticeNo.25R03.30Sometimesreferredtoasdifferentialstudiesormeasuredproductivitycomparisons.

    31Schwartzkopf,W.(1995).Calculatinglostlaborproductivityinconstructionclaims,Wiley,NewYork.32Zink,D.A.(1986).Themeasuredmile:Provingconstructioninefficiencycosts.CostEng.,28(4),1921.

    33Jones2003;CalveyandZollinger2003;AssociationfortheAdvancementofCostEngineering(AACE)International,Inc.

    (2004).Estimatinglostlaborproductivityinconstructionclaims.AACEInternationalRecommendedPracticeNo.25R03.

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    14/31

    TheAnalysisandValuationofDisruption

    Page|14

    The above illustrates a nondisrupted period of excavation and a later disrupted period where the

    volumeofexcavationperunitoftimehasbeenadverselyaffectedbyoperationalandaccessrestrictions

    imposedupontheContractor.

    Thereareseveralassumptionsandprerequisitesunderlyingthemeasuredmiletechnique:

    First,theremustbeanonimpactedorleastimpactedperiod,socalledmeasuredmileperiod,forthespecifictypeofworkbeingassessed. Theadversefactorsaffectingproductivityduring

    themeasuredmileperiod,ifany,mustbesolelyattributabletothecontractor;

    Second,thelengthofthisperiodshouldbesignificantcomparedtotheimpactedperiodandthecourseofwork. Itwouldbeunreasonabletoextrapolate2%ofprogress into80%ofexpected

    costs34;

    Third,sufficientamountsofcontemporaneousprojectdatashouldbeavailablefortheanalysis.At most the physical units of work completed have to be periodically recorded so that the

    cumulativelabourhourscanbeplottedthroughthecourseofwork.

    Fourth, the project data are assumed to be error free. That is, the contemporaneousdocumentationmustbeaccuratelyrecordedbythecontractor;and

    Finally, all disruptions during the impacted period are due to one partys (say, the owners)actionsorinactions. Itisextendedthatotherfactorsunrelatedtotheclaimedimpactshaveto

    beaccountedforandremoved fromthe impactedperiodanalysistothedegreethese factors

    occurredduringthemeasuredmileperiod35.

    34Zink,D.A.(1986).Themeasuredmile:Provingconstructioninefficiencycosts.CostEng.,28(4),1921.

    35AssociationfortheAdvancementofCostEngineering(AACE)International,Inc.(2004).Estimatinglostlaborproductivityin

    constructionclaims.AACEInternationalRecommendedPracticeNo.25R03.

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    15/31

    TheAnalysisandValuationofDisruption

    Page|15

    Considerable limitations are embedded in these assumptions. The measured mile analysis becomes

    unreliableorevenimpossiblewheneitheranonimpactedperiodsimplydoesnotexistorthatperiodis

    not sizeable. The fact that the analysis requires identical or substantially similar activities for

    comparisonscanhamperitsapplicabilityasthemethodisinappropriateforuniqueandcomplextasks36.

    Thereliabilityofthemethod ischallenged if inaccuratecontemporaneousprojectdata isused forthe

    analysis. Unfortunatelyreportingerrorsarecommonplaceinprojects

    37

    .

    Otherlimitationsaremore implicit. Projectedcumulativelabourhourscanbeextrapolateddifferently

    duetodifferentoptionsofthetimeframe.GulezianandSamelian38pointedoutthat:

    (1) Different time frame and segments selected within the measured mile period may produce

    differentnumbers;and

    (2) Variationofdailyproductivity isconcealedtovaryingextentsbythecumulatingnatureofthe

    measuremileanalysis.

    Theyalsoarguethatthemeasuredmiledoesnotnecessarilyreflecttheproductivitynormallyachieved

    bythecontractorduetothesmoothingeffectofsuccessivecumulativedataandthenatureofvariation

    inunit

    productivity

    values.

    Inaddition,

    the

    two

    average

    productivity

    rates,

    which

    are

    readily

    calculated

    andcompared fornonimpactedand impactedperiods,maymaskthefactthatacontractorgenerally

    doesnotattainasinglerateofproductivitythroughoutatimeperiod39.

    ExampleMeasuredMileCalculationComparisonofUnitCostforImpactedandNonimpactedAreas40

    TheContractorplannedtoperformallofthecrosstaxiwaypavingonanuninterruptedbasis,andtouse

    pavingmachinesforalloftheconcretepavingexceptforthefilletareas,whichweretobedonebyhand

    pours.

    Becauseoftheengineer'schanges inthetaxiway lightingandarequirementtoputpavementsensing

    devices in the concrete for a longrangepavementwear study, theworkon the south taxiwayswas

    performedona sporadicand intermittentbasis. In fact,muchof itwasperformedon ahandbasis

    ratherthanusingthelargeconcreteslipformpavingspread. Thiscausedasubstantiallygreatercostof

    performingtheworkonthesouthtaxiwaysthancouldbereasonablyanticipated.

    Theworkon thenorth taxiwayswasperformedundernormalconditions, since the changeswereall

    made prior to the start ofworkon thenorth taxiways and the pavementwear studywould not be

    conducted on the north taxiways. Runway's cost as a result of these changes can be calculated by

    comparingtheunitcostoflabourforthenorthtaxiways(whichwereessentiallynonimpacted)withthe

    unit cost of labour for the south taxiways (whichwere substantially impacted). Both the north and

    south taxiwayswere performed during normal paving periods under good weather conditions. The

    samelabourforceandthesameequipment(withtheexceptionthattheslipformpavingspreadcould

    notalwaysbeusedduetothechange)wasusedonbothareas. However,theunit labourcostonthe

    north taxiways,whichwerenonimpacted,was approximatelyhalfof the cost incurredon the south

    taxiways.

    36Loulakis,M.C.,andSantiago,S.J.(1999).Gettingthemostoutofyourmeasuredmileapproach.Civ.Eng.(N.Y.),69(11),

    69.37Thomas,H.R.,andSanvido,V.E.(2000).Quantificationoflossescausedbylaborinefficiencies:Whereistheelusive

    measuredmile?Constr.LawBus.,1.

    38Gulezian,R.,andSamelian,F.(2003).Baselinedeterminationinconstructionlaborproductivitylossclaims.J.Manage.Eng.,19(4),160165.39Finke,M.R.(1998).Statisticalevaluationsofmeasuredmileproductivityclaims.CostEng.,40(12),2830.

    40DrawnfromSchwartzkopf,CalculatingLostLaborProductivityinConstructionClaims,2

    ndEdition.

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    16/31

    TheAnalysisandValuationofDisruption

    Page|16

    On the above information and the following simplistic analysis, theContractor isentitled to bepaid

    $549,155inadditionalcoststhatitincurred,asillustratedinthefollowingformula:

    ActualNorthCross

    TaxiwayProduction

    ActualSouthCross

    TaxiwayProduction

    Hours 10,116.00 51,969.00

    SquareMetresProduced 102,256.00 281,746.60

    Hours/SquareMetre .099 .184

    IncreaseinUnitLabourRate 0.086

    QuantityAffectedbyBlockoutandLightChange 281,746.60

    IncreasedRate 0.086

    ManhourIncreaseDuetoChange 24,096.32

    LabourCostperManhour $22.79

    TotalAdditionalLabourCost $549,155.17

    BaselineProductivityAnalysisThisapproachwasproposedinordertoavoidsomeofthelimitationsandimpracticalassumptionsofa

    currentmeasuredmileanalysis. Similartothemeasuredmilemethod,baselineanalysisreliesonthe

    contractors actual performance of the project being analysed. A central point of this analysis is to

    establish the baseline productivity. It represents the best and most consistent productivity the

    contractorwasable toachieveon theproject41. Analysinga42projectdatabase42 revealed that the

    baseline productivity mainly depends on the complexity of the design and the work methods used.

    Unlike the measured mile analysis, a baseline analysis neither needs defined nonimpacted andimpactedperiodsnorbeconsecutivereportingperiodsinthebaselinetimeframe43. Inotherwords,the

    baselineanalysiscanbemoreflexibleandhencemoreapplicableincurrentpractice44.

    However, the process has not obtained consensus among studies though it is generally agreed that

    usingindividualproductivityvaluesisbetterthancumulativeproductivityforthecalculations. Thismay

    be due to varying views on the baseline productivity. Unlike Thomas and Zavrki45, Gulezian and

    Samelian46 noted that the baseline productivity reflects the normal operating performance of a

    contractor.

    41Thomas,H.R.,andZavrki,I.(1999).Constructionbaselineproductivity:Theoryandpractice.J.Constr.Eng.Manage.,

    125(5),295303.42Thomas,H.R.,andZavrki,I.(1999).Constructionbaselineproductivity:Theoryandpractice.J.Constr.Eng.Manage.,

    125(5),295303.43Thomas,H.R.,andZavrki,I.(1999).Constructionbaselineproductivity:Theoryandpractice.J.Constr.Eng.Manage.,

    125(5),29530344AdeterminingprocessofthebaselineproductivitycanbefoundinThomasandZavrki(1999),ThomasandSanvido(2000),

    andGulezian,R.,andSamelian,F.(2003).Baselinedeterminationinconstructionlaborproductivitylossclaims.J.Manage.

    Eng.,19(4),160165.

    45Thomas,H.R.,andZavrki,I.(1999).Constructionbaselineproductivity:Theoryandpractice.J.Constr.Eng.Manage.,125(5),295303.46Gulezian,R.,andSamelian,F.(2003).Baselinedeterminationinconstructionlaborproductivitylossclaims.J.Manage.Eng.,

    19(4),160165.

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    17/31

    TheAnalysisandValuationofDisruption

    Page|17

    ThomasandZavrki47andThomasandSanvido48determinethebaselineproductivityasthemedianof

    the individualproductivityvalues inthebaselinesubset. GulezianandSamelian49calculate itasthe

    meanproductivityofthepointsfallingwithinthecontrollimitsafterapplyinganiterativeprocessofan

    individualscontrolcharttodealwithdifferentsourcesofvariationofperiodicallyreportedproductivity

    values.

    Althoughthebaselineanalysissolvesseveralproblemsassociatedwiththemeasuredmileapproach,it

    is still limited. The way of calculating the baseline productivity should be more scientific and

    straightforward, subject to properly dealing with the reliability of reported data, variation of

    productivityvalues,andcasuallinkagestodisruptionsandinefficiency. Someshortcomingsarerelated

    totheestablishmentofthebaselinesampleasinThomasandZavrki50andThomasandSanvido51.They

    are:

    (1) Thebaseline sample is identified according to thebestdailyoutput insteadof thebestdaily

    productivity;and

    (2) The 10% requirement for the baseline sample size is arbitrary andnot based upon scientific

    principles52.

    Inadditionitisagreedthatthebaselineanalysisisacauseandeffectanalysis,yetitisqualitativeorvery

    roughlyapproximate innatureas inThomas53. Therehasbeennosoundmethod forwhichdamages

    inducedbytheownerandcontractorareclassifiedandquantifiedduringadisputedperiod. Especially,

    multipleand/orsimultaneousownerandcontractorcauseddisruptionsarenotuncommoninreallife.

    SystemDynamicsModellingSystemdynamics(SD)modellinghasbeenemployedtounderstandthebehaviourofvariousnatural,

    social, and engineered systems54. Developed at MIT55 in the late 1950s, SD is widely used in the

    defenceindustry.

    Anumberofdelayanddisruptionclaimshavebeensuccessfully settledwithextensive supportofSD

    modelling. OnesuchsuccessfulstorywasthedevelopmentandapplicationofaSDcomputersimulation

    modeltoresolvea$500millionshipbuilderclaimconsistingofthedirectimpactandtherippleeffects

    between Ingalls Shipbuilding and the U.S. Navy in the 1970s56. Other successful applications of SD

    modellingindelayanddisruptionclaimsandlawsuitshavealsobeenreported57.

    47Thomas,H.R.,andZavrki,I.(1999).Constructionbaselineproductivity:Theoryandpractice.J.Constr.Eng.Manage.,

    125(5),295303.48Thomas,H.R.,andSanvido,V.E.(2000).Quantificationoflossescausedbylaborinefficiencies:Whereistheelusive

    measuredmile?Constr.LawBus.,1.49Gulezian,

    R.,

    and

    Samelian,

    F.(2003).

    Baseline

    determination

    inconstruction

    labor

    productivity

    loss

    claims.

    J.Manage.

    Eng.,

    19(4),160165.50Thomas,H.R.,andZavrki,I.(1999).Constructionbaselineproductivity:Theoryandpractice.J.Constr.Eng.Manage.,

    125(5),295303.51Thomas,H.R.,andSanvido,V.E.(2000).Quantificationoflossescausedbylaborinefficiencies:Whereistheelusive

    measuredmile?Constr.LawBus.,1.52Ibbs,W.,andLiu,M.(2005).Improvedmeasuredmileanalysistechnique.J.Constr.Eng.Manage.,131(12),12491256.

    53Thomas,H.R.(2005).Causationandcauseeffectanalyses.Constructionclaimsonline,WPL,3(4).

    54Itsprinciples,concepts,andtoolscanbefoundinForrester,J.(1961).Industrialdynamics,PegasusCommunications,

    Waltham,Mass,Richardson,G.,andPugh,A.(1981).Introductiontosystemdynamicsmodelingwithdynamo,Pegasus

    Communications,Waltham,Mass,andSterman,J.D.(2000).Businessdynamics,systemthinking,andmodellingforacomplex

    world,IrwinMcGrawHill,NewYork.55MassachusettsInstituteofTechnology.

    56Cooper,K.G.(1980).Navalshipproduction:Aclaimsettledandaframeworkbuilt.Interfaces,10(6),2036.

    57Ackermann,F.,Eden,C.,andWilliams,T.(1997).Modelingforlitigation:Mixingqualitativeandquantitativeapproaches.Interfaces,27,4865;Eden,C.,Williams,T.,Ackermann,F.,andHowick,S.(2000).Onthenatureofdisruptionanddelay.J.

    Oper.Res.Soc.Jpn.,51,291300;Williams,T.M.,Ackermann,F.,andEden,C.(2003).Structuringadisruptionanddelay

    claim.Eur.J.Oper.Res.,148,192204.

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    18/31

    TheAnalysisandValuationofDisruption

    Page|18

    The SD approach seeks to create a computer model of the project that maps all relationships and

    feedbackloopsinacomprehensivedynamicmodel. Asimplisticrepresentationofthatmodelmaylook

    somethinglike:

    Thesequenceofmodelledeventsmayrunalongthefollowinglines:

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    19/31

    TheAnalysisandValuationofDisruption

    Page|19

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    20/31

    TheAnalysisandValuationofDisruption

    Page|20

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    21/31

    TheAnalysisandValuationofDisruption

    Page|21

    Problemsearlyintheprojectpropagatetodownstreamwork. Changeimpactsoriginallyisolatedinthe

    engineeringphasemayendupaffectingconstructionaswell. Thereanothersimilarsetofdynamicsis

    triggered, with the addition of some physical impacts aswell, such as crowding (congestion, trade

    stacking). Allthesedynamiceffectsinconstruction,astheyaffectlabourproductivity,canamplifythe

    magnitudeofdisruptionimpactsfromchanges.

    IllustrationsdrawnfromProjectChanges:Sources,Impacts,Mitigation,Pricing,Litigation&Excellence,PAConsultingGroup

    ByusingSDmodellingquantificationofcumulative impactscanovercomeoneofthelimitationsofthe

    measured mile and baseline analyses. As noted earlier the two methods are not able to easily

    accommodatemultipleand/orconcurrentdisruptionscausedbydifferentprojectparties. SDmodels

    canquantifyownerresponsibledelayanddisruptionimpactcostsanddemonstratethecauseandeffect

    relationshipofthecumulativeimpacts58. AkeyfeatureofSDsimulationmodellingisthatitallowsand

    directsansweringapoolofwhat ifquestionssuchas:What ifoneparticularcategoryofdisruptionshadnotoccurredbutallothershad? Whatiftheownerinterventionshadnotoccurred?59. Inaddition,

    itvisualisescausalityandallows forvalidationofcausal logic inquantitative termsandagainstactual

    dataatanyperiodoftheprojectindispute60.

    SD modelling has not achieved popularity in construction disputes compared to the measured mile

    analysis.

    58Cooper,K.G.(1980).Navalshipproduction:Aclaimsettledandaframeworkbuilt.Interfaces,10(6),2036.

    59Cooper,K.G.(1980).Navalshipproduction:Aclaimsettledandaframeworkbuilt.Interfaces,10(6),203;Eden,C.,

    Williams,T.,andAckermann,F.(2005).Analysingprojectcostoverruns:Comparingthemeasuredmileanalysisandsystemdynamicsmodelling.Int.J.Proj.Manage.,23,135139.60Eden,C.,Williams,T.,andAckermann,F.(2005).Analysingprojectcostoverruns:Comparingthemeasuredmileanalysis

    andsystemdynamicsmodelling.Int.J.Proj.Manage.,23,135139.

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    22/31

    TheAnalysisandValuationofDisruption

    Page|22

    One main reason is that SD simulation models are not readily understood due to the dynamic

    complexity and quantitative nature of those models61. In addition, unless the SD model is properly

    validated,itispointless,barelycredible,andthereforeuseless.

    ValidationofaSDmodelisproblematicandtimeconsumingandrequiresextensiveexpertiseoftheSD

    methodology. Insomecircumstances,itisassumedthatthereasonablenessoftheoriginalestimateinSDmodellingcandraw inaccurateandunpersuasivequantumofdamages. Also,although thecausal

    coefficients indicating the relationshipsbetweenactivitiesarevery important to theaccuracyofaSD

    model,theyarenoteasytoestimate62.

    EarnedValueAnalysisProductivitymeasurement issometimesdifficultwhenthere is insufficient informationconcerningthe

    physicalunitsofwork installedon theproject. In these situations, a simplistic form63 of theearned

    valueanalysismethodcanbeutilisedtocalculateestimated labourhours.64 Thecontractorsestimate

    or alternatively themonetaryvalueofpayment applications, contract amountsorunitprices canbe

    used

    to

    determine

    labour

    hours,

    when

    they

    were

    expended

    and,

    possibly,

    on

    what

    activities.

    65

    Physical

    unitsofworkcompletedmultipliedbybudgetunitratescanbeusedtodetermineearnedhours. The

    earnedhoursare thencompared to theactualhoursexpended for theperiodof the impactand the

    differencebetweenthetwomaybeusedtocalculatetheproductivitylossexperienced.

    Earnedvaluemeasurementofcontemporaneousprojectdocumentation,suchaspercentagescomplete

    from schedule updates or payment applications can assist with calculating labour productivity.66

    Additionally, the claimant may calculate the actual revenue per hour of labour versus the planned

    revenueperhour,asanalternative.67 Earnedvalueanalysismayalsobeutilisedtocalculateestimated

    labourhours.68

    Whenusingtheearnedvalueanalysistechnique, it iscautionedthatthebudgetusedtogeneratethe

    earnedvaluemetricsbecarefullyreviewedandverifiedforreasonableness. Anyearnedvalueanalysis

    baseduponanunreasonablebudget ishighlysuspect. Finally, it isnoted thata fullyresource loaded

    (labourandquantities)CPMscheduleisagoodsourceforobtainingearnedvaluemetricsandallowsfor

    liketimecausationanalysis.

    An earned value analysis can also be used to estimate the cumulative impacts, especiallywhen the

    physicalunitsofwork completed havenotbeen recorded adequately for employing amore reliable

    methodlikethemeasuredmileandbaselineanalyses.

    61Howick,S.(2005).Usingsystemdynamicsmodelswithlitigationaudiences.Eur.J.Oper.Res.,162,239250.

    62Ibbs,W.,andLiu,M.(2005).Systemdynamicmodelingofdelayanddisruptionclaims.CostEng.,47(6),1215.

    63Theuseofthetermearnedvaluemeansdifferentthingstodifferentpeople.Inthiscontext,simplifiedearnedvalueis

    usedtodistinguishbetweenformEarnedValueasrequiredbytheUSGovernmentonmanyoftheirprojectsandearnedvalue

    aspracticedbymanyEPCcontractors.SeeforexampleKennethK.Humphreys,JelensCostandOptimizationEngineering,Third

    Edition,McGrawHill,NewYork,1991;JamesM.Neil,ConstructionCostEstimatingforProjectControl,PrenticeHall,Inc.,

    EnglewoodCliffs,NewJersey,1982;andSkillsandKnowledgeofCostEngineering,FifthEdition,AACEInternational,

    Morgantown,WestVirginia,2004.64SeeStumpf,George,R.,editor,AACEIProfessionalPracticeGuidetoEarnedValue,AACEI,Morgantown,WV,1999.

    65SeeCass,DonaldJ.,EarnedValueProgramsforDOEProjects,CostEngineering,Vol.42,No.3,February2000.

    66SeeFleming,QuentinW.andJoelM.Koppelman,EarnedValueProjectManagement,ProjectManagementInstitute,Upper

    Darby,PA.1996.67SeeMcCally,BobM.,DemonstratedLaborEfficiency:AnEffectiveCostControlandAnalyticalTool,CostEngineering,Vol.41,

    No.11,pp.3337,November1999.68SeeJonesandDriscoll,Ibid,pageB24.

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    23/31

    TheAnalysisandValuationofDisruption

    Page|23

    Foraproject,thedifferencebetweenearnedhoursdeterminedfromtheearnedvalueanalysismethod

    andactualhoursexpendedforanimpactedperiodcanbeusedtocomputetheinefficiencysuffered69.

    As anearned value analysis isbasedon thepercent complete and thebudget, the credibilityof the

    methodcanbequestionable. Thereasonsarethat:

    (1) The percent complete method is not as detailed and accurate as the physical units of work

    completedmethod

    70

    usedinthepreviousquantifyingmethods;and(2) Theoriginalestimate is likely tobeunsubstantiated.Anyearnedvalue analysis relyingonan

    unreasonablebudgetisverydoubtful71.

    SamplingMethodsTwo sampling methods used for estimating lost productivity are work sampling and craftsmen

    questionnairesamplingmethods. Introductiontothesemethodscanbefoundelsewhere72.

    Worksampling isamethod inwhicha largenumberofdirectobservationsoftradesmenaremadeto

    determinewhattheyaredoingatvariouspointsintime.WorksamplingisdefinedasAnapplicationof

    randomsampling

    techniques

    tothe

    study

    ofwork

    activities

    sothat

    the

    proportions

    oftime

    devoted

    to

    differentelementsofworkcanbeestimatedwithagivendegreeofstatisticalvalidity.73

    From these observations the claimant determines, on a percentage basis, how much time is spent

    betweendirectwork(payitemwork);supportwork(movingtoolsandmaterialstotheworklocation);

    ordelays(timewhennoworkisbeingperformed). Byperforminganumberofworksamplingstudies,

    the analyst can draw comparisons of productivity before and after known events, between work

    activitiesorcrews,etc. Worksamplinghasbeenofferedasameansofdeterminingproductivitylossbut

    itcanonlybeperformedduringthe lifeoftheprojectand isnotcompatiblewithahindsightanalysis

    effort.74

    The samplingmethodsare typically simpleand inexpensive toanalyse labourproductivity. Although

    theycanbeusedforlostproductivityclaims,theirtrustworthinessisnothighastheyareonlyasampled

    measureoflabourproductivity.

    For instance,anassumptionofworksamplingthatthere isapositiverelationshipbetweenproductive

    timeandlabourproductivitywasfoundtobefalse75.

    Thequestionnaireapproachallowscraftsmentoestimatetheamountoflostproductivetimeinthefield

    on a daily or weekly basis, identifying the reason for the lost time. While, perhaps, not the most

    scientificofstudies,thisiscontemporaneousdocumentationifadministeredproperly. Theclaimantcan

    thentietheresultsofsuchasurveytotheentitlementandcausationarguments.76

    69AssociationfortheAdvancementofCostEngineering(AACE)International,Inc.(2004).Estimatinglostlaborproductivityin

    constructionclaims.AACEInternationalRecommendedPracticeNo.25R03.70Schwartzkopf,W.(1995).Calculatinglostlaborproductivityinconstructionclaims,Wiley,NewYork.

    71AssociationfortheAdvancementofCostEngineering(AACE)International,Inc.(2004).Estimatinglostlaborproductivityin

    constructionclaims.AACEInternationalRecommendedPracticeNo.25R03.72e.g.,Oglesby,C.H.,Parker,H.W.,andHowell,G.A.(1989).Productivityimprovementinconstruction,McGrawHill,New

    York..73AmericanInstituteofIndustrialEngineers,AmericanNationalStandardZ94.11,IndustrialEngineeringTerminology1120

    (1989).74SeeFwuShiunLiouandJohnD.Borcherding,WorkSamplingCanPredictUnitRateProductivity,JournalofConstruction

    EngineeringandManagement,Vol.112,No.1,page90(March,1986).Seealso,Jenkins,JamesL.andDarylL.Orth,Productivity

    ImprovementThrough

    Work

    Sampling,

    CostEngineering,Vol.46,No.3,pp.2732,(March2004).

    75Thomas,H.R.(1991).Laborproductivityandworksampling:Thebottomline.J.Constr.Eng.Manage.,117(3),423444..

    76LuhMannChangandJohnD.Borcherding,EvaluationofCraftsmenQuestionnaires,JournalofConstructionEngineeringand

    Management,Volume111,No.4,page426.(December,1985)

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    24/31

    TheAnalysisandValuationofDisruption

    Page|24

    AvariationofthismethodistheuseofaCraftsmenQuestionnaireattheendofthejob,toconfirmor

    modify a productivity loss analysis performed utilising another method. For example, a Board of

    ContractAppealscaseallowedaCraftsmenQuestionnairetobeusedasamodifierofanindustrywide

    studyandawardedlostproductivitycoststoamechanicalsubcontractoronthisbasis.77

    ComparisonStudies

    Comparisonstudiescanbeclassifiedascomparableworkandcomparableprojectstudies. AACE78also

    classifiesthecomparableworkstudiesintwoforms:

    (1) The contractor estimates lost productivity on the impacted period, and then locates an

    analogousorsimilarworkactivityonthesameproject,whichwasnonimpactedandcalculates

    itsproductivity;and

    (2) The contractor compares productivities during the impacted period and of similar but non

    impactedworkperformedbyanothercontractoronthesameproject.

    Comparable project studies are used to contrast the productivities of similar work activities on the

    projectbeinganalysedandasimilarproject.

    Thesuccessfuluseofcomparisonstudiescanbedifficult tosecuregiventhat thedefinitionofsimilar

    workorasimilarprojectarerarelyagreedbyprojectparties. Assuchbaselineproductivityanalysisor

    systemdynamicsmodellingshouldbeconsideredforsizableclaimswhenthereisnoclearnonimpacted

    period. Theothermethods canbe adopted as complementary andused to further substantiate the

    outcomeresultsachieved. Theremaybetimeswhentheyarethebestalternativeavailable.

    IndustryBasedMethods

    Specialty industryandgeneral industrystudiesarecalledthe industrybasedmethods. Astheirnames

    imply a specialty, industry study employs results of specific studies directly related to the cause of

    damages,whereas a general industry study is based on industrywidemanuals and/or reports. The

    specific studies can be about acceleration, learning curve, overtime, weather, and so forth79. The

    industrybasedanalysesmaybeemployedwhenthere isinsufficientprojectdocumentation. Theycan

    alsobeusedwithanothermethodtoaugmentsupportiveevidenceofdamages. Ingeneral,although

    the industrybasedmethodsarequickand inexpensive,theiruse incalculating lostproductivity isnot

    thefirstpreference.

    Cost

    Based

    Methods

    Ifitispossibletodemonstrateentitlementandcausationbutthereisinsufficientprojectdocumentation

    tosupportdamagecalculationsusinganyoftheabovetechniques,recommendedpracticeistouseone

    ofthecostingmethodssetforthbelow. Thesemethodsrequireanalysisoftheprojectjobcostrecords.

    Thepurposeofsuchpreliminaryanalysis is todetermineactualdirect labourhoursandcosts (having

    77SeeHenselPhelpsConstructionCo.,GSBCANos.14,744&14,877,011BCA31,249.January11,2001.

    78AssociationfortheAdvancementofCostEngineering(AACE)International,Inc.(2004).Estimatinglostlaborproductivityin

    constructionclaims.AACEInternationalRecommendedPracticeNo.25R03.

    79Sourcesofthesequalitativeand/orquantitativestudiesforvarioussubjectscanbefoundinBorcherding,J.D.,andAlarcon,L.F.(1991).Quantitativeeffectsonproductivity.Constr.Lawyer,11(1)andAssociationfortheAdvancementofCost

    Engineering(AACE)International,Inc.(2004).Estimatinglostlaborproductivityinconstructionclaims.AACEInternational

    RecommendedPracticeNo.25R03.

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    25/31

    TheAnalysisandValuationofDisruption

    Page|25

    strippedoutmaterials, installedequipment,supplies, fieldandhomeofficeoverhead,smalltoolsand

    consumables,etc.).

    Total cost and modified total cost methods are grouped into cost based methods. AACE80 further

    dividesatotalcostmethod intoatotalunitcostandatotallabourcostmethod. Underthetotalcost

    method,thecontractorsubtractsitsestimatedlabourcostsfromthecostsactuallyincurredtoarriveattheresultingoverrunasthebasisfor its inefficiencyclaims81. Themajordifferencebetweenthetotal

    costandmodifiedtotalcostmethodsisthatdamagesquantifiedbymodifiedtotalcostcalculationtakes

    into account unreasonable estimates and/or inefficiencies due to contractors problems. Thus, the

    secondmethod,outofthetwo,ispreferable.

    Successful use of the cost based methods is limited. In order to employ a total cost analysis, a

    contractorgenerallyhastoprovethefollowingrequirements:

    (1) Theimpracticabilityofprovingactuallossesdirectly;

    (2) Thereasonablenessofitsbid;

    (3) Thereasonablenessofitsactualcosts;and

    (4)

    Lackofresponsibility

    for

    the

    added

    costs

    82

    .

    Therequirementsfortheuseofthemodifiedtotalcostmethodaresimilarbutthebidandactualcosts

    shouldbereasonableafteradjustment

    OtherQuantifyingMethods

    There are other inefficiency estimations such as expert testimony andjury verdict. A considerable

    portionof lostproductivitycalculations isbasedprimarilyuponanexpertstestimony83. Althoughthis

    methodmightwork, it isextremelyuncertaindue toa lackofsupportinganalysis. Similarly, thejury

    verdict approach that is occasionally applied by USA boards, courts, and other bodies to determine

    damageshasnogroundonwhichacontractorshouldrely.

    80AssociationfortheAdvancementofCostEngineering(AACE)International,Inc.(2004).Estimatinglostlaborproductivityin

    constructionclaims.AACEInternationalRecommendedPracticeNo.25R03.81Jones,R.M.(2003).Updateonprovingandpricinginefficiencyclaims.Constr.Lawyer,Summer,311;Klanac,G.P.,and

    Nelson,E.L.(2004).Trendsinconstructionlostproductivityclaims.J.Profl.IssuesEng.Educ.Pract.,130(3),226236.82CentexBatesonConstructionCo.,VABCANo.4613,991BCA30,153at149,261,1998.

    83Sanders,M.C.,andNagata,M.F.(2003).Assessingmethodologiesforquantifyinglostproductivity.AACEInt.Transactions,

    CDR.18,18.

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    26/31

    TheAnalysisandValuationofDisruption

    Page|26

    MatchingtheQuantifyingMethodswithProjectPractice

    Theabovefigure84presentsaframeworkfromwhichthesuitabilityofavailableapproachesforanalysis

    andquantifyingtheeffectsofdisruptionmaybediscerned. Thisselectionprocessisprimarilybasedontheavailabilityandthecharacteristicsofinformationavailablesetagainstthedegreeofreliabilityofthe

    quantifying method. Available information can be from particular project practice and/or industry

    studies.

    Aseriesofquestionsareaskedtoselecttheappropriatequantifyingmethod. Accordingly,thematching

    processstructurescriticalquestionsbyvariousdecisionpoints. Thesedecisionpointsareorganised in

    suchawaythatmoregeneralquestionsregardingprojectpracticearisefirstsothatavailablemethods

    cangraduallybeclassifiedintermsoftheirfeasibility. Finally,themostadvantageousmethodemerges

    amongthefeasiblesetforacertaintypeofprojectdataandindustrystudies. Therelativeadvantages

    anddisadvantagesof the lostproductivityquantifyingmethodsarediscussed in theprevious section.

    84AdaptedfromQuantifiedImpactsofProjectChange,Ibbs,Long,NguyenandLee,JournalofProfessionalIssuesinEngineering

    EducationandPractice2007.

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    27/31

    TheAnalysisandValuationofDisruption

    Page|27

    Theaboveframeworkrecommendsthemostfavouredapproachratherthanasetofpossibleones. This

    meansthat,forexample,anearnedvalueanalysiscanalsobeusedincaseameasuredmilestudyisnot

    available. However, themeasuredmilemethod ismost favoured in that circumstance andhence is

    recommended. In addition, comparison studies do not appear in the possible outcomes of the

    framework since much more credible methods such as baseline productivity analysis and system

    dynamicsmodellingarepreferredwhentime,availabledocuments,andresourcespermit.

    Conclusions

    Underappropriatecircumstances,allofthemethodssetforthhereinaretechnicallyacceptable. Ofall

    the methods identified above, the most reliable are those reliant upon the analysis of factual,

    contemporaneousinformationdrawnfromthespecificprojectinquestion,i.e.ProjectSpecificStudies.

    These methods are based upon contemporaneous documentation and knowledge from the project.

    Thus,theyaretheclosesttoapproximatingactualdamagesfromtheproject. Allothermethodologies

    discussed are estimating techniques with varying degrees of reliability. Therefore, they must be

    consideredlessrobust. Thisagainhighlightstheimportanceofkeepinggoodrecordsfromtheoutsetof

    theproject.

    To reliablyquantify and successfully claim for lost productivity, damages have tobe associatedwith

    cause. Resultantinjurygoeshandinhandwithliabilityandcausationtoformthetriadofproof.

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    28/31

    TheAnalysisandValuationofDisruption

    Page|28

    REFERENCES

    AnalysisofChangeOrderMarkupAllowancesonStipulatedPriceBuildingContracts,AminahRobinsonFayek;MosesY.Nkuah,

    CostEngineeringJournal,Vol.44/No.1January2002

    AnalyzingtheCumulativeImpactofChanges,DavidD.Reichard;CherylL.Norwood,AACEInternationalTransactions,2001

    Analyzing the Impact of Change Orders on a Schedule, Jeffrey A. Veenendaal, Cost Engineering Journal, Vol. 40/No. 9

    September1998

    AppropriateRiskAllocationinLumpSumContracts WhoShouldTaketheRisk?,Dr.FrancisT.Hartman,PE;PatrickSnelgrove,

    P.Eng.;Dr.RafiAshrafi,CostEngineeringJournal,Vol.40/No.7July1998

    Assessing Methodologies for Quantifying Lost Productivity, Mark C. Sanders, PE; Mark F. Nagata, AACE International

    Transactions,2003

    Baseline Determination in Construction Labor ProductivityLoss Claims, Ronald Gulezian, Frederic Samelian, Journal of

    ManagementinEngineering,Vol.19,No.4,October2003

    Calculating Construction Damages, Second Edition, William Schwartzkopf, John J. McNamara, 2001, 2005 Cumulative

    Supplement,AspenPublishersISBN139780735514805,ISBN0735555060(supplement)

    CalculatingLossofProductivityDuetoOvertimeUsingPublishedChartsFactorFiction,RegulaBrunies,ZeyEmir,TheRevay

    ReportVolume20,Number3,November2001

    CalculatingLostLaborProductivityInConstructionClaims,SecondEdition,WilliamSchwartzkopf,2004AspenPublishers,ISBN

    0735548935

    CausationandDelay inConstructionDisputes,2ndEdition,NicholasJ.Carnell,BlackwellScience,2005, ISBN13:97814051

    18613

    ChangeManagementBestPracticesfortheEngineeringandConstructionIndustry,OracleWhitePaper,April2009

    ChangeOrdersImpactonConstructionCostandSchedule,GeorgeSuhanic,AACETransactions,1980

    ChangeOrderManagement,BobM.McCally,AACEInternationalTransactions,1997

    Claim Evaluation for Combined Effect of Multiple Claim Factors, Amarjit Singh, Cost Engineering Journal, Vol. 43/No. 12

    December2001

    ConsequentialCostEffects,PaulR.Heather,CCE;MichaelD.Summers,CCE,AACEInternationalTransactions,1996

    Construction Contracts: Shifting Risk or Generating a Claim?, Donald F. McDonald, Jr., PE CCE; John O. Evans III, AACEInternationalTransactions,1998

    ConstructionProductivity:ASurveyof IndustryPractices,GeorgeF. Jergeas;MohammadS.Chishty;Marko J. Leitner,AACE

    InternationalTransactions,2000

    ConstructionProductivity:MajorCausesofImpact,CharlesA.Leonard;Dr.PaulFazio;Dr.OsamaMoselhi,AACETransactions,

    1988

    ConstructionProjects:ChangeOrderManagement,Dr.CalinM.Popescu,AACETransactions,1986

    Construction Scheduling:Preparation, Liability andClaims, Second Edition, JonM.Wickwire, Thomas J.Driscoll, StephenB.

    Hurlbut,ScottB.Hillman,AspenPublishers,2003,ISBN0735529949

    ConstructiveChanges,AnthonyJ.Werderitsch;JamesE.Krebs,AACEInternationalTransactions,2002

    ContractorsProtectionAgainstConstructionClaims,Dr.GeorgeF.Jergeas,PE;FrancisT.Hartman,PE,AACETransactions,1994

    CopingwithChanges,StephenO.Revay,CCC,AACEInternationalTransactions,2003

    CopingwithExtras,StephenO.Revay,TheRevayReportVolume21Number2September2002

    CostGuidelinesforChangeOrders,RonaldF.Cilensek,CCE,AACETransactions,1986

    DelayandDisruptioninConstructionContracts,KeithPickavance,3rdEdition,LLP,2005,ISBN1843114267

    DelayandDisruption:LegalConsiderations,StuartCNash,SocietyofConstructionLaw,August2002

    Delay In The Performance Of Contractual Obligations, Dr John E Stannard, Oxford University Press, 2007, ISBN 978019

    9282654

    Demonstrated Labor Efficiency: An Effective Labor Cost Control and Analytical Tool, Bob M. McCally, AACE International

    Transactions,1998

    DisruptionClaims,HamishLal,HillInternation/CIOBMasterclassMay2008

    Dynamic Change Management for Fasttracking Construction Projects, Moonseo Park, Assistant Professor, Department of

    Building,SchoolofDesign&Environment,NationalUniversityofSingapore.NISTSP989;September2002.

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    29/31

    TheAnalysisandValuationofDisruption

    Page|29

    REFERENCES

    EffectiveManagementofProjectChangeOrders,EdwardE.DouglasIII,CCC,AACEInternationalTransactions,2003

    EP41513Modification ImpactEvaluationGuide,2July1979,DEPARTMENTOFTHEARMY,OfficeoftheChiefofEngineers,

    Washington,DC20314

    EstimatingandNegotiatingChangeOrders,LeonardA.McMahon,CCE,AACETransactions,1984

    EstimatingtheCostofChangeOrders,Dr.OsamaMoselhi,PE,AACEInternationalTransactions,1998

    EstimatingtheCostofChangeOrders,OsamaMoselhi,PE,CostEngineeringJournal,Vol.45/No.8August2003

    Evidence,TheCityLawSchool,CityUniversity, London,Editor JamesGriffiths,OxfordUniversityPress,2008, ISBN978019

    9553532

    ForwardPricingImpactonConstructionProjects,BrianE.Kasen;VictorC.Oblas,PE,AACEInternationalTransactions,1996

    GoingtheExtraMile,WalterBauer,P.Eng.,AACEInternationalTransactions,2004

    GuidelinesfortheManagementofMajorConstructionProjects,NEDO,1991,ISBN011701219X

    ImpactofChangeOrdersonConstructionProductivity,OsamaMoselhi,CharlesLeonard,PaulFazio,CAN.J.CIV.ENG.VOL.11,

    1991

    ImpactofChange'sTimingonLaborProductivity,William Ibbs,JournalofConstructionEngineeringandManagementASCE/

    November2005

    ImpactsAndConstructionInefficiency,DwightA.Zink,CostEngineeringJournal,Vol.32/No.11November1990

    Inefficiency,ZartabZ.Quraishi,PECCE,AACEInternationalTransactions,2003

    LaborProductivityImpacts:ACaseStudy,RobertD.Kelly,AACEInternationalTransactions,2000

    LaborProductivity,Disruptions,and theRippleEffect,Dr.H.RandolphThomas,PE;Dr.AmrA.Oloufa,PE,CostEngineering

    Journal,Vol.37/No.12December1995

    LearningCurveinConstruction,ZeyEmir,TheRevayReportVolume18,Number3,October1999

    LiquidatedDamagesandExtensionsofTime inConstructionContracts,ThirdEdition,BrianEggleston,WileyBlackwell,2009,

    ISBN9781405118156

    LossofLearninginDisruptionClaims,DavidA.Norfleet,CCC,AACEInternationalTransactions,2004

    Managing Changes in Construction Projects, Research funded by the Engineering and Physical Sciences Research Council(EPSRC):UniversityoftheWestofEngland:ProfessorMingSun,UniversityofSalford:DrMartinSexton,ProfessorGhassan

    Aouad,AndrewFleming,SepaniSenaratne,UniversityofLoughborough:ProfessorChimayAnumba,ProfessorPaulChung,Dr

    AshrafElHamalawi,DrIbrahimMotawa,MeiLinYeoh,20012004

    ManagingChangesinConstruction,NRCC,RR258,Hao,Q.,Shen,W.,Neelamkavil,J.,June1,2008.

    ManagingChangesinLargePrograms,AshishKumar,AACEInternationalTransactions,2000

    ManagingContractChanges,GerardBoyle,TheRevayReportVolume23Number3December2004

    ManagingProjectChange:ABestPracticeGuide,DLazarus,RClifton,ClRlAC556,2001,ISBN0860175561

    MeasuredMileAnalysisand InternationalMegaProjects,DanCrowley; JohnC.Livengood,AACE InternationalTransactions,

    2002

    MeasuredMileLaborAnalysis,TimothyT.Calvey,PE;WilliamR.ZollingerIII,PE,AACEInternationalTransactions,2003

    MeasuredMileProcessProjectControlstoSupportEquitableRecoveryofProductionInefficiencyClaims,ThomasW.Presnell,

    CCC,CostEngineeringJournal,Vol.45/No.11November2003

    MonitoringJobSiteProductivity,BrianFoster,TheRevayReportVolume19,Number2,May2000

    Monitoring theAdequacyof theAmountandProductivityofEngineeringandConstructionManpower,DwightA.Zink,CCE,

    AACETransactions,1980

    MoreForLess:AContractorsGuideToImprovingProductivityInConstruction,Horner,RMW,Duff,AR,ConstructionIndustry

    ResearchandInformationAssociation,C566,2001,CIRIA,ISBN0860175669

    PracticalAnalysesinProvingDamages,JackW.Harris;AndrewAinsworth,AACEInternationalTransactions,2003

    PracticalRiskAnalysisinScheduling,AbhiBasu,PE,AACEInternationalTransactions,1998

    ProactiveChangeOrderManagement,FrankKettlewell,AACEInternationalTransactions,2003

    ProjectChanges:Sources,Impacts,Mitigation,Pricing,Litigation&Excellence,PAConsultingGroup,2007

    ProofofDamagesinConstructionClaims,RichardJ.Long,AACETransactions,1988

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    30/31

    TheAnalysisandValuationofDisruption

    Page|30

    REFERENCES

    Putting the SCL Delay and Disruption Protocol into Practice is it what the industry wants? Keith Pickavance, Society of

    ConstructionLaw,September2004

    QuantifyingandManagingDisruptionClaims,HamishLal,ThomasTelford,2003,ISBN:0727731653

    QuantifyingDisruptionthroughSimulationandHeuristics,KennethG.Cooper;KimberlySklarReichelt;JonathanMoore,AACE

    InternationalTransactions,2004

    QuantifyingtheEffectofChangeOrdersonElectricalConstructionLaborEfficiency,Dr.AwadS.Hanna,PE;Dr.JeffreyS.Russell,

    PE;DavidThomack,CostEngineeringJournal,Vol.40/No.2February1998

    Recommended Practice No. 25R03 "Estimating Lost Labor Productivity in Construction Claims", AACE International, AACE

    InternationalRecommendedPractice,2004

    Statistical Evaluations ofMeasured Mile Productivity Claims, Michael Ross Finke, Cost Engineering Journal, Vol. 40/No. 12

    December1998

    SystemDynamicModelingofDelayandDisruptionClaims,WilliamIbbs,MinLiu,CostEngineeringVol.47/No.6June2005

    System Dynamics Modeling in the Legal Arena: Special Challenges of the Expert Witness Role, Craig A. Stephens, Alan K.

    Graham,JamesM.LyneisPAConsultingGroup,2002

    TheCumulativeEffectofChangeOrdersonLabourProductivitytheLeonardStudyReloaded,GeraldMcEniry,TheRevay

    ReportVolume26Number1May2007

    TheEffectOfChangeOrdersOnProductivity,CharlesA.Leonard,TheRevayReportVolume6Number2August1987

    TheFIDICFormsofContract,ThirdEdition,NaelG.Bunni,BlackwellPublishingLtd,2005,ISBN13:9781405120319

    TheMeasuredMile:ProvingConstructionInefficiencyCosts,DwightA.Zink,CostEngineeringJournal,Vol.28/No.4,April1986

    The NEC 3 Engineering and Construction Contract: A Commentary, 2nd Edition, Brian Eggleston, Blackwell Science, 2006,

    ISBN9780632053865

    TheProductivityBaseline,RonaldGulezian;FrederickZ.Samelian,AACEInternationalTransactions,2003

    TheQuantumAspectsofDelay,DavidKyte,KeithStrutt,HillInternation/CIOBMasterclassMay2008

    TheRoleoftheCostEngineerandtheChangeOrderProcess,AlfredL.Dellon,CCE,AACETransactions,1986

    TheSocietyofConstructionLawDelayandDisruptionProtocol(RevisedEdition),October2002,ISBN095438317

    Trends in Construction Lost Productivity Claims, Gerald P. Klanaca and Eric L. Nelsonb, Journal of Professional Issues in

    Engineering,EducationandPracticeASCE/July2004

    Understandingprojectdynamicscuttingprojectcosts,PAConsultingGroup,2008

    Understanding Risk to Mitigate Changes and Avoid Disputes, L. Adam Winegard; Stephen P. Warhoe, PE CCE, AACE

    InternationalTransactions,2003

    UpFrontCostEstimatingofChangeOrders,OsamaMoselhi; IhabAssem;KhaledElRayes,AACE InternationalTransactions,

    2002

    UseofProductivityFactorsinConstructionClaims,RobertDieterle,CCE;AlfredDeStephanis,AACETransactions,1992

    Using Industry Studies To Quantify Lost Productivity, Mark G. Jackson, Carl W. LaFraugh, Robert P. Majerus, West Group

    ConstructionBriefings,No.200112December2001

    Variations,TimeLimitsandUnanticipatedConsequences,RonanChampion,SocietyofConstructionLaw,May2007

  • 7/28/2019 P2011 - The Analysis and Valuation of Disruption - Derek Nelson

    31/31

    TheAnalysisandValuationofDisruption

    Attachment