nhs rotherham clinical commissioning group body papers... · key performance indicators (kpis)...
TRANSCRIPT
NHS Rotherham Clinical Commissioning Group Operational Executive 19 May 2017
Strategic Clinical Executive 24 May 2017
GP Members Committee 31 May 2017
Governing Body 7 June 2017
Commissioning Plan Performance Report: Quarter 4
Lead Executive: Ian Atkinson, Deputy Chief Officer Lead Officer: Lydia George, Planning and Assurance Manager
Alex Henderson-Dunk, Performance and Intelligence Manager Lead GP: N/a
Purpose:
For GPMC to note the progress with delivery of the CCGs Commissioning Plan as at the end of Quarter 4.
Background:
In 2013 a performance framework for the Commissioning Plan was developed so that the CCG could assess its progress against key priorities and on its implementation of the plan. The report has been refined each year but has broadly remained the same.
In Quarter1 of 2016/17, in line with the new CCG Improvement and Assessment Framework and the revision of the GB overall performance report the Commissioning Plan performance Report was revised to provide a fuller picture of delivery. The key changes were:
• Each of the 15 priority areas from the Commissioning Plan are reported• Each priority area has clear milestones and targets aligned to the Commissioning Plan• Each priority area includes Key Performance Indicators taken from the new CCG
Improvement and Assessment Framework metrics, the new Governing BodyPerformance report, Quality Premiums, the Better Care Fund or are regular key localmetrics already reported
• QIPP information is included for those priority areas that are subject to QIPP• Any associated risks from the GB Assurance Framework are reported• Lead GP and Lead officers are reported
From 2016/17 the performance framework will be reported 4 times a year and will be received at Governing Body in August, November, February with a final year- end report in May.
Analysis of key issues and of risks Lead officers have provided commentary against the milestones where performance is off track. From quarter 2 officers were asked to identify any milestones where the direction of travel had the potential to deteriorate or improve.
Milestones There are 52 milestones in total, see breakdown below:
RAG rate Number of milestones %
Red 0 0 Amber 4 7 Green 48 93 Total 52 100
The number of milestones on track or complete has slightly decreased from 94% in Q3 to 93% in Q4.
There are no red milestones and amber milestones are summarised below: RAG rate
Milestone description
Commentary Q1 Q2 Q3 Q4
Amber M10 Ensure replacement Risk Stratification Tool is in place to support the reduction in emergency admissions.
Moved from green to amber in Q4, tool was rolled out at the end of March 2017, there are some usability issues highlighted by practices which are being addressed through Dr Foster.
G G G A
M29 Delivery the required number of bed reductions as per Rotherham element of the LD plan
Moved from green to amber in Q2 due to the TCP trajectory not being met. However, both local and TCP are now not achieving. A remedial action plan is in place to achieve both trajectories by June 2017.
G A A A
M39 Involvement of the care co-ordination centre in the EOLC pathway
Discussions continue to take place and it is still the intention for the CCC to be a single point of access for EOLC.
R A A A
M40 Achieve 40% implementation of the Case Management Palliative Care Template in Primary Care
Decision to be included was delayed at the start of the year, implementation starting to take traction.
A A A A
It is worth noting that both the RAG rate and direction of travel remains the same for the following milestones:
Q3
RAG rate
Direction of travel Milestone description Commentary
Green M13: Completion of Business Case for the re-ablement village
There are delays due to the timing of decisions through organisations governance structures. Strategically, through the Rotherham Place Plan this area is on track, however there is a risk of not achieving this target set through BCF.
Green M25: RDaSH to produce a delivery plan including milestones and timescales for the delivery of the Adult Transformation Plan
On track, some concern that the plan will not be produced, assurance being monitored via the MH/LD QIPP Committee.
Key Performance Indicators (KPIs) There are 48 KPI’s in total, see breakdown below:
RAG Rate Number of KPIs %
Red 9 18 Amber 4 8 Green 18 37 *WD 17 36 Total 48 100
* these KPIs are awaiting further data nationally
Overall there are approximately 37% of KPIs on track, which has decreased from 42% in Q3. The three areas that have deteriorated to red are; Delayed Transfers of Care, 6 week IAPT and 62 day cancer – see table below.
KPIs that have deteriorated: KPI Description Q3 Q4 K9 Delayed transfers of care from hospital Green Red K21 Percentage of people who are "moving to recovery" of those who have
completed IAPT treatment Green Amber
K23 Proportion of people waiting 6 weeks or less from referral to entering a course of IAPT treatment
Green Red
K46 Percentage seen within 62 days after a referral by GP (Cancer) Amber Red KPIs that have improved: KPI Description Q3 Q4 K2 Utilise NHS e-referral service to enable choice at 1st routine elective
referral Red Amber
K4 Contain growth in A&E attendances Amber Green K40 Patients requiring a Continuing Healthcare assessment will have an
eligibility assessment within 28 days from the receipt of the continuing healthcare checklist - Adults
Amber Green
K41 Patients requiring a Continuing Healthcare assessment will have an eligibility assessment within 6 weeks from the receipt of the continuing healthcare checklist – Children’s
Amber Green
There remains a significant number of KPIs still awaiting national data.
Below is a list of the red and amber KPIs, commentary on performance can be found in the Governing Body Performance Report or Governing Body Quality Report.
RAG rate
No. Key Performance Indicator Description Q1 Q2 Q3 Q4
Red (9)
K3 Contain growth in the number of non-elective admissions
WD R R R
K5 Achieve A&E 4 hour access standard R R R R K7 People who have had a stroke who are admitted to the
acute stroke unit in 4 hours of arrival to hospital R R R R
K9 Delayed transfers of care from hospital G G G R K13 Cat A ambulance response calls within 8 minutes R R R R K17 Reduction in the number of antibiotics prescribed in
primary care G TBC R R
K23 Proportion of people waiting 6 weeks or less from referral to entering a course of IAPT treatment
A R G R
K44 Cancer (all) diagnosed at stage 1 and 2 R R R R K46 Percentage seen within 62 days after a referral by GP G R A R
Amber (4)
K2 Utilise NHS e-referral service to enable choice at 1st routine elective referral
R R R A
K21 Percentage of people who are "moving to recovery" of those who have completed IAPT treatment
A A G A
K28 Reduce the number of people admitted in line with the SY and North Lincolnshire LD TCP trajectory
G A A A
K37 Patients in receipt of CHC will have a completed annual review - Adults
G G G A
Finance The position in terms of QIPP savings reported in Q3 remains the same in Q4 with the following exceptions, narrative for the QIPP position can be found in the Finance and Contracting Governing Body report:
Commissioning Priority
QIPP Scheme Q1 Q2 Q3 Q4
Medicines Management
Medicines waste reduction Medicines Management QIPP Rebates and contract efficiencies Do not prescribe
Continuing Care and Funded Nursing Care
Review of Children’s CHC packages Review of assessment tool for determining packages
Review of high cost care packages
Risk To maintain consistency of reporting for the 2016-17 Performance Framework, the risks represent the position as at the end of February 2017. The GB Assurance Framework was significantly revised in March 2017 and these changes will be reflected in the updated Commissioning Plan Performance Framework for 2017-18.
Approval history:-
OE 19 05 2017
SCE 24 05 2017
GPMC 31 05 2017
CCG GB 07 06 2017
Recommendations:
GPMC are asked to note the report and that:
1. The year-end position in term of milestones is very positive, although there has been a slight deterioration from 94% in Q3 to 93% in Q4.
2. The position in terms of KPIs is positive, but has deteriorated from 42% in Q3 to 37% in Q4, this is due to deterioration in 3 areas.
3. There are still a number of KPIs which are waiting for national data. 4. The final QIPP position can be found in the Finance and Contracting report received at
Governing Body. 5. The risk position is as at the end of February 2017.
Commissioning Plan Performance Report 2016/17
Q4
Meeting Date
Operational Executive 19 05 2017 Strategic Clinical Executive 24 05 2017 GP Members Committee 31 05 2017 CCG Governing Body 07 06 2017
Definitions for RAG Ratings:
Red KPI Milestones QIPP
Less than 2% achieved Not started or significant issues Not started or Started but still high risk
Amber
KPI Milestones QIPP
Within 2% achieved Started but not on track OK with medium risk
Green
KPI Milestones QIPP
Achieved or complete On track Achieving as planned
Please note
• That there are a number of KPIs from the new Improvement and Assessment Framework where data is not available yet.
• To maintain consistency of reporting for this year, the risks scores reflect the position at the end of February 2017. From March 2017 a revised GB Assurance Framework was in place and this will be reflected in the updated Commissioning Plan Performance Framework for 2017-18.
1
1 Primary Care Lead GP: Jason Page Lead Officer: Jacqui Tufnell
Funding in 2016/17 = £0.6m for the LIS, £1.2m for Case Management and funding for the CCG Commissioned LES’s
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M1 Primary Care Quality Contract – implement and monitor 3 standards for 2016/17.
Com / primary care plan
Q1 G G G G Complete
M2 Primary Care Quality Contract – develop remaining standards for 2017/18
Com / primary care plan
Q3 G G G G Complete
M3 Primary Care Quality Contract – Agree contracts for 2017/18 standards
Com / primary care plan
Q4 G G G G Complete
M4 Primary Care Self-care pilot – complete tele-health evaluation
Com / primary care plan
Q2 A A G G Complete - the evaluation has been completed and it has been approved by the primary care committee to roll-out introduction to all practices.
M5 Monitor and evaluate the effectiveness of the Care Home Alignment with GP practices
Com / primary care plan
Q4 G G G G Complete
Key Performance Indicators (KPIs) Source 2016/17 Target Q1 Q2 Q3 Q4
K1 Patient experience of GP services (I&AF 128b)
I&A Framework Quality
premium
85% or a 3% increase on Jul-
16
WD WD A WD Performance from two most recent survey waves is 84.8% - wave 1 was Jul-Sep 15 / wave 2 was Jan-Mar 16. Almost achieved.
K2 Utilise NHS e-referral service to enable choice at 1st routine elective referral (I&AF 105a)
I&A Framework Quality
premium
80% or 20% increase on
Mar-16 (77%)
R 61.6%
R 73.1%
R 67.3%
October 16
A 74.2%
Agreed action plan in place with TRFT which we continue to monitor. There has been significant improvement across specialities, but 2 remain challenging. IT team are working with GPs to increase utilitsation. January performance was very high at 82%, February has fallen however to 74.2%. NHS Digital has not yet published March figures on which final achievement will be determined.
QIPP APMS Core Contract Values QIPP Plan £125,000 G G G G See GB Finance and Contracting report
Premises Costs reimbursements QIPP Plan £118,000 G G G G See GB Finance and Contracting report Property Services QIPP Plan £274,000 G G G G See GB Finance and Contracting report
Risks Risk Description Risk Score GP quality and Efficiency GB Assurance
Framework Failure to improve GP quality and efficiency in partnership with NHS England - current concerns are due to overall GP capacity
d l )
12
CQC inspection of practices GB Assurance Framework
Worst case scenario, a practice may be identified as so inadequate that emergency arrangements have to be enacted
12
Impact of changes to primary care support England from NHS to Capita contract
GB Assurance Framework
Issues in relation to collection and delivery of medical records, this is a national not local issue
12
To note, the following KPIs are within the I&A Framework but are not currently in publication • Primary care access (I&AF 128c) • Primary care workforce (I&AF 128d)
2 Unscheduled Care Lead GP: David Clitherow Lead Officer: Sarah Lever / Claire Smith
Funding in 2016/17 = £60.1m
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M6 Completion of the capital Build for the Emergency Centre (Q2 2017/18)
Com Plan STP
Q4 G G G G On track - Handover from Kier took place May. Infrastructure (IT and equipment) will be put in place before cleaning ready for decant from B1.
M7 Implement new IT system Com Plan Q3 G G G G IT system went live October. Initial problems encountered in recording performance data were rectified in December 16. M8 Full implementation of the Emergency
Centre Model Com Plan
STP Q3 G G G G On track - scheduled for 6th July 17
M9 Expand role of the Care Co-ordination Centre (CCC) to manage the interface between acute /community
Com Plan STP
Q3 A G G
G Expansion of CCC on track, further discussions to take place around the clinician to clinician proposals still ongoing. MH integration expected October 2017. Project group set up and action plan in development
2
M10 Ensure replacement Risk Stratification Tool is in place to support the reduction in emergency admissions
Com Plan Q4 G G G A Risk strat tool was rolled out at the end of March 17. Some usability issues have been highlighted by practices, which are being worked through with Dr Foster.
Key Performance Indicators (KPIs) Source 2016/17 Target Q1 Q2 Q3 Q4 Key Performance Indicators (KPIs)
K3 Contain growth in the number of non-elective admissions
Contractual target
Meet contracted
levels
R R R Emergency admissions as at February 17 YTD were £442k over plan. Emergency assessments were £645k over plan. RFT only, February provisional data only.
K4 Contain growth in A&E attendances Contractual target
Meet contracted
levels
A A G A&E attendances as at February 17 YTD were £296k under plan. RFT only, February provisional data.
K5 Achieve 4 hour access standard for A&E Constitutional GB Report
95% by Q4 R 91.6%
YTD as at 30/06
R 91.7%
YTD as at 02/10
R 79.2%
YTD as at Dec 16
R 88.6% 16/17
Full Year
The A&E standard of 95% hasn’t been met during the year, with 2016/17 performance at 88.6%. GP streaming has been implemented within the department, which has had an impact although maintaining staffing levels within the department remains challenging. The CCG continue to work closely with partners through the A&E delivery board to realise improvement. National performance against this standard remains challenged. The national position for England for February 17 was 87.6%.
K6 Reduce unplanned hospitalisation for chronic Ambulatory Care Sensitive conditions (I&AF 106a)
I&A Framework GB Report
tbc WD WD WD WD Data has been published as part of the IAF but no standard or target has been indicated.
QIPP Delivery of A and E Assessments through the Clinical Decision Unit
QIPP Plan £286,000 G G G G See GB Finance and Contracting report
Reducing levels of Activity growth in A&E QIPP Plan £280,000 A A R R See GB Finance and Contracting report
Reduce IHAM NHSE growth assumption in line with local trend analysis
QIPP Plan £226,000 R R R R See GB Finance and Contracting report
Risks Risk Description Risk Score Unscheduled Care QIPP GB Assurance
Framework Failure to deliver system wide efficiency programme for unscheduled care
20
A&E target GB Assurance Framework
Failure to meet A&E targets 16
3 Transforming Community Services
Lead GP: Phil Birks Lead Officer: Claire Smith Funding in 2016/17 =£28.5m
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M11 Implement and monitor the Integrated Locality Team at the Health Village
Com Plan Q2 G G G G On track – discussions are taking place in regards to Leeds University undertaking an independent evaluation in June 2017.
M12 Implement and monitor the Integrated Rapid response Service
Com Plan Q2 G G G G On track - Note that staff are integrated on one site a lead is now in post.
M13 Completion of the Business Care for the Re-ablement Village
Com Plan Q4 G G G
G
Significant analysis of the current position has been completed. A project group has been established. Joint approach required with RMBC, there have been delays due to timing of decisions. Strategically on track via Rotherham Place Plan, however risk of not achieving this BCF milestone
Key Performance Indicators (KPIs) Source 2016/17 Target Q1 Q2 Q3 Q4 Key Performance Indicators (KPIs)
K7 People who have had a stroke who are admitted to the acute stroke unit in 4 hours of arrival to hospital
Quality Premium GB Report
90% national standard
R 50.0%
R TRFT
position = 55%
R TRFT
Position = 73%
R TRFT
Position = 54% as at
Feb 17
TRFT position used for Q2 to Q4 (part of) as most up to date available and is reflective of overall CCG position. Standard has not been met throughout the year.
K8 Emergency readmissions within 30 days of discharge from hospital
BCF GB report
12.2% R Jun 16 YTD = 12.3%
G Sep 16 YTD = 12.2%
G Oct 16 YTD = 12.0%
G Feb 17 YTD = 12.1%
Performance has been consistent throughout the year being just over or under plan. As at Feb 17 readmissions were under plan.
3
K9 Delayed transfers of care from hospital (I&AF 127e)
I&A Framework BCF
GB Report Quality
Premium
Feb 17 Target YTD = 2492.6 delayed days
from hospital per 100,000
population ( 18+)
G Apr-Jun 16 YTD = 676
G Sep 16 YTD = 1345.3
G Oct 16 YTD =
1651.2
R Feb 17 YTD =
2698.7
Performance has gone off track. This is due to better processes across partners which better identify delayed transfers of care.
K10 Number of unscheduled admissions of patients > 65 years out of hours
TCS reporting Threshold = -15%
R April / May =
270
TBC WD WD Some concern as data has not been available since October. CCG are aware and the issue is being addressed through contract performance meetings.
K11 Number of A&E attendances by care home residents
TCS reporting Threshold = 1250
R R WD WD Some concern as data has not been available since October. CCG are aware and the issue is being addressed through contract performance meetings.
K12 GP satisfaction rate for the Integrated Community Nursing Service
TCS reporting Threshold = 80%
G G WD WD Some concern as data has not been available since October. CCG are aware and the issue is being addressed through contract performance meetings.
QIPP Reducing levels of Activity in Emergency Admissions - neuro rehab, integrated rapid response and integrated locality teams
QIPP Plan £1,039,000 A R R R See GB Finance and Contracting report
Risks Risk Description Risk Score None identified GB Assurance
Framework
4 Ambulance and Patient Transport Services
Lead GP: David Clitherow Lead Officer: Julia Massey
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M14 Develop a process to understand the CPR performance delivered to support improved patient outcomes
Com Plan Q4 TBC G G G Complete
M15 Improved hospital pre alert and treatment plans for patients with suspected Sepsis
Com Plan Q4 TBC G G G Complete
M16 Commission a provider for PTS service Com Plan Q4 G G G Complete
Key Performance Indicators (KPIs) Source 2016/17 Target Q1 Q2 Q3 Q4 Key Performance Indicators (KPIs)
K13 Response to category A (Red1) ambulance calls within 8mins (I&AF 127d)
I&A Framework GB report
75% R June = 59.3%
R Sep = 60.4%
R Nov = 58.6%
R Mar = 63.9%
YAS are currently participating in an NHS England-led Ambulance Response Programme (ARP), which went live from the 21st April 2016. The pilot ran for 3 months initially and has subsequently been extended. This programme resulted in a change to call category classifications. These classifications have subsequently been revisited by the programme and further changes implemented during October. The only standard currently available to assess performance is 75% of category 1 calls under 8 minutes. In March, YAS achieved 63.9% against the 75% standard.
QIPP None identified
Risks Risk Description Risk Score Ambulance Targets GB Assurance
Framework Failure of YAS to achieve RED 1 8 minute Target at CCG level and Yorkshire & Humber wide
20
4
5 Clinical Referrals (Diabetes is a clinical priority within the I&A Framework) Lead GP: Anand Barmade Lead Officer: Janet Sinclair-Pinder
Funding in 2016/17 = £66.7m
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M17 Implement 10 clinical thresholds Com Plan Q4 G G G G Complete
M18 Extension of virtual clinics from haematology to other areas such as endocrinology
Com Plan Q2 G R G G Complete – now part of NHSE CQUIN
M19 Delivery of agreed audit programme and implementation of recommendations (6 in 2016/17 – 4 clinical thresholds, 1 cancer, 1 emergency admissions)
Com Plan Q4 G G G G Complete
M20 Review and implement Rotherham Diabetes Care model around the Portsmouth care model which focuses around “super six” care.
Com Plan Q4 G G G G Complete
Key Performance Indicators (KPIs) Source 2016/17 Target Q1 Q2 Q3 Q4 Key Performance Indicators (KPIs)
K14 Patients waiting 18 weeks or less from referral to hospital treatment (I&AF 129a)
Constitution / I&A Framework
GB Report
92% G June 16 = 94.8%
G Sep 16
= 94.2%
G Nov 16 = 95.1%
G 94.5%
1617 Full Year
% Patients on incomplete non-emergency pathways waiting no more than 18 weeks. Performance remained on track throughout 16/17.
K15 Contain growth in elective activity Contractual Meet contracted
levels
TBC G G G 1.1m below plan for elective activity – RFT only, Feb provisional data.
K16 Achievement of outpatient follow up ratios
Contractual 11% reduction in follow ups from last year at RFT
TBC -3.6% G G RFT are down 6.5% on last year’s activity. We contracted for an 11% reduction in follow-up, therefore the trust are over planned activity. The over-performance continues in Cardiology, Respiratory Medicine, Geriatric Med, Ophthalmology, Dermatology, ENT, T&O, Rheumatology, Paediatrics and Paediatric Ophthalmology. An agreed ratio is in place in the contract above which the CCG will not pay. This is a £1.1m forecast reduction at month 11 flex.
QIPP Reduction in follow-ups where TRFT are above peer average
QIPP Plan £816,000 G G G G See GB Finance and Contracting report
Reducing levels of Activity growth in direct access pathology in line with clinical pathways
QIPP Plan £73,000 R A G G See GB Finance and Contracting report
Reduce IHAM NHSE growth assumption in line with local trend analysis
QIPP Plan £509,000 G R R R See GB Finance and Contracting report
Risks Risk Description Risk Score Planned Care QIPP GB Assurance
Framework Failure to deliver system wide efficiency programme for planned care
20
6 Medicines Management
Lead GP: Avanthi Gunasekera Lead Officer: Stuart Lakin Funding in 2016/17 =£48.0m
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M21 Potential savings of £447,500 have been identified by the introduction of a range of branded generic drugs. This figure will be adjusted as further schemes evolve. A target of 90% compliance has been set = annual savings £402,750.
Meds Management
Priority
90% G G G G On track - £470K delivered April 2016 - Feb 2017
M22 12 projects to be delivered over the financial year two have been completed £273,000 savings identified this figure will evolve has schemes are still being evaluated
Meds Management
Priority
12 projects G G G G On track - £370K delivered April 2016 - Feb 2017
M23 6 practices to have committed to become waste beacons and have begun the transformational work plan by September 2016. 9 practices have committed to the
Meds Management
Priority
Q3 TBC G G G On track - £414K delivered April 2016 - Feb 2017. 29 practices on target to be signed up by 31/03/2017.
5
programme and timescales
Key Performance Indicators (KPIs) Source 2016/17 Target Q1 Q2 Q3 Q4 Key Performance Indicators (KPIs)
K17 Reduction in the number of antibiotics prescribed in primary care (I&AF 107a)
Quality premium / I&A Framework
GB Report
4% reduction or 1.161 items per
STAR-PU
G 1.192
TBC R 1.210 Oct 16
R 1.244 Jan 17
Rotherham has a historically high use of antibiotics, and whilst our use of broad spectrum antibiotics is coming down, our overall volume is not. We have identified the practices with the highest use of antibiotics and are working with them to help them reduce.
K18 Appropriate prescribing of broad spectrum antibiotics in primary care (I&AF 107b)
Quality premium / I&A Framework
/ GB Report
lower than 10%, or to reduce by 20% from each CCG’s 2014/15
value
G 8.5
TBC G 7.4 Oct
16
G 7.1 Jan
17
On track
K19 Number of finance and quality “green” indictors
Meds Management
75% og 1302 indicators to be
green 976
G 552
(42%)
TBC G 56%
Oct 16
G As at October 2016 – increased to 56% of ‘green’ indicators.
QIPP Medicines Waste reduction QIPP Plan £700,000 A A A G See GB Finance and Contracting report Medicines Management QIPP QIPP Plan £550,000 A A A G See GB Finance and Contracting report Branded Generics QIPP Plan £250,000 G G G G See GB Finance and Contracting report Rebates and contract efficiencies. QIPP Plan £200,000 G G A G See GB Finance and Contracting report Do not prescribe QIPP Plan £150,000 A A A G See GB Finance and Contracting report Nationally Negotiated Price Reductions QIPP Plan £1,000,000 A G G G See GB Finance and Contracting report Service redesign - Nutrition/Gluten Free QIPP Plan £90,000 A A G G See GB Finance and Contracting report UNIDENTIFIED QIPP Plan £190,000 R R R R See GB Finance and Contracting report
Risks Risk Description Risk Score Prescribing QIPP GB Assurance
Framework Failure to deliver system wide efficiency programme for prescribing
20
7 Mental Health (Mental Health and Dementia are clinical priorities within the I&A Framework)
Lead GP: Russell Brynes (Adults) Richard Cullen (Childrens) Lead Officer: Kate Tufnell (Adults) Nigel Parkes (Childrens) Funding in 2016/17 =£35.0m
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M24 Externally evaluate Adult Mental Health Liaison and MH Social Prescribing programmes
Com Plan STP
Q3 G G G G Complete - Adult MH Liaison evaluation received and considered by MH & LD QIPP group. MH Social prescribing evaluation received and considered by CCG
M25 RDaSH to produce a delivery plan including milestones and timescales for the delivery of the Adult Transformation Plan
Com Plan Q4 G G G G On track, some concern that the plan will be produced, assurance being monitored via the QIPP Committee.
M26 Dementia – Implement and evaluation the Dementia LES
Com Plan Q3 G G G G Complete - LES has been implemented and referral numbers are increasing.
M27 Children and Young People - All children and young people will follow the agreed process in transitioning to adult services and all will have a transition plan in place.
Com Plan STP
Q4 G G G G Complete – A local CQUIN is in place for 2016/17 and a national CQUIN will apply for 2017/18. RDaSH have also completed the Transitions toolkit.
M28 Review of out of area placements in partnership with RDASH
Com Plan STP
Q2 G G G G Complete
Key Performance Indicators (KPIs) Source 2016/17 Target Q1 Q2 Q3 Q4 Key Performance Indicators (KPIs)
K20 People with 1st episode of psychosis starting treatment with a NICE- recommended package of care treated within 2 weeks of referral (I&AF 123b)
I& A Framework STP
GB report
50% G 72.9%
G Sep-16 = 57.1%
G Oct-16 = 87.5%
G Jan-17 = 100%
Performance has been on track throughout 1617.
K21 Percentage of people who are "moving to recovery" of those who have completed IAPT treatment (I&AF 123a)
I&A Framework GB Report
Quality Premium Health Outcomes
51.3% A 47.6%
Q1 YTD
A 50.1%
Sep YTD
G Oct 16 = 51.5%
A 16/17
Full Year = 50.5%
1617 full year did not meet the quality premium stretch target of 51.3%. It did meet the 50% national standard of 50% however.
K22 Diagnosis rate for people with dementia, as a percentage of the estimated prevalence (I&AF 126a)
GB Report I&A Framework
67% G June = 73.85%
G Sep = 75.1%
G Nov = 75.5%
G 1617 Year End = 75.9%
Standard has been on track during 1617. Final year end snapshot also met the national target.
6
K23 Proportion of people waiting 6 weeks or less from referral to entering a course of IAPT treatment
GB Report Health
Outcomes
75% A 71.8%
R 67.2%
G Nov = 78.0%
R 1617 Full
Year = 70.7%
1617 full year did not meet the national standard of 75%. Recent performance has been more positive however with 5 of the last 6 weeks (to w/c 8th May) achieving the standard.
K24 95% of children and young people who present at A&E in crisis will be seen within 1 hour
STP Com plan
No existing data
WD WD WD WD No data available
K25 95% of adults who present at A&E in crisis will be seen within 1 hour
STP Com plan
No existing data
WD WD WD WD No data available
QIPP MH and LD – joint risk share with RDASH to reduce the Out of Area activity
QIPP Plan £369,000 R R R R This was not achieved following a review by RDaSH / CCG to establish whether any OOA could be cared for more appropriately in a more local setting – see finance and contracting report for further detail.
Risks Risk Description Risk Score IAPT Waiting Times GB Assurance
Framework Failure to deliver the National IAPT waiting times standards for 6 and 18 weeks
16
CAMHS Reconfiguration GB Assurance Framework
Inability to deliver CAMHS reconfiguration in a timely manner
16
CAMHS Transformation GB Assurance Framework
Delivery of the CAMHS Local Transformation Plan 12
CAMHS Services GB Assurance Framework
Failure to improve Child and Adolescent Mental Health Services (CAMHS)
12
8 Learning Disability (Learning Disabilities is a clinical priority within the I&A Framework)
Lead GP: : Russell Brynes (Adults) Richard Cullen (Childrens) Lead Officer: Kate Tufnell
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M29 Deliver the required number of bed reductions as per Rotherham element of the plan
Com plan Q4 G A A A Q4 local and TCP trajectories are off track. Remedial action plan in place to achieve both trajectories by June 2017.
M30 Deliver GP training to support the Annual Health check DES
Com plan Q2 G G G G Complete
Key Performance Indicators (KPIs) Source 2016/17 Target Q1 Q2 Q3 Q4 Key Performance Indicators (KPIs)
K26 Ensure that patients receive a CTR prior to a planned admission to an Assessment and Treatment Unit or mental health inpatients
Com Plan STP
95% G G G G On track.
K27 Ensure that patients in an Assessment and Treatment Unit receive a Care and Treatment Review (CTR) every 6 months
Com Plan STP
100% G G G G On track
K28 Reduce the number of people admitted in line with the South Yorkshire and North Lincolnshire LD TCP trajectory
Local Reporting Target = 3 – CCG funded
LD beds
5 – NHSE funded secure
LD beds
G A A A Q4 local and TCP trajectories are off track. Remedial action plan in place to achieve both trajectories by June 2017.
QIPP Review of Assessment and Treatment Unit capacity in block purchase or spot purchase
QIPP Plan £483,000 G G G G See GB Finance and Contracting report
Risks Risk Description Risk Score None identified GB Assurance
Framework
To note, the following KPIs are within the I&A Framework but are not currently in publication • % of people with a learning disability on a GP register having annual health check (124b) • Reliance on specialist inpatient care for people with learning disability/autism (124a)
7
9 Maternity and Children’s Services (Maternity is a clinical priorities within the I&A Framework) Lead GP: Richard Cullen Lead Officer: Emma Royle
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M31 Complete a gap analysis and ‘next steps’ against the National Maternity Review: Better Births
Com Plan
Q3 G G G G Gap analysis completed and shared with NHSE as well as through the Working Together workstream. SY&B meetings are taking place to agree how to take forward Better Births on an STP footprint looking at common pathways /guidance, jointly monitoring populations health outcomes, joined up services, care, family support and development of self-management support. Local maternity System group in place and 4 Task and Finish Groups established.
M32 Complete a revised strategy and service specification for maternity services
Com Plan
Q3 G G G G Draft service spec has been completed (taking patient feedback into account) and shared with TRFT Clinical Director, Head of Midwifery for initial comment. Comments received from TRFT, final draft to go through contracting process for final sign off.
M33 Develop new community services specifications for children’s community nursing and specialist nurses to support the Care Closer to Home work-stream
Com Plan
Q3 G G G G On track -Parent Carers Forum consultation exercise ongoing. Draft Spec for Childrens Community Services completed and shared internally. Draft service spec for CCN shared with TRFT and comments received. TRFT looking at CCN models around the country, following this the spec will be agreed.
Key Performance Indicators (KPIs) Source 2016/17 Target Q1 Q2 Q3 Q4 Key Performance Indicators (KPIs)
K29 Reduce the number of neonatal mortality and still births (I&AF 125a)
I&A Framework GB Report
TBC WD WD WD WD Latest position is 9 per 1000 births for 2014. Awaiting more data to be published.
K30 % of children aged 10-11 classified as overweight or obese (I&AF 102a)
I&A Framework GB Report
TBC WD WD WD WD Latest position is 35.8% in 2015/16
K31 Maternal smoking at delivery (I&AF 101a)
I&A Framework GB Report
TBC WD WD WD WD Latest available position – Q3 16/17 - 19.9%
K32 Improve Women’s experience of maternity services (national maternity services survey) (I&AF 125b)
I&A Framework GB Report
TBC WD WD WD WD 2015 score of 7.87 is latest available position.
K33 Emergency admissions for children with lower respiratory tract infections
Health Outcomes GB Report
541.8 WD WD WD WD Latest position is 372.3 in 2015/16
K34 Unplanned hospitalisation for asthma, diabetes and epilepsy in under 19’s
Health Outcomes GB Report
364 WD WD WD WD Latest position is 272 in 2015/16
QIPP None identified
Risks Risk Description Risk Score Health Assessments for Children in Care GB Assurance
Framework NHS RCCG reputation as responsible commissioner for Children in Care - not having initial health assessments within statutory framework
12
10 Continuing Care and Funded Nursing Care
Lead GP: Richard Cullen Lead Officer: Alun Windle
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M34 Put in place a comprehensive range of agreed local policies and protocols in line with any contemporary guidance
CHC Standards AQuA
Assurance Report
Adults Q4
G G G G Complete - report to next AQA meeting.
M35 Children Q3
G G G G Complete – commences May 2017
M36 Develop a CHC training package for health and social care staff regarding local process and provision of CHC
CHC Standards AQuA
Assurance Report
Q4 G G G G Complete
M37 Implement processes fit for purpose with identified panels having an appropriate number, scope, size and membership
CHC Standards AQuA
Assurance Report
Adults Q1
G G G G Complete
M38 Children Q3
G G G G On track - new CHC strategic group for childrens with RMBC. Away day arranged for June to address issues.
8
Key Performance Indicators (KPIs) Source 2016/17 Target Q1 Q2 Q3 Q4 Key Performance Indicators (KPIs)
K35 People eligible for standard NHS continuing healthcare (I&AF 135a)
I&A Framework GB report
TBC WD WD WD WD
K36 Personal Health Budgets (I&AF 105b) I&A Framework GB report
TBC WD WD G G Target is for 250 to be achieved by 2020
K37 Patients in receipt of CHC will have a completed annual review
CHC Key Performance
Indicators
Adults 25-30%
outstanding
G G G A Physical and MH (CCGs CHC team) are below 25% LD (commissioned by RDaSH) is 46%
K38 Children 0%
outstanding
G G G G Complete
K39 Patients referred by Fast Track referral will receive a funding decision within 48 hours
CHC Key Performance
Indicators
100% Q4
G G G G Meeting the standard but reporting system does not provide evidence. New reporting system will be in place by May 2017.
K40 Patients requiring a Continuing Healthcare assessment will have an eligibility assessment within 28 days from the receipt of the continuing healthcare checklist - Adults
CHC Key Performance
Indicators
100% Q4
A A A G On track - increased focus on implementation and monitoring of the national framework, it is anticipated that it will gain traction. New reporting system will be in place by May 2017.
K41 Patients requiring a Continuing Healthcare assessment will have an eligibility assessment within 6 weeks from the receipt of the continuing healthcare checklist – Childrens
CHC Key Performance
Indicators
100% Q4
A A A G On track - increased focus on implementation and monitoring of the national framework, it is anticipated that it will gain traction. Vast majority are on track, however, new reporting system will be in place by May 2017 which will be able to provide accurate data.
QIPP Review of Children's CHC packages QIPP Plan £250,000 A A A G See GB Finance and Contracting report Review of Assessment tool for determining care packages
QIPP Plan £150,000 A A A G See GB Finance and Contracting report
Review of High Cost Care packages QIPP Plan £100,000 A A A G See GB Finance and Contracting report Risks Risk Description Risk Score
Equipment via IFR/CHC GB Assurance Framework
Equipment provided by RCCG via IFR/CHC - failure to have a procurement service to ensure cost effectiveness and service that ensures that the purchased equipment has a record of maintained and safety.
15
Failure to meet the National cut-off date for Previously Unassessed Periods of Care
GB Assurance Framework
Failure to meet the National cut-off date of 1st March 2017 for Previously Unassessed Periods of Care (PUPoC) - previously known as CHC Retrospective Claims
15
CHC overspend GB Assurance Framework
Overspend due to high costs of individual patients of continuing care
12
11 End of Life Care (EOLC)
Lead GP: Avanthi Gunasekera Lead Officer: Nigel Parkes Funding in 2016/17 =£3.0m
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M39 Involvement of the Care Co-ordination Centre in the EOLC pathway
Com Plan Q4 R A A A Started but not on track – discussions are still ongoing. It is still the intention for the CCC to be a single point of access for EOLC.
M40 Achieve 40% implementation of the Case Management Palliative Care Template in Primary Care
Com Plan Q4 A A A A Started but not on track, target = Q2 20%, Q3 30%, Q4 40%. Awaiting data.
Key Performance Indicators (KPIs) Source 2016/17 Target Q1 Q2 Q3 Q4 Key Performance Indicators (KPIs)
K42 Percentage of deaths which take place in hospital (I&AF 105c)
I&A Framework GB Report
TBC WD WD WD WD 2015/16 Q2 - 2016/17 Q1 – 46.1%
K43 Percentage of deaths not in hospital Public health 54% by Q4 WD WD WD WD Awaiting latest data.
QIPP None identified
Risks Risk Description Risk Score None identified GB Assurance
Framework
9
12 Specialised Services Lead GP: Richard Cullen Lead Officer: Jacqui Tufnell
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M41 Ensure robust arrangements for tier 3 Obesity in readiness for the transfer of tier 4 bariatric surgery in collaboration with public health
Com Plan Q4 G G G G Complete
Key Performance Indicators (KPIs) 2016/17 Target Q1 Q2 Q3 Q4 Key Performance Indicators (KPIs)
- n/a No KPIs QIPP
None identified Risks Risk Description Risk Score
Collaborative commissioning GB Assurance Framework
Effective collaborative commissioning of specialised services
12
13 Joint Work – local and Regional
Lead GP: Julie Kitlowski Lead Officer: Ian Atkinson/Keely Firth Funding in 2016/17 = BCF is £24.3m
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M42 Develop and deliver the STP STP Q3 G G G G On track M43 Develop and deliver the local place
based plan STP Q3 G G G G On track
M44 Oversee the implementation of the BCF with RMBC
Com Plan / BCF Plan
Q4 G G G G On track
Key Performance Indicators (KPIs) Source 2016/17 Target Q1 Q2 Q3 Q4 Key Performance Indicators (KPIs)
- Achievement of BCF KPIs – see BCF Plan Com Plan / BCF Plan
Q4 Please see BCF page of GB report
QIPP None identified
Risks Risk Description Risk Score Funding for BCF GB Assurance
Framework Resources reduced through introduction of BCF 12
14 Child Sexual Exploitation
Lead GP: Lee Oughton Lead Officer: Catherine Hall
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M45 As part of the annual update for GPs and practice staff, ensure minimum training level 3 is delivered
Com Plan Q1 G G G G Complete.
M46 Offer the same training as above to the remainder of primary care, social care and providers
Com Plan Q1 G G G G Complete
M47 Provide ongoing support to current and emerging SYP and NCA historic investigations
Com Plan Q1-Q4 G G G G Complete
M48 Provide 2 members to be part of the Multi Agency Safeguarding Hub team
Com Plan Q1- Q4 G G G G Complete
Key Performance Indicators (KPIs) Source 2016/17 Target Q1 Q2 Q3 Q4 Key Performance Indicators (KPIs)
- None identified QIPP
None identified Risks Risk Description Risk Score
None identified GB Assurance Framework
10
15 Cancer (Cancer is a clinical priorities within the I&A Framework) Lead GP: Richard Cullen Lead Officer: Janet Sinclair-Pinder
Deliverable Milestones for 2016/17 Source 2016/17 Target Q1 Q2 Q3 Q4 Comments
M49 Support on-going delivery of the TRFT Cancer Improvement action plan focusing on one year survival rates.
Com Plan STP
Q4 G G G G Now part of STP cancer alliance
M50 Implementation of NICE Cancer Guidelines
Com Plan STP
Q4 G G G G Now part of STP cancer alliance
M51 Fully engage with the Macmillan Living With and Beyond Cancer (LWABC) Programme to identify gaps in service and develop an action plan
Com Plan STP
Q3 G G G G Now part of STP cancer alliance
M52 Focus work on awareness raising / early diagnosis / 2 week wait
Com Plan STP
Q3 G G G G Now part of STP cancer alliance
Key Performance Indicators (KPIs) Source 2016/17 Target Q1 Q2 Q3 Q4 Key Performance Indicators (KPIs)
K44 Cancer (all) diagnosed at stage 1 and 2 (I&AF 122a)
I&A Framework Quality
Premium
>60% or 4 % point
improvement
R 2014 - 36.5%
R R R Off track but inconclusive as the latest reporting period was 2014 – Update as at May 17 – 2014 still latest published data
K45 Percentage seen within 2 weeks following an urgent referral by GP for suspected cancer
Constitution GB Report
93% G 95.9%
G Sep = 93.4%
G Oct = 95.3%
G Mar = 96.5%
On track all year
K46 Percentage seen within 62 days after a referral by GP (I&AF 122b)
Quality Premium
I&A Framework
85% G June = 89.2%
R Sep = 78.9%
A Oct = 83.6%
R Mar = 78.2%
Standard was met in February with performance at 85.7%, this has dipped however in March and February was the only month in the previous 7 where the standard was achieved
K47 Patient satisfaction rates >89% (Secondary care) (I&AF 122d)
I&A Framework Com Plan GB Report
Q1 G G G WD On track – note this is annual data
K48 Percentage of patients satisfied with support from their GP during treatment >66%
Com Plan STP
Q1 G G G WD On track – note this is annual data
QIPP None identified
Risks Risk Description Risk Score None identified GB Assurance
Framework
To note, the following KPIs are within the I&A Framework but are not currently in publication • Cancer one year survival rates – 2013 data (I&AF 122c)
Glossary
APMS Alternative Provider Medical Services BCF Better Care Fund CCC Care Co-ordination Centre CHC Continuing Healthcare
CAMHS Child and Adolescent Mental Health Services CQC Care Quality Commission EOLC End of Life Care GB Governing Body IFR Individual Funding Request I&A Improvement and Assessment LES Local Enhanced Services ‘Q’ ‘Quarter’
QIPP Quality Innovation Productivity and Prevention RMBC Rotherham Metropolitan Borough Council STP Sustainability and Transformation Plan TRFT The Rotherham Foundation Trust WIC Walk in Centre IHAM Indicative hospital activity model
11