nyeri county government state department of agriculture ... · dairy goats of the kenya alpine...
TRANSCRIPT
NYERI COUNTY GOVERNMENT
State Department of Agriculture
NJAA MARUFUKU KENYA (NMK) PROJECT
Component 3: Support to Private Sector Food Security Innovation
END OF PROJECT REPORT
Kieni East Sub County
Project Title: Kieni East Dairy Goat Upgrading Program For Better Nutrition and
Economic Empowerment
Contact Address: Pascal M. Mailu
Chief Executive Officer
G.R.A.C.E. Africa,
P.O.BOX 13993—00100,
NAIROBI.
Tel No: 020 523 0176 or +254 720 446 884
Website: www.graceusa.org
E-mail: [email protected]
SECTION A: OVERVIEW
Project Implementation and Progress
The project was implemented over a two year period between June 2013 and June 2015 with the
aim of improving the nutritional status and incomes of vulnerable members of the community
through upgrading of local goats for purposes of increasing dairy goat milk yields and
introduction of internal savings and lending schemes in Kieni East district
Implementation was jointly done by G.R.A.C.E Africa –Nanyuki office Project Manager, Mr
Gideon Muthuri, Ministry of Agriculture, NMK Desk officer, Kieni east Sub County-Mrs.
Beretha Ngunjiri and the Project Technical liaison officer, from ministry of Livestock-Ms Jane
Njuguna.
The progress made by the project from start to end was commendable, with almost all project
activities being implemented within the project’s time frame and numerous set targets exceeded
by the end of the project. The project’s financial and non financial resources were used in an
effective and efficient way, and community participation levels were high, thus ensuring high
levels of sustainability.
Fig 1: Project Sign post at Gakawa location, Kieni East Sub-County
Key Accomplishments/Milestones
The following key actives were implemented as per the project’s work plan;
1. District Coordination Unit (DCU) Meetings
All scheduled DCU meetings (which were later renamed as Sub-County Coordinating Unit-
SCCU meetings) were held during which project activities were planned and implemented
activities reviewed on a regular basis. The first SCCU meeting served a dual purpose as it was
also the project inception meeting during which the project manager and the technical liaison
officer shared the details of the project with the other members of the SCCU. However, it was
sometimes necessary to hold SCCU meetings between the scheduled meetings on a needs basis
as demanded by the different project implementation phases. This caused the number of SCCU
meetings to exceed the number initially planned and budgeted for in the initial work plan. The
number of SCCU meetings at the end of the project had reached 10.
2. Stakeholder Analysis and Stakeholder Workshops
In order to identify the different project stakeholders in the sub-county, a stakeholder
analysis/mapping was conducted during the first SCCU meeting in June 2013. A total of 18
stakeholders were identified and invitation letters sent out inviting all of them to the first
stakeholder meeting in order to introduce the project to them, granting them the opportunity to
interrogate it and eventually get their buy-in. A majority of the stakeholders remained committed
to the project throughout the project life as indicated by the regular attendance of the 3
Stakeholder workshops that were held bringing together 10 representatives from different
agencies.
Fig 2: A stakeholder Workshop in progress
3. Identification of Target Beneficiaries
The project was set to be implemented through organized groups of 10 members that would host
the pedigree dairy goats (bucks). A strict selection criterion was developed and used to vet the
more than 45 proposed groups, reducing the final number to 30 groups. These groups passed the
set criteria, whose requirement included the following;
The groups had to be registered with the ministry of gender and social services and have
renewed the certificate
Holding regular meeting with records of minutes of meetings
Groups were either Persons Living With Disability (PWD), Persons Living With
HIV/AIDS (PLWHAs) or groups comprised of or caring for Orphans and Vulnerable
Children (OVC)
Through the Provincial Administration, all groups that had met the selection criteria were invited
to attend public meetings (barazas), during which the project was introduced to them and
feedback obtained on their perception of the project so as to foster the project’s ownership by the
intended direct beneficiaries. The identification and selection process proved successful because
out of the 30 initial groups selected, all except 2 remained with the project through the
implementation phase and have remained active and functional even beyond the project life. The
2 groups had to be dropped because they were found to be short of some key selection criteria
but they were replaced in a timely manner
.
Fig 3.Sample project sensitization baraza.TLO Project Manager addressing the community at
different sites
4. Training of Enumerators
After the successful selection of the beneficiaries, 10 youths from the community were identified
and trained as enumerators. The training was conducted by the project manager and technical
liaison officer, who employed the training materials and procedures provided by the NMK
secretariat during the earlier workshop on Project Management and Implementation preceding
the release of the grants. The training equipped the selected youth with data collection skills in
preparation for the baseline survey aimed at providing baseline data on the state of dairy goat
farming and income levels among the intended beneficiaries before the project commenced.
5. Baseline Survey
In July 2013 and following a successful campaign to introduce the project to the community
through public meetings (barazas) a baseline survey was conducted in all the five locations,
covering all the beneficiary groups. The aim of the baseline survey was to establish the status of
the groups at time zero of the project in terms of their activities in dairy goat farming and other
enterprises and hence identify the gaps that would form the basis of the scheduled trainings. This
exercise was conducted by the enumerators and supervised by the project manager, TLO and
D.O.
A report detailing the outcomes of the survey was prepared and submitted. The baseline findings
not only guided the content and focus of the planned trainings but also provided important
information against which the project progress was to be measured during the continuous
monitoring activities as well as the end term evaluation exercise.
6. Constituting a Management Committee
A project management & implementation committee was constituted drawing representatives
from the project beneficiaries. The management committee was actively involved in project
management activities throughout the project period. The formation of this committee was part
of the exit and sustainability strategy through the provision of continuity beyond project life as
detailed in a later section of this report. The committee which was constituted in August 2013
has remained in office and continues to oversee the management activities of the project.
7. Trainings
Fig 4: G.R.A.C.E. Africa PM trains on Fig 5 A livestock officer puts a point through
In order to ensure successful implementation and uptake of the project by the beneficiaries and
the community at large, several capacity building trainings were conducted for the 30 selected
groups from September 2013. The topics of the training were modeled against the main project
components as well major cross-cutting issues and reached a total of 923 people, 61 of whom
were trained as Trainers of Trainees (ToTs) in valued addition and Income Generating Activities
(IGAs). Trainings provided were as follows;
i. Dairy goat upgrading and breeding.
ii. Housing and record keeping.
iii. Disease and disease control and routine management.
iv. Feeding, pasture establishment and conservation.
v. Nutritional management of HIV/AIDS and other vulnerable persons
vi. Establishment of high value kitchen gardens.
vii. SILC – Savings and Internal Lending Communities
viii. Value addition of the dairy goat milk (Yoghurt making)
ix. IGAs – Income Generating Activities (Bead work).
x. Cross cutting issues – Fuel Energy Conservation
Figs 6.NMK DO preparing for training Fig 7.Yorghut making demonstration
Table 1: Trainings modules and number of participant
Fig 8: SILC training Workshop Fig 9: Financial record book shot of SILC
Activity for Naromoru Child Support group
Tour/exposure visit to an advanced area in dairy goat farming
In order to build confidence of the beneficiaries and demonstrate the practicability of the project,
35 farmers were taken on an exposure visit to Mukurwe-ini sub-county to “look and learn” from
their counterparts in the region which is more advancement in dairy goat rearing. During the
Trainings DATES. expected total
1 Record keeping, kitchen garden
and disease control
24/9/2013,
25/9/2013
and 26/9/2013
300 292
2 Dairy goat feeding, fodder
establishment and routine
management
27/8/2013,
28/8/2013
and29/8/2013
300
285
3 Dairy goat breeding and housing;
Energy saving; HIV nutrition and
DGAK regulations and
opportunities.
30/7/13, 31/7/13
and
1/8/13
300
285
4 4.Training on value addition and
I.G.A(beadwork)
24/2/15, 25/2/15,
25/2/15 and26/2/15
30 (ToTs)
30
5 SILC (Table Banking)
26/5/14,27/5/14,
28/5/14 and29/5/14
30 (ToTs) 31
visit, the farmers were briefed on the best practices on dairy goat rearing, asked numerous
questions and got feedback from their hosts. The tour was a worthy investment as the farmers
returned determined to implement the project based on the lessons learnt from Mukurwe-ini.
Upon returning to the project site, the famers who participated in the visit passed on the
knowledge and skills gained to other farmers during group meetings and trainings.
Fig 10: Tour to Mukurwe-ini, host farmer shares his practices with participants
9. Sourcing and distribution of pedigree dairy goat (bucks)
In November 2013 and after all the preparatory project activities had been done, 30 pedigree
dairy goats of the Kenya Alpine breed were sourced from Muranga, Kirinyaga and Nyeri
municipalities and distributed to the 30 identified groups.
The groups had selected one group member who would host the buck, tend to it while making it
available to serve group members’ and community does within a set radius. Those receiving the
services paid an agreed fee. Most groups charged KES 200 for non-members and KES 100 for
members per service. The money was used to buy food supplements and meet other maintenance
costs associated with the bucks’ upkeep. The host farmers benefitted from the manure generated
by the goats to improve their farms’ soil fertility, leading to a significant increase in crop
production.
Fig 10: Sourcing of bucks- Kirinyaga County Fig 11: Distribution of dairy goats
10. Launch/ Famers’ Field Day
Group members launched the project during the inception period. All the thirty benefiting groups
were represented.
A field day was later held in August 2014 at the premises of the Gathiuru Hope OVC group in
Githima location at the height of the project implementation process to showcase the progress
and success of the project and to educate the community further on the various components of
the project. The event which was attended by 161 farmers, with 16 stakeholders groups
exhibiting their project work and related materials.
Fig11: Exhibitors during field day
11. Rotation of bucks
Based on animal health and production practices, the buck rotation was timed to take place
before its first off-spring came to maturity to prevent inbreeding. This was successfully done in
May 2015 by the implementing team and dairy goat association of Kenya (DGAK) staff.
12. Regular monitoring and evaluation exercises
Project monitoring and evaluation exercises were conducted every quarter beginning in the fifth
month of the project implementation for a total of 7 times. Key project indicators were monitored
and documented to inform progress made in project implementation. Opportunities and gaps
were identified during the exercise and addressed accordingly by the technical team or through
the project management committee to improve on the project.
Fig 12: Monitoring Exercise with SCAO Fig 13: Monitoring Exercise
13. Implementation of Exit and Sustainability Strategy
From the onset of the project and throughout the life of the project, various strategies were
implemented to prepare the beneficiaries for project termination (exit) and to set in place
sustainability mechanisms. These included;
i. The constitution of a project management and implementation committee comprised of
group leaders, who were actively involved in project management activities throughout
the project period and finally took over the management role of the project at the end of
the project.
ii. Training of project beneficiaries on the establishment and management of Savings and
Internal Lending Communities (SILC), a form of table banking to enhance provide
micro-finance for the beneficiaries. SILC operates through a collective pooling of
individual finances to form a common kitty from which members borrow and repay with
interest. The interest generated goes back to the members increasing their kitty and is
shared out equally at the end of each year. These skills enabled the beneficiaries to access
credit services to invest in their wellbeing (education, shelter, health) and in improving
livelihoods.
iii. Charging a fee to farmers and other community members who needed the services of the
bucks ensured that there was a small kitty to maintain the bucks’ health and other needs
as well as generating income for the group members.
14. End of project evaluation exercise and Final Report Submission
The implementing team conducted an end of project evaluation exercise, which was also
contractual obligation between G.R.A.C.E. Africa and the NMK secretariat. The evaluation was
aimed at assessing to what extent the project was successful in meeting its expected objectives
and results. The evaluation also sought to inform planning, implementation and management of
future G.R.A.C.E. Africa projects by embracing lessons learnt and replicating best practices. The
exercise was conducted between 03/06/2015 and 08/06/2015 by enumerators supervised by TLO,
PM, NMK DO and SCAO. All data collected was analyzed, collated, summarized and a report
produced, a copy of which is attached to this report.
Variances in Key Targets during the project Implementation Period
There was no significant variance between the set targets and those achieved by the end of the
project period. All the activities reported at least 100% implementation status of the key targets.
Table 2: Key Challenges/ Constraints Encountered During the Implementation Period, their Effects to Project Activities and How
they were addressed
NO Challenge Effect Anticipated
Outcomes
Home Grown Solutions
1. Shortage of DGAK staff to cover the
area adequately in terms of registration
of the offspring.
It took along time to
have the offsprings
registered.
Poor market prices
for the unregistered
goats.
Pool the goats together to
minimize the number of visits by
the DGAK staff and enhance a
wider coverage.
2. Securing of training venues that were
friendly to those groups of people with
disability, while at the same time fairly
considering the other vulnerable
categories.
PWDs concentration
levels were low due to
fatigue
Forgetfulness of
covered topics.
Future, trainings to be tailored to
the specific needs of different
groups based on the type and level
of their vulnerability.
3 Training lessons in the work plan were
very few with many topics forcing the
trainers to take more than 5 hrs for
training sessions which was not
desirable to PLWHAs.
High levels of fatigue
among participants
during training
sessions.
Low concentration
levels due to
tiredness.
Incorporation of other interesting
topics like solar lighting and
breaks (energizers) to keep the
audience alert.
Table 3: Level of Participation by Beneficiaries, Stakeholders/Collaborators
Direct beneficiaries 95%
Stakeholders 85%
Collaborators 80%
SECTION B: STATUS SUMMARY STATEMENTAT END OF PROJECT
Summary of Key Work-Plan Activities
Key Tasks Start Date Target Due Date % Complete Status at end of project
Project sensitization barazas 1st Month 1
st Month 100% Achieved
Stakeholder forums 1st Month 15
th Month 100% Achieved
DCU meetings 1st Month 26
th month 100% plus Achieved
Baseline survey 1st Month 1
st Month 100% Achieved
Baseline survey report writing 1st Month 1
st Month 100% Achieved
Constituting of management committees 3rd
Month 3rd
Month 100% Achieved
Training on dairy goat husbandry, Milk utilization & value
addition, record keeping, crosscutting issues and financial
management and IGAs
4th Month 26
th month More than
100%
Achieved
Supervision, monitoring and evaluation 5th Month Once every
quarter
More than
100%
Achieved
Tour to an advanced area 6th
Month 6th Month 100% Achieved
Sourcing and distribution of pedigree bucks 6th
Month 6th
Month 100% Achieved
Field Day / Launching of Project 15th Month 25
th Month 100% Achieved
Rotation of bucks 20th Month 100% Achieved
Report writing 3rd
Month 26th Month 100% Achieved
2. Project Activity Status SECTION C: DETAILED REPORT
1. Fund Utilization
Funds received
this Quarter
Cumulative Activity summary Expenditure
per activity
Cumulative
expenditure
Balance
1,773,128 1,960,686 1,960,686
15925.5 1976611.5 Bank Interest 1,976,611.5
Bank taxes 3293.2 3293.2 1,973,318.3
Mobilization and
sensitization
19,100 22393.2 1,954,218.3
SCCU meeting 67,450 89843.2 1,886768.3
Stakeholder forums 62,900 152743.2 1,823868.3
Trainings 761,630 914373.2 1,062238.3
Sourcing 31,750 946123.2 1030488.3
procurement 420,000 1366123.2 610488.3
Distribution 103,850 1469973.2 506638.3
M&E 211,100 1681073.2 295538.3
Baseline survey 73,090 1754163.2 222448.3
Tours 42,500 1796663.2 179948.3
Rotation of bucks 26500 1823163.2 153448.3
Field day/launch 50,700 1873863.2 102748.3
publicity 33930 1907793.2 68818.3
Retrieving the
bucks
10,000 1917793.2 58818.3
End of project
evaluation
38500 1956293.2 20318.3
Report
writing/stationery
20,250 1976543.2 68.3
Totals 1,976543.2
Key project
activity
Progress made Original
Schedule
Variance Actual Cost Budgeted
cost
Variance
Sensitization and
mobilization
More than 300
members and
five chiefs
sentisized
35,100 16,000 19,100 21,970
2,870
Baseline survey Conducted 51,000 22,000 73,090 51,000 22,000
report written
and submitted
publicity Erected in
Gakawa location
and banner
prepared
40,000 6,070 33,930 33,930 …….
trainings All training done 647,400 114,230 761,630 776,880 15,250
Stakeholders
meeting
3 meetings held 22,050 40,850 62,900 62,900 ……….
M&E 79,600 131,500 211,100 184,800 26,300
sourcing/
Procurement/
Distribution
30pedigree
bucks purchased
And distributed
628,000 72,400 555,600
555,600
…….
tour 1 tour held 47,000 4,500 42,500 42,500 ………..
Launch/field day 1 held 53,600 2,900 50,700 41,500 9,200
rotation 28 bucks rotated 34,650 8,150 26,500 26,500 …….
End evaluation Done and report
written
51,000 12,500 38,500 37,500 1,000
Explanatory Notes:
Explain variance in activities and costs. Also include:
Number of SCCU meetings exceeded the number of meetings planned; this was necessitated by demand created by the extensive project area
not envisioned in the initial project design.
The extensive area of coverage also required more days to conduct M&E visits and related exercises than had been planned and budgeted for
in the initial work plan and budget.
3. Project Outputs/Deliverables
Key project activity Projected output Actual realized Variance Remarks
Trainings 5 held 5 0
Stakeholders meeting 3held 3 1 achieved
SCCU meetings 4 10 held 6 More due to regular
planning meetings
Baseline survey Done and report
written
1 done 0 Report written and
submitted
Distribution of bucks 30bucks bought
and distributed
30 0 2 died
M&E 8 8 visits 0
Tour 1 held 1 0
Management
committee
1 1 0
Reports 8
Evaluation exercise 1 1 0
4. Extension Activities & Field Visits
Backstopping team Date of visit Key recommendation Remarks
SCAO,DO ,TLO,PM,LO 6/11/13 and
7/11/13
To advised to complete
house construction
SCAO,DO ,TLO,PM,LO 28/1/14 to
30/1/14
The groups were advised
to keep proper records
and deworm the bucks.
Most does served were
pregnant.
SCAO,DO ,TLO,PM, 22/7/14 to31/7/14 Community members
who are not already
6 groups had been formed
by end of project.
engaged in economic
empowerment activities
to form SILC/table
banking groups.
SCAO,DO
,TLO,PM,DGAK
22/10/14 to
31/10/14
Dgak assistance to be
visiting groups frequently
to address issue of
registering
Most farmers had offspring
from the bucks.
SCAO,DO
,TLO,PM,DGAK
26/3/15 to 1st
/4/15
Mange treatment for
those infected before
rotation.
Farmers ready for rotation.
SCAO,DO ,TLO,PM,L.O 2/5/15 to 6/5/15 Most bucks healthy after
rotation.
SCAO,DO ,TLO,PM &
Local chief
15/6/15 To follow up the sold
buck
Buck keeper to buy another
By September.
5. Collaboration with Stakeholders
Name of stakeholder Specific area of
collaboration
Remarks
Dairy Goat Association of Kenya
(DGAK)
Breeding program of dairy
goats
Registration with DGAK in
progress
Kieni East dairy goat farmers
association (KIDAGOFA)
Marketing and Value addition
of goats milk
All the 30 groups to register
with KIDAGOFA
Local administration Mobilization All chiefs and their assistants
were involved
6. Revolving Fund
Amount saved this quarter Cumulative saved to date Remarks
222,270.00 222,270.00 Not all groups have started
NB: The total amount of money saved by some of the groups since SILC/table banking training.