material requirement and planning

14
INDUSTRIAL ECONOMICS AND MANGEMENT MUHAMMAD ASIM 14ME127 SECTION-A

Upload: asim-irshad

Post on 12-Apr-2017

48 views

Category:

Economy & Finance


2 download

TRANSCRIPT

Page 1: Material Requirement and Planning

INDUSTRIAL ECONOMICS AND MANGEMENT

MUHAMMAD ASIM

14ME127

SECTION-A

Page 2: Material Requirement and Planning

INTRODUCTION

Production Planning and Control(PPC)

has three phases namely

• Planning Phase

• Action Phase

• Control Phase

Page 3: Material Requirement and Planning

“Getting the right materials to the right place at the right time”.

Page 4: Material Requirement and Planning

WHAT IS MATERIAL REQUIREMENT PLANNING??

“Materials Requirement Planning (MRP) is a technique for determining the quantity and timing for the acquisition of dependent demand items needed to satisfy master production schedule requirements.”

Page 5: Material Requirement and Planning

MATERIAL REQUIREMENT PLANNING(MRP)• Material Requirements Planning (MRP) is a production planning,

 scheduling, and inventory control system used to manage manufacturing processes. Most MRP systems are Software-based, but it is possible to conduct MRP by hand as well.

• It is a planning and scheduling technique with fixed lead time.

• It is a technique used to plan and control manufacturing inventories (these manufacturing inventories support the production process).

• It is computerized inventory system.

• Material Requirement Planning (MRP) is a system of planning and scheduling the time phased material requirements for releasing materials and receiving materials that enable the master production schedule to be implemented.

Page 6: Material Requirement and Planning

HISTORY

• In 1964, as a response to the Toyota Manufacturing Program(TMP), Joseph Orlicky developed Material Requirements Planning (MRP). The first company to use MRP was Black & Decker in 1964, with Dick Alban as project leader.

Page 7: Material Requirement and Planning

WHEN IT IS REQUIRED

• Manufacturing industries generally face the problems that demand is high than production. This requires some level of planning.

• Information Technology plays a major role in designing and implementing. Material Requirements Planning systems and processes provides information about manufacturing needs and also about inventory

Page 8: Material Requirement and Planning

OBJECTIVES

The MRP system should have at least these objectives.

• To assure that the materials and components are available for planned production.

• Maintain the lowest possible level of inventory.

• Plan manufacturing activities, delivery schedules and purchasing activities

• Reduction in the manufacturing and delivery lead times

• Realistic delivery commitments

• Increased efficiency

Page 9: Material Requirement and Planning

• Specifically organizational objectives of MRP are identified among three main dimensions, as

follows.

Page 10: Material Requirement and Planning

MRP SYSTEM

The inputs to the MRP system are

• A master production schedule

• An inventory status file

• Bill of materials (BOM).

The output of MRP system are

• Orders to be placed.

• Order rescheduling.

• Planned orders for future.

Page 11: Material Requirement and Planning

CLASSES OF MRP USER/COMPANIES

MRP systems fall into four categories, in terms of use and organizational implementation. • Class A represents full implementation of MRP. System is tied up with company’s

financial system as well as capacity planning etc.• Class B represents a less than full implementation. MRP system is confined in

the manufacturing area.• Class C represents a classical MRP approach in which the system is confined to

management of inventories. • Class D represents a data processing application of MRP. System is used for

keeping track of data rather than as decision-making tool.

Page 12: Material Requirement and Planning

ADVANTAGES OF MRP

• Improved Business Results

• Improved Manufacturing Results

• More Accurate And Timely Information

• Less Inventory

• Material wastage is less

• Higher Reliability

• More Responsiveness To Market Demand

Page 13: Material Requirement and Planning

DISADVANTAGES OF MRP

• Increase In Material Acquisition Cost

• Higher Transportation Costs And Higher Unit Cost

• Potential Hazard Of A Production Slowdown Or Shutdown

• Use Of Standardized Software Packages

Page 14: Material Requirement and Planning

Don’t become a follower, be a leader, and become a Entrepreneur