nathan welsh: northparkes mines - winder east skip derailment

15
Northparkes Mines Winder East Skip Derailment Nathan Welsh, Senior Maintenance Engineer

Upload: nsw-resources-energy

Post on 16-Apr-2017

121 views

Category:

Government & Nonprofit


0 download

TRANSCRIPT

  • Northparkes Mines Winder East Skip Derailment Nathan Welsh, Senior Maintenance Engineer

  • Northparkes Mines

  • Winder Friction winder

    Non Man Riding (Excluding

    Maintenance & Emergency

    Egress)

    500 Metre Lift

    MDG33 & MDG2005 Compliant

    SIL Level 2 Compliant

    Single materials handling

    source of ore from the

    Underground Mine

  • Winder Head Ropes Haulage Rope

    Tail Ropes Balances Head

    Rope Load

    Guide Ropes Locates Skip in

    Horizontal Plane

    Guide Rope Weights Provides

    Guide Rope Tension

    Arrestor Frame Physical Barrier

    E-Cam Communication from

    Skip Devices to PLC, Utilises

    Head & Tail Ropes to Transmit

  • Fixed Guide Operation

    Fixed guides are

    installed at the skip

    loading and

    unloading points

    Prevents horizontal

    movement of the skip

    when loading and

    unloading

  • Fixed Guide Operation

  • Incident Details

    Time and Date of Incident: 1:38am

    10th of March 2015

    Incident Location: Main Winder

    Loading Station Docking Point

    Duration: 9140 minutes (6.3 Days)

  • Incident Aftermath

    Lower Shoes on East Skip Did

    Not Engage with Fixed Guides

    Four Structural Beams Damaged

    East Skip Stuck on Fixed Guides

    at Loading Station Docking

    Point

  • Timeline 01:35:49 Winder Tripped E-Cam Fault & Tub Latch Fault

    @ Fresh Air Base

    01:45:20 Winder Started in Manual

    Lower Shoes on East Skip Do Not Engage with Fixed Guides

    01:45:36 Winder Tripped E-Cam Fault & Tub Latch Fault

  • Timeline 01:47:10 Winder Started in Manual

    01:47:15 Winder Tripped E-Cam Fault & Tub Latch Fault

    Post 01:47:15 Maintenance Technician Calls SCADA to Shutdown

    Winder due to Loud Noise Winder is Isolated East Skip

    Derailment Identified

  • Photos

  • Investigation Investigation Item Outcome

    Misalignment of Conveyance Due to ballast weight, liners, ore hang up, or skip moving within the bridle Disproved

    Misalignment of Fixed Guides Due to impact damage (prior to incident), fatigue, or corrosion Disproved

    Uncontrolled Entry into Fixed Guides Due to fault in the winder control code or elongation of the head ropes Disproved

    Induced Conveyance Oscillation Due to loose or worn guide rope shoes/slippers, air flow, or obstruction in shaft Disproved

    Guide Rope Oscillation Due to failure of stauff clamps or insufficient guide rope tension Disproved

  • Investigation Investigation Item Outcome

    Misalignment of Conveyance Due to west shoe failing when struck by fixed guide Contributing Factor

    Induced Conveyance Oscillation Due to acceleration/deceleration when restarting mid shaft in Contributing Factor manual, insufficient guide rope lubrication, or the skip stopping in a zone of high turbulence (fresh air base)

    Investigation reviewed by OEM and 3rd party

    Contributing factors identified but root cause could not be verified

    3rd party modelling could not replicate incident using known

    parameters

  • Controls Contributing Factor Countermeasure/Control

    Misalignment of Conveyance West Shoe Failed When Struck by Fixed Guide

    Induced Conveyance Modified control system so that skip will slow Oscillation: to 1 m/s at 25 metres above the fixed guides - Accelerating/Decelerating when in manual

    when restarting mid shaft Greased guide ropes and confirmed 4 - Insufficient Guide Rope

    weekly guide rope greasing is active inLubrication system - Shaft Air Flow

    In addition Northparkes Mines is investigating the option of increasing

    guide rope weights to reduce conveyance oscillation

    Updated 4 weekly winder inspection with criteria and actions for visual inspection of the guide shoes

  • Summary Winder tripped 3 times on e-cam & tub latch fault

    Lower Shoes on East Skip Do Not Engage with Fixed Guides

    between 1st and 2nd trip

    Multiple contributing factors were identified in the

    investigation however a root cause cannot be validated

    Actions were implemented to control identified contributing

    factors before resuming production

    Additional countermeasure is under investigation

    Slide Number 1Northparkes MinesWinderWinderFixed Guide OperationFixed Guide OperationIncident DetailsIncident AftermathTimelineTimelinePhotosInvestigationInvestigationControlsSummary