automation @ northparkes rio tinto
TRANSCRIPT
-
8/13/2019 Automation @ Northparkes Rio Tinto
1/30
Automation @ Northparkes
-
8/13/2019 Automation @ Northparkes Rio Tinto
2/30
2
What we will cover today:
Implementation pathways4
Automation trials building the case for LHDautomation
3
1 Vision
2 Context
5 The way forward
-
8/13/2019 Automation @ Northparkes Rio Tinto
3/30
Unincorporated JV Rio Tinto (80% & manager) and Sumitomo Group (20%)
230 staff and 500 contractors
Copper and gold producer
Total production to the end of 2009
715,000 tonnes Cu
985,000 ounces Au
1,630 ha of mine lease within 5,670 ha of agricultural land (+ 2,102 ha nearby)
Current Life of Mine is 2024
Who we are!
-
8/13/2019 Automation @ Northparkes Rio Tinto
4/30
E22
E27
E26
E48
2km
Site Overview
TSF1
TSF2
-
8/13/2019 Automation @ Northparkes Rio Tinto
5/30
Hoisting Shaft
Main
Decline
9800 Level
ConveyorDeclines
Access Decline
9450 Level
S N
E26L1
E48
L2 L2N
L1
Operations based on block-cave mining
L1
First block cave in Australia: E26 Lift 1 commissioned in 1997
E26 L2 in 2004 and E48 L1 in 2010
5.5 - 6.0Mtpa production rate
Industry-leading mine productivity (t/manhour; t/m2 footprint)
800m
-
8/13/2019 Automation @ Northparkes Rio Tinto
6/30
-
8/13/2019 Automation @ Northparkes Rio Tinto
7/30
The Northparkes mining concept continuous,
automated & minimal intervention
400t primary
feed bin
400t ore bin
BK Crusher
1050tph conveyor
Hoist to surface
4-Way Tipple
-
8/13/2019 Automation @ Northparkes Rio Tinto
8/30
The Safety Proposition
Removing LHD operators from a
hazardous environment:
Wall collisions
3-4 LHDs to achieve 18ktpd
Each LHD operator will load
300+ buckets in a 12 hour shift
23kph top speed (3.5m wide
machine in a 4.5m wide drive)
Multiple equipment interactions
Dust
Uncontrolled draw point flows
Rock falls
Whole body vibration
-
8/13/2019 Automation @ Northparkes Rio Tinto
9/30
9
History of LHD automation extension of tele-
remote loading
2007 2008 2009 2010200620052004200320022001200019991998
NPM joined AMIRA Autonomous
Underground Mining Vehicle project
First trial in SW quadrant of Lift 1 mine
E48 Project commences construction
E48 Project scope varied to
include autonomous LHDs
Full implementation of autonomousloaders on E48 Production level
Design of compliant barrier systems
Second production trial at Lift 2 mine
1
2
-
8/13/2019 Automation @ Northparkes Rio Tinto
10/30
Concept
Concept to Production
Develop Scope:
Network
Barriers
LHD interface
Conduct RiskAssessment
(each aspect)
Commission and Test:
Proof of concept
Build business case
Handover to production:
Risk register
Operating procedures Maintenance procedures
Documentation
Training systems
-
8/13/2019 Automation @ Northparkes Rio Tinto
11/30
Trials based on a mixture of systems
Sandvik 450E electr ic LHD
3rd party automation system (DAS)
-
8/13/2019 Automation @ Northparkes Rio Tinto
12/30
Operator located in surface control room
Scanning ladars allows machineto monitor its location
Operator is located remotely inthe surface control room
Operator loads in tele-remote
Tramming and tipping functionsautomated (learnt)
Front and rear cameras providevisual control for operator
Audio feedback to allow operatorto feel loading process
-
8/13/2019 Automation @ Northparkes Rio Tinto
13/30
Man-Machine Interface Tactical Screen
-
8/13/2019 Automation @ Northparkes Rio Tinto
14/30
Man-Machine Interface - Strategic
-
8/13/2019 Automation @ Northparkes Rio Tinto
15/30
Trial 1: Proof of concept
Lessons Learned:
Navigation system able toaccurately control the location of
the LHD
Automated haulage and dump
cycle successfully tested
Operator comfortable with tele-remote load function
Aims:
Confirm reliability of navigation system
Confirm ability to operate in the underground environment
Issues raised:
Reliability (sensitivity) of barriersystem
Barrier system required to comply
with AS61508
On-board processing capacity
limits LHD speed to 12-13kph
-
8/13/2019 Automation @ Northparkes Rio Tinto
16/30
Barrier system is THE critical interface for
autonomous mining equipment
Typical Barrier Setup
Barrier system must contain the
LHD under all circumstances
Prevent access of unauthorised
personal and trips the LHD in theevent the area is accessed
Comply with the requirements of
AS 61508 to achieve an
appropriate level of safety
-
8/13/2019 Automation @ Northparkes Rio Tinto
17/30
Trial 2: Building the business case
Trial design:
Automated loader operating incentral two extraction drives on
Lift 2 extraction level
LHD running in 3rd gear
Automated loader responsible for
25% of mine production
Barrier system compliant with AS
61508
Aims:
Test the system as a front line production tool against manual loaders
Evaluate system availability, productivity factors, maintenance costs
9450 L Extraction Level
ED3
ED4Crusher
-
8/13/2019 Automation @ Northparkes Rio Tinto
18/30
Trial 2 didnt start well
Problems encountered:
Steering bias LHD driving into bull noses (cracking loader boom)
Unplanned movements relating to joystick feedback
Whipping trailing cables tripping light barriers
Loss of Rio Tinto network interface Inadequate operator training
Insufficient spare parts
Lack of OEM automation specialist coverage
LHD2 PRODUCTION TRIAL METRICS
0%10%20%30%40%
50%60%70%80%90%
100%
Week1
Week2
Week3
Week4
Week5
Week6
Week7
Week8
Week9
Week1
0
Week1
1
Week1
2
Week1
3
0
200
400600
800
1000
1200
1400
1600
mins
Availability
Utilisation
MTBF
Production metrics:
Max 24hr production of 414
buckets vs 382 buckets/24
hr period in Week 11
Max 12hr production of 212
buckets vs 207 buckets/12
hr period in Week 13
Initial assessment:
Automation system NOT
operationally ready,
BUT, glimmers of hope!
-
8/13/2019 Automation @ Northparkes Rio Tinto
19/30
Trial stopped and issues addressed
Upgraded automation equipment and
software
Additional offsite OEM technical
support 24/7
Upgraded communications between
site and OEM offices
Additional training for both
maintenance and operations
personnel
-
8/13/2019 Automation @ Northparkes Rio Tinto
20/30
Second stage of trial was successful
204.5tph
Manual LHD
restricted to 3rd
gear
206.4tph
Trial Average
(2nd Stage)
Results achieved during 2006:
No additional wall contacts
15% reduction in maintenance costs reduced
gearbox, tyre and cable damage
Peak demonstrated production rate 4,973 t/24 hrs 78% system availability (8 mths) vs 85.9% (manual)
Auto LHD operating up to 22.5hrs/day vs 17hrs/day
manual
221tph
Required*
Product ion Rate
* Assuming 4 LHDs
to achieve 17ktpd
Availab ility & Uti lisation Analysis
0
100
200
300
400
500
600
LHD2April
LHD2May
LHD2June
LHD2July
LHD2August
LHD2September
LHD2October
LHD2Average
ManualFleetYTDAverag
Hours
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
70.0%
80.0%
90.0%
100.0%
Avail.
&
Util.
Machine Run Hours Availability Utilisation
-
8/13/2019 Automation @ Northparkes Rio Tinto
21/30
Forks in the road
We have demonstrated operability of the automation system
achieving comparable results to manually operated machines!
Do we continue to test and develop the
MineGem automation system?
Improve reliability of the system
4th gear function (speed)
Traffic management (multiple units
interacting)
How does automation fit with
our future plans?
At Northparkes (E48
Project)?
Within Rio Tinto? What are the
alternatives?
-
8/13/2019 Automation @ Northparkes Rio Tinto
22/30
Options review undertaken through Rio
Tinto Underground OEM Directorate
Northparkes
requirements
Rio Tintos
requirements
Available systems
Sandviks AutoMine
Caterpillars MineGem (DAS)
Atlas Copco
Other company implementations
De Beers (Finsch)
Codelco (El Teniente)
Freeport (Grasberg)
REVIEW
-
8/13/2019 Automation @ Northparkes Rio Tinto
23/30
Ertsberg EastSkarn System
Grasberg Pitrasberg Pit
GrasbergUnderground
GrasbergUnderground
Kucing Liarucing Liar
igGossan
Domom
ESZ DOZOZ
MLZLZDeep MLZeep MLZ
re
Final Pit
Automated LHDs are key enabler for
Rio Tintos UG mining ambitions
-
8/13/2019 Automation @ Northparkes Rio Tinto
24/30
Two key alternatives at the time
Fully integrated
OEM LHD-
automation system
Hybrid - LHD + 3rd
party automationsystem
De Beers:
AutoMine on Sandvik truck
Codelco:
AutoMine on Sandvik LHD
Freeport:
MineGem on Caterpillar LHD
Northparkes:
MineGem on Sandvik LHD
-
8/13/2019 Automation @ Northparkes Rio Tinto
25/30
Northparkes decided to change to SandviksAutoMine system based on LH514Es
Fully integratedOEM LHD
automation system
Functional Specification:
1. No speed limitation
2. Full traffic management3. Barrier systems compliant with AS61508
4. Tyre Management (TKPH Calcs)
5. Integrated production planning &
accounting system
6. Remote support
Additional:
7. Support both electric and diesel LHDs
8. Support very large complex mass mining
operations
-
8/13/2019 Automation @ Northparkes Rio Tinto
26/30
E48 Automation
Complete turn key package
with Sandvik
5 x AutoMine-ready LHDs
delivered by Q3 2010
Control room upgrade
Automation install to
commence in Sep 2010 with
Zone 1 commissioning in
Feb 2011
Completion in Jun 2011
Typical ACS Barrier Arrangement
-
8/13/2019 Automation @ Northparkes Rio Tinto
27/30
E48 Automation maximum flexibility
E48 AutoMine Hardware Layout
Barrier design ensures
maximum flexibility for
production teams
-
8/13/2019 Automation @ Northparkes Rio Tinto
28/30
Auto
LHD/Truck
Cave
Management
System
Production
Control
System
Mission
Control
System
Operator
Station
Daily drawpoint tons
Progressive drawpoint tons
Current drawpoint statuses
Cycle time data
Drawpoint status history
Daily draw order
Extraction tunnel priorities
System
Operator
Operating
ManagerManual production list
Auto mission list
Updated drawpoint statuses
SCADA
(Citect)
Fleet status
Production area statuses
Production data
Cycle time data
Mission statuses
Production order statuses
Crusher bin level
Crusher operational statusCrusher bin withdrawal rate
U/Cut pass levels
Rockbreaker status
AutoMine
Production scheduling input
Manual production list modifications
Updated drawpoint status
Drawpoint status
& history reports
Secondary
Breaking
CrewProduction scheduleProduction reports
Missions
(drive orders)
Auto LHD/truck location
Measurements & statuses
LHD bucket weights
Tele-operation commands
Fleet status
Drawpoint status
Automation is an integrated production
system
-
8/13/2019 Automation @ Northparkes Rio Tinto
29/30
HoistingShaft
9100L
9800L
ConveyorDecl
inesMonzonite Stock
9450L
Lift 1
Lift 2/2N
Lift 3Lift 1
Lift 1
Not
mined
Lift 2
Lift 1
1 ki lometre
Concentrator
Step Change Infrastructure
HoistingShaft
9100L
9800L
ConveyorDecl
inesMonzonite Stock
9450L
Lift 1
Lift 2/2N
Lift 3Lift 1
Lift 1
Not
mined
Lift 2
Lift 1
1 ki lometre
Concentrator
Step Change Infrastructure
E26 GRP314 E48E22
NS
Cross Section
E48 + LHD automation not the end of the
line Automation systems a key enabler for Northparkes next stage of mining
Future innovation: LHD loading, secondary breaking, hang-up drilling
-
8/13/2019 Automation @ Northparkes Rio Tinto
30/30
Automation @ Northparkes
VISION
EXPERIMENTATION
+
PERSEVERANCE
+
=
INNOVATION