material requirements planning isqa 459 class 4 mellie pullman

20
Material Requirements Material Requirements Planning Planning ISQA 459 Class 4 Mellie Pullman

Upload: walker-delanoy

Post on 29-Mar-2015

231 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: Material Requirements Planning ISQA 459 Class 4 Mellie Pullman

Material Requirements Material Requirements PlanningPlanning

ISQA 459 Class 4 Mellie Pullman

Page 2: Material Requirements Planning ISQA 459 Class 4 Mellie Pullman

Materials Requirements Materials Requirements PlanningPlanning

Material Requirements Planning (MRP)MRP Logic and Product Structure

TreesMRP ExampleLot Sizing in MRP Programs

Page 3: Material Requirements Planning ISQA 459 Class 4 Mellie Pullman

Material Requirements Material Requirements PlanningPlanning

Materials requirements planning (MRP) is the logic for determining the number of parts, components, and materials needed to produce a product.

MRP provides time scheduling information specifying when each of the materials, parts, and components should be ordered or produced.

Dependent demand drives MRP.MRP is a software system.

Page 4: Material Requirements Planning ISQA 459 Class 4 Mellie Pullman

Example of MRP Logic and Example of MRP Logic and Product Structure TreeProduct Structure Tree

B(4)

E(1)D(2)

C(2)

F(2)D(3)

A

Product Structure Tree for Assembly ALead TimesA 1 dayB 2 daysC 1 dayD 3 daysE 4 daysF 1 day

DemandDay 10 50 ADay 8 20 B (Spares)Day 6 15 D (Spares)

Given the product structure tree for “A” and the lead time and demand information below, provide a materials requirements plan that defines the number of units of each component and when they will be needed.

Page 5: Material Requirements Planning ISQA 459 Class 4 Mellie Pullman

LT = 1 day

Day: 1 2 3 4 5 6 7 8 9 10A Required 50

Order Placement 50

First, the number of units of “A” are scheduled backwards to allow for their lead time. So, in the materials requirement plan below, we have to place an order for 50 units of “A” in the 9 th week to receive them in the 10th week.

Page 6: Material Requirements Planning ISQA 459 Class 4 Mellie Pullman

Next, we need to start scheduling the components that make up “A”. In the case of component “B” we need 4 B’s for each A. Since we need 50 A’s, that means 200 B’s. And again, we back the schedule up for the necessary 2 days of lead time.

Day: 1 2 3 4 5 6 7 8 9 10A Required 50

Order Placement 50B Required 20 200

Order Placement 20 200

SparesLT = 2

B(4)

E(1)D(2)

C(2)

F(2)D(3)

A 4x50=200

Page 7: Material Requirements Planning ISQA 459 Class 4 Mellie Pullman

Day: 1 2 3 4 5 6 7 8 9 10A Required 50

LT=1 Order Placement 50B Required 20 200

LT=2 Order Placement 20 200C Required 100

LT=1 Order Placement 100D Required 55 400 300

LT=3 Order Placement 55 400 300E Required 20 200

LT=4 Order Placement 20 200F Required 200

LT=1 Order Placement 200

B(4)

E(1)D(2)

C(2)

F(2)D(3)

A

40 + 15 spares

Part D: Day 6

Finally, repeating the process for all components, we have the final materials requirements plan:

7

Page 8: Material Requirements Planning ISQA 459 Class 4 Mellie Pullman

Material Requirements Material Requirements Planning SystemPlanning System

Based on a master production schedule, a material requirements planning system:Creates schedules identifying the

specific parts and materials required to produce end items.

Determines exact unit numbers needed.

Determines the dates when orders for those materials should be released, based on lead times.

Page 9: Material Requirements Planning ISQA 459 Class 4 Mellie Pullman

Firm orders from knowncustomers

Forecastsof demand

from estimates

Aggregateproduct

plan

Masterproductionschedule

(MPS)

Materialplanning(MRP)

Engineeringdesign

changes

Bill ofmaterial

file

Inventorytransactions

Inventoryrecord

file

Reports

9

Page 10: Material Requirements Planning ISQA 459 Class 4 Mellie Pullman

Bill of Materials (BOM) FileBill of Materials (BOM) FileA Complete Product DescriptionA Complete Product Description Materials Parts Components Production sequence Modular BOM

Component or Subassemblies BOM Planning BOM or kits

create an artificial parent to the BOM used for inexpensive items like washers or pins to group.

Explosion: revealing the requirements for each component.

Page 11: Material Requirements Planning ISQA 459 Class 4 Mellie Pullman

CodingCoding

If identical items exist at various levels in the BOM: Item is coded at

lowest level at which it occurs

D (Level 2 or Level 3)

This number identifies the part at the lowest level of usage.

A

B C

D E E F

G D

Page 12: Material Requirements Planning ISQA 459 Class 4 Mellie Pullman

Inventory Records FileInventory Records File

Buckets= time units in MRP system Week bucket vs. day bucket

Each inventory item carried as a separate file Status according to “time buckets”.

Pegging Identify each parent item that created demand.

Parent vs. child Parent= Items above the current level Child = Items below the current level

Page 13: Material Requirements Planning ISQA 459 Class 4 Mellie Pullman

Primary MRP ReportsPrimary MRP Reports

Planned orders to be released at a future time.

Order release notices to execute the planned orders.

Changes in due dates of open orders due to rescheduling.

Cancellations or suspensions of open orders due to cancellation or suspension of orders on the master production schedule.

Inventory status data.

Page 14: Material Requirements Planning ISQA 459 Class 4 Mellie Pullman

Secondary MRP ReportsSecondary MRP Reports

Planning reports, for example, forecasting inventory requirements over a period of time.

Performance reports used to determine agreement between actual and programmed usage and costs.

Exception reports used to point out serious discrepancies, such as late or overdue orders.

Page 15: Material Requirements Planning ISQA 459 Class 4 Mellie Pullman

Additional MRP Additional MRP Scheduling TerminologyScheduling Terminology

Gross Requirements: needed during each period.

Scheduled Receipts: Existing orders that arrive at beginning of period.

On-hand or available balance:

(depending on software convention, could be at the beginning of each period or end):

Book: Inventory balance at end of each period.

Net requirements: What is need to meet requirements and safety stock.

Planned order receipt: arrives at beginning of period.

Planned order release: Addresses lead time.

Page 16: Material Requirements Planning ISQA 459 Class 4 Mellie Pullman

MRP ExamplesMRP Examples

Page 17: Material Requirements Planning ISQA 459 Class 4 Mellie Pullman

Closed Loop MRPClosed Loop MRP

Production PlanningMaster Production SchedulingMaterial Requirements PlanningCapacity Requirements Planning

Realistic?No

Feedback

Execute:Capacity PlansMaterial Plans

Yes

Feedback

Page 18: Material Requirements Planning ISQA 459 Class 4 Mellie Pullman

Lot Sizing in MRP Lot Sizing in MRP ProgramsPrograms

Lot-for-lot (L4L)Economic order quantity (EOQ)Least total cost (LTC)Least unit cost (LUC)Part Period Balancing-changing lot

sizes to reflect requirements in the future (how many periods should be combined to reduce cost)

Page 19: Material Requirements Planning ISQA 459 Class 4 Mellie Pullman

MRP GameMRP GameDifferent types of lot sizes

Page 20: Material Requirements Planning ISQA 459 Class 4 Mellie Pullman

Tinker Toy Lawn MowerTinker Toy Lawn Mower