master's thesis / diplomarbeit identification of lean enablers for program management

159
Master’s Thesis / Diplomarbeit Identification of Lean Enablers for Program Management by Kristian Kinscher © Kristian Kinscher 2011. All rights reserved. Signature of the Author ______________________________________________________________ Kristian Kinscher Mechanical Engineering, RWTH Aachen University Certified by ________________________________________________________________________ Dr. Josef Oehmen Thesis Supervisor Research Scientist, Lean Advancement Initiative (LAI), MIT Accepted by _______________________________________________________________________ Marcus Rauhut Thesis Supervisor Research Scientist, Laboratory for Machine Tools and Production Engineering WZL, RWTH Aachen University

Upload: others

Post on 04-Feb-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

Master’s Thesis / Diplomarbeit

Identification of Lean Enablers for Program Management

by Kristian Kinscher

© Kristian Kinscher 2011. All rights reserved.

Signature of the Author ______________________________________________________________

Kristian Kinscher

Mechanical Engineering, RWTH Aachen University

Certified by ________________________________________________________________________

Dr. Josef Oehmen

Thesis Supervisor

Research Scientist, Lean Advancement Initiative (LAI), MIT

Accepted by _______________________________________________________________________

Marcus Rauhut

Thesis Supervisor

Research Scientist, Laboratory for Machine Tools and Production Engineering WZL, RWTH Aachen University

Page 2: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management
Page 3: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

I Acknowledgments i

I Acknowledgments

I would like to express my heartfelt gratitude to the individuals who supported me throughout

the research of this thesis.

First and foremost, I would like to thank my advisor Dr. Josef Oehmen from the Lean

Advancement Initiative (LAI) of the Massachusetts Institute of Technology (MIT) for his

excellence guidance and relentless support. Furthermore, I would like to thank Dr. Eric

Rebentisch who contributed a lot of guidance and without whom a contact to the Lean

Advancement Initiative could not have been established.

In Germany, my biggest thanks go to Prof. Dr. Günther Schuh and Dr. Bastian Franzkoch

who made it possible for me to write my diploma thesis at MIT. In addition, I would like to

thank Marcus Rauhut for supervising my thesis from the side of the Laboratory for Machine

Tools (WZL) in Germany.

My greatest thanks go to all researchers and staff of the Lean Advancement Initiative for their

contributions to my thesis. Especially, I would like to thank the program managers of the

Lean Advancement Initiative – Sean Dorey, Dan Marticello, Gregory McKnew, Dave Morgan

and Dustin Ziegler - for their time in many hours of interviews. I would also like to thank Sid

Rupani, Christoph Knoblinger, and Stephan Baur for being great lab partners and real

friends. I owe my biggest thanks especially to Denis Bassler since he was not only a good

squash and lab partner, but also contributed many valuable ideas in countless discussions.

Page 4: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

II Abstract ii

II Abstract

Companies and governments grapple with an environment of increasing complexity in large-

scale and highly innovative engineering development programs. Program management is

recognized as a key tool to manage the transition of project-based organizations to face

these difficulties. However, there are major challenges in program management: First, there

are immense differences between people’s concepts of what program management is.

Second, conjoined with the unclear definition is a lack of a framework specifically for

engineering development program management. Third, there is no comprehensive

compilation of common issues and pitfalls in engineering programs. Last, there is no

approach adapting the idea of “lean thinking” to program management.

These challenges led to major research questions for this thesis: first, “What is program

management and how can it be defined?”; second, “Is there a framework for engineering

program management?”; third, “What are common pitfalls in program management?”; fourth

and last, “Are there ways to adapt “lean thinking” to program management?”

The findings in this thesis are: First, program management in the context of engineering

development programs can be defined as “the management of multiple related projects and

the resulting enterprise over an extended period of time to deliver a complex value

proposition and utilize efficiency and effectiveness gains.” Second, there is a framework

provided by the Lean Advancement Initiative (LAI) which includes both aspects of program

management – cross-cutting program management capabilities and an engineering program

life cycle. The framework is verified in this thesis through interviews, a survey and insights

from an industry focus group. It is structured in six major parts: Program Execution;

Enterprise Management; Scoping, Planning & Contracting; Technology Integration; Product

Design; and Production, Use, Service & Decommissioning. Third, 99 pitfalls in engineering

programs, mapped to the LAI program management framework, were identified. Fourth, 310

Lean Enablers customized to program management are described in detail. In addition, a

mapping of the Lean Enablers to program management pitfalls is carried out to highlight

potential areas of application of the Lean Enablers.

This thesis is based on extensive literature reviews, interviews with Air Force program

managers, a survey and insights from an industry focus group consisting of seven industry

companies in the aerospace and defense sectors and two organizations.

Page 5: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

III Table of contents iii

III Table of contents

I  Acknowledgments ........................................................................................................... i 

II  Abstract ........................................................................................................................... ii 

III  Table of contents ........................................................................................................... iii 

1  Introduction ..................................................................................................................... 1 

1.1  Program management can help reaching performance goals .................................. 1 

1.2  Research Goals ........................................................................................................ 2 

1.3  Thesis organization .................................................................................................. 3 

2  Current state and research gaps in program management ....................................... 6 

2.1  Existing program management frameworks ............................................................. 6 

2.1.1  Defense Acquisition System of the United States Department of Defense .......... 7 

2.1.2  Managing Successful Programmes (MSP) of the United Kingdom Government 10 

2.1.3  The Standard for Program Management of the Project Management Institute

(PMI) 13 

2.1.4  Lean Advancement Initiative (LAI) program management framework ................ 17 

2.1.5  Comparison of existing frameworks .................................................................... 20 

2.2  Issues in program management ............................................................................. 29 

2.3  Introduction to lean management ........................................................................... 29 

2.4  Identified gaps in current literature ......................................................................... 30 

2.5  Research approach ................................................................................................ 31 

2.5.1  Literature review ................................................................................................. 32 

2.5.2  Interviews ............................................................................................................ 32 

2.5.3  Surveys ............................................................................................................... 33 

2.5.4  Industry focus group ........................................................................................... 33 

2.6  Summary of current state of program management ............................................... 35 

3  Definition of program management ............................................................................ 36 

3.1  Definition of project management ........................................................................... 36 

3.2  Definition of program management ........................................................................ 38 

3.3  Summary ................................................................................................................ 42 

4  Selection of a framework for engineering programs ................................................ 44 

4.1  Discussion of current state of program management in industry ............................ 45 

Page 6: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

III Table of contents iv

4.2  Validation of the LAI program management framework ......................................... 46 

4.2.1  Insights from interviews with program managers ............................................... 47 

4.2.2  Insights from the industry focus group ................................................................ 54 

4.3  Summary ................................................................................................................ 55 

5  Common issues and pitfalls in program management ............................................. 57 

5.1  Identification of common program management pitfalls ......................................... 57 

5.2  Verification of the pitfalls through interviews and the industry focus group ............ 67 

5.3  Mapping pitfalls to program management framework ............................................. 68 

5.4  Summary ................................................................................................................ 72 

6  Lean Enablers in program management .................................................................... 74 

6.1  Sources of Lean Enablers ...................................................................................... 74 

6.1.1  Introduction to Lean Enablers in the context of program management .............. 75 

6.1.2  Discussion and comparison ................................................................................ 76 

6.2  Findings along the Lean Principles ......................................................................... 76 

6.2.1  Principle 1: Specification of customer value ....................................................... 77 

6.2.2  Principle 2: Value Stream definition .................................................................... 77 

6.2.3  Principle 3: Creation of a continuous flow ........................................................... 78 

6.2.4  Principle 4: Pull of the value ............................................................................... 79 

6.2.5  Principle 5: Striving for perfection ....................................................................... 79 

6.2.6  Principle 6: Respect for People .......................................................................... 79 

6.3  Synthesis in one general framework ....................................................................... 80 

6.4  Assessment through the industry focus group ...................................................... 102 

6.5  Summary .............................................................................................................. 102 

7  Mapping of Lean Enablers to program management pitfalls ................................. 103 

7.1  Methodology for the mapping ............................................................................... 103 

7.2  Results of the mapping process ........................................................................... 104 

7.3  Verification through review by the industry focus group ....................................... 111 

7.4  Summary .............................................................................................................. 112 

8  Conclusion and research outlook ............................................................................. 113 

IV  Table of symbols and abbreviations ........................................................................... iv 

V  Index of literature .......................................................................................................... vi 

VI  Table of figures and spreadsheets ............................................................................ xxi 

Page 7: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

III Table of contents v

VII  Appendix A .............................................................................................................. xxv 

VIII  Appendix B ............................................................................................................. xxxi 

Page 8: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

1 Introduction 1

1 Introduction

Whereas project management is well understood and much research and literature exists for

it, there is little guidance for program management. The time since the 1990s is

characterized by highly dynamic, highly uncertain and very quickly executed projects

(Williams 1999). Projects have often been perceived as happening in isolation and current

research partly still uses this approach (Fricke and Shenhar 2000).

Current requirements and user needs are often too complex to be achieved by a single

project. By executing large developments in multiple parallel projects, a program

management environment is created (Haughey 2001). Examples of the benefits of a program

organization are the ability to introduce process standardization or a coordinated use of a

common pool of (limited) resources (Platje 1993; Fricke and Shenhar 2000).

1.1 Program management can help reaching performance goals

The concept of program management is used by both companies and governmental

organizations, but both sectors struggle with its execution. For example, companies in the

aircraft industry, with their highly complex products, often do not reach their cost and

schedule goals. The A380 program of Airbus (Michaels) as well as Boeing’s 787

(Dreamliner) (Tang and Zimmerman 2009) missed their originally stated cost and schedule

aims by several billion dollars and several years.

On the governmental side, the US Department of Defense, for example, runs an enormous

number of programs. Many of them, categorized as “major defense acquisition,” are

equipped with vast budgets, totaling $1.6 trillion in the federal fiscal year 2009. In the same

year, the Department of Defense spent $384 billion for contracts on goods and services. As

of March 10 2010, the Department of Defense was facing a cost overrun of $296 billion and

an average schedule overrun of 22 months in the major acquisition programs, with R&D

costs being an average of 45% over budget (GAO 2010).

Figure 1-1 shows the cost overrun of the entire Department of Defense acquisitions portfolio

for each of three recent fiscal years. It is clear that the deviation over the years became

larger rather than smaller.

Page 9: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

1 Introduction 2

42,0%40,0%

37,0%

25,0%26,0%

FY2008

50%

40%

30%

20%

10%

0%FY2007FY2003

19,0%

Change in total cost

Change in RDT&E cost

Figure 1-1: Total Department of Defense acquisition portfolio: actual cost compared to

initial estimate (GAO 2006; GAO 2010)

Though the idea of program management is already widely used in larger companies and

governmental organizations, it is obvious that there is a vast potential for achieving further

benefits through its correct application.

1.2 Research Goals

Despite the rising importance of program management, there is a widespread lack of a clear

understanding of what it is. Therefore, the term “program management” must be defined to

establish a common base for further discussions. Since there is no doubt in the current

literature that the success of a program is highly dependent on project management, the first

step toward establishing a definition of program management should be to provide a clear

definition of project management.

An extensive literature review on program management reveals multiple facets in current

research. Including all important aspects in a definition of the term will provide one that is not

only comprehensive but also hopefully can be widely accepted.

In addition to general program management, there are some specialized frameworks for a

program management environment. Most of these approaches have shortcomings in certain

characteristics due to their specialization and are not used in industry. Based on research

undertaken by the LAI and on the generally accepted literature, a new program management

framework is proposed in this thesis and included in the comparison of existing approaches.

Page 10: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

1 Introduction 3

This framework is one that is intended to provide a knowledge base for every program

manager – commercial and governmental – and to avoid any shortcomings since there is no

specialized context for this framework.

Further, this thesis gives an overview of existing lean management literature. Based on the

different recognized sources a set of promising lean enablers for a program management

environment can be identified.

The identification of the most common pitfalls in program management provides a base for

the application of these lean enablers. By connecting the lean enablers and the pitfalls telling

conclusions about the applicability of “lean thinking” to program management can be derived.

One possible insight can be the type of distribution of pitfalls according to different framework

parts and the corresponding lean enablers.

1.3 Thesis organization

Figure 1-2 shows the general thesis organization. The different research domains addressed

are shown on the left side. Program management embraces all chapters within this thesis.

The idea of “lean thinking” or lean management is only found during identifying the lean

enablers and the corresponding mapping to the program management pitfalls. In addition,

the figure shows the different research question and where they are answered. All research

questions are posed during the initial literature review in chapter 2. Further, the different

research approaches and the parts where they are utilized in this thesis are displayed.

Page 11: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

1 Introduction 4

Research QuestionChapter in Thesis

Research Approach

RQ4: Are there ways to adapt lean thinking to 

PM?Chapter 6

RQ3: What are common pitfalls in PM? Chapter 5

RQ2: Is there a framework for engineering PM?

Chapter 4

RQ1:What is program management and how can it be defined?

Chapter 3

Literature

review

Interviews

Survey

IFG

X

X X X X

X X X

X X

X

Research Domain

Program

 Man

agem

ent

Lean

 Man

agem

ent

Chapter 6

Figure 1-2: Thesis organization

In chapter 2 of this thesis a literature review on current research about program management

and lean management is described. During this review different gaps can be identified.

These gaps lead to research question which are phrased in the different sections. Figure 1-3

shows the four research question of this thesis and the section where the gap corresponding

with the question is discovered.

Page 12: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

1 Introduction 5

Research Question 4:Are there ways to adapt lean thinking to program management?

Research Question 3:Are there common pitfalls in program management?

Research Question 2:Is there a framework for engineering program management?

Research Question 1:What is program management and how can it be defined?

Chapter 2.3

Chapter 2.2

Chapter 2.1

Figure 1-3: Research question and corresponding sections in chapter 2

Chapter 3 answers the first research question. This chapter fills the gaps of the missing

understanding of program management by suggesting a definition based on multiple different

facets used in the current literature.

The second gap is addressed in chapter 4. Different aspects of program management are

considered and the necessary elements for a framework for technical development program

are determined. Based on these findings a framework will be selected and necessary

improvements of it are further investigated.

The identification of common pitfalls in program management is explained in detail in chapter

5. Based on an extensive literature review a first collection of challenges is presented and

afterwards improved and validated through interviews and insights from an industry focus

group.

In chapter 6 the way to a comprehensive pool of lean enablers for program management is

explained. Further, the different lean enablers are briefly explained.

Together with chapter 6, chapter 7 answers the fourth and last research question about the

way to adapt “lean thinking” in program management. This chapter explains a method to map

the findings of the pitfalls and lean enablers to highlight possible connections. These

connections could be used to effectively obviate occurring pitfalls during a program

execution.

The last chapter of this thesis - chapter 8 – summarizes the findings and gives and succinct

research outlook. Further, imaginable shortcomings of this thesis are shown and possible

improvement potentials in the research approaches are presented.

Page 13: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 6

2 Current state and research gaps in program

management

This chapter will provide an overview of the existing literature in the fields of program

management and lean management. Figure 2-1 shows the four research questions of this

thesis and how they correspond to the sections of this chapter.

The first part of this chapter will describe various existing frameworks for program

management and compare them in detail. The different frameworks have diverse focuses,

and their ways of understanding and defining program management differ. In addition,

common issues and pitfalls in program management will be discussed briefly. Furthermore,

the idea of lean management and its basic principles will be explained in this chapter. The

contents of this chapter provide the foundation of knowledge which is necessary in order to

proceed further through this thesis.

Research Question 4:Are there ways to adapt lean thinking to 

program management?

Research Question 3:Are there common pitfalls in program 

management?

Research Question 2:Is there a framework for engineering 

program management?

Research Question 1:What is program management and how 

can it be defined?

Chapter 2.3

Chapter 2.2

Chapter 2.1

Summary2.4

Research Approach

2.5

Figure 2-1: Correlation of the research questions and sections

2.1 Existing program management frameworks

There are some existing frameworks for program management in the current literature. This

chapter will briefly describe four different frameworks. Furthermore, the frameworks will be

compared and assessed regarding various aspects. These aspects will be developed within

this chapter.

Basically, the current literature describes two fundamental aspects of program management:

- Programs as a method for organizational change (this might include the use of small

change projects)

Page 14: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 7

- Programs in an engineering environment in the context of large development efforts

and the management of multiple related projects

In this chapter, examples of frameworks will be presented which especially emphasize one or

both of the aspects.

2.1.1 Defense Acquisition System of the United States Department of

Defense

A widely accepted and used framework in the United States is the one utilized by the

Department of Defense (DoD) in the context of defense acquisitions. A defense acquisition

“includes design, engineering, test and evaluation, production, and operations and support of

defense systems” (University 2009). The Joint Capabilities Integration and Development

System (JCIDS) identifies capability gaps in the current equipment and organizations using a

capabilities-based assessment (CBA) (University 2011). Figure 2-2 shows how the JCIDS fits

in the general decision-making support systems (University 2009). While the JCIDS is

responsible for the identification of capability gaps, the Planning, Programming, Budgeting,

and Execution (PPBE) Process is the Department of Defense’s process for crafting plans

and programs to satisfy the demands of the National Security Strategy. The Defense

Acquisition System is the management process for acquiring new materiel (including, for

example, weapon systems and automated information systems) (University 2011).

Figure 2-2: DoD Decision Support Systems (University 2011)

Capability gaps can be transformed into needs and possible solutions based on the

DOTMLPF guideline (University 2009). The DOTMLPF guideline enables the DoD to find

Page 15: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 8

solutions structured along different possibilities with different extents (e.g., necessary

organizational changes, budget):

- Doctrine: the way the military acts and fights; e.g., new maneuvers

- Organization: the organizational structures within the military; e.g., Army, Navy, Air

Force, etc.

- Training: the training which is necessary for fighting; e.g., different types of training

(basic vs. advanced)

- Materiel: all resources to equip the forces; e.g., weapons, spares, etc.

- Leadership and education: the education of the leaders of the forces; e.g., different

ranks (squad leader up to general)

- Personnel: accessibility of well-trained people for different purposes (fighting,

peacetime, etc.)

- Facilities: installations and facilities; e.g., government owned ammunition production

facilities (Defense 2010; University 2011)

In the context of this thesis, the acquisition of materiel is the special focus. New materiel is

acquired within defense acquisitions, which are part of the Defense Acquisition System (see

Figure 2-2). In general, the system is defined by the Department of Defense Directive

5000.01 (DoDD 5000.01) (DoD 2003) and the Department of Defense Instruction 5000.02

(DoDI 5000.02) (DoD 2008). While DoDD 5000.01 focuses on policies and principles to

govern defense acquisition, the DoDI 5000.02 provides a management framework to

implement these policies and principles (University 2009; University 2011).

Depending on the category of defense acquisition, the processes differ in details; e.g.,

different persons are in charge for milestone decisions. These categories depend on the

budget of the acquisition. Table 2-1 gives an overview of the different categories and the

criteria.

Table 2-1: Different Categories of defense acquisitions (University 2009)

Budget

>$365M for research,

development, testing

and evaluation; or total

procurement >$2.190B

>$140M for research,

development, testing

and evaluation; or total

procurement >$660M

Less than other

categories

Acquisition categories

for weapon systems

ACAT I

(major defense

acquisition)

ACAT II ACAT III

Acquisition categories

for automated

information systems

ACAT IA does not apply ACAT III

Page 16: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 9

The Defense Acquisition Management System is an event-based process and structured

along the life cycle of a program. Figure 2-3 shows the life cycle from the identification of

user needs, technology opportunities, and resources to operations and support or finally

decommissioning.

Figure 2-3: Life cycle for defense acquisitions (University 2011)

The pre-systems acquisition is the first phase of the life cycle and incorporates material

solution analysis and technology development. The purpose of this phase is to reduce

technology risk, determine appropriate technologies, and show the capabilities of these

technologies by building representative prototypes. In addition, a traceable requirements flow

to complete a preliminary design for the full requirement is often established (University

2011). The technology development phase starts with the results of the Analysis of

Alternatives (AoA) on a high level of abstraction. The goal is to narrow the scope to continue

development. The technology development phase might include different types of reports

(e.g., System Requirements Review (SRR), System Functional Review (SFR), Preliminary

Design Review (PDR), etc.) that ensure accurate documentation (University 2011).

There is a first milestone during the pre-systems acquisition phase that is required by DoDI

5000.02 (DoD 2008). Milestone A includes multiple technology development demonstrations

to ensure that the chosen technology is affordable, militarily useful, and based on mature

technology (University 2011). This guarantees that no unsuitable technologies are used for

further development during the life cycle.

Milestone B at the end of the technology development phase is based on a Capability

Development Document (CDD) and approves the acquisition strategy, the program baseline,

and the type of contract for the next phase and allow the program to enter the next phase

(University 2009). The CDD provides more details on the material solutions and contains the

thresholds and objectives for the system attributes to measure the delivered capabilities

(University 2009).

The first phase during systems acquisition is engineering and manufacturing development.

The purpose of this phase is to develop the technologies entering from Milestone B to a level

Page 17: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 10

which is ready for production. This involves contract definition (with suppliers), complete full-

system integration, development of a manufacturing process, ensure operational

supportability, further documentation, etc. (University 2009; University 2011).

After engineering and manufacturing development, Milestone C authorizes entry into low-rate

initial production (LIRP), if required. The documents submitted for Milestone C should include

completion/approval dates for the Capability Production Document (CPD). The CPD as an

approach for Milestone C is similar to the CDD as an approach for Milestone B. In addition to

the CPD, the requirements of the Initial Production Baseline (IPB) have to be fulfilled, and the

technical reviews have to be completed (University 2011). If Milestone C approves low-rate

initial production, an additional subsequent review is necessary to authorize full-rate

production (University 2009).

During the production and deployment phase, the system is produced and delivered for

operational use. The focus during this phase is to ensure an economical production and

meet the user requirements. It might be necessary to conduct further tests with repetition

parts (University 2009).

The last phase of a program life cycle is operations and support. Full operational capability is

achieved during this phase. Operational readiness is assessed and should be established.

Further, logistics support (e.g., supply, maintenance, training, etc.) is evaluated. This phase

also includes life cycle sustainment and at the end the disposal of the system (University

2009).

DoDI 5000.02 describes the requirements during the different phases of the program life

cycle. To provide guidance, the Defense Acquisition University (DAU) published the Defense

Acquisition Guidebook (University 2011), which describes the steps and tools necessary

during each program phase. The Defense Acquisition Guidebook references additional

literature for specific topics. This literature often focuses on a single topic and offers in-depth

knowledge (e.g., “Manager's Guide to Technology Transition in an Evolutionary Acquisition

Environment” (Defense 2005) or “Risk Management Guide for DoD Acquisitions” (Defense

2006)).

2.1.2 Managing Successful Programmes (MSP) of the United Kingdom

Government

A framework in widespread use in the United Kingdom is that presented in “Managing

Successful Programmes” (MSP) published by the Office of Government Commerce (OGC)

(Commerce 2007). They provide a framework to manage programs – “a temporary, flexible

organization created to coordinate, direct and oversee the implementation of a set of related

projects and activities in order to deliver outcomes and benefits related to the organization’s

strategic objectives […] and is likely to have a life that spans several years" (Commerce

2007).

The OGC further defines program management as “the action of carrying out the coordinated

organization, direction and implementation of a dossier of projects and transformation

activities […] to achieve outcomes and realize benefits of strategic importance to the

Page 18: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 11

business” (Commerce 2007). It states that there are three critical organizational elements for

program management:

- Corporate strategy

- Delivery mechanisms for change

- Business-as-usual environment (Commerce 2007)

Figure 2-4 shows the MSP framework, which is based on three concepts:

- Outer ring: MSP principles; the principles are based on lessons learned from both

positive and negative observations of programs

- Second ring: MSP governance themes; the governance themes allow the definition,

measurement, and control of the organization’s approach to program management.

They enable the organization to find the right leadership, delivery team,

organizational structures, and information control to achieve the planned outcomes

and realize the expected benefits

- Inner circle: MSP transformational flow; this part of the framework represents the

life cycle of the program from its conception, through delivery of benefits and desired

outcomes, to the implementation of the benefits and the close of the program

(Commerce 2007).

Page 19: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 12

Figure 2-4: The “Managing Successful Programmes” framework of the Office of Government

Commerce (Commerce 2007)

The MSP framework is used to manage programs that deliver change in parts of an

organization, the entire organization, multiple organizations, or the environment of the

organization (Commerce 2007). The inner circle of the MSP framework shows the

transformational flow, which is an iterative process to achieve the change (Commerce 2007).

This flow represents the life cycle of the program and is structured in three major parts:

- Defining a program: This phase provides the baseline for the further development of

the program. It should include the creation of the program definition document,

plans/schedules, and the control framework (Commerce 2007).

- Managing the tranches: Based on the baseline from the definition phase further tasks

are executed to deliver the capability and realize benefits. The projects and activities

during this phase are grouped into tranches. Each tranche delivers a different part

necessary for the change. Throughout this phase it is essential to monitor the

Page 20: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 13

progress and observe the external environment to ensure that the program is still on

track (Commerce 2007).

- Closing the program: This phase is initiated when the necessary capabilities to

achieve the change are fully developed and implemented. It must be judged whether

the program was successful or not. In addition, it has to be assessed, wheter the

implemented change will be beneficial in the business-as-usual environment. Beside

the planned closure of a program due to the completion of the work, there are

additional possible reasons for a program ending: changes in the external

environment, changed strategy, evidence that goals cannot be achieved by the

program, evidence that the remaining benefits to be realized are disproportionate to

the necessary effort, and the discovery of more beneficial methods for achieving the

outcome (Commerce 2007).

2.1.3 The Standard for Program Management of the Project Management

Institute (PMI)

The Project Management Institute (PMI) is an American non-profit professional organization

(Institute 2011). PMI is well known for its project management framework described in “A

guide to the project management body of knowledge” (PMBOK guide) (Institute 2004). Based

on the established PMBOK framework, PMI published a first edition of a similar approach for

program management: “The Standard for Program Management” (Institute 2006). Two years

later an updated, improved, and three-times-longer second edition was issued (Institute

2008).

The PMI understands program management as being “the centralized coordinated

management of a program to achieve the program’s strategic objectives and benefits. It

involves aligning multiple projects to achieve the program goals and allows for optimized or

integrated cost, schedule, and effort.” (Institute 2008). The definition implies that there is a

hierarchy between projects and programs (programs consist of projects). Figure 2-5 shows

different possible structures of projects, programs, and portfolios (one level above a

program). There are projects that can be part of a portfolio directly rather than through a

program. In addition, Figure 2-5 expresses that programs always consist of at least one

project in the understanding of the PMI.

Page 21: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 14

Portfolio

ProjectsPortfolio Programs

Programs Projects ProjectsPrograms Projects

Projects Projects Projects

Figure 2-5: Portfolio, programs and projects: high-level view (Institute 2008)

The primary intention of PMI’s framework for program management is to describe and

capture generally accepted best practices. In addition, a general language for program

management and an understanding of program management in the context of portfolio and

project management are established. The framework defines all processes that are

necessary to successful execute a program (Institute 2008).

The framework primarily addresses the following groups of persons:

- Project managers: The framework provides knowledge enabling them to better

understand their own role in the context of a program organization. In addition, the

interfaces between project and program managers are described.

- Program managers: The framework ensures that they understand existing best

practices for effectively managing programs.

- Portfolio managers: The framework clarifies their role in the context of actively

managed portfolios of programs and ensures that they know their interfaces with

program managers and, if appropriate, project managers

- Stakeholders: The framework improves their understanding of the role of a program

manager and how the program manager interacts with various types of stakeholders;

the types of stakeholders are described within the framework (Institute 2008).

Figure 2-6 shows the interaction between the levels of project and program management. It

displays the information flow between those two areas. During the life cycle of a program,

many projects are initiated and overseen by the program manager. He or she provides

direction and guidance to the project managers. In general, the interactions between the

program manager and the project managers tend to be cyclical and iterative (Institute 2008).

The direction and type of interaction between the program and project levels changes during

the life cycle of project. In the early stages, the information flows from the program to the

project level. The program manager guides the project managers and frames the desired

goals and benefits. Later in the project life cycle, the project managers send reports on

Page 22: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 15

various areas – e.g., project status, risks, changes, costs, issues, etc. to the program domain

(Institute 2008).

Program Management Process

Project Management Process

Initiating Planning

Project

Project

•Project Risk•Change Request•Change in Baselines (time, cost & quality)• Issues

•Program Desired Goals•Benefits•Management Approach

ExecutingMonitoring & Controlling

Closing

Figure 2-6: Interaction between project management and program management (Institute 2008)

The upper part of Figure 2-7 shows a program life cycle. The lower part of Figure 2-7 shows

the basic steps of program benefits management. Both – program life cycle and benefits

management – being earlier, during pre-program phases, with preparations for the program

life cycle and benefits identification(Institute 2008).

During “pre-program preparations” needs are identified that are supported by a valid

business case. This is to ensure that one has a stable groundwork for the initiating of the

program (Institute 2008). Throughout the first phase of the program life cycle valid plans are

created, and information is gathered about and definitions established for organizational

strategies, internal and external influences, program drivers, and, especially, the benefits the

program is supposed to deliver (Institute 2008).

In the phase of “program initiation” the ways in which the program can be structured and

managed to generate the desired benefits are detailed. During this phase, a program charter

is created to capture all conclusion of the pre-program work. The charter normally contains

several different aspects; e.g., justification, vision, outcomes, scope, etc. (the full list can be

found on p. 24 in (Institute 2008)). Later decisions and detailed plans within the program will

be based on the charter (Institute 2008).

The phase of “program setup” is reached after passing the phase-gate review G2, which

implies that the program has received “approval in principle.” The program manager, who

has already been identified by a committee, starts to progressively elaborate the program

charter and develops a detailed “roadmap” for the future activities and directions of the

Page 23: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 16

program. Furthermore, the basic infrastructure of the program is established and a basic plan

about cost and schedule is created (Institute 2008).

In the phase of “delivery of program benefits” the program has passed another review (G3),

and the execution of the core work of the program takes place. This phase only comes to an

end when the expected benefits are achieved and are fully delivered to the customer. During

this phase, the program manager checks constantly and ensures a correct program

alignment. The project managers perform similar tasks on a project level. One must consider

that different capabilities might be deliverable earlier than others. To ensure the delivery of

the full committed benefits of the program it might be necessary to integrate these

capabilities with capabilities delivered by another project before the associated benefit can

be achieved (Institute 2008).

The last phase in the program life cycle is the “program closure.” This phase is reached

when all work is completed and the benefits are accruing. It is necessary to initiate activities

to shut down the program organization and the corresponding infrastructure. Some programs

might be completely closed, while others are managed by normal operations to ensure

support during the operation phase of the delivered product. During this phase, it is essential

to establish processes to guarantee good documentation providing feedback to different

stakeholders and manage the transition to operations (if applicable) (Institute 2008).

Usually projects as well as programs deliver benefits to the organization. In general,

programs are created to deliver bigger benefits than a single project could. While projects

normally deliver their benefits or products at the end of their life cycle, programs can do the

same or deliver parts of the benefits incrementally during their execution. Therefore, it is vital

to emphasize benefits management within the program.

Benefits management requires processes and metrics to track and measure benefits

throughout the program life cycle. Good benefits management assesses the value of

individual program benefits, identifies interdependencies within benefits, and assigns

responsibilities for the creation of the benefits. At the end of a program, the delivered benefits

must be compared to the desired and planned benefits to benchmark program performance

(Institute 2008).

Page 24: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 17

Benefits Identification

• Identify and qualify business benefits

Benefits Analysis & Planning

• Derive and prioritize components

• Derive benefits metrics

• Establish benefits realization plan and monitoring

• Map benefits into program plan

Benefits Realization

• Monitor components

• Maintain benefits register

• Report benefits

Benefits Transition

• Consolidate coordinated benefits

• Tranfer the ongoing responsibility

Program Benefits Management

Pre‐Program Preparations

Program Integration

Program Setup

Delivery of Program Benefits

Program Closure

G1 G2 G3 G4

Figure 2-7: Program life cycle and program benefits management (Institute 2008)

2.1.4 Lean Advancement Initiative (LAI) program management framework

The program management framework of the Lean Advancement Initiative (LAI) was

developed based on former work by the institute. The framework focuses on engineering

development projects in the aerospace and defense industry; the LAI refers to these as

“programs”. The generic term “project” is used for smaller-scale efforts; e.g., the

development of subsystems within the program. These programs lead to the formation of

“enterprises”. An enterprise is the interorganizational network that has the common purpose

of the development and delivery of a system. An enterprise is comprised of both public

organizations, such as the program office, as well as private organizations, such as the main

contractor and its suppliers (Stanke 2006).

Figure 2-8 shows the structure of a program and the corresponding stakeholders. The parts

shown in the brackets represent the parts being understood as the program enterprise. The

program enterprise is not just the program office, but rather the program office, the main

contractor and the 1st tier suppliers. A result of the interorganizational nature of (program)

enterprises is that they have distributed responsibility and leadership, and they have

stakeholders with both common and diverse interests.

Page 25: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 18

Government, Congress, Agencies, Services and the General Public

Program Office

Main Contractor

System Supplier 1

2nd Tier Supplier 1.1

3rd Tier Supplier 1.1.1

2nd Tier Supplier 1.y

...

System Supplier x

2nd Tier Supplier x.1

3rd Tier Supplier x.1.1

2nd Tier Supplier x.z

...

Figure 2-8: Program structure and stakeholders

Program management can be perceived as a “black box.” In general, program management

coordinates the transformation of various input factors, such as stakeholder needs,

technology, competitive actions, process definitions, organization, skills, manpower,

allocated budget, regulations, etc., into the final product, an operational system. The

representation in Figure 2-9 is clustered around the core competencies of a program

enterprise to successfully deliver the operational system, given a certain set of input factors,

or resources. The core competencies can be structured into two major parts:

- Cross-cutting program management capabilities (program execution and enterprise

management)

- Engineering life cycle processes (scoping, planning, and contracting; technology

integration; product design; production, use, service, and decommissioning)

Figure 2-9 provides an overview of the LAI program management framework. The upper part

represents general program management activities. These are independent of the type of

program and must be executed within both engineering programs and change programs.

The lower part of Figure 2-9 represents the life cycle of an engineering program. This life

cycle covers an engineering program from the decision for material development to the start

Page 26: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 19

of production. The structure of the life cycle does not represent a strict time line for the

execution; it is more a way to organize the different processes. Various activities from

diverse categories of the framework might be executed iteratively and repetitively during the

execution of the program. For example, programs can go through several spirals of planning,

technology integration, and design.

The framework focuses on the processes and organizational practices that are important for

successful program execution from both a government program office perspective and a

contractor’s perspective. Whereas some practices in the model explicitly focus on

interactions between the program office and the main contractor and on interactions within

those two entities, many recommendations are also valid for the extended program

enterprise. Furthermore, the recommendations are valid for interactions between the main

contractor and the system suppliers, between the system suppliers and their suppliers, and

so forth, and for interactions within those entities.

Scoping, Planning & Contracting

• Stakeholder needs & requirements definition

• Managing trade‐offs

• Cost estimation & life cycle costing

• Incentive alignment, contract negotiation & conclusion

• Defining lifecycle strategy

Technology Integration

• Technology maturation monitoring

• Technology transition management

Product Design

• PD team organization

• Integrated product and process development

• PD and SE best practices

• Monitoring PD progress

• Product architecting

• Value Stream Optimization

• Product design strategy

• Testing & prototyping

Production, Use, Service & 

Decommissioning

Program Execution

• Integrating and leading the program organization

• Stakeholder management

• Progress monitoring and management

• Risk management

• Project management

• Multi‐project coordination

• Developing intellectual capital

• Program manager qualifications

Enterprise Management

• Building and transforming the program enterprise

• Understanding the program enterprise

• Learning and improving the program enterprise

• Knowledge management

• Secure IT information / document sharing in the enterprise

• Program portfolio and environment management

Figure 2-9: Lean Advancement Initiative (LAI) program management framework

The program management activities are structured in six main areas: Program Execution;

Enterprise Management; Scoping, Planning, and Contracting; Technology Integration;

Product Design; and Production, Use, Service, and Decommissioning. As the LAI research

focuses on the early phases of a system’s life cycle, the last phase of the engineering life

cycle, Production, Use, Service, and Decommissioning, is not covered in the model.

Program Execution focuses on the practices for efficient execution of a program by the

government program office, the main contractor, and the system suppliers. Enterprise

Management addresses more generally those aspects that are important in creating,

Page 27: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 20

understanding, and improving large and complex enterprises. During Scoping, Planning, and

Contracting, the user needs are translated into a legal contract between the program office

and the main contractor. During Technology Integration, technologies for the design phase

are selected and integrated into the program. The readiness of low-maturity technologies

may be increased in parallel technology development tracks to a level that is suitable for their

introduction into the design process. In Product Design, system integration and the

components of the system are specified to a level that makes it fit for production. During

Production, Use, Service, and Decommissioning, the system to satisfy the user needs is

produced, delivered to the customer, serviced, and eventually dismantled. Since the last

phase is out of focus of the LAI, there are no subcategories listed in this main area.

2.1.5 Comparison of existing frameworks

Comparison of the different frameworks makes it clear that there are major differences in the

understanding of what the necessary aspects of program management are. On one hand, all

the approaches emphasize fully addressing all possible aspects program management. On

the other hand, as the remainder of this chapter will show, not all frameworks cover the same

processes and facets of program management. In addition, many authors hold that there is a

lack of a clear definition for program management in current literature (Ferns) (Williams and

Parr) (Vereecke, Pandelaere et al. 2003) (Haughey 2001) (Görög 2011). Basically, as has

been mentioned, the literature describes two fundamental aspects in program management:

- Programs as a method for organizational change (this might include the use of small

change projects)

- Programs in an engineering environment in the context of large development efforts

and the management of multiple related projects

Vereecke (Vereecke, Pandelaere et al. 2003) discusses a survey undertaken by e-

Programme.com (E-Programme.com 2011) (a website host findings of an organization

dealing with program management) early in 2001. One focus of the survey was the

identification of the common understanding of program management. The two major answers

from the respondents were that program management is “the management of organizational

change through projects that bring about change” (ca. 50%) and that it is “the management

of multiple projects” (ca. 40%) (Vereecke, Pandelaere et al. 2003).

These findings lead to the first research question of this thesis:

“What is program management and how can it be defined?”

Due to the fact that no clear definition of program management has wide acceptance, it is

even harder to find a broadly accepted framework for program management. In addition,

most descriptions of frameworks do not provide any empirical verification but rather just state

that program management has to be executed in a specific way.

This leads to the second research question, which will be answered partly in this chapter and

partly in chapter 4:

“Is there a framework for engineering program management?”

Page 28: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 21

As discussed earlier, there are two major perspectives in program management: cross-

cutting program capabilities, as majorly occurring in change programs, and a program life

cycle. Consequently, it is beneficial to assess the existing frameworks in terms those aspects

and choose the most promising one for the further development of this thesis.

The frameworks are compared and assessed based on the literature sources named in

Table 2-2. Additional publications by the same author or organization are not taken into

account. This is especially important for the framework “The Standard for Program

Management” of the Project Management Institute (Institute 2008), since many chapters are

completely blank with the comment: “This section is not included in this standard, but is

provided so as to be aligned with the PMBOK® Guide – Fourth Edition” (e.g., chapters 7,8,

and 9 (Institute 2008)). The PMI simply refers to its publication “A Guide to the Project

Management Body of Knowledge: (PMBOK guide)” (Institute 2004), which is a widely

accepted standard for project management. In the same way, the “Defense Acquisition

Guidebook” of the Defense Acquisition University (University 2011) often refers to other

publications such as “Integrated Product and Process Development Handbook” (Defense

1998), “Manager’s Guide to Technology Transition in an Evolutionary Acquisition

Environment” (Defense 2005), and “Risk Management Guide for DoD Acquisitions” (Defense

2006). Furthermore, the Office of Government Commerce also refers to its book “Managing

Successful Projects with PRINCE2” (OGC 2009) – also a standard for project management –

in the description of the “Managing Successful Programmes” framework.

Table 2-2: Literature sources for framework evaluation

Framework Literature Source

Defense Acquisition System of the United

States Department of Defense

“Defense Acquisition Guidebook” by the

Defense Acquisition University (University

2011)

Managing Successful Programmes (MSP) by

the Office of Government Commerce

“Managing Successful Programmes” by the

Office of Government Commerce

(Commerce 2007)

The Standard for Program Management of

the Project Management Institute (PMI)

“The Standard for Program Management” by

the Project Management Institute (Institute

2008)

Lean Advancement Initiative (LAI) program

management framework

Internal unpublished whitepaper

The sources which are used to compare the frameworks having been described, the criteria

need to be defined. The first set of criteria derives from the cross-cutting program

management activities. For each topic, the individual frameworks are assessed and rated on

the degree to which they address a topic on a scale with three levels:

Page 29: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 22

- Not addressed (displayed in table as )

- Somewhat addressed (displayed in table as )

- Fully addressed (displayed in table as )

Table 2-3 presents the first comparison of the frameworks. The framework topics are taken

from the various frameworks themselves. As one can see, every topic is fully addressed by

at least one framework. The exception is portfolio management, which was considered

important enough by the author to be included in the assessment but is not fully addressed

by any framework.

The major findings from the first comparison, which looks at cross-cutting program

management activities, are that all frameworks address each topic to some degree except for

the Defense Acquisition System. This is due to the fact that the DoD framework mainly

focuses on a technical program life cycle rather than general program activities.

Table 2-3: Comparison of frameworks in terms of cross-cutting program management activities

Framework

topic

Defense

Acquisition

System (see.

section 2.1.1)

Managing

Successful

Programmes

(see section

2.1.2

The Standard

of Program

Management

(see chapter

2.1.3)

LAI program

management

framework

(see section

2.1.4)

Risk

management

Progress

management

Improvement

management

Managing

organizational

influences

Forming and

improving the

program

enterprise

Information

management

Portfolio

management

Page 30: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 23

The second part of the assessment focuses on the life cycle of an engineering program. The

phases are very closely related to those of a process for new product development and

production. Cooper (Cooper 2001) defines the following steps for a Stage-Gate approach – a

broadly accepted standard for product development:

1. Discovery: Pre-work to discover and uncover opportunities and needs and create

ideas.

2. Scoping: The initial exploration of the project/product.

3. Build business case: A more detailed investigation involving primary market and

technical research. This leads to a business case with product and project definition

and justification, and the development of a master plan.

4. Development: The actual design and development phase of the product and its

production processes.

5. Testing and validation: Tests with different focuses: market acceptation, lab

evaluation of technical performance, etc.

6. Full production and market launch: Commercialization: full production of the product,

marketing, and selling (Cooper 2001)

These phases by Cooper can be transferred to a program environment. This transfer

produces the following stages:

1. Pre-Program and Program Establishment

2. Technology Development

3. Product Design

4. Production, Deployment, and Disposal

Figure 2-10 shows how the gates of the Stage-Gate process correlate with the phases of the

program life cycle. The Stage-Gate process has many stages, especially during the early

phases, but they can easily be grouped in broader categories.

Page 31: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 24

1. Pre‐Program and Program Establishment

2. Technology Development

3. Product Design

4. Production, Deployment & Disposal

1. Discovery

2. Scoping

3. Build Business Case

4. Development

5. Testing & Validation

6. Full Production & Market Launch

Program Environment Stage‐Gate Process

Figure 2-10: Correlation of program life cycle phases and the stages of a Stage-Gate process

Page 32: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 25

Table 2-4 compares the frameworks under discussion in terms of the first phase of the

program life cycle. It is obvious that the frameworks that are focusing on change programs

rather than technical programs do not fully address all aspects of this life cycle phase. The

aspect of contracting, in particular, is not normally part of change programs, because they

are mostly executed internally in an organization or company and do not require any kind of

external support. In contrast, technical development programs typically involve several

different suppliers, and they might also contribute to the development of the product. These

suppliers might even be structured hierarchically (i.e., 1st-tier suppliers as direct contractors

of the program enterprise, 2nd-tier contractors as contractors of a 1st-tier supplier, and so on).

Page 33: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 26

Table 2-4: Comparison of frameworks in terms of pre-program and program establishment

activities

Framework

topic

Defense

Acquisition

System (see.

section 2.1.1)

Managing

Successful

Programmes

(see section

2.1.2

The Standard

of Program

Management

(see chapter

2.1.3)

LAI program

management

framework

(see section

2.1.4)

Need

identification

Identification of

alternatives

Requirement

definition

Contracting

Definition of life

cycle strategy

Page 34: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 27

Table 2-5 compares the different frameworks according to how fully they address activities in

the phase of technology development. Again, it is particularly the frameworks that focus on

change programs or try to provide a broader overview of program management that do not

contribute any information about the specific necessary actions and best practices. In

addition, the Defense Acquisition System of the DoD does not provide many insights into

technology development and technology maturation monitoring, even though the main focus

of the framework is the technical program life cycle.

Page 35: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 28

Table 2-5: Comparison of frameworks in terms of technology development activities

Framework

topic

Defense

Acquisition

System (see.

section 2.1.1)

Managing

Successful

Programmes

(see section

2.1.2

The Standard

of Program

Management

(see chapter

2.1.3)

LAI program

management

framework

(see section

2.1.4)

Technology

maturation

assessment

Technology

transition

management

Table 2-6 assesses the frameworks in terms of the activities during the phase of product

design. Once more, the general program management and change program management

frameworks do not address this aspect very well. Both frameworks which include a technical

program life cycle provide information and best practices for nearly all activities during

product design. There is no aspect which is not contributed to in either of the technical

program frameworks.

Table 2-6: Comparison of frameworks in terms of product design activities

Framework

topic

Defense

Acquisition

System (see.

section 2.1.1)

Managing

Successful

Programmes

(see section

2.1.2

The Standard

of Program

Management

(see chapter

2.1.3)

LAI program

management

framework

(see section

2.1.4)

Individualizing

the design

process

Process

monitoring and

improvement

Testing and

evaluation

Page 36: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 29

A comparison of the frameworks in terms of the life cycle phase of production, deployment,

and disposal is shown in Error! Not a valid bookmark self-reference.. Since this phase is

outside the scope of this thesis, it is not broken down in the table into component activities.

The primary focus of this thesis is on development programs and not on the production of the

product itself. In addition, only one framework can contribute any insights about this phase.

Since there are no activities listed, the full circle in the table only indicates that some kind of

information and/or best practices is provided in the Defense Acquisition System framework.

Table 2-7: Comparison of frameworks in terms of production, deployment, and disposal

Framework

topic

Defense

Acquisition

System (see.

section 2.1.1)

Managing

Successful

Programmes

(see section

2.1.2

The Standard

of Program

Management

(see chapter

2.1.3)

LAI program

management

framework

(see section

2.1.4)

Production,

Deployment &

Disposal

By aggregating each framework’s ratings for the different activities of an individual program

life cycle phase, an overall rating can be produced for each framework for each life cycle

phase. All activities are weighted equally in this aggregation. An entirely filled circle means

that all activities of the life cycle phase are fully addressed while an empty circle means that

none of the activities in the phase is addressed by the framework. In total, eight different

ratings (from empty to full circle) are possible. A quarterly filled circle for example means that

one fourth of all possible activities in this life cycle phase are fully addressed (or half of the

activities can be partly addressed).

Page 37: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 30

Table 2-8 shows the results of the rating process. The only two frameworks which contribute

information and/or best practices for the different life cycle phases are the Defense

Acquisition System by the Department of Defense and the LAI program management

framework.

Page 38: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 31

Table 2-8: Comparison of frameworks in the phases of an engineering program lifecycle

Framework

topic

Defense

Acquisition

System (see.

section 2.1.1)

Managing

Successful

Programmes

(see section

2.1.2

The Standard

of Program

Management

(see chapter

2.1.3)

LAI program

management

framework

(see section

2.1.4)

Pre-Program

and Program

Establishment

Technology

Development

Product Design

Production,

Deployment,

and Disposal

To gain an even broad overview, only the two major categories – cross-cutting program

activities and the technical life cycle activities – are assessed in Table 2-9. The results show

that there is only one framework that addressed both of these categories.

Table 2-9: Overall comparison of the different frameworks

Framework

topic

Defense

Acquisition

System (see.

section 2.1.1)

Managing

Successful

Programmes

(see section

2.1.2

The Standard

of Program

Management

(see chapter

2.1.3)

LAI program

management

framework

(see section

2.1.4)

Cross-cutting

program

activities

Technical

program life

cycle activities

(not including

production)

Page 39: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 32

2.2 Issues in program management

There are a number of sources that provide valuable insights into common issues in program

management. Most of these publications focus on a specific kind of program environment.

One very helpful source for the identification of challenges, especially in the environment of

defense acquisition programs (this is in the context of the Defense Acquisition System of the

United States Department of Defense; see section 2.1.1 for a detailed description), are the

annual reports of the Government Accountability Office (GAO). These reports assess all

major acquisition programs (ACAT I programs and programs designated major acquisition

programs for other reasons). The findings are summarized together with possible actions to

improve the performance of these programs. Unfortunately, these reports only emphasize

the findings of the current assessment. Older identified issues and recommendations for

improvements are not mentioned again. Consequently, one must examine all reports ever

published by the GAO to find all challenges identified in defense acquisition programs by this

agency.

Another source for common challenges is general program management literature,

especially literature on frameworks, because they claim to be based on known best practices

for avoiding common pitfalls. In addition, there are many publications dealing with challenges

in program environments or parts of these environments (e.g., product development). By

compiling the diverse findings, one can produce a comprehensive collection of common

issues in program management.

This discussion leads to the third research question of this thesis:

“What are common pitfalls in program management?”

2.3 Introduction to lean management

The term “lean” as applied to management was first used by John Krafcik (Krafcik 1988) in

the paper, “Triumph of the lean production system” (Womack, Jones et al. 1990). He

differentiates between buffered and lean production (Krafcik 1988). By buffered, Krafcik

means the way Western companies used to produce, which included many buffers between

different steps in the production process.

Later, the term was coined by Womack et al. in their book, “The Machine That Changed the

World” (Womack, Jones et al. 1990). In their five-year study with a budget of $5 million, the

authors investigated various automobile companies around the world. They identified

fundamental differences between the production processes of Western and Japanese

(especially as represented by Toyota) companies. The efficiency of Toyota’s processes was

found to be better by factors of up to 10 compared to Western companies in terms of defect

rates, plant productivity, manufacturing lead times, or use of resources.

Over the years, a number of studies examined the Toyota Production System (TPS), and the

idea of “lean thinking” emerged. The term is often misunderstood as “doing the same work

with fewer employees” or “creating flatter hierarchies” (Hoppmann 2009). The main vision of

lean thinking is to create an uninterrupted, continuously flowing value stream that delivers in

Page 40: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 33

the shortest time with the least waste (Womack and Jones 1996). In an effort to detail the

idea of lean thinking two of the three authors of the “The Machine That Changed the World”

produced the book “lean thinking” (Womack and Jones 1996). Womack and Jones structure

their understanding of lean along five principles (Womack and Jones 1996):

1. Specification of customer value

2. Identification of the value stream

3. Creation of a continuous flow

4. Pull of the value

5. Striving for perfection

Originally, the principles derived by Womack and Jones originated in production. Today, the

idea of lean thinking is spread throughout the entire enterprise. Morgan for example

conducted a two-and-a-half-year, in-depth study of Toyota’s product development system to

determine if the same principles as in production are applicable to product development.

Together with Liker he describes his findings in “The Toyota Product Development System”

(Morgan and Liker 2006).

As Toyota outperforms its competitors in all areas where it uses lean, the adaption of lean

thinking to program management – a discipline with major issues (see section 2.2 and

chapter 5) – might be beneficial. This led to the fourth research question of this thesis:

“Are there ways to adapt Lean to program management?”

2.4 Identified gaps in current literature

In this section, gaps in the current research and the corresponding literature are identified,

and for each of them the correlative research question of this thesis is given:

- Lack of definition: There is currently no clear definition of “program management,”

even though many authors are using the term. Consequently, a broadly accepted

definition must be established in order to provide a common understanding for further

discussions. The research question for this gap is:

“What is program management and how can it be defined?”

- Lack of a framework for engineering programs: In addition to there being no clear,

widely accepted understanding of the term “program management,” there is no widely

used framework for this discipline. Some existing approaches have been assessed in

this thesis in terms of the two major aspects of program management in the context of

engineering programs: cross-cutting program activities and technical program life

cycle activities. It became clear that there is only one framework which addresses

both facets with any approach to thoroughness: the Lean Advancement Initiative

(LAI) program management framework. Unfortunately, this framework is only

literature based, and there is no empirical validation of it available. This leads to the

research question:

Page 41: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 34

“Is there a framework for engineering program management?”

- No existing collection of common pitfalls: Currently, one can only find literature

addressing possible issues in quite limited aspects of the field of program

management. There is no comprehensive collection of the issues and pitfalls in all

possible aspects of program management. Consequently, it is necessary to collect

current knowledge about issues and summarize it to enable research to better

grapple with the biggest problems in program management. The research question

for this gap is:

“What are common pitfalls in program management?”

- No application of “lean thinking” in program management: Research and experience

in various fields (e.g., production and product development) has shown that the

practice of “lean thinking” is beneficial. Up to now, there are no approaches for

adapting lean ideas to program management, even though there are major issues

where the application of lean might be advantageous. This leads to the fourth and last

research question of this thesis:

“Are there ways to adapt lean thinking to program management?”

2.5 Research approach

To address the research questions of this thesis scientifically, diverse research approaches

have been chosen. Figure 2-11 shows a list of the research approaches and where they are

used in this thesis. Not all methods fit all of the different research questions.

Literature review

Interviews

Surveys

Industry focus group

Chapter 6Chapter 5Chapter 4Chapter 3

Chapter 6Chapter 5Chapter 4Chapter 3

Chapter 6Chapter 5Chapter 4Chapter 3

Chapter 6Chapter 5Chapter 4Chapter 3

Figure 2-11: Usage of different research approaches in the thesis

Since the method of reviewing literature provides basic knowledge about specific topics and

enables one to formulate hypotheses, it is used extensively throughout this thesis. It ensures

that the diverse aspects and perspectives captured in current literature are considered for

Page 42: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 35

future research steps. The technique of conducting interviews was used for more focused

research to gain insights into specific areas. By undertaking a survey, one collects more data

from a broader audience than by conducting an interview, but the focus and level of detail

are limited since extremely long surveys are normally not well accepted. The last research

method – exploiting the knowledge of an industry focus group – is in between a survey and

an interview. Working with a large group of experienced people can provide valuable insights

from different companies in the form of “mini case studies.” The interviewer gets the chance

to specify his or her questions to gain exactly the desired information (this is only partly

possible in a survey).

2.5.1 Literature review

Many of the sections of this thesis are based on knowledge gained in a review of literature.

The main sources of the literature are:

- MIT libraries (engineering as well as business libraries).

- WorldCat Search Engine: A search engine that includes all university and public

libraries in the United States. An interlibrary loan service based on this service

provides access to books that are not available at the MIT libraries.

- Google: A large Internet search engine.

- Google Scholar: A search engine provided by Google for scholarly literature in

various formats and for various disciplines.

- Amazon.com: A large online shop and database for books.

- Recommendations from other researchers.

The literature review started with basic keyword searches. Following up on the most

promising findings, forward and backward searches based on identified citations were

conducted. These in-depth searches focused on specific fields with smaller scopes.

2.5.2 Interviews

In addition to the literature review, interviews were used as a source of information. Seven

interviews were conducted with Air Force program managers. All interviews were carefully

planned based on a literature review of study research (Eisenhardt 1989; Eisenhardt 1991;

Yin 2009). All interviews were based on preplanned questionnaires to ensure appropriate

administering of them.

The main goals of the interviews were:

- Evaluation of the LAI program management framework (detailed in chapter 4)

- Ranking of the LAI program management framework parts (also detailed in chapter 4)

- Verification of the identified pitfalls (detailed in chapter 5)

- Refinement of a survey for further data collection on pitfalls and Lean Enablers

(detailed in chapter VIII (Appendix B))

Page 43: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 36

Five of the seven interviews were conducted to verify the LAI program management

framework. A detailed description of the questionnaire that was used and the results can be

found in section 4.2. The primary goal of the other two interviews was to validate the findings

about pitfalls in program management from current literature. The secondary goal was to test

the effectiveness of a questionnaire to collect data about pitfalls and lean enablers from the

industry focus group. Details from the second two interviews may be found in sections 5.2

and section VIII (Appendix B).

2.5.3 Surveys

In general, there are several methods to acquire data (Fowler 1995; Aday and Cornelius

2006; Neuman 2006; Fowler 2009). As already discussed, interviews focus only on a small

sample but provide in-depth information. A survey normally covers a larger sample but has a

lower level of detail. Consequently, a survey is less suitable for exploratory research. On the

other hand, conducting a survey will provide meaningful insights for explanatory research

attempting to verify hypothesizes.

For this thesis, a web-based survey type was chosen, for several reasons. First, the link to

the web-based survey can be sent to the exact focus group (Aday and Cornelius 2006). In

this case, the members of the industry focus group and the LAI consortium were the

participants in the survey. Second, the cost per unit is very low for a web-based survey,

compared to a sending a printed survey to various companies (Fowler 2009). Third,

convenience for the respondent is higher due to there being no constraints on when and

where to answer the survey (the respondent must carry a printed version with him/her to be

able to fill it out wherever and whenever he/she chooses to). Fourth, the throughput time of a

web-based survey is dramatically lower than that of a paper-based version. The process of

printing and mailing does not apply to a web-based version. Finally, all data collected during

a web-based survey is directly accessible electronically. Most websites for web-based

surveys offer the option to download the data in a spreadsheet that can be further processed

by any spreadsheet software (e.g., Microsoft Excel).

The questionnaire used in this thesis will be explained in a detailed way in section 4.2.2. It

was pre-evaluated with a number of people, including research assistants, students, and

program managers, to ensure clarity, comprehensiveness, and acceptability (Aday and

Cornelius 2006). Due to the findings of this pretest, the survey was dramatically

shortened to decrease the time expense and therefore increase the likelihood of

participation by possible respondents.

2.5.4 Industry focus group

The idea of the industry focus group is closely related to case study research. The general

idea is to gain in-depth information about specific topics from experienced participants

(Eisenhardt 1989; Eisenhardt 1991; Yin 2003).

The industry focus group for this these had members from different companies as well as

organizations. Error! Not a valid bookmark self-reference. gives an overview of the

Page 44: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 37

participating companies, Table 2-11 of the participating organizations. Due to the

confidentiality of some of the information provided, the general information about the

participants is only provided in an anonymous form. For the different companies the given

information consists of the number of employees, the revenue in 2010 (if available, otherwise

from 2009), and the sector of the company. Since the organizations are nonprofit-oriented,

there is no data available about revenue for them.

Table 2-10: List of companies participating in the industry focus group

Company Name # of Employees Revenue Sector

Company A 107,000 $31.60 B Aerospace, Defense

Company B 160,500 $64.31 B Aerospace, Defense

Company C 36,000 $12.94 B Aerospace,

(Defense)

Company D 72,000 $25.18 B Aerospace, Defense

Company E 20,000 $4.70 B Aerospace,

(Defense)

Company F 405,000 $104.53 B Technology

Company G 3,900 unknown Aerospace

Table 2-11: List of organizations participating in the industry focus group

Organization # of Members Focus

Organization A 6,000+ System Engineering

Organization B 318,400+ Project Management

The industry focus group was used for different methods of verification:

- A day-long group meeting with the key participants in the industry focus group took

place at the end of January 2011 in California. The companies present debated

general topics related to program management and had a guided discussion about

topics with high relevance for this thesis and further research (Haberfellner and

Daenzer 2002).

- Regularly occurring telephone conferences with durations of one and a half hours

were used to discuss certain topics.

Page 45: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 38

- The members of the industry focus group participated in a survey undertaken to rank

different topics in program management in terms of the future relevance for further

research.

- The members of the group were occasionally asked to provide feedback via email

about the current findings of the research for this thesis as it proceeded.

2.6 Summary of current state of program management

In this chapter, the current state of the literature on various topics related to program

management has been discussed. In addition, research questions have been formulated for

each of the four identified literature gaps.

First, different existing frameworks of program management were described. Second, these

frameworks were compared. This analysis and evaluation led to the identification of two gaps

in the current literature: There is currently no broadly accepted definition of program

management, even though there are a noticeable number of publications dealing with it.

Furthermore, none of the frameworks currently available fully covers all identified aspects of

program management. There is one framework, that of the Lean Advancement Initiative,

that addresses both basic facets, but it has not been verified yet.

Third, an additional insight from the literature review was there is no inventory of the issues

or pitfalls in program management. While there is research that tries to unveil issues in

program management, these publications only cover aspects and do not attempt to deliver a

comprehensive list of issues or pitfalls.

Last, the idea of “lean thinking” was identified as promising for producing performance

improvements in multiple environments. However, there are no approaches to adapt lean

ways and ideas to program management.

Figure 2-12 lists the research questions with the sections where the corresponding gaps

were identified.

Page 46: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

2 Current state and research gaps in program management 39

Research Question 4:Are there ways to adapt lean thinking to program management?

Research Question 3:Are there common pitfalls in program management?

Research Question 2:Is there a framework for engineering program management?

Research Question 1:What is program management and how can it be defined?

Chapter 2.3

Chapter 2.2

Chapter 2.1

Figure 2-12: Research questions and corresponding sections

Page 47: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

3 Definition of program management 40

3 Definition of program management

In the preceding chapter it became clear that there are various different concepts of program

management. None of them has gained widespread acceptance. This chapter compares

various existing definitions and tries to identify the most common themes within these

definitions. Based on these findings, a definition will be formulated covering all of the facets

of program management. This will establish an understanding of program management

before the thesis progresses further and describes details based on that understanding. In

addition, the first research question, related to the lack of a clear definition of program

management, is answered by providing a comprehensive definition.

3.1 Definition of project management

Most authors consider program management to in some manner includes project

management (Ferns 1991; Williams 1999; Fricke and Shenhar 2000; Haughey 2001;

Andersen and Jessen 2003; Archibald 2003; Institute 2004; Lycett, Rassau et al. 2004;

Maylor, Brady et al. 2006; Commerce 2007; Hut 2008; Mao, Cheng et al. 2008; Patanakul

and Milosevic 2008; Patanakul and Milosevic 2009). Therefore, it is necessary to briefly

discuss project management and establish a definition of it before developing a definition of

program management.

There are three major aspects of a project (Maylor, Brady et al. 2006):

1. Uniqueness: A project is a unique endeavor; the same project is normally never

executed in the same way more than once (Maylor, Brady et al. 2006; Williams and

Parr 2006; Patanakul and Milosevic 2009). However, the same set of capabilities can

be required for the execution of more than one project (Davies and Brady 2000).

2. Temporariness: A project is a finite task, temporally (Maylor, Brady et al.).

Temporariness does not necessarily imply brevity; there are projects with durations of

even 40 years which still are not fully integrated into the normal organization of a

company and are therefore temporally restricted (Maylor, Brady et al.). A project

normally comes to an end when the desired product or process is delivered (Williams

and Parr).

3. Level of pre-determinism: When a project starts, normally what is to be achieved, in

what timescales, and with what resources is defined (Maylor, Brady et al. ; Williams

and Parr). In addition, the tool set necessary to execute the project successfully must

be discussed, clarified, and provided to the members of the project team before the

project starts (Commerce).

Table 3-1 summarizes existing often-quoted definitions of the terms “project” and “project

management.” The definition most often found in current literature is the one from the Project

Management Institute. “A Guide to the Project Management Body of Knowledge: (PMBOK

Page 48: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

3 Definition of program management 41

guide)” (Institute 2004) provides a widely – especially in the United States – accepted

framework for project management consisting of a collection of best practices. The other very

frequently cited definition is provided by the Office of Government Commerce. Since, the

OGC is a public organization of the United Kingdom, the framework PRINCE2, described in

“Managing successful projects with PRINCE2“ (Commerce 2009), is more widely used in

Europe. However, the definition from the Office of Government Commerce emphasizes the

aspect of the level of pre-determinism more than the one from the Project Management

Institute.

Table 3-1: Broadly used definitions of “project” and if available “project management”

Author Definition

International Organization for

Standardization (ISO 1994)

(revised by (ISO 2005))

“A set of co-ordinated activities, with a specific start and

finish, pursuing a specific goal with constraints on time,

cost and resources.”

Sapsed (Sapsed and Salter) “‘Project’ is used for a system of work activities for which

there is a predefined outcome to deliver and an

associated timeline with an end date."

Office of Government

Commerce (Commerce)

“A project is also a temporary organization, usually

existing for a much shorter duration, which will deliver

one or more outputs in accordance with a specific

business case. A particular project may or may not be

part of a program.”

Office of Government

Commerce (Commerce)

“Project Management is the planning, delegating,

monitoring and control of all aspects of the project, and

the motivation off those involved, to achieve the project

objectives within the expected performance targets for

time, cost, quality, scope, benefits and risks.”

Project Management Institute

(PMI)

“A project is a temporary endeavor undertaken to create

a unique product, service, or result.”

Project Management Institute

(PMI)

“Project management is the application of knowledge,

skills, tools and techniques to project activities to meet

project requirements. Project management is

accomplished through the application and integration of

the project management processes of initiating, planning,

executing, monitoring and controlling, and closing.”

It became clear that the definitions for “project” and “project management” from the Office of

Government Commerce fit best with the definition components most often found in the other

definitions. Consequently, these two definitions will be used for further discussion about

project-management-related topics.

Page 49: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

3 Definition of program management 42

3.2 Definition of program management

After the clarifying the definition of project management, the logical next step is to define the

terms “program” and “program management.” Table 3-2 gives the definitions of those terms

found in widely used literature. If available, both definitions – “program” and “program

management” – are provided.

Table 3-2: Definitions of “program” and “program management”

Author Definition

(Andersen and Jessen

2003)

“A program could be a new product development, an

organizational restructuring of the company or the

implementation of an advanced software package in different

departments of the company. Program management is the

effective management of all the projects under the umbrella of

the program."

(Management 2006) “Program management is the coordinated management of

related projects, which may include related business-as-usual

activities that together achieve a beneficial change of a

strategic nature for an organization”

(Archibald 2003) “Program: A long-term undertaking that includes two or more

projects that require close coordination.”

(Brown 2007) “Program Management is management of a group of projects

and/or operations to achieve business targets, goals, or

strategies, and may or may not have a defined end point.”

(University 2009) “The process whereby a single leader exercises centralized

authority and responsibility for planning, organizing, staffing,

controlling, and leading the combined efforts of participating/

assigned civilian and military personnel and organizations, for

the management of a specific defense acquisition program or

programs, through development, production, deployment,

operations, support, and disposal. (DAU Glossary)”

(Ferns 1991) “A program is a group of projects that are managed in a

coordinated way to gain benefits that would not be possible

were the projects to be managed independently.

“Program management is the coordinated support, planning,

prioritization and monitoring of projects to meet changing

business needs.”

(Haughey 2001) “Program management is a technique that allows

Page 50: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

3 Definition of program management 43

organizations to run multiple related projects concurrently and

obtain significant benefits from them as a collection. Program

management is a way to control project management, which

traditionally has focused on technical delivery. A group of

related projects not managed as a program are likely to run

off course and fail to achieve the desire outcome.”

(Hut 2008) “In the simplest of terms, program management is the

definition and integration of a number of projects to cause a

broader, strategic business outcome to be achieved. Program

management is not just the sum of all project management

activities but also includes management of the risks,

opportunities and activities that occur “in the white space”

between projects.”

(Lycett, Rassau et al. 2004) “Program Management – defined as the integration and

management of a group of related projects with the intent of

achieving benefits that would not be realized if they were

managed independently. Whilst connected, this is distinct

from portfolio management.”

(Mao, Cheng et al. 2008) “However, in general, it is concluded that a Program consists

of a series of interrelated projects while Program

Management is to manage all interrelated projects as a whole

in a harmonic manner which is beneficial to successfully fulfill

each single project and the entire program.”

(Commerce 2007) “In MSP [Managing Successful Programmes], a program is

defined as a temporary, flexible organization created to

coordinate, direct and oversee the implementation of a set of

related projects and activities in order to deliver outcomes and

benefits related to the organization’s strategic objectives. A

program is likely to have a life that spans several years.”

(Commerce 2007) “Program management is the coordinated organization,

direction and implementation of a dossier of projects and

transformation activities (i.e. the program) to achieve

outcomes and realize benefits of strategic importance.”

(Patanakul and Milosevic

2008)

“On the other hand, a program, led by a program manager, is

a family of projects that are strongly dependent, share

common goals, and lead to a single deliverable product or

service.”

Page 51: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

3 Definition of program management 44

(Patanakul and Milosevic

2009)

“Another case of MPM [multi-project management] is program

management, where the projects in the group are mutually

dependent, share a common goal, and lead to a single

deliverable product or service. In contrast with MGMP

[management of a group of multiple projects], program

management is the centralized coordinated management of a

group of goal-related projects to achieve the program’s

strategic objectives and benefits.”

(Institute 2008) “Program Management is the centralized coordinated

management of a program to achieve the program’s strategic

objectives and benefits. It involves aligning multiple projects

to achieve the program goals and allows for optimized or

integrated cost, schedule, and effort.”

By comparing the different existing definitions, five key aspects could be identified:

1. A program consists of multiple, related projects. The first aspect in which all

definitions for program management found in current literature agree (except for one)

is that a program consists of multiple projects. A broadly accepted definition for the

term “project” was established in the preceding section, 3.1. Programs may also

evolve from single projects as they become more complex (Andersen and Jessen

2003). The organization of the projects within a program can vary depending on the

purpose of the program. Projects can be organized sequentially, run in parallel as

hybrid sequential-parallel models, or be organized as a network of interlinked projects

(Lycett, Rassau et al. 2004). However, perhaps the most common concept of the

organization of projects within a program is an environment of interlinked projects.

2. Long program duration. The second aspect focuses on the duration of a project or

program. Whereas projects are time constrained, programs in general do not need to

have a fixed end date. A program can only come to an end when the deliverable

(e.g., a product or service) is fully developed and handed over to the user/customer

(Lycett, Rassau et al. 2004; Maylor, Brady et al. 2006). In addition, some authors

state that a program is also responsible for the time after handing over the product or

service to the user. This may include, for example, deployment, operations, support,

and disposal (DoD 2008; University 2009; DAU 2010).

3. Management economy of scale. There are many tasks and objectives in the projects

within a program that are similar. By identifying best practices among different

projects and introducing organization-wide learning, huge benefits can be gained

when projects are managed in a program instead of being managed in isolation in a

project management context (Ferns 1991; Lycett, Rassau et al. 2004).

4. Complex value proposition. A program focuses on multiple stakeholders and has to

satisfy a complex value proposition. While a single project may only deliver an output

such as a product, a program has to satisfy the multifaceted needs of several

Page 52: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

3 Definition of program management 45

stakeholders. A program could, for example, provide a transportation solution for

urban environments, while the project would deliver a train or bus for this purpose

(Commerce 2007).

5. Programs define their own enterprise. Based on the research undertaken by the LAI,

the formation of a program enterprise is included in the definition of program

management used in this thesis. The organization of each program is unique and

established to satisfy the needs of all stakeholders in the best way. Since a program

has its own program office and has to defend decisions against undue influence from

single stakeholders, a program has a certain degree of autonomy.

Similarly to the approach of comparing the different frameworks in section 2.1.5, Error! Not a

valid bookmark self-reference. assesses and compares the different definitions of program

and program management presented in Table 3-2. Again, there are three different ratings for

a definition. When an aspect is not mentioned at all in the definition, an empty circle is given.

If the aspect is partly addressed (maybe the aspect is only implied), the rating is a half-filled

circle. An entirely filled circle is given if the aspect is explicitly mentioned in the definition.

Even though there might be additional aspects mentioned in the publication where the

definition appears, only the formal definition itself is considered in these ratings. The purpose

of this chapter is to find a short and precise definition of program management, not to

generally assess the current program management literature.

Table 3-3: Comparison of definitions of “program management”

Author

Aspect 1: Consists of

multiple projects

Aspect 2: Long

program duration

Aspect 3: Generates

management economy of

scale

Aspect 4: Complex

value propositio

n

Aspect 5: Defines

own enterprise

Andersen

(Andersen and

Jessen 2003)

Association for

Project

Management

(Management

2006)

Archibald

(Archibald 2003)

Brown (Brown

2007)

DAU (University

2009)

Page 53: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

3 Definition of program management 46

Ferns (Ferns

1991)

Haughey

(Haughey 2001)

Hut (Hut 2008)

Lycett (Lycett,

Rassau et al.

2004)

Mao (Mao,

Cheng et al.

2008)

OGC (Commerce

2007)

Patanakul

(Patanakul and

Milosevic 2008;

Patanakul and

Milosevic 2009)

PMI (Institute

2004)

: Fully addressed : Partly addressed : Not addressed

The table shows that there is no current definition that fully covers all aspects. In particular,

the aspects of long program duration and definition of a program enterprise are not widely

addressed. This leads to the necessity of formulating a definition for use in this thesis. The

term “program management” in the proceeding thesis will be understood as follows:

“Program management is defined as the management of multiple related projects and the

resulting enterprise over an extended period of time to deliver a complex value proposition

and utilize efficiency and effectiveness gains.”

3.3 Summary

This chapter has answered the first research question, “What is program management

and how can it be defined?” The first step was to provide the basic knowledge necessary

to understand a definition of program management. Since many authors state that a program

consists of multiple (interrelated) projects, a clear definition of project management had to be

found. Various aspects of project management were presented, and a number of definitions

from the literature were compared and assessed.

Page 54: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

3 Definition of program management 47

Afterwards, a comprehensive compilation of definitions of program management from the

literature was presented. Again, different aspects could be identified within the spectrum of

definitions. It became clear that no current definition fully covers all facets of program

management. Consequently, a new definition had to be formulated. The definition and hence

the answer to the first research question is:

“Program management is defined as the management of multiple related projects and

the resulting enterprise over an extended period of time to deliver a complex value

proposition and utilize efficiency and effectiveness gains.”

Page 55: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

4 Selection of a framework for engineering programs 48

4 Selection of a framework for engineering programs

This chapter answers the research question, “Is there a framework for engineering

program management?” The first step is to finalize the comparison of existing approaches

in section 2.1.5 and determine whether there is an existing approach that could be used.

Three approaches that are well known (but not widely used in industry) and one new

approach were chosen for the comparison:

- Defense Acquisition System – United States Department of Defense

- Managing Successful Programmes – Government of Great Britain

- The Standard for Program Management – Project Management Institute

- The Lean Advancement Initiative (LAI) program management framework

Consequently, the LAI program management framework will be the framework used for

further research in this thesis. As stated in section 2.1, the second research question

addresses the existence of a framework for the management of technical programs. The

findings so far are that there is a framework, but since this framework is only described in an

internal, unpublished whitepaper, there is no empirical evidence for the correctness of the

framework. Hence, it is necessary to empirically validate the framework in this thesis to

ensure that it covers the diverse aspects of program management. The validation will be

described in detail in the next sections.

Page 56: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

4 Selection of a framework for engineering programs 49

Table 4-1 summarizes the comparison made in section 2.1.5. The table shows how the

different frameworks address the two major aspects of program management – cross-cutting

program activities, and activities of a technical program life cycle.

The Defense Acquisition System describes necessary steps and phases throughout the life

cycle of a defense acquisition program, a technical program. Hence, its rating for the life

cycle activities of a technical program is the second-best, while its cross-cutting program

activities are rated worst. The Managing Successful Programmes framework provides

knowledge for organizational change programs but does not consider activities of a program

life cycle. Consequently, its rating for the technical program life cycle activities is the worst,

and the cross-cutting activities are addressed very well. The Standard of Program

Management does not focus on change programs nor on technical programs. Therefore, its

rating for the technical program life cycle activities is also low, while the cross-cutting

program activities are addressed very well. The LAI program management framework’s

development was based on research about technical programs. Hence, its rating for the

technical life cycle activities is very good. In addition, the LAI program management

framework covers most of the cross-cutting program activities and receives a good rating for

that.

Consequently, the LAI program management framework will be the framework used for

further research in this thesis. As stated in section 2.1, the second research question

addresses the existence of a framework for the management of technical programs. The

findings so far are that there is a framework, but since this framework is only described in an

internal, unpublished whitepaper, there is no empirical evidence for the correctness of the

framework. Hence, it is necessary to empirically validate the framework in this thesis to

ensure that it covers the diverse aspects of program management. The validation will be

described in detail in the next sections.

Page 57: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

4 Selection of a framework for engineering programs 50

Table 4-1: Overall comparison of existing program management frameworks (see section 2.1.5)

Framework

topic

Defense

Acquisition

System (see.

section 2.1.1)

Managing

Successful

Programmes

(see section

2.1.2

The Standard

of Program

Management

(see chapter

2.1.3)

LAI program

management

framework

(see section

2.1.4)

Cross-cutting

program

activities

Technical

program life

cycle activities

(without

production)

4.1 Discussion of current state of program management in industry

One major goal of the workshop at the end of January with the industry focus group was to

determine the current state of program management in industry. In particular, the aspect of

the application of a framework was discussed in detail.

The first finding was that no company uses a program management framework provided in

current literature. None of the frameworks described in this thesis are being used, and they

are mostly not known in industry. The only framework that is partly recognized is the Defense

Acquisition System, because many of the companies are defense contractors and therefore

involved in the acquisition process. However, most companies (even those dealing with

defense acquisition) are not familiar with the framework itself and know only the interfaces

and types of reports necessary to interact with the governmental organizations involved in

defense acquisitions.

The organizations that published the different frameworks are well recognized in industry.

However, the companies of the industry focus group are most familiar with the Project

Management Institute because of its geographical focus on the United States and the

famous project management framework, “A Guide to the Project Management Body of

Knowledge (PMBOK Guide)” (PMI 2004). Most companies know the project management

framework PRINCE2 (OGC 2009), and hence they are aware of the Office of Government

Commerce. But very few of the companies know that both organizations have also published

program management frameworks.

Only one of the collaborating companies in the industry focus group uses a formal program

management framework. The framework consists of a set of best practices drawn from

Page 58: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

4 Selection of a framework for engineering programs 51

different fields of expertise (e.g., risk management, program organization, etc.). The best

practices are assessed on a yearly basis to improve their quality and ensure that they

continue to be considered best practices. Most of these assessments are done internally

rather than by external consultants in audits. The company itself had already stated during

the discussion that the best practices are more focused on the execution of the program than

on the implementation of new organizational structures for a program.

A second company indicated that it uses formal guidelines for program management but has

not implemented an actual framework. The company emphasizes that the main aspect of the

guidelines is a focus on the valuestream life cycle. Again the guidelines are based on

identified best practices and guidelines, which are updated regularly. And also similarly to the

first company, this company’s guidelines focus not on program organization but on the

execution of a program.

A third company described its program managers as “small business owners” capable of

executing a program on their own. This company stated that there are program management

models used in their programs. However, these models or frameworks are not standardized,

but rather are created individually by the program managers.

None of the other participating companies were using any formal model in their program

management. Some implemented best practices to improve program performance but only

sporadically, not systematically.

Finally, all of the companies agreed that a formal program management framework might

help them understand the necessary processes of program management. In addition, a

formal model might improve program performance because companies would know about

best practices (if they are included in the framework) in different disciplines of program

management.

In summary, it can be stated that there is a need for a formal program management

framework. Existing publications seem not to fit companies’ needs, since they are not widely

implemented or even recognized. Consequently, a new approach to the design of a program

management framework is necessary. This approach should reflect current needs and

include companies during the development process to ensure the practicability of the

framework.

4.2 Validation of the LAI program management framework

As the comparison in section 2.1.5 showed, the LAI program management framework is a

promising approach in the context of technical programs. In addition, there is no final

publication of it and during the workshop with the industry focus group it became clear that

industry needs an approach better aligned with its needs. The LAI program management

framework was in a preliminary state before the study documented in this thesis improved

and validated it; in its development, this study made extensive use of information gathered

from industry .

Page 59: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

4 Selection of a framework for engineering programs 52

To recapitulate the general structure of the LAI program management framework, it is shown

in Figure 4-1. The program management activities are structured in six main areas: Program

Execution; Enterprise Management; Scoping, Planning, and Contracting; Technology

Integration; Product Design; and Production, Use, Service, and Decommissioning. As the LAI

research focuses on the early phases of a system’s life cycle, the last phase of the

engineering life cycle – Production, Use, Service, and Decommissioning – is not covered in

the model.

This framework covers both cross-cutting program activities (the upper two categories:

Program Execution and Enterprise Management) and technical program life cycle activities

(the lower categories: Scoping, Planning, and Contracting; Technology Integration; Product

Design; and Production, Use, Service, and Decommissioning).

Scoping, Planning & Contracting

• Stakeholder needs & requirements definition

• Managing trade‐offs

• Cost estimation & life cycle costing

• Incentive alignment, contract negotiation & conclusion

• Defining lifecycle strategy

Technology Integration

• Technology maturation monitoring

• Technology transition management

Product Design

• PD team organization

• Integrated product and process development

• PD and SE best practices

• Monitoring PD progress

• Product architecting

• Value Stream Optimization

• Product design strategy

• Testing & prototyping

Production, Use, Service & 

Decommissioning

Program Execution

• Integrating and leading the program organization

• Stakeholder management

• Progress monitoring and management

• Risk management

• Project management

• Multi‐project coordination

• Developing intellectual capital

• Program manager qualifications

Enterprise Management

• Building and transforming the program enterprise

• Understanding the program enterprise

• Learning and improving the program enterprise

• Knowledge management

• Secure IT information / document sharing in the enterprise

• Program portfolio and environment management

Figure 4-1: The Lean Advancement Initiative (LAI) program management framework

In order to refine and validate the structure of the framework, interviews with Air Force

program managers were conducted and insights from those interviews and from the industry

focus group were incorporated. These two research methods are described in section 4.2.1

(interviews with program managers) and section 4.2.2 (insights from the industry focus

group).

4.2.1 Insights from interviews with program managers

In order to validate the framework, the author conducted five interviews with government

program managers. All of them had at least five years of experience and an aerospace

defense background. The duration of each interview was between one and two hours. All of

the interviews were one-on-one.

Page 60: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

4 Selection of a framework for engineering programs 53

In the interviews, two main subjects were addressed:

1. Framework validation: At the beginning of each interview, the author introduced the

interviewee to the current approach of the LAI framework. The author asked

questions regarding the general structure of the framework to find out if any

restructuring is necessary. Furthermore, the interviewees were asked if any elements

are missing from the framework. By posing general questions about the daily work of

a program manager, the author tried to discover additional activities and elements the

framework should cover.

All insights about the structure gained during these interviews were used to modify

the basic structure of the framework. The general findings were that some elements

needed to be added and some activities had to be restructured or their description

supplemented.

2. Identification of “biggest issues”: In addition to assessing the framework, the author

tried to identify the “biggest issues” in order to use them to guide subsequent

research in this study. By posing four questions for each framework part, the

necessary insights were gained. The author asked the program manager to answer

all questions based on his or her experiences with different programs. The first

question addressed whether the specific framework part was important in the

interviewee’s opinion. The second question dealt with the difficulty of execution of the

specific framework part. The third question assessed the extent to which the

framework part is addressed by best practices in current literature (including general

program management literature as well as documents published by the Department

of Defense). The last question asked if the best practices, if any, are feasible and can

be used in the daily work of a program manager.

All questions were formulated as statements. The interviewees could state that they “fully

disagree,” “fully agree,” or fall somewhere in between, using a five-point Likert-type scale

(Likert 1932). The rating “1” in the figures below represents “fully disagree,” while a “5” is

“fully agree.” Consequently, an average rating of a framework part higher than 3 implies that

the program managers agree with the statement that a part is important, difficult to execute,

well addressed by existing best practices, or addressed by feasible best practices (if any).

Figure 4-2 summarizes the results of the findings from these interviews regarding the

importance and the difficulty of execution of the framework parts, each of which belongs to

one of two themes, Program Execution and Enterprise Management. Since some

refinements were made later to the LAI program management framework, there are aspects

of the current version that were not assessed during the interviews. These additional

refinements were identified based on the interviews or on comments from the members of

the industry focus group.

By consideration of the two different ratings – importance and difficulty – individually, one

arrives at different conclusions about some of the framework parts. The importance is a

measure indicating whether the part should be kept in the framework. A low rating would

imply that this part is less important and could be removed from the framework. On the other

Page 61: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

4 Selection of a framework for engineering programs 54

hand, a high ranking indicates that the framework part is important and should be kept as

part of the framework. The difficulty rating gives guidance for possible future research.

Framework parts with a high ranking regarding difficulty might be the focus for future

research efforts. Whether a framework part requires more detailed research also depends on

the availability of best practices and literature. If these are lacking, one should consider this

framework part as being important for future research that can improve the existing

knowledge base.

In the framework themes Program Execution and Enterprise Management, there are no parts

which were identified as unimportant. Consequently, all current parts should be kept in the

framework. Furthermore, most framework parts in the two themes are considered difficult by

the program managers.

4,1

4,8

4,4

5,0

2,8

4,6 4,54,8 4,8

5,0

3,8

4,5

3,3

4,8

4,04,03,7

4,04,3

4,8

4

3

2

1

difficulty

5

importance

Learning and improving in the program enterprise

Understanding the program enterprise

Building and transforming the program enterprise

Developing intellectual capital

Multi‐project coordination

Project management

Risk management

Progress monitoring and management

Stakeholder management

Integrating and leading the program organization

Program Execution andEnterprise Management

n = 3‐5

Figure 4-2: Interview results for Program Execution and Enterprise Management

Figure 4-3 shows the ratings for the framework parts of the theme Scoping, Planning, and

Contracting. These framework parts are considered even more important by the program

managers. In addition, these parts are perceived as being more difficult in their execution

than the ones of the themes of Program Execution and Enterprise Management.

Page 62: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

4 Selection of a framework for engineering programs 55

4,65,0

4,5

5,0

4,6

5,04,84,8

2

1

3

5

difficulty

4

importance

Incentive alignment, contract negotiation & conclusion

Cost estimation & life cycle costing

Definition of stakeholder needs and requirements

Managing trade‐offs

Scoping, Planning & Contracting

n = 3‐5

Figure 4-3: Interview results for Scoping, Planning & Contracting

Figure 4-4 displays the ratings for the two parts of the LAI program management framework

that pertain to the theme Technology Integration. Both are rated important and of greater

than average difficulty to execute.

4,0

4,7 4,74,7

importance

2

1

3

4

5

difficulty

Technology maturation monitoring

Technology transition management

Technology Integration

n = 3‐5

Figure 4-4: Interview results for Technology Integration

The last figure, Figure 4-5, shows the ratings for the theme Product Design. Again, these

entire framework parts should be kept in the framework, because they are all considered

important (for each, an average response of at least “agree” was given by the program

managers to the statement that the framework part is important). The average rating of

difficulty in this theme is not as high as the ones in Scoping, Planning, and Contracting and

Page 63: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

4 Selection of a framework for engineering programs 56

Technology Integration. But all parts are to some extent considered difficult to execute since

the rating is higher than “3” for each of them.

3,5

4,7

3,3

4,04,34,3

4,0

4,7 4,74,7

4,0

5,0 5,05,04,7

5,0

3

4

importance

2

1

5

difficulty

Product Architecting

Value Stream Optimization

Product design strategy

Testing & prototyping

PD and SE Best Practices

PD team organization

Integrated Product and Process Development

Monitoring PD ProgressProduct Design

n = 3‐5

Figure 4-5: Interview results for Product Design

Figure 4-6 presents the average ratings regarding difficulty and importance for all framework

parts combined. The average importance rating of 4.72 indicates that all of the framework

parts of the LAI program management framework are relevant and should be kept in the

framework. Furthermore, the average difficulty rating of 4.18 shows that the general

perception of program management is that it is very hard to execute properly.

Page 64: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

4 Selection of a framework for engineering programs 57

1 2 3 4 5 6

Average rating Difficulty

Importance

Figure 4-6: Average rating of all framework parts combined (including standard

deviation)

In Figure 4-7 , the interview results for the most relevant parts of program management are

visualized (the legend is shown in Figure 4-8 to improve the readability of the text in the

figures). Each circle equals one part of the framework. The two axes display the importance

and the difficulty of the specific part. The size of the circle for the part corresponds to the

level of being addressed by feasible best practices. Because there are two different

conditions being assessed in relation to best practices – existence and feasibility – the circle

size reflects the arithmetic average of these two ratings. In the figure, only 11 framework

parts are displayed since if the display included all framework parts it would be difficult to

discern the information in it. The parts with the highest combined overall ratings for difficulty

and importance are shown.

Page 65: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

4 Selection of a framework for engineering programs 58

Product Architecting

Incentive alignment, contract negotiation & conclusion

Cost estimation & life cycle costing

5,0

4,8

4,6

4,4

4,2

4,0 importance

difficulty

5,2

Definition of stakeholder needs and requirements

Learning and improving in the program enterprise

Project management

Risk management

Stakeholder management

Technology transition management

5,004,904,804,704,60

Testing & prototyping

Product design strategy

Figure 4-7: Difficulty and importance rating of the most relevant elements of the LAI program

management framework

1

3

5

Program Execution

Enterprise Management

Scoping, Planning & Contracting

Technology Integration

Product Designn = 3‐5

Level of being addressed by existing best practices:

Framework theme:

Figure 4-8: Legend for Figure 4-7

Page 66: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

4 Selection of a framework for engineering programs 59

In the interviews, in addition to being asked questions relevant to validation of the framework

and the rating of its parts, the program managers were asked for individual feedback

regarding the general structure of the LAI program management framework and the different

framework parts. Based on this feedback some definitions were rephrased and the general

structure was adjusted.

4.2.2 Insights from the industry focus group

The resource consisting of the work experience of the industry focus group was exploited in

two ways:

- The members of the industry focus group were asked for individual feedback on the

LAI program management framework. The version which was up-to-date at that time

was sent to the members via email and feedback was requested.

- The members of the industry focus group were asked to participate in a survey on the

LAI program management framework. The major aim was to gain a better

understanding of their assessment of the relative importance of the different

framework themes through having them rate the themes for their importance.

The feedback from individual members of the industry focus group regarding the LAI

program management framework mostly arrived in annotated Microsoft Word documents.

The members commented on the definitions of the framework parts and the general structure

of the framework. Due to their input, some framework parts received refinements in their

definitions, their names, or their places in the framework. In addition, the members were

asked to report whether any aspects of the framework were illogical and whether the

framework was missing any aspects.

Shortly before the meeting with the industry focus group at the end of January, a survey was

conducted to gain insights into the members’ assessment of the relative importance of the

different framework themes for future research through having them rate the themes for their

importance. This enabled the author and the other members of the LAI to be better prepared

for the workshop and for questions about specific framework themes. Figure 4-9 shows the

results of this survey. The members ranked the framework theme Program Execution as the

most important one. The themes Scoping, Planning, and Contracting and Enterprise

Management were ranked second and third in importance.

The finding that Program Execution was considered most important matches the findings of

the literature review and the current state of the resources available to the industry. The only

framework that currently is widely used or known – the Defense Acquisition System of the

United States Department of Defense (see section 2.1.1 for detailed description) – does not

address the theme of Program Execution very well. Consequently, there is a lack of

knowledge in this area. In addition, the members of the industry focus group stated during

the workshop that they struggle with requirement definition. Since dealing with requirements

is a major part of the framework theme Scoping, Planning, and Contracting, it is logical that

that theme was also rated as being very important. Finally, the theme Enterprise

Page 67: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

4 Selection of a framework for engineering programs 60

Management is also inadequately addressed by the only widely used framework and also

ranked high in the survey.

2,37

2,61

3,05

3,32

3,67

Technology Integration

Product Design

Enterprise Management

Scoping, Planning & Contracting

Program Execution

n = 19

Please rank the program management categories regarding their importance for future research (5 – high to 1 – low):

Figure 4-9: Rating of the importance of framework themes by members of the industry focus

group

4.3 Summary

The primary objective of this chapter was to answer the research question, “Is there a

framework for engineering program management?” By comparing the existing

approaches, it became clear that the LAI program management framework is the most

promising approach for fully covering all aspects of the management of a technical program.

One disadvantage of this framework was that it had not been validated through empirical

analysis. Consequently, the author decided to validate the structure and the elements of the

framework before using it. By conducting interviews with experienced Air Force program

managers, meaningful insights could be gained about the degree of correctness of the

framework. These findings were used for refining and validating the framework. Additional

information about the importance of different framework parts and the difficulty of executing

them was gathered and may be used to determine the direction of future research in program

management.

The knowledge of the industry focus group was exploited in two additional ways beside

interviews. First, the members of the group were asked for individual feedback on the LAI

program management framework. Second, the members participated in a survey to rate the

importance of the different framework themes; this survey was conducted in order to improve

the contents of the workshop and adjust the direction of future research.

Page 68: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

4 Selection of a framework for engineering programs 61

In summary, all feedback was considered in creating the current version of the LAI program

management. In addition, all members of the industry focus group and the program

managers approved the structure and the definitions of the framework parts of the current

version of the framework. Therefore, the LAI program management framework can be

considered to have been validated as suitable for technical programs. Consequently, the

answer to the research question is that there is a framework for technical programs. The LAI

program management framework meets all requirements for fully addressing the

management of technical programs and has been refined and validated via the feedback of

a large group of experts in this discipline.

Page 69: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

5 Common issues and pitfalls in program management 62

5 Common issues and pitfalls in program management

This chapter answers the research question, “What are common pitfalls in program

management?” The first step is the identification of pitfalls in program management via the

current literature (see section 5.1). The second step is the verification of the findings (see

section 5.2). The final step is the mapping of the pitfalls to the LAI program management

framework (see section 0). This step is necessary for later analyses in this thesis.

5.1 Identification of common program management pitfalls

There are a number of sources that are highly useful for identifying common issues in

program management. Most of these sources fall into one of three major groups:

1. Government reports: One very helpful source for the identification of challenges,

especially in the management of defense acquisition programs (this is in the context

of the Defense Acquisition System of the United States Department of Defense; see

section 2.1.1 for a detailed description) is the reports published annually by the

Government Accountability Office (GAO). These reports assess all major acquisition

programs (ACAT I programs and programs designated major acquisition programs for

other reasons). The findings are summarized, together with possible actions to

improve the performance of these programs.

2. General program management literature: Another source for common challenges is

general program management literature and literature that focuses on topics within

program management. The LAI program management framework is based on

publications from the LAI, and the vast majority of these publications give useful

insights into topics in program management. The findings of many of these papers,

theses, etc., can be used to identify common challenges in program management. In

addition, the other, more well-known frameworks claim to be based on known best

practices to avoid common pitfalls. Consequently, the literature on the other

frameworks can also be used to identify common pitfalls.

3. Discussions with experts: The workshop with the industry focus group at the end of

January was used for conducting a first effort to collect data on pitfalls experienced in

program management. The participating members were grouped in small teams

(between four and six persons per team) and asked to compile their insights into

challenges and issues in program management. In addition, two Air Force program

managers were interviewed to learn their opinions about possible reasons for failures

of programs. These interviews were divided into two parts. First, a general discussion

about their experiences with failures was conducted to gain uninfluenced insights.

Second, the list of pitfalls that had identified by this study, up to that point in time,

from current literature was used to help the program managers remember more

pitfalls and frame their experiences within the existing categories.

Page 70: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

5 Common issues and pitfalls in program management 63

Table 5-1 shows the entire set of diverse pitfalls in program management that were derived

from the three different sources. For better identification, a unique ID number was assigned

to each pitfall. The table also indicates the sources that state that the identified pitfall has a

major impact on program management or one of the processes in program management.

The sources might be literature (different types of publications; e.g., theses, papers, books,

etc.), the workshop with the industry focus group, or the interviews with the Air Force

program managers.

Table 5-1: Compilation of program management pitfalls and corresponding sources

ID Pitfall Sources

1 Unstable funding (undermining program

stability)

(Mandelbaum, Kaplan et al.

2001; Kirtley 2002; Shroyer

2002; Ferdowsi 2003; Wirthlin

2009; McKnew 2010; Kinscher

2011; LAI 2011)

2 Long waiting time for external stakeholders

(e.g., Acquisition Panel) activities

(Ippolito 2000; Wirthlin 2009)

3 “Firefighting”

(Morgan 1999; CMU 2008;

Levine and Novak 2008;

McKnew 2010; Kinscher 2011)

4 Lack of leadership commitment to cycle

time reduction

(McNutt 1998)

5 No incentives for cycle time reduction (Cowap 1998; McNutt 1998;

Stanke 2006)

6 Overriding influence of funding-related

constraints

(McNutt 1998)

7 Wrong allocation of responsibilities and

decision-making rights

(Klein, Cutcher-Gershenfeld et

al. 1997; McKenna 2006;

Stanke 2006)

8 Lack of coordination of communication (Cohen 2005; McKenna 2006)

9 Lack of process standardization (Cohen 2005; Bador 2007)

10 Poor communication with stakeholders

(Lucas 1996; Rebentisch 1996;

Dare 2003; Roberts 2003;

Gordon, Musso et al. 2009;

McKnew 2010)

11 No realistic program schedule (Gordon, Musso et al. 2009;

Lamb 2009; LAI 2011)

Page 71: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

5 Common issues and pitfalls in program management 64

12 Lack of metrics

(Cunningham 1998; Beckert

2000; Stagney 2003; Cohen

2005; McKenna 2006; Stanke

2006; Bador 2007; Boehm,

Valerdi et al. 2008; Rhodes,

Valerdi et al. 2009; Roedler,

Rhodes et al. 2010)

12.1 No metrics to reflect cross-functional

processes

(Ittner and Larcker 1998;

Hammer, Haney et al. 2007;

Blackburn 2009; Rhodes,

Valerdi et al. 2009; Roedler,

Rhodes et al. 2010)

12.2

No process implemented to measure

project performance or project

progress (e.g. EVM)

(Whitaker 2005)

13

Wrong metrics: Not using the right measure

(ignoring something important) or choosing

metrics that are wrong

(Schmenner and Vollmann

1994; Hauser and Katz 1998;

McGarry and Card 2002;

Blackburn 2009) (Klein,

Cutcher-Gershenfeld et al.

1997; Cunningham 1998;

Beckert 2000; Stagney 2003;

Boehm, Valerdi et al. 2008;

Rhodes, Valerdi et al. 2009;

Office 2010; Roedler, Rhodes

et al. 2010)

13.1

Implementing metrics that focus on

short-term results, or that do not give

thoughts to consequences on

human behavior and enterprise

performance

(Schmenner and Vollmann

1994; Kerr 1995; Hauser and

Katz 1998; Ittner and Larcker

1998; McGarry and Card 2002;

Hammer, Haney et al. 2007;

Blackburn 2009)

13.2

Metrics that are not actionable or are

hard for a team/group to impact, or

collecting too much data

(Hauser and Katz 1998; Ittner

and Larcker 1998; McGarry

and Card 2002; Blackburn

2009)

14 No activity-based costing and management (Paduano 2001)

15 No defined risk management process

(Browning, Deyst et al. 2002;

Oehmen 2005; Bresnahan

2006; Stanke 2006; Valerdi,

Page 72: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

5 Common issues and pitfalls in program management 65

Rieff et al. 2007; Wagner 2007;

Wirthlin, Seering et al. 2008;

Madachy and Valerdi 2010;

McKnew 2010; Oehmen and

Ben-Daya 2010; LAI 2011;

Oehmen and Seering 2011)

16 Lacking ability to understand

uncertainty/risk

(Ferns 1991; Cunningham

1998; Browning, Deyst et al.

2002; Oehmen 2005; Valerdi

2005; Bresnahan 2006;

McKenna 2006; Stanke 2006;

Wagner 2007; Wirthlin, Seering

et al. 2008; Ahern 2009;

America 2009; Rhodes, Valerdi

et al. 2009; Francis, Golden et

al. 2010; McKnew 2010;

Oehmen and Rebentisch 2010;

Roedler, Rhodes et al. 2010;

LAI 2011; Oehmen and

Seering 2011)

17 Lacking the staff/capacity to deal with

uncertainty/risk

(Ferns 1991; McKenna 2006;

Stanke 2006; Wirthlin, Seering

et al. 2008; Ahern 2009;

America 2009; (AT&L) 2010;

Francis, Golden et al. 2010;

McKnew 2010; Oehmen and

Rebentisch 2010; Roedler,

Rhodes et al. 2010; LAI 2011)

18 Not all staff is involved into risk

management

(Bresnahan 2006)

19 Insufficient management of sub-projects (PMI 2004; PMI 2008; OGC

2009)

20 Competing resource requirements (e.g.

allocation and choice of resources)

(McKenna 2006)

21 Too much overtime (Herweg and Pilon 2001)

22 Overly unstable project priorities (Herweg and Pilon 2001)

23 Too much outsourcing (Herweg and Pilon 2001)

24 Unrealistic plan or no plan for ramp-up and

ramp-down regarding staffing

(Herweg and Pilon 2001;

Kinscher 2011)

Page 73: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

5 Common issues and pitfalls in program management 66

25 Troubled projects are not canceled early (Herweg and Pilon 2001)

26 No buffer scheduled between projects (Herweg and Pilon 2001)

27 Inadequate identification of individual skill

development

(Hernandez 1995; Cohen

2005; Davidz 2006; Kinscher

2011)

28 Unsupportive environment for experiential

and general learning

(Browning 1996; Klein,

Cutcher-Gershenfeld et al.

1997; Forseth 2002; Cohen

2005; Davidz 2006; Lamb

2009)

29 No or insufficient assessment of intellectual

capital base regarding program needs

(Siegel 2004)

30 No specialist career path

(Wheelwright and Clark 1992;

Forseth 2002; Cohen 2005;

Kinscher 2011)

31 Inadequate team experience

(Susman and Petrick 1995;

Klein, Cutcher-Gershenfeld et

al. 1997; Valerdi 2005; Stanke

2006; Valerdi, Rieff et al. 2007;

Lamb 2009; LAI 2011)

32 Insufficient program manager qualifications

(Ferns 1991; Wheelwright and

Clark 1992; Klein, Cutcher-

Gershenfeld et al. 1997; Lycett,

Rassau et al. 2004; Kinscher

2011)

33

Lack of enterprise-wide coordination of

optimization: only local processes and

organizational optimization

(LAI 2001; Nightingale and

Mize 2001; Jobo 2003; Davidz

2006; Stanke 2006; Stanke,

Nightingale et al. 2008; LAI

2011)

34 Lack of performance incentives for staff

(Susman and Petrick 1995;

Klein, Cutcher-Gershenfeld et

al. 1997; Cowap 1998; Cohen

2005; Stanke 2006)

35 Wrong performance incentives for staff

(Susman and Petrick 1995;

Klein, Cutcher-Gershenfeld et

al. 1997; Cowap 1998; Cohen

2005; Stanke 2006)

Page 74: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

5 Common issues and pitfalls in program management 67

36 No utilization of a social network (Stanke 2006)

37 Too little customer and stakeholder

interaction

(Downen 2005; Glazner 2006;

Stanke 2006)

38 Too little integration of suppliers

(Lucas 1996; Rebentisch 1996;

Bozdogan, Deyst et al. 1998;

Ippolito 2000; Glazner 2006)

39 No fostering and maintaining of personal

accountability for plans and outcomes

(Klein, Cutcher-Gershenfeld et

al. 1997; Stanke 2006)

40 Understaffing

(Ahern 2009; (AT&L) 2010;

McKnew 2010; Office 2010;

Roedler, Rhodes et al. 2010;

LAI 2011)

41 Insufficient resource planning (no

identification of possible understaffing)

(Ahern 2009; (AT&L) 2010;

McKnew 2010; Office 2010;

Roedler, Rhodes et al. 2010;

LAI 2011)

42

Insufficient use of benchmarking and

assessment tools for evaluation of

enterprise structure

(LAI 2001; Nightingale and

Mize 2001)

43 No enterprise-wide integrated continuous

improvement process

(Imai 1986; Bessant, Caffyn et

al. 1994; Laraia, Moody et al.

1999; Maass and McNair 2009)

44

Insufficient use of benchmarking and

assessment tools to identify improvement

potentials

(Constantinescu and Iacob

2007; Nightingale, Stanke et al.

2008; Stanke, Nightingale et al.

2008)

45 No enterprise-wide organizational learning

and change management plan

(Kotter 1990; Klein, Cutcher-

Gershenfeld et al. 1997; Roth

2008)

46 No open information sharing

(Klein, Cutcher-Gershenfeld et

al. 1997; Bernstein 2000;

Stanke 2006)

47 No documentation of lessons learned (Klein, Cutcher-Gershenfeld et

al. 1997; Cunningham 1998)

48 Insufficient or non-standardized usage of

information technology

(Browning 1996; Rebentisch

1996)

49 Insufficient information flow (Bozdogan, Deyst et al. 1998;

Page 75: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

5 Common issues and pitfalls in program management 68

Pomponi 1998; Ippolito 2000)

50 Unclear requirement definition

(Ferns 1991; Walton 1999;

Wirthlin 2000; Dare 2003;

Derleth 2003; Tondreault 2003;

Kadish, Abbott et al. 2006;

McKenna 2006; Cameron,

Crawley et al. 2008; Mahé

2008; Ahern 2009; Francis

2009; Andrews, Cooper et al.

2010; Dickerson and Valerdi

2010; Francis, Golden et al.

2010; McKnew 2010; Office

2010; LAI 2011)

51 No understanding of stakeholder needs

(Ferns 1991; Cunningham

1998; Ferdowsi 2003;

Tondreault 2003; Valerdi 2005;

Kadish, Abbott et al. 2006;

Loureiro, Crawley et al. 2006;

Valerdi, Rieff et al. 2007;

Cameron, Crawley et al. 2008;

Mahé 2008; Ahern 2009;

Francis 2009; Andrews,

Cooper et al. 2010; Francis,

Golden et al. 2010; McKnew

2010; LAI 2011)

52 No learning from previous need definitions (Downen 2005; Mahé 2008;

Office 2010)

53 Insufficient multi-attribute trade-

offs/tradespace exploration

(Derleth 2003; Roberts 2003;

Ross 2003; Spaulding 2003;

Tang 2006)

54 Lack of requirement understanding (Valerdi 2005; Valerdi, Rieff et

al. 2007; Valerdi 2010)

55 Lack of life cycle documentation (Valerdi 2005; Valerdi, Rieff et

al. 2007; Valerdi 2010)

56 Insufficient probabilistic cost estimates (Dorey 2011; LAI 2011)

57 Too little updating on estimated costs during

early phases

(Valerdi 2010)

58 Cost estimates do not reflect all aspects of

the life cycle

(Silva 2001; Tondreault 2003)

Page 76: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

5 Common issues and pitfalls in program management 69

59 Imprecise or unclear contract terms

(Ferns 1991; Kadish, Abbott et

al. 2006; McKenna 2006;

Ahern 2009; Andrews, Cooper

et al. 2010)

60 Ill-designed contract scope (Ferns 1991; Kinscher 2011)

61 Unclear award criteria and process (Kinscher 2011)

62 Lack of incentives

(Cowap 1998; Mandelbaum,

Kaplan et al. 2001; Kirtley

2002; McVey 2002; Cohen

2005; McKenna 2006; Stanke

2006)

63 Lack of incentive transparency

(Cowap 1998; Mandelbaum,

Kaplan et al. 2001; Kirtley

2002; McKenna 2006; Ahern

2009; (AT&L) 2010)

64 Mismatch of incentive with desired outcome

(Cowap 1998; Mandelbaum,

Kaplan et al. 2001; Kirtley

2002; McVey 2002; McKenna

2006; Ahern 2009; (AT&L)

2010; McKnew 2010)

65 No standard structure for (sub-)contracts (Stanke 2006)

66 Mismatch of contract type with risk profile of

program

(Kinscher 2011)

67 Missing parts in the contract (e.g., include

adaptability)

(Dare 2003; Kinscher 2011)

68 Too much granting of waivers (Cowap 1998)

69 Insufficient probabilistic cost estimates in

contracting

(Dorey 2011)

70 No process implemented to assess

technology maturation

(Kenley and Creque 1999;

Francis 2009; Rhodes, Valerdi

et al. 2009; Tang and Otto

2009; Francis, Golden et al.

2010; McKnew 2010; Office

2010; Roedler, Rhodes et al.

2010)

71 Use of immature technology (Baccarini 1996; Office 2010;

Kinscher 2011)

Page 77: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

5 Common issues and pitfalls in program management 70

72 No established technology insertion process

(Shroyer 2002; Francis 2009;

Francis, Golden et al. 2010;

McKnew 2010)

73 No person/team in charge to manage and

monitor technology transition

(Pomponi 1998; Shroyer 2002;

Francis 2009; Francis, Golden

et al. 2010; McKnew 2010)

74 No formal reviews and communication plans

for technology transition

(Shroyer 2002)

75 No diverse learning strategies (Bresman 2004)

76 Misalignment between team goals and

program goals

(Ferns 1991; Wheelwright and

Clark 1992; Susman and

Petrick 1995)

77 Lack of skill and functional diversity within

team

(Wheelwright and Clark 1992;

Hernandez 1995; Susman and

Petrick 1995; Browning 1996;

Bozdogan, Deyst et al. 1998;

Pomponi 1998; Oehmen 2005)

78 No established flow to and from IPT level (Pomponi 1998)

79

No balance between teams and functions

(only applies to programs with matrix

organizations)

(Ferns 1991; Wheelwright and

Clark 1992; Hernandez 1995)

80

System architecture does not support

product development process or IPTs

(complex organizations often give rise to

overcomplicated system designs)

(Lucas 1996; LAI 2011)

81 Ignoring the aspect of standardization

(Beckert 2000; Nuffort 2001;

Silva 2001; Bador 2007; Boas

2008; Mahé 2008; LAI 2011)

82 Ignoring the aspect of reusability (Nuffort 2001; Bador 2007;

Boas 2008; LAI 2011)

83 Ignoring the aspect of modularity (Nuffort 2001; Bador 2007; LAI

2011)

84 Ignoring the aspect of supportability (Kinscher 2011)

85 Ignoring the aspect of maintainability (Kinscher 2011)

86 Ignoring the aspect of usability (Kinscher 2011)

87 Lack of understanding of what waste is (Kato 2005; McManus 2005;

Page 78: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

5 Common issues and pitfalls in program management 71

Pessôa 2008; Oehmen and

Rebentisch 2010)

88 Lack of understanding of how to deal with

different types of waste or waste in general

(Kato 2005; McManus 2005;

Pessôa 2008; Oehmen and

Rebentisch 2010)

89 No understanding of current vs. preferred

Value Stream

(Kato 2005; McManus 2005;

Oehmen and Rebentisch 2010)

90 No mechanism for Value Stream

improvements

(McManus 2005)

91 Mismatch between program characteristics

and chosen development process

(Bernstein 1998; Ferdowsi

2003; Roberts 2003; Stagney

2003; Tondreault 2003)

92 Finishing engineering and 3D drawings too

late

(Office 2010)

93 Insufficient exploration of alternative

solutions

(Bernstein 1998)

94 Wrong test approaches/frameworks

(Weigel 2000; Carreras 2002;

Deonandan, Valerdi et al.

2010; Hess, Agarwal et al.

2010; Hess and Valerdi 2010;

Office 2010)

95 No balance regarding amount of testing (too

much or too little)

(Office 2010; Kinscher 2011)

In total, 99 different pitfalls were identified using the three types of sources. As one can see,

the different pitfalls have different numbers of sources. Figure 5-1 shows the distribution of

the number of sources for all pitfalls. It becomes clear that a large number of the pitfalls (28)

are each based on only one source. Then again, there are seven pitfalls with more than 10

sources. In general, a decreasing regression line could be shown in the figure. It is

reasonable to infer that the issues that are widely spread among different sources are

important. On the other hand, regarding the many pitfalls which are not often mentioned in

the literature and were not often mentioned in the discussions held as part of this study:

these may be unimportant or they may be important but relatively unrecognized.

Page 79: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

5 Common issues and pitfalls in program management 72

110

1000

3

01

0

3

66

108

17

14

2830

20

10

01 1211109 171615142 1383 75 6 194 18

Number of sources

Pitfalls

Figure 5-1: Distribution of the number of sources for all pitfalls

5.2 Verification of the pitfalls through interviews and the industry focus group

Two different approaches were used to verify the findings presented in Table 5-1:

1. Interviews with Air Force program managers

2. Insights from the members of the industry focus group (telephone interviews and

workshop)

In two separate interviews with Air Force program managers the findings from the literature

were discussed. The interviews were between one and a half hour and two hours long. The

first part of the interviews was used to gain a general overview of the opinion of the

interviewees about pitfalls in program management. This part was based on a free

discussion guided by some starting questions. During the second part of the interview the list

of pitfalls was discussed. Every single pitfall was analyzed in detail together with the program

managers. The author supported the program managers whenever help was needed to

understand the pitfall. These unclarities often implied that the phrasing of the pitfall was not

precise enough. Consequently, some of the pitfalls were rephrased together with the

program managers.

During these discussions it often became clear that there might be additional pitfalls.

Whenever the program manager stated that a missing pitfall is essential for a comprehensive

collection, the pitfall was added to the list. It is outside the objectives of this thesis to

inventory every possible pitfall in program management. Several discussions about specific

pitfalls indicated that some pitfalls on the list could be subdivided into several pitfalls at a

higher level of detail. The author and the program managers tried to provide the level of

detail that was most useful for the purposes of this study.

The second approach to verify the pitfalls was based on the insights of the industry focus

group. First, the workshop with the industry focus group at the end of January was used to

Page 80: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

5 Common issues and pitfalls in program management 73

collect data on program management pitfalls experienced by the members of the group. The

participants were grouped in small teams (four to six persons per group) and asked to

compile their insights into challenges and issues in program management. This data was

compared to the findings from the literature. All identified pitfalls from the workshop were

already in the list and no further insights could be added. This indicates that some of the

pitfalls from the literature can also be found in real programs. Consequently, some of the

pitfalls in the list can be considered to be verified by practical experience.

In addition, the list of pitfalls was further discussed with members of the industry focus group

in a telephone conference. All participants in the conference received the list via email in

advance and were asked to be prepared to provide feedback. During the telephone

conference the participants discussed the organizational structure of the pitfalls and their

experiences of them.

In summary, the members of the industry focus group participating in the telephone

conference as well as the program managers who were interviewed stated that the final

version of the list of program management pitfalls is a complete inventory of common pitfalls

occurring in real programs.

5.3 Mapping pitfalls to program management framework

All identified program management pitfalls correspond with at least one of the framework

parts of the LAI program management framework (otherwise aspects would be missing in the

framework). A pitfall might relate to multiple framework parts, but it is most practicable to

assign a single framework part for each pitfall. For each pitfall there is one framework part

which corresponds most closely with it. The discipline where the pitfall originates (e.g., risk

management) gives a good indication of which framework part might fit. The author identified

the framework part that applies to each pitfall best.

Page 81: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

5 Common issues and pitfalls in program management 74

Table 5-2 shows the results for the framework parts belonging to the Program Execution

area of the framework. The ID numbers given to the pitfalls in Table 5-1 are used again to

show the results of the mapping. On the left side of the table the name of the framework part

is shown, while the right column shows which pitfalls fit best into the framework part. Some

parts of the framework do not have any assigned pitfalls. These are not shown in the

following tables. Furthermore, the number of assigned pitfalls per framework part varies. This

can be explained by the fact that there are different levels of research – and therefore

different numbers of pitfalls which can be identified – in the different framework parts.

Page 82: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

5 Common issues and pitfalls in program management 75

Table 5-2: Mapping of pitfalls to the Program Execution parts of the LAI program management

framework

LAI program management framework

part within Program Execution Corresponding pitfall IDs

Integrating and leading the program

organization

1-9

Stakeholder management 10

Progress monitoring and management 11-14

Risk management 15-18

Project Management 19

Multi-project coordination 20-26

Developing Intellectual Capital 27-31

Program manager characteristics 32

Table 5-3 shows the results of the mapping of the framework parts belonging to Enterprise

Management. Not all framework parts in this area have pitfalls allocated. The part

“Understanding the program enterprise” seems to be underrepresented compared to the

number of pitfalls in the other parts in this area.

Table 5-3: Mapping of pitfalls to the Enterprise Management parts of the LAI program

management framework

LAI program management framework

part within Enterprise Management Corresponding pitfall IDs

Building and transforming the program

enterprise

33-41

Understanding the program enterprise 42

Learning and improvement of the program

enterprise

43-45

Knowledge management 46-49

Table 5-4 displays the results of the mapping of the framework parts belonging to Scoping,

Planning and Contracting in the LAI program management framework. It is clear that the

framework part “Incentive alignment, contract negotiation, and conclusion” is especially

difficult, since 11 pitfalls are allocated to it. On the other hand, the framework part “Managing

trade-offs” seems to be relatively easy—or there might not be enough research on that part

to identify further pitfalls.

Page 83: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

5 Common issues and pitfalls in program management 76

Table 5-4: Mapping of program management pitfalls to the Scoping, Planning & Contracting

framework parts of the LAI program management framework

LAI program management framework

part with Scoping, Planning, and

Contracting

Corresponding pitfall IDs

Definition of stakeholder needs and

requirements

50-52

Managing trade-offs 53

Cost estimation and life cycle costing 54-58

Incentive alignment, contract negotiation,

and conclusion

59-69

Table 5-5 shows the pitfalls in the area of Technology Integration. Only five pitfalls are

allocated to the two parts of this area.

Table 5-5: Mapping of pitfalls to the Technology Integration parts of the LAI program

management framework

LAI program management framework

part within Technology Integration Corresponding pitfall IDs

Technology maturation monitoring 70-71

Technology transition management 72-74

The last table in this series, Table 5-6, presents the pitfalls in the area of Product Design.

The framework part “Monitor PD progress” has the same pitfalls as the framework part

“Progress monitoring and management” in the area of Program Execution; these two

framework parts address nearly the same activities and are closely related but have different

scopes.

Table 5-6: Mapping of pitfalls to the Product Design parts of the LAI program management

framework

LAI program management framework

part within Product Design Corresponding pitfall IDs

PD team organization 75-77

Integrated product and process development 78-80

Monitor PD progress 11-14

Product Architecting 81-86

Page 84: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

5 Common issues and pitfalls in program management 77

Value Stream Optimization 87-90

Product Design Strategy 91-93

Test & Prototyping 94-95

Figure 5-2 shows how many pitfalls are assigned to a framework part. The figure shows that

there are framework parts which cover only very little pitfalls as well as there are framework

parts which cover up to 11 pitfalls.

1

0

22

11

2

3

6

2

5

10987654321

2

4

6

110

Number of pitfalls in a framework part

Framework parts

Figure 5-2: Distribution of number of pitfalls per framework part

Another meaningful insight can be gained by showing the distribution of the 99 pitfalls among

the five major areas within the LAI program management framework; see Figure 5-3. The

numbers of pitfalls correspond very well with the ratings of the members of the industry focus

group shown in Figure 4-9. The members were asked to rate the major framework areas in

terms of the need for future research. Except for the area Product Design, the numbers of

identified pitfalls within the framework areas correspond with the ratings from the survey.

With 36 pitfalls, Program Execution has the highest number, and it was also rated as most in

need of further research. The other areas also “rank” the same in number of pitfalls as they

do in the survey. The areas with high numbers of pitfalls and therefore high chances of

negatively affecting program performance are perceived as not well covered by current

research.

Page 85: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

5 Common issues and pitfalls in program management 78

99

5

36

0

20

TotalTechnology Integration

Enterprise Management

17

Scoping, Planning & Contracting

20

Product Design

21

Program Execution

40

60

80

100

Figure 5-3: Number of pitfalls for the major areas within the LAI program management

framework

5.4 Summary

This chapter was intended to answer the research question, “Are there common pitfalls in

program management?”

The findings in this chapter show that there are indeed common issues and pitfalls in

program management. Table 5-1 is based on conclusions drawn from the current literature.

Two different types of literature are covered by the comprehensive list. First, publications

pertaining to the performance of Defense Acquisition System programs were reviewed.

These are performance assessments carried out by the Government Accountability Office

(GAO), an independent governmental organization that evaluates acquisition program

performance. These reports were used to identify pitfalls and failure patterns in program

management. Second, literature about program management in general, or aspects of it, was

reviewed in order to identify best practices, recommendations for improving performance,

and examples of “worst practices” (actions which lead to degraded performance). All these

results were summarized in the form of a list of pitfalls.

The content of the pitfall list was verified in two basic ways. The first was two interviews with

Air Force program managers. These interviews were used to generate additional pitfalls in

order to cover all crucial aspects of program management. In addition, the pitfalls included in

the list as it stood before these interviews were discussed in detail; this led to the refining of

some of the pitfalls’ definitions and to the elimination from the list of pitfalls that the program

managers stated were not sufficiently important.

Page 86: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

5 Common issues and pitfalls in program management 79

The second verification was performed through work with the industry focus group. First,

some of the pitfalls found in literature were verified by program managers’ having

experienced them during their professional careers. Second, the collection of pitfalls was

discussed with key members of the industry focus group during a telephone conference. All

attendees received the list in advance and were asked to be prepared to provide feedback

during the conference.

In summary, the members of the industry focus group participating in the telephone

conference as well as the program managers who were interviewed stated that the final

version of the list of program management pitfalls includes all of the common pitfalls

occurring in real programs.

To better understand the aspects of program management that are affected by the pitfalls, a

mapping of the pitfalls to the different parts of the LAI program management framework was

conducted. This mapping led to the conclusion that the number of pitfalls related to each of

the five basic framework themes correlates closely with the ratings of the themes in terms of

the need for further research efforts. It was found that the themes rated as more in need of

research in a survey of the members of the industry focus group also had more pitfalls.

Page 87: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 80

6 Lean Enablers in program management

This chapter intends to adapt the ideas of “lean thinking” to program management and will

partly answer the research question, “Are there ways to adapt lean thinking to program

management?”

Section 2.3 briefly introduced the idea of “lean thinking” and its roots. As was explained, the

idea derived from a manufacturing environment. Womack and Jones describe six case

studies in which the use of lean ideas in manufacturing improved costs, lead times, and

inventory up to 90% (Womack and Jones 1996). Especially notable were cost and lead time

reductions of up to 50% achieved by rearranging machines in a factory to establish a

continuous flow. These results were achieved in only a couple of days (LEI 2007).

Even though Toyota also applies “lean thinking” to design and engineering, supply chain

management, and all support activities, not just to production (Morgan and Liker 2006), many

companies, especially in the United States, understand lean as a phenomenon mostly used

in manufacturing (Womack and Jones 1996). This perception might lead to the false

impression that lean is only usable in manufacturing environments.

Another common misperception of “lean thinking” is that it only applies to high-volume/mass

production (Oppenheim, Murman et al. 2011). The fact is that “lean thinking” might also be

effective in one-off applications; e.g., engineering projects or systems engineering.

Oppenheim et al. state that in many environments that are one-off “the processes and

individual tasks should use repeatable logic based on best engineering practices”

(Oppenheim, Murman et al. 2011).

Since the development of “lean thinking,” which was concentrated in the period 1990–96, the

idea has been widely adapted in other environments, such as engineering (McManus,

Haggerty et al. 2007), product development (Morgan and Liker 2006; Ward 2007), education

(Emiliani 2004), supply chain management (Bozdogan 2005), health care (Graban 2008),

and enterprise management (LAI 2001; Jones 2006). The different approaches to adapting

the idea of “lean thinking” to diverse environments demonstrate that the concept of adapting

it to program management is far from unrealistic.

6.1 Sources of Lean Enablers

The work and ideas of Oppenheim et al. (Oppenheim, Murman et al. 2011) pertaining to

identifying Lean Enablers for a specific environment (system engineering) have been very

well known and respected in industry as well as in academia.

Oppenheim defines lean and Lean Enablers in the following manner: “Any enterprise process

which follows the six Lean Principles will be regarded as Lean. As a corollary, any practice

that enables the Value and follows the Lean process will be defined as a Lean enabler.”

(Oppenheim, Murman et al. 2011)

Page 88: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 81

The major advantage of the idea of Lean Enablers is that those best practices can be used in

any program management environment regardless of which management framework is used.

Lean Enablers can be understood as a supplement to currently implemented guidelines. A

comprehensive collection might be used as a road map for implementing “lean thinking” in

program management.

6.1.1 Introduction to Lean Enablers in the context of program management

The Lean Enablers identified in this thesis for application to program management are based

primarily on six sources in the literature, interviews with program managers, and insights

from the industry focus group.

The first source in the literature is “Lean thinking: Banish waste and create wealth in your

corporation” (Womack and Jones 1996) by Womack and Jones. The two authors posit and

describe in detail five lean principles:

1. Specification of customer value

2. Identification of the value stream

3. Creation of a continuous flow

4. Pull of the value

5. Striving for perfection

The second source in the literature is “Toyota's principles of set-based concurrent

engineering” (Sobek, Ward et al. 1999) by Sobek, Ward, and Liker. They describe the idea of

set-based concurrent engineering being used by Toyota. Rather than committing early to a

design solution during the product development process, “design participants reason about,

develop, and communicate sets of solutions in parallel and relatively independently. As the

design progresses, they gradually narrow their respective sets of solutions based on

additional information from development, testing, the customer, and other participants’ sets”

(Sobek, Ward et al. 1999).

Oppenheim’s paper “Lean Product Development Flow” (Oppenheim 2004) is the third source

in the literature used here in identifying Lean Enablers for program management. The author

proposes a framework, based on the five lean principles from Womack and Jones, for

product development. The framework adapts “lean thinking” to product development; its

elements include the ideas of value and waste in product development, best practices to

adapt the five lean principles, metrics to measure if the lean principles are successfully

implemented, etc. The paper also emphasizes the idea of a chief engineer, the person in

charge of the entire program.

The fourth, dual source in the literature is the book chapter “Lean Innovation – Auf dem Weg

zur Systematik” (Schuh, Adickes et al. 2008) and the corresponding paper “Lean Innovation:

Introducing Value Systems to Product Development” (Schuh, Lenders et al. 2008) by Schuh

et al. The authors adapt the idea of “lean thinking” to innovation management, the

management of product or process innovations and their development (Schuh, Lenders et al.

Page 89: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 82

2008). The published framework focuses mainly on the ideas of value and waste in the

development processes.

The fifth source in the literature source of Lean Enablers for program management is “The

Toyota product development system: integrating people, process, and technology” (Morgan

and Liker 2006) by Morgan and Liker. The authors conducted a two-and-a-half-year, in-depth

study of the product development system of Toyota. They define 13 new lean principles for

product development in three subsystems: processes, people, and tools.

The sixth and last source in the literature is the paper, “Lean enablers for systems

engineering” (Oppenheim, Murman et al. 2011) by Oppenheim et al., published in 2011. The

authors identify 194 Lean Enablers for systems engineering. They structure these Lean

Enablers in accord with six lean principles: the five from Womack and Jones (Womack and

Jones 1996) and the principle “respect for people,” emphasized by Sugimori (Sugimori,

Kusunoki et al. 1977).

6.1.2 Discussion and comparison

The literature sources provide multiple insights into various applications of “lean thinking.”

Since many different processes across diverse disciplines are part of program management

(see chapter 4 and the framework description for a detailed overview of the

processes/framework parts), the different sources in the literature can be used to identify

lean ideas for program management. Because this thesis focuses on technical development

programs, the sources that describe ideas of “lean thinking” in this environment are

especially valuable for adaptation to program management.

The identification of Lean Enablers for systems engineering highly influenced the approach

of the author of this thesis. The first idea of the author was to adapt lean ideas to program

management. It became clear that this approach would fail to produce methods that would

be easily applicable. The use (by Oppenheim et al.) of lean best practices, also called Lean

Enablers, to structure findings is simple and brilliant. The term “best practices” is well known

in industry, and developing one’s work methods by identifying and implementing best

practices is common. Consequently, the idea of Lean Enablers will be used in this thesis and

their application will be adapted from systems engineering to program management.

6.2 Findings along the Lean Principles

As described in section 6.1.2, the author uses an approach to structuring lean ideas in

program management that is similar to the approach Oppenheim et al. used for systems

engineering. Oppenheim et al. structure their Lean Enablers in accord with six lean

principles. These six principles are derived from the five from Womack and Jones and from

the principle “Respect for people” posited by Sugimori (Sugimori, Kusunoki et al. 1977).

By using the same structure for Lean Enablers in program management as in system

engineering, one can easily merge these approaches (if this will be necessary). In addition,

Oppenheim et al. used the six principles to structure their Lean Enablers so as to ensure

compatibility with the work of the organization INCOSE (International Council on Systems

Page 90: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 83

Engineering) (INCOSE 2011). Consequently, any Lean Enablers identified for program

management will also be structured in accord with the publications and works of INCOSE.

The next section will describe key findings of the author about “lean thinking” in program

management, organized according to the six lean principles. These findings were used to

create new Lean Enablers for program management and to adapt existing Lean Enablers for

systems engineering to program management.

6.2.1 Principle 1: Specification of customer value

The basic idea of the first lean principle is to distinguish value for the customer and waste in

processes (Morgan and Liker 2006). Value can be defined as every activity which satisfies

the three following criteria:

- The external customer is willing to ”pay” for it

- It transforms information or material or reduces uncertainty

- It provides specified performance right the first time (Oppenheim, Murman et al. 2011)

A key idea for ensuring the delivery of value is the implementation of a chief engineer.

Oppenheim as well as Morgan and Liker emphasizes appointing an employee with broad

experience in different divisions of the company (Oppenheim 2004; Morgan and Liker 2006).

The chief engineer is often described as “the voice of the customer” (Morgan and Liker

2006). He or she has the power to make the final decisions about the directions of the

program, decisions intended to ensure that the final deliverable product or service will fit

customer needs.

The idea of set-based concurrent engineering partly relates to the first lean principle. All

three authors, Sobek, Oppenheim, and Schuh, assert that set-based concurrent engineering

enables a program to explore more solutions than would a traditional product development

approach. Consequently, using the newer approach increases the likelihood of finding a

solution that will satisfy all customer needs (Sobek, Ward et al. 1999; Oppenheim 2004;

Schuh, Adickes et al. 2008).

Another aspect of the first principle is a way to structure the goals of a program according to

the value they deliver to the customer. Schuh suggests a method called “Value System” to

establish a hierarchy in the different goals (Schuh, Adickes et al. 2008). Schuh emphasizes

that his method prevents programs from delivering capabilities that are not required by the

customer and from failing to satisfy some customer needs (Schuh, Adickes et al. 2008).

6.2.2 Principle 2: Value Stream definition

The basic idea of the second principle is the identification of all value-adding and non-value-

adding activities (Hoppmann 2009). The sequence of activities, throughout the program, that

eventually delivers value to the customer is called the value stream.

The idea of the chief engineer’s defining the value stream is explained by Morgan and Liker

and by Oppenheim (Oppenheim 2004; Morgan and Liker 2006). The authors state that the

Page 91: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 84

chief engineer should be responsible for the final definition of the value stream since he or

she is “the voice of the customer.” The chief engineer is also accountable for finding a

consensus across functions regarding the value stream.

A widely used method to define a value stream in a company or a program is value stream

mapping (Oppenheim 2004; McManus 2005; Schuh, Adickes et al. 2008). A core team

(including the chief engineer) plans the activities necessary to deliver a product or service to

satisfy customer needs. The different activities span from the first contact with the customer

through product development and production to the final delivery.

Morgan and Liker describe the idea of frontloading a program (Morgan and Liker 2006). This

idea is especially applicable to development programs since its original application was in a

product development environment.

Another aspect of the idea of set-based concurrent engineering can be found in the second

lean principle. Sobek states that that engineering method is able to provide knowledge to

improve the definition of the value stream (Sobek, Ward et al. 1999). Consequently, all

aspects of set-based concurrent engineering influencing the value stream are found as Lean

Enablers associated with the second lean principle.

A further aspect of the second lean principle is the monitoring of the performance of the

value stream. Oppenheim et al. recommend the implementation of leading indicators and

metrics to manage the program (Oppenheim, Murman et al. 2011).

6.2.3 Principle 3: Creation of a continuous flow

The basic idea of the third lean principle is the implementation of a flow in the activities

defined in the value stream. Some authors state that this principle might be the superordinate

vision of “lean thinking” (Hoppmann 2009).

Having clear and stable requirements (stemming ultimately from customer/user needs) is

crucial to ensure a smooth flow in the program. Therefore, a continuous assessment and

updating of the requirements is essential during the execution of the program (Oppenheim,

Murman et al. 2011).

Since many programs are highly dependent on the information, products, and services of

their suppliers, Morgan and Liker suggest fully integrating the suppliers in the decision-

making of the program (Morgan and Liker 2006). They advocate long-term relationships and

growing trust between the program and the suppliers. In addition, they propose a way to

structure the suppliers hierarchically.

Oppenheim recommends the strategic separation of product development and long-term

research in a program (Oppenheim 2004). He states that research in general is not very

predictable and therefore difficult to synchronize with the rest of the program.

All of the authors – Schuh, Oppenheim, Womack, and Morgan and Liker – describe best

practices for promoting a smooth flow in the program. The use of integrative events on a

regular basis is promoted by Oppenheim (Oppenheim 2004). Morgan and Liker advocate

wrap-up meetings in addition to integrative events (Morgan and Liker 2006).

Page 92: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 85

In addition to implementation of a chief engineer who is also responsible for promoting a

smooth flow in the program, the idea of a “war room” is described in literature (Oppenheim

2004; Morgan and Liker 2006). The war room provides workspace for the chief engineer and

his/her team, and space for their meetings with staff leaders. There are a few best practices

for the furnishing of the war room; e.g., the use of “mobile walls” is recommended.

6.2.4 Principle 4: Pull of the value

The concept of pull, in the strictest sense, is that all processes and activities along the value

stream should be triggered by the customer (Womack and Jones 1996).

Beside some mentions that the chief engineer might help to enforce the concept of pull in the

program (Morgan and Liker 2006), there is not much about applying this principle in current

literature. Only Oppenheim et al. describe some best practices for enforcing the idea of pull

in a program (Oppenheim, Murman et al. 2011).

6.2.5 Principle 5: Striving for perfection

The fifth lean principle describes the concept of the continuous striving for perfection. The

execution and implementation of this concept is never-ending, because a perfect state will

never be reached (Hoppmann 2009).

The ideas of the fifth principle are broadly explained in nearly all literature sources that

describe the five lean principles. Consequently, because the Lean Enablers for systems

engineering are based on these sources, implementing the fifth principle through them can

be accomplished by adjusting the context from systems engineering to program

management.

Some additional aspects, which are not part of the Lean Enablers for systems engineering,

must be added. The practice of comparison with your competition is described by Morgan

and Liker (Morgan and Liker 2006). This practice ensures that managers of future programs

and activities not only learn from past mistakes of their own company or program but also

utilize knowledge gained through the experiences of competitors in a similar environment

with comparable customers.

6.2.6 Principle 6: Respect for People

The concept of the sixth lean principle, “Respect for people,” is not widespread in

conventional lean literature. Oppenheim et al. made a great contribution by developing Lean

Enablers based on the sixth lean principle (Oppenheim, Murman et al. 2011). Since the Lean

Enablers for systems engineering can easily be adapted to program management, most of

the Lean Enablers for program management associated with the sixth lean principle are

based on the work of Oppenheim et al.

Page 93: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 86

6.3 Synthesis in one general framework

The major findings described in section 6.2, together with feedback from various sources,

lead to the comprehensive list of Lean Enablers for program management presented in

Error! Not a valid bookmark self-reference.. The table shows the Lean Enablers and the

corresponding literature which was used to create and phrase the Lean Enablers.

Table 6-1: Lean Enablers for program management

Lean Enabler Literature

source

1. Specification of customer value

(Womack and Jones

2003; Oppenheim

2004)

1.1 Establish customer-defined value to distinguish added

value from waste

(Morgan and Liker

2006)

1.1.1 Define value as the outcome of an activity that satisfies

at least three conditions

(Oppenheim,

Murman et al. 2011)

1.1.1.a. The external customer is willing to pay for it (Oppenheim,

Murman et al. 2011)

1.1.1.b. It transforms information or material or

reduces uncertainty

(Oppenheim,

Murman et al. 2011)

1.1.1.c. It provides specified performance right the

first time

(Oppenheim,

Murman et al. 2011)

1.1.2. Define added value in terms of value to the customer

and for filling his needs

(Oppenheim,

Murman et al. 2011)

1.1.3. Develop a robust process to capture, develop, and

disseminate customer value with extreme clarity

(Oppenheim,

Murman et al. 2011)

1.1.4. Develop an agile process to anticipate, accommodate

and communicate changing customer requirements

(Oppenheim,

Murman et al. 2011)

1.1.5. Do not ignore potential conflicts with other stakeholder

values; seek consensus

(Oppenheim,

Murman et al. 2011)

1.1.6. Explain customer culture to program employees; i.e.,

the value system, approach, attitude, expectation, and issues

(Oppenheim,

Murman et al. 2011)

1.2. Establish a chief engineer (CE) who is ultimately

responsible for delivering value to customer

(Oppenheim 2004;

Morgan and Liker

2006)

Page 94: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 87

1.2.1. CE must have education in systems engineering and

broad experience in all areas involved in programs (Oppenheim 2004)

1.2.2. CE must have technical superiority and exceptional

engineering skills

(Morgan and Liker

2006)

1.2.3. CE has strong leadership skills to mobilize the

organization

(Morgan and Liker

2006)

1.2.4. CE is system designer and overall architect of the

product

(Morgan and Liker

2006)

1.2.5. CE develops the product concept (Morgan and Liker

2006)

1.2.6. CE guides a process of developing consensus across

functions

(Morgan and Liker

2006)

1.2.7. CE is more responsible for decisions about system

integration than personal decisions and project administration

(Morgan and Liker

2006)

1.2.8. CE is responsible for product architecture, product

performance, and product characteristics

(Morgan and Liker

2006)

1.2.9. CE sets performance targets (Morgan and Liker

2006)

1.2.10. CE is responsible for product objectives (Morgan and Liker

2006)

1.2.11. CE is system integrator (bottom-up and technical

integration, rather than top-down approach and social

coordination)

(Morgan and Liker

2006)

1.2.12. CE provides data for parameters in early stages of

the program (Oppenheim 2004)

1.2.13. CE has a no-compromise attitude to achieving targets

(even against stakeholders)

(Morgan and Liker

2006)

1.2.14. CE decides about level of modularity fitting long term

program/company strategy (Oppenheim 2004)

1.3. Set-based concurrent engineering

(Oppenheim 2004;

Schuh, Lenders et al.

2010)

1.3.1. Define feasible regions (Sobek, Durward et

al. 1998)

1.3.2. Explore trade-offs by designing multiple alternatives (Sobek, Durward et

al. 1998; Schuh,

Page 95: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 88

Lenders et al. 2010)

1.3.3. Communicate sets of possibilities (Sobek, Durward et

al. 1998)

1.3.4. Do not narrow down design space early (Schuh, Lenders et

al. 2010)

1.4 Value System – Target Hierarchy (Schuh, Lenders et

al. 2010)

1.4.1. Prioritize targets (Schuh, Lenders et

al. 2010)

1.4.2. Make targets visible to… (Schuh, Lenders et

al. 2010)

1.4.2.a. customers (Schuh, Lenders et

al. 2010)

1.4.2.b. stakeholders (Schuh, Lenders et

al. 2010)

1.4.3.c. suppliers (Schuh, Lenders et

al. 2010)

1.5. Fully integrate your suppliers in the process of the

customer value definition

(Morgan and Liker

2006)

1.3.1. Everyone involved in the program must have a

customer-first spirit

(Oppenheim,

Murman et al. 2011)

1.3.2. Establish frequent and effective interaction with

internal and external customers

(Oppenheim,

Murman et al. 2011)

1.3.3. Pursue an architecture that captures customer

requirements clearly and can be adaptive to changes

(Oppenheim,

Murman et al. 2011)

1.3.4. Establish a plan that delineates the artifacts and

interactions that provide the best means for drawing out

customer requirements

(Oppenheim,

Murman et al. 2011)

2. Value Stream Definition

(Womack and Jones

2003; Oppenheim

2004; Schuh,

Lenders et al. 2010)

2.1 Establish a CE who is ultimately responsible to define the

value stream

(Oppenheim 2004;

Morgan and Liker

2006)

2.1.1. CE is system designer and overall architect of the (Morgan and Liker

Page 96: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 89

product 2006)

2.1.1.a. CE defines value stream according the

product structure

(Morgan and Liker

2006)

2.1.1.b. CE develops product concept (Morgan and Liker

2006)

2.1.1.c. CE is responsible for product architecture,

product performance and product characteristics

(Morgan and Liker

2006)

2.1.2. CE guides a process of developing consensus across

functions

(Morgan and Liker

2006)

2.1.3. CE has a vision for all functional program teams (Morgan and Liker

2006)

2.1.4. CE is responsible to find consensus across functions

regarding the ideal Value Stream (Oppenheim 2004)

2.2. Map the Value stream over the whole program, including all

projects and sub-processes, and improve it

(Womack and Jones

2003ff.; Oppenheim

2004; Schuh,

Lenders et al. 2010)

2.2.1 Develop and execute clear communication plan that

covers entire value stream and stakeholders

(Oppenheim,

Murman et al. 2011)

2.2.2 Have cross-functional stakeholders work together to

build the agreed-upon value stream

(Oppenheim,

Murman et al. 2011)

2.2.3 Maximize co-Iocation opportunities for different

planning departments in the program

(Oppenheim,

Murman et al. 2011)

2.2.4 Use formal value Stream mapping methods to identify

and eliminate waste, and to tailor and scale tasks

(Oppenheim,

Murman et al. 2011)

2.2.5. Scrutinize every step to ensure it adds value, and plan

nothing because “it has always been done”

(Oppenheim,

Murman et al. 2011)

2.2.6. Carefully plan the precedence of both SE and PD

tasks (which task to feed what other task(s) with what data

and when), understanding task dependencies and parent-

child relationships

(Oppenheim,

Murman et al. 2011)

2.2.7. Maximize concurrency of tasks within the program (Oppenheim,

Murman et al. 2011)

2.2.8. Synchronize work flow activities using scheduling

across functions, and even more detailed scheduling within

functions

(Oppenheim,

Murman et al. 2011)

Page 97: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 90

2.2.9. For every action, define who is responsible, approving,

supporting, and informing (“RASI”), using a standard and

effective tool, paying attention to precedence of tasks

(Oppenheim,

Murman et al. 2011)

2.2.10. Plan for level work flow and with precision to enable

schedule adherence and drive out arrival time variation

(Oppenheim,

Murman et al. 2011)

2.2.11. Plan below full capacity to enable work without

accumulation of variability, and permit scheduling flexibility in

work loading; i.e., have appropriate contingency and

schedule buffers

(Oppenheim,

Murman et al. 2011)

2.2.12. Plan to use visual methods wherever possible to

communicate schedules, workloads, changes in customer

requirements, etc.

(Oppenheim,

Murman et al. 2011)

2.3. Plan for Frontloading the Program (Morgan and Liker

2006)

2.3.1. Plan to utilize cross-functional team made up of the

most experienced and compatible people at the start of the

project to look at a broad range of solution sets

(Oppenheim,

Murman et al. 2011)

2.3.2. Anticipate and plan to resolve as many downstream

issues and risks as early as possible to prevent downstream

problems.

(Oppenheim,

Murman et al. 2011)

2.3.3. Plan early for consistent robustness and “first time

right” under “normal” circumstances instead of hero behavior

in later “crisis” situations

(Oppenheim,

Murman et al. 2011)

2.4. Set-based concurrent engineering

(Oppenheim 2004;

Schuh, Lenders et al.

2010)

2.4.1. Integrate knowledge to improve value stream (Sobek, Durward et

al. 1998)

2.4.2. Look for intersections of feasible sets (Sobek, Durward et

al. 1998)

2.4.3. Impose minimum constraint (Sobek, Durward et

al. 1998)

2.4.4. Seek conceptual robustness (Sobek, Durward et

al. 1998)

2.5. Use a CE concept paper (Morgan and Liker

2006)

2.5.1. Let the CE and his/her team create a concept paper (Morgan and Liker

Page 98: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 91

2006)

2.5.2. Schedule meetings to enable including all data in the

concept paper (customer data, marketing department, etc.)

(Morgan and Liker

2006)

2.5.3. Declare the concept paper highly confidential (Morgan and Liker

2006)

2.5.4. Ensure that the length of the concept paper is between

15 and 25 pages

(Morgan and Liker

2006)

2.5.5. Use tables, graphs, and sketches to underpin the

information

(Morgan and Liker

2006)

2.5.6. Use the concept paper as a guideline for future

decisions

(Morgan and Liker

2006)

2.5.7. Distribute the final version of the concept paper to all

assistant CEs and functional staff leaders on the program

(Morgan and Liker

2006)

2.6. Plan to Develop Only What Needs Developing

(Morgan and Liker

2006; Oppenheim,

Murman et al. 2011)

2.6.1. CE is visionary and innovative yet aware of technology

maturation

(Morgan and Liker

2006)

2.6.2. The CE guides tradeoff between creativity and

standard/legacy knowledge (Oppenheim 2004)

2.6.3. The CE takes no unnecessary risks, but does not

avoid risk in general

(Morgan and Liker

2006)

2.6.4. Well-organized research output should be in the form

of technologies that are mature enough to be made robust

but are not yet so (Oppenheim 2004)

2.6.5. Promote reuse and sharing of program assets: Utilize

platforms, standards, busses, and modules of knowledge,

hardware, and software

(Oppenheim,

Murman et al. 2011)

2.6.6. Insist that module proposed for use is robust before

using it

(Oppenheim,

Murman et al. 2011)

2.6.7. Remove show-stopping research/unproven technology

from critical path, staff with experts, and include it in the Risk

Mitigation Plan

(Oppenheim,

Murman et al. 2011)

2.6.8. Defer unproven technology to future technology

development efforts, or future systems

(Oppenheim,

Murman et al. 2011)

2.6.9. Maximize opportunities for future upgrades (e.g., (Oppenheim,

Page 99: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 92

reserve some volume, mass, electric power, computer

power, and connector pins), even if the contract calls for only

one item

Murman et al. 2011)

2.7. Plan Leading Indicators and Metrics to Manage the

Program

(Oppenheim,

Murman et al. 2011)

2.7.1. Use leading indicators to enable action before waste

occurs

(Oppenheim,

Murman et al. 2011)

2.7.2. Focus metrics around customer value, not profit (Oppenheim,

Murman et al. 2011)

2.7.3. Use only few simple and easy-to-understand metrics

and share them frequently throughout the enterprise

(Oppenheim,

Murman et al. 2011)

2.7.4. Use metrics structured to motivate the right behavior (Oppenheim,

Murman et al. 2011)

2.7.5. Use only those metrics that meet a stated need or

objective

(Oppenheim,

Murman et al. 2011)

3. Creation of continuous flow

(Womack and Jones

2003; Oppenheim

2004; Morgan and

Liker 2006; Schuh,

Lenders et al. 2010)

3.1. Establish a CE to ensure a flow throughout the program

(Oppenheim 2004;

Morgan and Liker

2006)

3.1.1. CE has strong leadership skills to mobilize the

organization and establish a flow

(Morgan and Liker

2006)

3.1.2. CE is responsible for product architecture, product

performance, and product characteristics

(Morgan and Liker

2006)

3.1.3. CE sets performance targets (Morgan and Liker

2006)

3.2. Use derivative approaches and platforms

(Morgan and Liker

2006; Schuh,

Lenders et al. 2010)

3.2.1. Use a modular architecture (Schuh, Lenders et

al. 2010)

3.2.2. Plan a frequency for launching new product versions (Schuh, Lenders et

al. 2010)

3.2.3. Define a module or system life cycle (Schuh, Lenders et

Page 100: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 93

al. 2010)

3.2.4. Use derivation management to synchronize the life

cycle with the launch of new products or derivations

(Schuh, Lenders et

al. 2010)

3.2.5. Group modules in a logical way to identify subsystems

to be used again, substituted, or further developed

(Schuh, Lenders et

al. 2010)

3.3. Clarify, Derive, Prioritize Requirements Early and Often

During Execution

(Oppenheim,

Murman et al. 2011)

3.3.1. Since formal written requirements are rarely enough,

provide for follow-up verbal clarification of the context and

need, without allowing requirement creep

(Oppenheim,

Murman et al. 2011)

3.3.2. Create effective channels for clarification of

requirements (possibly involve customer participation in

development IPTs)

(Oppenheim,

Murman et al. 2011)

3.3.3. Listen for and capture unspoken customer

requirements

(Oppenheim,

Murman et al. 2011)

3.3.4. Use architectural methods and modeling for system

representations (3D integrated CAE toolset, mockups,

prototypes, models, simulations, and software design tools)

that allow interactions with customers as the best means of

drawing out customer requirements

(Oppenheim,

Murman et al. 2011)

3.3.5. “Fail early, fail often” through rapid learning techniques

(prototyping, tests, digital reassembly, spiral development,

models, and simulation)

(Oppenheim,

Murman et al. 2011)

3.3.6. Identify a small number of goals and objectives that

articulate what the program is set up to do, how it will do it,

and what the success criteria will be to align stakeholders

and repeat these goals and objectives consistently and often

(Oppenheim,

Murman et al. 2011)

3.4. Fully integrate the supplier into the program (Morgan and Liker

2006)

3.4.1. Do not only focus on costs while choosing suppliers:

balance between quality and cost

(Morgan and Liker

2006)

3.4.2. Help out struggling suppliers if necessary (Morgan and Liker

2006)

3.4.3. Design contracts that are easy to understand (Morgan and Liker

2006)

3.4.4. Invite engineers from your suppliers into your program (Morgan and Liker

2006)

Page 101: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 94

3.4.4. Honor the contracts – do not renege on them to save

costs

(Morgan and Liker

2006)

3.4.5. Treat suppliers with respect (Morgan and Liker

2006)

3.4.5.1. Do not change orders without reimbursement

for the supplier

(Morgan and Liker

2006)

3.4.5.2. Prevent any bureaucracy in the interaction

with your supplier

(Morgan and Liker

2006)

3.4.5.3. Never bully your supplier (Morgan and Liker

2006)

3.4.5.4. Respect the intellectual property of the

knowledge of your suppliers

(Morgan and Liker

2006)

3.4.6.Set aggressive performance targets, but work together

with suppliers to achieve them

(Morgan and Liker

2006)

3.4.7. Implement a process for supplier selection (Morgan and Liker

2006)

3.4.8. Use a tier structure for your suppliers: (Morgan and Liker

2006)

3.4.8.a. Partner: highest level of supplier; technically

autonomous; delivers products with highest technical

complexity

(Morgan and Liker

2006)

3.4.8.b. Mature: very strong engineering and

manufacturing capabilities, but a bit less autonomous;

relies on specification of program; delivers products

with high technical complexity

(Morgan and Liker

2006)

3.4.8.c. Consultative: influences the specifications by

own suggestions; program can tap into its expertise;

delivers products with low technical complexity

(Morgan and Liker

2006)

3.4.8.d. Contractual: no major relationship; delivers

products with low technical complexity; program

should monitor quality, cost and delivery

(Morgan and Liker

2006)

3.5 Front-load the product development process in the program (Morgan and Liker

2006)

3.5.1. Product Line Optimization – Feature Clusters (Schuh, Lenders et

al. 2010)

3.5.1.1. Use a technology model to structure the (Schuh, Lenders et

Page 102: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 95

product al. 2010)

3.5.1.2. Use “musts” and “don’ts” to classify product

characteristics

(Schuh, Lenders et

al. 2010)

3.5.2. Use a clear architectural description of the agreed-

upon solution to plan coherent program, engineering, and

commercial structures

(Oppenheim,

Murman et al. 2011)

3.5.3. All other things being equal, select the simplest

solution

(Oppenheim,

Murman et al. 2011)

3.5.4. Invite suppliers to make a serious contribution to

various stages of the program as trusted program partners

(Oppenheim,

Murman et al. 2011)

3.6. Strategic separation of research, development and

deployment (Oppenheim 2004)

3.6.1. Research should be strategic, long-term, and ongoing

(must not even be connected to the program) (Oppenheim 2004)

3.6.2. Functional engineering department transforms and

translates the research output into a robust, mature

technology using modularization and ensuring maximum: (Oppenheim 2004)

3.6.2.a. Degree of usability (Oppenheim 2004)

3.6.2.b. Manufacturability (Oppenheim 2004)

3.6.2.c. Low cost (Oppenheim 2004)

3.6.3. Incorporate the robust, mature technology into the

program flow (Oppenheim 2004)

3.6.4. Ensure that there is an established flow between the

three functions (but independent from the internal program

flow) (Oppenheim 2004)

3.7. Use Efficient and Effective Communication and

Coordination

(Oppenheim,

Murman et al. 2011)

3.7.1. Capture and absorb lessons learned from almost all

programs: “never enough coordination and communication”

(Oppenheim,

Murman et al. 2011)

3.7.2. Maximize coordination of effort and flow (Oppenheim,

Murman et al. 2011)

3.7.3. Maintain counterparts with active working relationships

throughout the enterprise to facilitate efficient communication

and coordination among different parts of the enterprise, and

with suppliers

(Oppenheim,

Murman et al. 2011)

3.7.4. Use frequent, timely, open and honest communication (Oppenheim,

Page 103: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 96

Murman et al. 2011)

3.7.5. Promote immediate direct informal communications as

needed

(Oppenheim,

Murman et al. 2011)

3.7.6. Use concise, one-page electronic forms (e.g., Toyota’s

A3 form) rather than verbose unstructured memos to

communicate, and keep detailed working data as backup

(Oppenheim,

Murman et al. 2011)

3.7.7. Report cross-functional issues to be resolved on

concise standard one-page forms to Chief’s office in real time

for his/her prompt resolution

(Oppenheim,

Murman et al. 2011)

3.7.8. Communicate all expectations to suppliers with crystal

clarity, including the context and need, and all procedures

and expectations for acceptance test, and ensure that the

requirements are stable

(Oppenheim,

Murman et al. 2011)

3.7.9. Trust engineers to communicate with suppliers’

engineers directly for efficient clarification, within a framework

of rules, (but watch for high-risk items, which must be

handled at top level)

(Oppenheim,

Murman et al. 2011)

3.8. Promote smooth flow in the entire program

(Womack and Jones

2003; Oppenheim

2004; Morgan and

Liker 2006; Schuh,

Lenders et al. 2010)

3.8.1. Use integrative events (Oppenheim 2004)

3.8.1.a. Question everything with multiple “whys” (Oppenheim,

Murman et al. 2011)

3.8.1.b. Align process flow to decision flow (Oppenheim,

Murman et al. 2011)

3.8.1.c. Resolve all issues as they occur in frequent

integrative events

(Oppenheim,

Murman et al. 2011)

3.8.1.d. Discuss trade-offs and options (Oppenheim,

Murman et al. 2011)

3.8.2. Establish daily wrap-up meetings (Morgan and Liker

2006)

3.8.3. Be willing to challenge the customer’s assumptions on

technical and meritocratic ground, and to maximize program

stability, relying on technical expertise

(Oppenheim,

Murman et al. 2011)

3.8.4. Ensure the use of the same measurement standards (Oppenheim,

Page 104: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 97

and ensure data base commonality Murman et al. 2011)

3.8.5. Ensure that both data deliverers and receivers

understand their mutual needs and expectations

(Oppenheim,

Murman et al. 2011)

3.9. Provide a workspace for CE and his team: the “war room”

(Oppenheim 2004;

Morgan and Liker

2006)

3.9.1. Staff leaders (leaders of functional groups) meet CE in

the “war room”

(Morgan and Liker

2006)

3.9.2. Staff leaders have desk in their functions and come to

the war room regularly

(Morgan and Liker

2006)

3.9.3. There are long, collaborative work sessions in the war

room (not traditional meetings)

(Morgan and Liker

2006)

3.9.4. Room is equipped with “mobile walls” that can be used

as display surfaces for visualization

(Morgan and Liker

2006)

3.9.5. Engineers plaster the room’s walls and “mobile walls”

with information

(Morgan and Liker

2006)

3.9.6. Information on the wall is organized in terms of the

projects of the program

(Morgan and Liker

2006)

3.9.7. Project managers are responsible for assignment of

person in charge of providing visualizations of information in

the war room

(Morgan and Liker

2006)

3.10. Align your organization through simple, visual

communication, and make program progress visible to all

(Morgan and Liker

2006)

3.10.1. Avoid too many and too long meetings (Morgan and Liker

2006)

3.10.2. Make work progress visible to and easy to

understand for all, including external customer

(Oppenheim,

Murman et al. 2011)

3.10.3. Utilize visual controls in public spaces for best

visibility (avoid computer screens)

(Oppenheim,

Murman et al. 2011)

3.10.4. Develop a system that makes imperfections and

delays visible to all

(Oppenheim,

Murman et al. 2011)

3.10.5. Use traffic light system (green, yellow, red) to report

task status visually (good, warning, critical) and make certain

problems are not concealed

(Oppenheim,

Murman et al. 2011)

3.11. Set-based concurrent engineering (Oppenheim 2004;

Schuh, Lenders et al.

Page 105: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 98

2010)

3.11.1. Establish feasibility before commitment to ensure

smooth flow

(Sobek, Durward et

al. 1998)

3.11.2. Narrow sets gradually while increasing level of detail (Sobek, Durward et

al. 1998)

3.11.3. Stay within sets once committed (Sobek, Durward et

al. 1998)

3.11.4. Control by managing uncertainty at process gates (Sobek, Durward et

al. 1998)

3.12. Utilize rigorous standardization to reduce variation and to

create flexibility and predictable outcomes

(Morgan and Liker

2006)

3.12.1. Adapt the technology to fit the people and process (Morgan and Liker

2006)

3.12.2. Use lean tools to promote the flow of information and

minimize handoffs: small batch size of information, small takt

times, wide communication bandwidth, standardization, work

cells, training

(Oppenheim,

Murman et al. 2011)

3.12.3. Use minimum number of tools and make common

wherever possible

(Oppenheim,

Murman et al. 2011)

3.12.4. Minimize the number of software revision updates

and centrally control the update releases to prevent

information churning

(Oppenheim,

Murman et al. 2011)

3.12.5. Adapt the technology to fit the people and process (Oppenheim,

Murman et al. 2011)

3.12.6. Avoid excessively complex “monument” tools (Oppenheim,

Murman et al. 2011)

3.13. Capacity planning/balancing Model (Schuh, Lenders et

al. 2010)

3.13.1. Implement a control loop to control capacity utilization (Schuh, Lenders et

al. 2010)

3.13.2. Identify necessary skills for program execution and

specify profiles for each job position based on the skills

(Schuh, Lenders et

al. 2010)

3.13.3. Calculate available capacity for each identified skill (Schuh, Lenders et

al. 2010)

3.13.4. Base capacity planning on the deviation between

available capacity and the capacity utilization aimed at

(Schuh, Lenders et

al. 2010)

Page 106: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 99

(command variable)

3.13.5. Evaluate and execute different actions (e.g., employ

more/fewer employees, develop your employees, etc.) to

minimize deviation

(Schuh, Lenders et

al. 2010)

4. Pull of the value (Womack and Jones

2003; Oppenheim

2004)

4.1. Establish a CE

(Oppenheim 2004;

Morgan and Liker

2006)

4.1.1. CE has strong leadership to mobilize the organization

and to coordinate the pull through the program

(Morgan and Liker

2006)

4.1.2. CE sets performance targets to pull information

through the program

(Morgan and Liker

2006)

4.2. Pull Tasks and Outputs Based on Need, and Reject Others

as Waste

(Oppenheim,

Murman et al. 2011)

4.2.1. Let information needs pull the necessary work

activities

(Oppenheim,

Murman et al. 2011)

4.2.2. Understand the Value Stream Flow (Oppenheim,

Murman et al. 2011)

4.2.3. Train the team to recognize, for every task, who the

internal customer (receiver) is and who the supplier (giver) is,

using a SIPCO (supplier, inputs, process, outputs, customer)

model to better understand the value stream

(Oppenheim,

Murman et al. 2011)

4.2.4. Stay connected to the internal customer during task

execution

(Oppenheim,

Murman et al. 2011)

4.2.5. Avoid rework by coordinating task requirements with

internal customer for every non-routine task

(Oppenheim,

Murman et al. 2011)

4.2.6. Promote effective, real-time direct communication

between each giver and receiver in the value flow

(Oppenheim,

Murman et al. 2011)

4.2.7. Develop giver-receiver relationships based on mutual

trust and respect

(Oppenheim,

Murman et al. 2011)

4.2.8. When pulling work, use customer value to separate

added value from waste

(Oppenheim,

Murman et al. 2011)

5. Striving for Perfection (Womack and Jones

2003; Oppenheim

2004; Morgan and

Page 107: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 100

Liker 2006; Schuh,

Lenders et al. 2010)

5.1. Strive for Excellence of Program Management (Oppenheim,

Murman et al. 2011)

5.1.1. Build a culture to support excellence and relentless

improvement

(Morgan and Liker

2006)

5.1.2. Do not ignore the basics of Quality: (Oppenheim,

Murman et al. 2011)

5.1.2.a. Build-in robust quality at each step of the

process, and resolve to not pass along problems

(Oppenheim,

Murman et al. 2011)

5.1.2.b. Strive for perfection in each process step

without introducing waste

(Oppenheim,

Murman et al. 2011)

5.1.2.c. Do not rely on final inspection; error-proof

wherever possible

(Oppenheim,

Murman et al. 2011)

5.1.2.d. If final inspection is required by contract,

perfect upstream process pursuing 100% inspection

pass rate

(Oppenheim,

Murman et al. 2011)

5.1.2..e. Move final inspectors upstream to take the

role of quality mentors

(Oppenheim,

Murman et al. 2011)

5.1.2..f. Apply basic PDCA method (plan, do, check,

act) to problem solving

(Oppenheim,

Murman et al. 2011)

5.1.2.g. Adopt and promote a culture of stopping and

permanently fixing a problem as soon as it becomes

apparent

(Oppenheim,

Murman et al. 2011)

5.1.3. Promote excellence under normal circumstances

instead of hero behavior in “crisis” situations

(Oppenheim,

Murman et al. 2011)

5.1.4. Use and communicate failures as opportunities for

learning, emphasizing process and not people problems

(Oppenheim,

Murman et al. 2011)

5.1.5. Treat any imperfection as an opportunity for immediate

improvement and a lesson to be learned, and frequently

review lessons learned

(Oppenheim,

Murman et al. 2011)

5.1.6. Maintain a consistent, disciplined approach to

engineering

(Oppenheim,

Murman et al. 2011)

5.1.7. Promote the idea that the system should incorporate

continuous improvement in the organizational culture, but

also…

(Oppenheim,

Murman et al. 2011)

Page 108: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 101

5.1.8. …balance the need for excellence with avoidance of

wasteful overprocessing (pursue refinement to the point of

ensuring value and “first time right”)

(Oppenheim,

Murman et al. 2011)

5.1.9. Use a balanced matrix/project organizational

approach, avoiding extremes: such as functionally territorial

organizations with isolated technical specialists and all-

powerful IPTs separated from functional expertise and

standardization

(Oppenheim,

Murman et al. 2011)

5.2. Build a culture that supports excellence and relentless

improvement

(Morgan and Liker

2006)

5.2.1. Use lessons learned from past programs in future

programs

(Oppenheim,

Murman et al. 2011)

5.3.1. Maximize opportunities to make each next

program better than the last

(Oppenheim,

Murman et al. 2011)

5.3.2. Create mechanism to capture, communicate,

and apply experience-generated learning and

checklists

(Oppenheim,

Murman et al. 2011)

5.3.3. Insist on workforce training regarding

identification of the root cause of a problem and

appropriate corrective action

(Oppenheim,

Murman et al. 2011)

5.3.4. Identify best practices through benchmarking

and professional literature

(Oppenheim,

Murman et al. 2011)

5.3.5. Share metrics of suppliers’ performance with

them so they can improve

(Oppenheim,

Murman et al. 2011)

5.2.2. Compare your results with your competitors’

results

(Morgan and Liker

2006)

5.2.2.1. Evaluate your products by competitor

teardowns regarding…

(Morgan and Liker

2006)

5.2.2.1.a. Quality (Morgan and Liker

2006)

5.2.2.1.b. Performance (Morgan and Liker

2006)

5.2.2.1. c. Ease of manufacturing (Morgan and Liker

2006)

5.3. Develop policy of perfect communication, coordination and

collaboration across people and processes

(Oppenheim,

Murman et al. 2011)

Page 109: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 102

5.3.1. Develop a plan for – and train the entire program team

in – communications and coordination methods at the

beginning of the program

(Oppenheim,

Murman et al. 2011)

5.3.2. Include communication competence among the

desired skills during hiring

(Oppenheim,

Murman et al. 2011)

5.3.3. Promote good coordination and communications skills

with training and mentoring

(Oppenheim,

Murman et al. 2011)

5.3.4. Publish instructions for email distributions and

electronic communications

(Oppenheim,

Murman et al. 2011)

5.3.5. Publish instructions for artifact content and data

storage – central capture versus local storage, paper versus

electronic – balancing between excessive bureaucracy and

the need for traceability

(Oppenheim,

Murman et al. 2011)

5.3.6. Publish a directory of the entire program team and

provide training to new hires on how to locate nodes of

knowledge as needed

(Oppenheim,

Murman et al. 2011)

5.3.7. Ensure timely and efficient access to centralized data (Oppenheim,

Murman et al. 2011)

5.3.8. Develop an effective body of knowledge that is

historical, searchable, and shared by the team, and a

knowledge management strategy to facilitate the sharing of

data and information within the enterprise

(Oppenheim,

Murman et al. 2011)

5.4. For every program, develop a chief engineer system

(Oppenheim 2004;

Morgan and Liker

2006)

5.4.1. Provide small team to the CE (Morgan and Liker

2006)

5.4.2. CE guides a process of developing consensus across

functions

(Morgan and Liker

2006)

5.4.3. CE is more responsible for decisions about system

integration than personnel decisions and project

administration

(Morgan and Liker

2006)

5.4.4. CE has a vision for all functional program teams (Morgan and Liker

2006)

5.4.5. Implement a culture to support the CE (Morgan and Liker

2006)

5.4.6. CE has good interpersonal skills to motivate and lead (Oppenheim 2004;

Page 110: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 103

his/her team and is a patient listener Morgan and Liker

2006)

5.4.7. CE is a good communicator, both internally and

externally

(Morgan and Liker

2006)

5.4.8. If Program Manager and Chief Engineer are two

separate individuals (required by contract or organizational

practice), co-locate them to facilitate constant close

coordination

(Oppenheim,

Murman et al. 2011)

5.5. Use powerful tools for standardization and organizational

learning

(Morgan and Liker

2006)

5.5.1. Use a model of product architecture, technology-

and function

(Schuh, Lenders et

al. 2010)

5.5.1.1. Promote design standardization through

engineering checklists, standard architecture,

modularization, busses, and platforms

(Oppenheim,

Murman et al. 2011)

5.5.2. Promote process standardization in development,

management, and manufacturing

(Oppenheim,

Murman et al. 2011)

5.5.3. Promote standardized skill sets with careful training,

mentoring, rotations, strategic assignments, and

assessments of competencies

(Oppenheim,

Murman et al. 2011)

5.5.4. Organize so as to balance functional expertise and

cross-functional integration

(Morgan and Liker

2006)

5.6 Motivate the employees of the program through product

identity

(Schuh, Lenders et

al. 2010)

5.6.1. Motivate all members of the program intrinsic (Schuh, Lenders et

al. 2010)

5.6.2. Establish an emotional tie to the product (Schuh, Lenders et

al. 2010)

5.6.2.1. Communicate uniqueness of product (Schuh, Lenders et

al. 2010)

5.6.2.2. Idealize and perfect the product (Schuh, Lenders et

al. 2010)

5.6.2.3. Make the product experienceable (Schuh, Lenders et

al. 2010)

5.6.2.4. Imprint identification with the product on

employees early and follow up by making use of this

imprinting

(Schuh, Lenders et

al. 2010)

Page 111: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 104

6. Respect for People (Oppenheim,

Murman et al. 2011)

6.1. Build an Organization Based on Respect for People (Oppenheim,

Murman et al. 2011)

6.1.1. Create a vision which draws and inspires the best

people

(Oppenheim,

Murman et al. 2011)

6.1.2. Invest in personnel selection and development to

promote enterprise and program excellence

(Oppenheim,

Murman et al. 2011)

6.1.3. Promote excellent human relations: trust, respect,

empowerment, teamwork, stability, motivation, drive for

excellence

(Oppenheim,

Murman et al. 2011)

6.1.4. Ensure that there is professional trust through: (Morgan and Liker

2006)

6.1.4.1. Integrity: People must have the intent to do

what they say they will

(Morgan and Liker

2006)

6.1.4.2. Competence: They must be capable of doing

it

(Morgan and Liker

2006)

6.1.5. Read applicants’ resumes carefully for both technical

and non-technical skills, and do not rely upon computer

scanning for keywords

(Oppenheim,

Murman et al. 2011)

6.1.6. Promote direct person-to-person communication (Oppenheim,

Murman et al. 2011)

6.1.7. Promote and honor technical excellence – establish a

technical meritocracy

(Oppenheim,

Murman et al. 2011)

6.1.8. Reward people based upon team performance, and

include teaming ability among the criteria for hiring and

promotion

(Oppenheim,

Murman et al. 2011)

6.1.9. Use flow-down of responsibility, authority and

accountability (RAA) to make decisions at lowest appropriate

level

(Oppenheim,

Murman et al. 2011)

6.1.10. Eliminate fear and promote conflict resolution at the

lowest level

(Oppenheim,

Murman et al. 2011)

6.1.11. Keep management decisions crystal clear but also

promote and reward the bottom-up culture of continuous

improvement, human creativity, and entrepreneurship

(Oppenheim,

Murman et al. 2011)

6.1.12. Do not manage from cubicle; go to the spot and see (Oppenheim,

Page 112: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 105

for yourself Murman et al. 2011)

6.1.13. Within program policy and within their area of work,

empower people to accept responsibility by promoting the

motto “Ask for forgiveness rather than ask for permission”

(Oppenheim,

Murman et al. 2011)

6.1.14. Build a culture of mutual support (there is no shame

in asking for help)

(Oppenheim,

Murman et al. 2011)

6.1.15. Prefer physical team co-location to virtual co-location (Oppenheim,

Murman et al. 2011)

6.2. Develop towering technical competence in all engineers

and strive for technical excellence

(Morgan and Liker

2006)

6.2.1. Establish training across functions (Morgan and Liker

2006)

6.2.2. Establish standardization for skill expectations (Morgan and Liker

2006)

6.2.3. Establish and support a communities of practice (Oppenheim,

Murman et al. 2011)

6.2.4. Invest in Workforce Development (Oppenheim,

Murman et al. 2011)

6.2.5. Ensure tailored lean training for all employees (Oppenheim,

Murman et al. 2011)

6.2.6. Give leaders at all levels in-depth lean training (Oppenheim,

Murman et al. 2011)

6.3. Nurture a Learning Environment (Oppenheim,

Murman et al. 2011)

6.3.1. Perpetuate technical excellence through mentoring,

training, continuing education, and other means

(Oppenheim,

Murman et al. 2011)

6.3.2. Promote and reward continuous learning through

education and experiential learning

(Oppenheim,

Murman et al. 2011)

6.3.3. Provide knowledge experts as resources and for

mentoring

(Oppenheim,

Murman et al. 2011)

6.3.4. Cultivate the most powerful competitive weapon: the

ability to learn rapidly and continuously improve

(Oppenheim,

Murman et al. 2011)

6.3.5. Value people for the skills they contribute to the

program; foster mutual respect and appreciation

(Oppenheim,

Murman et al. 2011)

6.3.6. Capture learning to stabilize the program when people

change their position in the program or leave the program

(Oppenheim,

Murman et al. 2011)

Page 113: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 106

6.3.7. When developing a standard, consider human factors,

including reading and perception abilities

(Oppenheim,

Murman et al. 2011)

6.3.8. Immediately organize quick training in any new

standard

(Oppenheim,

Murman et al. 2011)

6.4. Treat People as the program’s most valued assets, not as

commodities

(Oppenheim,

Murman et al. 2011)

To provide a better overview of the different sources used in compiling Lean Enablers for

program management, Figure 6-1 shows the percentage of the enablers that were derived

from each of the different sources. The total adds up to 108,1% because some of the Lean

Enablers are based on more than one source.

108,1%

2,3%3,5%

47,7%

Morgan & Liker 2006

31,6%

Oppenheim et al. 2011

TotalWomack 2003Sobek 1998Oppenheim 2004

10,3%

Schuh 2008

12,6%

Figure 6-1: Percentage of the compiled Lean Enablers for program management that were

derived from each literature source

Figure 6-2 shows the total number of Lean Enablers. In addition, the number of categories

into which these Lean Enablers are divided is shown (e.g., 1.1 is a category of lean principle

1.). Each category has an average of slightly under nine Lean Enablers.

Page 114: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 107

35

310

Total

Subcategories

Enablers

Figure 6-2: Total number of Lean Enablers and categories

Figure 6-3 shows how the different Lean Enablers are distributed over the six lean principles.

One can see that a higher number of Lean Enablers corresponds with a higher number of

categories. Consequently, the average number of Lean Enablers per category estimated

from Figure 6-2 seems to be also valid for each lean principle’s portion of the subcategories.

The third lean principle has the highest number of Lean Enablers. This is in accord with the

finding in section 6.2.3 that many authors consider the third lean principle – the creation of a

continuous flow – as the one most fundamental to the implementation of lean thinking.

462

137

3

36

61

13

103

55

42

6. Respect for People

5. Striving for Perfection

4. Pull of the Value3. Creation of a Continuous Flow

2. Value Stream Definition

1. Specification of Customer Value

Enablers

Subcategories

Figure 6-3: Distribution of the Lean Enablers and the subcategories among the six lean

principles

Page 115: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 108

6.4 Assessment through the industry focus group

To verify the comprehensiveness of the list of Lean Enablers presented in The major findings

described in section 6.2, together with feedback from various sources, lead to the

comprehensive list of Lean Enablers for program management presented in Error! Not a

valid bookmark self-reference.. The table shows the Lean Enablers and the corresponding

literature which was used to create and phrase the Lean Enablers.

Table 6-1, a document containing the list was sent to the members of the industry focus

group for review. The results of the reviews by the members of the industry focus group were

discussed in a telephone conference. All participants provided feedback to further improve

the list.

One participant of the group who developed the Lean Enablers for Systems Engineering was

a participant in the telephone conference. She provided insights into the development

process for the Lean Enablers for System Engineering and could give precise and specific

feedback on the development process and structure of the Lean Enablers for program

management.

All feedback from the members of the industry focus group provided in writing or during the

telephone conference was used to improve the list of enablers. In summary, it can be stated

that all persons from the industry focus group contributing final feedback on the list of Lean

Enablers for program management found the list as presented in The major findings

described in section 6.2, together with feedback from various sources, lead to the

comprehensive list of Lean Enablers for program management presented in Error! Not a

valid bookmark self-reference.. The table shows the Lean Enablers and the corresponding

literature which was used to create and phrase the Lean Enablers.

Table 6-1 to be comprehensive and to be easy to comprehend in terms of the descriptions of

the enablers.

6.5 Summary

This chapter described the first part of the adaption of “lean thinking” to program

management. This adaption corresponds to the fourth research question of this thesis: “Are

there ways to adapt lean thinking in program management?”

The author adapted the idea of Lean Enablers for Systems Engineering from Oppenheim et

al. (Oppenheim, Murman et al. 2011). Oppenheim et al. identified best practices

corresponding with lean and called them Lean Enablers. These Lean Enablers are structured

according to six lean principles: the five principles from Womack and Jones (Womack and

Jones 1996) and the principle “Respect for people” from Sugimori (Sugimori, Kusunoki et al.

1977).

The first part of this chapter gave an overview of the sources that were used to identify Lean

Enablers for program management. The sources were all briefly discussed. Afterwards, the

adaptability of Lean Enablers in general to program management was assessed.

Page 116: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

6 Lean Enablers in program management 109

Using the same structure as Oppenheim et al. for the Lean Enablers for program

management, six lean principles were discussed in terms of how they can be applied through

Lean Enablers for program management. The literature sources provide knowledge about

lean best practices in program environments.

Based on these findings, a list of 310 Lean Enablers for program management was created

and presented. The approach to having the industry focus group verify the

comprehensiveness and clarity of the list was then described.

Page 117: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

7 Mapping of Lean Enablers to program management pitfalls 110

7 Mapping of Lean Enablers to program management

pitfalls

In this chapter, the central findings of chapter 6, the list of 310 Lean Enablers for program

management are taken to the next step in the application of “lean thinking” to program

management. This step is the enabling of persons involved in program management (e.g.,

program managers, members of the program office, et al.) avoid the identified pitfalls in

program management. The approach used is to map the Lean Enablers of chapter 6 to the

program management pitfalls identified in chapter 5. The basic idea of the mapping of the

Lean Enablers to the program management pitfalls is the identification of the most beneficial

combinations. If the Lean Enablers are applied correctly, the most common pitfalls can be

evaded by the program managers. If program managers know about some pitfalls which are

especially likely to happen in their programs, they can use the specialized Lean Enablers to

improve program performance by escaping these pitfalls.

Together with the mapping of the Lean Enablers to the common program management

pitfalls, program managers are fully capable of using lean thinking in program management.

Consequently, the research question: “Are there ways to adapt lean thinking in program

management?” will be answered at the end of the chapter by combing the findings of the

mapping of this chapter with the Lean Enablers and the program management pitfalls.

7.1 Methodology for the mapping

The mapping approach used in this thesis to map the Lean Enablers to the program

management pitfalls is a connection matrix between the enablers and the pitfalls. The first

decision regarding this approach was the scope of the mapping. In order to map all 310 Lean

Enablers to all 99 pitfalls, one would have to assess about 30,690 possible connections.

Assuming that it takes about 10 seconds to judge if there is a connection between a Lean

Enabler and a pitfall (this might even be underestimating, since the mere reading of the pitfall

description and the Lean Enabler description would take several seconds), one would need

5.115 minutes to perform the mapping. In addition, it would not be very useful if the program

manager were to be confronted by a list of dozens of Lean Enablers for a single pitfall.

Consequently, the author decided to limit the scope of the mapping. The approach used in

this thesis maps the 35 categories of the Lean Enablers to the 99 pitfalls. This still leads to

3,465 possible connections, but this number is smaller by about an order of 10 than the one

that would result from a full mapping. This method required about 600 minutes of mapping

(based on the same estimate of 10 seconds per possible connection).

The assessment of whether a Lean Enabler subcategory would be beneficial in connection

with a pitfall was based on the author’s personal experience and opinion. The author based

his decisions on the knowledge gained during the literature research, the interviews with

program managers, and the interactions with the members of the industry focus group.

Page 118: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

7 Mapping of Lean Enablers to program management pitfalls 111

In the matrix (recorded using a Microsoft Excel spreadsheet), the pitfalls are arranged in

rows and the Lean Enabler subcategories in columns. The author judged whether a pitfall

and an enabler have a connection (indicated by an “x” in the appropriate cell) or not

(indicated by an empty cell). Error! Reference source not found. is a screenshot of the

spreadsheet.

Figure 7-1: Screenshot from the mapping (in Microsoft Excel)

An example of a connection that was judged to be beneficial by the author is the link

between the pitfall “Lack of metrics” (ID #12) and the Lean Enabler subcategory “Plan

Leading Indicators and Metrics to Manage the Program” (2.7). An example of a lack of

connection is the same pitfall, “Lack of metrics” (ID #12), and the Lean Enablers subcategory

“Build an Organization Based on Respect for People” (6.1).

It is clear that all of the assessments made by the author regarding possible connections

were highly subjective. One might argue that some beneficial connections were omitted and

that some of the inclusions should have been omitted. But it is the author’s opinion that a

proliferation of connections would have led to confusion rather than helping. Giving program

managers a usable tool to avoid common pitfalls in their program environment was the

purpose of the mapping. Therefore, focused, specific guidance has been provided rather

than recommending all possible Lean Enablers for each pitfall.

Page 119: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

7 Mapping of Lean Enablers to program management pitfalls 112

7.2 Results of the mapping process

This section describes various analyses of the results of the process. The main objective of

this section is to determine where the application of the Lean Enablers for program

management is most beneficial. A complete record of the mapping itself can be found – as a

list of pitfalls and corresponding Lean Enablers subcategories – in chapter VII, Appendix A.

The first results are shown in Figure 7-2. The figure displays the distribution of the number of

identified connections per program management pitfall. The average number of identified

connections to Lean Enablers for one program management pitfall is 9,17. Most pitfalls are

addressed by 4–15 Lean Enablers; very few pitfalls are addressed by more or fewer than

that.

100

2

0

3

0

233

2

6

4

1515

11

2

10

5

9

32

00

5

10

15

1 2 3 54 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Average 9,17

Figure 7-2: Number of identified connections with a Lean Enabler per program management

pitfall

A second finding of the mapping is how well the various Lean Enabler categories address the

different framework themes of the LAI program management framework. Figure 7-3 displays

the numbers of identified connections between Lean Enabler categories and pitfalls that are

associated with each framework theme. The pitfalls of the framework theme “Program

Execution” are addressed by the largest number of Lean Enabler categories. On the other

hand, the number of connections between the Lean Enabler categories and the pitfalls

associated with the framework theme “Technology Integration” is very small.

Page 120: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

7 Mapping of Lean Enablers to program management pitfalls 113

244

41

180

93

341

Scoping, Planning & Contracting

Technology Integration

Product DesignProgram Execution Enterprise Management

Figure 7-3: Number of identified pitfall-enabler connections per framework theme

To accompany the detailed analysis of the findings for the different framework themes, the

following figures provide the number of identified connections between Lean Enabler

categories and the pitfalls assigned to each of the framework parts of each framework

theme. Figure 7-4 shows the number of connections for the framework theme Program

Execution. The most connections are identified between the Lean Enabler categories and the

framework parts “Integrating and leading the program organization” and “Progress monitoring

and management.” The pitfalls of the framework part “Project management” seem to be only

weakly addressed: they have only four connections to Lean Enabler categories.

341

15

16

43

TotalStakeholder management

Risk management

44

Project management

4

Progress monitoring 

and management

82

Program manager 

characteristics

Multi‐project coordination

52

Integrating and leading the program organization

85

Developing intellectual capital

Figure 7-4: Number of identified pitfall-enabler connections for the framework parts of the

theme "Program Execution"

Page 121: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

7 Mapping of Lean Enablers to program management pitfalls 114

Figure 7-5 shows the number of connections for the pitfalls of the framework parts of the

theme “Enterprise Management.” Again, one framework part, “Building and transforming the

program enterprise,” has a very large number of connections while another framework part,

“Understanding the program enterprise,” is nearly unaddressed by Lean Enabler

subcategories.

933

55

17

Knowledge management

18

Building and transforming the program enterprise

Learning and improvement of the program enterprise

TotalUnderstanding the program enterprise

Figure 7-5: Number of identified pitfall-enabler connections for the framework parts of the

theme "Enterprise Management"

Figure 7-6 displays the results for the LAI program management framework theme “Scoping,

Planning, and Contracting.” Once more, one framework part, “Incentive alignment, contract

negotiation, and conclusion,” has many more connections than any other.

Page 122: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

7 Mapping of Lean Enablers to program management pitfalls 115

1806

38

Cost estimation & life cycle costing

Incentive alignment, contract 

negotiation & conclusion

Total

114

Managing trade‐offs

Definition of stakeholder needs and 

requirements

22

Figure 7-6: Number of identified pitfall-enabler connections for the framework parts of the

theme "Scoping, Planning and Contracting"

Figure 7 7 shows the results for the framework parts of the framework theme “Technology

integration.” The numbers of identified connections between Lean Enabler subcategories and

the pitfalls corresponding with each of the two framework parts differs by a factor of three.

However, one must consider that there might be different numbers of pitfalls in the different

framework parts . A detailed discussion of this factor will follow later in this section.

Page 123: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

7 Mapping of Lean Enablers to program management pitfalls 116

11

41

TotalTechnology transition 

management

30

Technology maturation monitoring

Figure 7-7: Number of identified pitfall-enabler connections for the framework parts of the

theme "Technology Integration"

Figure 7-8 displays the number of identified connections between the Lean Enabler

subcategories and the pitfalls of the framework parts of “Product Design.” Even though the

framework theme “Product Design” has the second-highest number of identified connections

(244), the distribution of these connections among the different framework parts is very even.

244

52

32

TotalValue stream optimization

42

Test & prototyping

40

Product design strategy

Product architecting

48

PD team organization

30

Integrated product and process 

development

Page 124: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

7 Mapping of Lean Enablers to program management pitfalls 117

Figure 7-8: Number of identified pitfall-enabler connections for the framework parts of the

theme "Product Design"

As mentioned earlier, the total number of identified connections might not be the perfect

metric to assess how well the Lean Enablers help in different framework parts, since the

number of pitfalls in these parts might differ enormously. Figure 7-9 shows, for each of the

five framework themes, the number of that theme’s identified connections as a percentage of

the total number of identified connections. On average, every fourth connection (25,9%) out

of the total number is judged to be beneficial to help avoiding pitfalls of some kind. The two

framework themes “Program Execution” and “Product Design” have the highest percentage

of identified connections. This might imply that the Lean Enablers are especially applicable to

these two themes. A possible reason for this is the fact that the Lean Enablers for program

management are primarily based on lean best practices from the literature describing the

execution of a program or product development. On the other hand, the framework theme

“Enterprise Management” seems to be not well addressed by the current set of Lean

Enablers for program management. Once more, the sources of the Lean Enablers might

explain why this is the case. The lean literature used does not focus on the forming of a

program enterprise and is more focused on its processes and handling during program

execution. Consequently, the current set of Lean Enablers might not perfectly fit the early

phases of a program.

25,9%

33,2%

23,4%25,7%

15,6%

27,1%

40%

30%

20%

10%

0%AverageProduct DesignTechnology 

IntegrationScoping, Planning & Contracting

Enterprise Management

Program Execution

Figure 7-9: Percentage of total number of identified connections that is applicable to each

framework theme

Other insights that might be gained from the results of the mapping pertain to the level of

usefulness of the various Lean Enabler categories. In particular, the number of identified

connections from each lean principle’s categories and the percentage that number

represents of the total number of Lean Enablers within that principle’s categories are

interesting subjects for further investigation. These findings are shown in Figure 7-10. For

Page 125: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

7 Mapping of Lean Enablers to program management pitfalls 118

each principle, the red bar displays the number of identified connections, while the blue line

shows the percentage of that principle’s Lean Enablers.

One can see that the highest number of connections derives from the third lean principle,

Creation of a Continuous Flow. This corresponds well with the literature’s assertion that the

third lean principle is essential to implementing the idea of lean thinking. However, the

percentage those connections make up of that principle’s total number of Lean Enablers is

not the highest. This might imply that the Lean Enablers of the third principle are important

overall, but the number of them might be reduced without a deleterious effect on outcomes.

The highest percentage of identified connections compared to the number of Lean Enablers

is found in the first lean principle, Specification of Customer Value. This might be explained

by the fact that a basic understanding of lean (especially value and waste) is found in the first

lean principle. Consequently, the first lean principle and the corresponding Lean Enablers

must be extensively utilized in order to implement the idea of lean thinking.

72

20

310

130

0

50

100

150

200

250

300

350 50,0%

40,0%

30,0%

20,0%

10,0%

0,0%6. Respect for People

5. Striving for Perfection

156

4. Pull of the Value

3. Creation of a Continuous 

Flow

2. Value Stream 

Definition

211

1. Specification of Customer 

Value

% of established of possible connections

Number of connections

Figure 7-10: Total number of identified connection per lean principle and % identified of

possible connections

7.3 Verification through review by the industry focus group

To verify the results of the mapping, a document containing a list similar to that in chapter

VII, Appendix A, was sent to the members of the industry focus group for review. The results

of their reviews were discussed in a telephone conference. All participants provided feedback

that further improved the list.

Page 126: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

7 Mapping of Lean Enablers to program management pitfalls 119

All feedback from the members of the industry focus group provided in writing or during the

telephone conference about the connections identified between the Lean Enabler

subcategories and the program management pitfalls was used to enhance the list presented

in this thesis.

In summary, it can be stated that all persons contributing final feedback about the list -

containing the results of the mapping process between the Lean Enabler subcategories and

the program management pitfalls - found the list to be comprehensive and the used method

comprehensible.

7.4 Summary

This chapter presented an analysis that connected the program management pitfalls and

Lean Enablers identified by this study. After describing the approach used to map the

enablers to the pitfalls, the chapter presented some major findings and results in a series of

figures. It raised some questions about the quality of the Lean Enablers and the mapping.

Some could be answered by the present study, while some call for further research and

analysis.

The results of this study make it possible to give persons involved in program management

better guidance about the lean best practices to use in order to avoid common pitfalls. When

a program manager knows that his/her program is especially susceptible to specific pitfalls,

he/she can foster the use of applicable Lean Enablers and thus improve program

performance.

The list of the Lean Enablers for program management together with the mapping explained

in this chapter can be used to implement lean thinking in program management. Hence,

chapters 6 and 7 combine to give a positive answer to the fourth and final research question

of this thesis, “Are there ways to adapt lean thinking in program management?”

Page 127: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

8 Conclusion and research outlook 120

8 Conclusion and research outlook

This final chapter summarizes the findings and contributions of this thesis. It also discusses

the follow-up research that is called for.

Four research questions have been raised and answered:

1. “What is program management and how can it be defined?”

2. “Is there a framework for engineering programs?”

3. “Are there common pitfalls in program management?”

4. “Are there ways to adapt lean thinking in program management?”

Figure 8-1 shows how the chapters of this thesis correspond with these questions.

Chapter 6

Chapter 5

Chapter 4

Chapter 3

Chapter 6

Research Question 4:Are there ways to adapt lean thinking to program management?

Research Question 3:Are there common pitfalls in program management?

Research Question 2:Is there a framework for engineering program management?

Research Question 1:What is program management and how can it be defined?

Figure 8-1: Research questions and corresponding chapters

This thesis began by screening the current literature on program management. In particular,

existing program management frameworks were analyzed in detail. One finding of this

screening was that there is no widely accepted definition of program management. Many

authors use the term but few of them formally define it. Another finding was that there is no

widely accepted or widely used framework for technical development programs. The only

framework addressing the necessary, established aspects of program management in a

technical environment was the LAI program management framework. The source for this

framework was an unpublished, internal white paper of the LAI; the framework was based on

literature research and had not been assessed. The author refined and assessed this

framework through interviews with experienced program managers in order to ensure its

practicability and the appropriateness of using it in the further analysis in this thesis.

Page 128: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

8 Conclusion and research outlook 121

The next step after identifying a framework for program management was identifying

common challenges in program management. The initial collection of so-called program

management pitfalls was based on a comprehensive literature review including more than

110 literature sources. To verify the results, additional interviews with program managers

were conducted. In addition, the insights of members of an industry focus group representing

seven companies and two organizations were used for further refinement and verification of

the compilation of pitfalls.

The final idea presented in this thesis was the adaptation of lean thinking to program

management. In the existing literature, the work that appeared most promising as an

ingredient in pursuing this idea was that of Oppenheim et al. (Oppenheim, Murman et al.

2011). The authors used the idea of lean best practices, so-called Lean Enablers, to

implement lean ideas in systems engineering. Since the results are widely accepted and

praised and are compatible with the work of INCOSE (the International Council on Systems

Engineering), using a similar approach for program management made sense.

The first collection of Lean Enablers for program management, based on various sources of

“lean thinking,” was assessed in interviews with members of the industry focus group. This

assessment was used in producing a revised, comprehensive list of 310 Lean Enablers for

program management; these Lean Enablers were organized in 35 categories. Again, after

revision, the list was verified based on feedback from the members of the industry focus

group.

To help program managers improve program performance by avoiding common pitfalls, the

Lean Enablers for program management were mapped to the identified pitfalls. This idea

originated in the hypothesis that the use of specific Lean Enablers might be beneficial in

circumventing pitfalls. The analysis of connections between the Lean Enablers and the

pitfalls provided great insights regarding the applicability of the Lean Enablers in different

parts of program management.

Figure 8-2 summarizes the contributions of this thesis in two categories. The provision of a

clear definition of program management, the evaluation of existing frameworks, and the

refinement and verification of the LAI program management framework will be used in the

final, published version of the LAI program management white paper. The collections of

program management pitfalls and Lean Enablers, together with the mapping, can be directly

applied or can be used as bases for further intensive research in the industry focus group.

Page 129: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

8 Conclusion and research outlook 122

Relevant to LAI program management whitepaper1. Provision of  a clear definition of program management (PM)2. Comparison and evaluation of existing PM frameworks3. Refinement and verification of the LAI PM framework

Relevant to further research in the industry focus group4. Identification of common PM pitfalls5. Identification of Lean Enablers for PM6. Mapping of Lean Enablers to PM pitfalls

Figure 8-2: Contributions of this thesis

Research in the following areas is called for to follow up on the work of this thesis:

- Due to the small number of interviews (five), one might argue that further verification

of the LAI program management framework is necessary. Since all of the

interviewees stated that no further major refinements are necessary, a survey

approach might be used for a final verification of the framework.

- The current list of 99 pitfalls consists of root causes as well as secondary effects. It

might be beneficial or even necessary for further research to distinguish these two

categories. A discussion with experts (e.g., the program managers interviewed to

verify the LAI program management framework and members of the industry focus

group) could lead to a connection diagram or fishbone diagram of the 99 pitfalls

identified in this thesis. A brief discussion during one of the interviews indicated that

some root causes might be identifiable as such with little effort and that it also might

not be difficult to accurately trace many secondary-effect pitfalls back to their root

causes.

- The literature basis used for the development of the Lean Enablers for program

management might be too small. There are several other sources that describe lean

thinking in different environments. The main focus of the sources used in this thesis

was product development, and it might be necessary to examine adaptations of lean

thinking in additional environments. Section 0 discusses briefly the fact that the early

phases of program management (development of the program organization and the

immediately following steps) seem not to be optimally covered by the current set of

Lean Enablers for program management.

- In addition to drawing upon more sources for the Lean Enablers, further verification of

the Lean Enablers might be necessary. The current list of them was only reviewed by

a small number of people (mostly the members of the industry focus group). Again, a

Page 130: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

8 Conclusion and research outlook 123

survey might be applicable. Oppenheim et al. (Oppenheim, Murman et al. 2011) used

the same approach to verify their collection of Lean Enablers for systems

engineering.

Page 131: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

IV Table of symbols and abbreviations iv

IV Table of symbols and abbreviations

ACAT Acquisition category

AoA Analysis of Alternatives

CDD Capability Development Document

CE Chief Engineer

CPD Capability Production Document

DAU Defense Acquisition University

DoD Department of Defense

DOTMLPF Doctrine, Organization, Training, Materiel,

Leadership and Education, Personnel, and

Facilities

GAO Government Accountability Office

IFG Industry Focus Group

INCOSE International Council on Systems Engineering

IPB Initial Production Baseline

IPT Integrated

JCIDS Joint Capabilities Integration and Development

System

LAI Lean Advancement Initiative

LIRP into low-rate initial production

MSP Managing Successful Programmes

OGC Office of Government Commerce

PD Product Development

PDR Preliminary Design Review

PM Program Management

PMBOK guide “A Guide to the Project Management Body of

Knowledge” by PMI

PMI Project Management Institute

PO Program Office

PPBE Planning, Programming, Budgeting, and

Execution

RDT&E Research, Development, Testing and Evaluation

Page 132: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

IV Table of symbols and abbreviations v

SFR System Functional Review

SRR System Requirements Review

USD(AT&L) Under Secretary of Defense for Acquisition,

Technology, and Logistics

Page 133: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

V Index of literature vi

V Index of literature

(AT&L), U. S. o. D. (2010). Better Buying Power: Guidance for Obtaining Greater Efficiency

and Productivity in Defense Spending. Memorandum. Washington D.C.

Aday, L. A. and L. J. Cornelius (2006). Designing and conducting health surveys: a

comprehensive guide, Jossey-Bass Inc Pub.

Ahern, D. (2009). OSD Study of Program Manager Training and Experience, Defense

Acquisition University Press.

America, U. S. o. (2009). Public Law 111–23: Weapon System Acquisition Reform Act

(WSARA).

Andersen, E. S. and S. A. Jessen (2003). "Project maturity in organisations." International

Journal of Project Management 21(6): 457-461.

Andrews, R., J. Cooper, et al. (2010). House Armed Services Committee Panel on Defense

Acquisition Reform Findings and Recommendations.

Archibald, R. D. (2003). Managing high-technology programs and projects: A complete,

practical, and proven approach to managing large-scale projects with

emphasis on those involving advanced technology. Hoboken, NJ, John Wiley

& Sons Inc; Wiley.

Baccarini, D. (1996). "The concept of project complexity-a review." International Journal of

Project Management 14(4): 201-204.

Bador, D. (2007). Improving the Commonality Implementation in the Cockpit of Commercial

Aircraft. Cambridge, MA, Master's thesis, LAI and MIT.

Beckert, M. T. (2000). Organizational Characteristics for Successful Product Line

Engineering. Cambridge, MA, Master's thesis, LAI and MIT.

Bernstein, J. I. (1998). Design Methods in the Aerospace Industry: Looking for Evidence of

Set-Based Practices. Cambridge, MA, Master's thesis, LAI and MIT.

Bernstein, J. I. (2000). Multidisciplinary Design Problem Solving on Product Development

Teams. Cambridge, MA, PhD thesis, LAI and MIT.

Bessant, J., S. Caffyn, et al. (1994). "Rediscovering continuous improvement." Technovation

14(1): 17-29.

Blackburn, C. D. (2009). Metrics for Enterprise Transformation. Cambridge, MA, Master's

thesis, MIT and LAI.

Page 134: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

V Index of literature vii

Boas, R. C. (2008). Commonality in Complex Product Families: Implications of Divergence

and Lifecycle Offsets. Cambridge, MA, PhD thesis, LAI and MIT.

Boehm, B., R. Valerdi, et al. (2008). "The ROI of Systems Engineering: Some Quantitative

Results for Software-Intensive Systems." Systems Engineering 11(3): 221-

234.

Bozdogan, K. (2005). Supplier networks transformation toolset. Cambridge, MA, Lean

Advancement Initiative, Massachusetts Institute of Technology.

Bozdogan, K., J. Deyst, et al. (1998). "Architectural innovation in product development

through early supplier integration." R&D Management 28(3): 163-173.

Bresman, P. H. M. (2004). Learning Strategies and Performance in Organizational Teams.

Cambridge, MA, PhD thesis, MIT and LAI.

Bresnahan, S. M. (2006). "Understanding and Managing Uncertainty in Lean Aerospace

Product Development." Master's Thesis Retrieved 01/14, 2010.

Brown, J. T. (2007). The Handbook of Program Management. New York, McGraw-Hill

Professional.

Browning, T. R. (1996). Systematic IPT Integration in Lean Development Programs.

Cambridge, MA, Master's thesis, LAI and MIT.

Browning, T. R., J. J. Deyst, et al. (2002). "Adding Value in Product Development by Creating

Information and Reducing Risk." IEEE Transactions on Engineering

Management 49(4): 443-458.

Cameron, B. G., E. F. Crawley, et al. (2008). "Value flowmapping: Using networks to inform

stakeholder analysis." Acta Astronautica 62(4-5).

Carreras, C. E. (2002). Opportunities for Lean Thinking in Aircraft Flight Testing and

Evaluation, Master Thesis, LAI and Massachusetts Institute of Technology.

CMU (2008). Acquisition Archetypes: Firefighting. C. M. U.-S. E. Institute.

Cohen, J. L. (2005). United States Air Force Air Logistics Centers: Lean Enterprise

Transformation and Associated Capabilities. Cambridge, MA, Master's thesis,

MIT and LAI.

Commerce, O. o. G. (2007). Managing successful programmes. London, TSO.

Commerce, O. o. G. (2009). Managing successful projects with PRINCE2. London, TSO.

Constantinescu, R. and I. M. Iacob (2007). "Capability Maturity Model Integration." Journal of

Applied Quantitative Methods 2(1): 187.

Page 135: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

V Index of literature viii

Cooper, R. G. (2001). Winning at New Products: Accelerating the Process from Idea to

Launch, Basic Books.

Cowap, S. A. (1998). Economic Incentives in Aerospace Weapon Systems Procurement,

Master Thesis, MIT and LAI.

Cunningham, T. W. (1998). Chains of Function Delivery: A Role for Product Architecture in

Concept Design. Cambridge, MA, PhD thesis, LAI and MIT.

Dare, R. E. (2003). Stakeholder Collaboration in Air Force Acquisition: Adaptive Design

Using System Representations. Cambridge, MA, PhD thesis, LAI and MIT.

DAU (2010). Public Access Course Material of the Defense Acquisition University.

https://myclass.dau.mil/webapps/portal/frameset.jsp?tab_id=_54_1, Defense

Acquisition University.

Davidz, H. L. (2006). Enabling Systems Thinking to Accelerate the Development Senior

Systems Engineers. Cambridge, MA, PhD Thesis, LAI and MIT.

Davies, A. and T. Brady (2000). "Organisational capabilities and learning in complex product

systems: towards repeatable solutions." Research Policy 29(7-8): 931-953.

Defense, D. o. (1998). "Integrated Product and Process Development Handbook." from

https://acc.dau.mil/adl/en-

US/37477/file/9017/DoD%20IPPD%20Handbook%20Aug%2098.pdf.

Defense, D. o. (2005). Manger's Guide to Technology Transition in an Evolutionary

Acquisition Environment. Fort Belvoir, Defense Acquisition University Press.

Defense, D. o. (2006). Risk Management Guide for DoD Acquisitions.

http://www.acq.osd.mil/se/docs/2006RMGuide4Aug06finalversion.pdf,

OUSD(AT&L) Systems and Software Engineering.

Defense, D. o. (2010). "Dictionary of Military and Associated Terms." from

http://www.dtic.mil/doctrine/new_pubs/jp1_02.pdf.

Deonandan, I., R. Valerdi, et al. (2010). Cost and Risk Considerations for Test and

Evaluation of Unmanned and Autonomous Systems of Systems.

Loughborough, UK, 5th IEEE International Conference on Systems of

Systems Engineering, June 2010.

Derleth, J. E. (2003). Multi-Attribute Tradespace Exploration and its Application to

Evolutionary Acquisition. Cambridge, MA, Master's thesis, LAI and MIT.

Dickerson, C. and R. Valerdi (2010). Using Relational Model Transformations to Reduce

Complexity in SoS Requirements Traceability: Preliminary Investigation.

Page 136: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

V Index of literature ix

Loughborough, UK, 5th IEEE International Conference on Systems of

Systems Engineering, June 2010.

DoD (2003). Department of Defense Directive 5000.01.

DoD (2008). Department of Defense Instruction 5000.02.

DoD (2008). Operation of the Defense Acquisition System, Department of Defense

Instruction (DoDI) 5000.02, Department of Defense.

Dorey, S. P. (2011). Enchancing Cost Realism Through Risk-Driven Contracting: Designing

incentive Fees Based on Probabilistic Cost Estimates, Master's Thesis, LAI

and Massachusetts Institute of Technology.

Downen, T. D. (2005). A Multi-Attribute Value Assessment Method for the Early Product

Development Phase With Application to the Business Airplane Industry.

Cambridge, MA, PhD Thesis, MIT and LAI.

E-Programme.com. (2011). "Homepage." from http://www.E-Programme.com.

Eisenhardt, K. (1989). "Building theories from case study research." Academy of

management review 14(4): 532-550.

Eisenhardt, K. (1991). "Better stories and better constructs: The case for rigor and

comparative logic." Academy of management review 16(3): 620-627.

Emiliani, M. L. (2004). "Improving business school courses by applying lean principles and

practices." Quality Assurance in Education 12(4): 175-187.

Ferdowsi, B. (2003). Product Development Strategies in Evolutionary Acquisition.

Cambridge, MA, Master's thesis, LAI and MIT.

Ferns, C. (1991). "Developments in programme management." International Journal of

Project Management 9(3): 148-156.

Forseth, C. E. (2002). The Pursuit of Acquisition Intrapreneurs. Cambridge, MA, Research

Report, LAI and MIT.

Fowler, F. (1995). Improving Survey Questions. Design and Evaluation. Thousand Oaks,

SAGE Publications.

Fowler, F. (2009). Survey Research Methods. Thousand Oaks, SAGE Publications.

Francis, P. (2009). Defense Acquisitions: Charting a Course for Lasting Reform:

Congressional Testimony. Washington D.C., DIANE Publishing.

Francis, P., M. Golden, et al. (2010). Defense acquisitions: Managing Risk to Achieve Better

Outcomes. Washington D.C.

Page 137: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

V Index of literature x

Fricke, S. E. and A. J. Shenhar (2000). "Managing multiple engineering projects in a

manufacturing support environment." IEEE Transactions on Engineering

Management 47(2): 258-268.

GAO (2006). Defense Acquisitions - Major Weapon Systems Continue to Experience Cost

and Schedule Problems under DOD’s Revised Policy (GAO-06-368).

Washington, United States Government Accountability Office, Report to

Congressional Committees.

GAO (2010). Defense Acquisitions - Managing Risk to Achieve Better Outcomes (GAO-10-

374T). Washington, D.C., United States Government Accountability Office.

Glazner, C. G. (2006). Enterprise Integration Strategies Across Virtual Extended Enterprise

Networks: A Case Study of the F-35 Joint Strike Fighter Program Enterprise.

Cambridge, MA, Master's thesis, LAI and MIT.

Gordon, M., C. Musso, et al. (2009). "The Path to Developing Successful New Products."

The Wall Street Journal, November 30, 2009.

Görög, M. (2011). "Translating single project management knowledge to project programs."

Project Management Journal 42(2): 17-31.

Graban, M. (2008). Lean hospitals: Improving quality, patient safety, and employee

satisfaction. Florence, KY, Productivity Press.

Haberfellner, R. and W. F. Daenzer (2002). Systems Engineering - Methodik und Praxis.

Zürich, Verlag Industrielle Organisation.

Hammer, M., C. J. Haney, et al. (2007). "The 7 Deadly Sins of Performance Measurement."

MIT Sloan Management Review 48(3): 80-.

Haughey, D. (2001). "A perspective on programme management." Project Smart Website.

Hauser, J. and G. Katz (1998). "Metrics: you are what you measure!" European Management

Journal 16(5): 517-528.

Hernandez, C. M. (1995). Challenges and Benefits to the Implementation of Integrated

Product Teams on Large Military Procurements. Cambridge, MA, Master's

thesis, LAI and MIT.

Herweg, G. M. and K. E. Pilon (2001). System Dynamics Modeling for the Exploration of

Manpower Project Staffing Decisions in the Context of a Multi-Project

Enterprise, Master Thesis, LAI and Massachusetts Institute of Technology.

Page 138: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

V Index of literature xi

Hess, J., G. Agarwal, et al. (2010). Normative and Descriptive Models for Test & Evaluation

of Unmanned and Autonomous Systems of Systems. Chicago, IL, 20th

INCOSE Symposium, July 2010.

Hess, J. T. and R. Valerdi (2010). Test and Evaluation of a SoS using a Prescriptive and

Adaptive Testing Framework. Loughborough, UK, , 5th IEEE International

Conference on Systems of Systems Engineering, June 2010.

Hoppmann, J. (2009). The Lean Innovation Roadmap - A Systematic Approach to

Introducing Lean in Product Development Processes and Establishing a

Learning Organization. Institute of Automotive Management and Industrial

Production. Braunschweig, Technische Universitaet Braunschweig.

Hoppmann, J. (2009). The Lean Innovation Roadmap: A Systematic Approach to Introducing

Lean in Product Development Processes and Establishing a Learning

Organization. Lean Advancement Initiative. Cambridge, Massachusetts

Institute of Technology (MIT).

Hut, P. M. (2008). "How Program Management Differs From Project Management." from

http://www.pmhut.com/how-program-management-differs-from-project-

management.

Imai, M. (1986). Kaizen: The key to Japan's competitive success. New York, McGraw-Hill.

INCOSE. (2011). "International Council on Systems Engineering (INCOSE) website."

Retrieved March 6, 2011.

Institute, P. M. (2004). A Guide to the Project Management Body of Knowledge: (PMBOK

guide) ; an American national standard, ANSIPMI 99-001-2004. Newton

Square, Pa.

Institute, P. M. (2006). The Standard for Program Management. Newton Square,

Pennsylvania, Project Management Institute.

Institute, P. M. (2008). The Standard for Program Management. Newton Square,

Pennsylvania, Project Management Institute.

Institute, P. M. (2011). "Project Management Institute website." Retrieved 20.02.2011, 2011,

from http://www.pmi.org/.

Ippolito, B. J. (2000). Identifying Lean Practices for Deriving Software Requirements.

Cambridge, MA, Master's thesis, LAI and MIT.

ISO (1994). ISO 8402:1994(E) - Quality management and quality assurance -- Vocabulary.

Geneva, International Organization for Standardization.

Page 139: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

V Index of literature xii

ISO (2005). ISO 9000:2005(E) - Quality management systems -- Fundamentals and

vocabulary. Geneva, International Organization for Standardization.

Ittner, C. and D. Larcker (1998). "Innovations in performance measurement: Trends and

research implications." Journal of management accounting research 10: 205-

238.

Jobo, R. S. (2003). Applying the Lessons of “Lean Now!” To Transform the US Aerospace

Enterprise - A study guide for government lean transformation. Cambridge,

MA, LAI Report.

Jones, C. M. (2006). Leading Rockwell Collins Lean transformation. San Antonio, TX, April 9,

2006 LAI Keynote Talk: http://mitworld.mit.edu/video/378/.

Kadish, R. T., G. Abbott, et al. (2006). "Defense acquisition performance assessment report."

from https://acc.dau.mil/adl/en-

US/18554/file/733/Defense%20Acquisition%20Performance%20Assessment

%20Report%202006.pdf.

Kato, J. (2005). Development of a Process for Continuous Creation of Lean Value in Product

Development Organizations, Master Thesis. LAI and Massachusetts Institute

of Technology.

Kenley, C. R. and T. R. Creque (1999). "Predicting Technology Operational Availability Using

Technical Maturity Assessment." Systems Engineering 2(4): 198-211.

Kerr, S. (1995). "An academy classic: On the folly of rewarding A, while hoping for B."

Academy of Management Executive 9(1): 7-14.

Kinscher, K. (2011). Interviews with Air Force program managers. Cambridge, MA, United

States, Lean Advancement Initiative.

Kirtley, A. L. (2002). Fostering Innovation across Aerospace Supplier Networks, Master

Thesis, LAI and Massachusetts Institute of Technology.

Klein, J., J. Cutcher-Gershenfeld, et al. (1997). Implementation Workshop: High Performance

Work Organizations. Cambridge, MA, LAI Report RP97-02-34.

Kotter, J. P. (1990). A force for change: How leadership differs from management, Free Pr.

Krafcik, J. F. (1988). "Triumph of the lean production system." Sloan Management Review

30(1): 41-52.

LAI (2001). Lean Enterprise Self-Assessment Tool (LESAT) Version 1.0.

LAI (2011). Seminar "Lean in Program Management: Establishment of a Community of

Practice". Seal Beach, CA, Lean Advancement Initiative.

Page 140: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

V Index of literature xiii

Lamb, C. M. T. (2009). Collaborative Systems Thinking: An exploration of the mechanisms

enabling team systems thinking. Cambridge, MA, PhD thesis, LAI and MIT.

Laraia, A. C., P. E. Moody, et al. (1999). The Kaizen Blitz: accelerating breakthroughs in

productivity and performance. New York, Wiley.

LEI (2007). Reflections on Lean. Boston, Lean Enterprise Institute.

Levine, L. and B. Novak (2008). Identifying Acquisition Patterns of Failure Using Systems

Archetypes. Systems Conference, 2008 2nd Annual IEEE, Montreal, QC,

Canada IEEE.

Likert, R. (1932). "A technique for the measurement of attitudes." Archives of Psychology

140: 1-55.

Loureiro, G., E. Crawley, et al. (2006). "From Value to Architecture - Ranking the Objectives

of Space Exploration (IAC-06-D1.4.2)." Proceedings of the International

Astronautical Congress (IAC 2006), Valencia, Spain, 2 - 6 October 2006.

Lucas, M. V. (1996). Supplier Management Practices of the Joint Direct Attack Munition

Program. Cambridge, MA, Master's thesis, LAI and MIT.

Lycett, M., A. Rassau, et al. (2004). "Programme management: a critical review."

International Journal of Project Management 22(4): 289-299.

Maass, E. and P. D. McNair (2009). Applying Design for Six Sigma to Software and

Hardware Systems, Prentice Hall Press Upper Saddle River, NJ, USA.

Madachy, R. and R. Valerdi (2010). "Automating Systems Engineering Risk Assessment."

Proceedings of the 8th Conference on Systems Engineering Research,

Hoboken, NJ, March 17-19 2010.

Mahé, V. R. (2008). A Survey of Front End Modularity as an Automotive Architecture and its

Ability to Deliver Value. Cambridge, MA, Master's thesis, MIT.

Management, A. f. P. (2006). Body of Knowlegde. High Wycombe, UK, APM.

Mandelbaum, J., W. S. Kaplan, et al. (2001). Incentive Strategies for Defense Acquisitions.

Washington, D.C., Department of Defense.

Mao, P., H. Cheng, et al. (2008). Innovation of Large-Scale Project Multi-Programme

Construction Management Mode, IEEE.

Maylor, H., T. Brady, et al. (2006). "From projectification to programmification." International

Journal of Project Management 24(8): 663-674.

McGarry, J. and D. Card (2002). Practical software measurement: objective information for

decision makers. Boston, Addison-Wesley Professional.

Page 141: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

V Index of literature xiv

McKenna, N. (2006). The Micro-foundations of Alignment among Sponsors and Contractors

on Large Engineering Projects. Cambridge, MA, Master's thesis, MIT and LAI.

McKnew, G. (2010). An Examination of the Patterns of Failure in Defense Acquisition

Programs, Master Thesis. LAI and Massachusetts Institute of Technology.

McManus, H. (2005). Product Development Value Stream Mapping (PDVSM) Manual.

Cambridge, MA, Lean Advancement Initiative (LAI) at MIT.

McManus, H., A. Haggerty, et al. (2007). "Lean engineering: a framework for doing the right

thing right." Aeronautical Journal 111(1116): 105-114.

McNutt, R. T. (1998). Reducing DoD Product Development Time: The Role of the Schedule

Development Process, PhD Thesis, LAI and Massachusetts Institute of

Technology.

McVey, M. E. (2002). Valuation Techniques for Complex Space Systems: An Analysis of a

Potential Satellite Servicing Market Cambridge, MA, Master's thesis, LAI and

MIT.

Michaels, D. Airbus Woes Darken Jet Delivery. Wall Street Journal.

Morgan, J. M. and J. K. Liker (2006). The Toyota Product Development System. New York,

Productivity Press.

Morgan, J. M. and J. K. Liker (2006). The Toyota product development system: integrating

people, process, and technology. New York, Productivity Press.

Morgan, S. (1999). The Cost and Cycle Time Implications of Selected Contractor and Air

Force System Program Office Management Policies during the Development

Phase of Major Aircraft Acquisition Programs, Master Thesis, LAI and

Massachusetts Institute of Technology.

Neuman, W. (2006). Social Research Methods. Qualitative and Quantitative Approaches.

Boston, Pearson.

Nightingale, D., A. Stanke, et al. (2008). Enterprise Strategic Analysis and Transformation

(ESAT) - Version 2.0. Cambridge, MA, LAI Guide.

Nightingale, D. J. and J. H. Mize (2001). "Development of a Lean Enterprise Transformation

Maturity Model." Information, Knowledge, Systems Management 3(1): 15-30.

Nuffort, M. R. (2001). Managing Subsystem Commonality. Cambridge, MA, Master's thesis,

LAI and MIT.

Page 142: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

V Index of literature xv

Oehmen, J. (2005). Approaches to Crisis Prevention in Lean Product Development by High

Performance Teams and through Risk Management. Munich and Cambridge,

Technical University of Munich and LAI. Master's Thesis: 161p.

Oehmen, J. and M. Ben-Daya (2010). A Reference Model for Risk Management in Product

Development Programs. Research Paper of the MIT-KFUPM Center of Clean

Water and Energy, Cambridge and Dhahran, MIT and KFUPM.

Oehmen, J. and E. Rebentisch (2010). Risk Management in Lean PD. LAI Paper Series

"Lean Product Development for Practitioners", Cambridge, MA, LAI and MIT.

Oehmen, J. and E. Rebentisch (2010). Waste in Lean Product Development. LAI Paper

Series "Lean Product Development for Practitioners", Cambridge, MA, LAI and

MIT.

Oehmen, J. and W. Seering (2011). Risk-Driven Design Processes – Balancing Efficiency

with Resilience in Product Design. The Future of Design Methodology. H.

Birkhofer. London, Springer.

Office, G. A. (2010). Defense Acquisition: Assessments of Selected Weapon Programs.

GAO-10-388SP. Washington D.C.

OGC (2009). Managing Successful Projects with PRINCE2. London, Office of Government

Commerce, The Stationary Office.

Oppenheim, B. W. (2004). "Lean product development flow." SYSTEMS ENGINEERING-

NEW YORK- 7(4): 352-378.

Oppenheim, B. W., E. M. Murman, et al. (2011). "Lean enablers for systems engineering."

Journal of Systems Engineering 14(1): 29-55.

Paduano, R. (2001). Employing Activity Based Costing and Management Practices Within

the Aerospace Industry: Sustaining the Drive for Lean. Cambridge, MA,

Master's thesis, MIT and LAI.

Patanakul, P. and D. Milosevic (2008). "A competency model for effectiveness in managing

multiple projects." The Journal of High Technology Management Research

18(2): 118-131.

Patanakul, P. and D. Milosevic (2009). "The effectiveness in managing a group of multiple

projects: Factors of influence and measurement criteria." International Journal

of Project Management 27(3): 216-233.

Pessôa, M. V. P. (2008). Weaving the waste net: a model to the product development

system low performance drivers and its causes. Cambridge, MA, LAI White

Paper 08-01.

Page 143: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

V Index of literature xvi

Platje, H. (1993). "Breakthrough in multiproject management: how to escape the vicious

circle of planning and control* 1." International Journal of Project Management

11(4): 209-213.

PMI (2004). A Guide to the Project Management Body of Knowledge (PMBOK Guide).

Newton Square (PA), Project Management Institute.

PMI (2008). A guide to the project management body of knowledge (PMBOK guide). Drexel

Hill, PA, Project Management Institute.

Pomponi, R. A. (1998). Organizational structures for technology transition : rethinking

information flow in the integrated product team. Cambridge, MA, PhD thesis,

LAI and MIT.

Rebentisch, E. (1996). Preliminary Observations on Program Instability. Cambridge, MA, LAI

Whitepaper LEAN 96-03.

Rhodes, D. H., R. Valerdi, et al. (2009). "Systems Engineering Leading Indicators for

Assessing Program and Technical Effectiveness." Systems Engineering 12(1):

21-35.

Roberts, C. J. (2003). Architecting Evolutionary Strategies Using Spiral Development for

Space Based Radar. Cambridge, MA, Master's thesis, LAI and MIT.

Roedler, G., D. H. Rhodes, et al. (2010). Systems Engineering Leading Indicators Guide

(Version 2.0), INCOSE-TP-2005-001-03.

Ross, A. M. (2003). Multi-Attribute Tradespace Exploration with Concurrent Design as a

Value-Centric Framework for Space System Architecture and Design.

Cambridge, MA, Master's thesis, LAI and MIT.

Roth, G. (2008). The Order and Chaos of the Learning Organization. Handbook of

Organization Development. T. Cummings. Newbury, CA, Sage.

Sapsed, J. and A. Salter (2004). "Postcards from the edge: local communities, global

programs and boundary objects." Studies 25(9): 1515-1534.

Schmenner, R. and T. Vollmann (1994). "Performance Measures: Gaps, False Alarms, and

the “Usual Suspects”." International Journal of Operations & Production

Management 14(12): 58-69.

Schuh, G., H. Adickes, et al. (2008). Lean Innovation - Auf dem Weg zur Systematik. AWK

Aachener Werkzeugmaschinen-Kolloquium: Wettbewerbsfaktor

Produktionstechnik - Aachener Perspektiven, Aachen, Apprimus Verlag.

Page 144: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

V Index of literature xvii

Schuh, G., M. Lenders, et al. (2008). Lean innovation: introducing value systems to product

development: Management of Engineering & Technology, 2008. PICMET

2008. Portland International Conference on, IEEE.

Schuh, G., M. Lenders, et al. (2010). Lean Innovation – Introducing takt time to product

development processes. Proceedings of APMS2010 - International

Conference on Advances in Production Management Systems. Mailand,

Poliscript - Politecnico di Milano.

Shroyer, E. (2002). Lean Transition of Emerging Industrial Capability (LeanTEC), Final

Report, Cooperative Agreement F33615-97-2-5153, U.S. Air Force and

Boeing Company.

Siegel, L. R. (2004). Measuring and Managing Intellectual Capital in the U.S. Aerospace

Industry. Cambridge, MA, Master Thesis, LAI and MIT.

Silva, L. M. (2001). A Partitioning Methodology for Helicopter Avionics System with a focus

on Life Cycle Cost. Cambridge, MA, Master's thesis, LAI and MIT.

Sobek, K. Durward, et al. (1998). "Another look at how Toyota integrates product

development." Harvard Business Review 76(4): 36-47.

Sobek, D. K., A. C. Ward, et al. (1999). "Toyota's principles of set-based concurrent

engineering." Sloan Management Review 40(2): 67-84.

Spaulding, T. J. (2003). Tools for Evolutionary Acquisition: A Study of Multi-Attribute

Tradespace Exploration (MATE) Applied to the Space Based Radar.

Cambridge, MA, Master's thesis, LAI and MIT.

Stagney, D. B. (2003). The Integrated Concurrent Enterprise. Cambridge, MA, Master's

thesis, LAI and MIT.

Stanke, A., D. Nightingale, et al. (2008). Enterprise Strategic Analysis and Transformation

(ESAT) - Facilitator’s Guide - Version 2.0. Cambridge, MA, LAI Guide.

Stanke, A. K. (2006). Creating High Performance Enterprises, PhD Thesis, LAI and

Massachusetts Institute of Technology.

Stanke, A. K. (2006). Creating high performance enterprises. Lean Advancement Initiative

(LAI). Cambridge, Massachusetts Institute of Technology (MIT).

Sugimori, Y., K. Kusunoki, et al. (1977). "Toyota production system and kanban system

materialization of just-in-time and respect-for-human system." International

Journal of Production Research 15(6): 553-564.

Page 145: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

V Index of literature xviii

Susman, G. and I. Petrick (1995). Product Development Team Effectiveness. Cambridge,

MA, LAI Whitepaper 95-06.

Tang, C. S. and J. D. Zimmerman (2009). "Managing New Product Development and Supply

Chain Risks: The Boeing 787 Case." Supply Chain Forum: An International

Journal 10(2): 74-85.

Tang, V. (2006). Corporate Decision Analysis: An Engineering Approach. Cambridge, MA,

PhD thesis, LAI and MIT.

Tang, V. and K. N. Otto (2009). "Multifunctional Enterprise Readiness: Beyond the Policy of

Build-Test-Fix Cyclic Rework." Proceedings of the ASME 2009 International

Design Engineering Technical Conferences & Design Theory and Design

IDETC/DTM 2009 , August 30 - September 2, 2009, San Diego, California: 1-

9.

Tondreault, J. P. (2003). Improving the Management of System Development to Produce

More Affordable Military Avionics Systems. Cambridge, MA, Master's thesis,

LAI and MIT.

University, D. A. (2009). Introduction to Defense Acquistion Management. Fort Belvoir,

Defense Acquisition University Press.

University, D. A. (2011). Defense Acquisition Guidebook. Fort Belvoir, Defense Acquisition

University Press: online accessible at https://dag.dau.mil.

Valerdi, R. (2005). The Constructive Systems Engineering Cost Model (COSYSMO). Los

Angeles, CA, PhD Thesis, USC.

Valerdi, R. (2010). "Heuristics for Systems Engineering Cost Estimation." IEEE Systems

Journal.

Valerdi, R., J. E. Rieff, et al. (2007). Lessons Learned From Industrial Validation of

COSYSMO. San Diego, CA, 17th INCOSE Symposium, June 2007.

Vereecke, A., E. Pandelaere, et al. (2003). "A classification of development programmes and

its consequences for programme management." International Journal of

Operations & Production Management 23(10): 1279-1290.

Wagner, C. (2007). Specification Risk Analysis: Avoiding Product Performance Deviations

through an FMEA-based Method. Munich and Cambridge, Technical

University of Munich and LAI. Master's Thesis: 149p.

Walton, M. A. (1999). Identifying the Impact of Modeling and Simulation in the Generation of

System Level Requirements. Cambridge, MA, Master's thesis, LAI and MIT.

Page 146: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

V Index of literature xix

Ward, A. C. (2007). Lean product and process development. Cambridge, United States,

Lean Enterprises Institute Inc.

Weigel, A. L. (2000). Spacecraft System-Level Integration and Test Discrepancies:

Characterizing Distribution and Costs. Cambridge, MA, Master's thesis, MIT

and LAI.

Wheelwright, S. C. and K. B. Clark (1992). Revolutionizing product development: Quantum

leaps in speed, efficiency, and quality. New York , Toronto , New York, Free

Press; Maxwell Macmillan Canada; Maxwell Macmillan International.

Whitaker, R. B. (2005). Value Stream Mapping and Earned Value Management: Two

Perspectives on Value in Product Development. Cambridge, MA, Master's

thesis, MIT and LAI.

Williams, D. and T. Parr (2006). Enterprise programme management: Delivering value.

Basingstoke, Palgrave MacMillan.

Williams, T. M. (1999). "The need for new paradigms for complex projects." International

Journal of Project Management 17(5): 269-273.

Wirthlin, J. R. (2000). Best Practices in User Needs / Requirements Generation. Cambridge,

MA, Masters thesis, LAI and MIT.

Wirthlin, J. R. (2009). Identifying enterprise leverage points in Defense Acquisition Program

performance. Engineering Systems Division. Cambridge, Massachusetts

Institute of Technology (MIT).

Wirthlin, J. R., W. Seering, et al. (2008). "Understanding Enterprise Risk Across an

Acquisition Portfolio: A Grounded Theory Approach." Seventh National

Symposium on Space Systems Engineering & Risk Management, Los

Angeles, CA, February 26-29, 2008.

Womack, J. and D. Jones (1996). Lean Thinking - Banish Waste and Create Wealth in Your

Corporation. New York, Simon Schuster.

Womack, J. P. and D. T. Jones (1996). Lean thinking: Banish waste and create wealth in

your corporation. New York, Simon & Schuster.

Womack, J. P. and D. T. Jones (2003). Lean thinking: banish waste and create wealth in

your corporation thinking: Banish waste and create wealth in your corporation.

New York, Simon and Schuster; Free Press.

Womack, J. P., D. T. Jones, et al. (1990). The machine that changed the world: Based on the

Massachusetts Institute of Technology 5-million-dollar 5-year study on the

Page 147: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

V Index of literature xx

future of the automobile. M. I. o. Technology. New York, Rawson: VIII, 323 S.

/// 323.

Yin, R. (2009). Case study research: Design and methods, Sage Publications, Inc.

Yin, R. K. (2003). Case study research - Design and methods. Thousand Oaks, Sage

Publications.

Page 148: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

VI Table of figures and spreadsheets xxi

VI Table of figures and spreadsheets

Figure 1-1: Total Department of Defense acquisition portfolio: actual cost compared to initial

estimate (GAO 2006; GAO 2010) ..................................................................................... 2 

Figure 1-2: Thesis organization ................................................................................................ 4 

Figure 1-3: Research question and corresponding sections in chapter 2 ................................ 5 

Figure 2-1: Correlation of the research questions and sections ............................................... 6 

Figure 2-2: DoD Decision Support Systems (University 2011) ................................................ 7 

Figure 2-3: Life cycle for defense acquisitions (University 2011) ............................................. 9 

Figure 2-4: The “Managing Successful Programmes” framework of the Office of Government

Commerce (Commerce 2007) ........................................................................................ 12 

Figure 2-5: Portfolio, programs and projects: high-level view (Institute 2008) ....................... 14 

Figure 2-6: Interaction between project management and program management (Institute

2008) .............................................................................................................................. 15 

Figure 2-7: Program life cycle and program benefits management (Institute 2008) .............. 17 

Figure 2-8: Program structure and stakeholders .................................................................... 18 

Figure 2-9: Lean Advancement Initiative (LAI) program management framework ................. 19 

Figure 2-10: Correlation of program life cycle phases and the stages of a Stage-Gate

process ........................................................................................................................... 24 

Figure 2-11: Usage of different research approaches in the thesis ........................................ 31 

Figure 2-12: Research questions and corresponding sections .............................................. 35 

Figure 4-1: The Lean Advancement Initiative (LAI) program management framework .......... 47 

Figure 4-2: Interview results for Program Execution and Enterprise Management ................ 49 

Figure 4-3: Interview results for Scoping, Planning & Contracting ......................................... 50 

Figure 4-4: Interview results for Technology Integration ........................................................ 50 

Figure 4-5: Interview results for Product Design .................................................................... 51 

Figure 4-6: Average rating of all framework parts combined (including standard deviation) .. 52 

Page 149: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

VI Table of figures and spreadsheets xxii

Figure 4-7: Difficulty and importance rating of the most relevant elements of the LAI program

management framework ................................................................................................. 53 

Figure 4-8: Legend for Figure 4-2 .......................................................................................... 53 

Figure 4-9: Rating of the importance of framework themes by members of the industry focus

group .............................................................................................................................. 55 

Figure 5-1: Distribution of the number of sources for all pitfalls ............................................. 67 

Figure 5-2: Distribution of number of pitfalls per framework part ........................................... 71 

Figure 5-3: Number of pitfalls for the major areas within the LAI program management

framework ....................................................................................................................... 72 

Figure 6-1: Percentage of the compiled Lean Enablers for program management that were

derived from each literature source .............................................................................. 100 

Figure 6-2: Total number of Lean Enablers and categories ................................................. 101 

Figure 6-3: Distribution of the Lean Enablers and the subcategories among the six lean

principles ...................................................................................................................... 101 

Figure 7-1: Screenshot from the mapping (in Microsoft Excel) ............................................ 104 

Figure 7-2: Number of identified connections with a Lean Enabler per program management

pitfall ............................................................................................................................. 105 

Figure 7-3: Number of identified pitfall-enabler connections per framework theme ............. 106 

Figure 7-4: Number of identified pitfall-enabler connections for the framework parts of the

theme "Program Execution" ......................................................................................... 106 

Figure 7-5: Number of identified pitfall-enabler connections for the framework parts of the

theme "Enterprise Management" .................................................................................. 107 

Figure 7-6: Number of identified pitfall-enabler connections for the framework parts of the

theme "Scoping, Planning and Contracting" ................................................................. 108 

Figure 7-7: Number of identified pitfall-enabler connections for the framework parts of the

theme "Technology Integration" ................................................................................... 109 

Figure 7-8: Number of identified pitfall-enabler connections for the framework parts of the

theme "Product Design" ............................................................................................... 110 

Figure 7-9: Percentage of total number of identified connections that is applicable to each

framework theme .......................................................................................................... 110 

Page 150: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

VI Table of figures and spreadsheets xxiii

Figure 7-10: Total number of identified connection per lean principle and % identified of

possible connections .................................................................................................... 111 

Figure 8-1: Research questions and corresponding chapters .............................................. 113 

Figure 8-2: Contributions of this thesis ................................................................................. 115 

Table 2-1: Different Categories of defense acquisitions (University 2009) .............................. 8 

Table 2-2: Literature sources for framework evaluation ......................................................... 21 

Table 2-3: Comparison of frameworks in terms of cross-cutting program management

activities .......................................................................................................................... 22 

Table 2-4: Comparison of frameworks in terms of pre-program and program establishment

activities .......................................................................................................................... 25 

Table 2-5: Comparison of frameworks in terms of technology development activities ........... 26 

Table 2-6: Comparison of frameworks in terms of product design activities .......................... 26 

Table 2-7: Comparison of frameworks in terms of production, deployment, and disposal ..... 27 

Table 2-8: Comparison of frameworks in the phases of an engineering program lifecycle .... 28 

Table 2-9: Overall comparison of the different frameworks .................................................... 28 

Table 2-10: List of companies participating in the industry focus group ................................. 34 

Table 2-11: List of organizations participating in the industry focus group ............................. 34 

Table 3-1: Broadly used definitions of “project” and if available “project management” ......... 37 

Table 3-2: Definitions of “program” and “program management” ........................................... 38 

Table 3-3: Comparison of definitions of “program management” ........................................... 41 

Table 4-1: Overall comparison of existing program management frameworks (see section

2.1.5) .............................................................................................................................. 45 

Table 5-1: Compilation of program management pitfalls and corresponding sources ........... 58 

Table 5-2: Mapping of pitfalls to the Program Execution parts of the LAI program

management framework ................................................................................................. 69 

Table 5-3: Mapping of pitfalls to the Enterprise Management parts of the LAI program

management framework ................................................................................................. 69 

Page 151: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

VI Table of figures and spreadsheets xxiv

Table 5-4: Mapping of program management pitfalls to the Scoping, Planning & Contracting

framework parts of the LAI program management framework ....................................... 70 

Table 5-5: Mapping of pitfalls to the Technology Integration parts of the LAI program

management framework ................................................................................................. 70 

Table 5-6: Mapping of pitfalls to the Product Design parts of the LAI program management

framework ....................................................................................................................... 70 

Table 6-1: Lean Enablers for program management ............................................................. 80 

Page 152: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

VII Appendix A xxv

VII Appendix A

Figure VII-1: Common pitfalls in program management and corresponding Lean Enablers

ID Pitfall Corresponding Lean Enablers

1 Unstable funding (undermining program

stability) 2.5.; 3.13.

2

Long waiting time for external

stakeholders (e.g., Acquisition Panel)

activities

1.5.; 2.7.

3 “Firefighting”

2.3.; 2.4.; 2.5.; 2.6.; 2.7.; 3.1.; 3.2.;

3.3.; 3.4.; 3.5; 3.6.; 3.7.; 3.8.; 3.10.;

3.11.; 3.12.; 3.13.; 5.1.; 5.3.; 5.4.;

5.5.; 5,6; 6.4.

4 Lack of leadership commitment to cycle

time reduction

1.2.; 1.4; 2.1; 2.7.; 3.1.; 3.12.; 4.1.;

4.2.; 5.1.; 5.2.; 5.4.; 6.2.

5 No incentives for cycle time reduction 1.1.; 1.4; 1.5.; 2.6.; 3.4.; 5.6; 6.1.;

6.2.; 6.3.; 6.4.

6 Overriding influence of funding-related

constraints 1.4; 2.2.; 2.5.; 5.4.

7 Wrong allocation of responsibilities and

decision-making rights

1.2.; 1.5.; 2.1; 2.5.; 3.1.; 3.3.; 3.4.;

3.6.; 3.7.; 3.9.; 4.1.; 5.4.

8 Lack of coordination of communication 1.2.; 1.5.; 2.1; 2.2.; 2.5.; 3.1.; 3.4.;

3.7.; 3.8.; 3.9.; 3.10.; 5.3.; 5.4.

9 Lack of process standardization 1.3.; 2.2.; 2.4.; 2.5.; 3.2.; 3.11.; 5.5.

10 Poor communication with stakeholders

1.1.; 1.2.; 1.3.; 1.4; 1.5.; 2.1; 2.5.;

2.7.; 3.3.; 3.4.; 3.7.; 3.10.; 3.11.;

5.3.; 5.4.

11 No realistic program schedule 1.1.; 2.5.; 2.7.; 3.5; 3.6.; 3.7.; 3.10.

12 Lack of metrics 2.2.; 2.5.; 2.7.; 3.7.; 3.10.; 3.13.;

4.2.; 5.3.; 5.5.

12.1 No metrics to reflect cross-

functional processes

2.2.; 2.5.; 2.7.; 3.7.; 3.9.; 3.10.;

3.13.; 4.2.; 5.3.; 5.5.

12.2

No process implemented to

measure project performance or

project progress (e.g. EVM)

1.1.; 1.2.; 1.3.; 1.4; 1.5.; 2.1; 2.2.;

2.5.; 2.7.; 3.3.; 3.4.; 3.7.; 3.10.;

3.13.; 4.2.

Page 153: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

VII Appendix A xxvi

13

Wrong metrics: Not using the right

measure (ignoring something important)

or choosing metrics that are wrong

2.2.; 2.5.; 2.7.; 3.7.; 3.10.; 3.13.;

4.2.; 5.3.; 5.5.

13.1

Implementing metrics that focus

on short-term results, or that do

not give thoughts to

consequences on human

behavior and enterprise

performance

2.2.; 2.5.; 2.7.; 3.7.; 3.10.; 3.13.;

4.2.; 5.3.; 5.5.

13.2

Metrics that are not actionable or

are hard for a team/group to

impact, or collecting too much

data

2.2.; 2.5.; 2.7.; 3.7.; 3.10.; 3.13.;

4.2.; 5.3.; 5.4.; 5.5.; 6.4.

14 No activity-based costing and

management

1.1.; 1.2.; 1.4; 1.5.; 2.1; 2.2.; 2.5.;

2.7.; 3.4.; 3.7.; 3.10.; 3.13.

15 No defined risk management process 1.3.; 1.5.; 2.4.; 2.7.; 3.4.; 3.5; 3.10.;

3.11.; 5.4.

16 Lacking ability to understand

uncertainty/risk

1.1.; 1.2.; 1.3.; 1.4; 1.5.; 2.1; 2.2.;

2.3.; 2.4.; 2.5.; 2.6.; 2.7.; 3.1.; 3.3.;

3.11.; 5.5.; 6.2.; 6.3.

17 Lacking the staff/capacity to deal with

uncertainty/risk

2.5.; 3.3.; 3.13.; 5.6; 6.1.; 6.2.; 6.3.;

6.4.

18 Not all staff is involved into risk

management

1.3.; 2.4.; 2.5.; 3.3.; 3.11.; 5.4.; 6.2.;

6.3.; 6.4.

19 Insufficient management of sub-projects 2.1; 2.2.; 2.7.; 5.4.

20 Competing resource requirements (e.g.

allocation and choice of resources)

1.5.; 2.1; 2.2.; 2.5.; 3.4.; 3.9.; 3.13.;

5.4.

21 Too much overtime 2.6.; 2.7.; 3.1.; 3.2.; 3.3.; 3.10.;

3.13.; 6.1.; 6.2.; 6.4.

22 Overly unstable project priorities 1.1.; 1.2.; 1.3.; 1.4; 1.5.; 2.1; 2.2.;

2.5.; 2.7.; 3.3.; 3.4.; 3.5

23 Too much outsourcing 1.4; 1.5.; 2.6.; 3.2.; 3.4.

24 Unrealistic plan or no plan for ramp-up

and ramp-down regarding staffing

2.1; 2.2.; 2.3.; 2.5.; 2.7.; 3.1.; 3.8.;

3.13.

25 Troubled projects are not canceled early 2.5.; 2.7.; 3.3.; 3.10.

26 No buffer scheduled between projects 2.5.; 2.6.; 2.7.; 3.6.; 5.1.

Page 154: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

VII Appendix A xxvii

27 Inadequate identification of individual

skill development

5.1.; 5.2.; 5.3.; 5.5.; 5.6; 6.1.; 6.2.;

6.3.; 6.4.

28 Unsupportive environment for

experiential and general learning

5.1.; 5.2.; 5.3.; 5.5.; 5.6; 6.1.; 6.2.;

6.3.; 6.4.

29

No or insufficient assessment of

intellectual capital base regarding

program needs

2.7.; 5.1.; 5.3.; 5.5.; 6.3.; 6.4.

30 No specialist career path 5.1.; 5.2.; 5.3.; 5.5.; 6.1.; 6.2.; 6.3.;

6.4.

31 Inadequate team experience 1.5.; 3.4.; 5.1.; 5.2.; 5.3.; 5.5.; 5.6;

6.1.; 6.2.; 6.3.; 6.4.

32 Insufficient program manager

qualifications

1.2.; 2.1; 2.5.; 3.1.; 3.9.; 4.1.; 5.1.;

5.2.; 5.3.; 5.4.; 5.5.; 5.6; 6.1.; 6.2.;

6.3.; 6.4.

33

Lack of enterprise-wide coordination of

optimization: only local processes and

organizational optimization

1.5.; 2.2.; 2.5.; 2.7.; 3.4.; 3.7.; 3.12.;

5.1.; 5.2.; 5.3.; 5.5.; 5.6; 6.1.; 6.2.;

6.3.

34 Lack of performance incentives for staff 2.7.; 3.7.; 3.10.; 5.2.; 5.6; 6.1.; 6.2.;

6.3.

35 Wrong performance incentives for staff

36 No utilization of a social network 3.10.; 5.3.; 5.5.

37 Too little customer and stakeholder

interaction

1.1.; 1.2.; 1.3.; 1.4; 1.5.; 2.7.; 3.3.;

3.4.; 3.7.; 3.10.; 5.4.

38 Too little integration of suppliers 1.5.; 2.7.; 3.4.; 3.7.; 3.10.; 5.4.

39 No fostering and maintaining of personal

accountability for plans and outcomes 1.4; 2.7.; 3.7.; 3.10.

40 Understaffing 2.5.; 2.7.; 3.10.; 3.13.

41 Insufficient resource planning (no

identification of possible understaffing) 2.5.; 2.7.; 3.10.; 3.13.

42

Insufficient use of benchmarking and

assessment tools for evaluation of

enterprise structure

2.7.; 3.7.; 3.10.

43 No enterprise-wide integrated

continuous improvement process 5.1.; 5.2.; 5.3.; 5.5.

44 Insufficient use of benchmarking and

assessment tools to identify 2.7.; 3.7.; 3.10.

Page 155: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

VII Appendix A xxviii

improvement potentials

45 No enterprise-wide organizational

learning and change management plan

5.1.; 5.2.; 5.3.; 5.4.; 5.5.; 5.6; 6.1.;

6.2.; 6.3.; 6.4.

46 No open information sharing 2.7.; 3.7.; 3.10.; 5.3.

47 No documentation of lessons learned 5.1.; 5.2.; 5.3.; 5.5.; 6.3.

48 Insufficient or non-standardized usage of

information technology 2.7.; 3.7.; 3.9.; 3.10.; 5.3.

49 Insufficient information flow 3.1.; 3.5; 3.7.; 3.8.

50 Unclear requirement definition 1.1.; 1.2.; 1.3.; 1.4; 1.5.; 3.3.

51 No understanding of stakeholder needs 1.1.; 1.2.; 1.3.; 1.4; 1.5.; 2.5.; 2.6.;

2.7.; 3.3.; 3.4.

52 No learning from previous need

definitions 3.3.; 5.1.; 5.2.; 5.3.; 5.5.; 6.3.

53 Insufficient multi-attribute trade-

offs/tradespace exploration 1.3.; 1.4; 1.5.; 2.3.; 2.4.; 3.11.

54 Lack of requirement understanding 1.1.; 1.2.; 1.3.; 1.4; 1.5.; 2.7.; 3.3.;

3.4.; 3.7.; 3.10.

55 Lack of life cycle documentation 1.2.; 1.5.; 2.1; 2.2.; 2.5.; 2.7.; 3.3.;

3.7.; 3.9.; 3.10.

56 Insufficient probabilistic cost estimates 1.1.; 1.2.; 1.3.; 1.4; 1.5.; 2.4.

57 Too little updating on estimated costs

during early phases 1.1.; 1.2.; 1.3.; 1.4; 1.5.; 2.4.

58 Cost estimates do not reflect all aspects

of the life cycle 1.1.; 1.2.; 1.3.; 1.4; 1.5.; 2.5.

59 Imprecise or unclear contract terms 1.5.; 2.5.; 2.7.; 3.3.; 3.4.; 3.7.; 3.10.;

3.12.; 5.3.

60 Ill-designed contract scope 1.5.; 2.5.; 2.7.; 3.3.; 3.4.; 3.7.; 3.10.;

3.12.; 5.3.

61 Unclear award criteria and process 1.5.; 2.5.; 2.7.; 3.3.; 3.4.; 3.7.; 3.10.;

3.12.; 5.3.

62 Lack of incentives 1.1.; 1.2.; 1.3.; 1.5.; 2.4.; 2.5.; 2.7.;

3.3.; 3.4.; 3.7.; 3.8.; 3.10.; 3.12.; 5.6

63 Lack of incentive transparency 1.1.; 1.2.; 1.3.; 1.5.; 2.4.; 2.5.; 2.7.;

3.3.; 3.4.; 3.7.; 3.8.; 3.10.; 3.12.; 5.6

64 Mismatch of incentive with desired 1.1.; 1.2.; 1.3.; 1.5.; 2.4.; 2.5.; 2.7.;

Page 156: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

VII Appendix A xxix

outcome 3.3.; 3.4.; 3.7.; 3.8.; 3.10.; 3.12.; 5.6

65 No standard structure for (sub-)contracts 1.5.; 2.5.; 2.7.; 3.3.; 3.4.; 3.7.; 3.10.;

3.12.; 5.3.

66 Mismatch of contract type with risk

profile of program

1.5.; 2.5.; 2.7.; 3.3.; 3.4.; 3.7.; 3.10.;

3.12.; 5.3.

67 Missing parts in the contract (e.g.,

include adaptability)

1.5.; 2.5.; 2.7.; 3.3.; 3.4.; 3.7.; 3.10.;

3.12.; 5.3.

68 Too much granting of waivers 2.6.; 3.1.; 3.2.; 3.5; 3.6.; 3.7.; 4.1.;

5.1.; 5.2.; 5.4.; 5.5.; 6.2.

69 Insufficient probabilistic cost estimates in

contracting 1.1.; 1.2.; 1.3.; 1.4; 1.5.; 2.4.

70 No process implemented to assess

technology maturation 2.3.; 2.5.; 2.6.; 3.6.; 3.11.

71 Use of immature technology 1.3.; 2.3.; 2.4.; 2.6.; 3.6.; 3.11.

72 No established technology insertion

process

1.3.; 2.3.; 2.4.; 2.6.; 3.1.; 3.2.; 3.5;

3.6.; 3.11.; 5.5.

73 No person/team in charge to manage

and monitor technology transition

1.3.; 2.3.; 2.4.; 2.6.; 3.1.; 3.2.; 3.5;

3.6.; 3.11.; 5.5.

74 No formal reviews and communication

plans for technology transition

1.3.; 2.3.; 2.4.; 2.6.; 3.1.; 3.2.; 3.5;

3.6.; 3.11.; 5.5.

75 No diverse learning strategies 5.1.; 5.2.; 5.3.; 5.5.; 5.6; 6.1.; 6.2.;

6.3.; 6.4.

76 Misalignment between team goals and

program goals

2.7.; 3.13.; 5.1.; 5.2.; 5.3.; 5.5.; 5.6;

6.1.; 6.2.; 6.3.; 6.4.

77 Lack of skill and functional diversity

within team

1.5.; 3.4.; 3.9.; 5.1.; 5.2.; 5.6; 6.1.;

6.2.; 6.3.; 6.4.

78 No established flow to and from IPT

level

3.1.; 3.2.; 3.3.; 3.4.; 3.5; 3.6.; 3.7.;

3.8.; 3.9.; 3.10.; 3.11.; 3.12.; 3.13.

79

No balance between teams and

functions (only applies to programs with

matrix organizations)

1.5.; 3.4.; 3.9.; 5.1.; 5.2.; 5.6; 6.1.;

6.2.; 6.3.; 6.4.

80

System architecture does not support

product development process or IPTs

(complex organizations often give rise to

overcomplicated system designs)

1.3.; 2.3.; 2.4.; 2.5.; 2.6.; 3.2.; 3.5;

3.11.; 3.12.

81 Ignoring the aspect of standardization 1.3.; 2.3.; 2.4.; 2.6.; 3.2.; 3.3.; 3.5;

Page 157: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

VII Appendix A xxx

3.11.

82 Ignoring the aspect of reusability 1.3.; 2.3.; 2.4.; 2.6.; 3.2.; 3.3.; 3.5;

3.11.

83 Ignoring the aspect of modularity 1.3.; 2.3.; 2.4.; 2.6.; 3.2.; 3.3.; 3.5;

3.11.

84 Ignoring the aspect of supportability 1.3.; 2.3.; 2.4.; 2.6.; 3.2.; 3.3.; 3.5;

3.11.

85 Ignoring the aspect of maintainability 1.3.; 2.3.; 2.4.; 2.6.; 3.2.; 3.3.; 3.5;

3.11.

86 Ignoring the aspect of usability 1.3.; 2.3.; 2.4.; 2.6.; 3.2.; 3.3.; 3.5;

3.11.

87 Lack of understanding of what waste is 2.1; 2.2.; 2.3.; 2.6.; 2.7.; 4.2.; 5.1.;

5.2.; 5.3.; 5.5.

88

Lack of understanding of how to deal

with different types of waste or waste in

general

2.1; 2.2.; 2.3.; 2.6.; 2.7.; 4.2.; 5.1.;

5.2.; 5.3.; 5.5.

89 No understanding of current vs.

preferred Value Stream

2.1; 2.2.; 2.3.; 2.6.; 2.7.; 4.2.; 5.1.;

5.2.; 5.3.; 5.5.

90 No mechanism for Value Stream

improvements

2.7.; 3.7.; 3.8.; 3.10.; 3.12.; 5.1.;

5.2.; 5.3.; 5.4.; 5.5.; 5.6; 6.2.

91

Mismatch between program

characteristics and chosen development

process

1.3.; 2.3.; 2.5.; 2.6.; 2.7.; 3.2.; 3.3.;

3.4.; 3,5; 3.6.; 3.7.; 3.8.; 3.10.; 3.11.;

3.12.; 4.2.; 5.2.; 5.4.

92 Finishing engineering and 3D drawings

too late

2.3.; 2.4.; 2.6.; 2.7.; 3.1.; 3.2.; 3.3.;

3.4.; 3,5; 3.6.; 3.7.; 3.8.; 3.9.; 3.10.;

3.11.; 3.12.; 3.13.; 4.2.

93 Insufficient exploration of alternative

solutions

1.1.; 1.2.; 1.3.; 1,4; 1.5.; 2,1; 2.2.;

2.4.; 2.5.; 2.6.; 2.7.; 3.11.; 5.1.; 5.2.;

5.3.; 6.2.

94 Wrong test approaches/frameworks

2.5.; 2.6.; 2.7.; 3.1.; 3.3.; 3,5; 3.6.;

3.7.; 3.8.; 3.9.; 3.10.; 3.11.; 3.12.;

3.13.; 4.1.; 4.2.; 5.1.; 5.2.; 5.3.; 5.5.

95 No balance regarding amount of testing

(too much or too little)

2.5.; 2.6.; 2.7.; 3.1.; 3.3.; 3,5; 3.6.;

3.7.; 3.8.; 3.9.; 3.10.; 3.11.; 3.12.;

3.13.; 4.1.; 4.2.; 5.1.; 5.2.; 5.3.; 5.5.

Page 158: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

VIII Appendix B xxxi

VIII Appendix B

Data collection approach for pitfalls for program management:

The document begins with a brief introduction to the LAI program management framework to

enable the interviewee to categorize the pitfalls he/she wants to add or relocate.

General question regarding the interviewee:

1. What type of organization do you work for? a. Government organization b. Company c. Non-profit organization

2. What is the yearly budget of your company or government organization? a. Less than $1 million b. $1 - $10 million c. $10 - $100 million d. $100 million - $1 billion e. $1 billion - $10 billion f. More than $10 billion

3. How many years of total experience do you have? a. Text field

4. How many years of experience in your present company/government organization do you have?

a. Text field 5. In how many programs did you have a significant involvement during your career?

a. Text field 6. What role did you have in these programs?

a. Program manager b. Chief engineer c. Member of the PMO d. Contracting Officer e. Finance Officer f. Engineer g. Other (please specify)

7. What kind of academic background do you have? a. BS b. BA c. MS d. MA e. Phd f. Other (please specify)

8. Which of the following DAU certifications do you have? (0: no certificate) (only applies if DoD background)

a. Program Management (1-3) i. Text field

b. Systems Planning, Research, Development and Engineering (1-3) i. Text field

c. Test & Evaluation (1-3)

Page 159: Master's Thesis / Diplomarbeit Identification of Lean Enablers for Program Management

VIII Appendix B xxxii

i. Text field d. Other (please specify)

9. Please list the type of certifications you have corresponding with your current position (only applies if not DoD background):

a. Please list

Questions asked for every pitfall:

1. Please rate the impact of the pitfall based on your experience: a. 1 – low (local effect: e.g. overtime of some employees) b. 3 – medium c. 5 – high (program wide impact: major deviance from plan (e.g. in cost, quality

or schedule)) 2. Please indicate the area where the pitfall had a direct impact:

a. Cost b. Quality/technical performance c. Schedule

3. How frequently does the pitfall occur in your experience (1: one every 10 programs; 10: in 10 out of 10 programs):

a. Text field (0-10) 4. In which size of programs have you experienced that pitfall?

a. Small (e.g. ACAT III and below; less than $660M total procurement) b. Medium (e.g. ACAT II; between $660M and $2.190B total procurement) c. Large (e.g. ACAT I; more than $2.190B total procurement) d. Universally applicable

5. Please list any leading indicators/metrics/best practices that might be used to discover you are in this pitfall. (General example: How does one know they have unclear requirements?):

a. Text box

The data collection for the assessment of the existing and the capturing of additional Lean

Enablers consists of the list of Lean Enablers shown in Table 6-1: Lean Enablers for program

management. For each Lean Enabler the following categories are to be filled out:

1. Title and description of Lean Enabler

2. Indicator to measure performance of Lean Enabler

3. Experience-based relevance of Lean Enabler (low / medium / high)

4. Application example (anonymized)

5. Literature reference

6. Reference to relevant PM Pitfall (number only)