POMS Abstract Acceptance - 020-0451 Abstract Title - Optimal selection of Suppliers in a Supply Chain Network with Multiple Bidders for Each stage Author 1: Shashank Garg Handheld Solutions & Research Labs 36, 20 th Main 1 st Cross, 1 st Stage BTM Layout, Bangalore – 560068 [India] Email: [email protected] Tel: +91-80-26685035 Author 2: D. Krishna Sundar Indian Institute of Management Bangalore Bannerghatta Road, Bangalore – 560076 [India] Email: [email protected] Tel: +91-80-26993276 POMS 22 nd Annual Conference Reno, Nevada, USA April 29 to May 2, 2011 Abstract In a cost competitive commodity market, procurement of raw materials, production and supply of finished goods at minimum cost plays a vital role in managing an efficient supply chain. It becomes complex while dealing with agricultural products, where procurement of raw material(s) is seasonal, production is partly seasonal where as finished product’s demand is steady throughout the year. Further complications arise when changes come in the set of service providers (supply side & distribution side) & their commercial contracts, annually. This paper models such a supply chain as a project network in which multiple time-cost bids are provided by multiple suppliers for each stage/node of the network. Market intelligence curves are developed for each stage/activity to determine the baseline cost-time solution for the network. Optimal set of suppliers is determined using the market intelligence curves and suppliers’ actual bids by formulating the problem as a linear programming problem. Keywords: Supplier Selection, Supply Chain Networks, Market intelligence curves, Optimization

Upload: trinhnguyet

Post on 29-Mar-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

POMS Abstract Acceptance - 020-0451

Abstract Title - Optimal selection of Suppliers in a Supply Chain

Network with Multiple Bidders for Each stage

Author 1: Shashank Garg Handheld Solutions & Research Labs 36, 20th Main 1st Cross, 1st Stage BTM Layout, Bangalore – 560068 [India]

Email: [email protected] Tel: +91-80-26685035

Author 2: D. Krishna Sundar Indian Institute of Management Bangalore Bannerghatta Road, Bangalore – 560076 [India] Email: [email protected] Tel: +91-80-26993276

POMS 22nd Annual Conference Reno, Nevada, USA April 29 to May 2, 2011

Abstract In a cost competitive commodity market, procurement of raw materials, production and supply of finished goods at minimum cost plays a vital role in managing an efficient supply chain. It becomes complex while dealing with agricultural products, where procurement of raw material(s) is seasonal, production is partly seasonal where as finished product’s demand is steady throughout the year. Further complications arise when changes come in the set of service providers (supply side & distribution side) & their commercial contracts, annually. This paper models such a supply chain as a project network in which multiple time-cost bids are provided by multiple suppliers for each stage/node of the network. Market intelligence curves are developed for each stage/activity to determine the baseline cost-time solution for the network. Optimal set of suppliers is determined using the market intelligence curves and suppliers’ actual bids by formulating the problem as a linear programming problem. Keywords: Supplier Selection, Supply Chain Networks, Market intelligence curves, Optimization

020-0451

Optimal selection of Suppliers in a Supply Chain Network with Multiple

Bidders for Each stage

Abstract

In a cost competitive commodity market, procurement of raw materials,

production and supply of finished goods at minimum cost plays a vital role in managing

an efficient supply chain. It becomes complex while dealing with agricultural products,

where procurement of raw material(s) is seasonal, production is partly seasonal where as

finished product’s demand is steady throughout the year. Further complications arise

when changes come in the set of service providers (supply side & distribution side) and

their commercial contracts, annually. This paper models such a supply chain as a project

network in which multiple time-cost bids are provided by multiple suppliers for each

stage/node of the network. Market intelligence curves are developed for each

stage/activity to determine the baseline cost-time solution for the network. Optimal set of

suppliers is determined using the market intelligence curves and suppliers’ actual bids by

formulating the problem as a linear programming problem.

Keywords: Supplier Selection, Supply Chain Networks, Market intelligence curves, Optimization

1. Introduction

Management of an efficient supply chain in the agro-products market requires that

procurement of raw materials, production and supply of finished goods be done at

minimum cost and within time constraints since the raw materials are of perishable

nature. Dealing with agricultural products is complex because procurement of raw

materials is often seasonal, production is partly seasonal whereas the demand for the

finished product demand is steady throughout the year. The set of service providers and

suppliers also changes periodically, resulting in fresh negotiations and contracts every

time. A project is often defined as consisting of specified sets of activities to be executed

as a one-time set of activities. Since in an agro-products supply chain a re-assessment of a

potentially new set of suppliers for a specified set of services is required every year or at

some other periodic interval, the task of optimal supplier selection can be treated as a

fresh project every time. It is for this reason that we use a project activity network as our

model for time-cost optimization.

In the literature a project has been defined in terms of events and activities to

provide a mathematical basis for critical-path planning and scheduling Kelley &

Walker(1959), Kelley(1961). Elmaghraby(1977) defines a project as a medium or large-

scale undertaking consisting of a range of activities requiring the consumptions of

varying types of resources over the entire duration of the set of activities that compose a

project. The concept of a project as being one of its kind and limited by a beginning and

an end, in contrast with the typical assembly-line production which constitutes a set of

activities repeated over a long period of time has been highlighted by Elmaghraby(1977).

Resource optimization in project activity networks has been studied by many authors. See

Parikh & Jewell(1965), Parikh & Jewell(1965), Golenko-Ginzburg(1989), Drexl(1991),

Demeulemeester(1995) and Golenko-Ginzburg & Blokh(1997). Optimization techniques

have been extensively used in the agriculture sector to provide improvement in various

aspects such as harvesting, transportation, agricultural production etc. Balm(1980) has

discussed linear programming models for application in Scottish agriculture.

Sargent(1980) has studied the impact of optimization techniques on agricultural

production. Optimization techniques have also been applied to increase sugar production

in the Australian context by Jiao, Higgins et al.(2005). Modeling techniques in the sugar

supply chain have been extensively discussed by Higgins, Beashel et al.(2006).

Scheduling and optimization of transport in the sugar sector has been discussed by

Higgins(2006), and Higgins & Laredo(2006). A production scheduling case study of a

South African sugar mill is provided in Le Gal, Lyne et al.(2008). The applicability of

decision support systems for the management of the sugar-cane supply chain has been

discussed by Lejars, Le Gal et al.(2008). Colin(2008) has used mathematical

programming models to develop strategies for the optimal management of land usage for

the sugarcane crop cycle to prevent land overuse. A comprehensive review of the

planning models used in the agriculture supply-chain has been provided by Ahumada &

Villalobos(2007). Useful insight into “transaction cost economics” in the sugar supply

chain in the Australian sugar industry was provided by Banarjee & McGovern(2004).

The design of performance metrics for measurement of efficiency in the supply chain was

studied by Baiman, Fischer et al.(2001). Strategies for replacement of inventory to gain

competitive advantage in the supply chain have been discussed by Borgman &

Rachan(2007). An overview of the modeling and analysis techniques used in the

management of manufacturing supply chains has been covered by Gunasekaren, Macbeth

et al.(2000).

The remainder of the paper is organized as follows: Section 2 describes the

proposed project activity network model for an agro-product supply chain. Market

intelligence curves are developed in section 3. This provides a baseline approximation for

the minimum time and minimum cost for a project, though it does not help in selecting

the most optimal supplier set. Extrapolation of bids using linear programming is

developed in Section 4 and Section 5 presents the results for an experimental data-set of

supplier bids for a small activity network representing the scenario in an agro-product

supply-chain. In Section 5 we conclude with suggestions for further improvements in the

optimization model.

2. Modelling an Agro-product Supply Chain

In this paper, we model an agro-product supply chain as a project network in which

multiple time-cost bids are provided by multiple suppliers for each stage or node in the

network. At each stage of the project, there are a host of suppliers or service providers

who provide widely varying bids for their products or services. The value of a bid is

dependent on the time of execution for that service. In general, if a particular service is to

be executed in a shorter time then the cost for that service will be higher than the cost of

the same service if it is performed at a slower pace. Therefore, each supplier can be

expected to provide multiple time-cost bids for the same service. Since procurement of

services for the project involves multiple inter-related activities, arriving at an optimal

selection of suppliers is non-trivial. When the project can be modeled as an activity

network involving tasks that have to be done in a particular sequence, then it should be

feasible to determine all the critical paths and the optimal supplier set.

The critical path of an activity network is the path which takes the longest time to

complete i.e. the summation of duration of all the activities falling in that path is the

largest of all other paths. The nodes falling in a critical path have a property that their

earliest realization time and latest realization time are same. Hence slack at these nodes

(or events) is zero. The activities and events falling in the critical path have to be

completed within whatever time is assigned to them, whereas events and activities in

other paths can be given a delay which should not be more than the slack available to

them. Otherwise the activities ahead of them will get delayed.

In an agro-product’s supply chain, each activity in the network model represents

some quantum of work to be done for which there are multiple suppliers who can supply

materials, resources or skills. Suppliers bid for each activity individually and each

supplier is asked to offers multiple cost-time bids for each activity. These supplier bids

generally fall into a convex curve such that cost of service decreases as time increases.

While discrete cost-time bids are offered, in reality the suppliers bids can be treated as

stochastic because suppliers can deviate from their time bids with a Gaussian probability

distribution which has mean equal to the time bid as specified and some standard

deviation. This standard deviation is typically derived based on past experience with this

particular supplier in earlier projects. The standard deviation is different for different bids

of a supplier and it generally decreases as the time bid increases. This is logical because

the tendency for deviations decreases if the amount of time given to a supplier increases.

As the number of activities and the number of suppliers increases, going with the lowest

bidding supplier for each activity may not be the most optimal solution. So the objective

of the proposed network model is to enable the project manager to choose the set of

suppliers that is most optimal for the entire project. The main objective of the project

manager can be divided further into multiple sub-objectives which may or may not be

independent of each other. These sub-objectives are:

• To calculate the minimum possible time of completion of the project (with no

constraint on cost) with the given bids and also to come up with a selection of

suppliers whose bids will achieve this minimum time. This eventually gives an

idea of the maximum cost that the complete project can incur with the given bids.

• To calculate the minimum possible cost of completion of project (with no

constraint on time) with given bids and also the corresponding selection of

suppliers which results in the minimum cost for the project. This gives an idea of

the maximum time a project can take.

• To choose a supplier for each activity in such a way that the cost of the complete

project is minimized given that the project is completed in a given expected

amount of time (obviously greater than the minimum time calculated in para one

above).

2.1 Market Intelligence Curves for a Project Network

In this section we study market intelligence curves and follow-up with

extrapolation of individual cost-time curves in the next section. To obtain market

intelligence curves, the cost-time curves of all the suppliers for a particular activity are

taken and plotted on the same graph to find the best-fitting curve passing through them.

This curve is called a market intelligence curve. The market intelligence curves based

approach gives the base-line time-cost solution for a given set of supplier bids for each

activity in the supply chain network.

Generally, all suppliers submit discrete bids for each activity. A supplier provides

bids in a collection of (time, cost, variance) where discrete integer time values are given

in terms of days, or weeks, or months and the cost bid for a particular time value can be a

real number. Often, there will be situations in which a supplier for an activity doesn’t

even bid for a specific discrete time value, whereas some other supplier for the same

activity may have bid for that particular time value. However, over the entire range of

bids by all suppliers for a particular activity, there is a minimum time bid and similarly

there is a maximum time bid. In this approach, the cost-time curve of each supplier is first

extrapolated by joining that supplier’s bid points in time-cost space. In case a cost bid

doesn’t exist at the minimum-time value or at the maximum-time value, then an

assumption of a very high cost bid value is made at these points. To obtain market

intelligence curves for each activity, we implement the following steps in our algorithm:

Step 1: For each activity, arrange individual supplier bids for that activity in the 3-

tuple format representing (time, cost, variance) in an ascending order of

time such that the lowest time bid is the first entry in the sequence and the

highest time bid is the last entry in the sequence. This is repeated for all

supplier bids for each activity.

Step 2: Develop the activity_on_node network which is defined as a set of

activities with start_node and end_node in the form of a tuple ,( , )i i ia s e ,

where ia represents the activity for the ith node

is represents the start node of activity ia

ie represents the end node of activity ia

and i varies from 0 to n-1 nodes.

Step 3: Using a depth-first search algorithm, derive a path array [ ],P i j whose

elements are the activity numbers of all paths in the network where i

represents the index of the path number and j is the index of the jth activity

on the ith path, using a depth-first search algorithm on the above activity

network.

Step 4: Derive the array [ ], ,time i j k which holds the kth time value (integer) and

the array [ ]cos , ,t i j k holds the kth cost value taken from the jth Supplier’s

bid for activity i, where i is the activity number from 0 to n-1, j is the jth

supplier for activity i and k is the kth time bid of jth supplier for activity i.

We also define a variable ijt as the completion time for an activity which

has starting node i , and ending node j , where i =0,1,…(n-1), j

=0,1,…(n-1).

Step 5: Next, we define variable ( )iZ as the time of completion of ith end node,

where i = 0, 1, …, n-1 nodes.

The variable T is defined as the expected time of completion of the

project.

Step 6: Define another variable iy , as the cost incurred by activity i . Thus, the

total cost of the project is the sum of the costs for all the associated

activities, which we have to minimize.

Hence, the Objective Function is

1

0minimize

n

ii

y−

=∑ (2.1)

subject to the following constraints:

(1) All ijt for which there is no activity starting at node i and ending at

node j , shall be made zero. This is expressed as

i j0, if no activity exists starting at node and ending at node otherwise the value needs to be foundijt

=

(2.2)

(2) The time for an activity i shall lie between min it and max it , where

min it is the minimum time bid for activity i , taken from the supplier bid,

and

max it is the maximum time bid for activity i , taken from the supplier

bid.

Hence, this constraint is defined as

,min ( ) ( )i i ii s e et t Z≤ ≤ (2.3)

(3) Time for completion of starting node of an activity i plus activity time

should be less than or equal to time of completion of ending node of

that activity. Hence,

,( ) ( ) ( )i i i is s e etZ Z+ ≤ (2.4)

(4) Time for completion of terminal node should be less than or equal to

the expected time of completion of the project. Hence,

( )1nZ T− ≤ (2.5)

The above algorithm is then implemented in the following steps:

Step 1: Using the best-fitting curve function tAe λ− as an approximation which is applied to all supplier bids for each activity, we obtain market intelligence parameters ( ),i iA λ .

Step 2: Find max it , the maximum time bid for activity i and min it , the minimum time bid for activity i .

Step 3: Let ( ) ti iy t A e λ−= be the cost function for activity i on the time variable t

which represents the time taken for the activity i starting at node is and ending at node ie .

Step 4: 1

0minimize

n

ii

y−

=∑ subject to constraints in equations (2.2), (2.3), (2.4) and

(2.5) above.

3. Linear Programming Model for a Project Network

As already mentioned, over the entire range of bids by all suppliers for a

particular activity, there is a minimum time bid and similarly there is a maximum time

bid. In this approach, the cost-time curve of each supplier is first extrapolated by joining

that supplier’s bid points in time-cost space. In case a cost bid doesn’t exist at the

minimum-time value or at the maximum-time value, then an assumption of a very high

cost bid value is made at these points. Once extrapolated cost-time curves are available

for each supplier, another cost-time curve is obtained as an “envelope curve” such that

for each time bid, starting with the minimum-time value to the maximum-time value, the

minimum-cost bid is selected out of all cost bids available at that particular time value

from extrapolated curves of all suppliers for that particular activity. This gives rise to a

new cost-time curve which is used in selecting the winning suppliers.

The linear programming model is implemented in the following steps in our

algorithm:

Step 1: For each activity, arrange individual supplier bids for that activity in the 3-

tuple format representing (time, cost, variance) in an ascending order of

time such that the lowest time bid is the first entry in the sequence and the

highest time bid is the last entry in the sequence. This is repeated for all

supplier bids for each activity.

Step 2: Develop the activity_on_node network which is defined as a set of activities with start_node and end_node in the form of a tuple ,( , )i i ia s e ,

where ia represents the activity for the ith node

is represents the start node of activity ia

ie represents the end node of activity ia

and i varies from 0 to n-1 nodes.

Step 3: Using a depth-first search algorithm, derive a path array [ ],P i j whose

elements are the activity numbers of all paths in the network where i

represents the index of the path number and j is the index of the jth activity

on the ith path, using a depth-first search algorithm on the above activity

network.

Step 4: Derive the array [ ], ,time i j k which holds the kth time value (integer) and

the array [ ]cos , ,t i j k holds the kth cost value taken from the jth Supplier’s

bid for activity i, where i is the activity number from 0 to n-1, j is the jth

supplier for activity i and k is the kth time bid of jth supplier for activity i.

We also define a variable ijt as the completion time for an activity which

has starting node i , and ending node j , where i =0,1,…(n-1), j

=0,1,…(n-1).

Step 5: Next, we define variable ( )iZ as the time of completion of ith end node,

where i = 0, 1, …, n-1 nodes.

The variable T is defined as the expected time of completion of the

project.

Step 6: Define another variable iy , as the cost incurred by activity i . This cost iy

will fall on the piecewise linear curve derived from lower-most envelope

of extrapolated cost-time curves of suppliers for each activity i . Thus, the

total cost of the project is the sum of the costs for all the associated

activities, which we have to minimize.

Hence, the Objective Function is

1

0minimize

n

ii

y−

=∑ (3.1)

subject to the following constraints:

(1) All ijt for which there is no activity starting at node i and ending at

node j , shall be made zero. This is expressed as

i j0, if no activity exists starting at node and ending at node otherwise the value needs to be foundijt

=

(3.2)

(2) The time for an activity i shall lie between min it and max it , where

min it is the minimum time bid for activity i , taken from the supplier

bid, and

max it is the maximum time bid for activity i , taken from the supplier

bid.

Hence, this constraint is defined as

,min ( ) ( )i i ii s e et t Z≤ ≤ (3.3)

(3) Time for completion of starting node of an activity i plus activity time

should be less than or equal to time of completion of ending node of

that activity. Hence,

,( ) ( ) ( )i i i is s e etZ Z+ ≤ (3.4)

(4) Time for completion of terminal node should be less than or equal to

the expected time of completion of the project. Hence,

( )1nZ T− ≤ (3.5)

The above algorithm is then implemented in the following steps:

Step 1: For each supplier of each activity, extract piece-wise linear extrapolated

cost-time curve, given the discrete cost-time bids. Let this extrapolated

cost-time curve ( )ijy t be defined as the cost-time function of the supplier

j for the activity i .

At 0t = and t = max it , arbitrarily high values are assigned to cost. This

results in bids in the first and last segments not being selected. Due to the

extrapolation, new bids are generated where actual discrete bids do not

exist in the supplier file j for activity i.

Step 2: Once extrapolated cost-time curves are generated for all the suppliers for

the activity i , another cost-time curve is extracted which is the lowest cost

envelope for all suppliers j iε . This gives the cost function

( ) min( ( )),i ijy t y t j iε= ∀

This lower-most envelope represents the cost-time, piece-wise linear function for activity i.

Step 3: 1

0minimize

n

ii

y−

=∑ subject to constraints in equations (3.2), (3.3), (3.4) and

(3.5) above.

This lower-most envelope represents the cost-time, piece-wise linear function for

activity i . The cost bid is chosen as the lowest value on this curve even though the

winning supplier has not actually provided that bid. Since the winning supplier has not

provided the intermediate winning bid, the project manager can negotiate with the

winning supplier for this specific bid.

4. An Experimental Model for a Sugar Supply Chain

In this section we present a small-sized experimental network consisting of eight

activities representing a typical supply chain for sugar production. The Table 4-1 shows

all activities in sorted order, with a 3-tuple comprising (activity, start_node, end_node)

given against each activity.

Table 4-1: List of Activities in an Experimental Network Model of a Sugar Supply Chain

List of Activities Activity Tuple (activity, start_node, end_node)

A0: Purchase Sugar-cane (0,0,2) A1: Purchase Chemicals (1,0,1)

A2: Purchase Bags (2,0,3) A3: Ship Sugar-cane to Crusher (3,2,4) A4: Ship Chemicals to Factory (4,1,5)

A5: Crush Sugar-cane (5,4,5) A6: Ship Bags to Factory (6,3,6) A7: Refine Sugar (7,5,6) A8: Package Sugar & Ship-out (8,6,7)

Based on the activity tuples listed in the above table, we construct a project

activity network shown in Figure 1 below. This figure shows the connectivity for this

network in an activity-on-arrow (AOA) network mode and its equivalent activity-on-node

(AON) mode. As already mentioned, in an A-on-A network an activity is represented by

an arc and an event is represented by a node, whereas in an A-on-N network an activity is

represented by a node and an event is represented by an arc. See Kelley (1961) and

Elmaghraby (1977) for a more comprehensive discussion on AOA and AON network

modes. Our experimental implementation uses the AON model of the network.

Figure 1: An Experimental Network Model of a Sugar Supply Chain

Table 4-2 gives the supplier bids for all activities in this experimental sugar

supply chain (SSC) network. Suppliers provide multiple cost-time bids for each activity

for each activity and each supplier bid is a 3-tuple representing (time, cost, variance).

Individual supplier bids are sorted in ascending order of the time component in the bid.

Table 4-2: Supplier Bids for an Experimental Sugar Supply Chain

Activity Suppliers Bid 1 Bid 2 Bid 3 Bid 4

A0 Purchase Sugar-cane

S00 90,10000,5 100,9000,4 120,8000,3 -

S01 90,11000,6 110,8800,5 120,7700,4 130,6600,2

S02 100,11000,6 110,10000,4 120,8500,3 130,8000,1

S03 95,11800,5 110,10500,4 125,8800,3 -

S04 100,11200,5 110,10200,3 120,9700,2 130,8500,1

A1 Purchase Chemicals

S10 5,2010,2 7,1985,1 9,1776,1 12,1560,0

S11 4,2210,1 6,2085,1 10,1976,1 12,1530,0

S12 6,2010,2 8,1985,1 10,1906,1 12,1570,0

S13 7,2000,2 10,1885,1 12,1806,1 14,1470,0

A2 Purchase Bags

S20 40,1400,5 50,1300,4 60,1250,3 80,1150,0

S21 45,1400,3 60,1200,2 90,1100,1 100,1000,0

S22 40,1550,6 60,1350,4 80,1200,3 90,1050,1

S23 52,1450,5 77,1240,3 92,1080,2 102,1000,0

A3 Ship Sugar-cane to

Crusher

S30 2,2900,1 4,2200,0 5,1850,0 -

S31 2,3200,1 4,2500,0 6,1950,0 -

S32 3,2900,1 5,2400,1 6,2050,0 -

A4 Ship Chemicals to

Factory

S40 2,2900,1 4,2200,0 5,1850,0 -

S41 2,3200,1 4,2500,0 6,1950,0 -

S42 3,2900,1 5,2400,1 6,2050,0 -

A5 Crush Sugar-cane

S50 16,8000,3 22,7200,2 26,6700,2 30,6100,1

S51 19,7800,3 24,7500,2 29,7100,2 33,6600,1

S52 16,8100,2 23,7700,2 28,7350,2 34,6950,1

S53 15,8600,3 21,7950,2 27,7450,2 32,7050,1

S54 17,8050,3 22,7930,2 27,7450,2 32,7050,1

A6 Ship Bags to Factory

S60 2,2900,1 4,2200,0 5,1850,0 -

S61 2,3200,1 4,2500,0 6,1950,0 -

S62 3,2900,1 5,2400,1 6,2050,0 -

A7 Refine Sugar

S70 5,803,2 6,728,2 7,675,2 8,612,1

S71 5,774,2 6,748,2 7,713,2 8,676,1

S72 5,830,2 7,785,1 9,732,1 -

S73 7,875,3 8,805,2 9,756,2 10,715,1

S74 5,865,2 6,807,2 7,751,2 8,727,1

A8 Package Sugar & Ship

Out

S80 2,2900,1 4,2200,0 5,1850,0 -

S81 2,3200,1 4,2500,0 6,1950,0 -

S82 3,2900,1 5,2400,1 6,2050,0 -

According to the sequence of steps described in 2.1, the ( , )i iA λ pairs are first

computed for each activity and a market intelligence curve is generated for each activity.

Once all ( , )i iA λ pairs have been computed for all the activities, these values are used in

the MIC model. The market intelligence curves are generated by using a best-fitting

curve function ( ) iti iy t Ae λ−= for each activity i . The market intelligence curves for one

such activity A0, based on the related supplier bids for this activity, are shown in the

figure below:

Figure 2: Market Intelligence Curves for Activity A0

Similar market intelligence curves have been obtained for all activities but are not

presented here for brevity. The market intelligence curves based approach gives the base-

line time-cost solution for a given set of supplier bids for each activity in the supply chain

network.

4.1 The Results of the Experimental Models

In this section we give the simulation results of the MIC and LP models that were

implemented for the experimental sugar supply chain network.

Table 4.1-1 lists the results for minimizing time with no cost constraints, using the

MIC and LP models. As can be seen, both models result in the same minimal time of

execution for the project network but the LP model delivers a lower cost. The list of

winning suppliers, from amongst the list of all suppliers for all activities is also shown.

Table 4.1-1: Minimizing Time

Results for Minimizing Time using MIC & LP Models for

the Experimental Sugar Supply Chain Network

Model Time Project Cost Winning Suppliers

MIC minimize Time 114 35838

LP minimize Time 114 33893 0,0,1,0,0,3,0,1,0

The Table 4.1-2 lists out the results of minimising cost with no time constraints. Once

again, the MIC model merely provides baseline data for decision making, whereas the LP

model gives a better idea of the optimal cost and the list of winning suppliers.

Table 4.1-2: Minimizing Cost with No Time Constraints

Results for Minimizing Cost using MIC & LP Models for

the Experimental Sugar Supply Chain Network

Model Time Project Cost

Suppliers

MIC minimize Cost with no Time constraints 186 25658

LP minimize Cost with no Time constraints 178 23182 1,3,3,0,0,0,0,0,0

In Table 4.1-3 we have listed the results of an experiment in which cost is minimized

under time constraints. The project time is specified as an external input to the simulation

model for each cycle of the simulation sequence. While the MIC model delivers the

corresponding project cost, the LP model provides a lower value of project cost, along

with a list of winning suppliers for each activity. This simulation has been run with

externally supplied time constraints, with the minimum and maximum time constraints

obtained from the MIC model.

Table 4.1-3: Minimizing Cost with Time Constraints

Results for Minimizing Cost with Time Constraints using MIC & LP Models

for the Experimental Sugar Supply Chain Network

MIC LP

Externally Supplied Time Constraint Project Cost Project Cost Winning Suppliers

120 31112 28994 0,3,3,0,0,0,0,1,0

130 29891 27469 0,3,3,0,0,0,0,1,0

140 28996 26244 0,3,3,0,0,0,0,1,0

150 28144 25482 0,3,3,0,0,0,0,0,0

160 27333 24982 0,3,3,0,0,0,0,0,0

170 26560 23894 1,3,3,0,0,0,0,1,0

178 25838 23182 1,3,3,0,0,0,0,0,0

5. Conclusions

Due to the seasonal and perishable nature of agro products, the production supply

chain needs to be efficiently and optimally managed. Since the set of service providers

may suppliers and conditions change on a periodical basis, every procurement cycle is

essentially a new project. So the agro supply chain can be treated as a project activity

network comprising multiple activities which can attract multiple bids from multiple

suppliers and service providers. This can pose enormous challenges for the project

managers in choosing the most optimal supplier set for a given set of objectives. Since

minimising cost is a project goal, a linear programming model can be applied to the

activity network.

In this paper we have proposed an approach in which market intelligence curves

are first derived to give the decision makers an idea of the baseline cost-time curves. A

linear programming model approach is then applied to extrapolate supplier’s bid points in

time-cost space. In case a cost bid doesn’t exist at the minimum-time value or at the

maximum-time value, then an assumption of a very high cost bid value is made at these

points. The extrapolated cost-time curves are first generated for each supplier and then

another cost-time curve is obtained as an “envelope curve” such that for each time bid,

starting with the minimum-time value to the maximum-time value, the minimum-cost bid

is selected out of all cost bids available at that particular time value from extrapolated

curves of all suppliers for that particular activity. This gives rise to a new cost-time curve

which is used in selecting the winning suppliers for each activity. This lower-most

envelope for each activity represents the cost-time as a piece-wise linear function for that

activity. The cost bid is chosen as the lowest value on this curve even though the winning

supplier has not actually provided that bid. Since the winning supplier has not provided

the intermediate winning bid, the project manager can negotiate with the winning

supplier for this specific bid.

This approach has certain limitations in that there may not be discrete bids

available from the winning suppliers and other optimization models may be need to be

considered. Another limitation of this approach is that the execution of an activity by a

service provider may deviate from the stated time for completion of the given activity.

This can be studied by considering the execution time for a project activity as a stochastic

variable with a given mean time for execution and some variance.

6. References Ahumada, O. & Villalobos, J.R. 2007, 'Application of planning models in the agri-food

supply chain: A review', European Journal of Operational Research, vol. 195, pp. 1-20.

Baiman, S., Fischer, P.E. & Rajan, M.V. 2001, 'Performance Measurement and Design in

Supply Chains', Management Science, vol. 47 (1) Design and Development, pp. 173-188.

Balm, I.R. 1980, 'LP Applications in Scottish Agriculture', The Journal of the

Operational Research Society, vol. 31 (5), pp. 387-392.

Banarjee, S. & McGovern, M. 2004, 'Sugar Supply Chains and Regional Development',

Twenty-eighth annual conference of the Regional Science Association International,

Australia and New Zealand Section Woolongong, 29th September to 1st October 2004, .

Borgman, H.P. & Rachan, W. 2007, 'Replacing Inventory: An Information Based

Strategy for Competitive Advantage in Supply Chain Management', Review of Business

Research, vol. 7 (3), pp. 148-157.

Colin, E.C. 2008, 'Mathematical programming accelerates implementation of agro-

industrial sugarcane complex', European Journal of Operational Research, vol. In press,.

Demeulemeester, E. 1995, 'Minimizing Resource Availability Costs in Time-Limited

Project Networks', Management Science, vol. 41 (10), pp. 1590-1598.

Drexl, A. 1991, 'Scheduling of Project Networks by Job Assignment', Management

Science, vol. 37 (12), pp. 1590-1602.

Elmaghraby, S.E. 1977, Activity Networks: Project Planning and Control by Network

Models, , John Wiley, NY.

Golenko-Ginzburg, D. & Blokh, D. 1997, 'A Generalized Activity Network Model', The

Journal of the Operational Research Society, vol. 48 (4), pp. 391-400.

Golenko-Ginzburg, D. 1989, 'A New Approach to the Activity-Time Distribution in

PERT', The Journal of the Operational Research Society, vol. 40 (4), pp. 389-393.

Gunasekaren, A., Macbeth, D.K. & Lamming, R. 2000, 'Modelling and Analysis of

Supply Chain Management Systems: An Editorial Overview', The Journal of the

Operational Research Society, vol. 51 (10), pp. 1112-1115.

Higgins, A. 2006, 'Scheduling of road vehicles in sugarcane transport: A case study at an

Australian sugar mill', European Journal of Operational Research, vol. 170, pp. 987-

1000.

Higgins, A., Beashel, G. & Harrison, A. 2006, 'Scheduling of Brand Production and

Shipping within a Sugar Supply Chain', Journal of the Operational Research Society, vol.

57 (5), pp. 490-498.

Higgins, A.J. & Laredo, L.A. 2006, 'Improving harvesting and transport planning within

a sugar value chain', Journal of the Operational Research Society, vol. 57, pp. 367-376.

Jiao, Z., Higgins, A.J. & Prestwidge, D.B. 2005, 'An integrated statistical and

optimisation approach to increasing sugar production within a mill region', Computers

and Electronics in Agriculture, vol. 48, pp. 170-181.

Kelley, J.E. & Walker, M.R. (1959). Critical-path planning and scheduling. IRE-AIEE-

ACM '59 (Eastern): Papers presented at the December 1-3, 1959, eastern joint IRE-

AIEE-ACM computer conference (pp. 160-173). New York, NY, USA:ACM.

Kelley, J.E. 1961, Critical-Path Planning and Scheduling: Mathematical Basis, .

Le Gal, P., Lyne, P.W.L. & Soler, L. 2008, 'Impact of sugarcane supply scheduling on

mill sugar production: A South African case study', Agricultural Systems, vol. 96, pp. 64-

74.

Lejars, C., Le Gal, P. & Auzoux, S. 2008, 'A decision support approach for cane supply

management within a sugar mill area', Computers And Electronics In Agriculture, vol.

60, pp. 239-249.

Parikh, S.C. & Jewell, W.S. 1965, 'Decomposition of Project Networks', Management

Science, vol. 11 (3) Series A, Sciences, pp. 444-459.

Sargent, E.D. 1980, 'The Impact of Operational Research on Agriculture', The Journal of

the Operational Research Society, vol. 31 (6), pp. 477-483.