Managing Projects
Chapter 10
![Page 2: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/2.jpg)
What is a Project?
A project has a unique purpose A project is temporary A project requires resources A project should have a primary sponsor or
customer A project involves uncertainty
![Page 3: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/3.jpg)
What is Project Management?
The application of knowledge, skills, tools, and techniques to project activities in order to meet project requirements
![Page 4: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/4.jpg)
Benefits of Project Management
Better coordination among functional areas Ensure that tasks are completed even when there
is personnel turnover Minimize the need for continuous reporting Identification of realistic time limits Early identification of problems Improved estimating capability Easier to monitor success
![Page 5: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/5.jpg)
Measures of Project Success
Completed on-time Completed within budget Delivery of required specifications Acceptance by customer Minimum number of scope changes (change
orders)
![Page 6: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/6.jpg)
What do Project Manager do?
Manage the people and resources necessary to meet scope, time, cost, and quality goals Reinforce excitement in the project Manage conflict Empower team members Encourage risk taking and creativity
Communicate the progress of the team with managers and customers
![Page 7: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/7.jpg)
Building the Project Team
Forming Storming Norming Performing
![Page 8: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/8.jpg)
Quantitative Tools
Gantt Charts Project Network Diagram
PERT uses AON (Activity on Node) methodology Many software programs (i.e., MS Project) use
boxes and arrows to display activities
![Page 9: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/9.jpg)
Quantitative Analyses
Constructing PERT diagrams and analyzing the critical path
Developing cost-time trade-off slopes Incorporating uncertainty into activity times
![Page 10: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/10.jpg)
Constructing PERT DiagramsBaking a Cake ExampleActivity Code Immediate
Predecessor
Duration (minutes)
Preheat oven A - 1.0
Measure ingredients B A 8.0
Mix ingredients for frosting C B 5.0
Mix ingredients for cake D B 5.0
Pour batter into cake pan E D 1.0
Bake F E 30.0
Cool cake G C, F 60.0
Frost cake H G 5.0
![Page 11: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/11.jpg)
PERT
A1 B8
C5
D5 E1 F30
G60 H5
Note:* Notation represents the activity code and the expected duration (t)* Critical Path = A-B-D-E-F-G-H = 110 minutes
![Page 12: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/12.jpg)
Notation for Critical Path Analysis
Item Symbol Definition
Activity duration t The expected duration of an activity
Early start ES The earliest time an activity can begin if all previous activities are begun at their earliest times
Early finish EF The earliest time an activity can be completed if it is started at its early start time
Late start LS The latest time an activity can begin without delaying the completion of the project
Late finish LF The latest time an activity can be completed if it is started at its latest start time
Total slack TS The amount of time an activity can be delayed without delaying the completion of the project
![Page 13: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/13.jpg)
PERT
A1 B8
C5
D5 E1 F30
G60 H5
ES = 0EF = 0+1=1
ES = 1EF = 1+8=9
ES = 9EF = 9+5=14
ES = 9EF = 9+5=14
ES = 14EF = 15
ES = 15EF = 45
ES = 45 (larger of 45, 14)EF = 105
ES = 105EF = 110
Begin at 1st activity andmake ES = 0
ES = EFpredecessor (if more than 1 EFpredecessor then use the largest value)EF = ES + t
![Page 14: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/14.jpg)
PERT
A1 B8
C5
D5 E1 F30
G60 H5
LS = 0LF = 1
LS = 1LF = 9 (smaller of 40, 9)
LS = 40LF = 45
LS = 9LF = 14
LS = 14LF = 15
LS = 15LF = 45
LS = (105-60)=45LF = LSsuccessor=105
LS = (LF-t) =(110-5)=105LF = EF = 110
Begin at last activity andmake LF=EF = 110
LF = LSsuccessor (If more than 1 LF = LSsuccessor then use the smallest value)LS = LF-t
![Page 15: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/15.jpg)
PERTActivity ES EF LS LF TS
A 0 1 0 1 0
B 1 9 1 9 0
C 9 14 40 45 31
D 9 14 9 14 0
E 14 15 14 15 0
F 15 45 15 45 0
G 45 105 45 105 0
H 105 110 105 110 0
Total Slack (TS) = LS-ES or LF-EF
Activities that have zero slack are critical, meaning they cannot be delayed without delaying the project completion time
![Page 16: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/16.jpg)
Gantt Chart
See either: Demonstration in MS Project Hardcopy distributed in class
![Page 17: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/17.jpg)
Project Network Diagram(produced by MS Project)
See either: Demonstration in MS Project Hardcopy distributed in class
![Page 18: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/18.jpg)
Tennis Tournament ExampleActivity Code Immediate Predecessor Estimated
Duration (days)
Negotiate for location A - 2
Contact seeded players B - 8
Plan promotion C A 3
Locate officials D C 2
Send RSVP invitations E C 10
Sign player contracts F B,C 4
Purchase balls and trophies G D 4
Negotiate catering H E,F 1
Prepare location I E,G 3
Tournament J H,I 2
![Page 19: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/19.jpg)
Tennis Tournament ExamplePERT
Possible paths: A-C-D-G-I-J (16), A-C-F-H-J (12), A-C-E-I-J (20), A-C-E-H-J (18), B-F-H-J (15)Critical path = A-C-E-I-J (20)
![Page 20: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/20.jpg)
Tennis Tournament ExamplePERT
Activity ES EF LS LF TS
A
B
C
D
E
F
G
H
I
J
![Page 21: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/21.jpg)
Gantt Chart
See either: Demonstration in MS Project Figure 10.8 in textbook
![Page 22: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/22.jpg)
Project Network Diagram(produced by MS Project)
See either: Demonstration in MS Project Figure 10.9 in textbook
![Page 23: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/23.jpg)
Trades-OffsCost and Time
Cost and time are inversely related
As time to complete a project goes down, costs for the project go up
As time goes up, costs go down
![Page 24: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/24.jpg)
Project Costs
![Page 25: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/25.jpg)
Activity Crashing
An activity is considered to be “crashed” when it is completed in less time than is normal by applying additional labor or equipment
![Page 26: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/26.jpg)
Determining the Impact of Activity Crashing
To determine the impact of activity crashing begin by identifying the Expedite-Cost Slope for each activity
To do this, a manager must identify “normal” and “crash” time and cost estimates
![Page 27: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/27.jpg)
Tennis Tournament ExampleCost and Time Estimates
8201212J
210823I
-101011H
110934G
715834F
54020610E
6171112D
3131023C
4302268B
1015512A
Slope ($/day)CrashNormalCrashNormalCode
Expedite-Cost*Direct Costs ($)Time Estimate (Days)
8201212J
210823I
-101011H
110934G
715834F
54020610E
6171112D
3131023C
4302268B
1015512A
Slope ($/day)CrashNormalCrashNormalCode
Expedite-Cost*Direct Costs ($)Time Estimate (Days)
*Slope = Crash Cost – Regular Cost (15 – 5) = 10 = 10 Normal Duration – Crash Duration (2 – 1) 1
![Page 28: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/28.jpg)
Activity Cost-Time Trade-off(Activity Code E)
Activity E: Normal Time = 10, Crash Time = 6, Normal Cost = $20, Crash Cost = $40)
![Page 29: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/29.jpg)
Incorporating Uncertainty into Activity Times
When a manager is unsure of the activity duration times, he/she needs to estimate activity times using a Beta distribution
The Beta distribution allows the manager to develop a probable range of times in which the activity time will fall
![Page 30: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/30.jpg)
Beta Distribution of Activity Duration
![Page 31: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/31.jpg)
Beta Distribution Time Estimates
Optimistic Time (A) – activity duration if no problems occur
Most Likely Time (M) – activity duration that is most likely to occur
Pessimistic Time (B) – activity duration if extraordinary problems arise
![Page 32: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/32.jpg)
Formulas
Activity time (t) = (A + 4M + B)/6 Standard deviation (σ) = (B - A)/6 Variance (σ2) = (B – A)2/36
![Page 33: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/33.jpg)
Assessing ProbabilityTennis Tournament Example
Let’s say we plan to begin the tennis tournament project on October 25th and plan to have it completed within 24 days (November 18th) because the tennis stadium is booked after that.
As a manager, you have estimated the optimistic, most likely, and pessimistic times for each activity
Now you want to find the probability that you will be able to finish the project in 24 days
![Page 34: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/34.jpg)
Time Estimates Tennis Tournament Example
Time Estimates
Activity A M B t σ σ2
A 1 2 3 2.00 0.33 0.11
B 5 8 11 8.00 1.00 1.00
C 2 3 4 3.00 0.33 0.11
D 1 2 3 2.00 0.33 0.11
E 6 9 18 10.00 2.00 4.00
F 2 4 6 4.00 0.67 0.44
G 1 3 11 4.00 1.67 2.78
H 1 1 1 1.00 0.00 0.00
I 2 2 8 3.00 1.00 1.00
J 2 2 2 2.00 0.00 0.00
![Page 35: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/35.jpg)
Time Estimates – Critical Path Tennis Tournament Example
Time Estimates Activity A M B t σ σ2 A 1 2 3 2.00 0.33 0.11 B 5 8 11 8.00 1.00 1.00 C 2 3 4 3.00 0.33 0.11 D 1 2 3 2.00 0.33 0.11 E 6 9 18 10.00 2.00 4.00 F 2 4 6 4.00 0.67 0.44 G 1 3 11 4.00 1.67 2.78 H 1 1 1 1.00 0.00 0.00 I 2 2 8 3.00 1.00 1.00 J 2 2 2 2.00 0.00 0.00
∑t = 2.00 + 3.00 + 10.00 + 3.00 + 2.00 = 20 days∑σ2 = 0.11 + 0.11 + 4.00 + 1.00 + 0.00 = 5.22 days∑σ = 0.33 + 0.33 + 2.00 + 1.00 + 0.00 = 3.66
![Page 36: Managing Projects Chapter 10. What is a Project? A project has a unique purpose A project is temporary A project requires resources A project should have](https://reader035.vdocuments.mx/reader035/viewer/2022062320/56649cf75503460f949c6dc1/html5/thumbnails/36.jpg)
Building Time DistributionTennis Tournament Example
Z = (X – μ)/σ
Z = (24 – 20)/√5.22
Z = 1.75
Z Table (p. 579 of textbook) shows that a Z value of 1.75 refers to a probability of (0.5000 – 0.4599)= 0.0401 or .04
Therefore, there is a 4% probability that the project would not be completed in 24 days