River Improvement METHOD STATEMENT Project Name : Wonokromo River Improvement Surabaya (Wonokromo) Sub Project (Package-3) Province : East Java Bidder Name : PT. BRANTAS ABIPRAYA (Persero) GENERAL Generally, all construction of Wonokromo River Improvement Surabaya (Wonokromo) Sub Project (Package-3), Surabaya (Wonokromo River) Sub Project (Package-3), east Java at construction begin, during construction and finish, contractor will follow procedure / protocol which apply and have been specified in Wonokromo River Improvement Surabaya (Wonokromo) Sub Project (Package-3) environment, JICA’s procedures and Republic of Indonesia’s rules as specially. 1. IDENTIFICATION 1.1. Location & Access Road The site is located in Wonokromo, East Java, Indonesia. Project Location ZOOM Location Site

Upload: doanminh

Post on 22-Feb-2018

214 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

River Improvement

METHOD STATEMENT Project Name : Wonokromo River Improvement Surabaya (Wonokromo) Sub Project (Package-3) Province : East Java Bidder Name : PT. BRANTAS ABIPRAYA (Persero)

GENERAL Generally, all construction of Wonokromo River Improvement Surabaya (Wonokromo) Sub Project

(Package-3), Surabaya (Wonokromo River) Sub Project (Package-3), east Java at construction begin, during construction and finish, contractor will follow procedure / protocol which apply and have been

specified in Wonokromo River Improvement Surabaya (Wonokromo) Sub Project (Package-3)

environment, JICA’s procedures and Republic of Indonesia’s rules as specially.

1. IDENTIFICATION 1.1. Location & Access Road

The site is located in Wonokromo, East Java, Indonesia.

Project Location

ZOOM

Location Site

Page 2: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

River Improvement

PLAN BY SATELITE

PROVICE OF EAST JAVA

Indonesia

Notes; - Image on below isn’t as real condition of Project location in this time

(condition at Tender time) - Image on below only as mark of project location will be constructed

PROJECT LOCATION

Page 3: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

River Improvement

ZOOM

Wonokromo River

Project Start

End Project

Location Plan of Base

Camp

Page 4: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

River Improvement

1.1.1. Existing Roads and Transportation Facilities Access to the Site can generally be achieved via the network of public roads and streets

in the vicinity of Site.

The Contractor will use the existing road for the works.

The Contractor shall fully inform himself of the conditions of roads, traffic conditions and traffic regulations with respect to gaining access to the Site for the purposes of

performing the Works and shall take all necessary actions to ensure availability of access to the Site as required.

1.2. Planning of Work

1. With Location Site are spread, Construction will be constructed as Frontal, mean that

construction at 1 location does not connections with others, only Equipment that connections. Each Location site will use Equipment.

Flow Chart

FINISH

CCSP

(2 Group)

Construction (North and South River)

Road Work (1 Group)

Construction (South River)

START

Earth Work & Demolising)

(1Group)

RC

Pile+Parapet (2 Group)

Construction (North and South River)

Construction

Dike Foot Protection (1Group)

Rivetment

(2 Group)

Construction (North and South River)

Earth Work (embankment)

Construction (North and South River)

Earth Work (embankment)

Construction (South River)

Construction (North and South River)

Earth Work (Excavation of

River Bank)

Page 5: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

River Improvement

WORK DIRECTION Usually, Construction in the River Will Be Construction From Upstream River up to

Downstream River

Work Direction

Page 6: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

River Improvement

2. Scope Of Works 2.1. Project Description:

Wonokromo River Improvement Surabaya (Wonokromo) Sub Project (Package-3).

Civil Works Package 3;

Construction of civil work for Channel improvement such as concrete sheet pile, channel excavation, embankment, and parapet in the middle reach of Wonokromo River From Nginden

Intan Bridge to Meandering Section of Whick length 3,950 meter

Time for Completion is 730 days and Defects Notification Period is 180 days

The main elements of the Works to be completed under this package shall consist of, but not

be limited to, the following: 2.1.1. Earth Works;

- Excavation Common Soil for Structure by Machinery - Excavation Common Soil for Structure by Man Power

- Hauling of Excavation Material

- Compacted Back Fill - Embankment Works from Borrow Area

- Sodding

2.1.2. CCSP and Revetment - CCSP CCSP, Tie Rod and Capping Beam Detail in CONSTRUCTION METHOD FOR

CCSP

Geotextile Sheet Sand Embankment

Lean Concrete K100, t=10 cm Cyclopean Concrete K175, (with thickness as according to the Drawing

- Riverment Earth Work (will be detail on CONSTRUCTION METHOD FOR EARTH WORK)

Drainage with Wet masonry Lean concrete K100, t=10cm

Reinforced Concrete K225, t=20cm Concrete Block 30x30x10, K 175

2.1.3. Parapet: - Preparatory Works

- RC Pile 20x20 - Concrete (Class as according to the Drawing and BQ)

- Reinforcing Steel

- Masonry 1:4 and PVC Hole Ø 2” - Geotextile

- Gabion - Etc

2.1.4. Road:

- Fence

Preparatory Works Wet Masonry

Plastering Concrete (Class as according to the Drawing and BQ)

Reinforcing Steel

Steel Galvanis Pipe Wire Mesh Fence

- Road Preparatory Works

Page 7: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

River Improvement

Sand & Precast Concrete Curb

Sand and Precast Concrete Tile

2.1.5. Other Works: - Works Item as according to BQ and To the Drawing

3. Equipments List of Minimum Equipments required for Construction (upon request tender documents)

Equipment Type

and Characteristic / Capacity

Minimum Number of Units

Excavator with capacity 0,75 m³ 2 ( Two )

Pontoon with capacity more than 70 ton 2 ( Two )

Dump Truck – Cap. 11 ton 10 ( ten )

Truck Mixer with capacity 4.2 m³ 4 ( Four )

Crawler Crane with with Vibratory Hammer with capacity more than 50 ton

2 ( Two )

Crawler Crane with capacity more than 25 Ton 2 ( Two )

Bulldozer with capacity 0.75 m³ 2 ( Two )

Water Jet Equipment for Driving 1 ( One )

Work equipment used (type, number and capacity) is actually in accordance with Attachment of "List

Of Construction Plant " which is an integral part of the Bid Documents

4. TECHNICAL CONCTROL / SITE MANAGEMENT and TRAFFIC MANAGEMENT

TECHNICAL CONCTROL

Technical Control is a process of activities performed to ensure the results of work in accordance in

the contract documents. Result and Quality will be realized in the form of Premary hand Over Certificate (PHO) Final Hand Over (FHO).

In Technical Control, Before – During – After (Begining – Process construction – Finish), as according

to; 4.1. Work Contract

Work Contract, Bill of Quantity, Tender Drawing, Technical Specifications, payment procedures

and measurements, Addendum Contract (if any). And reference the Technical Regulations Construction and procurement of construction,

4.2. Engineering

Activities include and are not limited to the measurement / calculation, checking of Work Site,

Approved of Shop Drawing and As built Drawing and approval of construction materials, documentation, Quality Control Plan (QCP), test, inspection and checks for Construction.

Process of approval and the procurement of materials, regulations and Determined Permit as requirements.

4.3. Construction Management This Construcstion Management is Managed by Project manajement that consist of main

Personal. Team of Project management will draft of Construction Stage refers to Stage Construction in the Contractr document. Next, based of Stage / Sequence Construction will be

made Construction Method as Payment Item as Bill of Quantity. It was to get how to effective and effcient based on Existing site and Controlling risk during contruction until Finish

4.4. Site Management This activity is an arrangement of placement of equipment, materials and labor of accordance

with the sequence of work and working methods to be applied.

Page 8: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

River Improvement

4.5. Construction Stage / Sequence of Construction Sequence of Construction is a sequence of physical Construction and it’s very important and as

a basis for mobilization / demobilization of personnel, equipments, materials, as according to kind, capacity and schedule when needed

4.6. Construction Method Based on the Sequence of Construction then made construction methods in detail in

accordance with technical of construction and other determined specified in the contract documents. Mean of Construction Method to determine of Equipments, materials, and labor to

goal of plan of target productivity and also function for quality control and control of construction schedule to get the target of commitment contracts.

Construction Method each Works Item are test & Commisioning (Ok & No) and continue, that became Construction as according to the tender document (BQ, Shop Drawing & technical

specification) and on time / as time schedule

4.7. Quality Control Plan

Quality Control Plan is activity of making shop drawings, procurement and mobilization of materials, equipment and skilled personnel selection process.

4.8. Safety and Health of Work (K-3)

Safety and Health for Labor or other wise determined should be ensured with Made of Team K3 Project

4.9. Others Determined Standard (Like; socialization, etc)

Page 9: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

River Improvement

Flow Chart of Technical Control / Site Management

Work Contract

Permit Learn of Contract Coordination with Owner & Consultant Supervision

Survey & Measurement Notes :

Construction of work item

Construction of next work item

Engineer & MC0

Ok

No

Ok

No CONSTRUCTION

Request of next work Item , etc

= Cek :

- Shop Drawing & BQ

- Technical Specification (include Inspection & Test Quality

Control

- Approved Consultan Supervision &

Owner

Request

Construction of next work item, etc

Ok

No Construction of work item

Ok

No

Request of next work Item

Ok

No

START

FINISH

Page 10: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

River Improvement

FLOW CHART OF CONTRUCTION

SELESAI

Understanding of contrac rules (Pemahaman Syarat

Kontrak)

Understanding of contrac rules

Check

No

Yes

Socialization Pra Construction

Permit with 3d party (Perijinan dg Pihak

Terkait)

Scope of Works (Scope Pekerjaan)

Coordination with Owner & consultant supervision

(Koordinasi dg Pihak Owner & Konsultan

Penawas)

Input from Owner & consultant supervision (Masukan dari Pihak Owner & Konsultan

Penawar)

Check

No

Yes

Check with owner of Scope of contract

Check

No

Yes

Construction of scope of contrac (as conctruction

flow chart & BQ)

Field Engineering (Pembuatan Gambar

Pelaksanaan)

Check

No

Yes

Shop Drawing (Gambar Pelaksanaan)

Construction (Pelaksanaan Pekerjaan)

Check

No

Yes

Primary Hand Over (Serah terima Pekerjaan)

(PHO)

Maintenance (Pemeliharaan)

Final hand Over (Serah Terima Akhir) /

(FHO)

Prepair

Yes

No

As Build Drawing

Check

No

Yes

START

FINISH

FINISH

Page 11: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

River Improvement

TRAFFIC MANAGEMENT With Work site without disturb of Traffic Existing, the Traffic Management and Construction can be

execute at same time

Traffic using Rubber Cone as border between work site and traffic existing.

Traffic Sign Rubber cone

Fabrication of Rubber cone. Form as according to technical specification, continued placing on determined location as signs / bottle neck of the traffic.

Flagman

Flagman is placed on all construction that disturbing of traffic flow. The flag man instructing and manage of traffic flow that passing and around the construction.

Traffic Management

During Construction

Traffic Management

for Hauling Material

Ex Excavation to Disposal Area and

Mobilization

Equipment for Construction at

Project Location

Others Equipments Will be Mobilized via Existing Road (Dump truck, Excavator, etc)

Page 12: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

5. DETAIL CONSTRUCTION METHOD

5.1. General 1. Mobilization / Preliminary Works

Description Upon the signing of the contract, the contractor for with initiate site activities by first

mobilizing and demobilizing (preliminary works) of works including :

1.1. Mobilization of the contractor’s personal who are competent and experienced,

consisting of office staff site personal as according to the key personnel list proposed within the bid offer documents.

Page 13: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

1.2. Procurement of site facilities according to the specifications in the tender documents such as : Board of directors with dimension as according in BQ, the contractor’s office, the

material warehouse, material storage, site water supply, communication apparels , the project’s name board, and other facilities required.

Measure just for sample ( no reference), Real measure as determined or as field condition.

Base Camp

4

1

2

3

56 7

89

KETERANGAN :

1. Kantor Kontraktor

2. Mess Pekerja

3. Laborat

4. Gudang

5. Musholla

6. Kantin

7. Klinik

8. Mobil & Motor pool

9. Pos Jaga

JalanKerja

10.Tandon Air

10

8

Stock Yard

Image above only lustration of ” Construction of Base Camp” in the Project. Measure and real form as Field condition and needed.

CONTRACTOR FACILITIES / KEET DIRECTION

BARAK PEKERJA/BASE CAMP

DIREKSI KEET

Page 14: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

GUDANG/STORAGE

Gudang/Storage

BENGKEL KERJA/WORK SHOP

> Worshop and office Fabrication

Base Camp / Site Installation

1. Problem - Plan of Base Camp in Empty Space that already

Owner is Right side / South of access road. 2. Solution

- Contractor will rent from the owner while in the

process of rent will be assistant by Owner and other determined.

- After Approved by both of parties, contractor will constructed of base camp with accessories

required

- Around location of base camp will be given zinc fence as a barrier (with entrance-exit) are painted and given a logo contractors and other symbols required

Base Camp

Page 15: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

1.3. Board of Project name and Fence of Base Camp Board of Project name

Board of Project name made of Multiplex or Aluminum Plate and Frame of wood beams inscribed project name, project number, Project Cost, Fiscal Year and name of contractor

or determined in accordance with the technical specifications.

Base Camp’s Fence.

Base camp Needed Fence with determined Location (near / close with public ). Fence is made by zinc waves minimum 180 to 200 cm of the

soil surface with a wood frame or other specified technical specifications. Safety fence is intended to facilitate surveillance and

patrolling the incoming material and facilitate the control of the

environment and out of base camp.

Material and Tools were needed for this work :

a. Materials : Borneo Wood 5/7, Zinc waves BJLS 32, paint and anchor b. Tools

Construction Method :

- Cutting of Kaso wood as according to Height of Plan of fence as base of fence, forming as determined so that fence can stand up.

- Installing of Fence on kaso wood already stand around base Camp

- Painting the fence with contras color.

1.4. Mobilization of equipment among others : genset, theodolite and water pass, tamper & Pedestrian Roller, Excavator, Crane, etc, as required in the tender document.

1.5. Site Survey Works Description :

Initial survey to check the reference poles (Bench Mark Point) will be performed jointly with the Consultant and the Engineer immediately after the contract is signed or after the

issuance of Notice to Proceed.

The measurement will include:

Checking of reference points (BM) by measuring the polygon and water pass in order to find the actual (x,y,z) coordinate of the BM points, which will be compared to the BM

points data as seen on the drawing, from where could be seen weather it is still in good condition or not.

The construction/installation of the temporary BM to facilitate staking out during

performance of work. Surveying must be carried out by Surveying team using equipment as follows :

- The Total Station or EDM for the measuring of polygon. - Automatic Wild Nak level complete with its static and measuring aluminum measuring

rods (4m) for the water pass measurement.

The result of Measurement will be reported to the Consultant and the Engineer for comments and approval.

Further, the result of measurement will be applied for preparation of shop drawing, calculation MC0 volume, also as reference for implementation of the physical work.

Page 16: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

FLOW CHART

1.6. Traffic Management For construction, The traffic using traffic sign.

Signs from wood/wooden plate

At first The signs from wood/wooden plate made as according to technical specification and placing on determined location. Execution using labors and tools (hammer, saw,

etc)

Rubber cone

Fabrication of Rubber cone. Form as according to technical specification, continued placing on determined location as signs / bottle neck of the traffic.

Flagman

Flagman is placed on all construction that disturbing of traffic flow. The flag man instructing and manage of traffic flow that passing and around the

construction.

1.7. Water Supply Work Water and Electricity Work

Water Supply by boring well or PDAM, for working and water in Base camp environment,

clean water from sludge, oil and other chemicals for the purposes of sanitary workers. Waste Discharge / Dirt, with the waste stream into a Septic tank

Supply of electric by temporary connecting of PLN during construction or supply electric

with self by Genset with enough power during construction

1.8. Documentation and Project Administration

During project needs a portrait photo documentation of construction from 0% to 100%, which is collected in an album for weekly and monthly reports or determined according to

technical specifications and will be submitted to the project owner.

All administration of the project; Contract work, Licensing, Shop drawings, Work Request ,

Work Progress in daily, weekly and monthly, correspondence, As build drawing, Archiving, documents relating to the Construction, etc carried out by the contractor with systematic,

neat and accurate to implement procedures that exist on ISO’s Standard by Contractor’s

ISO Standard

1.9. Environmental response and Licensing / Permit Contractor will permitting that relates directly or indirectly to the Related Parties, either

Party Government and private parties / outside Government Agencies (also relevant parties around the project / socialization), It is important to ensure of "Clear of process "

Construction in order to get “on time schedule / schedule of Construction. In the Permit

Process, contractor will require cooperation and assistance of owner to facilitate of permitting process related.

PENGECEKAN TITIK REFERENSI BM (BENCH MARK)

PEMBUATAN DAN PEMASANGAN PATOK-PATOK TBM ( TEMPORARY BENCH MARK), JIKA DIPERLUKAN

PENGUKURAN KONDISI EXISTING

SURVEY DAN PENANDAAN LOKASI PEKERJAAN.

Page 17: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

1.9.1. Construction of Work Permit In this construction, we also implement standardized procedures in accordance

with the quality system owned and inform / permits each stage will perform the work, so in the future does not happen the things that are not desirable and to

avoid disassembly work resulting in delays and increased costs .

1.9.2. Shop Drawing, As Built Drawing and Documentation

- Each Constructions begins with making the proposed shop drawings for approval Supervisory Consultant.

- Shop Drawing made by the Site Engineer (each field) and signed by the Project Manager prior to submission to Consultant Supervisor.

- Approved Shop Drawing Supervision Consultant is distributed to each Project

manager respective as a reference of each construction type. - The construction of each type will drawn in As Built Drawing.

- Stage Documentation of Each Construction type for purposes of the project report.

- Activity-making shop drawings, as built drawings, documentation of ongoing

since the project started until the end of the project.

1.9.3. Construction Materials To maintain of Quality Control, the materials that will be used in this construction,

should be proposed sample for approval by Consultant Supervisor

All material to be used in this construction completed by manufacturer’s

specification as brochure and also referring to technical specification and technical procedure.

In this construction, contractor will be prepared and made the specimen as

according to standard determined

1.10. Construction Method to Goal of Work construction as “On Time & Quality as

according to technical specification” Early Finishing of Time Schedule (Percepatan Waktu Pelaksanaan Pekerjaan)

- To Early Finishing of Construction (as time schedule) and fully determined Quality as

according to technical specification, The contractor will be powered (Labor,

Equipment, Example: Concrete By Ready Mix, All construction will use good Condition of Equipment work Estimate on schedule & Quality.

1.11. Site Management - With one package and area, the mobilization of equipment & Personil / labor will

Clear (undifficult) / make less times. Equipments puts in base camp an soon as posible to mobilized into work site while

the construction will begin

- Traffic Management Start – During – Finish

Supplying & Handling of The Material 1. CCSP, Spun Pile and Embankment Material

- Supplying by good Supplier

2. Concrete - Supplying by Batching Plant Ready Mix

- Supplying by Concrete Mixer

Page 18: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

1.12. Other a. Diversion Chanel / Management System of Drainase

Generally, this project does not need Diversion Chanel. For determined location, if necessary a Diversion chanel (costruction was conected with

water existing), the contractor will make a diversion chanel with dimension of drainage

as volume of water existing

Next, if Project is finish, the diversion chanel will be return to existing condition.

b. Dewatering/unwatering For determined location, if necessary a Dewatering (costruction was conected with

water existing), the contractor will make a dewatering by Sand bag, and water will

pump to out site by water pump.

c. Protection construction

Generally, this project does not need protection Construction

For determined location, if necessary

a Protection Construction, Specialy

excavation work that possible have slide down, contractor will make a

Protection Construction by Dolken on excavation side (between excavation

location and existing)

Dolken will installed / pilling each

± 0.3 m

d. Other Mobilization - Communication equipments supplying

- Make and supplying As built Drawing. - Other equipment as according to Tender Document

Page 19: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

5.2. Detail Construction

5.2.1. Preparation and General Work Already Description on Previous Page

Survey & Measurement

Personal Mobilization

Equipment Mobilization

Etc (as List Equipment)

Electrical supplying

Documentation

Water Supplying

Shop Drawing & As Built Drawing

Others works as according tender document (BQ)

Page 20: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

5.2.2. Safety Tools ( using by labors) /Peralatan K3 dipakai oleh pekerja Proyek There are several tools that are used to protect a person from

accidents or hazards that may be going on in the construction process. This equipment shall be used by someone who works

in a construction environment. This equipment shall be used

by someone who works in a construction environment.

Health and safety are two very important things. Therefore, all companies konstraktor shall provide all necessary equipment /

personal protective equipment or personal protective equipment (PPE), as according to below:

1. Work Clothes / Dungaress

The purpose of work wear is to protect the human body against the effects of

an unhealthy or that could harm the body. Cause Character of the project site construction, which generally reflects the harsh conditions of work clothes

should be used is also not the same as the clothing worn by employees who work in the office. The company clearly understands this problem generally

provide as many as 3 pairs in each year.

2. Safety Shoes

Safety shoes is foot protection. All Labors should wear shoes with thick soles

to be able to freely walk everywhere without getting hurt by sharp objects or possessed by the dirt from the bottom. Face of shoe should be loud enough

for foot does not hurt when falling objects from above.

3. Work Glasses

Safety glasses are used to protect eyes from dust wood, stone, or metal debris

floating in the breeze blow. That the dust particles are so small that sometimes are not visible to eye. Therefore, eyes need to be protected.

Welder is Usually use this glasses for weldening

4. Gloves Gloves are required for certain types of jobs. The main purpose is the use of

gloves to protect hands from hard objects and sharp for its activities. One of the activities that require lifting gloves are reinforced steel, wood, etc

5. Helm Helmet is important to use as headwear, and is a must for any construction

workers to use it properly according to the rules. This helmet is used to protect the head from the dangers that come from above, such as no goods,

either equipment or construction material falling from above. Indeed, we often see the discipline of labors to use is still low which can certainly harm

themselves.

Page 21: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

6. Ears Plug

This tool is used to protect the ears from the sounds issued by a machine that

has the volume quite loud and noisy. Sometimes the effect is for the long term, if every day hear the noise without earplugs this.

7. Fire extinguisher Lightweight (APAR=Alat Pemadam Api Ringan) If there is a fire in the workplace, immediate action is taken to extinguish a

fire light as the initial action. If not sufficient, please contact The fireman.

8. First Aid In case of accidents both light-and heavy construction workers, first aid should

be done on the project. Contractors are required to provide drugs that are used for first aid.

First Aid standard equipment on the project and it must be provided by the

contractor, perhaps mandatory. Remember preventive measures are much better and cheaper than was incident.

9. Signs and Safety Instructions Signs and Safety Instructions was performed at the beginning and during the

work progresses. Signs and instructions posted on site where the sign is and is useful as a sign / warning workers or others.

10. clothing buoy Clothing buoy Should be wear for construction Period for construction on at

water

Page 22: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

FLOW CHART OF CONSTRUCTION

Contract

Mobilization

Survey & Measurement

Shop Drawing Construction Method

START

Earth Work and Demolishing of Structure

Existing

Cek

Ok

No

CCSP - Left and Right River

- 2 Group

Traffic Management

Next Flow Chart will be described on next page

FLOW CHART OF CCSP

& FLOW CHART OF

REVETMENT

Cek

Ok

No

Mob. Equipments for earth work

Traffic Management

RC Pile 20x20 - Left and Right River - 2 Group

Next Flow Chart will be described on next page

FLOW CHART OF RC

Pile 20x20

Next Flow Chart will be described on next page

FLOW CHART OF PARAPET

(RETAINING WALL)

Parapet - Left and Right River - 2 Group

Excvation of River Bank - Left and Right River - 2 Group

Parapet - Left and Right River - 2 Group

Cek

Ok

No

Cek

Ok

No

FINISH

Mob. Equipments for earth

work

Traffic Management

Next Flow Chart will be described on next page

FLOW CHART OF ROAD

ROAD - Right River - 1 Group

Embankment For Dike (borrow material)

Page 23: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

DETAIL FLOW CHART

FLOW CHART of EXCAVATION of COMMON SOIL FOR STRUCTURE BY MACHINERY

SURVEYING WORKS

EXCAVATION

EXCAVATED MATERIAL

CHECK

YES

NO

CHECK

UNSUITABLE MATERIAL / WASTED

MATERIAL

SUITABLE MATERIAL /FILLED MATERIAL

Thrown of Excavated material into disposal

area

Direct Filling in work location /

Filling Area

collected and stocked in

temporaryplace.

Back Filling

Back fill / Common embankment

START

FINISH

Page 24: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

FLOW CHART of EMBANKMENT FROM BORROW AREA

*Process in Quarryupto into work site

Start

Excavation in

Borrow Pit

area

Suitable Unsuitable

Excavation &

Delivery

Filled area

Spreading Layer 1

Thickness >20cm

Compactor of

Layer 1

Check of thickness

Compact Max= 20cm

Check density

of layer 1

Spreading of layer

2N

Compactor of

Layer 2N

Check density

of layer 2N

Forming Finish

Grade

Check Top Level

Final Compaction

Check density

Trial Compaction

FINISH

No Process

Page 25: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

FLOW CHART OF CCSP

Pilling Process

pemancangan

Transportation of Sheet Pile

setting out Of location Pilling

Guide Beam Installation

Placed Sheet Pile on Work Site / stock area

Installation of Sheet Pile on Vibro Hammer (Pilling equipment)

Pilling

Finished Pillingi / Piled Sheet Pile

Check

No

Yes

Delivery of Sheet Material on Trailer

Check

No

Yes

Order & Manufacture By Supplier /

Sub Contractor

Equipment Mobilization (Crane with

Vibro Hammer)

FINISH

Anchor by Tie Rod dia. 32 mm (at location to determined to the drawing

Construction Of Revetment

Geotextile and Borrow embankment

Cyclope concrete

START

Finished Earth Work (Structure Excavation) & Temporary Embankment

Ok

No

Lean Concrete

Page 26: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

FLOW CHART OF REVETMENT

START @18m

Finished of CCSP Work

hekCh

ek kOk

oNo

Gravel Bedding

Chek

Ok

No

Base Concrete (Reinforcing, Form work and Concreting

K225

Chek

Ok

No

Base Concrete (Reinforcing, Form work and Concreting

K225

Chek

Ok

No

Top Concrete (Reinforcing, Form work and Concreting

K225

Chek

Ok

No

Placing Concrete Block and Weep Hole

Chek

Ok

No

Embankment from borrow

area

Chek

Ok

No

Fabrication of Concrete Block at Base Camp

Chek

Ok

No

Delivery FINISH

Construction Next Revetment

Chek

Ok

No

Joint Filler (elastic material)

Chek

Ok

No

FINISH

Earth Work (dike embankment)

Page 27: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

FLOW CHART of RC PILE 20x20

Driven Process

Loading and Delivery on Transportation Vehicle

Transportation of material

Setting out of Piling

Aproval

Placed into Work Site

Connecting (if any)

Finished Pile Driven

Cut of Top Pile (If any)

Pile Driven

FINISH

START

Finished Earth Work (Excavation of River bank)

Ok

No Finished Earth Work (Structure Excavation)

Ok

No

Pile Driven

Ok

No

RC Pile Installation at Driver Pile

Ok

No

Ok

No

Ok

No

Next Construction (Parapet / Retaining wall

Page 28: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

FLOW CHART OF PARAPET (RETAINING WALL)

Sand & Lean Concrete

Chek

Ok

No

Reinforcing Steel & Formwork (Footing)

Chek

Ok

No

Concreting

Chek

Ok

No

Reinforcing Steel & Formwork (Wall)

Chek

Ok

No

Concreting

Chek

Ok

No

Back Fill by selected excavation

Chek

Ok

No

FINISH

START (1 Segment)

Finished Earth Work (Structure Excavation) & RC Pile 20x20

Ok

No

Finished Earth Work (Excavation of River bank)

Ok

No

Next Segment

Chek

Ok

No

Joint Sealent

Chek

Ok

No

FINISH all Parapet

Page 29: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

FLOW CHART OF ROAD

START (1 Segment)

Finished Earth Work (Structure Excavation)

Ok

No

Wet Masonry 1pc:4sand

Chek

Ok

No

Instal Galvanis Pipe , Reinforcing steel and Form

work for Column

Chek

Ok

No

Concreting for Column

Chek

Ok

No

Reinforcing steel and Form work for sloof

Chek

Ok

No

Back fill with Selected excavation

Chek

Ok

No

Precast Concrete Curb & back Fill

Sand & Paving Block / Precast concrete Tile

Chek

Ok

No

FINISHED

Next Segment

Chek

Ok

No

Elastic Joint Filter

ChekC

OkO

NoN

FINISHED

Next Construction (Embankment for dike with Borrow material)

Installation Wire Mesh Fence

Chek

Ok

No

Page 30: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

DETAIL CONSTRUCTION OF WORKS ITEMS

Page 31: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

CONSTRUCTION METHOD FOR EARTH WORK

Description;

Construction of Earth Work will be devided of some Types;

1. Land Clearing and Demolishing

1.1. At Location as determined to the drawing

2. Excavation at Structure Plan; 1.1. By Heavy Equipment / Excavator & Dumptruck

1.2 By labors and Tool Usualy at base structure for prepare work

Unsuitable Material Ex Excavation will be trohwn to disposal area

Suitable Material Excavation will be used to Back fill Selected Excavated Material by Man

Power (or otherwise determined to technical specification)

As technicaly, Contruction will need Transportation Equipment

Page 32: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

1.3. Location - CCSP Location

- Other Location as determined

1.4. Hauling Material

3. Embankment Embankment material from Borrow Area

- Structure Embankment

- Dike Embankment

- and Other Location as determined to the drawing

Page 33: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Land Clearing & Grubbing

Land Clearing from unsuitable material as according technical

specifications(shrubs, grasses, shrubs, trees, pillars, existing

structure, etc.)

Equipment:

- Chain saw

- Bulldozer

- Excavator Loading

- Dump Truck hauling &

Dumping into disposal area

- Stripping of Soil Stripping done into a minimum of 15-20cm (as determined to

technical specification). The

trees were removed to its roots, then the roots of the

former filled with soil and then compacted.

if permitted, wood and twigs

were collected for later burned.

Collection and burning the material ex cleaning in sites is

considered safe, protected and no harm / harm the environment.

The remaining combustion is

extinguished altogether covering, re-planted and neatly.

Page 34: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Demolishing

Assumption : 1. Work by Labor and Tools

2. Work Location :Structure Existing as according to the drawing

Description : This work include all Demolishing in boundary plan according in drawing, removal, transportation, dismissal of structure existing, forming of excavation area and completion of open exaction area,

according to specification and line, height, sloping, measure and cross section which written in drawing and guide of Supervisor consultant.

Page 35: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Excavation Work

Excavation Common Soif for Structure by Machinery Assumption : 1. Work by heavy equipment ( mechanically)

2. Work location : As according to the drawing / Common excavation

Description This Work include all excavation in boundary plan according in drawing, removal, transportation,

useful or dismissal, forming of excavation area and completion of open excavation area, according to specification and line, height, sloping, measure and cross section which written in drawing and guide

of Supervisor consultant.

Works Sequences : 1. Work of Preparation include :

- Preparation of Shop Drawing till get approval from Engineer

- Preparation of Equipments work and man power / Labors - Traffic Management (if needed) For hauling and handling of material ex excavation

2. Work of Measurement.

- Before excavation started, must be done work of Measurement to know and boundaries of plan of excavation elevation by installation of stake marked with paint.

3. Excavation

- Excavation must be done according to height line and of elevation which shown in drawing. - Suitable of Excavated material to be deposit / collected and stocked in temporary place around

the excavation area or to be transported by dump truck direct to fill area (Embankment).

- Unsuitable material will be transported with dump truck thrown to area disposal agreed by director/Engineer.

Equipments :

- Excavator for excavation and load to dump truck - Dump truck to the transportation of excavated material.

Construction

Work Equipment & Used

Excavation

=

1.

2.

Excavator

For Cutting / Excavation in Cutting area and loading

into dump truck for transported into Embankment area (suitable material) of into wasted area /

disposal area (unsuitable material / unused material)

Dump Truck

2.1. Suitable material

To delivery the excavated material into Embankment are

2.2. Unsuitable material and Wasted material To delivery the excavated material into wasted

area / disposal area

Page 36: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Image

Excavation By Excavator for the location that probably work can using

Heavy Equipments

Structure Excavation, 0 – 2 meters in depth.

Generally, slope is made straight vertical, or otherwise determined as according to site condition , the slope is

made 1:3 or 1:2

Structure Excavation, 2 – 4 meters in

depth. Generally, slope is made 1:3 or 1:2

Handlling and Hauling of Excavated material

For Back Fill, Compaction by Pedestrian Roller or Hand Stamper

Suitable material

To delivery the excavated material into Back Fill

Unsuitable material and

Wasted material

To delivery the excavated material into wasted area /

disposal area

Page 37: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

FLOW CHART of EXCAVATION of COMMON SOIL FOR STRUCTURE BY MACHINERY

SURVEYING WORKS

EXCAVATION

EXCAVATED MATERIAL

CHECK

YES

NO

CHECK

UNSUITABLE MATERIAL / WASTED

MATERIAL

SUITABLE MATERIAL /FILLED MATERIAL

Thrown of Excavated material into disposal

area

Direct Filling in work location /

Filling Area

collected and stocked in

temporaryplace.

Back Filling

Back fill / Common embankment

START

FINISH

Page 38: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Embankment Works From Borrow Area

Assumption : 1. Work by heavy equipment ( mechanically)

2. Work location : Structure (at CCSP and Revetment), Dike Embankment and others location as

determined to the drawing

Sample

Description This work consist of transportation, hauling, placing/spreading and compaction material to execute of construction embankment/filling

Equipments; - Wheel Loader

To Loading material Into dump truck in Quarry / Borrow pit area - Dump Truck

To Transported / delivery the material into Filling Area - Bulldozer and Excavator

To spread the material in work site.

- Vibratory Roller and Stamper To Compaction

- Water tank Truck To watering (if water rate less than determined as according to technical specification)

- Tools

1. Material

- Material taken away from location which have been agreed by supervisor consultant pursuant to specifications.

- Material consist of earth excavated agreed by Engineer.

- Materials exclude the use earth excavated of high plasticity, which classified as A-7-6 according to AASHTO M145 or otherwise determined as according to technical specification.

- Test of Material accordance with SNI 03-1744-1989, have a CBR value of not less than 6% (six

percent) after 4 day soaking, when compacted to 100% of the maximum dry density ( MDD) as

determined according to SNI 03-1742-1989 or otherwise determined as according to technical specification.

- Used material having an activity value greater than 1,25 or degree of expansion classified by

AASHTO T258 or otherwise determined as according to technical specification.

Page 39: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

2. Measurement Measurement And location of border line at fill area, as according to elevation and distances plan

which have been determined, where work of Measurement have to follow procedure which have been determined and can understand by site engineer.

3. Sub grade preparation of back fill and it’s procedure. Placing/Spreading of Fill material layer by layer have same thickly and wide of embankment

material as according to sloping line, cross section and contained size measure in drawing. Compacted is done after spreading have been executed as follows :

1. Layer more than 30 cm below/under sub grade level to be compacted to 95% of the maximum standard dry density / laboratory determined according to AASHTO T 99

2. Layer 30 cm or less below sub grade level to be compacted to 100% of the maximum standard

dry density / laboratory determined according to AASHTO T 99 3. Density test to be made on each layer of the compacted fill in accordance with AASHTO T 191,

T 238, OR T 205

Compaction method from low place to high place and beginning at outer edges and progress

toward the center in such a manner that each section receives equal compacted effort and in the longitudinal direction

4. Water Rate.

If embankment do not contain enough water rate, require to watering by water tank reach optimum water rate. If embankment too wet hence require to be dried first before compacted.

5. Amount of Passing Compaction. Passing Compactor appliance determined pursuant to result of Trial Compaction which have been

agreed, as according to embankment type and utilized appliance type.

Common Embankment

Placing/Spreading of Embankment material layer by layer have same thickly and wide of Fill material as according to sloping line, cross section and contained size measure in drawing and

technical specification.

Material on Quarry / Borrow Pit Area Work by Wheel Loader

Material on Quarry / Borrow Pit Area

Work by Excavator

Page 40: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Embankment Construction Placing/Spreading of Fill material layer by layer have same thickly and wide of Fill material as

according to sloping line, cross section and contained size measure in drawing and technical specification.

Penghamparan dengan Bulldozer

Compaction by Vibratory Roller

Watering in filling process (if necessary) Watering is given to full of water rate as according to

technical specification

Trimming By Excavator (if neccersary) as according to the drawing Dike Embankment

Page 41: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

FLOW CHART of EMBANKMENT FROM BORROW AREA

*Process in Quarry

into work site

Start

Excavation in

Borrow Pit

area

Suitable Unsuitable

Excavation &

Delivery

Filled area

Spreading Layer 1

Thickness >20cm

Compactor of

Layer 1

Check of thickness

Compact Max= 20cm

Check density

of layer 1

Spreading of layer

2N

Compactor of

Layer 2N

Check density

of layer 2N

Forming Finish

Grade

Check Top Level

Final Compaction

Check density

Trial Compaction

FINISH

No Process

Page 42: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

CONSTRUCTION METHOD FOR CCSP

Description; - Structure Type Segmental (@ 18m) - Work of CCSP is conecction with Revetment work Finished of CCSP will continue with Revetment

Work

- Construction; Based of The drawing, Work site divide to 2 side of River. North River (left side) and South River

(Right side). For this Construction, Contractor will construction this work by some Group of Works

Base of Equipments to Construction this Work and access road;

Right side / South Left side / North

Page 43: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Notes;

Stage 1; - Site Condition Almost there is no Access Road

- Almost, Construction will be Constructed Via River (on Pontoon)

- on some location, If work site can be reach by access road, Construction will be constructed from

Land

Notes; Stage 2; - Site Condition Almost there is Access Road

- Almost, Construction will be Constructed from Land - on some location, If work site can,t be reach by access road, Construction will be constructed from

River (on Pontoon)

- Work group from Construction of Stage 1 (Construction had been finished), will be mobilization to construction on Stage 2 location

All construction will be constructed From Up stream (Hulu) into Down Stream (Hilir)

Stage 1 (2 Group)

Stage 2 (2 Group)

Group 1 Group 2

Group 1 Group 2

Work Direction

Work Direction

Page 44: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Construction Method for CCSP (Corrugated Concrete sheet Pile)

Refer to Tender Document, Work Stage / Construction Plan will be Constructed as bellowing Drawing

Existing

- Excavation For Structure

- Temporary Embankment for

Construction Yard - Temporary

Cofferdam (sand

Bag)

Driving of CCSP Via River by Pontoon (if construction can’t be constructed from Land)

- Driving for CCSP

Cofferdam

Temporary Embankment

Excavation for Structure

Page 45: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Driving of CCSP from land

Page 46: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Corrugated Concrete

Sheet Pile

Excavation of

Temporary

Embankment for replacing Borrow

embankment & Geotextile

Placing geotextile and Embankment of

Borrow material

Page 47: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Cut Top Pile

Anchor

Page 48: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Reinforcing of Capping Beam and Partition

Wall

Page 49: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Form work of Capping

Beam and Partition Wall

Concreting of Capping

Beam and Partition Wall

Page 50: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

FINISH

Page 51: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Works on Excavation (there is no Temporary embankment, at Construction period not need Cofferdam

and Temporary Embankment)

- Finished

Page 52: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

- Next Back fill with

Borrow Material (bottom cyclope)

- Lean Concrete

- Cyclope Concrete - Back fill and

embankment with Borrow Material for

Revetment

Page 53: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Construction Method for Revetment

- Gravel Bending

- Base Concrete

Top Concrete Frame - Reinforcing

- Form work

- Concreting

Page 54: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Back Fill with Borrow

material

Placing for Concrete Block 3x30x10 K. 175

and Closing concrete

Page 55: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Embankment For Dike

Page 56: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Construction of River Revetment is Segmental with @ 18 m

Jointing / Construction Joint for one Segmental Revetment with each other by Joint Filler (elastic

Material) as according to the Drawing

Page 57: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

- Construction by Segmental (@ 18 m)

- Construction will be Constructed by Continue, Mean that when work CCSP up to @18 m, the next

construction should be done. -

Illustration;

Stage 1 - CCSP Work

Stage 2

- CCSP Work - Capping Beam and other Work

Stage 3

- CCSP Work

- Capping Beam and other Work - Cyclope

Stage 4 and soon - CCSP Work

- Capping Beam and other Work - Cyclope

- Revetment and other work

Capping Beam CCSP

Cyclope Capping Beam CCSP

Cyclope Capping Beam Capping Beam CCSP

Page 58: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Detail Construction Of CCSP Work

Assumption:

1. Work by Heavy Equipment (Machinery) 2. Location : As according to the drawing

3. Material CCSP with Water Jet System and Have no water jet System

Description

1. Site Work Preparation - Work site made with good level that a Crane can stand up goodly

- Crane stand up above plate of form which in the form of steel plate 1,5 x 6 meter.

2. Stake point of Pilling - Stake point of pilling of Concrete Corrugated Sheet Pile is executed by surveyor which is approved

/ agreed by Consultant Supervisor

3. Fabrication of Material Steel sheet pile

- Fabrication / manufacturing of Concrete sheet pile is formed after the drawing has been approved by Consultant supervisor.

- Delivery to work site

4. Pilling

- Excavation by labor to get form of pilling

- Made of guide beam on pilling position using steel material WF type with elevation distance from sub grade 1 to 2 meter, before pilling is executed

- Guide beam is made with strength enough that can supporting of moment when pilling is executed and stabile

- Piling founded by vertical and monitored with measuring instrument ( Theodolite) and yarn in 2

direction which each other vertical

- Before pilling, pile with Vibro hammer have to in position of sentries

- Concrete Sheet pile is vibrated by Vibro hammer is and the Sheet pile will be pilled into ground

cause of gravitation moment and weight of Sheet pile it selfand also helped by Water Jet Pump

that spraying water, that mean this construction to easyly andalso helped byWaterJetPump thatspraying waterwhichis intendedtosoften of soileasierPilling proccess

- Vibratory is executed as sequence.

- At pilling time, between one of Steel Sheet pile and each other of side (has been pilled) if there is gap, can be near by trek beam.

- Pilling is executed until a Sheet pile reach deepness elevation plan as according to the drawing.

Page 59: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Pengadaan dan Transportasi Material Sheet Pile

Construction CCSP by Water Jet System

- Water Jet Pump that

spraying water, that mean this construction to easyly

andalso helped

byWaterJetPump thatspraying waterwhichis

intendedtosoften of soileasierPilling proccess

Page 60: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Page 61: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

At determined location, Sheet pile will be strength with Anchor

Description;

- Finished Sheet pile, at location where sheet pilet ierod/anchor will be installedin pit / hole sheet pile

that has been provided (pit / boring by ConcreteDrill)

- Material of TieRod Steel D32 (coating withgrease) insertedinto hole. At the end of threaded TieRod,

Bolt was given and CNP (as according to the drawing). Next bolt in will be installed with tied.

- Other side of sheet pile, will be installed of Tie rod with as same as squence work.

- Next, Both of end tie rod wll be united / connected by "Turnbuckle". Thisturnbucklebeside

asconecting, as fasteners to (beside a bolt on sheet pile it self)). After Tie rod installed

andtension/tightnessis obtainedby Caping Beam as according to the drawing.

- Continue with construction on Tie rod that cross section as according to the Drawing ( Sand embankment, lean concrete and Cyclope concrete)

Detail of Caping Beam

Caping Beam - Reinforcing Steel

- Form Work

Page 62: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

- Concreting as according to the

drawing and technical specification

Finish

Page 63: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

FLOW CHART OF CCSP

Pilling Process

pemancangan

Transportation of Sheet Pile

setting out Of location Pilling

Guide Beam Installation

Placed Sheet Pile on Work Site / stock area

Installation of Sheet Pile on Vibro Hammer (Pilling equipment)

Pilling

Finished Pillingi / Piled Sheet Pile

Check

No

Yes

Delivery of Sheet Material on Trailer

Check

No

Yes

Order & Manufacture By Supplier /

Sub Contractor

Equipment Mobilization (Crane with

Vibro Hammer)

FINISH

Anchor by Tie Rod dia. 32 mm (at

location to determined to the drawing

Construction Of Revetment

Geotextile and Borrow embankment

Cyclope concrete

START

Finished Earth Work (Structure Excavation) & Temporary Embankment

Ok

No

Lean Concrete

Page 64: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

FLOW CHART OF REVETMENT

START @18m

Finished of CCSP Work

Chek

Ok

No

Gravel Bedding

Chek

Ok

No

Base Concrete (Reinforcing, Form work and Concreting

K225

Chek

Ok

No

Base Concrete (Reinforcing, Form work and Concreting

K225

Chek

Ok

No

Top Concrete (Reinforcing, Form work and Concreting

K225

Chek

Ok

No

Placing Concrete Block and Weep Hole

Chek

Ok

No

Embankment from borrow area

Chek

Ok

No

Fabrication of Concrete Block at Base Camp

Chek

Ok

No

Delivery FINISH

Construction Next Revetment

Chek

Ok

No

Joint Filler (elastic material)

Chek

Ok

No

FINISH

Earth Work (dike embankment)

Page 65: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Concrete Reinforcement

- Reinforcing Steel Bar Assumption : 1. Work manually Labors and tools (bar bender and bar cutter)

2. Work Location : Structure Concrete

Description : 1. Reinforced steel Material become delivered from factory / supplier to work Site with

quality and dimension of the reinforcing steel as according to technical specification.

Otherwise determined to the drawing, used steel bar with quality as according to technical specification and the shop drawing

Characteristic Yield Strength of U24 = 2.400 kg/cm² Soft

Characteristic Yield Strength of U32 = 3.200 kg/cm² Middle

Characteristic Yield Strength of U39 = 3.900 kg/cm² Hard

Characteristic Yield Strength of U48 = 4.800 kg/cm² Hard

2. Material put down at stock area (storage).

3. Continued assembled of reinforced steel / manufacturing, that is in the form of needed measurement of length, cutting with bar cutter and bending with bar bender and done at

the time of cold temperature (as according to ACI.315 procedure or other wise determined

by technical specification).

4. After that Reinforced steel is compiled / to be attached as according to drawing execution and his cross is bound by strength with bend rat wire / Tie Wire.

Tie wire for fastening reinforcement is annealed steel wire conforming to AASHTO M32 – 90 or other wise determined by technical specification

5. Steel reinforcing is placed so that the minimum clear covering of concrete over the

outermost edge of the main steel bar is as follows.

5.1. 3.5 cm for concrete not exposed to weather or to ground water (for example, bottom of deck slab).

Size of Reinforcing Bar to be

Covered (mm)

Minimum Clear

Cover (cm)

5.2. 7.5 cm for all submerged concrete which cannot be

made accessible, for inaccessible concrete in which failure due to rusting of reinforcement could cause

loss of life or of the structure, for concrete placed

directly against the ground of rock, or for concrete subjected to sewerage or other corrosive liquids.

Minimum Cover over Reinforcing Steel for Exposed but

Accessible Concrete

16 mm bar and smaller 19 mm & 22 mm bars

25 mm bar and large

3.5 5.0

6.0

Page 66: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Page 67: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

FLOW CHART

No

Fabrication & Installation

OK No

Ok

List Bending of Bar (BAR BENDING)

Check of material -Strength Test

Material Weighing

Get another

material

Cutting and Bending

Installation on site

Check : - Diameter - Amount - Location

Ready to be concreted

Repair

Delivery bar material from supplier and transportation into site work

Stock deposit of material/storage

Result

Result

START

FINISH

Page 68: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

- CONCRETE

Assumption : 1. Work use mechanical equipment 2. Work Location : Structure Concrete

Eguipment: - Batching Plant + Truck Mixer - Tools

Considerations for producing a good concrete work - The quality of the concrete depends a great proportion of the materials

used such as cement, sand, aggregate and water - Lack of cement in the concrete mix causes less qualified and weak - Too much water leads to poor concrete quality - It is important to measure and add gravel and sand separately to create a

quality solid concrete - Always use a clean gravel

Description : Equipment ;

- Batching Plant & Truck Mixer

- Concrete Vibratory - Tools

A. Work Preparation.

A.1. The Work consist of the construction of all concrete structure

A.2. The Mixture material (cement, sand, aggregate) are delivered from supplier to work

location and storage. Concrete Production by Batching Plant.

It’s delivered to work location in the form of concrete ready mix and delivered by Truck mixer.

During delivery, mixer cylinder in truck mixer continue to rotate to mixing the mixture with rotation which is qualified so that the condition of the mixture has good quality

and it’s not run dry.

For storage of cement, done a special treatment. It’s storage in a weatherproof sheet

that is airtight, and has araised wooded floor (about 30 cm), which is covered with polyethylene sheeting. At all times stack of cement bags to be kept covered with an

envelope of polyethylene sheeting.

A.3. Used Concrete quality as according to concrete quality which asked in tender document and relative to Standard as below;

- AASHTO T141, T23, T126, T22

- Another Standard as asked/ as according to tender document

A.4 Used Portland cement type as according to request of tender document. Type of Portland cement conforming to AASHTO M85 except type IA, IIA, IIIA and IV

or other wise determined by technical specification. Unless other wise permitted by

the engineer, air-entraining admixtures shall not be used or other wise determined by technical specification.

Construction of Concrete Reinforcing Steel

Page 69: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

A.5. Water used in mixing, curing, or other designated is clean, and free from harmful

matter such as oil, salt, acid, alkali, sugar, or organic materials.

Water tested in accordance with, and meet the requirements of AASHTO T26, other wise determined by technical specification.

A.6 Coarse Aggregate, Which used ( measure / dimension) as according to request of

specification in tender document ( relative concrete standard of SNI 032-2816-1992

and AASTHO or other wise determined by technical specification) and have got approved by Directors.

Aggregate is clean and free from Mud, other smooth particle, alkali and materials organic / substance able to destroy quality of concrete.

Aggregate consist of clean, hard, durable particles obtained by crushing rock or

boulders, or by the screening and washing (if necessary) of natural river gravel and

sand.

Aggregate the used also conform with the other property specification given in table in technical specification.

A.7. Sand /fine aggregate the used is sand result of stone crushed or natural sand which got from river / source of nature and have got approvalof directors and have tested

Clean sand, free from clay, rock, materials of organic and alkali and other materials

able to destroy quality of concrete.

used sand ( measure / dimension) as according to request of technical specification in

tender document and have got approval of directors.

B. Mixing and production B.1. The material proportional of Mix design using method of determined standard in

technical specification and in accordance with the limits given in table in technical

specification in tender document.

B.2. Trial mix done and result of it will be made reference making of concrete at the time of work in work site and witnessed by directors.

Trial mix as according to request of technical specification in tender document and get the engineer’s approval.

B.3 Mix Property Requirements as according to technical specification in tender document.

B.4. Mixing :

B.4.1. The Concrete is mixed in a mechanically operated machine (Batching Plant)

B.4.2. The mixer is equipped with adequate water storage and device for accurately measuring and controlling the volume of water used in each batch.

B.4.3. The mixer is first charged with the catches aggregates and cement, and the mixer started, before any water is added.

B.4.4. The time of mixing is measured from the moment water is introduced into the

material dry mix.

C. Placement. - As preparation, work location of concreting cleared from garbage, wood cutting, bend

rat, nail and other garbage with vacuum cleaner, compressor and or water.

- Form work coated internally with mould oil till covering all surface. Leakage of form

work been checked and repaired. Construction joint with concreting before all have been coating with cal bond or cement water and also form work free from water pond.

Page 70: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Before concreting instruction, all permission the needed have been managed and agreed by directors / owner and work supervisor.

- For the Concrete of ready mix, concreting done by mechanically, from truck mixer pass gutter. Concrete shall not be dropped freely into form work heights greater than 150

cm. So it’s not happened dissociation between the weight aggregate with concrete pasta, ( segregation).

- Compaction helped with adequate selected vibrator type mechanically in number. Vibrator pipe inserted into the wet concrete vertically so that it penetrate to the bottom

of the freshly placed concrete and provides consolidation throughout the full depth of section and it’s not to happened air pocket. Vibrator do not hit shutter or bar except

cover of concrete.

1. Preparation

YES

YES

Check of Material

Make trial mixture

Concreting at Site

Get another material

NO

Make another Mixture

NO

Result

Test

Page 71: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

2. Preparation at site

Preparing of structure : - Check dimension, elevation - Check form work of concrete - Check of Bar (amount, dimension, form) - Check material which embedded (if any)

Preparing of equipment and material : - Preparing of material (amount &

quality) - Preparing equipment (vibrator) - Preparing tools (light, pump, tend, etc)

Concreting prepare : - Batching Plant, Gutter ,etc. - Man power

Concrete mixing

Concreting & compacting Take Concrete Cube

Curing

Removal of form work

Reject Good

Repair

Work is Accepted

Good

Age 28 day Test

Check Of Concrete

Check Result

Page 72: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Checking Of Cube

Take concrete cube

7 day test and otherwise determined in the technical

specification

NO Good

Evaluation

28 day Test Repair Mixture Work is Continued

NO Good

Work is Accepted Evaluation

Take sample from structure

NO Good

Dismantle

Work is accepted Notes :

- Repair mixing (if any) - Better method of working - etc.

Result

Result

Test

Page 73: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

CONSTRUCTION METHOD FOR RC PILE

- Construction;

Based of The drawing, Work site divide to 2 side of River. Left River and Right River. For this Construction, Contractor will construction this work by some Group of Works

Base of Work volume; for Left Retaining Wall (North) = 1 group of works

for Right Retaining Wall (South) = 1 group of work

Construction will be constructed after earth work (excavation) has been done

Detail Construction 1. RC Pile 20x20 Mini Pile

Construction

Work Sequence for this Construction from Equipment of Pile Driven Mobilization, Procurement of

Material RC Pile, Pile Driving, Cut top Pile (If any)

Pile Driven Mobilization For Pile Driving will using Pile driver, that is; Pile Driver type Drop Hammer / Mini Driver Hammer

This equipment will be mobilized into work site 1 Week before Pile Driving Process for preparation

of work that connection of Driven, there are Boom Installation and Hammer

Procurement of RC Pile

After Approval of Minutes of Procurement material of RC Pile 20x20 between Supplier and Contractor, The contractor ask to Request RC Pile as soon as possible as Technical Specification to

Director (Owner) to get approval

Ordering of RC Pile to Supplier can be executed after get the approval. The material by

manufacture with Technical Specification 200x200 mm and material length as according to the drawing. Delivery by Trailer or Flat Bed Truck

Pile Driven Sequence of Pile Driven;

- Shop Drawing - Study of Place / Pile position to Center

- Adjust the placement of the material stock piles, which is safe enough to maneuver heavy equipment.

- Location must be free of disturb that can be resist of Construction

Page 74: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

- Request permission to consultants Supervisory and coordination with surroundings.

- Check the marking / measurement and Center of Longitudinal and cross section. - Check of piling driver to as according to technical specification

- Check stabilization and perpendicular of Driver Machine

After all preparation driven is complete, Pile driver and RC Pile was already on site, soon Pile

Driven can be done, with Construction method as bellow: - Before Driven, RC Pile marked with flashy paint every 20 cm, as a benchmark by checking

calendaring by survey officer. - Determination of Pilling Stake. Work site as according to the drawing and installed with Stake

guard of Pilling, continue ask to approval from Owner / Director one day before Pile Driven - Pile Driven will be constructed by placing Pile with vertically position above on point Pilling

and hammer placed sentries on it.

- Each pile is placed near the location of pilling. To lift and move of pile implemented as shown below

- As a tool anvil hammer or cushion used type of wood or plywood are good enough to be

replaced periodically. - Head of RC Pile is protected from direct impact hammer with a bearing of boards or plywood

with a thickness of 10 cm. - Weight or power hammer should be enough to guarantee a final penetration of not more than 5

mm per blow.

- Hammer used is the heaviest and limit the number of strokes in order not to damage of RC Pile. - To maintain verticality Pile, then at Driven Process constantly monitored by theodolith placed

perpendicular upfront and in side of Driven Pile. - Decreased Pile that has been marked with flashy paint each 20 cm interval carefully noted the

number of strokes from the beginning to the end in Form of Pile Driving Log and then signed and submitted to Director (Owner).

- Pile Driving performed continuously until it reaches pile penetration as determined by the

Consultant / Director with a particular set of conditions without approaching Ram stroke is considered critical by the manufacturer and do not exceed the specified total number of strokes.

- Before Final penetration, made Calendaring form on paper millimeter blocks placed on RC Pile and the final decision must be approved by Director.

- Pile test by PDA method at point where the biggest burden stake occur as instructed Director (If

any / determined)

0.2 L 0.6 L 0.2 L

Page 75: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Pile Driven Process

Material Transportation

Driven Process

Construction Method as Below :

At first, Cut top pile will start by cutting Top elevation by Concrete cutter (gerinda) to sign of

border, so cutting proces getting smooth On top the brder, demolishing by manually (man

with tools (Hammer, etc)

Page 76: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

FLOW CHART of RC PILE 20x20

Driven Process

Loading and Delivery on Transportation Vehicle

Transportation of material

Setting out of Piling

Aproval

Placed into Work Site

Connecting (if any)

Finished Pile Driven

Cut of Top Pile (If any)

Pile Driven

FINISH

START

Finished Earth Work (Excavation of River bank)

Ok

No Finished Earth Work (Structure Excavation)

Ok

No

Pile Driven

Ok

No

RC Pile Installation at Driver Pile

Ok

No

Ok

No

Ok

No

Next Construction (Parapet /

Retaining wall

Page 77: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

CONSTRUCTION METHOD FOR PARAPET / RETANING WALL

Page 78: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Description;

- Structure Type Segmental (@ 12m) - Construction;

Based of The drawing, Work site divide to 2 side of River. Left River and Right River. For this Construction, Contractor will construction this work by some Group of Works

Base of Work volume; for Left Retaining Wall (North) = 2 group of works for Right Retaining Wall (South) = 1 group of work

North South

Based to the drawing, Location of Retaining will constructed side of River and there is Distance between Water and Location Not need Cofferdam

Construction Sequence of Retaining Wall

Type C 763 m WN.5950+12 - WN.6700+26 889 m WN.6800+29 - WN.7650+44

813 m WN.6800+15 - WN.7600

1576 m 889 m

First Stage = Footing structure

Second Stage = structure Wall

Work Direction

Page 79: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

- Before, Construction of Structure Excavation & Construction Of RC Pile 20x20 L=3 m Has been Finished

Pile Driven Process

Material Transportation

Driven Process

Construction Method as Below : At first, Cut top pile will start by cutting Top

elevation by Concrete cutter (gerinda) to sign of

border, so cutting proces getting smooth On top the brder, demolishing by manually (man

with tools (Hammer, etc)

- Sub Grade Preparation (compaction by Man pwer and hand Stamper) - Cut Top Pile

- Lean Concrete

Page 80: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Construction

Construction will be constructed by overlaping

each segmental as Chees Board = @12m (as according to the drawing)

- Production of Concrete Ready Mix

Construction of Footing

Structure Construction;

- Reinforcing Steel and Form

work - Concreting by ready mix

Equipment;

- Batching Plant & Truck mixer

- Bar bender dan bar cutter - Concrete Vibrator

- Tools

Page 81: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Reinforcing Steel and Formwork

Equipments; - Bar bender and bar cutter

- Scafolding - Tools

At construction of Reinforcing and form work, Dowel bar and PVC Water Stop should be given for construction joint next structure. Location as according to the Drawing

Concreting

Equipments; - Batching Plant

- Truck Mixer - Concrete Pump

- Concrete Vibrator

- Tools

Page 82: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

FLOW CHART OF PARAPET (RETAINING WALL)

Sand & Lean Concrete

Chek

Ok

No

Reinforcing Steel & Formwork (Footing)

Chek

Ok

No

Concreting

Chek

Ok

No

Reinforcing Steel & Formwork (Wall)

Chek

Ok

No

Concreting

Chek

Ok

No

Back Fill by selected excavation

Chek

Ok

No

FINISH

START (1 Segment)

Finished Earth Work (Structure Excavation) & RC Pile 20x20

Ok

No

Finished Earth Work (Excavation of River bank)

Ok

No

Next Segment

Chek

Ok

No

Joint Sealent

Chek

Ok

No

FINISH all Parapet

Page 83: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

CONSTRUCTION METHOD FOR ROAD

- Based to the drawing, Location of Road will be constructed side of River and there is Distance between Water and Location Not need Cofferdam

Type B 1448 m WN.4950+25 - WN.6400+10

Work Direction

Page 84: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Description; - For Fence Construction, Structure Type Segmental (@ 5m)

- Construction; Based of The drawing, Work site on Right River.

For this Construction, Contractor will construction this work by 1 Group of Work

Base of Work volume; for Right Retaining Wall (South) = 1 group of work

Works Consist of; - Earth Work Structure Excavation by Machinery & Man

- Fence;

Wet masonry 1pc : 4 sand Concrete K175 for column and sloof / toping construction

Galvanish Pipe Ø 2” for holding of Wire mesh Fence

Wire mesh Fence h=1.2m Ø 6mm - Road

Precast Concrete Curb with mortar Sand

Precast Concrete Tile 30x30x6cm K-175 (for pedestrian) Other location at WN4400 up to WN 4600

Page 85: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Construction Sequence

Page 86: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Page 87: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Detail 1. Wet Stone Masonry, Mortar 1 pc : 4 sand

Assumption : 1. Work by Labors and tools (include concrete mixer)

2. Work location :Structure as according to the drawing

Description : 1. Stone materials delivered to work site.

The stone is used ;

- The stone is clean , hard, without weak seams or cracks and shall be of a kind known to be durable.

- The stone is flat, wedge or oval shaped and able to be closely interlocked when placed

together. - Unless otherwise directed by the engineer, stones have a thickness of not less than 15

cm, a width of not less than one and half times their respective thickness, and a length of not less than one and a half times their respective width.

2. Cement, sand and water with comparison / composition as according to technical specification are mixed became mortar by labor and tools or by Concrete mixer (if

necessary)

3. The stone is cleaned and watering all the surface with water before placed

4. Work by labor and tools with stage as following;

4.1. Placing of mortar; - Preparing work location as the drawings and technical specification.

- Mortar bedding layer is spread on sides of stones adjacent to the one being placed - The thickness of the mortar in the range 2 cm to 5cm and is the minimum

necessary to ensure all voids between the placed stones are completely filled.

- The extent of the mortar bedding placed at any one time is limited so that stones are placed only in fresh, unset mortar.

4.2. Placing of stones

- A bedding of fresh mortar at least 3 cm thick is placed on the prepared foundation

immediately before placing each stone in the first course. Large selected stone is used for the bottom course and in the corners. Care shall be taken to avoid

grouping of stones of the same size - Stones are laid with their longest face horizontal and the exposed face of

individual stones is set parallel to the face of the wall in which the stones are set - The stones are handled so not to jar or displace the stones already set.

At placing is provided with weep holes with location and weep hole material as

according the drawings and technical specification.

5. For elevation using with wood and yarn (between the wood)

6. Finishing after installation.

Page 88: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

Page 89: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

FLOW CHART (PRODUCTION BY CONCRETE MIXER)

Water Sand Cement

Mixed by concrete mixer

Stones Material

Cleaned and

Wetted

Mortar materials

Construction (Location 1)

Finishing

Production By Labors & Tools

Ok

No

Ok

No

Distribute by Labors & Tool (handcarts)

Construction in Others Locations

Ok

No

Finishing

START

FINISH

Page 90: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

2. Precast Concrete for Pedestrian 2.1. Precast Concrete Curb

Assumption : 1. Work by labors and tools

2. Work Location ; concrete Curb as according to The drawing (For Pedestrian /

Trotoar)

Description : 1. Quality of Curb Material as according to technical specification produced in base

camp/work shop (Fabrication of Curb material)

2. Transportation/delivery of curb material from base camp/work shop to work location

by Flat truck/Dump truck /transport equipment

3. Base/bed of curb to be constructed ( Sand Mortar 1:3) As according to technical specification.

4. Continued, the curb installed on mortar layer and installation with smooth/well where height of curb equalized one and the other

5. Finishing after installation have been done

Page 91: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

FLOW CHART

Material Fabrication in

Base Camp/work

shop

Work Site Preparation

Check

No

Transportation/delivery of curb by flat truck

Ok

Stock pile material in work site.

Delivery of concrete Class

Bo by truck mixer, and

mortar production on work sites by concrete mixer

Curb Installation (include filling gap between curb with mortar)

Finishing and curing

Start

Finish

Page 92: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

2.2. Precast Concrete Tile (paving block) Assumption: 1. Work by Labor and tools (manually) 2. Location : For Pedestrian / Trotoar

Description: Concrete Paving Block executed after sand bedding have been finished with thickly as

according to the drawings /as according to Technical Specification.

1. Concrete Paving Block delivered to work site 2. Form/Dimension of Concrete Paving block is determined as according to Drawings

and Technical Specification.

3. Construction;

3.1. Curb, Common Embankment and Sub Grade Preparation has been finished.

3.2. Sand Bedding.

The Material is delivered into work site by dump truck and spread / placing by labor and tools. Fill compacted is 10 cm thickness as according to the drawing.

3.3. Installation / placing of paving block

The block installed to be started from back part or edge straight and walk forwards above sand bedding sand which have been spread / placed. Joint,

including chamfer between paving block, not less 2 mm or more than 6 wide

mm .

3.4. Gap between paving block and side beginning , drainage structure or other building which cannot fill with full paving block , filled with paving block which

have been cut. Cutting done with Hydraulic splitter, saw masonry , or other

equipment which result in good shape ( mechanically cut to shape tolerance when abutting curb and edges). Gap measure between side and block or

structure which more than 6mm not be accepted or paving block is laid in such a manner the block are not in direct contact with each other and that

uniform joint of between 2mm and 3mm wide are formed. No block shall be

reused if cut to less than 25% of their original size.

3.5. Continued bedded of paving block. Paving block is bedded flush by at least two passes of heavy-duty plate compactor fitted with a rubber bas-pad. The

compactor as according to technical specification. The difference in level between edges of adjacent pavers not exceed 2.0 mm.

3.6. After the units have been bedded, sand for filling the joint spread over the surface of the units and brushed into the joints that all joints are completely

filled. Joint is filled as soon as practicable after bedding and on the day the units are laid and bedded

3.7. Paved areas is further compacted by at least three passes of a plate compactor fitted or other wise determined to technical specification and approved to the

engineer (as according to trial compaction).

Compaction process it’s that the sand material can be filled gap between block interlocking

Page 93: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

FLOW CHART OF PAVING BLOCK

For detail Construction of

- Embankment Describe / Refer to Construction Method For Earth Work (as describe on previous page)

- Reinforcing Steel

- Concrete Describe / Refer to Construction Method For Parapet (as describe on previous page)

Paving block Checking : - Dimension - Quality of Paving block - As according to asked

specification

Result

Ok

No

Looking for another material

Delivered Paving block to stock area/storage

Delivered Paving block to work site

Paving block installation / laid by Labor an Tools

Check

Ok

No

Compaction of paving block by compactor

Next laid / Installation step by step

Curb , Common embankment (sub grade preparation) &

Sand Bending

Check

Ok

No

START

FINISH

Page 94: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

FLOW CHART OF ROAD

START (1 Segment)

Finished Earth Work (Structure Excavation)

Ok

No

Wet Masonry 1pc:4sand

Chek

Ok

No

Instal Galvanis Pipe , Reinforcing steel and Form

work for Column

Chek

Ok

No

Concreting for Column

Chek

Ok

No

Reinforcing steel and Form

work for sloof

Chek

Ok

No

Back fill with Selected

excavation

Chek

Ok

No

Precast Concrete Curb & back Fill

hek

k

o

Sand & Paving Block / Precast concrete Tile

Chek

Ok

No

FINISHED

Next Segment

Chek

Ok

No

Elastic Joint Filter

ChekC

OkO

NoN

FINISHED

Next Construction (Embankment for dike with Borrow material)

Installation Wire Mesh Fence

Chek

Ok

No

Page 95: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

6. OTHERS SUPPORTING OF CONSTRUCTION 6.1. Cooperation with the Supplier for Material Construction and Specific sub-

contractors The Contractor shall cooperate with Competent of Sub contractors and Supplier in their

field and with approval directors / Owner. Regularly and periodically, contractor will

evaluate the work and materials, where the results of the evaluation to be a reference for during Construction

if the results of evaluation of sub-contractors and Suppliers are satisfactory (Refer to

technical specifications), Contractor will continue to use services of sub-contractors and suppliers during Construction process, otherwise it will look for a replacement contractor

and other parties who are competent in their field and with the approval of board of

directors / Owner

6.2. Quality and quantity Control - To ensure implementation of quality control used Quality Management System

Standard ISO (International Standard) which is owned by the contractor include:

▪ Make Creating Project Quality Plan. ▪ Make Construction’s Procedures.

▪ Make Work Instructions. ▪ Make Inspection and Test Plan

- To ensure that any material to be used has to meet the requirements of the

specification and the production process has complied with the procedures specified

in the requirements specification and any outcome of any work actually meets the requirements of the specification and drawings, required a Project Quality Plan (Project

Quality Plan) by Technical Specifications. - To ensure the implementation of the Quality Assurance system, need a means of

quality control is to perform Internal Quality Audit and External Quality Audit conducted

periodically during the contract period.

6.3. Technical Aspects of Safety and Security Asset In this construction, specially in technical aspects of safety, contractor will implement

"Procedure of Implementation of K-3".

For Operating Procedures K-3 and Labor, Contractor / Service Provider using the

procedures specified work and has received Certificate Management System Occupational Health and Safety from the Department of Labor of the Republic of

Indonesia and OHSAS Certificates.

In terms of security of assets, contractor will work with the relevant security forces, the

internal security of the use of a reliable force in the field.

Insurance Program will also provided at starting time, during construction and final construction of project according technical specification / tender documents.

Page 96: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

LOGO / SIMBOL – SIMBOL K3

6.5. Critical anticipation

To ensure of Construction can be completed on time, time perion as determined by Time Schedule, translated again to schedule two (2) weekly, weekly to daily.

Monitoring of daily Schedule will be executed every day and always in "Up Date" by

Construction on work site, if delay of construction on that day, delay should be

replaced the next day, for example by adding working hours or other means so that delays can be met.

KESELAMATAN DAN KESEHATAN KERJA

KESELAMATAN

KERJA KESEHATAN

KERJA

Page 97: METHOD STATEMENT - Brantas Abiprayaknowledge.brantas-abipraya.co.id/wp-content/uploads/2014/03/Metode... · METHOD STATEMENT Project Name : ... Technical Control is a process of activities

RiverImprovement

7. CLOSING For the construction that not be detailed in this construction Method, will be constructed as

according to;

- All detail and construction sequence will reference and as according to Construction Sequence

was described in “technical specification” in tender document, include the addendum document (if any), which apart of tender document

- All construction, with form, dimension, type, detail as according to the drawing (shop

Drawing)

- All construction reference and use and will meet all standards specified in the "Technical

Specifications" in the tender document including additional documents / addendum (if any) and other applicable standards in the Republic of Indonesia.

- Construction will be done by experts in their field

- Construction will get maximum results, precision and neat in accordance to technical specifications and the drawing.

Surabaya, 19th November 2012 PT. BRANTAS ABIPRAYA (Persero)