mw antenna
TRANSCRIPT
-
7/27/2019 MW Antenna
1/8
Sales department : Radio Frequency Systems
Kabelkamp 20, D-30179 Hannover (Germany) Tel. +49-511 676-2520 Fax +49-511 676-2521
Plant: RFS France Trignac (France) Tel +33 (0)2 40 45 95 45 Fax +33 (0)2 40 90 41 43 1/8
Installation Instructions
3 ft Antennas (with E-Mount)
DA, DAX, UA, UDA, UXA
SD, SDX, SU, SUX NMT 532-02(e)
These Installation Instructions are valid for antennas in the following version :
- Reflector 0.9 m (3 ft)- Pipe mount for installation on pipe 114 mm ( 89 mm optional)- Antenna offset to the left or to the right- Standard installation on 114 mm pipe with offset to the left- Safety collar for easy installation- 2 spindles for fine adjustment ofElevation 15 andAzimuth 5- Reflector with shroud, shroud aperture covered by a flexible radome- 200 km/h version : No sway bar- 250 km/h version : With sway bar 33 mm x 1 m(mandatory)
200 km/hsurvival windspeed
antenna version
250 km/hsurvival windspeed
antenna version
These installation instructions have been written for qualified, skilled personnel. The antenna shall be inspected once per year by qualified personnel to verify properinstallation, maintenance, and condition of equipment. It is important to adhere precisely to all parts of the installation instructions. RFS disclaim any responsibilityresulting from improper or unsafe installation. RFS reserves the right to alter details at any time, especially with respect to technical improvements.
-
7/27/2019 MW Antenna
2/8
NMT 532-02e 2/8
1 - Tools required for installation(Non not included with antenna) 2 Antenna Offset
- Hoisting device for 100 daN- Torque wrench from 0 to 50 Nm- Shackle(s), roll(s), pulley(s) and lifting accessories- Water balance, compass, cutter, tape measure- 2 strong ropes (approx. length 1.5x tower high)- 1 strong rope or cable (approx. length 2.5 tower high)- Key for socket screw : M3(2.5), M4(3)- Wrenches for hexagon bolts : M5(8), M6(10), M8(13), M10(17), M12(19)
(values in brackets = openings of spanners)
3 Shroud orientation and installation in the reflector
Shroud
Loosen the 4 bolts M5 on the shroud(pre-assembled in factory)
Remove the last bolt M5(if pre-installed in factory)
gnikcaP
draobdrac
For the 2 holes rep. A
25 screws M5x1250 washers 5.3 15
25 sl nuts M5
Add 2 serrated lockwashers 5.3 between the2 washers 5.3 15
DO NOT TIGHTEN
bolted joint
until RF Braid
installationbetween shroud
& reflector rim
Shroud assembly detail
OUT
IN
+
+
OUT
IN
A
A
A
For an offset rightFor an offset left
Shroudjunction
Shroudjunction
Reflector TOP markin opposition with
shroud junction
Reflector TOP markaligned with shroud
junction
A
AntennaVerticalAxis Packing
cardbo
ard
Packing
cardbo
ard
AntennaVerticalAxis
The shroud must be installedinside of the reflector
The shroud must be installedinside of the reflector
Offset left
Drain holes of the shroudtowards the antenna bottom
Reflector TOP atthe antenna top
Reflector TOP at theantenna bottom
Drain holes of the shroudtowards the antenna bottom
Azimuth fineadjustment spindle
Offset right
Elevation fineadjustment spindle
Holes for feed with guy wires
-
7/27/2019 MW Antenna
3/8
NMT 532-02e 3/8
Cardb
oard
Push
Push
4 - Sway bar clamp installation(Only for antenna provided with a sway bar)
5 - Feed system installation*(Refer to feed system installation instructions)
* For monopolarized feed systems with freq. below 10 GHz, and for dualpolarized feed systems below 11 GHz, the feed system must be installed before radome installation(due to mixed mounting design). If your feed system is not concerned, skip this step, you can install it later.
6 - Radome installation
For an offset rightFor an offset left
Sway barterminal
SL nut M10Washer 10.5
Sway bar clamp 33(L-Profil 40x40)
Washer 10.5 30Screw M10x30
(Tighten the assembly, keeping thesway bar clamp 33 and the sway barterminal free in rotation without gap)
SL nut M10Washer 10.5
Sway bar clamp 33(L-Profil 40x40)
Sway barterminal
Washer 10.5 30Screw M10x30
(Tighten the assembly, keeping thesway bar clamp 33 and the sway barterminal free in rotation without gap)
Replace the 2 M5 bolts on the reflector rim 90 clockwise from theshroud junction, by the M8 bolts as described below.
Replace the 2 M5 bolts on the reflector rim, 90 counter-clockwise fromthe shroud junction, by the M8 bolts as described below.
- Install the radome over the shroud aperture- Push on the J-Bolts springs to hook them in the
radomes eyelets.
- After J-Bolts complete installation, adjust the radometension with the 1st M5 nut to have a spring length of20 mm on each J-Bolts (proceed by opposite J-Bolts).
- Then lock each 1st nut in position with the 2nd one withusual wrenches.
20 mm
J-Bolts installation
principle
Loosen M5 nuts toput them J-Bolt
extremity
Shroud junction(alway at theantenna bottom)
Logotype at the antenna top(at the opposite of shroud junction)
Edge protectorinstallation on reflector
rim(mandatory)
Cardbo
ardC
lip
Shroud rim junctionwithout edge protector
Edge protector coveringshroud rim junction
J-Bolts tension
gnikcaP
draobdrac
gnikcaP
draobdrac
2 screws M8x252 washers 8.4 24
2 SL nuts M82 washers 8.4 24
2 SL nuts M82 washers 8.4 24
Shroud junction Shroud junction
2 screws M8x252 washers 8.4 24
-
7/27/2019 MW Antenna
4/8
NMT 532-02e 4/8
Carefully turn up theantenna to have theradome face down
7 - Pre-assembly of the mount(Feed system not shown)
8 - Feed system installation*(refer to feed system installation Instructions)
* For monopolarized feed systems with freq. over 10 GHz, and for dualpolarized feed systems over 11 GHz, the feed system could be installed after radome installation (due torear mounting design). If have already fitted the feed system you are not concerned, skip this step.
9 - Safety collar installation and orientation on pipe support
Minimumspace 340 mm
Minimumspace 35 mm
Minimumspace 340 mm
MinimumSpace 35 mmV-Bolt M10
Steel clamp2 washers 10.5 30
4 M10 nuts
For an easy operation of the bolted joints, and correct torque tightening, Anti Seize installation paste must be applied to all threads of bolts and fine adjustment spindles.After this, keep the lubricated threads free of dust and dirt! (a Torque Table is attached for specifications)
7.4 7.5
7.1 7.2
7.3
Connecting Support 3 ftE-Mount
SteelU-Mount 3 ft
3 screws M10x253 SL washers 10
3 washers 10.5 30(Torque tighten)
For an antenna
offset left
For an antenna
offset right
6 screws M10x30
6 SL washers 106 nuts M10(Torque tighten)
Eye spindle M10x1002 brass nuts M10
2 washers 10.5 30
Respectscrews
orientation
Respect screwsorientation
Cardb
oard
For an
offset right
For an
offset left
-
7/27/2019 MW Antenna
5/8
NMT 532-02e 5/8
Strong rope or cable fixedto antenna steel mount to
avoid collision with thetower structure during
hoisting
Strong rope fixed at the tower top.The rope is slipping through a steel
roll or a shackle, which is fixed on thereflector casting eye (8.5 mm)
To winch
Shackle
Steelmount
Strong rope attached on thereflector casting eye (8.5 mm)
with a shackle, and linkedto winch
Principle fora left offset
Shackle
10 - Hoisting on the tower (Feed system not shown)
-
7/27/2019 MW Antenna
6/8
NMT 532-02e 6/8
11 - Antenna installation on pipe support(Feed system not shown)
Azimuth spindle installation
M10 nutSL washer 10
Screw M10x30
Eye spindleM10x130
2 M10 brass nuts2 washers 10.5
(Rear view)
Principle for
a left offset
After Azimuth spindleinstallation, torque tigthen
the 2 M12 bolts(see torque table joined)
2 U-Bolts M12
4 washers 13374 nuts M12
(handtigthen the V-bolts to permit the
antenna free rotation around the pipe, forthe azimuth spindle installation)
Principle fora left offset
Azimuth safety collarinstalled on pipe support
-
7/27/2019 MW Antenna
7/8
NMT 532-02e 7/8
Loosen or tightenM10 brass nuts toadjust the elevationof the antenna
Principle fora left offset
Loosen turnthe 3 M10 bolts
A B
12 - Azimuth fine adjustment
13 - Elevation fine adjustment 14 - Sway bar installation(Only for antenna with a sway bar)
After complete elevation fine adjustment,torque tigthen the 3 M10 bolts, and lock
the 2 M10 brass nuts on the steel mount
For antennas provided with a sway bar,
the sway bar installation is mandatory !
Offsetleft
Feed systemnot shown
Offsetright
Screw M10x70
Washer 10.5SL nut M10
Loosen M12nuts turn
Loosen or tighten M10 brass nuts toadjust the azimuth of the antenna
After complete azimuthadjustment, torque tighten
the 4 first M12 nuts
(V-bolts must have
been greased)
4 M12 nuts (tightenwith an usual wrench)
Lock the 2 M10 brass nutson the steel clamp
Steelclamp
Principle fora left offset
A
B
C
D
E
-
7/27/2019 MW Antenna
8/8
NMT 532-02e 8/8
Washer 13 24SL nut M12
Fixing platesway bar 33
Sway bar
extremity
Typical config.
for direct mount on towerangle structure
Alternative config.
with optional interface
SMA-SKO-UNIVERSAL
for installation on towerpipe or angle structure
Fixing clamp sway bar(L-Profil 60x60)
Fixing clamp sway bar(L-Profil 60x60)
1 screws M10x251 washers 10.5
1 SL nuts M10
Screw M12x30
Screw M10x25
Optional interface
SMA-SKO-UNIVERSAL
Washer 10.5SL nut M10
1 screws M10x25
1 washers 10.51 SL nuts M10
2 U-Bolts M6x334 washers 6.48 nuts M6
15 - Sway bar / Tower fixation configurations(Only for antenna with a sway bar)
16 - Final Check
When the installation of the antenna has been completed, it is necessary to make sure that the installation instructions have been followed in allaspects. It is especially important to check that all bolted joints are torque tightly locked (mandatory).
Sway Bar orientation
After complete
sway bar orientation,torque tighten all
bolted joints
Torque wrench
OffsetLeft
OffsetRight
25 25