mgsc ibdp: optimization of surface facilities...inspection and maintenance 5 service valves, piston...
TRANSCRIPT
TRIMERIC CORPORATION
Presented at Midwest Carbon Sequestration Science Conference on 9/18/12
Presented by:
Ray McKaskle, P.E. Trimeric Corporation
MGSC IBDP: Optimization of Surface Facilities
TRIMERIC CORPORATION
Presentation Overview
p Equipment Design, Installation, and Operation
p Equipment Performance p Lessons Learned p System Improvements p Relationships Between Surface and
Downhole Conditions p Summary p Acknowledgements
9/18/12 2
TRIMERIC CORPORATION
Design Basis and Permit Conditions Summary
Note – Values above are for normal operating conditions, startup, testing, and shutdown conditions may vary
Parameter Units Design
Requirement UIC Permit
Requirement
Injection Rate tonne / day 250 - 1,000 < 1,200 Injection Rate MMscfd 4.8 - 19.0 Flow Control % of set point + / - 10 Surface Pressure psig 1,057 - 2,000 < 1,950 Surface Temp. deg F 88 - 120 60 - 150 CO2 Purity % mol. > 99 Oxygen Content ppm < 100 Water Content lb / MMscf < 30 Water Content ppm < 633
9/18/12 3
TRIMERIC CORPORATION
Block Flow Diagram
9/18/12 4
TRIMERIC CORPORATION
Overall Process Flow Diagram
9/18/12 5
TRIMERIC CORPORATION
CO2 Source: Fermenter Wet Scrubber Discharge
9/18/12 6
TRIMERIC CORPORATION
Blower and Compressor Buildings
9/18/12 7
TRIMERIC CORPORATION
Blower System
9/18/12 8
TRIMERIC CORPORATION
Reciprocating Compressors
9/18/12 9
TRIMERIC CORPORATION
Interstage Coolers
9/18/12 10
TRIMERIC CORPORATION
Dehydration System - Contactor
9/18/12 11
TRIMERIC CORPORATION
Dehydration System – Regeneration Skid
9/18/12 12
TRIMERIC CORPORATION
Final Cooler
9/18/12 13
TRIMERIC CORPORATION
Multistage Centrifugal Pump
9/18/12 14
TRIMERIC CORPORATION
Injection Well
9/18/12 15
TRIMERIC CORPORATION
Actual Injection Rate vs. Date
9/18/12 16
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
11/3/11 12/3/11 1/2/12 2/1/12 3/2/12 4/1/12 5/1/12 5/31/12 6/30/12 7/30/12 8/29/12 9/28/12
Daily In
jection Ra
te (ton
ne/day)
TRIMERIC CORPORATION
Causes for Unscheduled Downtime
Item
Reduced Rate Days
Down Days Comment
Blower Motor 2 13 Motor Wiring (Warranty Issue) (8 days) Oil Leak Led to Bearing Failure (7 days)
Cylinder Lube Oil Systems 14
Replaced Pumps with New Design and Corrected Wiring Issues Jul. 2012
Motor Soft Starter 8 Initial Construction Wiring Issues Operating Limits 5 Press., Temp. and Level Limits
Equipment Related Totals 29 13
Data from 11/8/11 – 9/10/12
9/18/12 17
TRIMERIC CORPORATION
Causes for Scheduled Downtime
Item
Reduced Rate Days
Down Days Comment
Scheduled Preventive Maintenance 2 6 Compressor Hardware Inspection and Maintenance 5
Service Valves, Piston Rods, Seals, etc.
Equipment Related Totals 7 6
Data from 11/8/11 – 9/10/12
9/18/12 18
TRIMERIC CORPORATION
Downtime Due to External Factors
Item
Reduced Rate Days
Down Days Comment
Well / Instrument Testing 14 4
Includes Step Rate and Shut In Tests, Well Logging, Instrument Calibrations
Utility / Source Outage 5 1
Includes CO2 Supply, Power, Cooling Water Outages or Shortages
External Factor Totals 19 5
Data from 11/8/11 – 9/10/12
9/18/12 19
TRIMERIC CORPORATION
Oxygen Content During Injection
9/18/12 20
0
10
20
30
40
50
60
70
80
90
100
11/3/11 12/3/11 1/2/12 2/1/12 3/2/12 4/1/12 5/1/12 5/31/12 6/30/12 7/30/12
O2 co
ncen
tration, ppm
v
TRIMERIC CORPORATION
Water Content During Injection
9/18/12 21
0
5
10
15
20
25
30
11/3/11 12/3/11 1/2/12 2/1/12 3/2/12 4/1/12 5/1/12 5/31/12 6/30/12 7/30/12
H2O con
centratio
n, lb
H2O
/ M
Mscf
Moisture analyzer was out of service due to upstream regulator failure
TRIMERIC CORPORATION
Performance Metrics
Performance Metric Status
Inject 333,333 tonne / year Injection to date equates to 312,806 tonne /
year, which is 94% of goal Water content
(typical 7 lb/MMscf, spec. 30 lb/MMscf)
Average 5 lb/ MMscf Max 10 lb / MMscf
1-sigma Standard Deviation 1 lb / MMscf Oxygen Content (typical 7 ppmv, spec. 100 ppmv)
Average 7 ppmv Max 93 ppmv
1-sigma Standard Deviation 7 ppmv
9/18/12 22
TRIMERIC CORPORATION
Lessons Learned
p Temperature control for cooling water supply may be required to keep control cooling water return temperatures at acceptable levels in cold weather
p Pipeline insulation was needed due to concerns with downhole pressure variations induced by ambient temperature and weather variations
p Even after insulating pipeline, variations in surface injection temperature due to cooling water temperature variations caused undesirable variations in downhole pressure
9/18/12 23
TRIMERIC CORPORATION
System Improvements and Optimization (1 of 2)
p Blower recycle valve is now used in addition to blower vent valve in response to high blower discharge pressure
p Interstage cooling temperature set points lowered to reduce power consumption and cooling water return temperatures
p Low pressure shutdowns on reciprocating compressors replaced with differential pressure shutdowns to reduce nuisance trips
p New type of cylinder lubrication pumps installed and wiring issues corrected. Further improvements are in progress.
9/18/12 24
TRIMERIC CORPORATION
System Improvements and Optimization (2 of 2)
p Tuning dehydration reboiler fuel gas valve and reducing reboiler temperature set point have reduced fuel consumption
p Pipeline insulation added to stabilize injection temperature in order to reduce downhole pressure variations previously caused by changes in ambient temperature and weather
p Raised temperature set point for CO2 leaving final cooler to a value that can be sustained even when cooling water supply temperatures are high
9/18/12 25
TRIMERIC CORPORATION
Possible Future Improvements and Optimization
p Temperature control for cooling water supply may be required to keep control cooling water return temperatures at acceptable levels in cold weather
p Heat exchangers may need to be taken out of service for cleaning in 2013
p Multistage pump may be used to sustain desired injection rates in future years if cooling water supply temperatures are high, if heat exchanger performance degrades, or if resistance from formation increases
9/18/12 26
TRIMERIC CORPORATION
Surface vs. Downhole Before Insulation
0
20
40
60
80
100
120
3000
3050
3100
3150
3200
3250
3300
3350
3400
3450
3500
1/11/12 12:00 1/12/12 0:00 1/12/12 12:00 1/13/12 0:00 1/13/12 12:00 1/14/12 0:00
Tempe
rature, d
eg F
Pressure, p
sig
Downhole Press Surface Injection Temp CWS TempAmbient Temp Final Cooler Temp
9/18/12 27
TRIMERIC CORPORATION
Surface vs. Downhole After Insulation
9/18/12 28
65
70
75
80
85
90
95
100
105
3100
3150
3200
3250
3300
3350
3400
3450
3500
7/2/12 0:00 7/2/12 12:00 7/3/12 0:00 7/3/12 12:00 7/4/12 0:00
Tempe
rature, d
eg F
Pressure, p
sig
Downhole Press Surface InjectionTemp CWS TempAmbient Temp Final Cooler Temp
TRIMERIC CORPORATION
Summary
p The compression and dehydration system performs in accordance with process design requirements
p Blower motor failures and cylinder lubrication system issues were the leading causes of unscheduled downtime
p Control of surface injection temperature has proven to be important to reduce downhole injection pressure variations
9/18/12 29
TRIMERIC CORPORATION
Acknowledgements
p Department of Energy – Darin Damiani and John Litynski
p Illinois State Geological Survey – Rob Finley and Scott Frailey
p ADM – Kevin Burris and Tom Stone
p Schlumberger Carbon Services – Scott Marsteller and Jim Kirksey
p Enerflex – Bill Strahan
p Trimeric – Kevin Fisher, Rosalind Jones, Joe Lundeen, and Brad Piggott
9/18/12 30