GLOBAL PURCHASING & MATERIALS HANDLING
CHAPTER III
PRODUCTİON PLANNİNG SYSTEM
MASTER SCHEDULİNG
MATERİAL REQUİREMENTS PLANNİNG
PRODUCTİON PLANNİNG
What do we need to produce?
Process
Machinery & Equipment
Labor Skills
Material1
QUESTİONS OF A PLANNİNG SYSTEM
What are we going to make?
What does it take to make?
What do we have?
What do we need?
2
QUESTİONS OF A PLANNİNG SYSTEM
Priority(Demand)
Capacity(Resources)
3
QUESTİONS OF A PLANNİNG SYSTEM
Priority:
What is needed?When?How much?
(Market)
Capacity:
Capability to produce what is needed
and when? 4
CAPACİTY
Capacity is the capability of
manufacturing in a period of time.
Capacity is up to resources of company as
machinery, labor, financial resources and
availability of materials form suppliers.
5
MAJOR LEVELS OF PLANNİNG
Strategic Business Plan
Sales and Operations Plan
Master Schedule
Material Requirements Plan(MRP)
Purchasing and Production Activity Control
6
PLANNİNG HİERARCHYStrategic
Business Plan
ProductionPlan
Master ProductionSchedule
MaterialRequirements
Plan
Production ActivityControl andPurchasing
MasterPlan
Planning
Implementation
8
CAPACİTY MANAGEMENT
At each level of the planning and control
system, reconcilation with resources must be
made.
Inadeqaute resources=missed production
schedules
Resources significantly exceed planned
production=idle resources and extra cost.12
SALES AND OPERATİONS PLAN
Strategic Business Plan
Marketing Plan ProductionPlan
Detailed Sales Plan
MasterProductionSchedule
SALES AND OPERATIONS PLAN
Annual
Monthly
Weeklyor
Daily
13
SALES AND OPERATİONS PLANNİNG
It can be used to update the strategic plan.
It provides a tool to manage change.
It enforces functional plans to be realistic and
coordinated.
It represents a plan to achieve company objectives
It provides management visibility of production,
inventory and backlogs. 14
BASİC PRODUCTİON PLAN STRATEGİES
Chase:Vary production rates to meet changes in
demand Often used when inventory cannot be used or when resources
are flexible and inexpensive to change
Level:Establish average demand level and set production
rate to that level
Often used when resources difficult or very expensive to
change
Hybrid: A combination of two strategies.
16
DEMAND CURVE
Demand
Number of Units
Time 17
CHASE PRODUCTİON CURVE
Demand
Number of Units
Time
Chase Production
18
LEVEL PRODUCTİON CURVE
Demand
Number of Units
Time
Level Production
19
LEVEL PRODUCTİON CURVE
Demand
Number of Units
Time
Level Production
CREATE Inventory
USE Inventory
20
36
MRP Determine Requirements – Calculated to meet
product requirements defined in the MPS.
What to order
How much to order
When to order
When to schedule delivery
Keep priorities current
39
BOM
40
BOM The BOM shows all parts to make one of the
item
Each part has one, and only one, part number
A part is defined by form, fit, and function – any
change requires a new part number
41
BOM
Defines the product
Provides method for design change control
Planning: What is needed and when?
Order Entry,order configuration and pricing
Production:Parts needed to assemble
Costing: Material cost of goods sold
43
BOM