me 414w/415w project management project management
TRANSCRIPT
ME 414W/415W Project Management
Project Management
ME 414W/415W Project Management
Project Management
DILBERT’S BOSS
ME 414W/415W Project Management
A Balancing Act
Deliverables Cost Quality
ME 414W/415W Project Management
Learning How
ME 414W/415W - http://www.me.psu.edu/sommer/me415/
MBA Industrial training programs
ME 414W/415W Project Management
Planning
Technical Time Resources
– Personnel– Equipment and Facilities– Budget
ME 414W/415W Project Management
Benefits of Planning
Framework for communication– Clients and coworkers
Allocate resources– Personnel, equipment and facilities, budget
Benchmark to measure progress
ME 414W/415W Project Management
Planning - Fundamentals
Establish Performance Standards at the BEGINNING
Use Decision Trees/Matrices, QFD, Taguchi Methods
Assure Performance Standards as Project Progresses
Verify Final Performance Against Standards NO SUPRISES!
ME 414W/415W Project Management
Time Planning
Identify TASKS Estimate DURATION of Tasks Establish PRECEDENCE of Tasks Record MILESTONES (Performance and
Dated) Plan Start and Finish DATES for Tasks
ME 414W/415W Project Management
Models
Gantt Charts - Bar Charts CPM/PERT - Network Control Charts - Planned versus Actual http://www.mne.psu.edu/me415/resources/doc
s/gantt chart.pdf
ME 414W/415W Project Management
Example Gantt ChartID Task Name Duration
1 Get final report from PSU 5d
2 Get blueprints for old hardware 1d
3 Time-motion study of existing hardware 2d
4 Design electrical and pneumatic renovations4d
5 Schedule down-time with production supervisor2d
6 Schedule truck to pickup hardware at PSU1d
7 Inform PSU about pickup 2d
8 Schedule contractor for electrical and pneumatic1d
9 Transport hardware from PSU 2d
10 Shut down production line 1d
11 Remove old hardware 2d
12 Store old hardware (just in case) 10d
13 Renovate electrical and pneumatic 2d
14 Install new hardware 3d
15 Shake-down test by engineering 2d
16 Training for production supervisor 2d
17 Shake-down test by production supervisor2d
18 Training for production workers 1d
19 Restart production 1d
20 Time-motion study of new hardware 2d
21 Scrap old hardware 3d
Wilbur
Wilbur
Orville,Production supervisor
Wilbur
Orville,Production supervisor
Orville
Orville
Wilbur
Trucking company
Production supervisor
Shop machinist
Wilbur
Contractor for electrical and pneumatic
Shop machinist
Wilbur,Orville
Orville,Production superv
Wilbur,Orvill
Orville
Producti
O
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T FApr 23, '00 Apr 30, '00 May 7, '00 May 14, '00 May 21, '00 May 28, '00
ME 414W/415W Project Management
Gantt Chart
Tabulate Project Tasks– Title and ID Number for Each Task– Estimate Duration of Each Task– Estimate Resource Requirements for Each Task
(May Need Dummy Tasks for Critical Resources) Identify Prerequisite Tasks for Each Task Layout Bar Chart with One Bar per Task
based on Time Add Dated Milestones
ME 414W/415W Project Management
Example Gantt ChartID Task Name Duration
1 Get final report from PSU 5d
2 Get blueprints for old hardware 1d
3 Time-motion study of existing hardware 2d
4 Design electrical and pneumatic renovations4d
5 Schedule down-time with production supervisor2d
6 Schedule truck to pickup hardware at PSU1d
7 Inform PSU about pickup 2d
8 Schedule contractor for electrical and pneumatic1d
9 Transport hardware from PSU 2d
10 Shut down production line 1d
11 Remove old hardware 2d
12 Store old hardware (just in case) 10d
13 Renovate electrical and pneumatic 2d
14 Install new hardware 3d
15 Shake-down test by engineering 2d
16 Training for production supervisor 2d
17 Shake-down test by production supervisor2d
18 Training for production workers 1d
19 Restart production 1d
20 Time-motion study of new hardware 2d
21 Scrap old hardware 3d
Wilbur
Wilbur
Orville,Production supervisor
Wilbur
Orville,Production supervisor
Orville
Orville
Wilbur
Trucking company
Production supervisor
Shop machinist
Wilbur
Contractor for electrical and pneumatic
Shop machinist
Wilbur,Orville
Orville,Production superv
Wilbur,Orvill
Orville
Producti
O
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T FApr 23, '00 Apr 30, '00 May 7, '00 May 14, '00 May 21, '00 May 28, '00
ME 414W/415W Project Management
Gantt Chart - Pros and Cons
Strengths– See Status of Each Task at Any Point in Time– See Overlapping and Parallel Tasks
Weaknesses– Unable to Tell if the Entire Project is on Time for
Highly Dependent Projects– Difficult to Show Critical Path
ME 414W/415W Project Management
CPM/PERT
Critical Path Method Program Evaluation and Review Technique
ME 414W/415W Project Management
Example PERT Chart
Design electrical andpneumatic renovations
4 4d
5/4/00 5/9/00
Schedule down-time withproduction supervisor
5 2d
5/10/00 5/11/00
Renovate electrical andpneumatic
13 2d
5/17/00 5/18/00
Get final report from PSU
1 5d
4/27/00 5/3/00
Schedule contractor forelectrical and pneumatic
8 1d
5/12/00 5/12/00
Inform PSUabout pickup
7 2d
5/5/00 5/8/00
Removeold hardware
11 2d
5/15/00 5/16/00
Shut down production line
10 1d
5/12/00 5/12/00
Install new hardware
14 3d
5/19/00 5/23/00
Schedule truck to pickuphardware at PSU
6 1d
5/4/00 5/4/00
Get blueprints for oldhardware
2 1d
4/27/00 4/27/00
Time-motionstudy ofexisting hardware
3 2d
5/4/00 5/5/00
Store old hardware (justin case)
12 10d
5/17/00 5/30/00
Transport hardware fromPSU
9 2d
5/9/00 5/10/00
ME 414W/415W Project Management
CPM/PERT Tabulate Project Tasks
– Title and ID Number for Each Task– Estimate Duration for Each Task D=(O+4M+P)/6
O = Optimistic, M = Most Likely, P = Pessimistic
– Estimate Resource Requirements for Each Task (May Need Dummy Tasks for Critical Resources)
Identify Prerequisite Tasks for Each Task Layout Flowchart of Tasks Based on
Dependencies NOT Time Indicate Performance Milestones on Flowchart
ME 414W/415W Project Management
CPM/PERT - continued Calculate Earliest Completion Time and
Latest Completion Time– Beginning at start of project, ECT for task = ECT
for preceding node + duration– Beginning at end of project, LCT for task = LCT for
following node - duration
Calculate Slack Time for Each Task– Slack for Task= ECT - LCT
Determine Critical Path– Longest Time Path– Zero Slack
ME 414W/415W Project Management
Example PERT Chart
Design electrical andpneumatic renovations
4 4d
5/4/00 5/9/00
Schedule down-time withproduction supervisor
5 2d
5/10/00 5/11/00
Renovate electrical andpneumatic
13 2d
5/17/00 5/18/00
Get final report from PSU
1 5d
4/27/00 5/3/00
Schedule contractor forelectrical and pneumatic
8 1d
5/12/00 5/12/00
Inform PSUabout pickup
7 2d
5/5/00 5/8/00
Removeold hardware
11 2d
5/15/00 5/16/00
Shut down production line
10 1d
5/12/00 5/12/00
Install new hardware
14 3d
5/19/00 5/23/00
Schedule truck to pickuphardware at PSU
6 1d
5/4/00 5/4/00
Get blueprints for oldhardware
2 1d
4/27/00 4/27/00
Time-motionstudy ofexisting hardware
3 2d
5/4/00 5/5/00
Store old hardware (justin case)
12 10d
5/17/00 5/30/00
Transport hardware fromPSU
9 2d
5/9/00 5/10/00
ME 414W/415W Project Management
CPM/PERT – Pros and Cons Strengths
– Shows Task Dependencies– Predicts Critical Path– Identifies Slack Time for Resources
Weaknesses– Assumes Subsequent Task Starts Immediately
After Prerequisite Concludes– Difficult to Visualize Timing
ME 414W/415W Project Management
Control Charts
Quality– Statistical Process Control
Schedule– Gantt, Milestone, PERT
Budget– Commitment– Performance– Cash Flow
ME 414W/415W Project Management
Budget Control Chart
ME 414W/415W Project Management
Resource Planning
LINK TO TIME PLANNING Personnel
– In-House– Vendors and Subcontractors– Circle-dot chart
ME 414W/415W Project Management
Circle-dot Chart
TASKDueDate
DateCompleted MOE LARRY CURLY SHEMP
A
B
C
D
E
ME 414W/415W Project Management
Resource Planning - continued Equipment and Facilities
– May Need to Add Dummy Tasks for Critical Resources
– Downtime for Expected Maintenance or Failure Budget
– Often Not Under Direct Control of Project Team– Contingency Funds– Variable Value of Money
Inflation International Currency
ME 414W/415W Project Management
Project Management is …
ME 414W/415W Project Management
… a Balancing Act