MOKOLO & CROCODILE WATER AUGMENTATIONPROJECT (MCWAP) - Project overviewFOSSIL FUEL FOUNDATION LIMPOPO CONFERENCE
Input by Ockie van den BergChief Engineer: Options Analysis North
17 & 18 October 2013
1
2
• MCWAP 1 : Pipeline & Pumping station from Mokolo Dam to Lephalale area (46 km). Packaged initially as a stand-alone-project to expedite water delivery but will be incorporated with MCWAP-2 into MCWAP system
• MCWAP 2 : Abstraction works and pumping station in Crocodile River (West) near Thabazimbi & pipeline to Steenbokpan and Lephalale (157 km).
• MCWAP 3: 83 km pipeline – only if river conveyance losses are excessive.
• MCWAP 4: Transfer scheme from Johannesburg KlipRiver wastewater treatment works to head waters of Crocodile River – only if surplus in Crocodile West is insufficient.
Objective: Water augmentation project to supply demands in the Waterberg Coal Fields (Eskom, IPP’s, associated mining & urban development), utilising available yield of the existing Mokolo Dam and surplus return flows from Gauteng being discharged in the Crocodile River (West ) Catchment.
3
Coal for power generation 28%
Coal for export 7%
Other industrial development 6%
Eskom power generation 47%
Municipal -urban 12%
Demand Composition - April 2013Demand Composition -2038
3
• Mokolo Dam ( Existing supply): MCWAP-1– Yield increased due to switch from irrigation to game and cattle farming– Raising assessed but not found as preferred option due to dependancy on single source and International Protocol requirements
• Return Flows in Crocodile West River (Future supply -indirectly imported via Vaal River system): MCWAP-2– Availability assessed in Reconciliation Strategy
• Augmentation from Vaal River (if needed): MCWAP-4• Further options
– Groundwater: limited availability– Re-use of local return flows
4
Mokolo Catchment
Crocodile West CatchmentVaal Catchment
Transfer from Vaal River via. Rand Water System
Treated Urban Return Flows
Growth areas
Urban
Mining
5
0
20
40
60
80
100
120
140
160
180
mill
ion
m3 /
aMokolo Crocodile Water Augmentation Project - Phase 2
Water Requirements and Water Availability
Lephalale Water Transfer Requirements (Apr 2013)
Lephalale Water Transfer Requirements (July 2012)
Water available at Vlieëpoort for transfer
Transfer to Lephalale
6
7
Phase 1
7
8
Project Features• New Mokolo Pump Station with a capacity of
1,2 m3/s• 900 mm diameter rising pipeline (4,8 km) from
Mokolo Pump Station to existing WolvenfonteinBalancing Dams.
• 1 100 mm diameter gravity pipeline (15,8 km) from the Wolvenfontein Balancing Dams to Rietspruitnek.
• 800 mm diameter gravity pipeline (22.1 km) from Rietspruitnek to the Point of Supply at Matimba
• Incorporation, refurbishment and integration of the existing water infrastructure owned by Eskom and Exxaro.
• Incremental capacities– Original 14,7 mill m3/a– Debottlenecking Step 1 20.1 mill m3/a– Debottlenecking Step 2 23.1 mill m3/a– MCWAP-1 30.5 mill m3/a
9
MILESTONE ACTIVITY Programme
Commence Construction
Water delivery : De-bottlenecking6.6 Km tie in - 37% capacity increase10.3 km tie in - 57% cumulative
capacity increase
19 May 2013
October 2013
Water Delivery : Phase 1 June 2014
Contract Completion Date Nov 2015
Refurbishment Existing infrastructure Nov 2014
Project Close-out Nov 2015
10
Project Features
• Abstraction Works on the Crocodile River (West) at Vlieëpoort near Thabazimbi
• Low lift pump station and pipeline to convey water to the balancing dams and appropriate sediment disposal facilities.
• High lift pump station and rising main pipeline (approximately 29 km) to the break pressure reservoir – provisional capacity 110 million m3/a
• Gravity main pipeline (approximately 128 km) from the break pressure reservoir to terminal points close to Medupi Power Station and Steenbokpan
• River management system to manage abstractions from, and the river flow in relevant parts of the Crocodile River (West) catchment upstream of Vlieëpoort Weir
PROJECT MILESTONES : MCWAP-2ACTIVITY START FINISH
Users obtain mandate for MCWAP-2 31-Dec-12
DWA formulates WSA with Users 01-Jan-13 31-Mar-14
Capacity MCWAP-2 Agreed 31-Mar-14
Users commit WSA with DWA 01-Apr-14 30-Jun-14
EIA Phase 2 06-Jan-14 2-Jan-15
Resolve ROD appeals 2 -Feb-15 30-Sep-15
Funding procurement 01-Jul-14 31-Jan-15
Tender design-abstraction works & pipeline 01-May-14 30-Jan-15
Tender & Evaluation period 31-Jan-15 31- Oct-15
Award Construction Contract 31-Oct-15
Construction (39 months) 4-Jan-16 5-Apr-19
Commissioning 6-Apr-19 30-Jun-19
Phase 2 Water Delivery - 01-Jul-19
Capital Unit Charge levied in Water Tariff 01-Jul-19 30-Jun-39
11
Fossil Fuel Foundation Limpopo Coalfields Conference II
Protea Hotel Ranch Resort, Polokwane, Limpopo18 October 2013
The Supply of and Demand for Water in the Limpopo Valley
Presented by:Lesiba Tloubatla / Bernie Badenhorst
12
Supply of and Demand for Water in the Limpopo Valley
• Different users• Agriculture Irrigation and game farming• Mines• Industry• Primary Users• Environment
13
Supply of and Demand for Water in the Limpopo Valley
• Sources• Limpopo River• Sand River• Nzhelele River• Nwanedi River• Mogalakwena River• Groundwater
14
Supply of and Demand for Water in the Limpopo Valley
• DWA actions• Nzhelele Implementation Ready Study (IRS)
- PSP appointed to do IRS - Water logged irrigation fields- Exchange water from downstream users- Raise Mutshedzi Dam
• Musina to Africa strategic supply hub initiative (MUTASSHI)PSP appointed to do IRSProgress
15
Supply of and Demand for Water in the Limpopo Valley
• Mining development largely uncertain- Who, where, when, how big- Determine water demand- Negotiate for source- Agreements- Funding
• Form a Joint Water Forum (JWF) of mines
16
Funding available – Water Services
Code Scheme District Municipality Local Municipality
Final Budget Allocation 2012/13
Budget Allocation 2013/14
Budget Allocation 2014/15
Budget Allocation 2015/16
LPR018 Giyani BW Supply Drought Relief Mopani Greater Giyani 11 889 099 35 000 000 42 000 000 0
LPR017 Mametya Sekororo MopaniMaruleng/ Richmond/ Oaks/ Willows
18 167 607 45 689 000 44 915 000 83 167 500
LPR016 Sinthumule Kutama BWA VhembeMakhado/ Kutama/ Sinthumule
15 000 000 60 000 000 25 000 000 0
LPR015 Mogalakwena BWS Waterberg Mogalakwena 90 000 000 60 000 000 84 000 000 141 499 500
LPR019 Moutse Bulk Water Supply Sekhukhune Elias Motsoaledi/ Ephraim Mogale 70 018 464 40 000 000 42 500 000 0
LPR011 Nebo BWS Sekhukhune Greater Tubatse/ Makhuduthamaga 24 062 951 40 000 000 40 000 000 80 000 000
LPR012 Mooihoek/Tubatse BWS Sekhukhune Burgersfort 30 299 056 46 286 725 43 000 000 80 000 000
LPR021 Sekhukhune Bulk Water Supply (De Hoop) Sekhukhune Various LMs 66 000 000 266 311 000 396 084 000 400 000 000
Table 1: RBIG Budget Allocations and MTEF Schedule
17
Funding available – Water Services
Code Scheme District Municipality
Local Municipality
Final Budget Allocation 2012/13
Budget Allocation 2013/14
Budget Allocation 2014/15
Budget Allocation 2015/16
LPR006 Nwamitwa RWS Scheme Mopani Greater Letaba 0LPR002 Nzhelele Valley BWS Vhembe Makhado 900 000
LPR005 Makhado West and Extension to Nandoni Dam Vhembe Makhado
600 000
LPR020 Provincial High Catalytic Projects - Mutash Hub Vhembe Musina 268 702 1 390 000
LPR022 Aganang Bulk Water Supply 0 511 000
LPR001 Matoks RWS Capricorn Molemolle 1 500 000
LPR008 Glen Alphine RWS Capricorn Molemolle 600 000
LPR003Lephalale - Bulk Water Augmentation(Eskom)
Waterberg Lephalale500 000
LPRnew Polokwane wwtw Capricorn Molemolle 1 500 000
LPR004 Magalies Water to Waterberg Waterberg Mookgopong 1 000 000
LPR007 Ohrigstad Greater Sekhukhune Greater Tubatse 0
LPR009 Lebalelo Central & North RWS
Greater Sekhukhune Greater Tubatse 0
RRU 0 1,000,000
Goods and services 0 250 000Total 325 867 571 594 586 725 717 499 000 784 667 000
Table 1: RBIG Budget Allocations and MTEF Schedule
18
Funding available – Water Services
Province WSA Project Name FY:2013/14(R’000)
TotalAllocation
Community Infrastructure: Water SupplyLimpopo Sekhukhune
DM Mokgoding WS2 000 2 000
Vhembe DM Makhado Water Supply 2 500 2 500Mopani Middle Letaba WS 4 695 4 695
Sub Total 9 195 9 195Water Conservation and Demand Management
Lephalale WCDM Interventions 3 680 3 680Capricorn WCDM Interventions 300 300Tzaneen WCDM Interventions 300 300Mogalakwena WCDM Interventions 1 000 1 000
Sub Total 5 280 5 280Waste Water Treatment works Refurbishment
Sekhukhune Refurb of Marble Hall WWTW 3 000 3 000Lephalale Refurb of Sewage Pumpstations 6 000 6 000Vhembe Refurb of the WWTW 6 400 6 400Sekhukhune Burgersfort WWTW 1 410 1 410
Sub Total 16 810 16 810Grand Total 31 285 31 285
Table 2: ACIP Budget Allocation Schedule
19
Funding available – Water Services
TA # Water Services Authority
2013/2014 (R’000)Refurb O&M Training HR Total
38 Mopani 20 000 0 0 0 20 000
39 Vhembe 29 260 0 0 27 959 57 219
40 Capricorn 20 669 0 0 0 20 669
41 Polokwane 10 000 0 0 0 10 000
43 Lephalale 5 000 0 0 0 5 000
44 Mogalakwena 5 000 0 0 0 5 000
45 Sekhukhune 15 000 0 0 0 15 000
75 Bela-Bela 0 0 0 0 0
Total Limpopo 104 929 0 27 959 132 888
Table 3: National Transfers Budget Allocation Schedule
20
Funding available – Water Services
Code Municipality 2013/14(R’000) 2014/15(R’000) 2015/16(R’000)Lim331 Greater Giyani 3 859 10 435 24 295Lim332 Greater Letaba 3 861 10 445 24 306Lim333 Greater Tzaneen 6 554 14 662 37 770Lim334 Ba-Phalaborwa 845 3 382 4 227Lim335 Maruleng 1 787 4 147 11 934Lim341 Musina 90 360 450Lim342 Mutale 8 307 19 921 46 535Lim343 Thulamela 14 501 25 452 77 506Lim344 Makhado 15 005 25 153 90 741Lim351 Blouberg 1 627 6 508 8 135Lim352 Aganang 1 453 5 813 7 266Lim353 Molemole 285 1 140 1 425Lim354 Polokwane 0 0 0Lim355 Lepele-Nkumpi 6 099 13 918 34 872Lim471 Ephraim Mogale 2 891 11 564 14 455Lim472 Elias Motsoaledi 9 278 28 135 46 891Lim473 Makhuduthamaga 3 626 14 505 18 132Lim474 Fetakgomo 376 1 503 1 879Lim475 Greater Tubatse 13 029 30 807 69 145Total Limpopo 93 473 227 850 519 964
Table 4: MWIG Budget Allocation and MTEF Schedule
21
Supply of and Demand for Water in the Limpopo Valley