minutes of the september 12. 1996 u.s. nuclear regulatory ... · * thermal test facility access...
TRANSCRIPT
- -
MINUTES OF THE SEPTEMBER 12. 1996U.S. NUCLEAR REGULATORY COMMISSION/U.S. DEPARTMENT OF ENERGY
TECHNICAL MEETING ON THE EXPLORATORY STUDIES FACILITY
On September 12, 1996, staff from the U.S. Nuclear Regulatory Commission metwith staff from the U.S. Department of Energy (DOE) to discuss items of mutualinterest regarding progress at DOE's Exploratory Studies Facility (ESF) atYucca Mountain and technical issues related to repository design. The itemsdiscussed included the ESF construction status including the status of mappingthe high-density fracture zone at the second bend of the ESF, the ESF testingstatus and the results of the recent ESF Appendix 7 visit, the description andstatus of the Engineering Design Program, and an overview of the DOE report onpredicting the effective thermal conductivity of spent nuclear fuel. Themeeting was held by three-way videoconference at DOE offices in Washington.1.C.: DOE offices in Las Vegas. Nevada: and Center for Nuclear WasteRegulatory Analyses (CNWRA) offices in San Antonio. Texas. The meeting wasanother of the continuing series of periodic ESF technical meetings.
Attachment 1, the meeting agenda, was included with the meeting announcementand also made available at the meeting.
Organizations other than NRC and DOE that were represented at the meeting werethe CNWRA; DOE's Management and Operating Contractor (M&O). U.S. GeologicalSociety (USGS), U.S. Nuclear Waste Technical Review Board (NWTRB), State ofNevada's Nuclear Waste Project Office (NWPO) and Nuclear Waste Task Force(NWTF). Nye County, and Weston. Attachment 2 is a list of those who were atthe meeting.
The first presentation was made by DOE. It provided an update of the statusof the ESF construction and of the tunnel mapping as well as a discussion ofthe high-density fracture zone at the second bend in the ESF. Thepresentation also addressed the excavation method for the In situ thermaltests and the fracture zone effects on drift design. Attachment 3 providesthe handouts/overheads that were used during this presentation. The tunnelboring machine (TBM) was reported to be about 150 meters short of the end ofthe second bend in the ESF. ESF mapping was reported to be complete up toabout 150 meters behind the TBM. Tunnelling was reported to be on hold" atthe time of the meeting in order to improve the ventilation in the tunnel andre-indoctrinate tunnel workers regarding safety of tunnel operations.Controlled drill and blast excavation was being used in the thermal testalcove with plans to use the alpine miner when repairs to it have beencompleted.
DOE then presented an overview of ESF testing activities and thermal testingissues. Attachment 4 includes the handouts/overheads that were used duringthis part of the meeting. The status of each ESF alcove, its test status, and
961105027 961029PDR WASTE PDR'
.
preliminary test results were given. including the status of Alcove 5. thealcove for the in situ thermal tests. These tests include a single heatertest - started in August 1996 - and a drift scale test - scheduled to start inSeptember 1997. DOE addressed the thermal test concerns that had been raisedpreviously by the NRC in the Appendix 7 meeting held on July 24. 1996. CNWRAsuggested that DOE consider using alternative thermal inputs in the driftscale heater test and agreed to supply additional information in this regardto DOE. Attachment 5 is a copy of what the CNWRA provided to DOE forconsideration. The information provided by DOE at this meeting is helpful tothe NRC staff in understanding the thermal test program at Yucca Mountain.Additional information is expected to be found in the DOE test design reportwhen it becomes available. Other topics that were addressed during thispresentation included chlorine-36 data and their implications, rock massquality for the main drift portion of the ESF, orientation of fractures withinthe ESF. surface based testing status. and the status of key fiscal year 1996deliverables. Continued progress was made toward NRC staff resolution of theissue of adequacy of fracture/fault data for licensing.
The M&O then described its engineering design system. Attachment 6 includesthe handouts/overheads that were used during this part of the meeting. TheM&O plans to use the current design process and controls through final design.That is, there will be a single pass design developed to support DOE'sviability assessment; then an environmental impact statement; then the licenseapplication. (The single pass design does not support construction.) Plansinclude prioritization provided by binning the level of design detail requiredat each of the noted points in the process. NRC has not providedrecommendations regarding DOE's proposed binning system. waiting, rather, tosee the system activated. DOE plans to have the design drawings and documentssummarized to the level of detail adequate for the viability assessment. andthe design details will be described at thetime of license application.Detailed construction drawings and specifications will be available on aschedule commensurate with the construction schedule.
The final presentation by DOE addressed a proposed methodology for determiningthe effective thermal conductivity of spent nuclear fuel. The presentationwas made to start a dialog with NRC regarding the methodology. Attachment 7includes the handouts/overheads that were used during this part of themeeting. DOE has concluded that the new methodology uses a simple calculationprocess to provide a "best estimate" of fuel element peak cladding temperatureand that benchmark results agree with reported results from spent nuclear fuelstorage cask testing. The methodology was developed using a two-dimensionalANSYS model.
- 2 -
At the close of the meeting. comments were made by the representatives of NyeCounty and the State of Nevada. The Nye County representative expressedconcern regarding the use of respirators by workers in the ESF and suggestedthat it would be preferred that an engineering "fix" could be found to solvethe problem of excessive dust without the use of additional water. Therepresentative from the State of Nevada requested that NRC management considerthe sufficiency of DOE's latest commitments on the level of detail in thereference design for its viability assessment and how the viability assessmentfits into the license application.
The meeting concluded at about 4:00 p.m. EDT. The next meeting in the seriesis scheduled for December 16, 1996.
hn G. Sraul<ivision of Waste ManagementOffice of Nuclear Material
Safety and SafeguardsU.S. Nuclear Regulatory Commission
Christian E. Einberg Regulatory Coordination Di iOffice of Civilian Radioactive
Waste ManagementU.S. Department of Energy
- 3 -
NRCIDOE VIDEO CONFERENCE AGENDAEXPLORATORY STUDIES FACILITY
3E-077 Forrestal Building, 1000 Independence Avenue SW, Washington, DC
Atrium Room, Summerlin, 1551 Hillshire Drive, Las Vegas, NV
Building 189 Video Conference Center, CNWRA, San Antonio, TX
September 12. 1996
12:30 EST .(9:30 PST)
12:40 EST(9:40 PST)
1:30 EST(10:30 PST)
2:30 EST1 1:30 PST)
2:45 EST1 1:45 PST)
Opening Remarks ................ DOE,NRC,NV,AULG
ESF Construction Update wstatus of mapping of the high-density fracture zone ............... DOE
(Include planned excavation method for thermal tests)(Include fracture zone effects on drift design)
ESF Testing Update w/Appendix 7 follow-up .... ...... DOE(Include elevated temperature of planned
drift-scale thermal tests)(Include fracture zone effects on heat distribution
and modeling groundwater/reflux flow)
Break
Description and Status of Engineering Design Program . . . DOE(Include design process control)
3:00 EST(12:00 PST)
3:45 EST(12:45 PST)
4:00 EST(1:10 PST)
Overview - SNF Effective Thermal Conductivity .......(Include predicting thermal effects on
waste package and EBS)
DOE
Closing Remarks and Discussion ....... DOE, NRC, NV, AULG
Adjourn (Next meeting scheduled for 12/16/96)
ATTACIMENT 1
. -
DOE/NRC SF TECHNICAL MEETING
SEPTEMBER 12, 1996
ATTENDANCE LIST
NAME ORGANIZATION PHONE
- DOE, Las Vegas, Nevada -
Hawe, Tim DOE (702) 794-1441
Haghi, Ali M&O (702) 295-4873
Harrington, Paul DOE (702) 794-5415
Tynan, Mark C. DOE (702) 794-5457
Bailey, Jack M&O (702) 794-7266
Skipper, Ken DOE (702) 794-1438
Frishman, Steve NV NWPO (702) 687-3744
Bahney, Robert H. III M&O (702) 794-5337
Segrest, Alden M&O (702) 794-1924
Gil, April DOE (702) 794-5578
Treichel, Judy NWTF (702) 248-1127
VanDerPuy, Mark DOE (702) 794-5563
Geer, Tom M&O (702) 295-5567
Doering, Thomas W. M&O (702) 794-1857
Glenn, Chad NRC (702) 388-6125
Hastings, Peter M&O (702) 794-1946
Belke, Bill NRC (702) 388-6125
Murphy, Mal Nye County, NV (360) 943-5610
- DOE, Washington, D.C. -
Einberg, Chris DOE (202) 586-8869
Dresser, Dan Weston (202) 646-6781
Wallace, Ray USGS (202) 586-1244
Murthy, Ram B. DOE (202) 586-1239
Spraul, Jack NRC (301) 415-6715
Hogsett, Steve NRC (301) 415-8537
ATTACHMENT 2
K]1, I
Pohle, Jeffrey NRC (301) 415-6703
Jagannath, Banad NRC (301) 415-6653
McFarland, Russ NWTRB (703) 235-4473
Fenster, Dave M&O (301) 488-6327
Rusell, John L. CNWRA (301) 881-0289
Nataraja, Mysore NRC (301) 415-6695
Chang, Kien NRC (301) 415-6612
Justus, Phil NRC (301) 415-6745
- CNWRA, San Antonio, Texas -
Cragnolino, Gustavo CNWRA (210) 522-5539
Manaktala, Hersh CNWRA (210) 522-5210
Chowdhury, Asad CNWRA (210) 522-5151
Green, Ron CNWRA (210) 522-5305
Hsiung, Simon CNWRA (210) 522-5209
McKague, Larry CNWRA (210) 522-5183
Rice, George CNWRA (210) 522-2293
{2u'1ofo~t d1W1/0/POOI�
*
U.S. Department of EnergyOffice of Civilian Radioactive Waste
Management
Exploratory Studies Facility
PRESENTED TONRC
PRESENTED BYPaul G. Harrington, Team LeaderAMEFO Planning & Procedures
(u.
I September 12, 1996
ESF Tunneling Operations Update* Completed ESF main drift excavation July 2,
1996, Sta 59 + 01
* TBM was at Station 63 + 47 on Sept. 9, 1996
* Thermal test facility access observation drift(Alcove #5) was completed on June 14,1996
* North Ghost Dance fault access (Alcove #6)was at Station 0 + 89 on Sept, 9, 1996
* Forecast "Hole-Out" - March 1997
* Excavation activities suspended bymanagement directive
nrc.ppt
ALCOVE EXCAVATION SEQUENCING
MIN TUNNEL
YNCIN IS ~h4 FORhIuPRSES ONLY ANID IS SUUJEtl110CHANGE AS RSQU RED IV
ITNESE SKCETCHES ARE NOT OA'jN10SCLE
SOUTH GHOST lAcE l:AhULT ALCOVE NORTH GHOST LANCE FAULT ALCOVE
SCHEDULED COMPLETION 10 JAN 97 SCHEDULED COMPLETION - 24 FEB 97MILESTONE COMPLETION 1 JAN 97 MILESTONE COIPLElION - 03 MAR 97
HEATER TSt ALCOVE *I
SCHEDULED COIPLETION - 24 FEB 97MILESTONE COMPLETION - 24 JAN 97
ALPINE MINER
DRILL IBAST
COMPLETED EXCAVATION UP DATED 0645
TUNNEL BORING MACHINE PROGRESSNorth Portal
Starting DateSeptember 20, 1994 South Portal
00+60
Compglex A #v-; Akove
12", 441 4
Faut
Performance Measurement Revised 6-13-96
METERS FEET
Total Scheduled Progress In 6195.5 20,326.2
Total Actual Progress in6347.1 20.823.6
Data Posted on o f9
78+57
miles
F 1240- 8/21195
Actual
6.14 47 1ng--0 9i
Adepal 1
4 _ SSoulhen Ghost Dance Fault
- - _
Nothern GhostDance Fautt
Akove86 60+00
6,000 meters1 9,685 feet3.7 miles_ _ -
50+00_
L ESO85M159+017-2-96
| z --:-i Scheduled25+00
N - Actual
Ditawing Not To Scale TBMPGREV.126.CDR/8.20-96
Repository Design - Lessons LearnedESF representative of full range ofpotential repository conditions
* Machine Design- Cutters
- Muck pick-upShield configuration
- Gripper configurationVentilation
* Fracture density and orientation
* Ground Supportnrc ppt
11-5
I
VEW OF PHOTOGANTRY IN 2ND CURVE FROn REAROTN
VIWOF THERNOMECHANICAL DRIFT FRON ALCOVE 5 EXTENSION)
II
itI
I
iit
i
.
0) 0
YUCCAMOUNTAIN
PROJECT
Scientific Program Update: OvTesting Activities and Thermal
erview ofTesting I';sues
Presented to:DOE/NRC Technical Meeting, Video Conference
Presented by:Mark C. TynanDOE Staff, Assistant Manager Scientific Programs
03
IhSeptember 12, 1996 U.S. Department of EnergyOffice of Civilian Radioactive
Waste Management
7sw,
n e I o r i n g M E IC hi
t a b 1 9 4 P g e S 8SO° POltaP
70+
G o tD n c P S k - ts*-
--- O--
-h--4
!~~~*ooC st
…-
B~~~~~~~~~~~~~~~~~~I
Sche ~ -
Coalede
D r S 4in A c tu a ,125f, 19 No O -
l
N
DOE / NRC TECHNICAL MEETING
ESF MAPPING STATUSTBM at Station 63+47
Full Periphery Mapping completed to Sta. 62+48- In Topopah Spring crystal-poor middle non-lithophysal (Tptpmn) to 63+47
Detailed Line Survey completed to Sta. 62+50
Stereophotography completed to Sta. 62+71
RQD Classification completed to Sta: 62+27
Q&RMR completed to Sta 62+00?
3
DOE I NRC TECHNICAL MEETING
Status Alcove Studies:
Alcove # mapping photographyline survey &
I complete complete2 complete complete3 complete complete4 complete complete5 complete complete
- to 130 m In at end of access I observation drift
6 not initiated not initiated- will begin mapping In next few weeks; 90m in
q -
DOE I NRC TECHNICAL MEETING
ESF Mapping product content- locations of structural features, samples, ground support,
convergence pins, closure pins, MPBX, SPBX and straingages are recorded on ESF maps; ground conditions
Consolidated Sampling- samples collected as required by LANLITCO Construction
Monitoring:- continued to read convergence pins, including alcoves
2,3,4,5Construction Activities
- Thermal Alcove (5): borehole drilling continues inAccesslObservation Drift I single heater test area;excavation has temporarily ceased at about 130m from main drift,concluding early construction phase
- Northern Ghost Dance Fault Alcove (6) constructioncompleted fro Phase I to 90m; preparation for drillingthermal corehole through Ghost Dance Fault
Figure 3. Q Values for Topopah Spring Middle Nonilthophysal Zone (Tptpmn)(Main Drift Station 27+16 to 44+30 m). S tinnal I aboratonie
WBS 1.2.3.2.7.3.4QA QA
Tptpmn - Topopah Spnag Tuff, Middle Nonlithophysal Zone1000
100
3CY
U
0
CA
to
0.1
0.
C),
~00Ut
aZ
0.01
0.001
i i----i
- i +-
Legend
* Rated Q
Moving Average Q
+ Installed Support
V
I I I- I � + � I -, 4 � 4 -� 4 � I � 4 � 4.I I -
I 11119111111111111 I111111111
2600 3000
I """'1"""'11""1""
100 3800 4200
Funnel Stationing in Meters4600 5000
6.
Figure 1. Q Values from Thermal Testing Facility (TTF) Surrounding the Single Element Heater Test.Sandia National LaboratoresWBS 1.2.3.2.7.3.4QA OA
1000
100
._
0au1
ao
10 -
0.1 -
0
ca
gD
04
0
0.01
0.001
. = _ _- X __ I _
Lcgend
* Rated Q
+ Installed Suppo rt
V
_ , .,
1
_ j i i ~ i I I I I I
250 I.0 2550 75 0 25-
Tunnel Stationing in Meters50
Station (30 to 58+75 m) versus Rated Q and Q Nbving Average in the Main Drift.Stratigaphy Sandia National Laboratones
Iudwft gw _Prlininary
1000 -_
100 -
-
I - 9
L=]: _ , ____ -
_ e t e f _ - L- - I f I I e I I :
. g ,:*.- * :,*. .. -i ......... - -- -.---- W-,
! -L;-@ b *-bL--- * >- *L--
m 1 *w#-w - 3 21''' 1 iililLi ::1E M;z: X ;L[;It8:SoI .-- :'.YSrl , * Sots 1
1.s - C - U W W ffi H
I
.0
10
I
II
Os@1
-* wE- * .- 'V. ̂4rL. f 4ll- 4- inI p
t
420Nl:l'A"jW4%+R.i. ...... Iv
IS OW yz I.ORC'tw e, "~~~~~~~~~V .".,,.r.-,,~,p,~,~",17 t"'_1,t~. "P g �-�ppnw H._g_1 � n�vp..-%,-
,.7 , . q,1.y ZA'7 01 _0.1 ,: -f ±-v lIV_ -b -.x-, - __I__ __ L ...-. ' -'- . -; |
.. L. I r M..Trt; Tu
-- -~-----~ 9-4
4. Tpbt4 & Toy - PreI - _
iva i*�nB-'e-dded_ -fik- -armI Yucca0.G1
0.001
[Mtn. T.
F :m
9 i Raild Q
Mo ilug Avac gcQ
+ limfladSuppn -I
v
. IP1 rn -. I . 1 ML. -UV~W1-Q T._ -Ia _A- T _nn.t: n 1 .J :4 L-nh-J 7nP.
I 1 ± L n 14p..JI * «l - *IJ I
9. Tpinm - Topopal SprifgTuff, kliddle lnonlittolhysal 4one - I - I __ I __ I- -. . ............III I IIIIII 1!1 11 III III III III IIIII I IIIII I II i II III III I11111 lIlIlIl� Ill Iii 11111111 �II 1111111111111
3000 3400 3800 4200 4600 5000 5400 . 5800Tunnel Stationing in Meters
I? -
Station (00+60 o 30+00 m) versus Rated Q and Q Mbving Average in the Win Drift
Stratigraphy Sa ndia National LaboratoiesPreliminary
1000
100
T3- - l- 41 5 16 7-8 9
_ I, _l | ,, = _ , _ _~~~~~~~~~~~~I
-
uD
.P£i
10
I
0.1 --
I t
I. -- It
. Ia - - ......" - - - - - .V
:_ .*t k
I 1 m
a
V
I
III
k .rV
0fi~
I "I - a ,. me- **k
dfF. V
-J
_ i !4
-_0 _ o
0
C,)
_.
ILo t.4
A
IV
iT.. Dipj IJ I UIL3 Tnl A - flfT"Y'
0.01
0.001
4. Tp &Ty- TiVa C yon dded uff a Yucca Mtn. TA
IGTnh2- nPa%4 d iZ Ie__ _I _ I _ , 7bof Si T l _1 7 Mp~ swiU Ir Zmyiinraan ~s oe
Legend
* RatedQ
Moving Avemge Q
+ h ed Spot
V
9. Tp pmn - opopa spd"mTuff 4ddlel ,nlifthhysal 4one I I I I11111 ri iIllil 11111 I Ij Il~l~llll 1111117111111lI 1171111111J 1111T 11111111 111111111111 I I IT7111111,1 I I I ~lIIII~rl I
0 400 800 1200 1600 2000Tunnel Stationing in Meters
2400 2800
C?
28+00 - 56+30 Fractures in the ESFFracture Density and Moving Average
Tptpmn14 .
12
10
8 10
A.
.0
4
2
0- - I ~- . . . .. . I a u I V- U t r -v- - -
co M- -81 8 8 M M § 1 I 8 I § ISg. (moto8 8 8 Statoning (mted)I L II E
U. S. Geological Survey/Bureau of Reclamation2.)*~~ ~~ ~~ ~~~ ~~~~~~~~~~~~
NWTRB Meeting, July 9-10. 199610
VV,
TpkfTpbt5/Tpc 0+60 - 28+00 Fractures in the ESFFracture Density and Moving Average
Tpcpv - Tptrv Tptm Tptrl-Tptpul14
12
10
8
4
2
0
- - - . . . I ' l l8W. § (81 & § § 181. § § § 8V- § 9 & § (80 SOO 1 8V- 8 1 1 § § R -§V- V- V- V- T- T- T- V- T- V-N �3 C4 C4 C4 N
Stationing (meters)U. S. Geological Survey/Bureau of Reclamation NWrRB Meeting, July 910, 1996 I I
.... . .
2U49 to 399 rDLs otuirs Contour Plot
SCHMIDT POLECONCNtRATI ONSX of total pr
1. X La
(4 x
< 19 x
< 12 x
w ~~~~~ ~~~~~~~( 4 xEQUAL AREA
LI4R. HEMISPHERE
2563 PolesHO BIAS
CORRECT ION
Poles to Planes
29499 to 33409 DLS Fwaotuz~s Scatter Plot
MUM. OF POLES
4o4*4 +*4 +eaeau I pole
\ *n ..++ .+ .+ + 4 to 7
so + + t0+4 +000 + go+eevo*4 4 4+ 4c *4.44*000 0 to 11
4*0 + +29**to *23
+ee+ e + +40 +0+0004 0 + 12 to 13*4 + +4 + + ++++ e0000e+**+ + gk e +*+eO*0/° t+e + +0+0 * 0 e 16 to 19
000+ + *+~~44 00 * 2 o3
4 e ++ + ++ + e 4* + + 4 + + *440 L3.ZR 20 to 23{oe+ +e++ + + +eeoe
* 4 4 4*+ 46 4 *4 *400
*r++ 4 4+ 4 04 44 ++ oe++00 0 24 to 27
40040 44* * 00+00
a + + o0+ * * +*4eo*0+ ++++ 00**0 44*4+**I * 28 to 31
w q +e~°t + ++ + eoe F *E o32 to 35
4000*4 44*440440 00~~40 000
I e ++e + +++ + + o P_\eove+ ++ + +o e + +++ ++ oez EQUAL AREA
e + + o+e + +t + +e00 o+ * +" 0: eL eetUR. HEMISPHERE
1 * ++ ++e ++ee e }+ + *++eed\ ++ + + e+ + +0
*+ e + o ++ + ooo
0 4 + e ~+ + + + +~$ + + .. 00*+ v+ + *+ e0
Oee+ ++e ++* + ++o*/>eoe-ee~eo + e++ +eex
boveevooe- ++ee + o
Po l s to P anes
.
35+99 to 42+99 DLS Firac tues Contour Plot-M i - - -- -
151 | SCHMIDT POLECONCENRAT I ONSv. of total per
.8 x area
( 2 K
( 4 V.
( 6
w -E (B VEQUAL AREA
LI4R. HEMISPHERE
2208 Poles
CORRECTI ON
Poles to Planes- .
35.92 to 42+99 DLS Fractures Contour Plot.
yo o ++* , FOOOO0^-/ 0+ ++ 0+00000>1+
>,to ++ + 0 o ooo-eo* s+ o+- ew + o+* **os
t Jo+ _ + ++o ooo Kw*+o + n ++ + +++0000o
o + + + _ oooooo
so+0+ + _ + ++ 0ovoxo~~+oo+ + a + + + o0
*ie+ ++ + (a ++e0eo+_ + o + + + 0+oo^
{ ° ° + + + 0 + +ofe + + + 0+*+Oe
s+ +o + : + +
Z2 + + " + ++ + o + *++ ++ 4i +000 + o0 7
S,~~~! + $*01D o o + + *++ + o+ o +
o + eo + + + 001o+ + o e+ eo + eo
\ + ~ +~v ++ + +e0oo
\+ + F O + O+ 000* s+ + o + + + +oooo0
*+ +~~~~ ++ +otoecO0oo+ + oo* + ooo
*+ +X + +oo**o+++o +oorb+ + + + 0 + oo{>+0 0 ++ + + ++oo
> ++ o + ++ + +ooo~oooovo+ + I + +00ow
ooooe~+ + o+ + v o>+ooo~ove ee e+ 0 o ' ovoo~olooeooot
HUM. OF POLES
+ I pole
o 4 to
O 8 to
o 12 to
* 16 to 2
* 29 to Z
* 24 to;
* 28 to
* 32 to'
* 36 to@
7
Ll
L5
L9
23
31
35
39
EQUAL AREA
LWR. HEMISPHERE
2208 Poles
s -Fo * * 2 -
4260 to 490 DLS F"otuzs Contour Plot
SCHMIDT POLECONCENTRATIONSx of total per
0.3 :4 aw~a
6
< 12
w --E (14EQUAL AREA
LUR. HEMISPHERE
3159 PolesNO BIAS
CORRECT ION
Poles to Planes
420 t 49*90 DLS Fraotures Scatter Plot
NU. OF POLES
* I pole
00,,00* oo *0**0 0 " ° 10 to 19
*S °, * ;*000 20 to 29
oo+ 4 *ooooo o 39 to 39
* 49 to 49
+~o+ + <1f$ e +ot @*50 to 59
+i~l $ s °+o¢+ooe o , 60 to 69
: _ + + 70 to 79
* 0 to 99
EQUAL AREA
L\ER. HEMISPHERE
3159 Poles00400 *0.0 . *0* 00
'0+ +1+ tt ::+0* on°°t4o000000
Poles to Plans
, .
z--
- --. -
49.90 to 56+31 DLS Fractures contour Plot
a ~~~~~~~SCHMIDT POLECONCEITRAT IONSX of total pp
I ~~~~9.2 aa
< 2.5 x
<(5 x
< 7.5 K
< 12.! K
< 15 Y.
w (E 17.5 V.EQUAL AREA
INN * HEMI SPHERE
2208 PolesNO Bs
CORRECT ION
Poles to PlanesIL
49+99 to 56+31 DLS Factures scatter PLQtib
HU". OF POLES
+ 1 pole
e 9 to 17
o le to 26
* 27 to 35
* 36 to 44
x 45 to 53
v 54 to 62
4* 63 to 71
* 72 to US
* el to e9
EQUAL AREA
INR. HEMISPHERE
2208 Poles
WI
Poles to Planes
DOE / NRC TECHNICAL MEETING
EXPLORATORY STUDIES FACILITYActivities and observations
Drilling blast monitoring holes in the AOD near thecross drift
,/4 V
DOE / NRC TECHNICAL MEETING
EXPLORATORY STUDIES FACILITYActivities and observations
- Ghost Dance Fault splay identified in NIS Main driftat station 57+02; 12m offset, strike 2050, dip issteep, with fracture zone on downthrown side
- Fracture zones with north/south to NEISWorientation from 58+00 to current position; priorfracture orientations more NW/SE in 35+00 to 55+00portion of the tunnel
11
DOE I NRC TECHNICAL MEETING
ESF ALCOVES: testing status and preliminaryresults
-Alcove I - Upper Tiva Canyon Alcove (UTCA)} Station 0+42.5a gas analysis, age are 100% modern
V
1.
DOE / NRC TECHNICAL MEETING
ESF ALCOVES: testing status and preliminaryresults-Alcove 2 - Bow Ridge Fault Alcove ( BRFA),
* Station 1+68
tests Tiva lower lithophysal, Bow Ridge Fault, pre-Rainier Mesa non-welded tuffsgas phase % carbon, C12113 ratio, 0181/16 ratio andC14 data should be availablegas age interpreted to be modern to 1000yrs oldno attenuation of barometric pressure changes inBRF zonetemperature measurements in boreholesCross hole tests and tracer tests indicate high airpermeabilities and porosities in fault zone (20 darcies,20-29% porosity); 5-27 darcies perm. for rock units tested
ESF Alcove 2Bow Ridge Fault Test; two radial boreholes ~30m deepr r ifs 95¢ vg~se~sai>W< >g~kg^¢*S-4s; so i....", -- S I...I . --. - ...
V~ti. ~~ e
DOE / NRC TECHNICAL MEETING
ESF ALCOVES: testing status and preliminaryresults-Alcove 3 - Upper PTn Contact Alcove (UPCA)
* Station 7+56; Tiva lower non-lithophysal I vitric contact
> gas phase % carbon, C12113 ratio, 018/16 ratio andC14 data should be available
a gas age interpreted to be modern to 2000 yrs old> tritium detected in borehole 4 (4 samples); none
detected in borehole 1 (1 sample), bomb pulse H20> Air permeability measurements, Tiva lower
nonlithophysal, 0.04 to 8 darcies; Tiva lower vitriczone, 1-24 darcies. Measurements reflect variation in intervalfracture density variation
> Shut-in pressure monitoring, gas chemistry sampling, C14, tritiumanalyses being performed; no further results to report today
ESF Alcove 3: Upper Paintbrush- Tuff Non-Welded ContactTest of Lower Tiva hydrostratigraphic unit; two radial
boreholes 30m deep each~~~~~~~~~~~ fl I~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Z
"a~~~SPl...Ž4 ............ .
OW~~~~~~ I, ,
TI 151 BROM~~~~~- I*'
MEN por~rl~oo ~.
~~~"--~~~~~~~~ A~~~AL PP O IM T
w~~~~~~~~~2.nctnncr-949
v
DOE I NRC TECHNICAL MEETING
ESF ALCOVES: testing status and preliminaryresults
-Alcove 4 - Lower PTn hydrostratigraphic contactalcove (LPCA)
> Station 10+27> Pre Pah Canyon Tuffs (PTn), Topopah vitric (TSwl)> no test results available
Test of PTn h)bI
ESF Alcove 4(drostratigraphic unit; one radialorehole 30m deep
\ / Office/Refuge
-ICri ApRniAT
B...''~
~~* Zag
~NRG- g ,~0 ~
~~~~~ ~ ~ ~ o ot Potl--
SALE APPROXIMATE
125.nrc.tynan.cdr - 9/4/96
V
DOE I NRC TECHNICAL MEETING
ESF ALCOVES: testing status and preliminaryresults
-Alcove 5 - Thermal Test Facility I Alcove:a Station 28+27o Topopah middle non-lithophysal tested in thermal
alcove; 0.001 to 10+ darcies bulk rock permeabilitiesrecorded
*> Single Heater Test initiated 8126196; heater testcontinues
a>. construction monitoring activities continuea Drilling continues in thermal test facility; most
borehole drilling to be completed within 1-2 weeks
ESF Alcove 5Thermal Testing - Phase I
IConstructron .0-S:-.Turnaround*-lw>>2..v. .X;uNIche;XX>;g.6P>--
.,:,,'o'^ ^ . s tE . I
�o - ' o >.. .?
t E ) n S
' . .
\,. i,
125.nrc.tynan.cdr -9/U96
Plate-LoadingNiche
Drift ScaleTest Region
HeatedDrift
Began: Jan. 19, '96
Connecting Drift
Drift
ThermomechanicalAlcove Extension
ThermomechanicalAlcove
IoRmCenterline @ CS 28+27 ESF Main Drift a
I9I
Figure 1-1. Plan View of ESF Thermal Test Facility.
21
Thermal Test Facility Layout
Floor HeatersBulkhead
\ if \\ \~Plate-oading 7 ell DAS
Instrument Holesfrom Observation Drift
Test
a
DOE I NRC TECHNICAL MEETING
Summary Single Heater Test Activity- Purpose: to study and characterize host rock
environment heat transfer, conduction, convection,moisture movement, thermally induced geochemicalchanges in water and rock chemistries and properties,and thermallmechanical properties; examine performanceof tunnel support systems
- Start of test on 8126195; 9-12 month test duration- About 25 cu meters rock to be heated to IOOOC by single
heater element in thermal test alcove- Heater element may reach temperatures of 3500C- Proximal to heater element, 2000C + for wall rock- Cooling phase, summer '97; test to be completed during
the fall of '97
I7)
DOE / NRC TECHNICAL MEETING
Characteristics of Drift Scale Test- Will be initiated in FY97 and continue for 24 years- 30,000cu ft of rock will be heated to OOOC; heater-
proximal wall rock temperatures may be 200OC-350 0C- heater element temperature may be 2 times higher than
temperature in wall rock (up to 4000C)- NOTE:
o Test development and model assumption is thatconduction is most important; thus, models reflectconduction only. If convection is involved oraccommodated by model, temperatures within host rockwould drop. Therefore, models of temperature / profileswithin host unit are conservative.Hot source (4000C) required to heat rock; area of thermalperturbation will be monitored, has been modeled, andeffects of induced thermal pulse on rock bulk hydrologicand physical properties will be measurable
DOE / NRC TECHNICAL MEETING
ESF ALCOVES: testing status and preliminaryresults
-Alcove 6 - N. Ghost Dance Fault Alcove (NGDFA)a Station 37+37a Test Topopah Tuffs, GDF zone
* Phase 1: thermal probe hole; constructioncomplete, drilling to begin in mid-September
* Phase 2: hydrologic and hydrochemical tests,maps, construction monitoring along GDF
* No tests conducted to report on yet
ESF Alcove 6Ghost Dance Fault test alcove: Phase I
-C �. : � � �e - - -M - -, ., - - - .." - -
ESF Acove 6Ghost Dance Fault test alcove: Phase 1
4 -- 4¾'i:
d. b p '~4. - ~ ..4-l 4 thru >'"'#34 4.444
ESF~~~~~~~~~~~~~~~ 4 4 -Cy 4 U.4,444
4-.4-'..4 4444 4- -
- -r-'-t- -~~'s~"-~- .4 4
.Jim. ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~~~~~¶4 44 444~
$44-.44444 4 4..44
e ogGhs a ~ut rcmap In-
44~',4 . 4 4 4 4
.44., ~ 4or 4ge
DOE / NRC TECHNICAL MEETING
SURFACE BASED TESTING
C-HOLE TESTING:> The third tracer test (sodium iodide injected in
borehole c#1 on 6/18196) has continued for threemonths. Observing of changes in concentration of tracer materials continues;interpreted breakthrough In 22 days, concentration peak after 68 days and steadily declining.Reactive (sorbing) tracer test to determine radionuclide travel time are on hold pending grant ofstate permitField determinations with the chromatograph continue are still variable but generally Indicate
an upward trend In iodide concentration at C-3 over the weekend. This reverses the trend seenpreviously. pump In C-3 continues to operate at about 153gpm. Cumulative volume pumpedfrom the C-3 borehole during the current series of tests exceeds 25 million gallons
G-2 TESTING:o Initiated initial pump test on 418196, draw down to
4125196; monitoring recovery since thenSlow recovery to current level at approximately 2 feet beloworiginal water elevation; barometric pressure changes evidentin curve
11
Al
Sampling Locations in ESF:Nnirth nol Chlorine=36IDwou I ImUai South Portal
* Systematic samples, 78+57200m spacing,
* Feature based samples75+00J
* B=indication of "young"Cl-36 bearing water, "Bomb Pulse"
70+a
Alcove
B 35+05 n=1 (43+63)nnl - -7 35+45n1 B(44+20)n=1 ,35+5Sn=1 \\
1! B(14+00)n=1
63+47. 19-9-96
Extent ofAnases9-1%§25+00
_ :0 N From: Fabryka-Martin,et a 3196
Drawing Not To Scale125.nrc.tynan.cdr 9/4/96
DOE / NRC TECHNICAL MEETING
STATUS OF KEY 1996 DELIVERABLESSynthesis Report "Characterization of Fractures atYucca Mountain" ( 3GGF205M; ESF, surfacegeology, pavement mapping data); received and inreview"Geologic Map of Yucca Mountain" (3GGF204M);received and in review
- Tectonics and volcanism synthesis reportsreceived and in review
- ESF Mapping deliverable s due) 60 - 4+00 due end 9196, report and maps
4- 28+00 due end 9196, report and maps> 27-55+00 due end 9196, maps and line survey data
DOE I NRC TECHNICAL MEETING
Thermal Test Concerns Raised by NRC1) By heating the rock mass to 4000C temperature, near
drift wall phenomena such as gravity driven refluxing Idripping may not occur
2) Relative importance of advection and bouyant flow maybe very different at 4000C
3) Is there a risk of instruments being affected by formationof saline brine
4) Would the clay in fractures behave differently at 4000Cthan at 2000C
5) How can the hydrologic flow heterogeneity expected inthe repository be studied in the test if there is nomoisture in the fractures of the dryout zone, because ofthe 4000C temperatures
3f
DOE / NRC TECHNICAL MEETING
Other Concerns of the NRC
-Status of the large block testX Likely to be an FY'97 activity; currently, testing suspendedv NRC should be aware that the test plan scope may be
modified in coming monthsv Dimensions of the block are__
DOE / NRC TECHNICAL MEETING
Other Concerns of the NRCThermal testing and related concerns- thermal load design needed to be addressed in links to
testing planned should be clear- document issues related to drill and blast operations;
impacts on rock from construction; drill and blast may bebad construction method for alcove construction. Alpineminer may be better
- test location may not be representative- DIE background work sufficient for thermal test; water
issues- Future plans for testing in the ESF
Significance of fracture zones (60+00-head)
3e
SupportInformation
*esf55-04a* *esf55-0 4 a*3D,fIx=O.O,all,280md,.86atm, 1 drft, 1.1 25kW/m, 1 25W/m2(4.5<T
TIME(YEARS) = 1
.,
ta:
,I 34
0.
21.
41.
61.
82.
102.
I 122.
142.
- 163.
183.
203.u
METERS
busch /us3/fnuoulpuVesI55-01 Extool version: 16.16Sun Jun 23 16:21:07 1996
V/
*esf55-01 a* *esf55-O1 a*3D,fIx=.05,all,1 .9microd,.86atm,1 drft,1.1 25kW/m,1 25W/m2(T
TIME(YEARS) = 1
A:
i 345ME
C
22.
45.
67.
h9.
-. 112.
--134.
-156.
-178.
201.
223.
I.
u
METERS
busch Ius3/nuIIoulpuVesl55-O0 Extool version: 16.16 Sal Jun 22 21:51:11 1996
.9?-
*estb5-01 aa* *esf55- O1 aa*3D,fIx=.05,all,1 .9microd,.86atm, 1 drft, 1.1 25kW/m,1 25W/mT
TIME(YEARS) = 3
cn
*5
o.
32.
128.
-160.
-] 192.
224.
256.
288.
320.
METERS
busch lus3lnulfoutpuVesl55-O1 Extool version: 16.16 Sun Jun 23 15:55:17 1996
'/3.
*esf55-04a* *esf55-040*3D,flx=O.Oall280md,.86atm,1 drft, 1.1 25kW/m, 1 25W/m2(4.5<T
TIME(YEARS) = 4
320 0.
325 _ 5.
330 _ 1_70.
335 1 v v *085. 70.
L 340lI I 12 1 4
350 _ 11109.11 a_ _ | .
244.
279.
314.365
349.m
UMETERS
busch /us3/nuft/outpuVes5501 Extool verson: 16.16 Mon Jun 24 10:02:01 1996
lesf55-O1 aa *esf55-O1 aa43Dflx=.05,all,1 .9microd,.86atm,1 drft, 1.1 25kW/m,1 25W/rTEMPERATURES ALONG UNE IN HEATER HORIZON THROUGH MDPOINT 0 DRIFT HEATER
NORMAL TO DRIFT HEATER AXIS--_
I,
:
C
I'
c
C
crv
IiC
x (m)Ca
Ib AMRi Exiwmt V'on: 1W16 Wed Atvj 14 1ZI21 1996
5 3'.
*esfS5-501 aa* esf55-O 1 aa*3D,f Ix=.05,all, 1 .9microd,.86atm. 1 drft, 1 .1 25kW/m, 125W/rnTEMPERATURES ALONG LINE IN HEATER HORIZON THROUGH L4IDPOINT OF DRIFT HEATER
NORMAL TO DRIFT HEATER AXIS350 I I I ' ' ' I ' ' ' I ' ' ' '
ZER PCOLATON
300-
2CO- / I'J. i \\i~~~~~*
CG
It
C.c
tr
r
. x (m)
beo AAQWUI Wo AvafEp on 1616 WedAug 14 122:54 196
. I
d
Oesf55-O1 aa *esf55-O1aa*3Dflx=.05,all,I .9microc,.86atm, 1 drft, 1 .1 25kW/-n,1 25W/mTEMPERATURES ALONG LINE IN HEATER HORIZON THROUGH MIDPOINT OF DRIFT HEATER
NORMAL TO DRIFT HEATER AXIS
PERCOLATION FlUX = 05 mm/fr
- - - .
iv
I-
C
z.I
p
C
C
�1
C
�C
ll�
'. I..
__ T_____ - 1.5..-...---- TtE(YERMS - 2
___ - - TECMAIM 3
J .1. -L L J I I -k.30 35
x m)
Ife Almftb" Exteohenwr. 1t4Wod Ato 14 13111:31 1996
*es,55-D1 aa* esf55-O 1 aa3D,flx=.05Oll,1 .gmicrod..86otm, 1 drft, 1 .1 25kW/m, 1 25W/rmTEMPERATURES ALONG LINE IN PLANE ONE METER ABOVE HEATER HORIZONDRAWN FROM DIRECTLY ABOVE CENTER OF DRIFT HEATER NORMAL TO AXIS
A~~~~~~~. 1%
'I
k
COIIDUCTiCN 0ILY
. \~~~~~~~11
< A.. In1% -
i II
c
- YEARS - .5
5-......
.... .
K
loo AaII.ff w ion 1Q16 VeedAiu� 14 14.11:36 1".1
c
*0sf55-04a* *esf5-04a 30,flx=O.O,all,280md,.86atm, 1 drft,1 .1 25kW/m, 1 25W/rm2(4.5<TEMPERATURES ALONG LINE IN PLANE ONE METER ABOVE HEATER HORIZONDRAWN FROM DIRECTLY ABOVE CENTER OF DRIFT HEATER NORMAL TO DRIFT
CC
4
C.c
rt
fC
ZERD PERCOLATION
, _r
C
r
cr. Iir
cCl
I.
IC1
C
1
*. � _ s
7IWEIYEAS w 1.5. Esn. 2
_ _ _ _ AdEYES 3
x (m) c
kg Amftff heoo V3"bo: 161l VindAul 14 12gOOt! 136
.
esf55-O laa esf55-01ta3D,flx=.05,all,1 .9microd,.86atn,ldrft,1 .1 25kW/m,125W/mTEMPERATURES ALONG LINE IN PLANE ONE METER ABOVE HEATER HORIZONDRAWN FROM DIRECTLY ABOVE CENTER OF DRIFT HEATER NORMAL TO DRIFT350 . * I a I * * * * * * _ *
PERCOLATION FLUX .05 mm/yr
300_
250
200-IO~H.,... .. _..... \
1
.5.~ ~~~1c
C
C.
Cc
TIIAE((EARS) 1.5T... £RS) - 2
-_ - - - TIME(MRS) 3
x (m)c
1o AMAG ff Ee wsimo 16.16 VisdAAjg 14 13A129 1996
*esf55-.O0la* esf55-O1aa3D,flx=.05,all,1 .9mlcrod.8otmo,1 drft,1.1 25kW/,n1 25W/mVERTICAL TEMPERATURE PROF-ILE THROUGH WING HEATERS
N0.4 FROM DRIFT HEATER AXIS
couRucnoNi ONLU
'A\
SC/ - -1II
4
z (m)
lee holes Exwxeltof m" %oSdAI4 14 1:4925 1"6
-5( A-
esfS5-04a* esf55-04a*3Dflx=O.O,al,25Omd,.86atm, 1drft, 1.1 25kW/m. 1 25W/m2(4.5<VERTICAL TEMPERATURE PROFILE THROUGH WING HEATERS
10.4 m FROM DRIFT HEATER AXIS
j
ZERD PERCOAIIN
A
I I I
I t& I
. I
I S
' I"
I \%I
L)
I
I
IF/ I
/
!
II
1%
1%
TIM .- 1.5..... .__TIIJE(YE"S 2-_-___- TN - 3
z (m)
ke Ailmw Etol WSon; 1616 Wod Aug 14 i I:Wol 1996
0
Al
*g3d4Oacl* *g 1 32xbt*3D,ftx=.05,all,280md,.86otm.1 drft,1 .OkW/m,. 1 25W/m2(4<x<qm)1 8VERTICAL TEMPERATURE PROFILE THROUGH WING HEATERS
10.4 m FROM DRIFT HEATER AXIS_
I v v I I I F ---- I - v * F
PERCOLATION RATE .05 mm/yr
----- T - I ...- - -
300J-
A
.'
250i
I
I
.
\ .
I '\2000
I-;
150
II
/II
CI'
i
i
C
C
C5 I
CC
CI
TMKYEMKS), 1.5. .. . MECY RS -2
-- -- -- TM"(iARS - 3_
z (n)
crom lr ff.16 WedAug 14 11:04:11 1996
H l TEM rmPti I D T MPL o w rc t f,
z o - S CI15o -ZOo C
10 - IgoC_
'Low
IUl
Uniform Temperature Load Parallel to DriftTemperature at GQu Year
Mwo ~~~~~~x
._~~~~~~~~~~~~~~~~~~~~~7
temp
so~~~~~~~~~~~~~~6
238
192
98 ~~169
ci)loM C
.1
Varying Temperature Load Parallel to DriftTemperature at 0.67 Years
7
CL)
YaX~(S
.168M156
145134123111100
300
8320
340 0~~~~~~
380
380 ~t= 4yr
0 50 100 150 200 250 300Temperature (C)
Figure 17. Vertical temperature profile along the center-line of a row of drift-emplaced, large-WP-sized heatersgenerating a lineal heat load of 0.8 kW/m and flanked bytwo horizontal-borehole-emplaced wing heater arrays. Theheater arrays are generating an APD of 105 W/m2 over theinterval 4 < lx < 9 m and 157.5 W/m2 over the interval 9 <Ld < 14 m from the drift centerline at = 4 yr. Bulk perme-
ability kb = 280 millidarcy, and vapor diffusion tortuosityfactor eff = 0.2. Curves are shown for two different thermalconductivity Kth sets, including the RIB version 3 Kth values(reference case) and the RIB version 4 Kth values.
Civilian Radioactive WasteManagement SystemManagement & OperatingContractor
Ta~Eiff
TRW Environmental SafetySystems Inc.
Engineering Design Description
Jack N. BaileySeptember 12, 1996
0
I
B&W Federal ServicesDuke Engineering & Services, Inc.Fluor Daniel, Inc.Framatome Cogema FuelsIntegrated Resources GroupINTERA, Inc.JAI Corporation
JK Research Associates, Inc.Kiewit/Parsons BrinkerhoffLawrence Berkeley LaboratoryLawrence Livermore National LaboratoryLos Alamos National LaboratoryMorrison-Knudsen Corporation
Science Applications International CorporationSandia National LaboratoriesTRW Environmental Safety Systems Inc.Woodward-Clyde Federal ServicesWinston & StrawnCooperating Federal Agency:
U.S. Geological Survey
Engineering Design Description
One Pass Program
Ongoing development of a Single Design to support:
Viability AssessmentEnvironmental Impact Statement andLicense Application
Developed over 5 year period
Civilian Radioactive WasteManagement SystemManagement & OperatingContractor
LV.EIO.JNB.09/96.036 2 919/96
Engineering Design Description (Con't)
Prioritized to:Meet needs of each area above,Identify latest design for post-closure evaluations andAddress likely regulatory issues associated with
first of a kind
Establishes adequate design basis to support Licensing butnot construction
Civilian Radioactive WasteManagement SystemManagement & OperatingContractor
LV.EIO.JNB.09/964M 3 99196
Engineering Design Description (Con't)I |~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Initial Design Efforts focus on VA:
Support to Performance AssessmentDesign of selected systems structures and components
Corrosion models & associated testing programs
Feasibility of technology of PA designExisting technology use in new applications
Underground ventilation
Civilian Radioactive WasteManagement SystemManagement & OperatingContractor
LV.EIO.JNB.09/96-W036 4 9/9/96
Engineering Design Description (Con't)
Cost to construct
Evaluate and develop design for significant cost driversGround Support
Establish regulatory basis for planning
Basis for regulatory acceptance precedented- yes or noIdentify acceptance criteria
Radiological waste processing systemsBare spent fuel handling operations
Determine level of detail for license submittalBinning
Civilian Radioactive Waste LV.EO.JNB.09/98436 5 9/9/
Management SystemManagement & OperatingContractor
Engineering Design Description (Con't)
Means of prioritizing
Binning Identifies priorities for level of detail at time ofLicense submittal:
Bin.3
Bin 2
Bin 1
Radiological involvement - No regulatoryprecedent
Radiological involvement - Regulatoryprecedent
No radiological involvement
Civilian Radioactive WasteManagement SystemManagement & OperatingContractor
LV.EIO.JNB.09A)6-. 6 919/96
Engineering Design Description (Con't)
Developed priorities to support ViabilityAssessment
Performance assessmentUse of existing technologyCostingLicensing planning
Use of expert panels to guide process
Civilian Radioactive WasteManagement SystemManagement & OperatingContractor
LV.EIOJB.09/96-036 7 919/96
Engineering Design Description (Con't)
Basic Design Development
Advanced Conceptual Design as Point of Departure
Identification of Systems Structures and Components
Development of Design Basis Events
Classification of System Structures and Components
Civilian Radioactive WasteManagement SystemManagement & OperatingContractor
LV.EIO.JN.09196036 8 9/9/96
.1
Engineering Design Description (Con't)
Identification of SSC design requirements considering
Postclosure performance requirementsPreclosure safety considerations and regulatory
precedentMDGS RequirementsIndustry codes and standardsetc.
Civilian Radioactive WasteManagement SystemManagement & OperatingContractor
LV.EIO.JNB.09f96-036 9 9/9196
Engineering Design Description (Con't)
Phases of Design and Products
Phase 1 Support to VAMajor decisions with regard to PA
Waste Package MaterialsMaterials of construction
Use of ConcreteInitial testing results
Cathodic ProtectionRepository Basic parameters on layout,
thermal, drift diameterEstablish basic design requirements for
the majority of SSCs
Civilian Radioactive WasteManagement SystemManagement & OperatingContractor
LV.EIO.JNS.09/96-036 10 9/9196
.
Engineering Design Description (Con't)
Considered as part of viability assessment
Phase 2 Interface for License Application
Design to support Preclosure radiological analysis
Design to support licensing for Bin 3 and some Bin 2
Phase 3 -Completion of Bin 1 and "fill-out" of Bin 2,and continuation of design
Civilian Radioactive Waste MV E10.0996-036 11 9/9/96
Management SystemManagement & OperatingContractor
Engineering Design Description (Conit)I 11 ~ ~ ~ ~ ~ ~ ~~~~~~~-
Design Control
Controlled documentation
Traceability of Design to:
Performance Assessment,
Costing and
Licensing documentation
Civilian Radioactive WasteManagement SystemManagement & OperatingContractor
LV.EIO.JNB.09/96-036 12 9/9/96
.1
Engineering Design Description (Con't)
One Pass Approach requires:
Control and documentation of design evolution,
Traceability of design requirements and design
solutions
Documentation of design decisions and alternatives
considered
Pointers to regulatory requirement solutions
Civilian Radioactive WasteManagement SystemManagement & OperatingContractor
LV.EIO.JN8.O98-O38 13 919/96
Engineering Design Description (Con't)
Documentation Design exists "in Process" on theboards
Design
Design
drawing and document list is summarized for VA
is described at the time of the License Application
Civilian Radioactive WasteManagement SystemManagement & OperatingContractor
LV.EIO.JNB.09/96-036 14 9/9196
U.S. Department of EnergyOffice of Civilian Radioactive Waste
Management
Spent Nuclear Fuel EffectiveThermal Conductivity Methodology
PRESENTED TONRC
PRESENTED BYThomas W. Doering
Manager, Waste Package Designim. | Robert H. Bahney III, Thomas L. Lotz
September 12, 1996
Overview
* Purpose
* Criteria and Technical Approach
* Industry Applications
L Cladding Temperature Methodologies
* Development of Methodology
* Benchmark Evaluations
* Findings and Conclusions
Civilian Radioactive WasteManagement SystemManagement & OperatingContractor
nimal.ppt 2 9/11/96
Purpose
* Effective Thermal Conductivity Reportdocuments methodology for predicting peakcladding temperatures
* Temperature limits maintain SNF cladding
- barrier (defense-in-depth) to radionuclide release
- maintain assembly geometry within waste package
* Open discussion of methodology with NRC
Civilian Radioactive Waste nfnml.ppt 3 9I11/9Management SystemManagement & OperatingContractor
Effective Thermal Conductivity
* Effective thermal conductivity methodologypredicts peak cladding temperatures withinany SNF container with a dry fill gas.
* Methodology provides a "best estimate" ofPWR and BWR cladding temperatures invarious container fill environments
* Applicable over the range of conditionsexpected in the potential repository
Civilian Radioactive Waste snfr~c .ppI 4 9/11/96
Management SystemManagement & OperatingContractor
0
Thermal Criteria for Disposal
U Drift wall temperature < 2000C
* SNF cladding temperature < 3500C
* Access drift temperature < 500C for 50 years afteremplacement
* Calico Hills and TSw3 rock temperature < 1 150C
* Ground surface temperature rise < 20C
- Maximize time WP above boiling consistent withthermal loading strategy
Civilian Radioactive WasteManagement SystemManagement & OperatingContractor
snnrCI.Wppt 5 911is8
Four Model Thermal Analysis Approach
aJr *a'-c -*
,. ... 1
,- .- - ,f
.. tt . .
i*: . v t,+ "Ig* 4. *. .L..t w
Repository DiskLong-Term Response
Due to Thermal Loading
Drift EmplacementProvide Time-Dependent
Boundary Conditionsfor Near-Field
to "' = - Pf
D0000 0 0 9@f :
DOOGOODO0OOO@@
1/4 SNF AssemblyPeak Cladding Temperatures
(Effective Conductivity)
Waste PackageIncorporate Specific Materials
and Design Configuration
.
Industry Applications* Demonstrate compliance with temperature
limits imposed on SNF to ensure claddingintegrity (by precluding creep rupture)
- Originally developed for waste packagethermal design (disposal)
- Applicable to any dry SNF canister(storage and transportation)
* Methodology supersedes previously used(and limited) empirical correlations (e.g.,Wooton-Epstein)
Civilian Radioactive Waste nrcl.ppt 7 9111s8
Management SystemManagement & OperatingContractor
Advantages to Industry.~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~0
* Effective thermal conductivity methodologyprovides best estimate of cladding temperatures
- Considers conductivity of fill gas (e.g., helium)
- Replace empirical approximation with increasedconfidence and known (appropriate) factor of safety
- Benefit to SNF container design capacity
* Calculation process is simple and benchmarked
Civilian Radioactive Waste snhrl.ppt a 9/11/96
Management SystemManagement & OperatingContractor
^ ls .
Cladding Temperature Methodologies
* Explicit model of every rod and heattransfer mechanism
Most accurate estimation (complex)Costly in setup and computational timeNot suited for parametric evaluation
- Empirical correlation (Wooton-Epstein)Limited range of applicability(horizontal PWR array in air)Multiple calculation steps (complex)
Civilian Radioactive Waste nf1nC.ppM 9 9/98Management SystemManagement & OperatingContractor
Waste Package Thermal Model UsingSNF Effective Thermal Conductivity
Intact Arrayof SNF Rods
SNF Assembly Modeledas a Smeared Heat
Source to AllowI I 7 More Modeling
Detail in the\&; > ..- \WP Internal
Structure
d .
If S
Cladding Temperature Methodologies (Continued)
* Effective thermal conductivity
Homogeneous SNF assembly
Conduction approximation of heat transfermechanisms
Use as part of SNF container thermal model
Benchmarked against SNF storage tests andexplicit models
Ideal for parametric evaluation and transients
Civilian Radioactive Waste srftrcl 11 919/96
Management SystemManagement & OperatingContractor I
Development of Methodology
* Detailed 1/4 assembly 2-D ANSYS model
* Multiple assembly geometries17x17, 15x15, and 14x14 PWRs9x9, 8x8, and 7x7 BWRsWith and without BWR channelsWith and without BWR water rods
* Helium, vacuum, nitrogen, and argon fillenvironments for horizontal SNF container
* Conduction and explicit thermal radiation
Civilian Radioactive Waste snfnrcl.ppt 12 9/996Management SystemManagement & OperatingContractor
.S I
ANSYS 5.1APR 8 1996
TemperatureDegrees C
Min =300Max =317
300301302
IMM 303F" 303r7'i 304EI 305arm 306I!M 307
!M 308P@! 308
309MS-- 310!!ff 311L ~J 312L__1 312EZJ 313ari 314
F" 315EP M, 316E!!M 317
Temperatures in17x17 PWR SNFAssembly withHelium Fill Gas
17x17 WE PWR SNF Assembly - 750 atts with 300 C Basket
ANSYS 5.1MAY 31 1996
TemperatureDegrees C
Min =250Max =261
250251251
SE!N 252PRk 252fl- 253l T] 253CT= 254Ew-9 254Aft- 255HP-q 256PWMI 256M!! 257
KV-91 257L l 258LIEl 258IZZI 259IarJ 259PEN 260OMw 261RIM 261
Temperatures in9x9 BWR SNFAssembly withHelium Fill Gas
9x9 BWR SNF w/80 mil Channel - 300 W w 250 C Basket a I d
I " 3 1
SNF Assembly Thermal Model Results* Evaluated over a parametric range:
25, 50, 100, 150, 200, 250, 300, 350, 4000C250, 500, 750, 1000 watts for PWRs100, 200, 300, 400, 500, 600 watts for BWRs
- Results indicate that detailed SNF model provides"best estimate" of cladding temperatures
* Cladding to basket temperature drop is non-linearfunction. of SNF basket temperature (due to radiationcomponent) and decay heat of assembly
* Alternate Wooton-Epstein calculation predicts abouttwice the temperature drop for helium fill gas
Civilian Radioactive Waste WfrC.pp" 15 91195Management SystemManagement & OperatingContractor
Calculation of Effective Thermal Conductivity
* Compare assembly model to a homogeneoussmearedmproperty heat-generating square
Use analytical solution of heat diffusion equationCalculate isotropic effective thermal conductivityPerform for each heat load and temperature case
* Define as a function of SNF basket temperaturefor use when SNF basket temperature is known
e Define as a function of SNF assembly mediantemperature for use in finite element (FEA) orfinite difference analyses
Civilian Radioactive Waste snfnhclppt 16 911/96Management SystemManagement & OperatingContractor
,. .
. .
PWR Effective Thermal Conductivities V I
1.6
1.4
E
0%Y-
E
0)
I-0
w
1.2
1.0
0.8
0.6
0.4
0.2
0.00 50 100 150 200 250 300 350 400
Assembly Median Temperature (Degrees C)
BY
E
*0c)
C0
0ci)
a)
c)04-0-ci
BWR (wI Channel) Effective Thermal Conductivities1.6
Recommended for Horizontal 9x9 BWRSNF Assembly with 80 mil Channel
1.4 ...1 .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . - - - - - - --.. . . . . . . .HeimFlGa
1.2.Calculated from BWR with:
Nitrogen Fill Gasr ........... Argon Fill Gas
0 .8 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .......................................... ......... .1.0 ~~~~~~~~~~~~Vacuum (No Fill) \
0.8 1
0.6 Calculated from0.6 .. . . . .. . . . .. . . . .. . . . .. . . .. . . . ..Wooton-Epstein
(9x9 in Air)\
0.4 . _
0 .2 .. ... .. .. . .... . . . . .. .. .. . . . . . . . . . . . . . . . .. . . . . .
0.00 50 100 150 200 250 300 350
Assembly Median Temperature (Degrees C)
400
t
6 '' e 0~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~& . 1 ;,
. , , . S
BWR (No Channel) Effective Thermal Conductivities1.6 _
1.4
se
CE
a).-
0
:=IL00
.-
w
1.2
1.0
0.8
0.6
0.4
0.2
0.00 50 100 150 200 250 300 350 400
Assembly Median Temperature (Degrees C)
Effective Conductivity Comparison for Helium1.6
1.4
IeE
.tC0
Ca
1.2
1.0
0.8
0.6
0.4
0.2
0.00 50 100 150 200 250 300 350' AnAd
a
Assembly Median Temperature (Degrees C)tv .
41 I -
Effective Conductivity Comparison for Nitrogen1.6
1.4
le
£
C).-
.0
00C)
I-0)
0
.-a)
'4-w
1.2
1.0
0.8
0.6
0.4
0.2
0.00 50 100 150 200 250 300 350 400
Assembly Median Temperature (Degrees C)
ANSYS 5.1MAY 24 1996
TemperatureDegrees C
Min =75Max =214
768389
PM 9766 103
. 110Fn 117
RN'" 124f!! 130Up 138MMt 145OM 151Ace 159ERF 165E~J 172Lii] 179Liii 186PFM 192MMt 200NM 206PMb 214
TN-24P Half CaskBenchmark,Horizontal withHelium Fill Gas.Assy. DI Guide TubeMeasured: 206.20CCalculated: 208.20C
24 PWR TN-24P Temperatures for Horizontal Helium Test C,. 4 '
"N
Findings and Conclusions
* Temperature-dependent SNF assemblyeffective thermal conductivities developed toprovide a simple method for calculating a"best estimate" of SNF peak claddingtemperature
* Benchmark results agreed with reported SNFstorage cask testing
* Reproducible calculation using an industrystandard code (ANSYS)
Civilian Radioactive Waste entm1.ppt 23 9,1/8Management SystemManagement & OperatingContractor