OVERCURRENT RELAY SETTING BY USING ADAPTIVE TECHNIQUE
PARISA ESMAILI
A project report submitted in partial fulfilment of the
requirements for the award from the degree of
Master of Engineering (Electrical-Power)
Faculty o f Electrical Engineering
Universiti Teknologi Malaysia
JUNE 2014
iii
To my beloved family and specially my dears father, mother and sister
iv
ACKNOWLEDGEMENT
In preparing this thesis, I was in contact with lots from people, researchers,
academicians, and practitioners. They have contributed towards my understanding
and thoughts. In particular, I wish to express my sincere appreciation to my main
thesis supervisor, Prof. Ir. Dr. Abdullah Asuhaimi bin Mohd Zin, for encouragement,
guidance, critics and friendship. Without his continued support and interest, this
thesis would not be as written.
I also like to express my apperception Librarians at UTM also deserve special
thanks for their assistance in supplying the relevant literatures.
My sincere appreciation also extends to all my colleagues and others who
have provided assistance at various occasions. Their views and tips are beneficial
indeed. Unfortunately, it is not possible to list all from them in this limited space. I
am grateful to all my family members.
v
ABSTRACT
As cost-effective protection relays, Overcurrent (OC) relays are used as the
main protection equipment in distribution grids and backup protection for distance
relays in transmission and sub-transmission lines. Basically, two parameters are
considered as OC relays settings: pickup currents ( Ipick up ) and Time Setting
Multiplier (TSM). Hence, the objective in the coordination problem of OC relays is
to determine Ipick up and TSM of each relay. These methods can be classified into
two different approaches: Off-line and On-line coordination approaches. By
analyzing all faults, abnormal operating conditions, and system contingencies as
well-known as Off-line coordination techniques, several methods have been
developed to solve coordination problem of OC relays. However, the response of
relays would not be satisfactory in a condition which has not been included the
analysis earlier. Meaning that, required short circuit currents due to any fault that
occurred in grid cannot be adjusted to the coordination problem of OC relays.
Therefore, the risk of occurring mal-operation or miss-coordination becomes high. In
order to achieve a robust protection scheme, the OC relays settings must be updated
regarding to any change which results into new topology of the grid. In this thesis, a
reliable protection scheme is achieved by implementing the proposed adaptive
protection algorithm. For this purpose, the idea of employing the Thevenin
equivalent circuit is utilized to check the power grid operation for any change
continuously. By applying the proposed technique, the accurate settings of
overcurrent relays in distribution network are determined. As a result, the proposed
adaptive protection algorithm can avoid the unnecessary blackouts in distribution
network and provide reliable and sensitive protection scheme.
vi
ABSTRAK
Untuk perlindungan geganti yang efekttif, geganti arus lebihan (OC)
digunakan sebagai alat perlindungan utama dalam grid agihan dan perlindungan
sokongan untuk geganti jarak dalam penghantaran dan sub-talian penghantaran. Pada
dasarnya, dua parameter yang dianggap sebagai tetapan geganti arus lebihan iaitu :
Arus Ambilan (PS) dan Masa Tetapan Pengganda (TSM). Oleh itu, objektif dalam
masalah penyelarasan daripada geganti arus lebihan ialah untuk menentukan Masa
Tetapan Pengganda bagi setiap geganti. Kaedah-kaedah ini boleh diklasifikasikan
pada dua pendekatan yang berbeza iaitu: Penyelarasan talian tertutup dan talian
terbuka. Dengan menganalisa semua kerosakan, keadaan operasi yang tidak normal,
dan sistem luar jangkaan yang dikenali sebagai teknik penyelarasan talian tertutup,
beberapa kaedah telah dicapai bagi menyelesaikan masalah penyelarasan geganti
arus lebihan. Walaubagaimanapun, keadaan tindak balas geganti kurang memuaskn,
dimana analisa kerosakan tidak dimasukkan lebih awal. Ini bermakna arus litar pintas
diperlukan kerana kerosakan yang berlaku dalam grid tidak dapat diselaraskan
dengan masalah penyelarasan geganti arus lebihan (OC). Oleh itu, risiko untuk
berlakunya ‘mal-operasi’ atau ‘miss-penyelarasan’ menjadi tinggi. Untuk mencapai
satu skim perlindungan teguh, tetapan geganti arus lebihan mestilah dikemaskini
berdasarkan sebarang perubahan kepada keputusan baru topologi grid. Dalam tesis
ini, skim perlindungan yang boleh dipercayai dicapai dengan melaksanakan
algoritma perlindungan penyesuaian yang telah dicadangkan. Bagi tujuan ini, idea
bagi menggunakan Litar Setara Thevenin digunakan untuk menyemak operasi kuasa
grid bagi apa-apa perubahan secara berterusan. Dengan menggunakan teknik yang
dicadangkan, tetapan tepat geganti arus lebihan dalam rangkaian agihan ditentukan.
Hasilnya, algoritma perlindungan penyesuaian yang dicadangkan boleh mengelakkan
kerosakan dalam pengedaran rangkaian dan menyediakan skim perlindungan yang
boleh dipercayai dan sensitif.
vii
viii
CHAPTER TITLE PAGE
DECLARATION ii
DEDICATION iii
ACKNOWLEDGEMENTS iv
ABSTRACT v
ABSTRAK vi
TABLE OF CONTENTS vii
LIST OF FIGURES xi
LIST OF TABLES xiv
LIAT OF ABBREVIATION xvi
LIST OF APPENDIX xvii
1 INTRODUCTION 1
1.1 Overview 1
1.2 Problem Background 2
1.3 Objective of Study 4
1.4 Scope of Study 4
1.5 Research Significant 5
1.6 Thesis Outline 5
2 LITERATURE REVIEW 6
2.1 Introduction 6
2.2 Overcurrent Relays 7
2.2.1 Types of Overcurrent Relays 7
TABLE OF CONTENTS
ix
2.2.1.1 Instantaneous Overcurrent Relays (Define
Current Relay) 7
2.2.1.2 Define Time Overcurrent Relay (DT
Relays) 8
2.2.1.3 Inverse Time Overcurrent Relay
(IDMT Relay) 8
2.2.1.4 Main and Backup Protection Zones 10
2.3 Off-line Coordination 12
2.3.1 Conventional Approaches 12
2.3.2 Optimization Approaches 13
2.3.2.1 Linear Programming Techniques 14
2.3.2.2 Intelligence Based Optimization Methods 15
2.3.2.2.1 Genetic Algorithm 16
2.3.2.2.2 Particle Swarm Optimization 17
2.4 On-line Coordination 19
2.5 Adaptive Protection Scheme 22
2.6 Summary 24
3 RESEARCH METHODOLOGY 25
3.1 Introduction 25
3.2 Research Frame Work 26
3.3 Case study: IEEE-14 Bus Test System 27
3.4 Proposed Adaptive Protection Algorithm 28
3.5 Operating Scenario for IEEE-14 Bus Power Grid 29
3.6 Thevenin Equivalent Circuit of Power Grid 32
3.7 Distribution System and Overcurrent Protection Scheme 36
3.7.2 The 230/20 kV Test Radial Distribution System
Configuration 36
3.8 Short Circuit Current Level Calculation 37
3.9 Normal Inverse Time Overcurrent Relay Setting
Procedure 38
3.10 Summary 39
x
4 RESULT AND DISCUSSION 40
4.1 Introduction 40
4.2 The Thevenin Equivalent Impedances under Normal
Operating Condition 41
4.2.1 Load Flow Analysis 43
4.2.3 Sampling Procedure under Normal Operating
Condition 45
4.3 The Thevenin Equivalent Impedances after loads
Connection 48
4.3.1 Sampling Procedure after Loads Connection 49
4.4 The Thevenin Equivalent Circuit after Compensators
Connection 53
4.5 The Thevenin Equivalent Circuit under Unexpected
Change 54
4.5.1 Sampling Procedure when G8 is taken out of use 55
4.6 Overcurrent Relays setting in Radial Distribution System 59
4.7 Short Circuit Current Calculation under Normal
Operating Condition 60
4.7.1 Overcurrent Relay Setting under Normal
Operating Condition 61
4.8 Short Circuit level and Overcurrent Relays Settings after
Loads Connection 63
4.8.1 Short Circuit level and Overcurrent Relays
Settings after G8 Disconnection 65
4.9 Results Discussion 67
4.9.1 Different Values o f the Thevenin Equivalent
Impedances 67
4.9.2 Affected Short Circuit Currents 69
4.9.3 Proposed Adaptive Overcurrent Relays Settings 70
4.10 Summary 71
5 CONCLUSIONAND FUTURE WORK 72
5.1 Conclusion 72
xi
5.2 Future Work: Protection Issues in Microgrids 73
5.2.1 Active Distribution Networks 74
5.2.2 Implementing of Adaptive Protection Approaches
as a Solution in Microgrids Protection Issues 75
REFERENCES
Appendix A-B
76
81-98
xii
LIST OF TABLES
TABLE NO. TITLE PAGE
2.1 Values of a and K determine the degree of inverse in
the IDM curves 10
4.1 Initial values of voltage, impedance, line and
load currents in pu 44
4.2 Voltage on buses 2, 3,4,5,7 and 9 during sampling
under normal operating condition in pu 45
4.3 Currents from buses 2, 3 and 5 into the bus 4 during
sampling under normal operating condition in pu 46
4.4 Currents from bus 4 into the buses 7 and 9 during
Sampling under normal operating condition in pu 46
4.5 Load current, and load impedance during sampling
under normal operating condition in pu 47
4.6 Voltage on Buses 2, 3,4,5,7 and 9 during sampling after
loads connection in pu 50
4.7 Currents from buses 2 and 5 into the bus 4 during
sampling after loads connection in pu 50
4.8 Currents from bus 4 into the buses 3,7and 9 during
sampling after loads connection in pu 51
4.9 Load and line currents during sampling after Loads
connection in pu 51
4.10 Load impedance during sampling after loads connection
in pu 52
4.11 Voltage on buses 2, 3,4,5,7 and 9 during sampling after
xiii
G8 disconnection in pu 56
4.12 Currents from bus 2 and 5 into the bus 4 during
sampling after G8 disconnection in pu 56
4.13 Currents from bus 4 into the bus 3,7and 9 during
sampling after G8 disconnection in pu 57
4.14 Load and line currents during sampling after G8
disconnection in pu 57
4.15 Load impedance during sampling after G8
disconnection in pu 58
4.16 CT Ratio, nominal and short circuit currents for
breakers under normal operating condition 61
4.17 Overcurrent relay setting data under normal operating
condition 63
xiv
FIGURE NO. TITLE PAGE
2.1 Definite current relay operating characteristics 8
2.2 Definite time relay operating characteristic 9
2.3 Inverse time minimum time relay operating
characteristic 9
2.4 IEC standard based characteristic curves 10
2.5 Primary and backup protection zone of OC relays 11
2.6 Traditional and modern configuration of overcurrent
relay: 20
2.7 Modern power systems configuration 21
2.8 Summaries of the proposed Off-line coordination
techniques 22
3.1 Research frame work 27
3.2 The single-line diagram of the IEEE-14 bus test system 28
3.3 The proposed adaptive algorithm to monitor the voltage
on the bus 4 31
3.4 Continuously changing operating condition of the grid 32
3.5 Per-phase equivalent circuit of the power grid for a line
led to a bus 33
3.6 Typical configuration of radial distribution systems 36
3.7 The 230/20 kV test radial distribution system
configuration 37
3.8 Equivalent circuit of power system under fault occurred
at LV side 37
LIST OF FIGURES
xv
4.1 simulated IEEE-14 bus test system in POWERWORLD 41
simulator under normal operating condition
4.2 Power flow direction to/ from Bus 4 under normal
operating condition in POWERWORD simulator 42
4.3 Workspace of power flow analysis in POWERWORLD
simulator 43
4.4 Simulated IEEE-14 bus test system in POWERWORLD
simulator after loads connection
Simulator after Loads Connection 48
4.5 Power flow direction to/ from the bus 4 after
loads connection in POWERWORLD simulator 49
4.6 Simulated IEEE-14 bus test system in POWERWORLD
simulator after compensation 53
4.7 Simulated IEEE-14 bus test system in POWERWORLD
after G8 disconnection 54
4.8 Power flow direction to/ from the bus 4 after
G8 disconnection in POWERWORLD simulator 55
4.9 Connection of 230/20 kV-distribution system to the
IEEE-14 bus power grid 59
4.10 Simulated 14-bus test system and its connected radial
distribution network after load connection 64
4.11 CT Ratio, nominal and short circuit currents for
breakers after loads connection 64
4.12 Overcurrent relay setting data after loads connection 65
4.13 Simulated 14-bus test system and its connected radial
distribution network after G8 disconnection 66
4.14 CT Ratio, nominal and short circuit currents for
breakers when G8 disconnected 66
4.15 Overcurrent relay setting data when G8 disconnected 67
4.16 Different values o f the Thevenin impedance under
continuously changing operating condition of the grid 68
4.17 Different short circuit levels under different operating
conditions 69
xvi
5.1 Active distribution networks configuration 74
5.2 Simulated 230/20 active distribution network in
POWERWORLD simulator 75
xvii
LIST OF APPENDICES
APPENDIX NO. TITLE PAGE
A IEEE-14 Bus Test System Data 81
B MATLAB Codes 83
xviii
LIST OF ABREVIATIONS
OC - Overcurrent
TSM - Time Setting Multiplier
PS - Plug Setting
LP - Linear Programming
MINLP - Mixed Integer Non-Linear Programming
SCADA - Supervisory Control and Data Acquisition
HV - High Voltage
IDMT - Inverse Define Minimum Time
DT - Define Time
NLP - Non-Linear Programming
IBFS - Initial Basic Feasible Solution
GA - Genetic Algorithm
POS - Particle Swarm Optimization
CGA - Continuous Genetic Algorithm
OF - Objective Function
NM - Nelder-Mean
DUT - Dominant Utilization Topology
ILP - Interval Linear Programming
DG - Distributed Generation
LV - Low Voltage
CIT - Coordination Time Interval
CHAPTER 1
INTRODUCTION
1.1 Overview
In the presence of increasing industrial developments and consequently
growing energy consumption, importance of accessing to reliable electricity widely
has been attention [1]. In addition to reliability, it is compulsory to generate
sufficient amount of electric power to transmit on a continuous basis where systems
efficiency depends on continuous electricity accessing [2]. To achieve this,
protection system associated with the power system must be able to identify and
compensate any effects or fails in the system which leads to long term blackouts [3].
Otherwise, more delays required to restore the system to its normal operating in case
of blackout or damage to equipments which is costly. Furthermore, utilization of the
suitable protective equipment is fundamentally important in terms of safety and
minimizing damages on the electrical devices. To achieve this, protective relays such
as overcurrent relays must promptly clear any fault with disconnecting as few
components as possible.
As cost-effective protective relays, overcurrent relays (OC) have been
employed in distribution system. Usually, these relays are the main protection
2
devices in distribution grids and backups for distance relays in transmission and sub
transmission lines [4]. Basically, two parameters are considered as OC relays
settings: pickup currents ( Ip iCk -U p ) and Time Setting Multiplier (TSM). Hence, the
objective in the coordination problem of OC relays is to determine Ipick - u p and TSM
of each relay [5]. In order to prevent any mal-operation or miss-coordination,
overcurrent relays must adjust with accurate values of pick up current and time dial
setting.
1.2 Problem Background
Several methods that have been developed to solve coordination problem of
OC relays can be classified into two different approaches: Off-line and On-line
coordination approaches. Traditionally, conventional approaches have been applied
to solve coordination problem of OC relays [10-16]. Since these approaches
encountered with problems for complex and interconnected networks, optimization
techniques introduced to overcome the mentioned problems [17-18]. These
optimization techniques can be divided into linear and non-linear techniques. In
linear techniques, pickup currents assumed to be known. Thus, the Linear
Programming (LP) is employed only to minimize operating time [19-22]. Since,
overcurrent relays coordination problem is a Mixed Integer Non- Linear
Programming (MINLP), LP techniques have limitations in term of low number of
restrictions. This leads to introduce non-linear technique or intelligence based
optimization methods. Considering the nonlinearity effects and integer variables in
problem formulation are the major benefits of the intelligent based optimization
methods [23-24]. Genetic algorithm (GA) and Particle Swarm Optimization (PSO)
have been presented as two powerful tools in order to solve this complex
optimization problem [25-34].
3
However the optimization techniques presented reliable performance in
order to solve coordination problem, these protection techniques are in relation to the
concept of pre-determinism which involves analysis of all faults, abnormal operating
conditions, and system contingencies. In protection scheme based on pre
determinism concept, the response of relays would not be satisfactory in a condition
which has not been included the analysis earlier [4-9]. Meaning that, required short
circuit currents due to any fault that occurred in grid cannot be adjusted to the
coordination problem of OC relays. Therefore, the risk of occurring mal-operation or
miss-coordination becomes high.
In order to achieve a robust protection scheme, overcurrent relays must be
adjusted by new settings. For this purpose, microprocessor based relays have been
employed in order to introduce adaptive protection scheme [35-37]. In this manner, a
Supervisory Control and Data Acquisition (SCADA) system checked the system for
any alterations continuously. As mentioned above, in protection scheme based on
pre-determinism concept, the response of relays would not be satisfactory due to
uncertainties. Although, the proposed centralized adaptive protection approaches
have been provided good solution for this problem, the coordination process depends
on the monitoring performance of SCADA system.
In this thesis, a reliable protection scheme is achieved by implementing the
proposed adaptive protection algorithm. According to the proposed algorithm, new
setting for the overcurrent relays can be obtained regarding to any change in
topology of the grid. The method is an On-line technique and based on the Thevenin
equivalent circuit of the grid that seen from each bus. This provides a monitoring
capability which removes any dependency on SCADA system performance. In this
thesis, proper settings o f overcurrent relays that adjusted in a High Voltage (HV)
substation are determined by employing proposed adaptive protection algorithm.
4
1.3 Objective of Study
The objectives of this study are as follow.
1. To obtain the Thevenin equivalent circuit parameters for the test system
2. To determine the required short circuit currents for accurate setting of
overcurrent relays in HV substation by applying obtained Thevenin
equivalent circuit parameters.
3. To propose new accurate setting of overcurrent relays in HV substation due
to any changes in grid topology (add/remove equipment).
1.4 Scope of Study
To achieve the research objectives, the following scopes will be covered:
1. Thevenin equivalent circuit is derived only for one bus.
2. IEEE 14-bus system is considered as case study.
3. MATLAB and POWERWORLD software are employed in this study.
4. Only HV substation relays are considered for finding accurate setting.
5. Changes in grid topology such as add new equipments or take out of use of
equipments are considered
5
1.5 Research Significant
The main significant in this work is to propose accurate settings for OC relays
in order to solve coordination problem regarding to any change in grid topology.
1.6 Thesis Outline
This thesis is prepared in five chapters as follow.
Chapter 1: Describe on the problem background and statement, objectives, scopes
and significances of the study.
Chapter 2: Reviews some related works done by previous investigators on
conventional and optimization methods to solve the coordination problem of OC
relays.
Chapter 3: Specifies the research process employed in this thesis.
Chapter 4: First, the Thevenin equivalent circuit impedances are obtained for
test system under different operating conditions. Then, required short circuit current
levels are calculated by applying different values of the Thevenin impedances
regarding to each operating condition. Finally, the accurate settings o f each OC
relays in test radial distribution network are determined according to the different
values of short circuit current levels.
Chapter 5: Presents conclusion and future work.
REFRENCES
[1] Painthakar, Y. G. and Bhide, S. Fundamentals o f Power System Protection,
5th edition. New Delhi: Prentice-Hall o f India Private Limited, 2007.
[2] Yesansure, T. M. and Arora, T. G. (2013). Numerical Quadrilateral Distance
relay, International Journal o f Innovative Research in Science, Engineering
and Technology, 2(7), 2920-2927.
[3] Li, S., Ding, M.and Du, S. (2009). Transmission Loadability With Field
Current. IEEE Transaction on Power Delivery, 24(4), 2142-2149.
[4] Ojaghi, M., Sudi, Z., Faiz, J., and Member, S. (2013). Implementation of Full
Adaptive Technique to Optimal Coordination of Overcurrent Relays. IEEE
Transactions on Power Delivery, 28(1), 235-244.
[5] Sung, B. C., Lee, S. H., Park, J., and Meliopoulos, A. P. S. (2013).
Adaptive Protection Algorithm for Overcurrent Relay in Distribution System
with DG. JE lectr Eng Technol, 8(2013), 805-814.
[6] Urdaneta, A. J., and Perez, L. G. (1997). Optimal Coordination of Directional
Overcurrent Relays Considering Daynamic Changes in The Network
Topology. IEEE Transaction on Power Delivery, 2(4), 1458-1464.
[7] Singah,J. (2013). Adaptive Coordination for Power System Protection: Issue
& Benefits. International Journal o f Electrical, Electronics and Data
Communication, 1(6), 30-32.
[8] Orduna, E., Garces, F., and Handschin, E. (2003). Algorithmic-Knowledge-
Based Adaptive Coordination in Transmission Protection. IEEE Transaction
on Power Delivery, 18(1), 61-65.
[9] Abdelaziz, A., Talaat, H.E., Nosseir, A., and Hajjar, A. A.(2002). An
Adaptive Protection Scheme for Optimal Coordination of Overcurrent
Relays. Electric Power Systems Research, 61(1), 1-9.
77
[10] Albrecht, R. E., Nisja, M. J., Feero, W. E., Rockefeller, G. D., and Wagner,
C. L. (1964).Digital Computer Protective Device Co-ordination Program:I-
General Program Description. IEEE Transactions on Power Apparatus and
Systems, 83(4), 402-410.
[11] Thangaraj, R., Pant, M., and Deep, K. (2010). Optimal Coordination of
Overcurrent Relays Using Modified Differential Evolution Algorithms.
Engineering
Applications o f Artificial Intelligence, 23(5), 820-829.
[12] Knable, A.H.(1969).A Standardised Approach to Relay Coordination. IEEE
WinternPower Meeting. Proc : IEEE,58-62.
[13] Bapeswaea Rao, V. V, and Sankara Rao, K. (1988). Computer Aided
Coordination
of Directional Relays: Determination of Break Points. IEEE Transactions on
Power Delivery, 3(2), 545-548.
[14] Dwarakanath, M and Nowitz, L. (1980). An Application of Linear Graph
Theory for Coordination of Directional Overcurrent Relays. In Erisman, A.M,
Neves, K.W &Dwarakanath, M. H(Ed) In Electric Power Problems:
Mathematical
Challenge.(pp.104-114). Philadelphia: SIAM.
[15] Jenlins, L., Khincha, H. P., Shivakumar, S., and Dash, P. K. (1992). An
Application of Functional Dependencies to the Topological Analysis of
Protection Schemes. IEEE Transaction on Power Delivery, 7(1), 77-83.
[16] Chattopahyay,B., Sachdev, M. S., and Ow, C. S. N. (1996). An On-line Relay
Coordination Algorithm for Adaptive Protection Using Linear Programming
Technique. IEEE Transaction on Power Delivery, 11(1), 165-173.
[17] Hussain, M. H., Musirin, I., and Abidin, A. F. (2013). Computational
Intelligence Based Technique in Optimal Overcurrent Relay Coordination: A
Review. The International Journal o f Engineering and Science (IJES), 2(1),
1-9.
[18] Urdaneta, A. J., Nadira, R., and Jimdnez, L. G. P.(1988). Optimal
Coordination of Directional Overcurrent Relays in Interconnected Power
Systems.IEEE Transaction on Power Delivery, 3(3), 903-911.
[19] Bedekar, P. P., Bhide, S. R., and Kale, V. S. (2009). Optimum Time
Coordination of Overcurrent Relays using Two Phase Simplex Method.
78
International Journal o f Electrical and Computer Engineering, 4(12), 774
778.
[20] Bedekar, P.P. and Kale, V.S. (2009). Optimum Time Coordination of
Overcurrent Relays in Distribution System Using Big-M ( Penalty ) Method.
WSEAS TRANSACTIONS on POWER SYSTEMS, 4(11),341-350.
[21] Bedekar, P.P., Bhide, S.R. and Kale, V.S. (2009). Optimum Coordination of
Overcurrent Relays in Distribution System Using Dual Simplex Method. In
2th International Conference on Emerging Trends in Engineering and
Technology (ICETET).16-18 December. Nagpur, India.555-559.
[22] Bedekar, P.P., Bhide, S.R. and Kale, V.S. (2010). Optimum Coordination of
Overcurrent Relay Timing Using Simplex Method. Electric Power
Components and Systems, 38(10), 1175-1193.
[23] Zeienldin, H., EL-saadany, E.F. and Salama, M.A. (2004). A Novel Problem
Formulation for Directional Overcurrent Relay Coordination. In Large
Engineering Systems Conference on Power Engineering. 28-30 July. Halifax,
Canada :IEEE .48-52.
[24] Noghabi, A.S., Mashhadi, H.R. and Sadeh, J. (2010). Optimal Coordination
of Directional Overcurrent Relays Considering Different Network Topologies
Using Interval Linear Programming. IEEE Transaction on Power Delivery,
25(3), 1348-1354.
[25] So, C. et al.(1977). Application of Genetic Algorithm to Overcurrent Relay
Grading Coordination. In 4th International Conference on Advances in
Power System Control, Operation and Management. 11-14 November. Hong
Cong, China: IEEE, 283-287.
[26] Razavi, F., Abyaneh, H. A., Al-Dabbagh, M., Mohammadi, R., and
Torkaman, H. (2008). A New Comprehensive Genetic Algorithm Method for
Optimal Overcurrent Relays Coordination. Electric Power Systems Research,
75(4), 713-720.
[27] Bedekar, P.P. and Bhide, S.R. (2011). Optimum Coordination of Directional
Overcurrent Relays Using the Hybrid GA-NLP Approach. IEEE Transaction
on Power Delivery, 26(1), 109-119.
[28] Bedekar, Prashant P., and Bhide, S. R. (2011). Optimum Coordination of
Overcurrent Relay Timing Using Continuous Genetic Algorithm. Expert
Systems with Applications, 38(9), 11286-11292.
79
[29] Kennedy, J., and Eberhart, R. (1995). Particle swarm optimization. In
Proceedings o f IC N N ’95 - International Conference on Neural Networks ,
4(1), 1942-1948.
[30] Zeineldin, H.H., El-Saadany, E.F. and Salama, M.M. a. (2006). Optimal
Coordination of Overcurrent Relays Using a Modified Particle Swarm
Optimization. Electric Power Systems Research, 76(11), 988-995.
[31] Bashir, M., Taghizadeh, M. and Mashhadi, R. (2010). A New Hybrid Particle
Swarm Optimization for Optimal Coordination of Over Current Relay. In
International Conference on Power System Technology. 24-28 October.
Hangzhou, China, 1-6.
[32] Liu, A. and Yang, M., (2012). A New Hybrid Nelder-Mead Particle Swarm
Optimization for Coordination Optimization of Directional Overcurrent
Relays. Mathematical Problems in Engineering.
[33] Noghabi, A. S., Mashhadi, H. R., and Sadeh, J. (2010). Optimal Coordination
of Directional Overcurrent Relays Considering Different Network
Topologies. IEEE Transactions on Power Delivery 25(3), 1348-1354.
[34] Noghabi, A.S., Mashhadi, H.R. and Sadeh, J. (2010). Optimal Coordination
of Directional Overcurrent Relays Considering Different Network Topologies
Using Interval Linear Programming. IEEE Transaction on Power Delivery,
25(3), 1348-1354.
[35] Phadke, A. G., and Horowitz, S. H. (1990). Adaptive Relaying. IEEE
Computer Applications in Power, 3(3), 47 - 51.
[36] Venkateshmurthy, B. S., and Venkatesh, V.V . (2013). Advanced Numerical
Relay Incorporating The Latest Features Which Can Compute The
Interfacing With The Automation Using DSP. Engineering, Computers &
Applied Sciences (JEC&AS), 2(1), 4-7.
[37] Al-Nema, M., Bashi, S., and Ubaid, A. (1986). Microprocessor-Based
Overcurrent Relays. IEEE Transaction on Industrial Electronic, 33(1), 49
51.
[38] Tegou, L., Polatidis, H., and Haralambopoulos, D. (2007). Distributed
Generation with Renewable Energy Systems: the Spatial Dimension for an
Autonomous Grid. The 47th Conference o f the European Regional Science
Association(ERSA),29-2 August. France, Paris,1-20.
80
[39] Chattopadhyay B., Sachdev M. S., and Sidhu T. S. (1991). Adaptive Relaying
for Protecting a Distribution System: Afeasibility Study. IEEE Western
Canada Conference on Computer, Power and Communications Systems in a
Rural Environment. 29-30 May. Canada:IEEE. 20-25.
[40] Jampala, A.k., Venkata, S.S. and Damborg, M.J. (1989). Adaptive
Transmission Protection: Concept and Computational Issues. IEEE
Transaction on Power Delivery, 4(1), 177-185.
[41] INTERNATIONAL STANDARD IEC 60255-151, Inverse-Time
Characteristic Equations for Overcurrent Relays, First edition 2008-2009.