north carolina cts committee meeting #7 april 17, 2001

77
North Carolina CTS North Carolina CTS Committee Meeting #7 Committee Meeting #7 April 17, 2001

Upload: myra-dean

Post on 13-Jan-2016

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: North Carolina CTS Committee Meeting #7 April 17, 2001

North Carolina CTS North Carolina CTS Committee Meeting #7Committee Meeting #7

April 17, 2001

Page 2: North Carolina CTS Committee Meeting #7 April 17, 2001

Introduction and Welcome Introduction and Welcome

Page 3: North Carolina CTS Committee Meeting #7 April 17, 2001

Scoping/Basin Plans

Status Updates:Status Updates:

Page 4: North Carolina CTS Committee Meeting #7 April 17, 2001

Schedule for Schedule for Completing Basin Completing Basin

PlansPlans

White Oak

Lumber

Tar-Pamlico

Cape Fear

Neuse

Pasquotank

12/14/00

12/27/00

1/23/01

2/27/01

4/13/00

5/1/01 (Est.)

May 2001

May 2001

End of May 2001

End of May 2001

June 2001

June 2001

River Basin Draft Date Final Date (Est.)

Page 5: North Carolina CTS Committee Meeting #7 April 17, 2001

Final Scoping Final Scoping MeetingsMeetings

Three separate meetings will be held to present the Draft Plan for the Neuse River Basin. Dates and locations include: April 23rd — Raleigh, NC April 24th — Goldsboro, NC April 25th — New Bern, NC

All impacted counties & communities invited

Provides final opportunity for input

Page 6: North Carolina CTS Committee Meeting #7 April 17, 2001

Final Scoping Final Scoping MeetingsMeetings

Two separate meetings are planned for the Pasquotank River Basin. Proposed dates and locations include: May 17th — Elizabeth City, NC May 18th — Manteo, NC

Draft Plan for Pasquotank River Basin under preparation

Page 7: North Carolina CTS Committee Meeting #7 April 17, 2001

After the Final After the Final MeetingsMeetings

Draft Basin Plan may be revised State’s Floodplain Mapping Contractor

will develop business and technical proposals

Basin Plan will be finalized and notification provided to all impacted counties and communities

Production phase will then begin

Page 8: North Carolina CTS Committee Meeting #7 April 17, 2001

Flood Data andMapping Development

Status Updates:Status Updates:

Page 9: North Carolina CTS Committee Meeting #7 April 17, 2001

White Oak River White Oak River BasinBasin

Negotiations completed Delivery Order finalized Field survey of hydraulic

structures and streams completed Engineering analyses underway

Expected completion mid-May 2001

Page 10: North Carolina CTS Committee Meeting #7 April 17, 2001

Lumber River BasinLumber River Basin

Negotiations completed Delivery Order finalized Field survey of hydraulic

structures and streams underway Engineering analyses underway

First of three phases expected to be completed end of May 2001

Page 11: North Carolina CTS Committee Meeting #7 April 17, 2001

Tar-Pamlico River Tar-Pamlico River BasinBasin

Negotiations completed Delivery Order finalized Field survey of hydraulic

structures and streams underway Engineering analyses underway

First of three phases expected to be completed end of May 2001

Page 12: North Carolina CTS Committee Meeting #7 April 17, 2001

Cape Fear River Cape Fear River BasinBasin

Negotiations completed Delivery Order finalized Field survey of hydraulic

structures and streams underway Engineering analyses underway

First of three phases expected to be completed end of May 2001

Page 13: North Carolina CTS Committee Meeting #7 April 17, 2001

LIDAR Surveys andDEM Development

Status Updates:Status Updates:

Page 14: North Carolina CTS Committee Meeting #7 April 17, 2001

Task 1 — LIDAR Data Task 1 — LIDAR Data Acquisition as of 4/10/01Acquisition as of 4/10/01

Watershed Concepts: Data collection is 100% complete

for the White Oak, Tar-Pamlico, Neuse, and Pasquotank River Basins

Greenhorne & O’Mara: Data collection is 90% complete for

the Lumber and Cape Fear River Basins

Page 15: North Carolina CTS Committee Meeting #7 April 17, 2001

Task 2 — Generation Task 2 — Generation ofof

Bare-Earth DEMsBare-Earth DEMsWatershed Concepts

Page 16: North Carolina CTS Committee Meeting #7 April 17, 2001

Task 2 — Generation Task 2 — Generation ofof

Bare-Earth DEMsBare-Earth DEMsGreenhorne & O’Mara

Page 17: North Carolina CTS Committee Meeting #7 April 17, 2001

Task 3 — Generation Task 3 — Generation of TINs and Breaklinesof TINs and Breaklines

Watershed Concepts:

Green = Completed

Orange = In Progress

Blue = Approved Awaiting shipment

of new DOQQs from CGIA

Page 18: North Carolina CTS Committee Meeting #7 April 17, 2001

Task 3 — Generation Task 3 — Generation of TINs and Breaklinesof TINs and Breaklines

Greenhorne & O’Mara: Breaklines for

Scotland, Hoke, Montgomery, Moore, and Richmond Counties are complete

TIN development has begun for 21 grids of the Lumber River Basin

Page 19: North Carolina CTS Committee Meeting #7 April 17, 2001

LIDAR Quality Control Surveys

Selected Firms for RFQ #19-000018

Status Updates:Status Updates:

Page 20: North Carolina CTS Committee Meeting #7 April 17, 2001

Quality Control Quality Control SurveysSurveys

LIDAR quality control field work has been completed for the White Oak and Lumber River Basins

LIDAR quality control field work is in progress for the Tar-Pamlico,Cape Fear, and Neuse River Basins

Page 21: North Carolina CTS Committee Meeting #7 April 17, 2001

DFIRM Graphic Specifications

Status Updates:Status Updates:

Page 22: North Carolina CTS Committee Meeting #7 April 17, 2001

NC DFIRM PrototypeNC DFIRM Prototype

North Carolina DFIRM prototype has been developed for review: Three colors Customized border, legend, and title block Customized map symbology 10,000’ x 10,000’ grid tiling “Statewide” mapping

One panel includes all communities/counties in that tile

Page 23: North Carolina CTS Committee Meeting #7 April 17, 2001

DFIRM Database Specifications

Status Updates:Status Updates:

Page 24: North Carolina CTS Committee Meeting #7 April 17, 2001

NC DFIRM DatabaseNC DFIRM Database

North Carolina DFIRM database design underway: Incorporates FEMA’s standard DFIRM

database items Base map data DFIRM features

Enhanced features Field inventory H&H model input and results

Supports future map updates

Page 25: North Carolina CTS Committee Meeting #7 April 17, 2001

Partnering

Status Updates:Status Updates:

Page 26: North Carolina CTS Committee Meeting #7 April 17, 2001

Information Technology Information Technology Requirements Analysis and Requirements Analysis and

Preliminary DesignPreliminary Design

Page 27: North Carolina CTS Committee Meeting #7 April 17, 2001

User Requirements User Requirements AnalysisAnalysis

User Requirements Document produced in draft form Summarizes survey and interview

results Establishes set of functional and data

requirements Will serve as basis for system design

Review needed by CTS Committee Location is www.ncfloodmaps.com

Page 28: North Carolina CTS Committee Meeting #7 April 17, 2001

Preliminary System Preliminary System DesignDesign

Preliminary System Design Document available in draft form by April 18th Builds on content of User Requirements

Document Establishes initial design parameters Enumerates options for future detailed

consideration Outlines potential implementation risks

Page 29: North Carolina CTS Committee Meeting #7 April 17, 2001

Next Steps for IT Next Steps for IT ComponentComponent

Finalize User Requirements Document Finalize Preliminary System Design

Document Develop schedule and work content for

Detailed Design and Implementation Phase

Prepare and issue Delivery Order for next phase

Page 30: North Carolina CTS Committee Meeting #7 April 17, 2001

Base Map Data Base Map Data Collection/Community Collection/Community

PartneringPartnering

Page 31: North Carolina CTS Committee Meeting #7 April 17, 2001

Working Group Working Group Reports/Updates:Reports/Updates:

Higher Standards

Page 32: North Carolina CTS Committee Meeting #7 April 17, 2001

Preliminary/Post-Preliminary/Post-Preliminary Processing forPreliminary Processing for

NC FISs and FIRMsNC FISs and FIRMs

Page 33: North Carolina CTS Committee Meeting #7 April 17, 2001

Current FEMA Current FEMA ProcessingProcessing

Preliminary FIS and FIRM issued 30-day comment period Final Community Meeting Publication of proposed flood

elevation determination in Federal Register and twice in local newspaper

Community notified by letter

(continued)

Page 34: North Carolina CTS Committee Meeting #7 April 17, 2001

Current FEMA Current FEMA ProcessingProcessing

90-day appeal period initiated by second newspaper publication

Any appeal/protests resolved Letter of Final Determination issued

(establishes effective date of FIS and FIRM and begins 6-month compliance period

FIS and FIRM become effective; distributed by Map Service Center

Process typically requires 1 to 1½ years

Page 35: North Carolina CTS Committee Meeting #7 April 17, 2001

6-Month Compliance 6-Month Compliance PeriodPeriod

To participate in the NFIP, communities must comply with Section 60.3 of the NFIP regulations

Section 60.2 requires that FEMA give communities 6 months to adopt/update ordinances that comply with Section 60.3 criteria.

Page 36: North Carolina CTS Committee Meeting #7 April 17, 2001

Land Management and Use Land Management and Use CriteriaCriteria

YesYesYesYes60.3(d) & (e)

YesNoYesYes60.3(e)

NoYesYesYes60.3(d)

NoNoYesYes60.3(c)

NoNoNoYes60.3(b)

NoNoNoNo60.3(a)

V Zones

Floodways

BFEs100-Year Flooding

Land-Use Classificati

on

Type of Flood Hazard InformationShown on FIRM

Page 37: North Carolina CTS Committee Meeting #7 April 17, 2001

Compliance withCompliance with60.3 Criteria60.3 Criteria

Most North Carolina communities have adopted 60.3(d)- and 60.3(e)-level model ordinances even without a floodwayand V zones

Most NC community ordinances specify that they apply as of the date of initial community NFIP map and “to any subsequent revisions”

For these communities, current ordinances will be adequate, and 6-month compliance period will not be needed

Others will have to update ordinances

Page 38: North Carolina CTS Committee Meeting #7 April 17, 2001

Post-Preliminary Processing for Post-Preliminary Processing for NC Counties in More than 1 NC Counties in More than 1

BasinBasin Majority of Phase I North Carolina

counties located in more thanone basin

Engineering for basins will not be completed at the same time

Engineering for portions of counties may be completed as much as a year before the other portions (longer for counties located partially in Phase II basins)

Page 39: North Carolina CTS Committee Meeting #7 April 17, 2001

Post-Preliminary Processing for Post-Preliminary Processing for NC Counties in More than 1 NC Counties in More than 1

BasinBasin Method of post-Preliminary

processing must: Meet all statutory and regulatory

requirements for due process Reduce time frames as much as

possible Be cost effective

Page 40: North Carolina CTS Committee Meeting #7 April 17, 2001

Recommended Recommended MethodMethod

Issue a Preliminary when the basin is completed, but include only the portion of the county in the basin

Initiate the 90-day appeal period for the Preliminary

When the other basin(s) are complete, issue a revised Preliminary(s) that includes the rest of the county and proceed with 90-day appeal period

Page 41: North Carolina CTS Committee Meeting #7 April 17, 2001

Recommended Recommended MethodMethod

If a basin affects only a portion of a panel, the Preliminary will be issued for all panels affected by the basin

For portion of panel not affectedby basin, base map informationwill be shown but not flooding information—Note on FIRM will refer users to effective map for flood hazard information in that area

Page 42: North Carolina CTS Committee Meeting #7 April 17, 2001

Recommended Recommended MethodMethod

To Expedite Processing: Schedule news releases to take place

within 1 week of issuance of the Preliminary

With Preliminary, notify community that 90-day appeal period will begin with the second news release and that the Final Meeting will be conducted during the first month of issuance of Preliminary

(continued)

Page 43: North Carolina CTS Committee Meeting #7 April 17, 2001

Recommended Recommended MethodMethod

To Expedite Processing: Thorough outreach should reduce number

of technical appeals and protests, thus making it safe to initiate the appeal period prior to the final meeting

When the basins for other parts of county are completed, use the same process

(continued)

Page 44: North Carolina CTS Committee Meeting #7 April 17, 2001

Recommended Recommended MethodMethod

To Expedite Processing: When State initiates engineering and

mapping for subsequent basins, give priority to areas within the basin that will complete the county

When last Preliminary for county is issued, provide notice of the appeal period and provide the effective date of the FIS and FIRM to begin the 6-month compliance period (continued)

Page 45: North Carolina CTS Committee Meeting #7 April 17, 2001

Recommended Recommended MethodMethod

To Expedite Processing: 6-month compliance period and last 90-

day appeal period will run concurrently Final Meeting will be conducted during

first month of issuance of Preliminary FIRM

Appeals will be processed on acase-by-case basis, depending onextent of area affected

(continued)

Page 46: North Carolina CTS Committee Meeting #7 April 17, 2001

Recommended Recommended MethodMethod

To Expedite Processing: Approach for counties partially in

Phase II basins will be more flexible If time lag might be more than a year,

effective information for portion in Phase II might be digitized and used to develop the initial county FIS and FIRM

When Phase II basin is complete, a revision would be processed

Page 47: North Carolina CTS Committee Meeting #7 April 17, 2001

Recommended Recommended MethodMethod

Final maps will become effective within approximately 7 months after issuance of final Preliminary for the county as compared to 1 to 1½ years with FEMA’s standard process

Page 48: North Carolina CTS Committee Meeting #7 April 17, 2001

Recommended Recommended MethodMethod

For 7 of the counties that are split between basins, Watershed Concepts is going to make complete county submissions.

For these counties, the complete countywide Preliminary FIS and FIRM can be issued and the 6-month compliance period will begin as soon as the Preliminary is issued. The90-day appeal period will begin with the second Public Notice.

Page 49: North Carolina CTS Committee Meeting #7 April 17, 2001

Preparation for Preliminary Preparation for Preliminary and Post-Preliminary and Post-Preliminary

ProcessingProcessing State and FEMA will begin

researching community ordinances to identify communities that will have to update their ordinances

Page 50: North Carolina CTS Committee Meeting #7 April 17, 2001

DFIRM Production:DFIRM Production:Priority Listing of Priority Listing of

CountiesCounties

Page 51: North Carolina CTS Committee Meeting #7 April 17, 2001

Phase I CountiesPhase I Counties

Engineering, mapping, and DFIRM production in the White Oak, Lumber, and Tar-Pamlico River Basins prioritized by county

Priority consideration given to (1) the anticipated impact of new mapping,(2) if the county is within multiple basins, and (3) contractor’s ability to complete county study by 09/30/2001

Page 52: North Carolina CTS Committee Meeting #7 April 17, 2001

White Oak River White Oak River Basin Priority ListingBasin Priority Listing

1.Carteret

2. Onslow

3. Jones

Yes

No

No

Mid-July

Mid-July*

Mid-July*

Complete County?

Estimated Prelim. Date

*For the portion of the White Oak River Basin

County

Page 53: North Carolina CTS Committee Meeting #7 April 17, 2001

Lumber River Basin Lumber River Basin Priority ListingPriority Listing

1.Columbus

2.Brunswick

3. Scotland

4. Robeson

5. Hoke

No

No

No

No

No

End of Sept*

End of Sept*

End of Sept*

End of Oct*

Mid-Sept*

Complete County?

Estimated Prelim. Date

*For the portion of the Lumber River Basin

County

Page 54: North Carolina CTS Committee Meeting #7 April 17, 2001

Lumber River Basin Lumber River Basin Priority Listing Priority Listing

(cont’d)(cont’d)

6. Bladen

7.Montgomery

8. Richmond

9. Moore

No

No

No

No

Mid-Sept*

End of Aug*

End of Aug*

Mid-Sept*

Complete County?

Estimated Prelim. Date

*For the portion of the Lumber River Basin

County

Page 55: North Carolina CTS Committee Meeting #7 April 17, 2001

Tar-Pamlico River Tar-Pamlico River Basin Priority ListingBasin Priority Listing

1. Edgecombe

2. Franklin

3. Pitt

4. Nash

5. Beaufort

Yes

Yes

Yes

Yes

Yes

Mid-Aug

Mid-Sept

Mid-Aug

Mid-Aug

End of Sept

Complete County?

Estimated Prelim. DateCounty

Page 56: North Carolina CTS Committee Meeting #7 April 17, 2001

Tar-Pamlico River Tar-Pamlico River Basin Priority ListingBasin Priority Listing

6. Hyde

7. Warren

8. Halifax

9. Granville

10. Martin

11. Vance

Yes

No

No

No

No

No

End of Sept

End of Sept*

Mid-Oct*

Mid-Oct*

End of Oct*

End of Oct*

Complete County?

Estimated Prelim. Date

*For the portion of the Tar-Pamlico River Basin

County

Page 57: North Carolina CTS Committee Meeting #7 April 17, 2001

Overall County Overall County PriorityPriority

12) Beaufort13) Hyde14) Warren*15) Halifax*16) Hoke*17) Granville*18) Martin*19) Vance*20) Bladen*21) Montgomery*22) Richmond*23) Moore*

1) Carteret2) Onslow*3) Columbus*4) Jones*5) Brunswick*6) Edgecombe7) Franklin8) Pitt9) Scotland*10) Nash11) Robeson*

*DFIRM production completed for only a portion of the county by September 30, 2001.

Page 58: North Carolina CTS Committee Meeting #7 April 17, 2001

How Will Flood Elevation How Will Flood Elevation Data for Approximate Data for Approximate Areas Be Depicted onAreas Be Depicted onNorth Carolina FIRMs?North Carolina FIRMs?

Page 59: North Carolina CTS Committee Meeting #7 April 17, 2001

How were Zone A Areas How were Zone A Areas on FEMA’s FIRMs on FEMA’s FIRMs

determined?determined? Designate a Special Flood Hazard

Area where FEMA has not determinedBase Flood Elevations Regulatory definition of Zone A in 44 CFR 64.3

Typically based on rudimentary calculations or other data source For example, regression equations and normal

depth computations; USGS floodprone quadrangle maps; hydric soils data

Page 60: North Carolina CTS Committee Meeting #7 April 17, 2001

What is Approximate Study What is Approximate Study Method Method

for NC Flood Mapping Program?for NC Flood Mapping Program? Based on H&H analyses using DEMs

Regression equations for discharges HEC-RAS models for flood profiles

Key difference from Detailed StudyMethod—bridge geometry will not be surveyed and cross sections will not include bathymetric data Where bridge geometry is readily available, coding

of bridge geometry will be attempted

“Buildable” analyses—can be upgraded later to full detailed study

Page 61: North Carolina CTS Committee Meeting #7 April 17, 2001

How can NC’s Flood Elevation How can NC’s Flood Elevation Data for Approximate Areas be Data for Approximate Areas be

used?used? Floodplain management Flood insurance policy rating

Rates are typically higher in A zones than in AE zones because risk is less well known

If BFE can be provided, rates are more actuarially based

Page 62: North Carolina CTS Committee Meeting #7 April 17, 2001

How Will Flood Elevation DataHow Will Flood Elevation Datafor Approximate Areas will be for Approximate Areas will be

depicted on NC FIRMs?depicted on NC FIRMs?

Publish on the FIRM as BFEs Designate zones as AE Provide Statutory 90-day appeal

period As required by 42 USC § 4104[a] Appeals must be based on scientific

or technical data

Page 63: North Carolina CTS Committee Meeting #7 April 17, 2001

How will BFEs in Approximate How will BFEs in Approximate Areas be distinguishable from Areas be distinguishable from

Detailed Areas? Detailed Areas? On FIRM:

No floodway or 500-year floodplain Considering alternate symbology for BFEs

In Flood Insurance Study Report: Profiles will have only 100-year profile Peak discharge table will only have

100-year discharge No Floodway Data Table Different methodology for determining BFEs

will be explained

Page 64: North Carolina CTS Committee Meeting #7 April 17, 2001

What are the What are the Benefits of this Benefits of this

Approach?Approach? Elevation data for approximate areas

will be readily available for floodplain managers and flood insurance agents

Elevation data will carry more weight Communities will be required to follow

more stringent 60.3(c) requirements versus 60.3(b) “best available data” requirements

Page 65: North Carolina CTS Committee Meeting #7 April 17, 2001

What are the potential What are the potential drawbacks of this drawbacks of this

approach?approach? Showing BFEs may imply higher

degree of accuracy than warranted

May result in more appeals Impacts time and cost

Page 66: North Carolina CTS Committee Meeting #7 April 17, 2001

Why not show the Why not show the approximate flood approximate flood

elevations as “AFEs” and elevations as “AFEs” and treat them as “Best treat them as “Best

Available Data”?Available Data”? FEMA’s regulations and governing

statutes do not permit this. In order to portray the AFEs on the

FIRMs and treat them as “Best Available Data,” an extensive rulemaking process would be required. Scheduling does not permit this.

Page 67: North Carolina CTS Committee Meeting #7 April 17, 2001

Local Contributions toLocal Contributions tothe NC Mapping Effortthe NC Mapping Effort

Page 68: North Carolina CTS Committee Meeting #7 April 17, 2001

Potential Pilot forPotential Pilot forLOMA DelegationLOMA Delegation

Page 69: North Carolina CTS Committee Meeting #7 April 17, 2001

Potential Pilot for Potential Pilot for LOMA/LOMR-F LOMA/LOMR-F

DelegationDelegation FEMA is considering delegation of

LOMA/LOMR-F issuing authority to engineers and surveyors

North Carolina Society of Surveyorshas volunteered to work with North Carolina Geodetic Survey ona potential pilot

Page 70: North Carolina CTS Committee Meeting #7 April 17, 2001

FEMA’s CommunityFEMA’s CommunityRating System (CRS)Rating System (CRS)

Page 71: North Carolina CTS Committee Meeting #7 April 17, 2001

CRS BackgroundCRS Background

Founded in 1990 and Codified in the Flood Insurance Reform Act of 1994

Flood insurance premiums are adjusted to reflect reduced risk resulting from activities that meet the three CRS goals: Reduce flood losses Facilitate accurate insurance ratings Promote awareness of flood insurance

Page 72: North Carolina CTS Committee Meeting #7 April 17, 2001

BenefitsBenefits

Reduced flood insurance premiums for property owners

Enhanced Public Safety Reduction in damage to property, public

infrastructure, and human suffering Avoidance of economic disruption and losses Protection of the environment Allows a community to evaluate itself against a

nationally recognized benchmark Provides technical assistance in providing and

implementing activities

Page 73: North Carolina CTS Committee Meeting #7 April 17, 2001

Benefits (cont’d)Benefits (cont’d)

Reduced Premiums Class 1 — 45% Class 2 — 40% Class 3 — 35% Class 4 — 30% Class 5 — 25%

Class 6 — 20% Class 7 — 15% Class 8 — 10% Class 9 — 5% Class 10 — n/a

Page 74: North Carolina CTS Committee Meeting #7 April 17, 2001

CRS Recognized CRS Recognized ActivitiesActivities

18 recognized activities eligible forCRS credit points 300 Series Activities — Public information

activities 400 Series Activities — Mapping and regulatory

programs focused on new development 500 Series Activities — Damage reduction

programs where current development is at risk 600 Series Activities — Flood preparedness

programs, flood warning and levee and dam safety programs

Page 75: North Carolina CTS Committee Meeting #7 April 17, 2001

Participating Participating CommunitiesCommunities

Communities receive a ranking between 1 and 10

9 is for the minimum amount of activities required to receive a reduced premium (5%)

As of October 1, 2000, there were 926 participating communities nationwide: 5 with a Class 10 rating 431 with a Class 9 rating 352 with a Class 8 rating 110 with a Class 7 rating 27 with a Class 6 rating 1 with a Class 3 rating

Page 76: North Carolina CTS Committee Meeting #7 April 17, 2001

ParticipatingParticipatingNorth Carolina North Carolina CommunitiesCommunities

North Carolina currently has 74 participating communities that are Class 9 and lower, including: 44 Class 9 24 Class 8 4 Class 7 2 Class 6 (the Towns of Southern Shores

and Wrightsville Beach)

Page 77: North Carolina CTS Committee Meeting #7 April 17, 2001

Action Items/Wrap UpAction Items/Wrap Up