may 21-25, 2007phase ii fsr1 iss hardware magnetic susceptibility testing and analysis trent martin...

17
May 21-25, 2007 Phase II FSR 1 ISS Hardware Magnetic Susceptibility Testing and Analysis Trent Martin NASA AMS Project Manager 281-483-3296 [email protected]

Upload: bonnie-butler

Post on 30-Dec-2015

213 views

Category:

Documents


0 download

TRANSCRIPT

May 21-25, 2007 Phase II FSR 1

ISS Hardware Magnetic Susceptibility Testing and Analysis

Trent Martin

NASA AMS Project Manager281-483-3296

[email protected]

May 21-25, 2007 Phase II FSR 2

History

• To minimize operations constraints, the AMS project worked with Hamilton Sundstrand, Boeing, and MacDonald Dettwiler Robotics to ascertain realistic limits for ISS hardware

• Testing/analysis was performed specifically on EVA equipment and nearby ORU’s

• Without substantial additional funding MDR was unable to raise the level of certification of the SSRMS above a 10 gauss limit

• SSRMS limitations may require a reduction in the magnetic field during nearby SSRMS usage

May 21-25, 2007 Phase II FSR 3

35G

100G

200G

300G

600G

1000G

Geometric center of AMS-02 Cryomagnet

Y(OUT OF PAGE)

Z

X

Y

Z

X-RAM(INTO PAGE)

ORBITER

ISS(PAS)

May 21-25, 2007 Phase II FSR 4

XZ

Y

Y Z(into page)

X-RAM

ISS(PAS)

ORBITER

35G

100G

200G

300G

600G

Geometric center of AMS-02 Cryomagnet

1000G

May 21-25, 2007 Phase II FSR 5

Solar Array Rotary Joint

AMS

S3 Truss

ISS Outboard

35G

100G

200G

300G

600G

1000G

Adjacent Attached Payload Envelope

May 21-25, 2007 Phase II FSR 6

AMS with ELC

6 Gauss10 Gauss

35 Gauss

May 21-25, 2007 Phase II FSR 7

EVA Tool Testing• Testing performed June 5-9, 2000 in Advanced Space

Propulsion Lab (ASPL), at the Sonny Carter Facility and at the Hamilton Sundstrand Space Systems EMC Facility

• The purpose was to evaluate the Extravehicular Mobility Unit (EMU) System level, Flight Accessory, SAFER and PGT equipment operation for exposure to magnetic B field exposure during EVA

• Equipment was suspended in various orientations and moved through field to determine susceptibility up to a maximum field of 600 gauss

• Results were documented in Report: FEM-0032 and EMU 1- 13-054

• Results were used to raise certification level of this hardware from 63 gauss, to 300 gauss.

May 21-25, 2007 Phase II FSR 8

EMU w/ ERCA setup (Horizontal)

May 21-25, 2007 Phase II FSR 9

EMU w/ ERCA setup (Vertical)

May 21-25, 2007 Phase II FSR 10

SAFER setup

May 21-25, 2007 Phase II FSR 11

PGT Setup

May 21-25, 2007 Phase II FSR 12

Testing of ISS ORU’s near AMS

• The Boeing Company analyzed and tested nearby ORU’s on the S3 Truss to ensure no susceptibility based on the magnetic field that would be present at their locations

• No issues were identified

May 21-25, 2007 Phase II FSR 13

SSRMS

• No testing has been performed on the Space Station Remote Manipulator Systems (SSRMS)

• Without other funded analysis MacDonald Dettwiler Robotics (MDR) has certified that the SSRMS can sustain up to 10X the earths magnetic field; roughly 10 gauss (total)

• Therefore, AMS magnet must either be deactivated while attached to the SSRMS or have a reduced field when SSRMS is operating in close proximity (adjacent attached payload site)

• While this is not ideal for mission success, AMS accepts this provisional operation for ISS Safety

May 21-25, 2007 Phase II FSR 14

Magnetic Field

• Certification Testing– Magnetic Field Mapping of the AMS-02 Cryomagnet– Magnetic Field Testing

• US EMU – Wireless Video System (WVS)/EMU RF Camera Assembly (ERCA)

transmits video but cannot switch lenses when exposed to fields in excess of 350 Gauss. Corrects itself when removed from field.

– Magnetic attraction of the EMU flight system equipment may exert a force of 8 lbs 4 oz when exposed at 600 Gauss. At this same level, the SAFER could not provide a means to rescue the crewmember.

– 300 Gauss set as new limit (factor of safety = 2)• Russian Orlan Suit – 175 Gauss set as new limit• Pistol Grip Tool (PGT)

– Stopped functioning at 250 Gauss, but recovered once removed from field.

– No damage at all up to 1000 Gauss.• Simplified Aid For EVA Rescue (SAFER)

– Experienced no failure at 1000 Gauss

May 21-25, 2007 Phase II FSR 15

Magnetic Field

• Certification Analysis– ISS Electromagnetic Effects Panel has reviewed

the following items which fall are on the S3 truss – all are acceptable with various caveats

• Umbilical Mechanism Assembly (UMA) • Capture Latch Assembly (CLA) • External TV Camera • Video Luminaire Assembly• Space Station Remote Manipulator System (SSRMS)• Special Purpose Dexterous Manipulator (SPDM)• RPCM• MDM

May 21-25, 2007 Phase II FSR 16

Component Design Magnetic

Field Level

Expected Worst Case AMS

Magnetic Field Level

Keep Out Zone Level

or Rational for no Keep Out Zone

EMU (Space Suit) 300 G 1000 G 300 G

Orlan (Russian Suit) 175 G 175 G 175 G

PGT >1000 G 1000 G 300 G (operates up to 250 G)

SAFER > 1000 G 1000 G 300 G

UMA None Established

(NE)

<6 G Fixed hardware that only operates in a field less than 6 G if an

adjacent payload is installed – currently not planned

External TV Camera NE <6 G Fixed Component

Video Luminaire Assembly

NE <6 G Fixed Component

SSRMS NE 8.4 G 10 G

SPDM NE 8.4 G 10 G

RPCM NE <6 G Fixed Component

MDM NE <6 G Fixed Component