Aggregate PlanningOperations Management
byP. Kalyanasundaram
-
8/14/2019 MBA IInd SEM POM Chapter 07 AggregatePlanningsimplfied
2/20
13-4
Types of OperationalPlanning Activities
TIME FRAME18 months 5+years
6-18 months
1 day 6 months
ACTIVITYLong-range planning
Medium-rangeplanning
Short-range planning
-
8/14/2019 MBA IInd SEM POM Chapter 07 AggregatePlanningsimplfied
3/20
ProductionPlanning
-
8/14/2019 MBA IInd SEM POM Chapter 07 AggregatePlanningsimplfied
4/20
The Role of the Aggregate
Plan
-
8/14/2019 MBA IInd SEM POM Chapter 07 AggregatePlanningsimplfied
5/20
Aggregate PlanningBased on composite (representative)products:
Simplifies calculationsForecasts for grouped items are moreaccurate
Considers trade-offs between holdinginventory & short-term capacitybased on workforce
-
8/14/2019 MBA IInd SEM POM Chapter 07 AggregatePlanningsimplfied
6/20
Aggregate Production
PlanningPurpose: specify the combination of production rate, workforce level, and
inventory on-hand that satisfies theforecasted demand at the lowest cost.Production rate: quantity of productproduced per unit of time (autos/day).Workforce level: number of workersrequired to meet a specific level of output.Inventory on hand: unsold units carriedover from one period to the next.
-
8/14/2019 MBA IInd SEM POM Chapter 07 AggregatePlanningsimplfied
7/20
13-6
Managing DemandPricingAdvertising and Promotion
Backlogs and ReservationsDevelop Alternative Products
-
8/14/2019 MBA IInd SEM POM Chapter 07 AggregatePlanningsimplfied
8/20
13-7
Managing Supply
(Capacity)Overtime/UndertimeHiring/Firing of Personnel
Temporary/Part-time PersonnelSubcontractingAdjusting InventoriesAdjusting Lead Times
-
8/14/2019 MBA IInd SEM POM Chapter 07 AggregatePlanningsimplfied
9/20
13-5
Objectives and
ApproachesObjectives:Match Supply and Demand (Effectiveness)
Minimize Costs (Efficiency)ApproachesReactive approach:
Allow volume forecasts based on Marketingplan to drive production planning
Proactive approach:Coordinate Marketing & Production plans tolevel demand using advertising & price
incentives
-
8/14/2019 MBA IInd SEM POM Chapter 07 AggregatePlanningsimplfied
10/20
Aggregate Plan StrategiesChase strategy:Match the production rate to meet thedemand rate by adjusting the workforcelevel (hiring/firing) as the demand ratechanges. Minimize finished goodinventories by matching demandfluctuations.
Level strategy:Use a stable workforce working at aconstant production rate. Use
inventories and backorders to absorbdemand eaks and valle s.
-
8/14/2019 MBA IInd SEM POM Chapter 07 AggregatePlanningsimplfied
11/20
Pure Aggregate Strategies
-
8/14/2019 MBA IInd SEM POM Chapter 07 AggregatePlanningsimplfied
12/20
-
8/14/2019 MBA IInd SEM POM Chapter 07 AggregatePlanningsimplfied
13/20
-
8/14/2019 MBA IInd SEM POM Chapter 07 AggregatePlanningsimplfied
14/20
Planning Links to MPS
-
8/14/2019 MBA IInd SEM POM Chapter 07 AggregatePlanningsimplfied
15/20
Role of the MPSAggregate plan:
Specifies the resources available ( e.g .:
regular workforce, overtime,subcontracting, allowable inventorylevels & shortages)
Master production schedule:Specifies the number & when to produceeach end item (the anticipated buildschedule)
Disaggregates the aggregate plan
-
8/14/2019 MBA IInd SEM POM Chapter 07 AggregatePlanningsimplfied
16/20
Objectives of Master
ScheduleThe Master Scheduler must:Maintain the desired customer service
levelUtilize resources efficientlyMaintain desired inventory levels
The Master Schedule must:Satisfy customer demandNot exceed Operations capacityWork within the constraints of the
Aggregate Plan
-
8/14/2019 MBA IInd SEM POM Chapter 07 AggregatePlanningsimplfied
17/20
Developing an MPSThe Master Scheduler:
Develops a proposed MPSChecks the schedule for feasibility with
available capacityModifies as needed
Authorizes the MPSConsider the following example:
Make-to-stock environment with fixed orders of 125 units There are 110 in inventory to startWhen are new order quantities needed tosatisfy the forecasted demand?
-
8/14/2019 MBA IInd SEM POM Chapter 07 AggregatePlanningsimplfied
18/20
The MPS Record
Projected Available = beginning inventory + MPS shipments - forecasted demand
The MPS row shows when replenishment shipments need to arrive toavoid a stock out (negative projected available)
W e e k BI 1 2 3 4 5 6 7 8 9 10 11 12
Forec as t 50 50 50 50 75 75 75 75 50 50 50 50
P rojec ted available 110 60 10 -40
M P S
W e e k B I 1 2 3 4 5 6 7 8 9 1 0 1 1 1 2
F orec as t 50 50 50 50 75 75 75 75 50 50 50 50
P rojec ted available 1 10 60 10 85 35 -40
M P S 125
-
8/14/2019 MBA IInd SEM POM Chapter 07 AggregatePlanningsimplfied
19/20
Revised and Completed MPSRecord
W e e k BI 1 2 3 4 5 6 7 8 9 10 11 12
Forec as t 50 50 50 50 75 75 75 75 50 50 50 50
P rojec ted available 110 60 10 85 35 85 10 -65
M PS 125 125
W e e k BI 1 2 3 4 5 6 7 8 9 10 11 12
Forecast 50 50 50 50 75 75 75 75 50 50 50 50
P rojec ted available 110 60 10 85 35 85 10 60 110 60 10 85 35
M PS 125 125 125 125 125
-
8/14/2019 MBA IInd SEM POM Chapter 07 AggregatePlanningsimplfied
20/20
Evaluating the MPSRough-cut capacity planning:
An estimate of the plans feasibility
Given the demonstrated capacity of critical resources (e.g.: direct labor &machine time), have we overloaded thesystem?
Customer service issues:Does available-to-promise inventorysatisfy customer orders? If not, can
future MPS quantities be pulled in to