minutes of 53 - welcome to western regional power committee · chhattisgarh for computation of...

53

Upload: others

Post on 08-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 2: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied

Minutes of 53rd CCM held on 08.09.2009 at Mumbai

1

MINUTES OF 53rd MEETING OF COMMERCIAL COMMITTEE HELD ON 8TH

SEPTEMBER 2009 AT WRPC, MUMBAI The 53rd meeting of Commercial Committee was held on 8th April 2009 at WRPC

office, Mumbai. The list of the participants is enclosed at Annexure-I. Sh. Manjit Singh, Member Secretary, WRPC welcomed the participants and

requested Sh. S.G.Tenpe, Superintending Engineer (Commercial), WRPC to take up

the Agenda for discussion.

ITEM No.1: CONFIRMATION OF THE MINUTES OF THE 52nd MEETING OF COMMERCIAL COMMITTEE

Superintending Engineer (Comml.), WRPC stated that the Minutes of the 52nd

meeting of Commercial Committee held on 9th April 2009 at WRPC office, Mumbai

were circulated to the constituents vide WRPC letter No.WRPC/Comml-

I/2/CCM/Min/2009-3951 dated 22.04.2009. Comments have been received from

MSETCL vide letter dated 6th May 2009 (on Para-2 of Item No. 6.2 regarding

payment of service tax etc. He stated that the minutes as recorded in para 2 of item

6.2 in general conveys the points raised by MSETCL. He also stated that, this issue

is again slated for discussion as an Agenda Item for today discussion.

The matter was discussed and the Minutes of 52nd CCM were confirmed without any correction. ITEM No.2: TRANSMISSION CHARGES FOR TRANSMISSION OF POWER TO

DD & DNH THROUGH GETCO TRANSMISSION SYSTEM FOR THE PERIOD 01.04.2004 TO 31.03.2009

2.1 Superintending Engineer (Comml.), WRPC stated that Hon’ble CERC in

Petition No. 64/2008 and Petition No. 67/2008 in the matter of fixation of and

adjudication on the transmission charges for use of the Gujarat transmission system

for conveyance of central sector power to UT of DD and DNH respectively under

sections 62 and 79 of the Electricity Act, 2003 gave guidelines vide order dated 3rd

February 2009, for calculations for transmission of charges. The matter was finally

heard by the commission and the Commission issued the order on 31st July 2009 in

Page 3: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied

Minutes of 53rd CCM held on 08.09.2009 at Mumbai

2

respect of the above matter. The Commission hold the calculation of the

transmission charges by WRPC Secretariat is in order and directed that the charges

be applicable for the period 01.04.2004 to 31.03.2009. The charges shall be shared

in the manner decided in Commission’s order dated 03.02.2009, which provided that

the applicable transmission charges for conveyance of C.S. power to DD & DNH

shall be shared by all long term customers of WR in the same manner in the regional

assets of PGCIL. The details of transmission charges applicable as per CERC order

for the year 2004-05 to 2008-09 for GETCO transmission system is summarized

below:

Years Period Transmission

charges for transmission of

power to DD

Transmission charges for

transmission of power to DNH

Total Transmission

charges

(Rs. Lakhs) (Rs. Lakhs) (Rs. Lakhs) 2004-05 01.04. 04 to 31.03.05 434.01 751.31 1185.32 2005-06 01.04.05 to 31.08.05 175.52 336.01 511.53 01.09.05 to 31.03.06 94.75 181.41 276.16 2006-07 01.04.06 to 31.03.07 157.22 321.58 478.80 2007-08 01.04.07 to 29.02.08 141.73 302.37 441.10 01.03.08 to 31.03.08 22.12 47.18 69.30 2008-09 01.04.08 to 30.06.08 67.31 143.60 210.91 01.07.08 to 31.03.09 103.91 221.71 325.62

He informed that WRPC Secretariat accordingly revised the concerned statement of

monthly REAs for the year 2004-05 to 2008-09 based on above directions of Hon,ble

CERC in the matter and the provisional bills raised earlier for the above period will

be modified. 2.2 The Commission also directed that w.e.f. 01.04.2009 WRPC shall calculate

the charges payable for use of GETCO System in the same manner and shall be

shared by WR Constituents as decided earlier by order-dated 03.02.2009. The

parties are at liberty to approach the Commission for resolving disputes, if any

regarding calculation / payment of charges in accordance with law.

Accordingly, the calculation of applicable transmission charges for conveyance of

C.S. power to DD & DNH in respect of GETCO system for the period 01.04.2009 to

Page 4: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied

Minutes of 53rd CCM held on 08.09.2009 at Mumbai

3

31.03.2010 is under progress. In this context WRTS-I, PGCIL representative stated

that they have issued the differential bill and once the refund is received from

GUVNL, they will pass on the credit to other constituents.

GUVNL representative stated that GETCO is in process of preferring an appeal including staying of CERC order dated 31.7.2007. However, the Sub-Committee opined that in the absence of any other directives, the orders dated 03.02.2009 and 31.07.2009 issued by Hon’ble CERC in respect transmission charges payable to GETCO for conveyance of C.S. power to DD & DNH through GETCO system need to be followed.

ITEM No.3: BILLING OF TRANSMISSION CHARGES IN RESPECT OF GETCO / MSETCL FOR TRANSMISSION OF CENTRAL SECTOR POERT TO DD & DNH /GOA THROUGH THEIR TRANSMISSION SYSTEM

3.1 Superintending Engineer (Comml.), WRPC stated that during the 10th Meeting

of WRP Committee held on 30th May 2009 the matter regarding billing of

transmission charges for billing of C.S. Power to UT of DD & DNH was discussed

and it was decided that till such time, any order is given by the Hon’ble CERC in

respect of determination of transmission charges for GETCO System for wheeling of

C.S. power to DD & DNH, the present methodology of billing of transmission charges

through PGCIL should be continued and the same would facilitate adjustment /

recovery of transmission charges due, if any, as the entire record and billing details

are available with PGCIL. Thereafter, the billing of transmission charges in respect of

above should be done by GETCO / MSETCL directly, as per REA issued by WRPC.

He further stated that Hon’ble CERC vide order dated 31st July 2009 in respect of

fixation of and adjudication on the transmission charges for use of the Gujarat

transmission system for conveyance of C.S. power to Union Territory of DD & DNH

directed that the applicable transmission charges as per above order for conveyance

of power to DD & DNH shall be shared by all long term customers of WR in the same

manner as in respect of the regional assets of PGCIL. Also, the parties are at liberty

to approach the Commission for resolving disputes, if any regarding calculation /

payment of charges in accordance with law.

Page 5: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied

Minutes of 53rd CCM held on 08.09.2009 at Mumbai

4

3.2 Representative of MSETCL stated that the mechanism for payment of

transmission charges towards wheeling of C.S. power to Goa and UTs of DD & DNH

was earlier agreed on account of non-connectivity of their respective system with

ISTS network because it is the responsibility of CTU to arrange connectivity of the

beneficiaries system with ISTS to transmit C.S. power to beneficiary State of the

region. Therefore the present arrangement of billing of transmission charges in

respect of MSETCL / GETCO for transmitting C.S. power to Goa/DD&DNH through

PGCIL should be continued. GETCO/GUVNL and rest of WR constituents also

opined on the similar lines. Goa, DD and DNH also gave their consent to continue

with the present billing arrangement.

However, PGCIL representative stated that for continuing the existing practice of billing, some working arrangement along with necessary agreement with MSETCL and GETCO would be required to be in place. It was therefore suggested by the Commercial Sub-Committee that the matter may put up to TCC / WRPC for further directions. ITEM No. 4: ISSUES RELATED TO SCHEDULING AND PAYMENT OF UI

CHARGES IN RESPECT OF NSPCL 4.1 SCHEDULING OF NSPCL SHARE TO DD

4.1.1 Representative of UT of DD stated that the Long Term Open Access for

transfer of 220 MW power from 2x250 MW NSPCL station at Bhilai viz. 50 MW to

Chhattisgarh, 70 MW to UT of Daman & DIU and 100 MW to UT of DNH has been

granted by CTU. So far as transfer of power to Chhattisgarh is concerned, it was

indicated in the LTOA meeting that they would directly draw power from NSPCL

through exclusive dedicated 220 kV line from the project, as far transfer of total

power of 170 MW to DD and DNH from the above project, CTU had identified

strengthening scheme i.e. construction of 400 kV NSPCL-Raipur D/c line. The above

generator and 400 kV NSPCL-Raipur D/c line have since been commissioned and

NSPCL power is being scheduled to DD & DNH and the responsibility of scheduling

of NSPCL has been entrusted to Load Despatch, CSEB now, Chhattisgarh State

Power Transmission Co. Ltd.

Page 6: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied

Minutes of 53rd CCM held on 08.09.2009 at Mumbai

5

In the above context, on the basis of bills raised by NSPCL on DD and the schedule

issued by Load Despatch Centre, CSPTCL, Bhilai, DD vide letter dated 24th Aug. 09

(enclosed at Annexure-4.1) pointed out that Chhattisgarh is applying 4.03 % as

transmission loss on the ex-bus NSPCL schedule for calculating ex-Raipur schedule.

However as per the LTOA granted by CTU, DD power from NSPCL bus is to be

delivered through 400 kV dedicated NSPCL-Raipur D/c line and as such the

transmission loss to the extent of the above line needs to be made applicable by

Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The

transmission loss presently being applied by Chhattisgarh is very much on higher

side and needs to be corrected.

4.1.2 In this context, CSPTCL representative stated that responsibility of

scheduling, controlling, etc. in respect of NSPCL generating station falls under the

jurisdiction of Chhattisgarh and 4.03 % loss on ex-plant NSPCL declared schedule is

applied by them in respect of DD and DNH to arrive at schedule at Raipur i.e. the

delivery point.

NSPCL representative stated that while granting Long Term Open Access by CTU

for sale of power to Chhatisgarh – 75 MW, DD-70 MW and DNH-100 MW, the CTU

directed for construction of 400 kV NSPCL-Raipur D/c line for delivery of power to

DD and DNH upto the CTU point Raipur. Since, Chhattisgarh had to draw power

from their dedicated line no LTOA to CTU was envisaged for them. He further stated

that as DD and DNH are the specific beneficiaries of NSPCL, the transmission

charges in respect of 400 kV NSPCL-Raipur are to be borne by DD and DNH at

present. He opined that it would be more appropriate to apply transmission loss to

the extent of actual loss for 400 kV NSPCL-Raipur line.

WRLDC stated that this being a typical case, if DD and DNH are only required to pay

transmission charges in respect of NSPCL-Raipur line, the transmission loss to that

extent may be applied. However, looking at the control area jurisdiction for NSPCL,

STU loss is applicable. He added that had the control area of this station been with

WRLDC, the STU loss would not have been applicable. GUVNL representative

Page 7: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied

Minutes of 53rd CCM held on 08.09.2009 at Mumbai

6

stated that since the above station is under control of Chhattisgarh State, system

losses for STU should be applicable.

Superintending Engineer (Comml.), WRPC stated that as per the LTOA of 170 MW

viz. 100 MW to DNH and 70 MW to DD granted by CTU to NSPCL for delivery of

power to nearest CTU point Raipur, the CTU directed for construction of 400 kV

NSPCL-Raipur D/c line and Chhattisgarh State transmission network is not used for

delivery of this power from NSPCL station to Raipur, the nearest CTU connectivity

point. He further stated that the transmission loss which is to be estimated as per

CERC regulation is based on the transmission network used under the control area

of the authority which has been entrusted the responsibility of scheduling, controlling

and issue of UI accounts etc. He stressed that by changing the jurisdiction control

area from SLDC to RLDC or vice-versa, the transmission losses applicable for

arriving at the schedule for any entity at the specified delivery would not change. He

stated that 400 kV NSPCL-Raipur D/c line is not owned by CSPTCL. This is a

dedicated line from NSPCL generating station bus to Raipur line constructed for

transfer of 170 MW to DD and DNH, which are presently the beneficiaries of this

ATS. In view of the above, he opined that only transmission losses of 400 kV

dedicated NSPCL-Raipur D/c line should be applied by Chhattisgarh on NSPCL ex-

bus schedule for computation of ex-Raipur schedule in respect of DD and DNH and

request made by DD seems to be in order.

As no consensus could be arrived at despite of detailed deliberations, Member Secretary, WRPC requested CSPTCL to look into the matter to review the loss applicability provision in respect of NSPCL project specific beneficiaries under CSPTCL control area and intimate. In this context, CSPTCL representative agreed to discuss the matter with their management and would revert back.

4.2 NON RECEIPT OF UI CHARGES BY NSPCL FROM CHHATTISGARH

GM, NSPCL vide letter dated 21st July 2009 pointed out that the responsibility of

scheduling monitoring and issuance of UI account etc. in respect of NSPCL 500 MW

(2x250 MW) project at Bhilai comes under jurisdiction of Chhattisgarh. The weekly UI

account is required to be issued by SLDC, Chhattisgarh State Power Transmission

Page 8: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied

Minutes of 53rd CCM held on 08.09.2009 at Mumbai

7

Company Ltd. whereas, the payment if any, in respect of the same has to be made

by the Chhattisgarh State Electricity Distribution Company Ltd.. The Unit No.-1 at

NSPCL has been commissioned and declared in commercial operation. The coal

firing of Unit No.-2 was done on 28th March 2009 and yet to be declared on

commercial operation. NSPCL further pointed out that so for no payment has been

made by Chhattisgarh State Electricity Distribution Company towards UI charges in

respect of generating units of NSPCL to them.

NSPCL representative further stated that UI charges amounting to Rs. 70.79 Crores

(including accrued interest due to delayed payment) for infirm power account in

respect of NSPCL generating units for period from 5.1.09 to 21.4.09 has not yet

been paid by Chhattisgarh as per the infirm power provisional energy accounts for

the above period. Further no UI accounts have been issued by SLDC Bhilai since

22.4.09. UI payment towards injection of infirm power from Unit No. 2 is also over

due. He further stated that they have already filed Petition with Hon’ble CERC for

determination of tariff in respect of NSPCL station and the NSPCL could not finalise

its account for submission to CERC due to non disbursement of UI amount of 70.79

crores which is a serious matter. He reiterated that having given the responsibility of

scheduling, controlling, issuing of UI accounts etc. to LD, CSPTCL, Bhilai in

accordance with CERC order/regulation and acceptance of the same by LD,

CSPTCL, Bhilai, delay in issuing of UI accounts and non disbursement of its

payment is a matter of serious concern.

Member Secretary, WRPC stated that as per the provisions under the IEGC / CERC

Regulations, payment towards UI bill has to be accorded top priority and the matter

regarding non payment of UI charges is viewed seriously by the Hon’ble Commission

and therefore requested that CSPTCL may expeditiously look into the matter in

issuance of UI account and disbursement of due amount payable by the State to

NSPCL.

Representative of LD, CSPTCL, stated that the bill is already in process and payment to NSPCL will be made shortly. He also agreed that the UI bills for the remaining period will be issued shortly.

Page 9: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied

Minutes of 53rd CCM held on 08.09.2009 at Mumbai

8

ITEM No.5: WIDE AREA MEASUREMENTS SYSTEM OF WR

5.1 Superintending Engineer (Comml.), WRPC stated that in the TCC meeting of

WR held on 29th May 2009 at Diu the matter regarding Wide Area Measurement

System (WAMS) in WR, PGCIL made detail presentation on CSIR approved project

under their New Millennium India Technology Leadership Initiative programme

namely, “Intelligent monitoring & Control of the interconnected Power Grid using

Wide Area Measurements (WAM)”. The presentation was well received and

appreciated by the constituent members. However, as this project is of high/new

technology area, the TCC recommended that the technical details etc. of the project

may be discussed in a meeting of all the constituents of WR at working level and

thereafter the matter should be put up to TCC/ WRPC for further direction. The

matter was further deliberated in detail in the 10th meeting of WRP Committee held

on 30th May 2009 and the WRP Committee endorsed the decision of TCC. It was

decided that technical details of the project may be discussed in the Regional

Protection Committee meeting and hereafter the matter will be put up to TCC /

WRPC for further direction.

5.2 Accordingly, the matter was deliberated in the 105th meeting of Protection

Committee of WRPC held on 18th June 2009. In the meeting the features of the

WAMS project proposed by PGCIL and IIT –B were presented. The members

expressed that they would go through for examining the details and would intimate

their observations that views on the same etc. The comments were received from

MPPTCL, GETCO and MSETCL. The matter was further deliberated during 106th

meeting of Protection Committee of WR held on 1st & 2nd September 2009. In the

meeting, MSETCL also made presentation regarding the WAMS project taken up by

them in MSETCL Grid on pilot basis in association with CPRI - Banaglore and IIT-

Kanpur. The Protection Committee members felt that the WAMS project proposed by

PGCIL might require inclusion in the scheme, a facility to enable availability of PMU

data to WR constituents, which is not envisaged in the PGCIL proposal. In view of

above Sub-committee requested that PGCIL may furnish detailed break up of the

total cost estimates on the project, role of the agencies involved in the project,

identification of the location of the 25-30 PMUs proposed to be installed and

Page 10: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied

Minutes of 53rd CCM held on 08.09.2009 at Mumbai

9

clarification to queries relating to above aspect for discussion and recommendation

of the WAMS implementation proposed in the Western region.

Committee noted the same.

ITEM No. 6: SIGNING OF PPA WITH RGPPL AND ITS SCHEDULING

6.1 Superintending Engineer (Comml.), WRPC stated that MoP vide letter dated

24.01.2008 had allocated 5% capacity of RGPPL viz. 1.5 % each to DD & DNH and

1% each to Goa and Madhya Pradesh. In this context, the issues concerning

signing of PPA, opening of LC etc. and scheduling of 5 % allocated capacity from

RGPPL had earlier been discussed in CCM/WRP Committee meeting and RGPPL

was requested to take the matter with their management in expediting early signing

of PPA to enable scheduling of the above power to the concerned beneficiaries as

per MoP order.

6.2 In the TCC meeting held on 29th May 2009 at Diu, Special Secretary (P), UTs

of DD & DNH stated that though MoP had allocated power to the tune of 1.5 %

capacity of RGPPL each to DD and DNH about a year back, the scheduling of power

from RGPPL to them has not yet commenced. The matter was also deliberated in

the 10th meting of WRP Committee held on 30th May 2009 wherein RGPPL had

stated that the issue concerning allocation of 5% power from RGPPL by the MoP

was discussed in the RGPPL Board meeting held in Feb. 2009. He further stated

that in the RGPPL Board meeting it was decided that scheduling of 5 % power to

other states should be commenced only after the project reaches its full capacity.

Subsequently, this RGPPL Board decision was discussed in the review meeting

taken by Secretary (P), GoI and it was requested therein to keep the above

allocation in abeyance till the project commences generating at its full capacity. 6.3 In the above context, the beneficiaries of WR viz. DD & DNH, Madhya

Pradesh and Goa had unanimously stated in the 10th WRP Committee meeting that

no communication was received by them from MoP till date in this regard and as

such the allocation made to them out of 5% capacity from RGPPL stood applicable

as on date. They had therefore requested RGPPL to take urgent steps for

Page 11: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied

Minutes of 53rd CCM held on 08.09.2009 at Mumbai

10

scheduling of the above allocated power immediately. Representative of RGPPL had

stated therein that he would look into the matter and revert back.

Member Secretary, WRPC earnestly requested RGPPL to look into the matter as this is a long pending issue. In this context, representative of RGPPL stated that their Board was due to meet shortly and the matter would be placed before it. RGPPL agreed to inform the outcome of the same to DD, DNH, Goa & MP. ITEM No.7: PAYMENTS OF UI AND REACTIVE ENERGY CHARGES

As per the information received from WRLDC, the status of payment to UI pool

account and reactive energy account as on 08.09.09 i.e. upto week 17.08.09 to

23.08.09 of the current financial year is given below: -

UI Pool Account Reactive Energy Pool account

Constituents Dues Constituents Dues

Chhattisgarh (35,440,538) Chhattisgarh (6,326,286)Madhya Pradesh (46,927,023) Madhya Pradesh 1,307,206 Gujarat (22,063,221) Gujarat 5,773,988 Maharashtra (187,728,964) Maharashtra (3,055,300)Goa 17,621,998 Goa (2,450,199)Daman & Diu 28,621,807 Daman & Diu 211,925 Dadra & Nagar Haveli 491,550 Dadra & Nagar Haveli 717,232 NTPC (168,180,380) NR Exchange 470,250,105 SR Exchange (253,798,843) ER Exchange 717,850,562 Jindal Power (176,196,911) HVDC Vindhyachal (879,270) HVDC Bhadravati (5,036,201) Lanco Amarkantak (910,073,864) Mundra APL 220,845,175 Diff. due to capping (1,869,347,230) Addl. UI charges (454,031,455) Total (2,674,022,703) Total (3,821,434)

Figures in bracket ( ) are receivables from pool GUVNL stated that their due from UI pool is not fully paid. In this context, WRLDC

stated that about Rs. 47 Crores and Rs. 60 Crores due from NR and ER is

Page 12: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied

Minutes of 53rd CCM held on 08.09.2009 at Mumbai

11

outstanding and the WRLDC have already taken up the matter with them. GETCO

pointed out that payment of Rs. 67.31 lakh from DD and Rs. 65.37 lakh from DNH

towards Reactive Energy Charges is still awaited.

DD and DNH were however requested to make payment towards reactive energy

charges to GETCO at the earliest.

ITEM No. 8: DISBURSEMENT OF INTEREST CALCULATED ON LATE

PAYMENT OF UI CHARGES AND THE INTEREST EARNED ON DEPOSIT AMOUNT FOR UI IN IDBI BANK.

8.1 WRLDC vide letter dated 27th August 2009 stated that presently, the residual

interest with UI pool account, after payment to the interest receivable members, is

distributed to the UI interest receivable members as per their UI receivables for the

period for which interest is calculated. Also as decided in the 43rd CCM, interest

earned on deposit amount for UI in IDBI bank is distributed to all the UI receivable

members of UI pool accounts in proportion to their total receivables for the period

during which interest is earned.

8.2 As per the clause 9 of Central Electricity Regulatory Commission

(Unscheduled Interchange charges and related matters) Regulations, 2009 the

Commission directed that all payments on account of UI charges including additional

UI charges levied under the above Regulations and the interest received on late

payment thereof shall be credited to a Fund called the “Unscheduled Interchange

Pool Account Fund”, which shall be maintained and operated in accordance with

provisions of the Grid Code. Further, as per clause 11 of the Regulation, all the

amount left after final settlement of claims of Unscheduled Interchange charges of

the generating station and the beneficiaries, shall be utilized, with the prior approval

of the Commission. The relevant Clause-11 of the Regulation is reproduce below:

“11. Application of fund collected through UI- (1) The amount left after final settlement of claims of Unscheduled Interchange charges of the generating station and the beneficiaries shall be utilised, with the prior approval of the Commission, for either or both of the following activities:

(a) Servicing of investment for transmission schemes of strategic importance, Provided that the Central Transmission Utility in consultation with Central

Page 13: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied

Minutes of 53rd CCM held on 08.09.2009 at Mumbai

12

Electricity Authority shall identify the inter-State transmission schemes of strategic importance, not being utilised up to optimum level and seek prior approval of the Commission for servicing of capital costs during the initial years from amount left in the “Unscheduled Interchange Pool Fund” after settlement of claims of Unscheduled InterchangeCharges.

Provided further that when utilisation of such transmission line or transmission system included in the transmission schemes of strategic importance reaches the optimum level of utilisation, the cost of such scheme shall be recovered from the users of the scheme in accordance with the methodology specified by the Commission.

(b) Providing ancillary services including but not limited to ‘load generation balancing’ during low grid frequency as identified by the Regional Load Despatch Centre, in accordance with the procedure prepared by it, to ensure grid security and safety:

(2) The amount of fund, allocable for the purposes specified under clause (1), shall be decided by the Commission from time to time.”

WRLDC therefore proposed that from 1st April’2009 onwards the surplus amount generated through the interest earned through deposit amount for UI in IDBI bank and the residual interest after payment to UI interest receivables will be kept in the “Unscheduled Interchange Pool Fund”. Committee noted the same. ITEM No.9: RECONCILIATION OF UI AND REC ACCOUNTS WRLDC stated that as decided in Commercial Committee meeting, representatives

of constituent have to de reconciliation of UI and REC pool accounts maintained by

WRLDC. He stated that the reconciliation UI and REC accounts for the period April

2008 to March 2009 is required to be done and all constitutes vide letter No.

WRLDC/OS/1541/09/1157 dated 17.6.2009 were requested to inform suitable dates

for reconciliation. So far only MSEDCL, NTPC and D&D has completed the

reconciliation process and the same to be done all other UI and REC pool members.

WRLDC proposed to complete the reconciliation process by 30th Sep. 2009. The

constituents’ members requested WRLDC to extend the date up to 15th October

2009 and WRLDC agreed to the same.

Page 14: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied

Minutes of 53rd CCM held on 08.09.2009 at Mumbai

13

Member Secretary, WRPC requested the constituents to send their representative to

WRLDC and complete the reconciliation of UI and REC account for the above period

latest by 15th Oct. 2009.

ITEM No.10: NON RECEIPT OF SEM DATA FROM VARIOUS LOCATIONS WRLDC stated that the SEM data from following locations are not received at

WRLDC for the past few weeks. The non receipt of data for each week is given in

the Annexure of weekly UI accounts issued by WRPC. It was decided in the 51st

CCM that, no separate communication will be sent from WRLDC and the

constituents should take prompt actions in ensuring the transmission of weekly SEM

data to WRLDC.

(a) GETCO - Both Mundra (220kV) and Nanikhakar (220kV) for 220kV

Nanikhakar-Mundra line

(b) MSEDCL- Akola, Kolahapur (400kV)

(c) MPPTCL- Gandhi Sagar, Malanpur (sent by Friday evening), Mehgaon (sent

by Friday evening)

The concerned constituents were requested to ensure the same. ITEM No. 11: GRANTING OF LTOA FOR ISTS BY CTU

Superintending Engineer (Comml.), WRPC stated that as per the communication

received from General Manager (Engg.), PGCIL, Long Term Open Access for

interstate transmission system has been granted in case of the following:

(i) LTOA for evacuation power from generation projects in Orrissa viz. Sterlite

Energy Ltd., GMR Kamalanga Energy Ltd., Navabharat Power Private

Ltd., Monnet Power Company Limited, Jindal India Thermal Power Ltd.

and Lanco Babandh Power Pvt. Ltd., issued vide PGCIL letter No.

C/ENG/E/00/SEF/OA dated 29.04.2009. Details enclosed at

Annexure-11.1.

(ii) LTOA for evacuation power from Farakka-III generation project of NTPC

Ltd. issued vide PGCIL letter No. C/ENG/E/00/SEF/OA dated 21.05.2009.

Details enclosed at Annexure-11.2.

Page 15: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied

Minutes of 53rd CCM held on 08.09.2009 at Mumbai

14

(iii) LTOA for evacuation of power from generation project in Sikkim. viz. PTC

India Ltd.for Teesta Urja Ltd., Lanco Energy Pvt. Ltd., DANS Energy Pvt.

Ltd., Jal Power Corporatioin Ltd., TT Energy Pvt. Ltd., Shinga Energy Pvt.

Ltd., Madhya Bharat Power Corporation Ltd., Gati Infrastructure Ltd. and

Gati Infrastructure Bhasmay Power Pvt. Ltd. vide PGCIL letter No.

C/ENG/E/00/SEF/OA dated 26.05.2009. Details enclosed at

Annexure-11.3.

(iv) LTOA to Heavy Water Board from KAPP issued vide PGCIL letter No.

C/ENG/SEF/W/06 / HWB dated 30.06.2009. Details enclosed at

Annexure-11.4.

(v) LTOA for evacuation of power from generation projects in A.P. viz.

Simhapuri Energy Pvt. Ltd., PTC India Ltd. (Meenakshi), A.P. Power

Development Co.Ltd. & Krishnapatnam Power Corp. Ltd. vide PGCIL

letter No. C/ENG/SEF/ TA/L/S/09/001 dated 6th July 2009. Details

enclosed at Annexure-11.5.

(vi) LTOA for evacuation of power from the generation projects of Lanco

Kondapalli Power Private Ltd, Andhra Pradesh vide PGCIL letter No.

C/ENG/SEF/TA/L/S/09/001 dated 6th July 2009. Details enclosed at

Annexure-11.6.

(vii) LTOA for evacuation of power from Nabinagar generation project of

Bhartiya Rail Bijalee Company Ltd. vide PGCIL letter No.

C/ENG/SEF/TA/L/E/09/002 dated 24th July 2009. Details enclosed at

Annexure-11.7.

(viii) LTOA for evacuation of power from generation projects in Chhattisgarh

viz. Maruti Clean Coal and Power Ltd., PTC India Ltd. (Dheeru) and

Dheeru Powergen Pvt. Ltd., and in Madhya Pradesh viz. Jaiprakash

Power Ventures Ltd. & Aryan Coal Benefications Pvt. Ltd., vide PGCIL

letter No. C/ENG/SEF/TA/L/W/09/001 dated 29th July 2009. Details

enclosed at Annexure-11.8.

The state utilities of WR have been intimated vide WRPC letter No. WRPC/Comml. -

I/4/Corr./2009 dated 28th August 2009. Committee noted the same.

Page 16: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied

Minutes of 53rd CCM held on 08.09.2009 at Mumbai

15

ITEM No. 12: ALLOCATION OF POWER FROM SUBANSIRI HEP (2000 MW) OF

NHPC AND KAMENG HEP (600 MW) IN ARUNACHAL PRADESH Superintending Engineer (Comml.), WRPC stated that MoP vide letter No.

11/1/2002/DO(NHPC) dated 14th July 2009 intimated that allocation of Subansiri,

HEP (2000 MW) and Kameng, HEP (600 MW) to the constituents of NER, NR and

WR. From Subansiri, HEP Western Region allocation is 25% equivalent to 500 MW

whereas, the allocation from Kameng, HEP is 25% equivalent to 150 MW. The

details are as under:-

S.No. States Allocation in %

Equivalent Power in MW from

Subansiri HEP

Equivalent Power in MW from

Kameng HEP 1. Gujarat 32.39 162 48 2. M.P. 21.10 105 32 3. Chhattisgarh 8.44 42 13 4. Maharashtra 36.55 183 15 5. Goa 1.52 8 2

Total 100.00 500 150 Committee noted the same. ITEM No. 13: AUTOMATIC METER READING SOLUTIONS BY M/S BPL WRLDC vide their letter dated 3rd Sept. 09 (copy enclosed at Annexure-13) have

stated that M/s BPL has developed an Automatic Meter Reading (AMR) solution for

downloading and transmitting the data from remote locations to RLDCs. The main

feature of this solution is that the data will be automatically read from the meter and

transmitted to RLDC. WRLDC added that M/s BPL have developed the output text

file exactly similar to one created by M/s SML and M/s L&T using their software

“SMARTGRID and “VINCOM” respectively and have given three different types of

architectures to download and transmit the data from remote location to respective

RLDC.

WRLDC further stated that a pilot project has been given to M/s BPL by WRTS-I,

PGCIL, Nagpur, to connect few meters at 400 kV Seoni S/s for one month with

required interface unit so that complete system can be verified for few weeks before

Page 17: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied

Minutes of 53rd CCM held on 08.09.2009 at Mumbai

16

it can be accepted completely. WRTS-I, PGCIL agreed to take up the responsibility.

As per the detailed budgetary proposal received from M/s BPL, the total cost for 531

Nos. SEMs (405 SML make and 126 L&T make), spread over 92 locations, comes

out to Rs. 77.73 Lakhs assuming that dedicated PCs are available in all these

locations. In addition to above, cost of TA/DA of PGCIL employee will also have to

be borne by the constituents. WRLDC proposed to share the cost of this project in

the same manner the cost of SEMs are shared. WRLDC also stated that M/s BPL

have agreed to take up this project at few 3 or 4 locations free of cost in the Western

Region.

The matter was deliberated in detail and the committee members unanimously opined that the above project may be initially taken at few 3 or 4 locations in the Western Region free of cost and based on the experience the decision for implementing the same for all locations will be taken later on. WRLDC suggested Asoj, Koradi or Kolhapur, Korba(W) and Bina or Bhopal locations can be initially taken up by M/s BPL to start the project. Constituents agreed to the same. The Sub-committee also suggested WRLDC to approach other developers in this project.

ITEM No. 14: DYNAMIC POWER SYSTEM STABILITY MONITORING SYSTEM

Superintending Engineer (Comml.), WRPC stated that during 52nd of Commercial

Committee held on 9th April 2009, WRLC made proposal regarding installation of

Dynamic Power System Stability Monitoring System of M/s. A-Eberle Systems Pvt.

Ltd., at few locations in WR. The Committee decided the WRPC will make necessary

presentation to the Protection Committee of WRPC for further action. It is understood

that M/s A-Eberle Systems Pvt. Ltd. made presentation during 105th meeting of

Protection Committee and the response is awaited from the Protection Committee.

WRLDC requested to expedite the response from Protection Committee to enable further course of action. ITEM No. 15: TIME CORRECTION OF SEMs WITH GPS SIGNAL WRLDC stated that time on analysis of SEM data, time drift have been noticed in

many SEMs at various locations in Western Regions. Though NTPC and NPC

Page 18: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied

Minutes of 53rd CCM held on 08.09.2009 at Mumbai

17

stations are carrying out time correction of SEMs installed at their locations on

regular basis, the same need to done by other constituents as well. WRLDC

requested that all the concerned to give necessary instructions to their respective

locations for monthly checking of SEMs for any time drift and incase of any drift, it

same may be rectified with intimation to WRLDC.

Committee members agreed to the same. ITEM No. 16: CONTROL AREA FOR SCHEDULING METERING ETC. IN

RESPECT OF MUNDRA POWER PROJECT DEVELOPED BY M/S. APL

Superintending Engineer (Comml.), WRPC stated that Chief Engineer (SLDC),

GETCO vide letter No. GETCO/SLDC/1184 dated 7th Sept. 2009 gave the following

Agenda Items concerning Mundra Power Project being developed by M/s Adani

Power Limited:

(a) Control Area for scheduling , metering and accounting of 4620 MW project.

(b) SEM data submission of 220 kV Nanikhakar-Mundra line to WRLDC.

(c) Short Term Open access permission granted to M/s APL

In view of above, WRPC vide letter dated 7th Sept. 09 invited M/s APL to participate

in this Commercial Committee meeting. In response, M/s APL vide letter No.

APL/CEA/070909 dated 7th Sept. 09 stated that due to short notice they will not be in

a position to attend this meeting. M/s APL further intimated that they had a meeting

with GETCO and GUVNL on 3rd Sept. 09 and the minutes of which are yet to be

finalized/issued. M/s APL requested that discussions on the Agenda points proposed

by GETCO vide letter dated 7th Sept. 09 may be taken up later so that the

discussions held in their meeting with GETCO/GUVNL on 3rd Sept. 09 are duly

considered and they will also able to attend the same

GETCO and GUVNL representative agreed to the same. Accordingly the agenda points proposed by GETCO vide letter dated 7th Sept. 09 related to Mundra Power Project developed by M/s APL could not be discussed by the Sub-committee.

Page 19: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied

Minutes of 53rd CCM held on 08.09.2009 at Mumbai

18

ITEM No. 17: DATE AND VENUE OF NEXT MEETING It was decided to hold next meeting of CCM (54th ) in Nov./Dec. 09. The date and

venue will be intimated separately.

The meeting ended with vote of thanks to the Chair.

* * * * *

Page 20: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied

Minutes of 53rd CCM held on 08.09.2009 at Mumbai

19

Annexure - I

LIST OF PARTICIPANTS FOR 53rd CCM OF WRPC HELD ON 08TH SEPTEMBER, 2009 AT MUMBAI

I GUJARAT URJA VIKAS NIGAM LIMITED

Shri P.J. Jani, Executive Engineer

II GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED Shri M. M. Chaudhari, Dy. Engineer

III MADHYA PRADESH POWER TRADING COMPANY LTD. Shri K. K. Agrawal, Superintending Engineer IV CHHATTISGARH STATE POWER DISTRIBUTION CO.LTD

None

V CHHATTISGARH STATE POWER TRANSMISSION CO.LTD Shri Girish Gupta, Executive Engineer (LD)

VI MAHARASHTRA STATE ELECTRICITY DISTRIBUTION CO. LTD Mrs. Rama Nair, Executive Engineer (PP) Mr. T. S. Basu, Executive Engineer (PP)

VII MAHARASHTRA STATE ELECTRICITY TRANSMISSION CO. LTD Shri V.T. Firke, Sonsulting Superintending Engineer Shri B.H.Gujrathi, Executive Engineer,SLDC Shri A. R. Kulkarni, A.E Shri U. S. Bhagat, A.E VIII ELECTRICITY DEPARTMENT, GOA

Shri B. Nigalye, Assistant Executive Engineer (IPM) IX ELECTRICITY DEPARTMENT, DAMAN & DIU.

Shri M. R. Ingle, Executive Engineer X ELECTRICITY DEPARTMENT, DADRA & NAGAR HAVELI. Shri P. S. Dave, Executive Engineer XI POWERGRID CORPORATION OF INDIA LTD.

Shri M. G. Raoot, Executive Director, WRLDC Shri P Pentayya , Addl. General Manager (OS), WRLDC Shri C. M. Verghese, Addl. General Manager (Comml), WRTS-I Mrs. S. Usha, Manager (OS), WRLDC Mrs. S. Pushpa, Manager (OS), WRLDC

Page 21: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied

Minutes of 53rd CCM held on 08.09.2009 at Mumbai

20

XI NATIONAL THERMAL POWER CORPORATION LTD. Shri Guryog Singh, AGM, CC. Shri B. P. Parida, AGM, WRHQ Shri H. Harchandani, DGM (Comml.), WRHQ Shri K. M. K. Prusty, DGM, WRHQ.

XII NUCLEAR POWER CORPORATION OF INDIA LIMITED None

XIII NARMADA CONTROL AUTHORITY None XIV NTPC SAIL POWER COMPANY LIMITED Shri G. Basu, General Manager Shri P. K. Dutta, Dy. General Manager XV RATNAGIRI GAS POWER PVT. LTD. Shri J. K. Baghel, AGM Shri B. M. Gulati, DGM (Comml) Shri Hemant Shinde, Dy. Manager XVI PTC INDIA LIMITED

None XVII WESTERN REGIONAL POWER COMMITTEE

Shri Manjit Singh, Member Secretary Shri S. G.Tenpe, Suptdg.Engineer (Comml) Shri O. P. Singh, Suptdg.Engineer (Operation) Shri M. R.Singh, Suptdg.Engineer (Protection) Shri M. M. Dhakate, Executive Engineer (Comml.-I) Shri Satyanarayana, Executive Engineer (Protection) Shri D. N.Singh, Executive Engineer (Comml-II) Shri K. Shanmughan, Asst. Director-II (Comml-I)

Page 22: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Shanmughan k
Text Box
Annexure- 4.1
Page 23: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 24: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 25: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 26: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 27: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 28: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 29: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 30: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 31: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 32: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 33: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 34: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 35: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 36: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 37: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 38: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 39: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 40: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 41: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 42: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 43: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 44: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 45: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 46: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 47: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 48: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 49: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 50: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 51: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 52: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied
Page 53: Minutes of 53 - Welcome to Western Regional Power Committee · Chhattisgarh for computation of ex-Raipur schedule in respect of DD and DNH. The transmission loss presently being applied