management plan for parking in ahmedabad
TRANSCRIPT
Management Plan for Parking in Ahmedabad
Major Project Report
Submitted by:
Nirav Vidwans (0727MPB)
Ambika Pandey (0719MPB)
In partial fulfilment for the
Degree of MBA (Infrastructure)
Submitted to:
Department of Policy Studies
TERI University
Vasant Kunj, New Delhi, India
May 2009
Student Declaration
We, Nirav Vidwans (0727MPB) and Ambika Pandey (0719MPB) hereby undertake that the work
submitted here namely ‘Management Plan for Parking in Ahmedabad’ done in collaboration with
ITDP, New York, is purely for fulfilment of academic requirements for the award of Degree of MBA
(Infrastructure), TERI University. The work has not been published anywhere else and due
acknowledgement to sources of reference has been made. The work was sub-divided between the
contributors and has been mentioned in the relevant sections of the report.
_______________________ _________________________
Nirav Vidwans Ambika Pandey
(0727MPB) (7019MPB)
Submission Form
Name of the student : Ambika Pandey (0719MPB)
Nirav Vidwans (0727MPB)
Programme : MBA (Infrastructure)
External Supervisor : Shrey Gadepalli, Senior Program Director, ITDP
Title of the research project : Management Plan for Parking in Ahmedabad
Date of completion of project : 10/05/2009
__________________ ____________________
Ambika Pandey Nirav Vidwans
(0719MPB) (0727MPB)
______________________
Shreya Gadepalli,
Senior Program Director,
ITDP, India.
Date:
Acknowledgement
We express our gratitude to ITDP (Institute for Transportation and Development Policy) for
nominating us to an eighteen weeks Internship Programme, conducted by Department of Policy
Studies, TERI University, New Delhi.
We express our sincere thanks to Ms. Shreya Gadepalli, Senior Programme Director, ITDP
(Ahmedabad) and her entire team, who helped us not only in providing necessary data for project
but also in guiding us during preparation of our report.
Also we would like to thank Dr. Kaushik Deb, Head of the Center, Department of Policy Studies
for highlighting some issues that can be taken up for the report work.
Ambika Pandey Nirav Vidwans
Abstract
As India‟s economy is expanding and growing at fast rate, the pressure on its transport
infrastructure can be easily felt. The needs of an increasingly urban population, coupled with
significant increases in industrial, trade and commercial demands, socio-economic
developments have placed immense strain on the existing transport infrastructure and
resulting steep increase in transport demand.
Over the past 10 years the vehicle population has increased hundred-fold while the road
length network has reportedly increased by a factor of only seven. The annual average rate of traffic
growth stands at around 8-10%. In the year 2004 a record breaking 1 million cars were sold which infers
the increase in dependence on private transportation. This increase in share of private transport have
started to cause traffic congestion, increase in parking space, various pollution etc. in almost all
the mega cities of India. However parking which is one of the basic elements of
transportation is never given importance unless and until it becomes inevitable. Parking
Policy plays a vital role in the overall development of a city. The basis of this study is to design a
parking facility for Ahmedabad.
This report is divided into 8 sections:
1. Introduction to the City
2. About the Project
3. Literature Review
4. Data Collection, Analysis and Modeling
5. Maninagar Parking Demand
Management Plan
6. Conclusion and recommended Policy
Directives
7. Annexure
8. References
Section: 1. Introduction to the City
This section gives a brief introduction to the the city, its Demographics, the Economy and Land use,
Existing Transportation scenario and Travel characteristics.
Section: 2. About the project
This section explains the reason behind this project, objectives, methodology and the scope of the study.
The study is intended to develop a management plan that addresses parking related issues for the city of
Ahmedabad. The plan shall provide solution in regulatory perspective for both on and off street parking
through pricing and supply management. The study will also look into the issues related to pricing
aspects.
The study shall help informing local government, developers, institutions, and citizens to broadly
implement optimal parking solutions.
Section: 3. Literature Review
Primarily parking is done to control ill-effects now it is considered as a tool in many developed
nations to reduce congestion, as a traffic management measure and finally as urban development policy
objectives. There is no uniform approach in solving this problem, this is seen in many metropolises which
have to be tackled and cured on scientific bases and hence the uniform approach for metropolitan cities.
The study is broadly divided into three parts, a) Policy Design, b) Pricing Mechanism and c) Management
Plan This sections includes the various strategies involved in a parking policy. It begins with the
introduction of parking terminologies, norms, types of surveys and designs and also gives a brief about
the pricing mechanism and management plan. The section also discusses four parking practices both on-
street and off-street covering international and domestic cases.
Section: 4. Data Collection, Analysis and Modeling
Out of the 21 major roads six cases were selected representing 27% sample size population of the listed
roads. These were:
Maninagar Station Road (Kankaria to Railway Station)
Ashram Road (Usmanpura to Delite Junction)
Relief Road (Circuit House to Kalupur Railway Station)
SG Highway (ISKON to Gurudwara)
Gurukul Road (Gurukul to Subhash Chowk)
CG Road (Panchvati to Stadium Cross Road)
Data Collection has been divided into two parts: primary data and secondary data.
Primary Data:
Site survey based: Parking volumes, inventory, Land use, accumulation, etc.
Questionnaire based: Parking interviews, Trip length, Trip purpose
Secondary Data:
Technical alternatives and cost
Scheduling of rates
Manpower and Enforcement cost and Building use conversion data
This section also discusses the detailed site analysis of all the six cases and the selection of location for
the pilot project. The location selected is MANINAGAR. Maninagar has different demand characteristics
in all the sections due to different activities.
Section: 5. Maninagar Parking Demand Management Plan
This section includes physical analysis, parking statistics, management options and pricing model. On-
street parking is generally 10% of the cost of off-street parking facility. Following options have been
identified to manage the proposed on-street parking facility.
Manual paper ticketing system
Smart card technology with portable meter and e-ticketing system
RFID Technology
The user of a publicly provided service should pay an amount sufficient to cover the public cost of
providing the service. Demand management plan includes:
Parking pricing
Regulating supply
Enforcement mechanism
Section: 6. Conclusion and Recommended policy directives
Parking is and will remain an issue that affects everyone in the community, from traffic management and
law enforcement to attraction owners to residents of nearby neighborhoods.
Parking must have:
ease of implementation
high revenue capability
The evolvement in parking management has shifted from the setting up of on-street parking via the
creation of off-street parking , towards parking management system as apart of wider traffic management
system.
Table of Content
Chapter 1: Introduction to the City ............................................................................................................ 1
1.1 About the City ............................................................................................................................... 1
1.2 Demographics ................................................................................................................................ 1
1.3 Economy & Land Use .................................................................................................................... 3
1.4 Existing Transportation Scenario ................................................................................................... 7
1.5 Travel Characteristics .................................................................................................................. 10
Chapter 2: About the Project ................................................................................................................... 13
2.1 About the Subject......................................................................................................................... 13
2.2 Need for the Study ....................................................................................................................... 14
2.3 Objective and Scope of Study ...................................................................................................... 14
2.4 Methodology ................................................................................................................................ 15
Chapter 3: Literature Review .................................................................................................................. 16
3.1 Parking Terminology (Khanna, Justo, 1979) ................................................................................ 16
3.2 Parking Norms for the city ........................................................................................................... 17
3.2.1 Parking Norms given by Indian Roads Congress (IRC-12) ....................................................... 17
3.2.2 Parking Norms of Ahmedabad City .......................................................................................... 18
3.3 Defining Parking Problems and Solutions .................................................................................... 19
3.4 Evaluation framework and criteria ............................................................................................... 20
3.5 Impact of parking ......................................................................................................................... 21
3.6 Best Practices ............................................................................................................................... 22
3.6.1 Domestic on-street parking scheme .......................................................................................... 22
3.6.2 Domestic off-street parking scheme .......................................................................................... 24
3.6.3 International on-street parking scheme ...................................................................................... 26
3.6.4 International off-Street parking scheme .................................................................................... 28
3.7 Parking surveys & Definitions ..................................................................................................... 29
3.7.1 Parking Space Inventory Survey ............................................................................................... 29
3.7.2 Parking Usage Survey by Patrol................................................................................................ 30
3.7.3 Questionnaire Type Parking Usage Survey ............................................................................... 31
3.7.4 Cordon Count Survey ............................................................................................................... 31
3.8 Design and Technology Alternatives ............................................................................................ 32
3.8.1 Common Methods of On Street Parking/ Kerb Parking ............................................................. 32
3.8.2 Types of Off Street parking facilities ........................................................................................ 33
3.9 Policy Study................................................................................................................................. 36
Chapter 4: Data Collection and Analysis (Nirav, Ambika)
............................................................................... 38
4.1 Study Area Delineation & Case Selection .................................................................................... 38
4.2 Field Surveys & Primary Data Analysis ....................................................................................... 40
4.2.1 Parking Volume Counts ............................................................................................................ 41
4.2.2 Land Use Survey ...................................................................................................................... 51
4.2.3 Parking Space Inventory ........................................................................................................... 55
4.2.4 Parking Duration ...................................................................................................................... 57
4.2.5 Parking Interview ..................................................................................................................... 59
4.3 Observation Summary .................................................................................................................. 60
4.3.1 Maninagar Analysis .................................................................................................................. 60
4.3.2 Ashram Road Analysis ............................................................................................................. 64
4.3.3 Relief Road Analysis ................................................................................................................ 66
4.3.4 C G Road Analysis ................................................................................................................... 68
4.3.5 Gurukul Road Analysis............................................................................................................. 71
4.3.6 S G Highway Analysis ............................................................................................................. 72
Chapter 5: Maninagar Parking Demand Management Plan ..................................................................... 74
5.1 Parking Development Plan for Maninagar .................................................................................... 74
5.1.1 Physical Analysis of Maninagar (Nirav)
....................................................................................... 74
5.1.2 Parking Statistics (Nirav, Ambika)
.................................................................................................... 77
5.1.3 Parking Scheme Physical Design Options (Nirav)
........................................................................ 81
5.1.4 Management Options (Ambika)
..................................................................................................... 84
5.1.5 Pricing and Financial Model (Nirav)
............................................................................................ 87
5.2 Demand Management Plan (Nirav, Ambika)
........................................................................................ 92
Chapter 6: Conclusion and Recommended Policy Directives .................................................................. 97
Annexure .......................................................................................................................................... 100
References ........................................................................................................................................ 103
List of Tables
Table 1.1: Population growth trend ......................................................................................................................................... 2
Table 1.2: Land Use Pattern – AMC and AUDA – 2011 .......................................................................................................... 4
Table 1.3: Motor Vehicle Growth in Ahmedabad .................................................................................................................... 7
Table 1.4: AMTS Operation Figures ....................................................................................................................................... 8
Table 1.5: GSRTC Service to Ahmedabad .............................................................................................................................. 8
Table 1.6: Roads in AMC ....................................................................................................................................................... 9
Table 1.7: Major Road Widths .............................................................................................................................................. 10
Table 1.8: Household distribution by income group ............................................................................................................... 11
Table 1.9: Travel Characteristics ........................................................................................................................................... 12
Table 3.1: Parking Norms – IRC (Indian Road Congress) ...................................................................................................... 18
Table 3.2: Parking Norms - GDCR ....................................................................................................................................... 19
Table 3.3: Parking management strategies (Donald Shoup-1999, TDM Encyclopaedia, EPCA Report 2008) .......................... 35
Table 4.1: Major Roads of the City ....................................................................................................................................... 38
Table 4.2: Case for Parking Survey (Primary Data – Phase-1) ............................................................................................... 39
Table 4.3: Survey Parameters................................................................................................................................................ 40
Table 4.4: Survey Schedule................................................................................................................................................... 41
Table 4.5: Survey Time Slots, [(*) – Phase-2 Survey]............................................................................................................ 41
Table 4.6: Parking Volume – Ashram Road .......................................................................................................................... 42
Table 4.7: Parking Accumulation - Maninagar ...................................................................................................................... 45
Table 4.8: Parking Accumulation – Relief Road .................................................................................................................... 45
Table 4.9: Parking Volume – S G Highway (22/02/09) .......................................................................................................... 47
Table 4.10: Parking Volume – Gurukul road (27/02/09) ........................................................................................................ 49
Table 4.11: Parking Volume – CG Road (21/03/09) .............................................................................................................. 50
Table 4.12: Maninagar Road - Land Use ............................................................................................................................... 52
Table 4.13: Ashram Road – Land Use ................................................................................................................................... 53
Table 4.14: Gurukul Road - Land Use ................................................................................................................................... 53
Table 4.15: C G Road – Land Use ......................................................................................................................................... 54
Table 4.16: S G highway – Land Use .................................................................................................................................... 54
Table 4.17: Parking Space Inventory – All Cases .................................................................................................................. 55
Table 4.18: Categorized Parking Duration - Maninagar ......................................................................................................... 57
Table 4.19: Categorized Parking Duration – Maninagar (Percentage) .................................................................................... 58
Table 4.20: Categorized Parking Duration – Ashram Road .................................................................................................... 58
Table 4.21: Categorized Parking – Ashram Road (Percentage) .............................................................................................. 59
Table 4.22: Trip Purpose - Maninagar ................................................................................................................................... 59
Table 4.23: Peak Hour Demand - Maninagar ......................................................................................................................... 63
Table 4.24: Parking Area Demand - Maninagar ..................................................................................................................... 63
Table 4.25: Demand Percentage of Supply ............................................................................................................................ 63
Table 4.26: High Volume section Demand – Maninagar ........................................................................................................ 64
Table 4.27: Peak HourVolume – Ashram Road ..................................................................................................................... 65
Table 4.28: Parking Area Demand – Ashram Road................................................................................................................ 65
Table 4.29: Parking Supply Percentage ................................................................................................................................. 65
Table 4.30: Paid Parking Lots in Walled City ........................................................................................................................ 67
Table 4.31: Peak Hour Demand – Relief Road ...................................................................................................................... 67
Table 4.32: Parking Area Demand – Relief Road .................................................................................................................. 67
Table 4.33: Parking Supply Percentage ................................................................................................................................. 68
Table 4.34: C G Road – Fees Schedule ................................................................................................................................. 69
Table 4.35: Peak Hour Demand – C G Road ......................................................................................................................... 70
Table 4.36: Parking Area Demand - C G Road ...................................................................................................................... 70
Table 4.37: Parking Supply Percentage ................................................................................................................................. 70
Table 4.38: Peak Hour Demand – Gurukul Road ................................................................................................................... 71
Table 4.39: Parking Demand – C G Road .............................................................................................................................. 71
Table 4.40: Parking Supply Percentage ................................................................................................................................. 72
Table 4.41: Peak Hour Demand – S G Highway .................................................................................................................... 73
Table 4.42: Parking Demand Area – S G Highway ................................................................................................................ 73
Table 4.43: Parking Supply Percentage ................................................................................................................................. 73
Table 5.1: BRTS corridor Parking details - Maninagar .......................................................................................................... 77
Table 5.2: Parking Statistics – Maninagar ............................................................................................................................. 77
Table 5.3: Total 2-wheeler daily demand - Maninagar ........................................................................................................... 79
Table 5.4: Parking Duration Volumes – Maninagar ............................................................................................................... 80
Table 5.5: Maximum Area Requirement - Maninagar ............................................................................................................ 80
Table 5.6: Parking Area Demand (Modewise) Peak Hour – Maninagar .................................................................................. 82
Table 5.7: On-street Parking Design Space Allocation – Maninagar ...................................................................................... 83
Table 5.8: Comparison of Parking Management Systems ...................................................................................................... 85
Table 5.9: Smart Card Technology Options ........................................................................................................................... 86
Table 5.10: Project Cost Options ........................................................................................................................................... 90
Table 5.11: Expected Revenue Comparison .......................................................................................................................... 90
Table 5.12: Linear Pricing Scheme ....................................................................................................................................... 91
Table 5.13: Incremental Pricing Scheme ............................................................................................................................... 92
List of Figures
0
Figure 1.1: City Growth Patter
Figure 1.2: AMC – Proposed Land Use 2011
Figure 1.3: AUDA – Proposed Land Use 2011
Figure 1.4: Proposed Land Use Map – AMC and AUDA – 2011
Figure 1.5: Existing Land Use patterns
Figure 1.6: motorized Vehicular Composition – 2007
Figure 1.7: Ahmedabad Road Network – 2011
Figure 1.8: Vehicle Ownership Distribution
Figure 3.1: Parking bays and accumulation curve
Figure 3.2: Hyderabad Airport Parking Design
Figure 3.3: Parking Patterns
Figure 3.4: Parking Policy Contents
Figure 4.1: Case Study Locations
Figure 4.2: Parking Volume Trend – Ashram Road – Section – 1
Figure 4.3: Parking Volume Trend – Ashram Road – Section – 2
Figure 4.4: Parking Accumulation – Ashram Road
Figure 4.5: Parking Accumulation - Maninagar
Figure 4.6: Parking volume – Relief Road (24.02.09)
Figure 4.7: Parking Volume – Relief Road (3 Days)
Figure 4.8: Parking Volume – 3 Sections (SG Highway)
Figure 4.9: Parking Volume – S G Highway
Figure 4.10: Total Parking Volume – SG Highway
Figure 4.11: Categorized Parking and Total Parking Volume – Gurukul Road
Figure 4.12: Categorical and Total Parking Volume – C G Road
Figure 4.13: Maninagar Road – Mapped Observations
Figure 4.14: Mapped Images – Ashram Road
Figure 4.15: CG Road – Mapped Observations
Figure 4.16: Gurukul Road – Mapped Observations
Figure 4.17: S G Highway – Mapped Observations
Figure 5.1: Maninagar Physical Analysis
Figure 5.2: Parking Accumulation Curve
TERI University, New Delhi Parking Policy and Management - Ahmedabad
1
Chapter 1: Introduction to the City
1.1 About the City
Ahmedabad is the commercial capital of Gujarat state and an emerging mega city of India. Founded in
1411 AD the city has now grown to be seventh largest city in the country and largest in the state (BRTS,
DPR – 2008). The city remains to be the financial and commercial/economic hub of the state with
extensive trade and manufacturing. Once famous as the „Manchester of India‟, Ahmedabad was textile
capital of the country. With current industrial basket comprising of manufacturing textiles, chemicals,
metals and alloys, pharmaceutical drugs and plastic the city attracts entrepreneurs for investments. The
city lies on the commercial belt of Gujarat and Maharashtra with a terminal position on the DMIC
corridor connecting northern and western India i.e. Delhi and Mumbai. The city has attracted more
investment after proposition of more than six SEZ‟s in and around the district. It is well connected to rest
of the country through rail, road and air routes. AMC (Ahmedabad Municipal Corporation) and AUDA
(Ahmedabad Urban Development Authority) are the governing bodies of the city. Ahmedabad has three
large industrial estates within the municipal limits governed by GIDC. The city is well electrified by
Torrent Power Company at stable power supply with minimum load shedding. Educational institutes and
research organizations like educational institutes IIM, CEPT, NID and research organizations like ISRO,
PRL etc. have brought the city name and fame. Rich in architectural heritage and culture the city reflects
its value through several monuments, temples etc. The city presently spans on eastern and western banks
of river Sabarmati with the walled city on eastern bank and the modern city on the western bank. With
projects like the BRTS, Metro Rail (proposed), Ahmedabad – Vadodra Expressway, Sabarmati River
Front, Kankaria Lake etc. the city is trying to provide world class urban infrastructure to its citizens. With
this progress trend the city has felt the need to develop its transport infrastructure, water and sanitation
and health and education infrastructure.
1.2 Demographics
The city of Ahmedabad spreads over an area of approximately more than 400 km² with a
population of more than 5.5 million (GIDB – Traffic Study 2004). While greater Ahmedabad covering
areas of AMC, AUDA, Gandhinagar and surrounding villages covers 4200 km² of land (AUDA – Master
Plan 2011). The city is composed of eastern bank with fort walled city having high population density,
heavy commercial activity density and traditional architecture with closely placed structures and narrow
streets. The socio-economic characteristic of eastern city is dominated by low to middle income group
with all the three industrial estates. The growth of eastern area is highly unplanned. Western side of the
city has seen growth since past two decades, but the speed has been immense as compared to the eastern
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
2
side. The west has relatively well planned housing with wider roads and major institutions. Western
suburb has noticed rapid industrial development and middle and higher income group residential
development. Increment in the urban sprawl can be mainly attributed to addition of residential and
commercial space in the city. Population growth trend of the city can be seen in the following table.
Location Population (million) Density
(Person/Ha) - 2001 1981 1991 2001
AMC 2.2 2.9 3.5 184
AUDA + AMC 2.7 3.8 4.7 77
Table 1.1: Population growth trend Source: Ahmedabad BRTS DPR – August 2008
Population of the city has been ever growing due to addition of new areas into the municipal limits and
inclusion of new areas to greater Ahmedabad. It has also grown due to immense employment opportunity
and better infrastructure as compared to rest of the state. Population growth rate has declined from 3.4 to
2.2 percent compounded annually in past two decades, however the rate varies spatially (BRTS, DPR –
2008). The walled city has reached saturation in terms of land use and population. There are more that
nine lakh households in the city that account for the city population. Ahmedabad ranks third in the
country with highest per capita income figure for year 2007-08(NCAER/FCR) with 23 % of the
population living below the poverty line (NCAER/FCR Report – 2008). The growth in per capita income
is mainly because of industrialization around the city, infrastructure development, retail business growth,
literacy growth etc. The diagram shows the city growth pattern in different time phases.
FIGURE 1.1: City Growth Patter Source: Ahmedabad BRTS DPR – Phase II - 2008
TERI University, New Delhi Parking Policy and Management - Ahmedabad
3
1.3 Economy & Land Use
Economy of the city is built by diverse professions and industries dominated by pharmaceutical
industries, chemical industries, textile business, real estate business and retail industry. A substantial
segment of the population is engaged in retail business and small scale industries. Development of malls
and multiplexes in the city has taken retail business to an organized sector from an unorganized pattern.
Real Estate business is flourishing on both the sides of the city with several housing schemes being
developed within and beyond the AMC limits. Ahmedabad contributes 20 % to the income of Gujarat
statev. The city has also attracted IT industry to a certain extent due to increase in demand of IT service
and availability of skilled manpower. Development of medium to large scale industries is also seen on the
fringe areas of the city owing to liberal industrial policies of the city. Ahmedabad is connected to all the
ports in Gujarat and with development of ports in the costal SEZ‟s in the state the city is becoming a
major trade terminal connecting northern and western parts of the country. This is also expected to attract
high end manufacturing industries in the district that shall generate employment opportunities and
strengthen the economy of the city. With such a prime location and connectivity through air, rail and road
the city is gaining importance as trading and manufacturing hub critically. Ahmedabad also acts as a
tourist terminal that attracts and distributes the tourism flux to other parts of the state. Agriculture has also
gained impetus in and around the district due to Narmada canal that brings water for irrigation. DMIC
corridor is expected to give a boost in transactions of agricultural products from the district to other parts
of the country. Ahmedabad has currently seven APMC (Agricultural Produce Market Committee)
operation sites that trade agricultural produce and have a turnover of more than 800 million Rs (APMC –
Ariculture Produce Market Committee – Annual Report 2008). Five of these market yards are located on
the suburban region of the city whereas two of these are in the city.
Land use and its nature of growth, has played a vital role in economic prosperity of the city. The
spatial arrangement of activities has aided this development. Existing economic development of the city is
highly dependent on spatial arrangement of different activities and their connectivity to other regions.
Ahmedabad is a ring radial city with two rings and radials on east and west of the city. Location of key
urban units like transport units (railway station, bus station and air port), freight handling units (APMC
yards, railway cargo yard etc.), government institutions etc. is decentralized in the city which helps to
partially regulate traffic and congestion. Land use in the city is regulated by the GDCR norms, but there is
a strong need felt to revise these norms due to conversion of land use, increase in unplanned land
allocation etc. The land around the city is not locked and thus has immense potential to expand in all
directions. The city has currently spread more in east – west direction against north – south direction. This
can be due to the developing industrial and residential zones in these two directions (east and west). Since
the river Sabarmati crosses the city from north to south it confines the development there.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
4
Following table shows the broad land use categories proposed for the city in 2011, and their composition
for AUDA and AMC territory.
Sr.
No.
Category Proposed Area (Ha) % of Total Land
AMC - 2011
1 Residential 8340.22 42.69
2 Commercial 263.06 1.35
3 Educational 387.30 1.98
4 General Industrial 2006.51 10.27
5 Special Industrial 786.72 4.03
6 Agricultural/Recreational/ Vacant 1643.60 8.41
7 Water bodies 937.97 4.80
8 Railway and Airport 826.86 4.23
9 Roads 1744.67 8.93
10 Walled City 645.56 3.30
11 Special Development Land 1955.37 10.01
Total 19536.98
AUDA – 2011
1 Residential 1 8536 36.21
2 Residential 2 3218 13.65
3 Residential 3 3500 14.85
4 Commercial 808 3.43
5 Educational & Public Utility 367 1.56
6 Services & Institutional 442 1.86
7 Industrial 909 3.86
8 Agricultural 2622 11.12
9 High Flood Hazard Zone 537 2.28
10 Sewage Treatment Plant 935 3.97
11 Road, Railways & Transport 1697 7.20
Total 23571.00
Table 1.2: Land Use Pattern – AMC and AUDA – 2011 Source: BRTS DPR 2008 & AUDA Website
As seen in the table above both the authorities have proposed to allocate maximum land to residential
development followed by industrial land in AMC and agricultural in AUDA region. Total area that shall
TERI University, New Delhi Parking Policy and Management - Ahmedabad
5
be under AMC and AUDA jurisdiction is around 43,107.98 Ha (AUDA – Development Plan -2011).
Following chart gives a comparative view of the proposed development.
Figure 1.2: AMC – Proposed Land Use 2011 Source: BRTS DPR – Phase II - 2008
Figure 1.3: AUDA – Proposed Land Use 2011 Source: AUDA Website
As seen in the above chart AMC and AUDA have proposed residential land use development up to the
level of almost 43% and 65% respectively. Industrial development in the AMC territory has been
proposed to an extent of about 15%. This can be seen from the current level of industrialization in the
fringe areas of AMC limits and its proximity to the core city areas. Industrial cluster development on the
fringe areas can even be attributed to easy access to market yards, warehouses, transport terminals,
highway, railway terminal etc. This growth however is not high in comparison to past data due to State
Governments restrictive policy. AUDA has proposed very low level of industrialization because of
42.69%
1.35%
1.98%10.27%4.03%
8.41%
4.80%
4.23%
8.93%
3.30%
10.01%
AMC - 2011 - Proposed Land Use Pattern % of Total LandResidential
Commercial
Educational
General Industrial
Special Industrial
Agricultural/Recreational/
VacantWater bodies
Railway and Airport
Roads
Walled City
Special Development Land
36.21%
13.65%14.85%
3.43%
1.56%1.88%
3.86%
11.12%
2.28%3.97%
7.20%
AUDA - 2011 - Proposed Land Use Pattern % of Total Land
Residential 1
Residential 2
Residential 3
Commercial
Educational & Public Utility
Services & Institutional
Industrial
Agricultural
High Flood Hazard Zone
Sewage Treatment Plant
Road, Railways & Transport
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
6
unavailability of infrastructure as compared to AMC territory. AUDA currently has high level of
agricultural land and proposes to promote agriculture more than any other land use except residential use
to a level of 12%. Land dedication to transport facilities falls next to agriculture to a level of around 7%.
This land use design shows that majority of the activities and employment options still remain
concentrated in AMC limits. There can thus be a hypothesis created saying that if residential development
grows at same rate in AUDA region it would envelope and limit industrial development in AMC region.
AMC is also proposing a third ring road to facilitate the through traffic to bypass the urban region.
Development of Educational and Commercial use is still marginal as compared to residential and
Industrial development. From past land use data it can be seen that the city is promoting industrial land
use more than educational, commercial and recreational/public spaces. Following is the proposed land use
map for AMC and AUDA region. The map shows spatial distribution of residential, commercial and
industrial spaces in the city that hold prime importance in the study. These three land uses attract almost
all the parking demand in the city and thus create a need for space. It can be seen that majority of the land
use remains confined in the AMC limits and have barely spread across to AUDA territory. Commercial
activity though not centralized but is spread in the central area of the city in small clusters.
Industrialization in Ahmedabad accounts for 21.5% of the industries and almost 18% employment of the
state which is seen mostly spread in the western side of the city. Recently in the city there has been shift
from manufacturing oriented economy to service based economy which has brought about drastic change
in land use pattern of the city. Industrialization has thus started to shift to the west suburban region of the
city due this drift in economic scenario. It can also be seen that there are few mixed clusters comprising
industrial and residential development stranding out of the ring radial city. These developments have been
promoted by the radials extending out of the core city. After the composite land use map classified land
use maps show the existing concentration/distribution of residential, commercial, public use and
industrial spaces respectively. More than 80% of the Greater Ahmedabad population resides within the
AMC limits composing residential land use to the maximum level BRTS, DPR – 2008). Level of
urbanization on the eastern city is more than the western part but is unplanned against the western city
development. Public facility space is very less against commercial and industrial development.
Figure 1.4: Proposed Land Use Map – AMC and AUDA – 2011 Source: BRTS – DPR Phase II - 2008
Figure 1.5: Existing Land Use patterns Source: CDP Strategies, Ahmedabad (2003)
TERI University, New Delhi Parking Policy and Management - Ahmedabad
7
73.40%
5.30%
12.80%
0.40%
3.10%
1.70%3.00% 0.30%
Motorized Vehicular Composition - 2007
2 wheelers
3 Wheelers
Cars
Taxis
Buses & HCV
LCV/ Trailor
Tractors/Tempo
Others
1.4 Existing Transportation Scenario
The city as mentioned earlier is well connected through rail, road and air routes. It has good networking
with national highways, state highways and district roads along with one expressway. The city has one
main railway junction and four other railway stations. With increase in population and total number of
vehicles in the city congestion and pollution are coming up as major problems. Road network length per
lakh number of vehicles also has reduced owing to vehicular growth and lack of space availability for
roads.
Vehicles in the city have drastically increased in past 40 years against the city and its infrastructure
growth. The table below shows the vehicular growth trend in the city since 1971.
Year Total Vehicles Two Wheelers Three Wheelers Four Wheelers AMTS Buses
1971 62922 21702 4865 4081 525
1981 165620 86550 16741 14098 610
1991 538182 361372 38359 47952 756
2001 1210278 863003 65868 114653 886
2007 1938518 1422666 90918 248130 920
Table 1.3: Motor Vehicle Growth in Ahmedabad Source: RTO Office, Ahmedabad – 2007
Vehicles in the city have grown at an average growth rate of 10.03%. Since 1971 total number of vehicles
in the city has grown up to 31 times. Total number of registered vehicles in Ahmedabad after its
formation in 1961, are above 90 lakhs that is 170 times the initial number (CRRI – City Transportation
Study – 2006). Ahmedabad accounts for over more than 21% of the total vehicles registered in the state.
Car use has increased in the city by an addition of 19858 cars last year. Ahmedabad accounts for the
highest per capita vehicles in the country with almost 290 vehicles per 1000 population (2002). Existing
motorized vehicular composition in the city is as shown.
Figure 1.6: motorized Vehicular Composition – 2007
Source: RTO Office, Ahmedabad
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
8
Public transport agency for the city is AMTS (Ahmedabad Municipal Transport Service) a statutory body.
It had 141 operational routes with 920 buses in 2007 (GSRTC website). Currently it faces several set of
problems in terms of excessive manpower, poor maintenance, large overheads, aged fleet, and weak
operational plans. Below shown is a past eight year statistic of AMTS operation in the city.
Year Fleet Size
(Buses)
No. of
Routes
Service
Km./day
Buses/ Lakh
population
Ridership
2000 942 144 155675 22 757852
2001 886 140 151245 21 678861
2002 801 136 124375 18 574257
2003 687 115 81802 15 385682
2004 601 110 76028 13 325378
2005 540 117 77411 11 349653
2006 848 131 117536 14 579254
2007 920 141 170255 15 744550
Table 1.4: AMTS Operation Figures Source: AMTS Records
The above table shows the least ridership numbers in the year 2005 which is the record low ridership
since 1971. This reduction was due to problem areas mentioned above. AMTS invited private contractors
to operate the buses and was able to increase its ridership and fleet size. This restructuring and policy
revision has helped AMTS reach its existing level of 1022 buses (538 operated by private operators and
484 by AMTS) and ridership of 936,886 passengers (AMTS Annual Statement – 2008).
Regional transport is being provided by GSRTC (Gujarat State Road Transport Company). It provides
intercity and interstate transport service to Ahmedabad by connecting it to rest of the state and adjoining
states like Rajasthan, Maharashtra and Madhya Pradesh. It provides city bus service between Ahmedabad
– Gandhinagar and Ahmedabad – Vadodra.
Table 1.5: GSRTC Service to Ahmedabad Source: IPTS Study, Louis Berger
Sr. No. Location No. of Buses
1 Gandhinagar 330
2 Mehamdabad 179
3 Bareja 40
4 Kalol 330
5 Dehgam 217
6 Sanand 153
TERI University, New Delhi Parking Policy and Management - Ahmedabad
9
Its major terminal in the city at Geeta Mandir and several pick up points spread across the city carry
around 2 lakh (two-way) passengers daily. Being the only major terminal it faces acute congestion
problem in terms of parking and traffic movement. To resolve this problem it is planning to distribute the
operations at different locations throughout the city.
Railway is another mode of daily commute for trips made outside the city. It carried around 25,000 daily
commuters in 2000. It has its main junction at Kalupur with 12 platforms and connected by over 100
trainsv. Other station at Maninagar is a source of daily rail commuted trips. These two stations are well
connected by AMTS routes and intermediate public transport modes.
Intermediate public transport service like the shared auto rickshaw (commonly known as chakdaas)
operates on several same routes as the AMTS giving it tough competition. These rickshaws carry four to
six passengers and charge fares almost as same as AMTS. These rickshaws have a well designed informal
network and operate on six to seven routes in the city. Another mode is the intercity private bus service
that provides pick up point to point service in the urban and suburban region. These buses originate and
terminate at six to seven locations in the city.
Ahmedabad urban agglomeration has a total road network of 3650 Kms. (2007) excluding NH,
Expressway, State Highways (R&B Roads). Urban local roads are constructed and maintained by AMC
and AUDA. The city has ring radial road network with 20 radials, 12 in the west and 8 in the east
(Analysis of Physical Map – Ahmedabad 2007). The radials provide cross mobility between the radials
reducing the travel distance. Out of the total road network in Ahmedabad, AMC maintains a length of
2398 Kms. Roads in AMC cover only 7% of the land against desired level of 15-18%. Average road
width in the city is 12 m and maximum RoW goes up to 60 m Road density per sq.km. has reduced from
6.66 to 5.2 since 2001 owing to expansion of AMC limitsv.
Parameters 2000-01 2006-07
Surfaced Roads (km) 1187.1 1823.2
% Asphalt Roads 93.34 76.0
Un-surfaced Roads (km) 84.64 575
Total Length of roads (km) 1271.74 2398.2
Length of Road per sq.km. 6.66 5.2
Table 1.6: Roads in AMC Source: AMC Statistical Outline
Figure 1.7: Ahmedabad Road Network – 2011 Source: AUDA Development Plan
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
10
Based on a study by CRRI, Ahmedabad has more than 16 major roads with average road width ranging
from 12 to 60 M.
Sr. No. Road Name Avg. Road Width (Mt)
1 Ashram Road 40.28
2 Gandhi Road 12.19
3 Tilak Road 18.29
4 Astodia Road 19.81
5 Mirzapur Road 15.24
6 Gheekanta Road 12.19
7 Circular Road along fort wall
a) Gandhi Bridge to Tilak Road Junction
b) Tilak Road Junction to Sardar Bridge
24.38
8 Chandola Road 24.38
9 Shyam Prasad Road 24.38
10 Rakhial Road 18.29
11 Stadium Road 18.29
12 Satellite Road 60.96
13 Sarkhej Road 30.48
14 Circular Road (Sardar Bridge to Gandhi Bridge) 24.38
15 Circular Road (Usmanpura to Paldi) 36.58
16 Circular Road (New Vadaj to NH8) 40.28
Table 1.7: Major Road Widths Source: Study on Ahmedabad Transport System - CRRI
The city has 10 bridges that cross river Sabarmati and one is under construction. There are nine rail-over
bridges and five under passes. Traffic congestion in city is moderate with travel speed ranging from 10-24
km/hr.
1.5 Travel Characteristics
Travel Characteristics are defined as trip length, trip rate, geographical distribution etc. and are derived
through household survey characteristic like occupation, vehicle ownership, age, sex, income etc.
Socio-Economic characteristic of Ahmedabad shows that majority of the population (58%) is in the active
age group while less than 8% are old age citizens. Occupation distribution of the city shows that majority
of the people are engaged in business (13%) followed by private service (12%) and government job (4%)
respectively. Students and House wives amount to 51% of the total population and unemployed
TERI University, New Delhi Parking Policy and Management - Ahmedabad
11
population of the city is 4%. 15% of the population is engaged in activities other than the mentioned
above. The occupation data has been derived from GIDB – IPTS Study (2000). Household distribution by
income group shows that major portion of the population has household income less than 5000 Rs.
/month.
Income Range Percentage
<5000 38.5
5000-10000 29.1
10000-20000 18.3
20000-30000 8.8
>30000 5.3
Table 1.8: Household distribution by income group Source: GIDB Metro Study (2004)
This trend of income distribution shows that there is a large potential for provision and promotion of
public transport and bicycle travel. This brings into consideration of TOD (Transit Oriented
Development) for the city and thus developing its transport network accordingly. Vehicle ownership also
supports this pattern of income distribution.
Figure 1.8: Vehicle Ownership Distribution Source: GIDB Metro Study (2004)
Despite of the development in living standards large number of the households (31%) don‟t have
motorized or personal vehicle (GIDB – Traffic Study – 2005). This distribution shows that the city needs
to provide better infrastructure for cyclists and pedestrians in terms of footpaths, cycle tracks, public
transport systems etc. This distribution shows that there is a need to shift the 2 – wheeler volume by
developing the above mentioned infrastructure. With increase in purchase power and readily available
finance percentage of 4-wheelers and 2-wheelers is increasing.
23.00%
59.00%
10.00%
8.00%Vehicle Ownership Distribution
Bicycles
2 - Wheelers
Cars
No Personal Vehicle
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
12
In recent studies for BRTS by AMC, trip rates were found out to be 1.92 for trip defined as more than 500
Mt. Almost 80% of the walk trips were less than one Km. If all trips less than one Km. are excluded the
trip rate comes out to be 1.14, excluding walk trips is 0.99. Mode of travel and Trip Length is shown in
the following table.
Mode of Travel & Trip Length
Mode %age Avg. Length (Km)
Walk 13.2 2.2
Bicycle 18.8 3.3
2 Wheeler 35 5.4
Auto Rickshaw 8.8 4
4 Wheeler 3.1 6
Bus 15 6.2
Others 5.8 4.6
Table 1.9: Travel Characteristics Source: Ahmedabad BRTS – DPR (2008)
Majority of the trips generated are work and business trips up to 23% and 19% respectively. These two
are the major trips followed by business trips at 9.5% and other purpose trips at almost 5% while rest of
the trips are return trips. Average trip length for all the trips through all the modes (<1 Km) is 5.4 Km.
Bus and car trips are long distance trips while auto rickshaw and 2-wheeler trips are medium distance
trips. There also exists a correlation between mode of travel and age group by maximum walk trips less
than age 15 and more than age 50. The age group between this uses rest of the modes.
TERI University, New Delhi Parking Policy and Management - Ahmedabad
13
Chapter 2: About the Project
2.1 About the Subject
Parking is a situation when any vehicle is at rest and occupies a land space and is and integral part of any
roadway system. With rapid urbanization and growing number of vehicles, parking demand has been
increasing consuming large urban spaces. As mentioned earlier vehicular growth rate in the city has been
considerable causing supply and demands demand disparity of parking space. Parking has become an
integral part of our cultural requirement and an issue of global concern. Fast, safe and reliable mobility is
a concern along with parking in auto based landscape developments (TDM Encyclopedia, WTPI, July
2008). Urban spaces in Indian cities have started to adopt auto based landscape developments that
dedicate large area of usable space to parking lots. Parking facility is considered as a fringe benefit by
everyone, being supplied without cost. Contrary to an auto-oriented urban sprawl aim should be towards
sustainable development and better planned environments (David King et.al. 2007). It thus becomes a
challenge to regulate, supply and incorporate parking as a crucial parameter for such a development. A
big challenge to face this rapid growth in sustainable manner is to identify new ways to address the
parking needs simultaneously minimizing its negative impacts and encouraging better and different
design. Parking consumes huge amount of space that could be otherwise developed. We lose land in
surface and structured parking lots that create sterile, unattractive environments that deaden city and
suburban streets, further isolate uses and preclude lively pedestrian-friendly streets (Deren Han, 2009).
Ahmedabad is one of the fast developing cities in India and has enabled itself to compete in the race
of mega cities ranking. With addition of huge area into its jurisdiction the city is fast growing and so are
the infrastructure needs. The city hence is facing several challenges one of them being the parking space
issue. The study addresses parking issue at domestic/city level with policy measures to regulate spaces
being used for parking through fair management and pricing mechanisms.
Parking can be broadly classified into two major categories viz. On-street Parking and Off-street
Parking. The facility can be paid or offered as fringe benefit. Ahmedabad follows the GDCR norms for
parking regulation and development in the city structures. Various guidelines and standards are laid down
by the NUTP, SP-12, UDPFI, IRC etc. for parking and its management. Parking strategies need to be
based on several components primarily being the demand and supply elasticity, pricing mechanism,
management alternatives, socioeconomic characteristics, land use, mode of travel etc. Parking regulation
causes significant impact on two major areas of vehicle ownership and road space usage characteristics.
Parking supply can be provided through a variety of methods and pricing/subsidized mechanisms.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
14
2.2 Need for the Study
AMC territory has a total land area of 19,536 Ha (AUDA Master Plan – 2011) that contains different land
uses and varying parking demands. The city provides paid as well as free on-street and off-street parking
facilities. Existing road widths are not sufficient for different uses on major lengths in the city. Existing
roads carry pedestrian load, cyclist load, motorized vehicular load, street vendors load and parking load.
Apart from this other activities like use of roads for recreational activity by putting up tents and stray
cattle movement also demean the road landscape. The study focuses on parking issue and tries to derive a
solution on case by case basis along with policy recommendation applicable for the city. Following points
establish the need for this study.
1. Increasing in number of motorized vehicles and availability of parking space as fringe benefit
2. Reduction of accessibility and mobility in CBD (central business district) and major areas
3. Negative impact on quality of health and life due to increased pollution by addition of new
vehicles on road and use of single occupancy vehicles
4. Intervention in pedestrian movement and bicycle mobility due to on-street parking.
5. Reduction in use of public transport system and high level of use of single occupancy vehicle.
6. Increase in mixed land use practice leading to congestion in residential areas
7. Lack of availability of on-street or off-street parking spaces for work trips which are maximum in
number.
8. Reduction in average traffic speed, reduction in available effective road width, bottle necks and
accidents due to unsystematic parking practices on street.
9. Low level of usage of off-street parking lots and their poor designs.
10. Unavailability of institutional arrangement for regulating and enforcing parking law in the city
2.3 Objective and Scope of Study
Objective of the study is to provide the city with a parking policy design guideline through pricing
mechanism and management and design alternatives that would help the city administrative authority to
regulate and govern on-street (kerb side) and off-street (multi level or ground level) parking schemes in
the city. Objective areas of the policy include the following:
a. Improving the quality of public spaces for pedestrians and cyclists
b. Improvement in accessibility to CBD areas
c. To provide effective enforcement of parking regulation through better institutional arrangement
d. Reducing pollution, noise, and congestion by discouraging the use of private motor vehicles and
promoting public transport systems
TERI University, New Delhi Parking Policy and Management - Ahmedabad
15
e. Minimizing the use of personal transport mode through regulated pricing and diversion of revenue
collected for other infrastructure facilities.
f. Encourage efficient use of available parking spaces through regulated supply
It is however true that without motorized mobility the sustenance of any economy is difficult, the policy
shall aim at restricting the volume of vehicle and eliminate the extra unwanted demand. The study shall
not capture off-street parking data but remain restricted to on-street parking only.
Scope of the study is limited to design parking scheme for one case that comprises of pricing
mechanism and management plan. The study shall also deliver draft directives for a comprehensive
parking policy for the city of Ahmedabad. The extent of the study area in physical terms remains
restricted within AMC boundaries, however the policy and model can be applied to AUDA limits. The
policy and research shall only provide and be applicable to municipal land and not on private land.
2.4 Methodology
The study is broadly divided into three parts viz. a) Financial Model and Pricing Mechanism, b)
Management and Design Alternatives c) Draft Policy Directives
Study methodology comprises of a step wise sequence of studies as mentioned below:
i. Literature study in form of:
a. About the city demographics, traffic, land use and economy, transportation systems etc.
b. Case studies for on-street and off-street parking at domestic and international level
c. Pricing methods, Management alternatives, engineering options and policy analysis at
domestic and international level
ii. Identification of study area with construction of survey plan and data collection formats
iii. Site visits and phase-1* of primary data collection in form of data sheets and questionnaires
iv. Secondary data collection
v. Primary data analysis elasticity studies and representative indicators for modeling
vi. Selection of two cases and phase-2* of data collection
vii. Physical analysis of the area and parking lot alternative generation (on-street or off-street) by
checking technical feasibility
viii. Financial modeling and pricing model of technically feasible alternatives and elasticity
analysis
ix. Recommendations in form of draft policy directives to the administrative authority
x. Enforcement plan to curb ill effects like bribe, spill over etc.
Phase 1 – Volume counts, Road space inventory, Land Use survey, Phase 2 – Parking
duration, Questionnaire survey.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
16
Chapter 3: Literature Review
3.1 Parking Terminology (Khanna, Justo, 1979)
A Space-Hour: is a unit of parking that defines the use of a single parking space for a period of 1 hour.
Parking accumulation: is defined as the number of vehicles parked at a give instant of time. Normally
this is expressed by accumulation curve. Accumulation curve is the graph obtained by plotting the
number of bays occupied with respect to time.
Parking volume: is the total number of vehicles parked at a given duration of time. This does not
account for repetition of vehicles. The actual volume of vehicles entered in the area is recorded.
Parking load: gives the area under the accumulation curve. It can also be obtained by simply multiplying
the number of vehicles occupying the parking area at each time interval with the time interval. It is
expressed as vehicle hours.
Average parking duration: is the ratio of total vehicle hours to the number of vehicles parked.
Parking turnover: is the ratio of number of vehicles parked in duration to the number of parking bays
available.
This can be expressed as number of vehicles per bay per time duration.
Parking index: is also called occupancy or efficiency. It is defined as the ratio of number of bays
occupied in time duration to the total space available. It gives an aggregate measure of how effectively
the parking space is utilized. Parking index can be found out as follows
Parking duration = parking load / parking volume
Parking turnover = parking volume / no. of bays available
Parking index = (parking load / parking capacity) X 100
TERI University, New Delhi Parking Policy and Management - Ahmedabad
17
Figure 3.1: Parking bays and accumulation curve
3.2 Parking Norms for the city
For any type of development to come up in a city, there is a regulation which regulates it. These
regulations are called General Development Control Regulation .i.e. GDCR. General Development
Control Regulation is a document which regulates the total development of city. All cities do
not have a common GDCR. GDCR‟s vary from city to city, this is because the Regulations are developed
keeping in mind the general development of the city. In the GDCR, there is section named as Parking
Regulations/Norms which provides the guidelines for the provision of parking for various land-use
activities. A study of Parking Regulations of some cities is been carried out and its description is listed
below.
3.2.1 Parking Norms given by Indian Roads Congress (IRC-12)
Indian Roads Congress has given parking space standards which is applicable in entire India. The
Standards given by Indian Roads Congress are tabulated below:
No Land Use Parking Space Standard
1 Residential
(i)Detached, Semi-Detached row house
a.Plot area upto 100 sq.m
b.Plot area from 101 to 200 sq.m c.Plot area from 201 to 300 sq.m
d.Plot area from 301 to 500 sq.m
e.Plot area from 501 to 1000 sq.m
f.Plot area from 1001 sq.m and above
(ii)Flats
(iii)Special, costly developed area.
(iv)Multi-storeyed group-housing schemes.
No private or Community parking space is required. Only Community parking space is required.
Only Community parking space is required.
Min. one-third of the open area be earmarked for parking.
Min. one-fourth of the open area be earmarked for parking.
Minimum 1/6thof the open area be earmarked for parking.
1 space for every 2 flats of 50-99sq.m or more of floor.
1 space for every flat of 50-100 sq.m of floor area.
1.5 spaces for every flat of 100-150 sq.m of floor area.
2 space for every flat of above 150 sq.m of floor area.
1 space for every 4 dwelling except in cities like Calcutta and Bombay
where the demand may be more
2 Offices 1 space for every 70 sq.m of floor area 3 Industrial premises 1 space for upto 200 sq.m of initial floor area. Additional spaces at the
rate of 1 for everysubsequent 200 sq.m of fraction thereof.
4 Shops and Markets 1 space for every 80 sq.m of floor area.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
18
5 Restaurants 1 space for every 10 seats.
6 Theatres and Cinemas 1 space for every 20 seats.
7 Hotels and Motels
(i)5 and 4 star hotels
(ii)3 star hotels
(iii)2 star hotels
(iv)Motels
1 space for every 4 guest rooms.
1 space for every 8 guest rooms.
1 space for every 10 guest rooms.
1 space for each guest room.
8 Hospitals 1 space for every 10 beds.
Table 3.1: Parking Norms – IRC (Indian Road Congress)
When applying the above standards, the parking space requirement of a car can be considered as 3m x
6m when individual parking space is required and 2.5m x 5m when community parking is
envisaged. For 2-wheelers, a stall of size 0.8m x 2.5m is desirable vii
.
3.2.2 Parking Norms of Ahmedabad City
Ahmedabad Municipal Corporation (AMC) and Ahmedabad Urban Development Authority (AUDA)
have jointly developed the parking Norms or regulation for all types of land-use activities
taking place in Ahmedabad City. This Parking Regulations are a part of the General Development Control
Regulation (GDCR) of Ahmedabad. As per the section of Parking Regulations mentioned in the
GDCR of Ahmedabad the Minimum parking space regulations are given below. Off-street parking
spaces for vehicles shall be provided for every new building constructed for the first use or when the use
of old building is changed to any of the uses mentioned in the table below:
Sr.
No
Type of use Parking Space Required Remarks
1 Residential
(Flats/Apartments)
15% of maximum permissible
F.S.I
(1) Dwelling units Above 80 Sq.Mts
built up area 50% of the total parking
space requirement shall be reserved for cars.
(2) Upto 80 Sq. Mts. built up area 25%
of the total parking space requirements
shall be reserved for cars.
(3) 10% of the total parking space
requirements shall be reserved for
visitors at ground level.
2 Cinema theatre, public
assembly hall
auditorium, stadium etc.
1 Sq Mts. per seat 50% of the total parking space
requirements shall be reserved for cars.
3 Industrial 10% of Building Unit 50% of the total parking space requirements shall be reserved for cars.
TERI University, New Delhi Parking Policy and Management - Ahmedabad
19
4 Commercial and business
establishments including
business office, bank,
hotel,
guest house, lodge,
eating house, restaurant,
institutional building etc.
and Health facilities
including Hospitals & Nursing Homes etc.
30% of maximum permissible
F.S.I
Note :
(1) The parking space so required
shall be provided excluding
required marginal space and Built
up area with solid plinth subject
to other regulation
(2) 20% of the parking space required at the ground level shall
be exclusively provided for
visitors.
50% of the total parking space
requirements shall be reserved for cars.
5 Community buildings
such as community hall/
marriage hall/
community wadi/
recreational club/ and
religious building, party
plot, club house etc.
50% of Building Unit. 50% of the total parking space
requirements shall be reserved for Cars.
6 a) Primary schools.
b) Secondary and higher
secondary schools
(c) Colleges and
coaching classes.
20 Sq. Mts. for every 100 Students.
50 Sq.Mts. for every 100 students
70 Sq. Mts. for every 100 students
For computing number of students 0.75 sq. mts. floor area is equal to 1 (one)
student.
7 Special building for
uncommon uses :
(a) stock exchange
(b) Grain market, timber
market, iron market, agricultural market, and
such other wholesale
Trade.
For (a) and (b) 30% of maximum
permissible F.S.I
For (a) 50% of the total parking space
requirement shall be reserved for cars.
For (b) 50% of the total parking space
requirement shall be reserved for heavy
motor vehicles.
Competent Authority/Municipal
Commissioner shall specify the number and types of vehicles likely to be use in
addition to Col. No. 4
For (a) and (b) of col. No.2
Table 3.2: Parking Norms - GDCR
3.3 Defining Parking Problems and Solutions
Parking problems are often defined to mean that motorists consider parking inadequate, inconvenient or
expensive. This implies that the best solution is to increase parking supply without directly charging
users. But there are other ways to define parking problems that suggest other parking solutions. Parking
problems may reflect:
Inadequate information for motorists on parking availability and price. The solution could be to
improve use information.
Inadequate user options. The solution could be to improve parking options, such as letting motorists
choose between convenient, priced parking and less convenient, free/inexpensive parking.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
20
Inconvenient Parking Pricing methods, such as mechanical meters that require users to predict how
long they will be parked and only accept certain coins (Ian Maher, 2002). The solution could be to
improve pricing systems.
Excessive automobile use. The solution could be to reduce Automobile Dependency and encourage
transportation alternatives. Concerns over spillover parking congestion in nearby areas if parking
supply is inadequate or priced. The solution could be to provide parking management and
enforcement in impacted areas.
Economic, environmental and aesthetic impacts of parking facilities. The solution could be to reduce
parking supply and improve parking facility design (Donald Shoup, 2001).
3.4 Evaluation framework and criteria
An evaluation framework specifies various details of an evaluation process. Evaluation Criteria refers to
factors that should be considered while evaluating the parking problems and solutions. Some important
criteria are discussed below:
a. Demand and adequacy
Parking Demand refers to the amount of parking that would be used at a particular time, place and price.
It is a critical factor in evaluating parking problems and solutions. Parking demand is affected by vehicle
ownership, trip rates, mode split, duration (how long motorists park), geographic location (i.e.,
downtown, regional town centre or suburban), the quality of travel alternatives, type of trip (work,
shopping, recreational), and factors such as fuel and road pricing.
There are usually daily, weekly and annual demand cycles. For example, parking demand usually peaks
on weekdays at office buildings and on weekend evenings at theatres and restaurants. Parking demand
can change with transportation, land use and demographic patterns. For example, a particular building
may change from industrial to residential or office use, neighbourhood demographics and density may
change, and the quality of transit service may change, all of which affects parking demand.
Different types of trips have different types of parking demand, and different types of parking facilities
tend to serve different types of trips. For example, commuters need long-term parking, and because they
park all day they are relatively price sensitive. Many commuters are willing to walk several blocks for
cheaper parking. Off-street parking leased by the month tends to serve commuters. Customers need
shorter-term parking that is located as close as possible to their destination, and are often willing to pay a
relatively high hourly price for increased convenience. On-street parking that is metered or regulated to
maximize turnover tends to serve customers.
TERI University, New Delhi Parking Policy and Management - Ahmedabad
21
Adequacy refers to whether there is sufficient parking at a particular time and location. What constitutes
adequacy varies depending on conditions and user expectations. For example, even in dense areas parking
is usually adequate during off-peak periods, or at a sufficient price. Similarly, parking may be considered
inadequate at a particular location, but is available a few blocks away. Unregulated parking it may be
adequate for residents and employees, who park early in the day, but inadequate for delivery vehicles,
customers and clients who arrive later. Conversely, parking with a 2-hour or less time limit, or is priced,
may be considered adequate for short-term users but inadequate for employees and residents who must
park all day.
Parking regulations often reflect an 85th percentile demand standard, which means that 85 out of 100 sites
will have unused parking supply even during peak periods xi. These standards tend to be excessive for
more accessible conditions, priced parking, where other TDM strategies are implemented, or where
parking facility costs are high.
Other factors include (Barbra J., 2001):
a. Consumer impacts
b. Equity impacts
c. Economic development impacts
d. Transportation and land use
impacts
e. Facility design
f. Parking facility costs
o Land
o Construction costs
o Operation and maintenance
o Transaction costs
o Environmental costs
o Total costs
o Load factor
3.5 Impact of parking
Parking Policy has a direct impact on vehicular ownership and road space use. However, there are some
ill effects of parking which are as follows:
1) Congestion
One of the serious ill-effects of parking is the loss of street space and the attendant traffic congestion. The
capacity of the streets is reduced, the journey speed drops down and the journey time and delay increases.
The operational costs of vehicles are thereby increased, causing serious economic loss to the community.
Due to 9 ECS on street parking the delay is increased by 3.37%, stops are decreased by 2.29%, and fuel
consumption is increased by 1.1% at the network level (Poole, 2007).
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
22
2) Accidents
The manoeuvres associated with parking and unparking are known to cause road accidents. Careless
opening of the doors of parked vehicles, moving out of a parked position and bringing a car to the parking
location from the mainstream of traffic are some of the common causes of parking accidents.
3) Obstruction to fire-fighting operations
Parked cars obstruct the movement of fire-fighting vehicles and greatly impede their operations. They
also block access to hydrants and to buildings.
4) Environment
Parked vehicles degrade the environment of the town centre. Stopping and starting of vehicles results in
noise and fumes. On-street parking tends to increase the air pollution levels in the congested streets due to
reduction in the capacity of streets. Vehicular emissions are of particular concern, since these are ground
level sources and thus have the maximum impact on general population.
In spite of the above ill-effects, parking has to be allowed on the streets or off the streets close to the
user‟s destination. The well-being of the community and the town centre demands that great thought
should be bestowed on the parking needs and how to best fulfil them.
3.6 Best Practices
3.6.1 Domestic on-street parking scheme
Parking management strategy for the Walled city of Jaipur (Jaipur Parking Demand Management
Study by CRRI - 2006)
This city does not have parking policy in place but has proposed development of several multi storey
parking lots to overcome congestion problems. Identified problem areas in the city are:
a. Unorganized parking spaces
b. On street parking spaces encroached by vendors and shoppers
c. Absence of planned spaces
d. Parking projects have come up but not a policy
e. Lack of enforcement
The Jaipur Development Authority (JDA) concerned with the growing demand for parking and the related
problems, (i.e., traffic circulation, congestion etc), requested the Central Road Research Institute, New
Delhi, to study the parking problems and suggest policies and schemes of management.
TERI University, New Delhi Parking Policy and Management - Ahmedabad
23
The scope of the study was restricted to Kishanpole bazaar in the west, Tripolia bazaar in the north, Mirza
Ismail Road (M I Road) in the south and Johari bazaar in the east
Objective and Scope Of The Study
The study was taken up with the following objectives:
Assess the parking demand and characteristics of the study area;
Assess the traffic operating conditions on the major roads within the study area;
Project the parking demand of the future;
Explore the possibilities of augmenting the parking spaces; and
Develop parking management schemes and policies to meet the parking demand of the present
and future.
Field Studies
With a view to assess the existing parking demand, parking supply, traffic volume and traffic speed on
major roads and related data was collected by carrying out field surveys, namely,
traffic volume survey;
speed and delay survey of traffic;
parking duration and accumulation surveys;
users opinion survey;
inventory of regulatory measures of parking; and
Inventory of parking spaces.
Existing Parking Supply: Kerbside parking is allowed on all the road sections in the study area and can
accommodate a total of 2645 ECS.
Projection of Parking Demand
The growth in parking demand is directly related to growth in activities located in the study area coupled
with increase in vehicle ownership in the city besides economic status of the people visiting the area.
Parking demands have been projected separately for cars and two-wheelers for the year 2001 and 2011
AD.
Recommended Strategies and Policies
The parking space available can cope with only two-third of the present demand and the projected
parking demand is much higher. Presently no parking fee is being charged for kerbside parking. In the
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
24
absence of parking fee the user can move from one parking lot to another thus creating avoidable demand.
Therefore, it is proposed to introduce parking fee in some of the areas. This will moderate parking
demand and also act as deterrent to the growth of parking demand up to certain time period. With the
continuous increase in economic status of the residents, the parking demand is bound to increase.
Therefore, there is a need to evolve strategies to meet the growing demand through demand management
and capacity augmentation.
i. Proposed fee and expected revenue :
The parking Fee is categorised in two sections with four wheelers and two wheelers as the modes. The
total revenue has increased from Rs. 19 to 30.78 miliion in the period 1996 -2001. it is expected to
increase upto Rs. 341.10 million By 2010.
ii. Cost of developing off street parking facilities and net revenue:
a. Area covering Ramnivas garden and Ajmeri gate requires Rs. 90 millions for development
and net revenue comes upto Rs. 98 millions.
b. Area covering Ram leela Ground , Sanjay Market , Old Pension office premises and Near
Rajastahn Ch of commerce requires Rs. 161 millions for development and net revenue comes
upto Rs.240 millions.
c. Area covering Choti Chaupur and Badi Chaupur requires Rs. 100 millions for development
and net revenue comes upto Rs.195 millions.
Thus, the revenue generated from parking fee was proposed to be earmarked as „parking fund‟ to be used
for capacity augmentation through private sector participation. Using this revenue an additional 2200
ECS of off-street parking facility was proposed to be developed at different locations in order to satisfy
the growing demand. It was shown that by streamlining the existing parking facilities and implementing
appropriate parking and management policies could provide better facilities for the users and at the same
time reduce the burden on local governments.
3.6.2 Domestic off-street parking scheme
Hyderabad International Airport Parking Policy (Tenega Parking Pvt. Ltd. – Managemetn Study of
APMS at Hyderabad International Airport)
o In line with its commitment to bring world-class services to Hyderabad, the New Hyderabad
International Airport in Shamshabad has been set in motion by setting up an Automated Parking
Management System (APMS) at the airport premises.
TERI University, New Delhi Parking Policy and Management - Ahmedabad
25
o The Parking Management System will be managed by Tenaga Parking (India) Private Limited, a
part of the Malaysia-based Tenaga Group. The company will take care of the Parking
Management in the new airport for a period of three years, which can be extended further on
mutual agreement.
o As per the contract, GHIAL will develop the car parking facility with necessary equipment,
technology including surfacing of entire car park area, internal roads, marking, signage,
landscaping, provision of utilities like electricity , water etc.
o Tenaga Parking (India) Pvt. Ltd, for its part, will perform, implement and execute the
Management Services for efficient and customer friendly management of the Parking Facility.
The features of the parking management in the new airport are:
Automated service which facilitates No Queuing and No Waiting by introducing the „Touch &
Go‟ concept
Traffic management of the car parking area for customers and other services in front of terminal
building comprises over 3500 car bays.
Traffic management of the parking area in front of Cargo terminal building comprises around 153
Two-Wheeler bays, 125 car bays, 30 truck parking bays and Dock parking bays.
Kerbside management at departure and arrival level includes VIP and VVIP Movement,
Taxi‟s/Cabs and Shuttle Buses
Valet Services
Management of public transport system like auto rickshaws, pre-paid taxi‟s, fleet taxis, buses,
government and staff vehicles in the parking area
The parking charges are as follows:
1. Car Parking Tariffs
a. Rs.70.00 for first two hours
b. Rs.110.00 for subsequent 2 to 3 hours
c. Rs.30.00 for each subsequent hour or part thereof
d. Rs.250.00 for 24 hours
2. Cargo Truck Parking
a. Rs.100/- for first 2 hours
b. Rs.50/- for each subsequent hour
3. 2-Wheeler Parking
a. Rs. 15/- for first 2 hours
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
26
b. Rs.10/- for each subsequent hour or part thereof
c. Upto a maximum of Rs. 100/- per 24 hours
Apart from the above mentioned details there does not exist any policy that guides the parking scheme.
Following is the site map that shows mobility plan and parking lot schematics.
Figure 3.2: Hyderabad Airport Parking Design
3.6.3 International on-street parking scheme
Perth Parking Policy (Perth Parking Policy, 1998)
The policy has been developed by the state government in consultation with the city of Perth.
Objectives of the policy include:
Ensure the continued economic vitality of the City of Perth.
Improve accessibility to, and within the city, for all users.
Improve the air quality and the physical environment of the city.
Keep the impacts of vehicular traffic within acceptable limits.
Encourage the efficient use of parking facilities in the policy area.
Provide a framework for the development of parking facilities within the city.
Principles adopted to achieve the objectives are:
TERI University, New Delhi Parking Policy and Management - Ahmedabad
27
An adequate range of parking facilities in regard to demand, availability of public transport, road
capacity, traffic flow, land use and environmental conditions.
Pedestrians will have priority; surrounding the pedestrian heart the emphasis will be on the provision
of short term parking. New public long term car parks may be located outside of the central area.
The level of desirable tenant parking will vary according to the category of street from which such
facilities take access; the general principle is that allowances are lower where access has greater
detrimental impact on pedestrian movement.
Parking facilities should complement their surroundings and provide a convenient service without
causing undue disruption or loss of amenity to surrounding uses.
Off street parking areas should be located and designed so they are an integral part of the
development of the site. Disabled and cycling parking facilities should be visible and conveniently
located
Policy Provisions
The provisions governing the establishment of parking facilities within the policy area break down into:
1. Public parking
a. Short-stay public parking facilities – at least 50% of vehicles stay less than 4 hours; and at least
90% stay less than six hours
b. Long-stay public parking facilities – for use without time constraints
This policy establishes three parking zones;
Pedestrian – priority zone(PPZ)
Short – stay parking zone(SPZ)
General parking zone(GPZ)
2. Tenant parking: is parking available, generally on site, for the exclusive use of tenants/occupants of
city commercial buildings.
Evaluation criteria for parking facilities:
The impact that the proposed parking facility would be likely to have on the amenity of the
environment within the Perth Parking Management Area.
The availability of public transport in the vicinity of the proposed parking facility.
The impact of the facility on traffic flows within the area.
The impact that establishing and operating the parking facility would have on pedestrian movement in
the vicinity of the facility.
Special provisions included for:
Residential Parking
Events Parking
Disabled people parking
Bicycle Parking
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
28
Special Purpose bays Combined Parking
3.6.4 International off-Street parking scheme
Hamilton Employee Parking (Extracts from the policy document)
This policy applies to all city employees (All city employees, including but not limited to permanent,
temporary and contract employees, and students, interns, and volunteers.) except those who have specific
parking provisions in their collective agreements. This policy encourages alternative forms of commuting
to work.
Employees have been given exemption to use private vehicle to perform their duties that needs travelling
as a part of their routine activity. Care has been taken to check contravention of the policy with any other
acts, laws, legislations etc.
Mission Statement:
A self-sustaining business unit, financed entirely by its users, which manages the life-cycle of the
municipal parking system - from planning, design and construction, to operation, maintenance and
enforcement - in support of the residential and business communities, and the City's Land Use,
Transportation and Economic Development initiatives.
Profile of the system:
Hamilton Municipal Parking System (HMPS) is committed to providing a wide variety of programs and
services and is responsible for the life-cycle management of the municipal parking system from planning,
design and construction to operations, maintenance and enforcement.
Parking enforcement
Parking fine inquiries and payments
Parking ticket reviews and adjudication
Towing
Private property enforcement
School Crossing Guards
Parking Operations
Parking Operations operates and maintains all municipal parking facilities and administers parking
regulations and programs with following services:
Management and operation of the City's Municipal Car Parks
TERI University, New Delhi Parking Policy and Management - Ahmedabad
29
Commercial and Residential Kerbside parking programs
Enactment/implementation of all on-street parking regulations
Disabled Parking Program
On-Street Parking Programs
Enactment/implementation of all alleyway parking regulations
Parking By-laws administration and maintenance
Special Event Parking
3.7 Parking surveys & Definitions
The type of parking survey to be conducted for formulating a comprehensive parking plan for an area can
be very detailed in scope. The data collected and the degree of sophistication employed depends upon the
funds available.
The following are the types of parking surveys usually conducted:
1. Parking space inventory survey
2. Parking usage survey by patrol (Khanna, Justo, 1976)
3. Questionnaire type parking usage survey
4. Cordon count survey
3.7.1 Parking Space Inventory Survey
The first step in a parking survey is to collect data on the amount, type and location of space actually or
potentially available for parking in an area. The area to be surveyed should first be delineated. The study
area can be a street or an area covering a numbers of streets. The study area is then sub-divided on a
street-by-street basis and the sub-division marked on a map. Sketch plans of the streets are then prepared
in advance. The data on parking facilities should be recorded on the sketch plans using suitable symbols.
The items to be recorded should include the following:
i. Total length of kerb and lengths governed by no waiting and limited waiting restrictions (TDM
Encyclopedia, 2008).
ii. Number of parking spaces provided in the street and street width.
iii. Location of bus stops, bus-bays, pedestrian crossings, fire hydrants, loading zones, taxi stands,
driveways and other features that are likely to affect the use of the street for parking.
iv. Number and type of traffic signs for regulation of parking.
v. Private streets, service and rear-access alleys.
vi. Vacant or unused land suitable for temporary or permanent parking space.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
30
Off-street parking facilities should be recorded separately, indicating the type, capacity, parking charges,
parking pattern, entrances and exits.
3.7.2 Parking Usage Survey by Patrol
Purpose
The purpose of parking usage survey is to obtain data on the extent of usage of parking space. The survey
will include counts of parked vehicles at regular intervals through a period, covering both the morning
and evening peak period, and the parking accumulations and turn over.
The survey can be for on-street and off-street parking. The general methodology for both the surveys is
similar, though minor details can be different. The method consists of making periodic observations of
parked vehicles on each patrol. For off-street observations, the entire parking space can be patrolled or,
alternatively, the entrances and exits may be observed continuously.
Mapping the street system
The first step is to prepare a map of the street system that will be covered by the patrol, showing therein
its sub-division in to sections. Street junctions make convenient points for determining the sections. The
recording can be for both sides of the road or separately for each side. The map and the forms should
clearly show the direction of travel by the patrol-man and the side or sides where observations are to be
recorded (by arrows).
Frequency of patrol (Khanna, Justo – 1976)
Though more frequent patrols result in more accurate data the field work and subsequent analysis
becomes more tedious. A frequency of ½ an hour is considered to be satisfactory for on-street parking,
while a frequency of 1 hour could be used for off-street parking. A frequency of ½ an hour likely to miss
short-term parkers (up to 29 minutes duration) and this makes it necessary to have more frequent patrols
in selected areas where short-term parking may be significant, e.g., near banks, post offices etc.
Method of observation
Usually patrols are by foot, but where vehicles are not parked, too close to one another a moving car may
also be used. As an aid, a tape recorder may be used to record the registration number of vehicles. If the
proportion of the short-term parker is more then only in and out of the vehicles are noted to have a more
realistic picture of parking demand.
TERI University, New Delhi Parking Policy and Management - Ahmedabad
31
Timing of survey
The survey should be done on a typical week day, free from factors likely to result in non-representative
characteristics. The period of the survey is usually 10 to 12 hours, so as to cover the arrival and departure
of commuters and shoppers.
3.7.3 Questionnaire Type Parking Usage Survey
The questionnaire type parking usage survey involves interviews with the drivers who use the parking
facilities. As a result, it is possible to collect information on the extent, to which the existing facilities are
being used, the parking requirements at the prices existing at the time of the survey, the parking demand
at different prices, the distribution of demand over area and time and the journey purposes of car parkers
(Economic Survey of Delhi – 2005-06).
The survey can either be made by making enquires among the vehicle owners living in the vicinity of the
survey area, or by making enquires among the drivers of vehicle seen to park in the area at the time of the
survey. In the former method, a sample of vehicle owners is selected from the list of vehicle owners and
the questionnaires are delivered to them. Non-respondents can be followed up and the requirements of the
sample are grossed up to the requirements of the whole population. The second method suffers from a
disadvantage that it misses information about potential parkers who never bring their vehicles to the
survey area for want of space, but this can be overcome by a supplementary sample.
In this interview of actual parkers, the information collected should include:
(i) Address of origin of the trip
(ii) Address of destination of the trip
(iii) Trip purpose
(iv) Time of arrival at the parking place
(v) Time of departure from the parking place
(vi) Type of parking space used
(vii) Type of vehicle
Normally one interviewer is required to cover about fifteen spaces. All the parkers in 8 or 10 hours period
are interviewed. The duration of the survey may be a single day (working day) or may spread over a
number of days.
3.7.4 Cordon Count Survey
In this method, the area to be surveyed is demarcated by a cordon line which is crossed by the roads
emanating from the area. Counting stations are established at these crossing points and a count is made of
all the vehicles entering and leaving the area (Khanna, Justo – 1976). The difference between the top
traffic gives the number of vehicles parked or in motion in the area. The counting can be manual or
automatic.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
32
3.8 Design and Technology Alternatives
3.8.1 Common Methods of On Street Parking/ Kerb Parking
Kerb parking facility may be either unrestricted or restricted type. The restricted kerb parking may either
be controlled by police or by metres and a certain fee is collected from those who park their vehicles for
certain duration of parking time.
Angle parking or parallel parking may be allowed in the kerb parking. Angle parking may be at angles
30, 60, or 90 degrees. Angle parking accommodates more vehicles per unit length of kerb and maximum
vehicles that can be parked are within an angle of 90 degrees (Khanna, Justo – 1976). The width of road
required for parking and non-parking manoeuvre also is more with angle parking and it increases with the
parking angle up to a maximum at 90 degrees. Angle parking is more convenient for the motorists than
the parallel parking, but it produces much more obstruction through traffic, resulting in more accidents
than the parallel parking. Out of various angles used in angle parking 45 degree angle is considered the
best from all considerations as discussed above.
Parallel parking is generally preferred when the width of kerb parking space and the width of the street
are limited. But the parking and non-parking operations are more difficult because of the need for a few
forward and reverse movements before parking properly or before taking out. Parallel parking may be
with equal spacing, facing the same direction or may be two cars placed closely with open interval
between two- car units, as shown in the figure below.
Figure 3.3: Parking Patterns
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
33
3.8.2 Types of Off Street parking facilities
On-street parking can only solve a part of the parking problem of major cities. For a satisfactory answer,
various types of off-street facilities become unavoidable. The types of off-street parking facilities
commonly considered are:
I. Surface car parks
Surface car parks, properly located and developed on a piece of vacant land or surrounding an office
complex or super market are very popular among the motorists. Great care is required in their design and
operation. The overall aesthetics of the area should receive due attention. A stall size of 2.5m x 5m is
probably adequate for Indian conditions predominated by small size cars, whereas for American
conditions 2.6m x 5.5m is recommended (Deren Han, 2009). If the surface parking is to be operated with
a fee-charging system, there should be arrangement for collecting the money. This can be done either
manually by stationing an attendant in a kiosk at the entrance.
II. Multi-storey car parks
Surface parking consume too much of the precious land in the heart of the city and are not, therefore,
always feasible. One of the alternatives when land is costly is to provide multi storey car parking. Such
facilities have become common and popular in many cities. Multi-storey car parking is generally designed
for a capacity of about 400 to 500 cars. Larger capacity tends to increase the time for exiting a car. About
five floors is also the upper limit for the same reason.
A multiplex was unveiled at Nariman Point in Mumbai on 20th October, 2004. The multiplex is having a
capacity of 1250 seats. The Complex is having 10 floors. Out of which 8 floors are used for car parking.
The car parking facility can accommodate 500 cars (TDM Seminar Proceedings – 11th May 2006,
MESN). Ahmedabad is having one multi-storey parking facility on Relief road.
III. Roof parks
A very popular method of solving the parking problems adopted in many cities is to park the vehicles on
roof tops. Access ramps or mechanical lifts provide the necessary access to the roofs. To economise,
many roofs may be linked together served by a single access ramp. An extensive system of linked car
parking at roof level, integrated with multi-storeyed parking garages is in use at Coventry, U.K (David
Han, 2007).
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
34
V. Underground car parks
The great advantage of underground car parking is the least intrusion they cause to the aesthetics of a
place (Donald Shoup, 1999). An excellent example is the underground parking space below Hyde Park in
London and in Connaught Place, New Delhi. Apart from this, the Crossroad shopping complex in
Mumbai is having underground car parking facility. This parking facility can be constructed in the
basement of any multi-storeyed building or below open spaces. Since the work involves large quantities
of excavation, construction of retaining walls, ventilation and lighting, such car parking tends to be very
costly.
3.5 Parking management Strategies
Parking Management includes a variety of strategies that encourage more efficient use of existing parking
facilities, improve the quality of service provided to parking facility users and improve parking facility
design. Parking Management can help address a wide range of transportation problems, and help achieve
a variety of transportation, land use development, economic, environmental objectives. The various
strategies are (Donald Shoup – 1999, TDM Encyclopaedia 2008):
Establishing a parking plan
Limit parking supply
Prioritize use
Regulate the parking facilities for
efficiency
Impose parking prices
Tax parking facilities or their use
Shared parking
More accurate parking requirements
Address spill over problems
Parking maximums
Allowing “in-lieu ”fees as an alternative
to onsite parking
Bicycle parking
Unbundle parking
Transportation Management
Association(TMA)
Developing overflow parking plans
The following table summarizes these parking management strategies, indicates their typical reduction in
parking requirements, and whether they tend to reduce vehicle traffic and therefore provide additional
benefits (such as reductions in congestion, accidents, energy consumption, pollution emissions and
consumer costs).
Strategy Description Typical
Reduction
Shared Parking Parking spaces serve multiple users and destinations. 10-30%
Parking
Regulations
Regulations favor higher-value uses such as service vehicles, deliveries,
customers, quick errands, and people with special needs.
10-30%
More Accurate
and Flexible
Adjust parking standards to more accurately reflect demand in a
particular situation.
10-30%
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
35
Standards
Parking
Maximums
Establish maximum parking standards. 10-30%
Remote Parking Provide off-site or urban fringe parking facilities. 10-30%
Smart Growth Encourage more compact, mixed, multi-modal development to allow
more parking sharing and use of alternative modes.
10-30%
Walking and
Cycling
Improvements
Improve walking and cycling conditions to expand the range of
destinations serviced by a parking facility.
5-15%
Increase Capacity
of Existing
Facilities
Increase parking supply by using otherwise wasted space, smaller stalls, car stackers and valet parking.
5-15%
Mobility
Management
Encourage more efficient travel patterns, including changes in mode, timing, destination and vehicle trip frequency.
10-30%
Parking Pricing Charge motorists directly and efficiently for using parking facilities. 10-30%
Improve Pricing
Methods
Use better charging techniques to make pricing more convenient and cost effective.
Varies
Financial
Incentives
Provide financial incentives to shift mode, such as cash out. 10-30%
Unbundle Parking Rent or sell parking facilities separately from building space. 10-30% Parking Tax
Reform
Change tax policies to support parking management objectives. 5-15%
Bicycle Facilities Provide bicycle storage and changing facilities. 5-15% Improve User
Information and
Marketing
Provide convenient and accurate information on parking availability and
price, using maps, signs, brochures and electronic communication.
5-15%
Improve
Enforcement
Insure that parking regulation enforcement is efficient, considerate and
fair.
Varies
Transportation
Management
Associations
Establish member-controlled organizations that provide transport and
parking management services in a particular area.
Varies
Overflow Parking
Plans
Establish plans to manage occasional peak parking demands. Varies
Address Spillover
Problems
Use management, enforcement and pricing to address spillover
problems.
Varies
Parking Facility
Design and
Operation
Improve parking facility design and operations to help solve problems
and support parking management.
Varies
Table 3.3: Parking management strategies (Donald Shoup-1999, TDM Encyclopaedia, EPCA Report 2008)
3.6 Parking Pricing Mechanism
Parking Pricing means that motorists pay directly for using parking facilities. Parking Pricing may be
implemented as a TDM strategy (to reduce vehicle traffic in an area), as a parking management strategy
(to reduce parking problems in a particular location), to recover parking facility costs, to generate revenue
for other purposes (such as a local transportation program or downtown improvement district), or for a
combination of these objectives. Below are specific Parking Pricing techniques:
Wherever possible, charge motorists directly for using parking. If parking must be subsidized, offer
comparable benefits for use of other travel modes, such as Cash Out payments (Poole, 2007).
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
36
Use variable rates that are higher for peak locations and times. Apply performance-based parking
prices, which mean that prices are set so that about 15% of parking spaces are unoccupied during
peak periods (Barbra J., 2001).
To increase revenues, expand when and where parking is priced rather than raising rates at existing
priced facilities. This is more efficient and equitable, reduces spillover problems, and usually raises
more total revenue.
Set parking prices to equal or exceed transit fares. For example, set daily rates at least equal to two
single transit fares, and monthly rates at least equal to a monthly transit pass.
Minimize discounts for long-term parking passes. For example, set daily rates at least 6 times the
hourly rates, and monthly rates at least 20 times daily rates. Even better, eliminate unlimited-use
passes altogether (Deren Han, 2009).
Unbundled parking from housing, so apartment and condominium residents pay only for the
parking spaces they need (Location Efficient Development) (TDM Encyclopedia).
If parking must be subsidized, use targeted discounts and exemptions, rather than offering free
parking to everybody and allow motorists to lease on-street parking spaces (Solomon, 1995).
Tax parking spaces, and encourage or require that this cost be passed on to users. Reform existing
tax policies that favour free parking. For example, tax land devoted to parking at the same rate as
land used for other development.
Price on-street parking in residential neighbourhoods. Create Parking Benefit Districts, with
revenues used to benefit local communities. (Shoup, 1995).
Use TDM Marketing and other information resources to provide information on parking prices and
availability, and on alternative travel options and use revenues to fund transportation programs.
(http://www.vtpi.org )
3.9 Policy Study
Parking management when combined with appropriately priced parking, limit on parking space and
improved access through other modes of transport, it is most effective in stimulating the switch from
private cars to alternative modes of transport. There is, therefore, considerable opportunity to develop
parking policy as an instrument to decongest, shift commuter choice towards public transport, and
discourage car use.
Objectives of Parking Policy
Demand Management Revenue generation
Reducing congestion
Reducing pollution
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
37
Support of economic development
Support of mode shift to public transport
Factors Considered during the parking Policy (Perth Parking Policy 1998, Poole 2009)
Area
o Characteristics of the area
o Use of mode
o Land use and density
o Characteristics of retail and
employment
Implementation
o Stakeholder involvement
o Parking information
o Analysis
o Best practice
o Monitoring
Contents of Parking Policy
Figure 3.4: Parking Policy Contents
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
38
Chapter 4: Data Collection and Analysis (Nirav, Ambika)
4.1 Study Area Delineation & Case Selection
The study area is confined within the AMC limits that extend up to Sardar Patel ring road as shown in the
road network map below. The city has more that 21 major roads as listed in the table. Land use on these
roads includes residential, commercial, industrial and mixed land use categories. The table lists the names
and available RoW of these roads.
Sr.
No.
Road Name RoW
(Mt.)
Major Land Use
1 Narol-Naroda Road (Jashodanagar to Rabari Colony) 60 Industrial, Commercial
2 Maninagar Station Road (Kankaria to Railway
Station)
22 Commercial, Residential
3 Bhairavnath Road 23 Residential, Commercial
4 Ashram Road 40 Commercial, Institutional
5 Gandhi Road 21 Commercial, Residential
6 Astodia Road 28 Commercial, Residential
7 Mirzapur Road 20 Commercial, Residential
8 Gheekanta Road 23 Commercial
9 Relief Road 21 Commercial
10 Chandola Road 40 Industrial, Commercial
11 Rakhial Road 35 Commercial, Industrial
12 Stadium Road to Sola Village 36 Residential, Commercial
13 Satellite Road 60 Residential, Commercial
14 SG Highway (Sarkherj to Sola) Commercial, Residential
15 120‟ ring road (Usmanpura to Paldi) Commercial, Institutional
17 Gurukul Road 26 Commercial, Residential
18 Drive – In road Commercial, Residential
19 Judges Bungalow Road 35 Residential, Commercial
20 Nehrunagar to SG Highway 45 Commercial, Residential
22 CG Road 28 Commercial
23 Netaji Road (Law garden Road) 23 Commercial, Institutional
Table 4.1: Major Roads of the City
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
39
The table shows major land use for each street with the approximate available RoW that carries all the
traffic, parking, pedestrian and other classes. Six cases have been selected that makes 27% sample size
representing the population of listed major roads. Industrial land use has not been taken into account for
case study selection because these areas don‟t experience motorized on-street parking as seen in rest of
the cases. Streets with industrial land use experience bicycle parking more than motorized vehicle
parking. Selected cases represent the present trend of land use, socio-economic and physical design
characteristics.
Sr.
No.
Road Name RoW
(Mt.)
Length of Survey
(Mt.)
1 Maninagar Station Road (Kankaria to Railway Station) 22 1650
2 Ashram Road (Usmanpura to Delite Junction) 40 1860
3 Relief Road (Circuit House to Kalupur Railway Station) 21 1984
4 SG Highway (ISKON to Gurudwara) 2290
5 Gurukul Road (Gurukul to Subhash Chowk) 26 725
6 CG Road (Panchvati to Stadium Cross Road) 28 2100
Table 4.2: Case for Parking Survey (Primary Data – Phase-1)
The selected cases are different from each other in terms of land use, physical land space distribution,
socio-economic characteristics, RoW, parking space inventory etc. Total road length covered by the
survey is 10 Km. (approx.) that captures parking statistic representing major city streets. Maninagar
Station road has a mixed land use characteristic with moderate density of street facing structures.
Majority of the buildings on this street are up to a height of G+2 dominated by retail business. Ashram
road is the major commercial street of the city with major office space followed by commercial
establishments. The street has buildings up to a height of G+ 10 level. Gurukul road has fairly similar
characteristics as that of Maninagar with mixed use buildings (residential + commercial) and experiences
similar parking load. The street has buildings with average height up to G + 3 level with almost no
parking space for commercial/work trips. Relief road is on of the busiest commercial street of the walled
city with densely placed buildings and wholesale commercial activity. Average floor height on this street
goes up to G + 2 level with minimal residential space. Sarkhej Gandhinagar Highway is the newly added
street in AMC limits with heavy urbanization. SG Highway is a part of NH-8 that now has high-rise
residential and commercial spaces with recreational establishments including shopping malls, theatres,
part plots etc. CG Road has paid parking facility with retail and office spaces and majority of G + 4
buildings. CG Road is the only street with paid parking facility operated by a private party.
Figure 4.1: Case Study Locations
AMC Limits
(SP Ring Road)
Ashram Road
Relief Road
CG Road
Gurukul Road
SG Highway
Maninagar
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
40
The section calculates and presents primary data analysis for all the six selected cases in form of Parking
accumulation, Land Use analysis, Parking Space Inventory and demand forecasting. Two out of these
cases shall be further analyzed by conducting parking duration survey and questionnaire survey. A
detailed parking scheme shall be proposed for two cases based on observing the analysis results.
Currently Maninagar and Ashram Road have been selected for designing a parking scheme based on site
visit observations.
4.2 Field Surveys & Primary Data Analysis
Data collection has been divided into two parts i.e. Primary Data collection and Secondary data
collection. Primary data collection has been divided into two phase viz. Phase-1 and Phase-2. Phase-1
shall capture parking data for all the selected cases to determine statistic related to parking volumes, land
use, parking inventory and RoW characteristics. Phase-2 of the survey is designed to gather data for
modeling parking scheme for one case. This survey shall provide with additional statistic pertaining to
parking durations, trip purpose and other relevant data.
Following table explains the phasing of survey and data collection parameters.
Sr.
No.
Parameters Location Phase
1 Parking Volumes All Six Cases
(Maninagar, Ashram
Road, Relief Road, CG
Road, SG Highway,
Gurukul Road)
Phase – 1
2 Parking Turnover
3 RoW
4 Land Use Data
6 Physical Roadway usage analysis
7 Parking Duration
Maninagar, Ashram
Road Phase – 2
8 Parking Questionnaire Survey
9 Parking Space Inventory
10 Parking Accumulation
Table 4.3: Survey Parameters
Primary data collection was done in two rounds in a day for all the above mentioned locations. Total
survey duration was 14 days. Data collection parameters for the survey were decided after the literature
study and in relevance with the modeling requirements. Surveys were done to capture peak volumes and
loads at each location depending on the land use characteristics for examples at S G Highway surveys
were done on one week day and one week end to capture commercial parking volumes and recreational
parking volumes. On Relief road parking is allowed on alternate side of the road each consecutive day,
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
41
therefore to capture differential parking characteristics three days of survey was done for this street.
Maningar has a mixture of work and recreational trips therefore we did a week day and a week end survey
for this location. Data collection was in two parts viz. phase – 1, phase – 2 along with site photography.
Following schedule shows the survey days for each of the location.
Sr.
No.
Loca
tion
Du
rati
on
(Days)
13/0
2/0
9
19/0
2/0
9
20/0
2/0
9
21/0
2/0
9
22/0
2/0
9
23/0
2/0
9
24/0
2/0
9
25/0
2/0
9
26/0
2/0
9
27/0
2/0
9
21/0
3/0
9
03/0
4/0
9
07/0
4/0
9
28/0
4/0
9
Ashram Road 2
SG Highway 2
Maninagar 2
Relief Road 3
Gurukul 1
CG Road 1 Table 4.4: Survey Schedule
Survey Phase – 1 Survey Phase – 2
Secondary data collection was in form of Schedule of Rates, Technology and labor costs for Parking Lot
management, Building use conversion permissions from AMC etc.
4.2.1 Parking Volume Counts
Parking volumes were taken for all the sites for varying duration on varying days. To capture peak
volume, the survey was conducted in two time slots i.e. the morning and evening slot. Parking volumes
for cycles, 2-wheeler, 3-wheeler and 4-wheeler were recorded. Apart from these categories of vehicles,
pedestrian and street vendor volumes were also recorded but have not been presented here. These have
been only discussed in the later section (5.3) of the chapter.
Date Location Time Slot
Morning Evening
13/02/09 SG Highway 10:30 – 13:30 19:00 – 21:00
19/02/09 Ashram Road 11:00 – 14:00 17:30 – 19:30
20/02/09 Ashram Road 11:00 – 14:00 17:30 – 19:30
21/02/09 Maninagar 11:30 – 13:30 16:30 – 18:30
22/02/09 SG Highway -- 18:30 – 20:30
23/02/09 Maninagar 10:30 – 14:30 15:30 – 18:30
24/02/09 Relief Road 10:00 – 13:45 17:00 – 19:40
25/02/09 Relief Road 10:00 – 13:45 17:00 – 18:20
26/02/09 Relief Road 10:00 – 13:45 17:00 – 19:40
27/02/09 Gurukul Road 10:00 – 13:00 17:00 – 19:00
21/03/09 CG Road 10:15 – 13:15 17:00 – 19:00
03/04/09 Maninagar Road 10:00 – 13:30 (*)
17:30 – 20:00 (*)
07/04/09 Ashram Road 10:20 – 13:30 (*)
17:00 – 19:45 (*)
28/04/09 Maninagar Road 10:30 – 13:30 -- Table 4.5: Survey Time Slots, [(*) – Phase-2 Survey]
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
42
Parking volumes are used to determine the parking accumulation. The sequential analysis of each site is
given showing hourly parking accumulation. Ashram Road, one of the busiest commercial street has
been distributed into two sections that are a) Section – 1 from Usmanpura Junction to Popular House
(Length – 1083 Mt.) and b)Popular House to Delite Cross Road (Length – 777 Mt.). Following table
shows hourly parking demand for different vehicle category on Ashram road sections for 19/02/09.
Section Time Cycle 2 – Wheeler 3 – Wheeler 4 – Wheeler
Section 1 Usmanpura To
Popular House
11:00 – 12:00 126 757 20 88
12:00 – 13:00 136 749 9 76
13:00 – 14:00 128 659 8 82
17:30 – 18:30 144 731 38 91
18:30 – 19:30 108 677 42 75
Section 2
Popular Hosue to
Delite Cross
Road
11:00 – 12:00 173 304 41 44
12:00 – 13:00 181 325 23 45
13:00 – 14:00 127 219 20 46
17:30 – 18:30 110 258 35 63
18:30 – 19:30 105 251 29 53
Table 4.6: Parking Volume – Ashram Road
In the above table it could be seen that 2-wheeler parking volume are the highest within a range of 200 –
750. Following graphs show the accumulation trend in both the sections of Ashram Road for duration of
five hours that capture morning and evening peaks.
Figure 4.2: Parking Volume Trend – Ashram Road – Section – 1
The graph shows that 2-wheeler parking is at the trough level during the afternoon hours (off-peak)
between 13:00 – 14:00 Hrs. Cycle parking doesn‟t seem to impose much load on the total length with a
volume of up to 180 cycles at maximum level parked in discrete clusters. The parking trend at section-2
of the street has similar characteristics as section-1 hence no diverse parking characteristics are seen.
Following is the parking accumulation trend in section-2 of the street.
0
100
200
300
400
500
600
700
800
11:00 - 12:0012:00 - 13:0013:00 - 14:0017:30 - 18:3018:30 - 19:30
Nu
mb
er o
f eh
icle
s
Parking Volume - Section-1 (Ashram Road)
Cycle
2 - Wheeler
3 - Wheeler
4 - Wheeler
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
43
Figure 4.3: Parking Volume Trend – Ashram Road – Section – 2
Parking trend covering all the vehicles and both the sections of the street length under study is shown in
the following graph for two survey days.
Figure 4.4: Parking Accumulation – Ashram Road
Above image shows that the parking trend attains a peak of 1550 parking vehicles out of two survey days
and a minimum volume of 1056 vehicles that can be considered as baseline hourly parking demand. It is
also noticeable to see that peak for all the vehicles doesn‟t occur at the same time but the cumulative
volume gives peak demand while individual vehicle category gives parking area requirement. Ashram
Road also has off-street parking space in several establishment but a major spill over is also seen on the
arterial roads that connect to the major road.
Maninagar has also been divided into two sections for identifying differential parking demand if any
throughout the stretch. As it is generally seen that no vehicle would tend to park substantially away from
its destination (if parked on-street) location if provided with free or unregulated parking space and
therefore would occupy space haphazardly creating congestion point. Maninagar has such characteristic
and has been therefore divided into two sections that are a) Pushpakunj to AMC Building (Length – 900
Mt.) and b) AMC Building to Maninagar Railway Station (Length 750 Mt.). Analyzing Maninagar
0
50
100
150
200
250
300
350
11:00 - 12:00 12:00 - 13:00 13:00 - 14:00 17:30 - 18:30 18:30 - 19:30
Nu
mb
er o
f V
eh
icle
s
Time
Parking Volume - Section-2 (Ashram Road)
Cycle
2 - Wheeler
3 - Wheeler
4 - Wheeler
11:00 - 12:00 12:00 - 13:00 13:00 - 14:00 17:30 - 18:30 18:30 - 19:30
Parking - 19/02/04 1553 1544 1289 1470 1340
Parking - 20/02/04 1425 1551 1322 1222 1056
0
200
400
600
800
1000
1200
1400
1600
1800
Nu
mb
er o
f V
eh
icle
s
Parking Volume - Ashram Road
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
44
0
50
100
150
200
250
300
350
400
450
10:30 -
11:30
11:30 -
12:30
12:30 -
13:30
13:30 -
14:30
15:30 -
16:30
16:30 -
17:30
17:30 -
18:30
Nu
mb
er o
f V
eh
icle
s
Time
Parking Accumulation - section -2 (Maninagar)
parking accumulation for second day of survey that gives considerable number of observation we observe
following accumulation in two sections.
Figure 4.5: Parking Accumulation - Maninagar
Maniangar observes high volume of cycle parking owing to presence of school near AMC building that
generates heavy on-street bicycle parking in the under construction BRTS corridor. This number takes
parking demand to peak in the morning hours. If we eliminate this volume and try to see the parking
accumulation curve, it is found that that the accumulation peaks in the evening against morning hours
mainly contributed by the 2-wheeler volume. Accumulation slumps to minimum of 505 vehicles during
the afternoon hours and gradually picks up to give maximum volume of 850. High variation is seen in
parking accumulation throughout the day due to changing trip purpose rates. 2-wheeler accumulation
peaks by 21% in section-2 near railways station against morning owing to trips made for commercial
(shopping) purpose. Further detailed analysis of the case shows that varying parking demand and lack of
off-street parking space availability makes the situation more acute.
050
100150200250300350400450500
10:30 -
11:30
11:30 -
12:30
12:30 -
13:30
13:30 -
14:30
15:30 -
16:30
16:30 -
17:30
17:30 -
18:30
Nu
mb
er o
f V
eh
icle
s
Time
Parking Accumulation - Section - 1
(Maninagar)
10:30 -
11:30
11:30 -
12:30
12:30 -
13:30
13:30 -
14:30
15:30 -
16:30
16:30 -
17:30
17:30 -
18:30
Parking - 21/02/04 1489 1374 826 990
Parking - 23/02/04 1273 1428 1294 693 724 913 1001
0
200
400
600
800
1000
1200
1400
1600
Nu
mb
er o
f V
eh
icle
s
Parking Accumulation - Maninagar
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
45
Following table shows the accumulation counts for peak hours on 23/02/09:
Section Time Cycle 2 - Wheeler 3 - Wheeler 4 - Wheeler S
ecti
on
– 1
Pushpakunj to AMC
Building
10:30 - 11:30 440 340 12 35
11:30 - 12:30 454 304 26 50
12:30 - 13:30 416 309 18 29
13:30 - 14:30 99 199 9 26
15:30 - 16:30 90 182 20 28
16:30 - 17:30 76 244 23 41
17:30 - 18:30 75 303 16 34
Secti
on
– 2
AMC Building to
Maninagar Railway
Station
10:30 - 11:30 122 281 20 23
11:30 - 12:30 166 341 44 43
12:30 - 13:30 133 308 38 43
13:30 - 14:30 89 232 22 17
15:30 - 16:30 88 258 25 33
16:30 - 17:30 103 344 39 43
17:30 - 18:30 79 413 28 53
Table 4.7: Parking Accumulation - Maninagar
Parking accumulation at Relief Road is highly dominated by 2-wheeler parking. Following table shows
accumulation at Relief road for all the three survey days.
Date Time Cycle %
2 -
Wheeler %
3 -
Wheeler
4 -
Wheeler
24
/02/2
00
9 10:00 - 11:15 251 19.72% 846 66.46% 99 77
11:15 - 12:30 337 17.44% 1400 72.46% 101 94
12:30 - 13:45 389 15.58% 1900 76.09% 109 99
17:00 - 18:20 353 22.88% 1018 65.98% 99 73
18:20 - 19:40 250 21.40% 802 68.66% 72 44
25
/02/2
00
9 10:00 - 11:15 330 19.90% 1121 67.61% 124 83
11:15 - 12:30 392 20.80% 1296 68.75% 119 78
12:30 - 13:45 291 17.47% 1225 73.53% 100 50
17:00 - 18:20 168 17.21% 705 72.23% 59 44
18:20 - 19:40 0 0.00% 0 0.00% 0 0
26/0
2/2
009 10:00 - 11:15 317 22.45% 932 66.01% 101 62
11:15 - 12:30 337 18.15% 1355 72.97% 75 90
12:30 - 13:45 328 14.24% 1831 79.47% 87 58
17:00 - 18:20 287 20.21% 986 69.44% 70 77
18:20 - 19:40 198 20.63% 656 68.33% 59 47
Table 4.8: Parking Accumulation – Relief Road
Parking on relief road is allowed on either side on consecutive days i.e. North side parking is allowed on
Monday, Wednesday and Friday while South side parking is allowed on rest of the days. Following graph
shows parking accumulation at relief road on 24/02/09.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
46
Figure 4.6: Parking volume – Relief Road (24.02.09)
It can be clearly inferred from the figure that 2-wheeler volume exceeds rest of the parking volumes by
contributing to almost 80% of the total accumulation. To this parking load other volumes like hawking
volume, loading vehicle volume occupy a considerable road space. Following graph shows volume on
Relief road on all three survey days.
Figure 4.7: Parking Volume – Relief Road (3 Days)
Volume on this street peaks during the noon hours mostly due to wholesale business trade hours of
industrial commodities. Being one of the major commercial streets of the city Relief road experiences
heavy number of commercial work trips on 2-wheelers and restricts volumes of 4-wheelers due to lack of
availability of road spaces for parking. Parking demand is fairly homogenously distributed along the
street but illegal parking is seen on the side where parking is not allowed on a specified day. Parking
volume does not provide with actual demand or turnover that occurs at a given location. Relief Road has
high parking turnover that needs to be regulated for limiting or deleting excess demand that spill on
footpaths and arterial roads.
0
200
400
600
800
1000
1200
1400
1600
1800
2000
10:00 - 11:15 11:15 - 12:30 12:30 - 13:45 17:00 - 18:20
Nu
mb
er o
f V
eh
icle
s
Time
Parking Accumulation - Relief Road
Cycle
2 - Wheeler
3 - Wheeler
4 - Wheeler
10:00 - 11:15 11:15 - 12:30 12:30 - 13:45 17:00 - 18:20 18:20 - 19:40
24/02/2009 1273 1932 2497 1543 1168
25/02/2009 1658 1885 1666 976
26/02/2009 1412 1857 2304 1420 960
0
500
1000
1500
2000
2500
3000
Axis
Tit
le
Parking Accumulation - Relief Road
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
47
S G Highway also generates on-street parking demand but not as high as Relief Road or Maninagar
Road. The selected stretch from ISKON Temple to Gurudwara has commercial, residential and
recreational establishments. Demand on this stretch of the highway differs during day and evening hours
with work trips during the day and recreational trips during the evening hours. The table gives hourly
parking volume on different sections of the street (three sections) on 22/02/09.
No. Section Time Cycle
2 -
Wheeler
3 -
Wheeler
4 -
Wheeler Total
1
ISKON cross road to
Balsam Group Bldg
(Cross Road after
Relaince Mall) – 590
Mt.
10:30 - 11:30 21 43 9 32 105
11:30 - 12:30 19 49 8 30 106
12:30 - 13:30 17 35 4 20 76
19:00 - 20:00 2 36 0 31 69
20:00 - 21:00 3 33 0 37 73
2 Balsam Group Bldg to
Nyay Marg – 760 Mt.
10:30 - 11:30 37 151 7 37 232
11:30 - 12:30 36 138 6 53 233
12:30 - 13:30 20 99 4 22 145
19:00 - 20:00 3 81 0 91 175
20:00 - 21:00 2 101 0 109 212
4 Nyay Marg Junction to
Gurudwara – 938 Mt.
10:30 - 11:30 18 162 16 66 262
11:30 - 12:30 14 143 17 68 242
12:30 - 13:30 12 112 9 70 203
19:00 - 20:00 11 159 7 114 291
20:00 - 21:00 9 155 4 117 285 Table 4.9: Parking Volume – S G Highway (22/02/09)
SG Highway has service lane, main highway carriage way, shoulder and parking space as major road way
components. East Side of the street has paved on-street parking facility that caters to the major existing
on-street demand against the Western side of the street. On-street parking demand is created by
establishments on the eastern side, while western side of the street creates concentrated demand.
Following graphs show the total parking volume for three sections of the street.
Figure 4.8: Parking Volume – 3 Sections (SG Highway)
0
50
100
150
200
250
300
350
10:30 -
11:30
11:30 -
12:30
12:30 -
13:30
19:00 -
20:00
20:00 -
21:00
Nu
mb
er o
f V
eh
icle
s
Time
Parking Accumulation - 3 Sections
ISKON cross road to Balsam
Group Bldg
Balsam Group Bldg to Nyay
Marg
Nyay Marg Junction to
Gurudwara
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
48
Figure 4.9: Parking Volume – S G Highway
Figure 4.10: Total Parking Volume – SG Highway
Accumulation peaks during the day and evening up to 600 vehicles but with different trip purpose. Major
accumulation volumes are due to 2-wheeler parking followed by 4-wheeler parking with a contribution of
almost 60% in the morning and 45% in the evening respectively. 2-wheeler parking goes down and 4-
wheeler parking goes up sharply during the evening hours due to trips attracted by shopping malls along
the highway.
Gurukul Road is a case similar to Maninagaroad but with majority of mixed use buildings and average
height up to G + 3 Level. Volume on this street is uniformly distributed along the length of the street
mostly composed of 2-wheeler parking. Surveyed length was 725 Mt. and was distributed in three
sections. Spillover on the arterials was observed at few locations and congestion was seen at crossroads
due to 3-wheeler parking, street vendor stands and pedestrian movement. Encroachment was a problem
for pedestrian movement and also led to concentrated volume of parking vehicles. Following table shows
the total volume at all the three sections of the street.
0
50
100
150
200
250
300
350
400
10:30 - 11:30 11:30 - 12:30 12:30 - 13:30 19:00 - 20:00 20:00 - 21:00
Nu
mb
er o
f V
eh
icle
s
Time
Parking Accumulation - S G Highway
Cycle
2 - Wheeler
3 - Wheeler
4 - Wheeler
599 581
424
535570
0
100
200
300
400
500
600
700
10:30 - 11:30 11:30 - 12:30 12:30 - 13:30 19:00 - 20:00 20:00 - 21:00
Nu
mb
er o
f V
eh
icle
s
Time
Parking Accumulation - S G Highway
Total
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
49
Sr.
No. Section Time Cycle
2 -
Wheeler
3 -
Wheeler
4 -
Wheeler
1
Gurukul Cross Road to
Surya complex cross
road
10:00 - 11:00 45 187 7 30
11:00 - 12:00 56 246 13 49
12:00 - 13:00 31 219 21 53
17:00 - 18:00 59 305 20 51
18:00 - 19:00 40 272 24 41
2
Surya Complex cross
road to tennis court
junction
10:00 - 11:00 54 187 15 28
11:00 - 12:00 74 278 26 27
12:00 - 13:00 85 191 15 21
17:00 - 18:00 68 255 16 47
18:00 - 19:00 55 212 17 32
3 Tennis court junction to
subash chowk
10:00 - 11:00 46 166 21 11
11:00 - 12:00 63 205 27 27
12:00 - 13:00 59 137 15 17
17:00 - 18:00 99 296 16 38
18:00 - 19:00 70 205 18 51 Table 4.10: Parking Volume – Gurukul road (27/02/09)
Following graph shows categorical parking volume and total parking volume on the total length.
Figure 4.11: Categorized Parking and Total Parking Volume – Gurukul Road
Above chart shows that 2-wheeler parking contributes up to 68% of the parking volume throughout the
day. This shows that majority of the parking space is occupied by 2-wheeler parking and this
540
729
547
856
689
0
100
200
300
400
500
600
700
800
900
10:00 - 11:00 11:00 - 12:00 12:00 - 13:00 17:00 - 18:00 18:00 - 19:00
Nu
mb
er o
f V
eh
icle
s
Time
Categorized Parking Accumulation - Gurukul Road
Cycle
2 - Wheeler
3 - Wheeler
4 - Wheeler
797
1091
864
1270
1037
0
200
400
600
800
1000
1200
1400
10:00 - 11:00 11:00 - 12:00 12:00 - 13:00 17:00 - 18:00 18:00 - 19:00
Nu
mb
er o
f V
eh
icle
s
Time
Total Accumulation - Gurukul Road
Total
Accumulation
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
50
phenomenon can be seen on ground in form of second layer of parking composed of 4-wheeler parking.
Further analysis of the condition is discussed in section 5.3.
The only functional on-street paid parking facility exists at C G Road. This road was developed by
Arvind Mills and was thereafter named as „Arvind Marg‟ in 1995. Private parties are invited by AMC to
operate the parking lot facility for tenure of 5 years. The parking facility has been developed on both sides
of the street with parking space for 2-wheeler and 4-wheelers for a total length of 2.10 Km. The street has
mixed land use composed of commercial, residential and recreational use. There are less work trips on
this street against recreational trips made during the evening hours. Majority of the commercial spaces are
the retail spaces that occupy major share in almost every building on the street. Further detail about the
paid parking facility has been discussed in chapter – 4. Following table shows parking volume on four
sections of the street.
Sr. No. Section Time Cycle
2 -
Wheeler
3 -
Wheeler
4 -
Wheeler
1 Panchvati to Lal
Bunglow Cross Road
10:15 - 11:15 19 86 7 41
11:15 - 12:15 17 111 17 53
12:15 - 13:15 15 102 11 38
17:00 - 18:00 51 86 19 43
18:00 - 19:00 37 86 27 51
2
Lal Bunglow Cross
Road to Girish
Coldrink Cross Road
10:15 - 11:15 78 138 10 74
11:15 - 12:15 81 158 13 79
12:15 - 13:15 88 138 15 77
17:00 - 18:00 60 166 15 63
18:00 - 19:00 32 155 23 69
3
Girish Coldrink Cross
Road to Swastik Cross
Road
10:15 - 11:15 53 84 12 40
11:15 - 12:15 63 108 12 37
12:15 - 13:15 60 121 20 41
17:00 - 18:00 55 141 19 49
18:00 - 19:00 55 177 23 54
4 Swastik Cross Road to
Stadium Cross Road
10:15 - 11:15 6 106 7 23
11:15 - 12:15 11 130 13 26
12:15 - 13:15 4 119 8 30
17:00 - 18:00 9 120 15 31
18:00 - 19:00 5 138 15 39 Table 4.11: Parking Volume – CG Road (21/03/09)
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
51
Following graphs shows the categorical parking volume/total parking volume on C G Road (21/03/09).
Figure 4.12: Categorical and Total Parking Volume – C G Road
It can be again seen here that the volume is mainly composed of 2-wheeler parking volumes contributing
up to a maximum of 56% during the evening peak hours. It is interesting to see that despite of the
existence of upper class socio-economic characteristics on the street and category of commercial activity,
4-wheeler volumes compose only 20-22% of the total volume. Spillover of parking occurs on this street
even, on the arterials and for a considerable length.
On-street parking volumes are highly dependent on the land use and socio-economic characteristics of the
street and are regulated by parameters like cruising time (time consumed to find a parking space), RoW,
congestion index etc. High reliance for mobility on 2-wheeler is seen followed by cars. Land use analysis
in next section explains the reasons for different demands in different streets.
4.2.2 Land Use Survey
Land Use survey of buildings facing the street was done to observe the relation between existing on-street
parking demand and demand generation parameters. Land use was done in form of use at different floor
levels in the building. After identifying the land use on a particular stretch we would later establish a co-
relation between the land-use and parking volumes for the street.
Following table shows the land use summary at different sections in Maninagar.
0
100
200
300
400
500
600
10:15 -
11:15
11:15 -
12:15
12:15 -
13:15
17:00 -
18:00
18:00 -
19:00
Nu
mb
er o
f V
eh
icle
s
Time
Categorical Parking Accumulation - C G Road
Cycle
2 - Wheeler
3 - Wheeler
4 - Wheeler
784
929 887942 986
0
200
400
600
800
1000
1200
10:15 -
11:15
11:15 -
12:15
12:15 -
13:15
17:00 -
18:00
18:00 -
19:00Time
Total Accumulation - C G Road
Total
Accum…
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
52
Section Building use No. of
Buildings
% Land
Use
Avg. No.
of Floors
Pushpakunj to Sardar
Patel Hospital
Commercial 17 61%
G + 2
Residential 4 14%
Public 5 18%
Institutional 2 7%
Mixed (Comm. + Resi.) 0 0%
Sardar Patel Hospital
to AMC Building
Commercial 4 29%
G + 3
Residential 4 29%
Public 4 29%
Institutional 1 7%
Mixed (Comm. + Resi.) 1 7%
AMC Building to
Maninagar Cross
Road
Commercial 19 66%
G + 3
Residential 5 17%
Public 1 3%
Institutional 0 0%
Mixed (Comm. + Resi.) 4 14%
Maninagar Cross
Road to Railway
Station
Commercial 14 88%
G + 5
Residential 0 0%
Public 0 0%
Institutional 0 0%
Mixed (Comm. + Resi.) 2 13% Table 4.12: Maninagar Road - Land Use
Above table shows that major land use comprises of commercial use in all the sections of the Maninagar
Road. It varies from 29% to 88% showing that major parking demand is created in section from
Maninagar Cross Road to Railway Station due to the retail business dominance in this section. Residential
land use also covers substantial land space but creates feeble on-street parking volume. It is therefore
inferred that parking concentration is high as compared to other sections of the street and dominated by
retail commercial business along the total length. With introduction of BRT Corridor it would be
interesting to see the impact on parking demand and land use on this street. BRT design has provision for
on-street parking space but the supply is less than the existing demand and existing on-street area
available for parking. This is expected to promote and make use of existing off-street parking spaces to
their maximum capacity. Socio-economic characteristics of the street includes major segment of middle
income group that occupy space and make trips to this street.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
53
Ashram Road as seen in the following table is again a pure commercial street with few public,
institutional and residential spaces.
Section Building use No. of
Buildings
% Land
Use
Avg. No.
of Floors
Usmanpura to Popular
House
Commercial 34 68%
G + 3
Residential 2 4%
Public 9 18%
Institutional 5 10%
Mixed (Comm. + Resi.) 0 0%
Popular House to
Delite Cross Road
Commercial 14 61%
G + 4
Residential 3 13%
Public 3 13%
Institutional 3 13%
Mixed (Comm. + Resi.) 0 0% Table 4.13: Ashram Road – Land Use
Almost all the commercial establishments on this street have off-street parking facility that service major
portion of the existing demand. Commercial spaces occupy up to 70% of the establishments facing the
street. Buildings beyond the street also majorly comprise of commercial use and create parking volume
on the arterials. Ashram Road has existing on-street parking facility for which the users are currently not
being charged. Parking on the carriage way is banned and traffic department enforcement works
efficiently to regulate the number of parking infractions.
Section Building use No. of
Buildings
% Land
Use
Avg. No.
of Floors
Gurukul Road
Commercial 17 34%
G + 3
Residential 13 26%
Public 0 0%
Institutional 0 0%
Mixed (Comm. + Resi.) 20 40% Table 4.14: Gurukul Road - Land Use
This street is highly dominated by mixed land use buildings facing the street with 40% share. The parking
occupies major road width because of unavailability of off-street parking space for commercial trips.
Almost all the existing off-street spaces are reserved for the residential floors in a mixed land use
building. This street was widened by the municipal corporation in 2003 by clearing all the encroachments
on the street to provide space for traffic movement but the situation has not yet improved to expected
level due to haphazard parking and multi layer parking.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
54
Following table shows land use summary at C G Road
Section Building use No. of
Buildings
% Land
Use
Avg. No.
of Floors
Panchvati to Lal
Bungalow
Commercial 56 86%
G + 4
Residential 8 12%
Public 0 0%
Institutional 1 2%
Mixed (Comm. + Resi.) 0 0%
Lal Bungalow to
Stadium Cross Road
Commercial 28 76%
G + 4
Residential 7 19%
Public 2 5%
Institutional 0 0%
Mixed (Comm. + Resi.) 0 0% Table 4.15: C G Road – Land Use
C G Road is also a commercial street with retail business dominance that caters to the mostly the upper
middle and high income group of the city. As against Ashram Road that contains office spaces more than
retail spaces, C G Road has major floor space occupied by retail business followed by office and
residential space. As mentioned earlier the street has paid on-street parking facility and functions well to
cater to the existing demand but face other operational issues that shall be discussed later. With almost up
to 80% commercial space the street has high income group demographics. Following Table shows land
use summary at S G Highway
Section Building use No. of
Buildings
% Land
Use
Avg. No.
of Floors
Gurudwara to Nyay
Marg
Commercial 24 63%
G + 3
Residential 4 11%
Public 3 8%
Vacant Land 5 13%
Mixed (Comm. + Resi.) 2 5%
Nyay Marg to
ISKCON Temple
Commercial 21 64%
G + 2
Residential 6 18%
Public 0 0%
Vacant Land 6 18%
Mixed (Comm. + Resi.) 0 0% Table 4.16: S G highway – Land Use
S G Highway has free on-street parking facility provided by the corporation on eastern side of the street
from ISKCON temple to Gurudwara stretch. Major land use is commercial with 64% and buildings with
wide lengths facing the road. This facility is provided on the service lane and caters mostly to the trips
with destination on eastern side of the street. Western side of the street is relatively less developed and
generates parking demand at few locations in concentrated volumes and almost all the demand is
generated by buildings on eastern side of the highway owing to feeble develop on the western side.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
55
4.2.3 Parking Space Inventory
Parking space inventory captures the actual physical characteristics of the parking space. This survey is
the first survey required to start physical design or parking load calculation etc. After delineation of
survey area the survey tires to calculate the parking space inventory in form of actual parking space
available, parking patterns, street furniture etc. Following list shows the items that need to be observed
during the survey.
i. Number of parking space currently available based on the pattern of parking
ii. Location of bus stops, pedestrian crossing, signals, parking restriction signage and other street
furniture
iii. Right of way available
iv. Encroachments and temporary structure
v. Special features like the BRT corridor etc.
vi. Characteristic of street in form of median divided street, effective usable road width etc.
Based on the above survey characteristic following table gives the road space inventory summary for all
the cases under study.
Location RoW
(Mt.)
Effective
RoW
(Mt.)
Parking
Area
(Sqm.)
Bus
Stops
(Nos.)
Street
Furniture
(Nos.)
Maninagar 21 11.5 4373 10 42
Ashram Road 35 14 4836 9 97
Relief Road (Single Side) 19 10.5 3472 11 73
Gurukul Road 27 13 2356 3 23
C G road 26 13 4725 13 83
S G Highway (Service Lane) 80 -- 6870 0 19 Table 4.17: Parking Space Inventory – All Cases
Parking area available (supply) is assumed after deducting the inventory widths, building entrance widths
etc. Parking is assumed to have 2-wheelers parked perpendicular to the kerb and 4-wheelers parked
parallel to the street in single level only. As shown in the above table parking space inventory lists the
number of bus stops and total street furniture that includes traffic signage, route signs, pedestrian crossing
signs, informatory signs, advertising boards, lamp posts etc. On average only half the road width is
available for traffic movement while rest of the width is consumed by pedestrians, parking, shoulder,
hawking and vending spaces ect. SG Highway has service lane that faces congestion problem and reduced
effective width due to unpaved surface. The highway lane doesn‟t experience parking on weekdays but
faces localized / concentrated parking volumes on weekends at clubs, restaurants and multiplex area.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
56
Existing parking space available has been calculated by deducting road length occupied by bus stops,
street furniture, building entrances and junction widths and adding area that experiences two level parking
(parking done in two levels perpendicular to the street).
Maninagar currently has no on-street parking facility that results in haphazard and random parking pattern
causing congestion points and bottle necks on several places on the street. Most of the commercial
buildings that provide off-street parking facility have poorly designed parking spaces that are inefficient
in handling the parking demand generated by the building resulting in haphazard off-street parking. With
introduction of the BRT corridor the effective and total available carriageway width has reduced and so
has the parking space supply. Similar to S G Highway, Maninagar has high parking demand on weekends
due to high number of recreational trips. The new BRTS design provides 3160 m2. of area for parking that
can be expected to control the parking demand volumes.
Ashram Road that has an existing on-street parking facility is not being used efficiently because of
reduced supply due to encroachments, pedestrian movement interference, random parking patterns etc.
Service lane provided for parking is used as pedestrian space and pedestrian space has street furniture that
makes pedestrian movement difficult. Parking space and pedestrian space at several places is encroached
by street vendor huts that create shabby landscape and need to be provided with dedicated hawking
spaces.
Gurukul road has similar characteristics as that of Maninagar in terms of parking practices. Two level of
parking is commonly seen here with first level having 2-wheeler parking and second level having 4-
wheeler parking and street vendors. Pedestrian movement is non-continuous with pedestrian space either
being encroached or is poorly built and/or unavailable. The street has no major street furniture or bus
stops and has relatively continuous parking space.
Relief Road allows parking on single side in a day but illegally parked vehicles do exist on the street due
to low frequency of enforcement patrol. The enforcement crew does not have enough fleet to check all the
infringements. There exists fairly continuous pedestrian space and parking space even but faces problems
at goods loading and unloading sites, street vendors on the carriageway and footpath. This street is a part
of the walled city and has no off-street parking facility in almost all the buildings. Street furniture
includes bus stops and traffic signage.
C G Road on-street parking facility provides billboard space on the raised platforms at both the ends of
the parking lots. Parking facility has easy entry and exit points to reduce congestion and queuing of
vehicle on the service lane but faces similar problem of service lane usage as pedestrian space as seen on
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
57
Ashram Road. S G Highway currently faces nearly no mobility problems except on weekends where high
traffic volumes reduce the efficiency of service lane.
4.2.4 Parking Duration
After observing the parking volume analysis and land use analysis, Maninagar can be selected for
designing parking scheme and parking management plan. Parking durations were calculated for
Maninagar and Ashram Road in two slots to identify relation between parking duration and trip purpose.
License Plate method of survey was used to calculate parking durations for the selected locations. This
method of survey yields most accurate and realistic data but needs accuracy and speed in collection.
Simple random sampling method was used to select vehicles from a parking lot to be listed for the survey.
The survey was conducted one day each for both the cases in morning and evening hours. Duration
counts were taken in 4 ranges of <30 min., 30 min. – 1 Hr., 1 Hr. to 3 Hrs. and 3Hrs. First class is termed
as short term parking, next two classes can be termed as medium term parking and last class can be
termed as long term parking. At Maninagar six parking lots were considered for the study and the
recording was done by cruising on a 2-wheeler. Following table presents the observations in morning
phase.
Time Location
Type
of
Vehicl
e
Parking Duration
Total
Vehicles < 30
min.
30 Min. –
1 Hr.
1 Hr. – 3
Hr.
> 3 Hrs.
Morn
ing
Maninagar Railway Station
to Maninagar Cross Road
2w 15 8 6 3 34
4w 2 3 1 0 6
Maninagar Cross Road to
AMC Building
2w 29 9 5 2 45
4w 7 4 1 0 12
AMC Building to
Pushpakunj
2w 37 19 6 0 62
4w 9 4 0 0 13
Ev
enin
g
Maninagar Railway Station
to Maninagar Cross Road
2w 11 9 0 1 21
4w 3 1 0 0 4
Maninagar Cross Road to
AMC Building
2w 18 11 4 0 33
4w 6 1 0 0 7
AMC Building to
Pushpakunj
2w 25 12 1 1 39
4w 7 1 1 0 9 Table 4.18: Categorized Parking Duration - Maninagar
Total vehicles surveyed in the morning phase were 172 (79 2-wheelers and 31 4-wheelers) and 113 in
evening (93 2-wheelers and 20 4-wheelers). Following table shows the morning and evening parking
duration for the entire length.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
58
Time Parking
Duration 2w %age 4w %age
Morning
< 30 Min. 81 58.27% 18 58.06%
30 Min. – 1 Hr. 36 25.90% 11 35.48%
1 Hr. – 3 Hrs. 17 12.23% 2 6.45%
>3 Hrs. 5 3.60% 0 0.00%
Evening
< 30 Min. 54 58.06% 16 80.00%
30 Min. – 1 Hr. 32 34.41% 3 15.00%
1 Hr. – 3 Hrs. 5 5.38% 1 5.00%
>3 Hrs. 2 2.15% 0 0.00%
Table 4.19: Categorized Parking Duration – Maninagar (Percentage)
Above table shows that more than half, i.e. almost 60% of the 2-wheelers and 80% of the 4-wheelers are
short term parking vehicles. Almost no vehicle is a long term parking vehicle on the entire stretch under
study. Average of morning and evening percentage could be considered to calculate duration for total
volumes. Parking duration for 2-wheelers is almost same in both the time slots. Volume of 4-wheelers is
low as compared to 2-wheelers and almost same in morning and evening hours for short term parking.
We can therefore say that 58% of 2-wheelers and almost 70% of 4-wheelers are short term parking
volumes while rest are medium term and almost no vehicle is long term parking vehicle.
Ashram Road is the second case under study that covered 193 vehicles (153 2-wheelers and 40 4-
wheelers) in the morning and 123 vehicles (94 2-wheelers and 29 4-wheelers) in the evening. Following
table gives volumes for different class of duration in morning and evening hours.
Time Location Type of
Vehicle
Parking Duration Total
Vehicles < 30
min.
30 Min.
– 1 Hr.
1 Hr. –
3 Hr.
> 3 Hrs.
Morn
in
g
Usmanpura To
Popular House
2w 61 16 3 3 82
4w 11 5 4 4 24
Popular Hosue to
Delite Cross Road
2w 47 15 7 2 71
4w 10 4 1 1 16
Even
ing
Usmanpura To
Popular House
2w 42 7 1 1 51
4w 12 5 1 0 18
Popular Hosue to
Delite Cross Road
2w 29 11 3 0 43
4w 9 2 0 0 11 Table 4.20: Categorized Parking Duration – Ashram Road
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
59
Time Parking
Duration
2w %age 4w %age
Morning
< 30 Min. 108 70.13% 21 52.50%
30 Min. – 1 Hr. 31 20.13% 9 22.50%
1 Hr. – 3 Hrs. 10 6.49% 5 12.50%
>3 Hrs. 5 3.25% 5 12.50%
Evening
< 30 Min. 71 75.53% 21 72.41%
30 Min. – 1 Hr. 18 19.15% 7 24.14%
1 Hr. – 3 Hrs. 4 4.26% 1 3.45%
>3 Hrs. 1 1.06% 0 0.00%
Table 4.21: Categorized Parking – Ashram Road (Percentage)
As seen in Maninagar, Ashram Road too has majority share of short term parking vehicles in both the
categories. It can thus be inferred that almost 75% of 2-wheelers and 60% 4-wheelers are short term
parking vehicles throughout the day on length under study. Morning hours on Ashram Road has small
volume of 4-wheeler parking vehicles near Times of India building that contribute to compose 12% of
long term parking share. Reason to state this is that Ashram Road has majority of office space that attracts
employee trips rather than visitor trips and uses off-street parking space. Contrary to this Maninagar has
majority of visitor trips to retail business.
4.2.5 Parking Interview
Questionnaire based survey was done to gather information pertaining to trip purpose and approximate
distance of parking from destination location. Total of 62 2-wheelers and 23 4-wheelers were interviewed
to gather this data. Following table shows the observation summary.
Location
Trip Purpose 2-Wheeler 4-
Wheeler
No. of
Trips
No. of
Trips
Maninagar
Road
Retail 36 9
Office 15 11
Personal 4 0
Work (institution) 1 2
Educational 6 1
Total 62 23 Table 4.22: Trip Purpose - Maninagar
The table shows that almost 60% of the trips made by 2-wheelers are retail trips and 50% o the trips made
by 4-wheelers are office work related trips. Average distance for 2-wheeler from parking location to the
destination is 55 m (approx.) and for 4-wheeler it is 40 m (approx.) in alignment with road. A vehicle thus
in Maninagar needs not cruise for parking space in normal days. The situation gets slightly different on
weekends but doesn‟t change significantly in terms of proximity of parking lot to destination location and
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
60
trip purpose either. Though the survey is smaller in size but has been able to reveal significantly
important findings in form of trip purpose and parking space to destination proximity. Questionnaires
were filled by people through random selection depending on visual observation of parking lot size and
volume of vehicles in that lot. The survey was conducted only for Maninagar.
4.3 Observation Summary
After conducting primary survey, site visits etc. the study has been able to gather qualitative data along
with quantitative data. This is formulated in terms of observations and presented in following sub topics.
This summary also presents the demand and supply analysis of parking space for each case and provides
with a base to formulate demand equation for parking modeling at Maninagar. Some assumptions done to
calculate parking area demand are as follows:
i. Parking area requirement for 4-wheeler is 5 x 2.5 mt. (excluding maneuvering space)
ii. Parking area requirement for 2-wheeler is 0.8 x 2 mt. (excluding maneuvering space)
iii. ECS conversion factor – Bicycle = 0.10, 2-wheeler = 0.2, 3-wheeler = 0.5, 4-wheeler = 1
(ECS is the space equivalent occupied by a car)
4.3.1 Maninagar Analysis
The total length has different parking demand characteristics in all the four sections from Maninagar
Railway Station to Pushpakunj. Land Use characteristics shows that Maninagar Railway Station to
Maninagar cross road has almost 88% commercial land use. Major number of buildings don‟t have off-
street parking space for visitors that come for commercial purpose and generally park their vehicle in
random positions ranging from parallel, perpendicular to inclined patterns. There exists no dedicated on-
street parking space and the existing road geometry doesn‟t clearly delineate pedestrian and vehicle space.
Highest congestion on this street can be seen in section-1 (Maninagar Station to Maninagar Cross Road)
during evening peak hours. Total length of the road is 1650 mt. and parking space available is 4373 sq.mt.
This parking space has been calculated based on following assumptions.
i. 2-wheeler parking is done perpendicular to the street and 4-wheeler parking is done parallel to
the street.
ii. Parking is not allowed in front of building entrances, on junctions, in fornt of bus stops and
petrol pumps and buildings of importance.
iii. Parking is done at an offset from the junction and can occupy any space other than that
mentioned above on the edge of the kerb.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
61
This parking area can be considered as existing supply and used for preliminary calculations since there
exists no official parking or no-parking space on this street. On observing the type of buildings and off-
street parking space provided by them it can be inferred that majority of the buildings on this street either
don‟t have a parking space for commercial visitors or have poor design of parking space that cannot be
practically used for parking. There are almost 66 buildings on this road out of which nearly 65% either
don‟t have a parking space or have poorly designed space that can‟t be accessed. Most of the commercial
space here is occupied by retail business that is owned by middle income group and has visitors from the
same group attracting major portion of 2-wheeler trips. Morning and evening hours experience street
vendor traffic also occupying kerb side space. Since the road is not completely paved paring is done at an
offset from the kerb that reduces the effective usable road width after adding the pedestrian occupied
space on the road pavement.
BRTS corridor is the new development on the street as a part of the Ahmedabad BRTS Project that
reduces the road width available for mixed traffic. The available RoW in this system shall contain
pedestrian space, parking lots, mixed traffic lanes and BRT corridor. It can be expected that the
completely paved surface up to the kerb shall help in optimal use of road by parking vehicles. Maninagar
has been selected for designing a detailed parking management program and it would be interesting to see
the impact of BRT corridor on parking behavior on this stretch. We shall further try to understand and
calculate the demand management mechanism that could be employed to improve the existing parking
scenario on this road. Over a period of time Maninagar Road land use has drastically changed from
residential to commercial land use. Majority of the buildings facing the street were residences that have
now been converted to commercial buildings and are attracting traffic volumes that create congestion and
parking problems. Space for pedestrian movement is minimal and pedestrians have to cruise along the
road between the parked vehicles or have to walk on the carriageway by obstructing traffic movement.
Situation at Maninagar Crossroads is bad due to presence of commercial establishments that create
parking along the turning curve of the junction. On this junction there exists a bank, a G + 3 commercial
building and an electric transformer, and street vendors that attract parking but provide no space adding to
congestion on the junction. This street has many eateries that attract parking volumes in the evening hours
but have no parking space and thus create bottlenecks at several locations. Currently the BRT lane which
is under construction is being used as a parking space by cycles that come to a school opposite to
Maninagar fire station and by 2-wheelers near the Railway Station. Pushpakunj attracts several 2-wheeler
trips in early morning hours that visit the newly developed „Kankaria Lake‟. Following images show the
Maninagar road and road network map with following items.
vii. Congestion Locations
viii. Buildings of Importance
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
62
ix. Heavy traffic volume locations
x. Arterial Roads with Parking (Parking on arterials)
xi. Parking locations on BRT Corridor
Deamand supply analysis for Maninagar Road follows the map and show section wise and cumulative
parking demand and supply comparisons, demand projections etc.
Figure 4.13: Maninagar Road – Mapped Observations
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
63
Peak hour demand for Maninagar Road is shown in following table. Total area required during peak hour
(1130 – 1230) is 3049 m2 i.e. 70% of the available area. Sect.1-Pushpakunj to AMC, Sect.2-AMC to
Railway Station. 2-wheeler demand in three sections from Railway station is 36%, 17% and 47%
respectively.
Section Cycle
(ECS)
%
ECS
Area
(m2)
2w %
ECS
Area
(m2)
3w
(ECS)
%
ECS
Area
(m2)
4w %
ECS
Area
(m2)
1 45.4 14% 340.5 60.8 19% 486.4 13 4% 144.82 50 16% 625
2 16.6 5% 124.5 68.2 21% 545.6 22 7% 245.08 43 13% 537.5
Total 62 19% 465 129 40% 1032 35 11% 389.9 93 29% 1162.5
Table 4.23: Peak Hour Demand – Maninagar
Section Vehicle
Type
Total ECS Peak Demand
Area (m2)
% of Total
Supply
Maninagar
Railway Station to
AMC Building
Cycle 78 124.5 3%
2w 435.4 660.8 15%
3w 108 245.08 6%
4w 255 662.5 15%
AMC Building to
Puhspakunj
Cycle 165 340.5 8%
2w 376.2 544.0 12%
3w 62 144.82 3%
4w 243 625.0 14%
Total 1722.6 3347.2 77% Table 4.24: Parking Area Demand – Maninagar
Section Time Total
ECS
Total
Area Req.
% of
supply
Maninagar
(Total Length) 10:30 - 11:30 254.4 2318.3 53.0%
11:30 - 12:30 319.0 3049.4 69.7%
12:30 - 13:30 278.3 2610.9 59.7%
13:30 - 14:30 163.5 1540.8 35.2%
15:30 - 16:30 189.3 1850.7 42.3%
16:30 - 17:30 250.5 2470.4 56.5%
17:30 - 18:30 267.6 2593.7 59.3%
Average 246.1 2347.7 53.7% Table 4.25: Demand Percentage of Supply
Parking area demand for on street parking is calculated by straightaway considering the stall size for all
the vehicle categories.
Cycles – 0.5 x 1.5 m = 0.75 sq.mt 2-wheeler – 0.8 x 2 m = 1.6 sq.mt.
3-wheeler – 1.9 X 2.925 = 5.575 sq.mt. 4-wheeler – 2.5 x 5 m = 12.5sq.mt.
As shown in the above tables it can be seen that the maximum parking demand is 70% for the entire street
in the morning hours. This cannot though be considered for individual sections of the street that attracts
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
64
different parking needs. We therefore need to see the demand pattern in high volume section i.e. from
Railway Station to Maninagar Crossroad in the following table. Area available for parking is 914 sq.mt.
Section Time
Total
ECS
Area Req.
(sq.mt.)
% of available
supply
Maninagar
Char Rasta to
Railway
Station
10:30 - 11:30 59.9 547 60%
11:30 - 12:30 88.9 874.95 96%
12:30 - 13:30 86.4 880.9 96%
13:30 - 14:30 52.1 502 55%
15:30 - 16:30 77.8 794.3 87%
16:30 - 17:30 98.8 1001.3 110%
17:30 - 18:30 101.8 1006.65 110% Table 4.26: High Volume section Demand – Maninagar
The table shows that average demand as % of supply is 88% throughout the day while peak demand is
110%. This excess demand percentage is a result of area that has been calculated under ideal parking
conditions (according to 5.2.3). The parking space thus needs to be allocated throughout the road in a
strategic manner that is able to cater to peak demand level in each section of the street.
4.3.2 Ashram Road Analysis
Ashram Road is a mixed office and retail corridor with almost 64% commercial buildings, Public and
institutional up to 25% and 8% residential buildings. RoW is 40 mt. and the street has been redesigned
with on-street parking space throughout the section under study. Parking demand near few buildings is
high with rest of the volumes almost homogenously distributed between the stretches from „Delite
Crossroad‟ to „Gandhi Bridge junction‟. Demand volumes are low from Gandhi Bridge to Usmanpura
junction owing to less number of prominent commercial establishments. Parking on the carriage way is
banned and enforcement operation being done could be seen almost daily at a frequency of 3 – 4 rounds
of patrol crane per day. The existing redesign has parking provision for only 2 and 4 wheelers and has no
dedicated space for cycle and 3-wheelers. RoW design includes (from the property line) Parking space,
service land, foot path (raised from road level – 150 mm approx.), main carriage way (2 lane). Parking on
the arterials is also seen composed of perpendicular 2-wheeler and parallel 4-wheeler parking. Parking is
currently provided as free facility and is not utilized to its fullest capacity. Almost all the arterials that
connect to the main street experience on-street parking and at several locations create congestion. A
Street parallel to the Ashram Road from Gandhi Bridge junction on the eastern side experiences heavy
long term 4-wheeler parking due to major commercial establishments. Car parking was seen at several
places on the main carriageway which were short term parking vehicles but a reason for congestion
during evening hours. Pedestrian space was partly inefficient due to presence of street furniture (benches,
Parking signage, trash bins) at several locations making pedestrian movement discontinuous. Walk ways
on the edge of the RoW were less than 1.5 mt. and occupied by street hawkers. Most of the buildings
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
65
similar to Maninagar had off-street parking that was poorly designed and unable to cater to the demand
generated creating localized high volumes. Auto rickshaws were parked in few clusters on the carriage
way parallel to the kerb near major buildings that includes Reserve Bank of India, City Gold multiplex,
Sales Tax office, Popular House etc. Images of Ashram road that locate the congestion points and other
important features are followed by the Demand Supply analysis.
Section Cycle
(ECS)
%
ECS
Area
(m2)
2w
(ECS)
%
ECS
Area
(m2)
3w
(ECS)
%
ECS
Area
(m2)
4w
(ECS)
%
ECS
Area
(m2)
1 14.4 3% 108 146.2 33% 1169.6 19 4% 211.66 91 20% 1137.5
2 11 2% 82.5 82.5 19% 412.8 17.5 4% 194.95 63 14% 787.5
Total 25.4 6% 190.5 228.7 51% 1582.4 36.5 8% 406.61 154 35% 1925
Table 4.27: Peak HourVolume – Ashram Road
Section Vehicle
Type
Total ECS Peak Demand
Area (m2)
% of Total
Supply
Usmanpura to
Popular House
Cycle 64.2 108 2.2%
2w 714.6 1211.2 25.0%
3w 58.5 233.94 4.8%
4w 412 1137.5 23.5%
Popular House to
Delite Cross Road
Cycle 69.6 135.75 2.8%
2w 271.4 520 10.8%
3w 74 228.37 4.7%
4w 251 787.7 16.3%
Total 1915.3 4362.46 90.2% Table 4.28: Parking Area Demand – Ashram Road
Section Time Total
ECS
Area Req
(sq.mt)
% of
Supply
Ashram
Road
(Usmanpura
to Delite
Junction
11:00 – 12:00 404.6 3911.62 81%
12:00 – 13:00 383.5 3646.89 75%
13:00 – 14:00 343.1 3352.01 69%
17:30 – 18:30 413.7 4104.51 85%
18:30 – 19:30 370.4 3640.02 75%
Average 383.06 3731.01 77% Table 4.29: Parking Supply Percentage
Figure 4.14: Mapped Images – Ashram Road
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
66
Total available parking area on Ashram Road is 4836 sq.mt. in the length of road under study including
the parking lot and the kerb side where parking lot is absent. Average parking requirement on Ashram
Road is 77% of the available parking space. If the enforcement actions are made more regular and
stringent, the capacity utilization could be increased and congestion on arterials could be minimized by
making these vehicles park in this parking facility. As shown in the above maps 10 arterials connect to the
main street and on-street parking is observed almost on each of it mostly composed of 4-wheelers. There
are few abandoned buildings and open plots that could be used to develop parking facility and provide
better pedestrian space on-street. As a recommendation the parking on these arterials must be prohibited
on any one side of the street and strict enforcement measures must be put in practice to check the
implementation. Measures can include, a) Patrol by traffic police on bikes, b) Putting up no-parking
signage and information of penalty against infringement. Measures must be taken to promote utilization
of off-street parking through parking pricing, enforcement rules and implementation, limiting on-street
supply etc.
4.3.3 Relief Road Analysis
Relief Road has an average right-of-way of 20 m, with heavy through traffic load from Kalupur Railway
Station end to Circuit House end. Heavy through traffic is experienced almost throughout the day except
night hours when the retail business closes for the day. Parking volumes vary through the day with high
parking volumes in morning with 1056 ECS‟s and afternoon hours with 1376 ECS‟s. Parking on this
street is allowed on Northern side on Saturday, Sunday, Tuesday and Thursday while rest of the days
parking is allowed on Southern side. There exists no parking facility in form of parking bays but
information signs help the parking vehicle to use the kerb side road space. The street is retail cum
wholesale industrial products hub with street side hawking activities. On-street parking and pedestrian
movement reduces the effective carriageway by 8-9 meters. Almost all the vehicles are parked in single
level and the total volume is quiet uniformly distributed through the entire length. There are several
loading and unloading points on the street where goods are brought and sent out that create temporary
congestion points on either side of the street. Despite of enforcement, illegal parking is seen on the side of
the street where parking for a given day is prohibited. For enforcement works the traffic police has out-
sourced towing operation to private operator that tows 2-wheelers and clamps 4-wheelers. Towed 2-
wheelers are taken to impoundment area near Roopalee theatre 400 mt. away from the street. There are
two towing trucks that work for this street but only one of them is operational for most of the days. The
private contractor is paid on per day mileage basis and a crew of 6 men is employed on one truck. The
truck has capacity of towing 6 2-wheelers at a time and therefore is able to do little against a large volume
of illegally parked vehicles. The towing operation is done at a frequency of 6-7 rounds per day. It has
been reported that the truck attendants generally accept a bribe of 50 Rs. for lowering a 2-wheeler rather
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
67
than taking it to impoundment area. The official fee for having a vehicle released from the towing centre
is Rs 100 for two-wheelers and Rs 200 for cars. There were nearly 120 hawkers on the study length with
35-37 freight loading and unloading points throughout the road stretch.
MAKRAND PARKING LOTS CHARGES
Cars – 8 Rs. / Hrs
2-wheelers – 4 Rs./Hrs
Cycles – 50 Paisa/ Hrs
After 5 hours charges increase by 2 Rs. /
hrs
Sec. Location Area m2 Total
fees /
year
Fee
/m2/
year
Type of vehicle Fee for
first hour
(Rs.)
Fee after
5 hours
(Rs.)
1 Makrand Desai
parking ,near Relief Theatre, Relief Road
G - 1288.87,
1st - 1288.87,
2nd
- 645.31
6,13,104 190.32 Car 8 4
Two wheeler 4 2
2 Kabutarkhana,Under the kalupur bridge
wing
1,435.44
6,94,966 484.14 Heavy vehicles 15 10
Cars/jeeps 8 4
Two wheelers 4 2 Cycles 1 0.5
3 Nr. Prem darwaja,Nr.
Pay & Use toilet
block.
500 2,98,521 597.04 Car / jeep 5 2
Two wheelers 2 1
Cycles 1 0.5
4 Opp. Ratan pole,Nr.
Manek chawk.
285.46
1,77,686 622.45 Two wheelers 2 1
Cycles 1 0.5 Table 4.30: Paid Parking Lots in Walled City
As mentioned in the above table there is a multi storey parking lot towards the western end of Relief Rd
with a highly affordable fee structure. There is little other off-street parking in basement at Regal Cinema
theatre and few newly developed commercial buildings. Utility level of this off-street parking lot is less
than 50% as reported by the management. The parking lot is named „Makrand Parking Lot‟ and offers
following fare structure. There are few other paid parking lots in and around the walled city that provide
parking space at affordable fees structure as mentioned. Following tables show parking demand and
supply for relief road. Peak demand is seen on Relief road on 24th Feb out of all survey days from 12:30
to 13:45.
Section Cycle
(ECS)
%
ECS
Area
(m2)
2w %
ECS
Area
(m2)
3w
(ECS)
%
ECS
Area
(m2)
4w %
ECS
Area
(m2)
Relief Road
39 7% 291.75 380 66% 3040 54.5 10% 607.13 99 17% 1237.5
Table 4.31: Peak Hour Demand – Relief Road
Section Vehicle
Type
Total ECS Peak Demand
Area (m2)
% of Total
Supply
Relief Road
(24/02)
Cycle 158 294 8.5%
2w 1193 3040 87.6%
3w 240 690.68 19.9%
4w 387 1237.5 35.6%
Total 1978 5262.18 151.6% Table 4.32: Parking Area Demand – Relief Road
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
68
Section Time Total
ECS
Area Req
(sq.mt)
% of
Supply
Relief Road
(Average of
3 days)
11:00 – 12:00 351.2 3297 95%
12:00 – 13:00 442.1 4066 117%
13:00 – 14:00 482.3 4307 124%
17:30 – 18:30 310.2 2878 83%
18:30 – 19:30 246.5 2268 65%
Average 366.5 3363.5 97% Table 4.33: Parking Supply Percentage
The total area available for parking officially is 3472 m2 for which an average daily demand as percentage
of supply is 97%. Peak demand day exceeds the available supply by 50% i.e. parking on the illegal side is
also counted in this demand. Major demand of space is created by cycle and 2-wheeler parking of an area
141 and 804 m2 respectively. Satellite images of the road are difficult to be shown since this street falls in
walled city and cannot be analyzed in plan view.
4.3.4 C G Road Analysis
In 1993 Arvind mills developed a proposal of Road Redesign on CG Road which included Paid on-street
Parking Facility. The redesigned section of the street extends from Panchvati Cross Road to Stadium
Cross Roads. Arvind Mills became the concessionaire for the parking and advertisement while AMC was
the facilitator for clearances. Arvind mills had the sole rights to collect parking fess and recover
advertisement revenue. Few years later the total control was taken over by the municipality and the
parking fees collection and advertisement rights were contracted to other private parties. Contract period
for both the contracts is five years and fresh bidding is done at the end of each session. AMC invited bids
for parking at an annual contract amount of Rs. 6.5 lakhs for first tenure, Rs. 12.5 lakhs for the second
tenure and Rs. 22 lakhs for the third tenure. This (2009) is the last year of the third tenure. Advertising
rights are currently with Sambhaav group and the parking contract with Associated Enterprise Pv. Ltd., a
Delhi based company.
Physical characteristics of the RoW (from property line) include foot path, service lane, parking lot, main
carriage way and median. There are 42 attendants who collect the fees for parking lot facility which is
collected manually, a parking receipt is issued at the time of parking and fee is collected at the time of
exit. Attendants deposit their daily collection to the manager in-charge along with the receipt book. Half
value of the contract amount i.e rs.22 Lakhs, is supposed to be deposited with AMC by the end of first
half of the year. AMC provides with the fees schedule and the operator is supposed to collect the fees and
report infringements to the traffic police.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
69
Fee schedule (Time – 7 am to 11 pm)
Vehicle
Type
1 hr. 2 hr. 4 hr. 6 hr. 8 hr. Above 8 hrs.
2 wheeler 1 2 4 6 8 12
3 & 4
wheelers
2 5 10 15 20 30
Table 4.34: C G Road – Fees Schedule As per Muni Standing Commitee Resolution No.508 e.f.Dt.4/9/05 & AMC Gen Board Reso. No.308 Dt 24/9/04
Parking Attendants and the Manager from Associated Enterprise raised the following problems:
1. There was very weak support from the administrative bodies that includes the AMC, the City
Police, and the Traffic Police Department etc.
2. There was lack of support from the municipality in timely completions of maintenance works.
3. Complains were registered by the traffic police or the city police only from the manager
4. Vehicles enter the parking lot from both the ends of service lane causing blockade
5. Parking vehicles had a common tendency of not willing to pay parking fees
6. Parking pattern observed was inclined for 4-wheeler and perpendicular for 2-wheelers but not
generally followed in the desired manner
7. Encroachments in the parking lots by the shop owners was a common practice and needed periodic
attention
8. Absenteeism of parking attendants was seen that led to reduced daily collection
Following are the images of C G Road from Panchvati to Stadium Cross Road that show urban pattern
around the street and highlight the major features.
Figure 4.15: CG Road – Mapped Observations
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
70
Following tables show demand and supply for the different sections of C G Road (Stadium Crossroad to
Girish Cold drink Cross Road, Girish Cold drink Cross road to Panchvati Cross Road.).
Section Cycle
(ECS)
%
ECS
Area
(m2)
2w %
ECS
Area
(m2)
3w
(ECS)
%
ECS
Area
(m2)
4w %
ECS
Area
(m2)
1 3.7 1.0% 27.75 17.2 4.5% 137.6 13.5 3.5% 150.39 51 13.4% 637.5
2 3.2 0.8% 24 31 8.1% 248 11.5 1.3% 128.11 69 18.1% 862.5
3 5.5 1.4% 41.25 35.4 9.3% 283.2 11.5 1.7% 128.11 54 14.2% 675
4 0.5 0.1% 3.75 27.6 7.2% 220.8 7.5 2.0% 83.55 39 10.2% 487.5
Total 12.9 3.4% 96.75 111.2 29.2% 889.6 44 2.0% 490.16 213 55.9% 2662.5
Table 4.35: Peak Hour Demand – C G Road
Section Vehicle
Type
Total ECS Peak Demand
Area (m2)
% of Total
Supply
Panchvati to Girish
Cold drink cross
road
Cycle 47.8 104.25 2.2%
2w 245.2 443.2 9.4%
3w 78.5 278.5 5.9%
4w 588 1650 34.9%
Girish Cold drink
cross road to
Stadium cross road
Cycle 32.1 55.5 1.2%
2w 248.8 504 10.7%
3w 72 211.66 4.5%
4w 370 1662.5 35.2%
Total 1682.4 4909.61 103.9% Table 4.36: Parking Area Demand - C G Road
Section Time ECS
Area
Req. (m2)
% of
supply
C G Road
10:15 - 11:15 294.4 3204.92 68%
11:15 - 12:15 341.1 3684.05 78%
12:15 - 13:15 325.7 3519.03 74%
17:00 - 18:00 340.1 3655.81 77%
18:00 - 19:00 381.1 4139.01 88%
Average 336.48 3640.564 77% Table 4.37: Parking Supply Percentage
From the table above it can be seen that the average daily demand is 77% of the supply available for the
section of road under study. Parking volumes near Stadium Cross Road end are low as compared to the
other end. Volumes are high near municipal market but not highly concentrated and it can also be seen
that area requirement for 4-wheelers reduces sharply by around 300 sq.mt.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
71
4.3.5 Gurukul Road Analysis
Total length of this road under study is 725 mt. and has mixed land use up to 40% followed by
commercial and residential with 34% and 26% respectively. With mixed land use the average height of
buildings here is G + 3. Similar to Maninagar this place has retail commercial land use in buildings up to
G + 2 levels in and residential in the floors above. Buildings with mixed land use do not allow visitor
parking thus creating parking volumes on-street and leading to congestion. Effective usable road width is
13 m including the median. There are several buildings in front of which 2 to 3 level of parking is seen
with first two levels of 2-wheeler parking and third level of 4-wheeler parking. Out of the 52 buildings on
both the sides of the stretch, only 47 buildings have off-street parking and majority of these spaces are
reserved for the residents of the building. Footpath observed was approximately 1 to 2.5 m wide with
encroachments on both the sides. Following images show the street map and urban form of the area.
Section Cycle
(ECS)
%
ECS
Area
(m2)
2w %
ECS
Area
(m2)
3w
(ECS)
%
ECS
Area
(m2)
4w %
ECS
Area
(m2)
1 5.9 1.7% 44.25 61 17.1% 488 10 2.8% 111.4 51 14.3% 637.5
2 6.8 1.9% 51 51 14.3% 408 8 2.2% 89.12 47 13.2% 587.5
3 9.9 2.8% 74.25 59.2 16.6% 473.6 8 2.2% 89.12 38 10.7% 475
Total 22.6 6.4% 169.5 171.2 48.1% 1369.6 26 7.3% 289.64 136 38.2% 1700
Table 4.38: Peak Hour Demand – Gurukul Road
Section
Vehicle
Type
Total ECS Peak Demand
Area (sq.mt.)
% of Total
Supply
Gurukul Cross
Road to Surya
complex cross road
Cycle 23.1 35.85 2%
2w 245.8 196.16 8%
3w 42.5 87.45 4%
4w 224 735 31%
Surya Complex
cross road to tennis
court junction
Cycle 33.6 24.07 1%
2w 224.6 199.04 8%
3w 44.5 80.02 3%
4w 155 462.5 20%
Tennis court
junction to
Subhash Chowk
Cycle 33.7 74.25 3%
2w 201.8 473.6 20%
3w 48.5 150.39 6%
4w 144 637.5 27%
Total 1398 3119.98 132% Table 4.39: Parking Demand – C G Road
Figure 4.16: Gurukul Road – Mapped Observations
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
72
Section Time ECS Area Req
% of
supply
Gurukul Road
10:15 - 11:15 213 2074.76 88%
11:15 - 12:15 301.1 2966.27 126%
12:15 - 13:15 243.4 2428.02 103%
17:00 - 18:00 355.8 3528.74 150%
18:00 - 19:00 307.8 3104.78 132%
Average 284.22 2820.514 120% Table 4.40: Parking Supply Percentage
4.3.6 S G Highway Analysis
S G Highway falls in fringe area of AMC limits and is fast developing as retail cum commercial cum
residential space. This development can be seen up till the intersection at S P Ring Road. Total length
under study is 2100 mt. and starts from ISKCON temple to Gurudwara. There exists an on-street non paid
parking facility on the western side of the road developed by AMC. Majority of the trips in and out are
made from this side of the road. Parking here is seen in concentrated form at 5 major locations that are,
ISKCON temple, Reliance Mall, Grand Bhagwati Hotel, Gurudwara and Rajpath Club. The land
adjoining the highway is considerably less occupied and buildings here facing the road have large widths.
Off-street parking facility is seen in almost all the buildings with better utility and efficiency levels.
Parking pattern was not uniform in a given parking lot and since it was not controlled, vehicles were
parked in varying patterns. Parking space for service lane and highway were substantial enough to cater to
current parking demand. It was also observed that vehicles were parked not only off of the service lane(s)
but also off the main carriageway of SG Highway. There are many vacant land pieces that could
accommodate existing on-street demand volumes but off-street spaces if utilized to full level could handle
this volume. Following are the images showing S G highway and adjoining urban pattern.
Figure 4.17: S G Highway – Mapped Observations
1
2
3
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
73
Section Cycle
(ECS)
%
ECS
Area
(m2)
2w %
ECS
Area
(m2)
3w
(ECS)
%
ECS
Area
(m2)
4w %
ECS
Area
(m2)
1 0.3 0.1% 2.25 6.6 2.0% 52.8 0 0.0% 0 37 11.4% 462.5
2 0.2 0.1% 1.5 20.2 6.2% 161.6 0 0.0% 0 109 33.6% 1362.5
3 0.9 0.3% 6.75 31 9.6% 248 2 0.6% 22.28 117 36.1% 1462.5
Total 1.4 0.4% 10.5 57.8 17.8% 462.4 2 0.6% 22.28 263 81.1% 3287.5
Table 4.41: Peak Hour Demand – S G Highway
Section Vehicle
Type
Total ECS Peak Demand
Area (m2)
% of Total
Supply
ISKON cross road
to Balsam Group
Bldg (Cross Road
after Relaince Mall)
Cycle 6.2 15.75 0.2%
2w 39.2 78.4 1.1%
3w 10.5 50.13 0.7%
4w 150 462.5 6.7%
Balsam Group Bldg
to Nyay Marg
Cycle 9.8 27.75 0.4%
2w 114 241.6 3.5%
3w 8.5 38.99 0.6%
4w 312 1362.5 19.8%
Nyay Marg Junction
to Gurudwara
Cycle 6.4 13.5 0.2%
2w 146.2 259.2 3.8%
3w 26.5 94.69 1.4%
4w 435 1462.5 21.3%
Total 1264.3 4107.51 59.8% Table 4.42: Parking Demand Area – S G Highway
Section Time ECS Area Req
(sq.mt.)
% of
supply
S G Highway
10:15 - 11:15 229.8 2492.34 36.3%
11:15 - 12:15 239.4 2639.92 38.4%
12:15 - 13:15 174.6 1925.04 28.0%
17:00 - 18:00 296.3 3442.59 50.1%
18:00 - 19:00 324.2 3782.68 55.1%
Average 252.86 2856.514 41.6%
Table 4.43: Parking Supply Percentage
Average parking demand on S G highway is very low and concentrated at few locations mentioned above.
This demand is mostly due to retail commercial business and restaurant business resulting in cumulative
contribution of 50-55%. The morning office hours demand is also very low at 40% level for on-street
parking.
From the results of this analysis it is found that designing a parking scheme for Maninagar shall help us
identify and test a common demand management mechanism for the city. Maninagar has different
demand characteristics in all the sections due to different activities. Following section proposes a parking
management scheme for Maninagar through management and design and pricing alternatives.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
74
Chapter 5: Maninagar Parking Demand Management Plan
5.1 Parking Development Plan for Maninagar
Primary analysis results and site visit observations show that Maninagar has typical parking
characteristics that represents majority of the street of Ahmedabad city. The street is dominated by retail
commercial activity and middle income space owners. The street has mixed land use characteristics and
with introduction of BRTS corridor would need serious attention to manage parking to maintain smooth
traffic flow. This section shall analyze physical characteristics of Maninagar Street and area adjoining the
street that experiences the impact of the activities performed there. Parking statistics have been worked
out to understand detailed parking characteristic and proceed with parking options.
5.1.1 Physical Analysis of Maninagar (Nirav)
Vehicles on Maninagar Road are parked within an average proximity of 45-60 mts from the destination
location. The following figure shows features as follows:
i. Maninagar main street, Arterial Roads
ii. Major points of congestion or high demand (10 nos.)
iii. Open or Vacant lands that could be potential site for off-street parking
iv. Major Junctions
v. High parking demand area on Maninagar Road
vi. High parking area on Arterials
vii. Limits of surveyed area for physical characteristics
As the list mentions, the total length of major road network that was surveyed for understanding
physical form of Maninagar is 10.5 Km. Total number of junctions (cross roads and „T‟ junctions)
were 25 out of which 3 were major junctions that formed the study sections. Total area covered under
physical survey is approximately 0.92 km2. Major number of buildings facing the street on main road
and arterials are commercial and mixed use buildings contributing approximately 60% and 25%
respectively to total number of establishments. Open lands are Railway Parking towards the western
end of the main street, municipal playground in shape of quarter circle adjoining the study area, Fire
station ground, private party plots towards the western end. Out of these, railway parking area and fire
station ground could be considered as potential sites for proposing multi-level parking lot. Railway
Parking has an approximate available land area of 490 sq.mt.(10 x 49) while Fire station ground has
land area of 3192 sq.mt. (57 x 56). From previous data analysis on-street parking space available is
4373 m2 against an on-street parking demand of 3050 m
2 (peak load).
Figure 5.1: Maninagar Physical Analysis
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
75
Following are the important physical characteristics of area observed in Maninagar pertaining to parking,
urban pattern, road network, building use, traffic etc.
i. On-street parking facility is not existent and kerb side parking is done in random patterns by
all the category of vehicles.
ii. Parking is not done in front of building entrances, fire station, bus stops, near junctions etc.
iii. Off-street parking lots were absent in majority of the buildings (65%) facing the main and
arterial streets.
iv. On-street parking was also seen on nearly 15 arterials up to an average length of 25 mt.
v. Majority of the buildings seen on the main and arterial streets are commercial or mixed land
use buildings while the buildings in internal zone are residential buildings and bungalows.
vi. The urban pattern in study area has linear form with buildings having average height of G + 2.
vii. Important structures in the study area include three major hospitals, one fire station, eight
schools, one police station, one post office, municipal zonal office and AMTS bus depot.
viii. Average RoW of the arterials is 15-17 m with unpaved kerb sides used for parking.
ix. Majority of the residential buildings have ground level parking reserved for the residents of
the building.
x. Pedestrian space on the entire network ranges from 0.5 – 1.5 mt. and is unavailable on certain
sections that brings pedestrian movement on the main carraigeway
xi. Residential spaces are closely placed and land area occupied by them does not have high
difference in space covered.
xii. There is high level of water logging problem during monsoons in this area.
xiii. BRTS corridor reduces the mixed traffic carriage way and creates congestion points near the
proposed bus stops.
xiv. Due to absence of space for street vendors on this street they currently contribute to distortion
of the street landscape.
xv. Traffic with low speed and parking volumes with high localized density are observed in the
evening hours and none of the junction is signal controlled
xvi. The urban pattern can be considered as a grid iron pattern with equally distributed land areas
among the buildings.
xvii. Towards the eastern end of the road there is a market and an informal street hawker space that
attracts and creates parking accumulation on the road along the railway line.
Based on the above observations following section proposes different parking options and schemes
testing them against field statistics and engineering feasibility. Following are the sites for this proposition:
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
76
i. Municipal Playground
ii. Railway Station Parking Space
iii. Municipal Ground B/h Fire Station
Other two plots are private plots and currently being used as spaces for organizing marriages, religious
and community gatherings etc. There also exists one municipal party plot but currently is being used by
municipality for community and recreational purpose. Evaluating all the three sites based on proximity,
capacity, development and maintenance, accessibility etc. following results have been derived.
Municipal Playground has an area of 24650 m2 with a radius of 100 m and is approximately 300 m away
from Maninagar road. Pedestrian mobility on this 300 m road is very low and RoW of this street is 16-18
m. High level of demand exists on section between Railway Station to Maninagar Cross Road that can be
catered by this site but due to following reasons this location cannot be selected to propose a multi level
parking.
i. Lack of pedestrian infrastructure on all roads that include the major road and the arterials that
connect to this plot.
ii. Distance of major junctions from this plot is more than 300 m and has RoW between 15-17 m.
iii. The plot is owned by sports club and is being used for sporting activities by different sport clubs,
schools and institutes. Using this land for developing parking structure will deteriorate sports
activities and construct a demeaning landscape.
iv. Being on the junction it would turn out to be congestion point due to movement of vehicles from
the parking lot if constructed.
v. Demand for the parking lot shall increase only if parking on Maninagar Road is banned and this
kind of enforcement shall lead to on-street parking on arterials.
Railway station parking space has poor geometry of 10 m width and 50 m length that cannot be suitable
to design a multi level off-street parking lot. It shall also be difficult to secure railway land and use it for
municipal development i.e. the arrangement between AMC and Indian Railways shall be difficult for this
development. It is also currently being used by railway to provide parking facility generally to daily
commuters for their 2-wheelers using railways.
Municipal Ground behind fire station appears to be in a good geometry and can be considered for
proposing a multi level parking structure. Physical analysis shows that the land is 57 x 56 m in dimension
and has an access road 11 m wide and is at a distance of approx. 90 m from the main road. Proposing a
multi level parking lot on this land shall be constrained by following parameters.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
77
i. The parking lot shall not be able to attract parking if the road continues providing on-street
parking facility.
ii. On-street parking facility should also be charged higher than the multi level parking lot or be
banned by not providing any such facility.
Currently the BRTS corridor being constructed on this street provides parking facility for which details
have been furnished below.
Sr.No. Description Section 1 Section 2 Section 3 Total
1 Total Length of Corridor 330 m 406 m 709 m 1445 m
2 Parking Length Available (average) 121 m 189 m 322 m 632 m
3 Width of Parking Stall 2.5 m 2.5 m 2.5 m 2.5 m
5 Total Area available (both sides) 605 m2 945 m
2 1610 m
2 3160 m
2
Table 5.1: BRTS corridor Parking details - Maninagar
In the above values total length of corridor has been calculated after deducting junction length, parking
length has been derived by deducting tree pit, bus stops, minor intersections, hawking spaces etc. Average
of parking length has been shown in the above table. Parking statistics help to determine a demand
equation for Maninagar Road.
5.1.2 Parking Statistics (Nirav, Ambika)
Parking accumulation counts were taken for 3 parking lots at Maninagar near Satyam Complex, Fire
Station and H J House. The survey was conducted for three hours with time interval as 15 minutes by
License Plate survey method. Following table shows the accumulation counts for 2-wheelers only. 4-
wheelers were not considered due to comparatively low volumes.
Time Interval
2-wheeler
Accumulation Parking Index
Parking Load
(Veh. Mins.)
10:30 - 10:45 64.0 58.2% 960
10:45 - 11:00 66 60.0% 990
11:00 - 11:15 66 60.0% 990
11:15 - 11:30 71 64.5% 1065
11:30 - 11:45 76 69.1% 1140
11:45 - 12:00 80 72.7% 1200
12:00 - 12:15 79 71.8% 1185
12:15 - 12:30 76 69.1% 1140
12:30 - 12:45 68 61.8% 1020
12:45 - 13:00 64 58.2% 960
13:00 - 13:15 55 50.0% 825
13:15 - 13:30 47 42.7% 705
Total/Average 812 (Total) 61.5% (Avg.) 12180 (Total) Table 5.2: Parking Statistics – Maninagar
Hourly accumulation of 4-wheelers can be considered for demand estimation and forecast during detail
design. Number of 2-wheeler parking bays under study are approximately 110 based on the parking stall
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
78
size considered for the study without maneuvering space being provided. Above table shows total parking
accumulation for 3 parking lots identified in Maninagar. Total of 812 vehicles were recorded to have used
the kerb side for parking. It is seen that the average occupancy of these parking bays is 61.5% generating
little more than 12,000 parking vehicle minutes. Total turnover for all the bays is 106 vehicles i.e. the
total number of vehicles entering the parking bays. Survey duration was 3 hours which experienced 67.66
vehicle hours in parking lots under observation. Parking duration is vehicle hours divided by the total
turnover in all the time intervals which was calculated as 38 minutes. Above results thus conclude that
there is high level of turnover using short term parking facility. Accumulation curve shows that the
turnover rate and demand volumes are high in the morning hours with maximum of 72% occupancy level
that could be applied for the entire length under study. Similar trend is also seen during the evening hours
with high turnover and increased utilization level with almost same parking duration. Thus the existing
average daily demand could be 68 2-wheeler vehicle hours i.e. 68 2-wheelers are parked for one hour on
average for the whole day. Parking duration per day could be taken as 10 hours per day between 0900
Hrs. to 2300 Hrs. Factor for computing peak demand volume of 2-wheeler for entire length is 5.86
(645/110).
Figure 5.2: Parking Accumulation Curve
Existing parking demand requirements for 4-wheeler, Auto rickshaws and bicycles can be taken as the
hourly average volume counts, reason being that the demand volumes of 2-wheelers exceed by almost
five times as that of 4-wheelers, three times as that of bicycles, and five times as that of 3-wheelers.
Parking demand is highly dependent on following parameters:
i. Vehicular Growth rate in the city
ii. Land Use Pattern
64 66 6671
76 80 79 7668 64
5547
0102030405060708090
Nu
mb
er o
f V
eh
ices
Time Interval
2-wheeler Accumulation
2-wheeler
Accumulation
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
79
iii. Socio-economic condition of the land use
iv. Trip purpose and trip length
v. Mode of Trip
vi. Parking space availability
vii. Degree of Congestion
viii. Time of day
ix. Parking duration
x. Type of vehicle
xi. Cost of Parking Facility
xii. Number of Dwelling units
Apart from the above mentioned parameters there are other parameters that directly or indirectly affect
parking demand that include availability of public transport, seasonal variability etc. As observed in the
parking accumulation the average parking duration is 38 min. approx. with duration categories as:
i. Short Term Parking (< 1 Hr.)
ii. Medium Duration Parking (1 – 3 Hr.) and
iii. Long Term Parking (> 3 Hr.)
Parking demand management can now be based on these parking durations. According to Donald Shoup
optimal parking occupancy level should be 85% which minimizes cruising time and provides the optimal
level of pricing. Existing demand levels for Maninagar are as follows with 10 hours of demand in a day.
Cycle volume per day has been divided by 2 since half of the demand is being created by the school near
fire station. Table 5.44 gives the total 2-wheeler demand throughout the day for entire study section in
number of vehicles.
Time Interval
2-Wheeler 4-Wheeler
Pushpakunj
to AMC
AMC to Railway
Station Total
Pushpakunj
to AMC
AMC to Railway
Station Total
10:30 - 11:30 567 483 1050 63 36 99
11:30 - 12:30 507 586 1093 90 67 157
12:30 - 13:30 515 530 1045 52 67 119
13:30 - 14:30 332 399 731 47 26 73
15:30 - 16:30 313 436 748 50 62 111
16:30 - 17:30 419 581 1000 73 80 153
17:30 - 18:30 521 698 1218 60 99 160
6885 872
Table 5.3: Total 2-wheeler daily demand - Maninagar
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
80
2-wheeler demand for the complete day of operation is 9836 number of vehicles while 4-wheeler daily
demand is 1245 vehicles in the entire section of the street. Duration based classification of vehicles is
shown in the following table.
Section Time
2-Wheeler Duration
Volumes
4-Wheeler Duration
Volumes
30 min.
45 min.
90 min.
180 min.
30 min.
45 min.
90 min.
180 min.
Pushpakunj to AMC Building
10:30 - 11:30 203 104 33 0 24 11 0 0
11:30 - 12:30 181 93 29 0 35 15 0 0
12:30 - 13:30 184 95 30 0 20 9 0 0
13:30 - 14:30 119 61 19 0 18 8 0 0
15:30 - 16:30 117 56 5 5 22 3 3 0
16:30 - 17:30 156 75 6 6 32 5 5 0
17:30 - 18:30 194 93 8 8 26 4 4 0
AMC Building to Maninagar
Railway Station
10:30 - 11:30 157 65 40 19 11 10 3 0
11:30 - 12:30 190 79 49 23 20 18 5 0
12:30 - 13:30 172 72 44 20 20 18 5 0
13:30 - 14:30 129 54 33 15 8 7 2 0
15:30 - 16:30 138 98 16 6 27 6 0 0
16:30 - 17:30 184 131 21 8 35 8 0 0
17:30 - 18:30 221 157 25 10 43 10 0 0
Total 2345 1234 359 120 338 132 27 0 Table 5.4: Parking Duration Volumes – Maninagar
Section Vehicle Type Maximum Area
Required (m2)
Maninagar Railway
Station to AMC
Building
Cycles 125.2
2-Wheelers 660.8
4-Wheelers 662.5
AMC Building to
Pushpakunj
Cycles 340.5
2-Wheelers 544.0
4-Wheelers 625.0
Total 2958 Table 5.5: Maximum Area Requirement - Maninagar
It is proposed that the 3-wheelers and Cycles shall not be charged for using parking facility and shall be
provided with free parking space based on the peak demand volume. Total peak volume requirement of
these two modes are 166 no. of cycles and 44 no. of 3-wheeler at Maninagar Railway Station to AMC
Building and 454 no. of cycles and 26 no. of 3-wheeler at AMC Building to Pushpakunj. These daily
volumes of 2-wheeler and 4-wheeler and peak volume of cycles and 3-wheelers can be employed to
generate design options for on-street and off-street parking facilities.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
81
5.1.3 Parking Scheme Physical Design Options (Nirav)
This exercise tries to provide with a demand management mechanism that can be applied to the entire city
to accomplish the said objective of bicycle and pedestrian promotion and traffic demand management.
The process of accomplishment of this goal is gradual and in several phases which employees Based on
the above calculations we need to propose on-street parking lot for existing peak demand volumes of 620
cycles, 70 3-wheelers and daily turnover of 9840 2-wheelers and 1245 4-wheelers. For off-street parking
design we consider only 2-wheelers and 4-wheelers for the following reasons.
i. One of the objectives of the project and the policy is to promote non-motorized and public
transport.
ii. Parking 3-wheelers in an off-street parking lot is not possible since boarding and alighting through
this mode is done on-street.
iii. Charging 3-wheeler either on-street or off-street is not feasible taking into account the socio-
economic condition of the operators of this mode.
iv. Physical space requirement for the observed volumes of these modes is very less in comparison
with 2 and 4 wheelers.
v. Parking duration and accumulation of 3-wheelers is generally less than 30 minutes.
vi. These modes of transport (bicycles and 3-wheelers) are mostly owned and operated by lower
income group that cannot be burdened by parking pricing.
On-street and Off-street parking options
Total available space on-street as per the assumptions in section 5.2.3 is 4373 m2 and the peak hour
demand is 69.7% i.e. 3050 m2 of the peak hour demand. This demand is distributed between Section1
(Maninagar Railway Station to Maninagar Cross Road) – 914 m2 (21%)
, section-2 (Maninagar Cross
Road to AMC Building) – 1220 m2 (28%) and section-3 (AMC Building to Pushpakunj) – 2238 m
2
(51%). With BRTS being constructed on this road the parking space gets further reduced from this value
and is 3160 m2. Details of which have been provided in section 5.4.1. Physical design options have been
provided in following form that are:
i. On-street parking facility for the complete length (except for spaces that include junctions,
bus stops, fire station frontage, building entrances, petrol pumps etc.)
ii. On-street parking in combination with off-street parking lot (on-street excludes the spaces as
mentioned above)
iii. Off-street parking facility for the entire length under study (facilitated by enforcement in form
of no provision and ban on on-street parking)
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
82
This section discusses on-street physical design options and on-street portion of combined parking
scheme. On-steer parking consumes considerable space of the RoW that could have been otherwise used
to developed pedestrian space, street hawker space etc. Parking patterns have been discussed in literature
study, we shall thus adopt 2-wheeler parking perpendicular to the kerb and 4-wheeler parking shall be as
parallel to the kerb. This land space has a cost and thus needs to be charged from the user. Option 1 i.e.
provision of complete on-street parking for the demand levels has space distribution as shown in the
table.
Section Parking Area
Available (m2)
Parking Area
Demand (m2)
Cycles
Demand (m2)
2w Demand
(m2)
3w Demand
(m2)
4w Demand
(m2)
1 605 874.95 93.75 371.2 210 200 2 945 577.73 30.75 174.4 35.08 337.5
3 1610 1596.72 340.5 486.4 144.82 625 Table 5.6: Parking Area Demand (Modewise) Peak Hour – Maninagar
Based on the above level of demands it can be seen that peak demand requires 3049 m2 of area which is
96% of the total available space. According to studies by Donald Shoup (1999) considering an optimal
level of supply as 85% can be considered as a base demand for the facility. This demand level includes
factor that considers cruising time which in this case is almost zero. With above levels of space
availability the demand as percentage of supply in peak hour is 145%, 61% and 99% respectively. This
demand therefore has to be shifted to other location or other mode. This option shall emphasize on
following areas.
i. Reducing trip frequency by converting multiple trips in a day to single or least possible
number of trips.
ii. Number of trips shall be reduced and would be made on the criticality of the work once
imposed with a charge for the facility.
iii. Make attempt to convert long distance trips made on private vehicle to shift the mode to
possible low cost option or public transit facility.
iv. Distribute the localized high parking density over a larger length to ease the congestion by
limiting the supply to an optimal level in specific sections.
v. Shifting existing on-street parking to existing off-street parking facilities through supply
management and pricing the service.
The design provides space for existing on-street peak load and considers that the future demands shall be
catered by off-street parking lots. The study also provides with off-street parking facility option that can
be implemented at a later point of time after analyzing the demand levels. As an initial guess of supply
levels, following table shows four options at 85%, 75%, 65% and 55% occupancy level in all the three
sections. The on-street supply shall be distributed among all the three sections after evaluating the site
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
83
conditions. Looking to the above levels of demand we need to accommodate the extra 45% demand to in
the design by allocating alternative location. This 45% extra demand requires an area of 270 m2 and needs
to be shifted to alternative location. Possible alternative locations are:
a) Western side of the street along the railway station (near sindhi market) where AMTS buses are
currently being parked.
b) Perpendicular street on north and south from Maninagar Cross Road.
Shifting this demand to any of the above mentioned alternative location would add to the existing
congestion on these streets. Possible alternative is to shift the extra demand to section-2 which has an
additional space of 367 m2 and can accommodate the existing demand on these perpendiculars. Upon
observing section-1 we find peak demand of 28 3-wheelers that can be provided with a supply capacity of
12 vehicles reducing the demand by 120 m2. Further more part of 2-wheeler trips made for medium to
long term duration can be shifted to subsequent section-2 and this volume is approx. 26% of the peak
demand that reduces the demand in section-1 by 96 m2. This shift in parking location shall be facilitated
by incremental parking (pay more for long duration). Total shift in space allocation is 216 m2 with an
expectation that residual demand shall shift in perpendicular connecting streets with space requirement of
54 m2 that would include cycles and 2-wheelers. All the perpendicular streets connecting the major road
shall be enforced with no-parking regulation for such a length that does not create congestion on
intersection. Section-2 has fairly low demand levels and tries to accommodate part of demand from
section-1 with said assumptions. Section-3 has high level of cycle parking demand in the morning phase
that is created by a school opposite to the fire station and is proposed to accommodate 20% of the existing
cycle parking demand in this section. Car parking is proposed to be provided with 85% (531.25 m2) of the
demand since there are off-street parking spaces in the buildings that can accommodate the remaining
15% demand. Reason for current trend of 4-wheeler parking is that the existing off-street parking spaces
are least accessible and poorly designed. It is also proposed that 3-wheeler parking be provided at approx.
every 100 m with a capacity of 3 nos. in one lot with total number as 36 and an area of 270 m2. This
proposal is facilitated by deducting additional space from 4-wheeler space. The final proposal for design
with exclusively on-street parking catering peak demand is as follows with a total supply of 2646.5 m2:
Section
Cycles
(m2)
Number
of Veh.
2-wheeler
(m2)
Number
of Veh.
3-wheeler
(m2)
Number
of Veh.
4-wheeler
(m2)
Number
of Veh.
1 93.75 125 274.7 172 90 12 200 16
2 30.75 41 270.4 169 35.1 5 337.5 27
3 68.10 227 486.4 304 270 36 499.82 40
Total 192.60 393 1031.5 645 395.1 53 1037.32 83 Table 5.7: On-street Parking Design Space Allocation – Maninagar
Second option is provision of parking facility in combination of on-street and off-street parking facility.
Now all the designs are being considered with no charging for cycles and 3-wheelers either on-street or
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
84
off-street. Option of combination parking considers no-parking regulation in a specified cordon up to a
maximum possible distance that can be covered by walking which is approx. 150 m, reason for this being
the parking duration of major portion of demand is less than 30 min. Analyzing parking demand in this
cordon peak hour volume for 2-wheelers is 179 vehicles and 4-wheelers volume is 38 vehicles that
demands an area of 762 m2. This area is only 25% of the plot area that can be expected to use the off-
street parking facility. It can be proposed to attract complete cycle parking demand generated by the
school to mitigate safety and congestion issues and create a no-parking zone on-street. We therefore
propose a free off-street ground level parking lot for all the category of vehicles. Third option considers
proposing exclusive parking lot for entire length converting kerb side into no-parking zone which
increases walking distance from 150 m to 700 m on the main street on either side. This would require
high level of enforcement in form of restricting entry of vehicles from the perpendicular streets, dedicated
pedestrian spaces by removing complete parking spaces. The existing condition of enforcement in the city
needs to build its capacity in order to meet the requirements of this proposal. It is thus proposed to
implement on-street parking facility through various enforcement mechanisms which are as follows.
i. Cordoning off an area of width 50 m on either side of the main street and enforcing no-parking
regulation on perpendicular streets.
ii. Shutting down few streets perpendicular to the main street and restricting spillover of parking to
residential spaces.
Enforcement has been discussed in detail in chapter 7 that proposed various enforcement actions. It is
thus proposed to implement a paid on-street parking facility in combination with free off-street parking
lot. The subsequent section discusses management option proposed to operate the facility. Following
diagram shows the typical cross-section of the street with parking bays, and plan view of the street with
design features.
5.1.4 Management Options (Ambika)
As a part of parking demand management, pricing the facility is one of the efficient mechanisms.
Maninagar parking pricing has been considered as a base to understand and devise a general mechanism
that can be employed to regulate parking demand management. Management options for parking facilities
are either manually operated, automatically operated or by a combination of both. On-street parking is
generally 10% of the cost of off-street parking facility. Following options have been identified to manage
the proposed on-street parking facility.
i. Manual paper ticketing system
ii. Smart card technology with portable meter and e-ticketing system
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
85
iii. RFID Technology
On evaluating all the above mentioned management systems we find that Manual paper ticketing system
that is being currently used at C G Road and multi-level parking at Relief road is resulting in high level of
inefficiency and inaccuracy. As reported by the management officer of C G Road parking facility nearly
20% of the parking vehicles don‟t get charged for using the facility due to various reasons. Later two
techniques have not been implemented in the city yet and therefore need to be examined for their
viability. Following table shows comparison of proposed technologies to operate and control the on-street
parking facility at Maninagar over the length of 1650 m.
Sr.N
o.
Parameter Manual Paper
Ticketing
Smart
Card
RFID (DSRC)
1 Level of technology required Low Medium High
2 Cost of Desired technology Low Low High
3 Control Capacity Low Medium High
4 Skill Level Required Low Medium High
5 Enforcement Required High Medium Medium/ High
6 Degree of Awareness among
citizens
Low High High
7 Degree of Error High Low Low
8 Level of Vehicle Safety Low Medium Medium Table 5.8: Comparison of Parking Management Systems
Manual paper ticketing system has limited applicability and functions efficiently for a system with
smaller size. The existing schemes are currently being operated by private operators and the municipality
earns fixed revenue per annum that is not being used anywhere in development of parking condition in
the city. This system of fare collection is now proving to be incapable of catering to existing grown
volume of parking demand with reduced efficiency and effectiveness. Fees collection is done on site by
attendant who generally cannot calculate exact amount based on parking duration. This system therefore
can work efficiently when flat rate for long parking duration is charged that results in attracting long term
parking vehicles. It simultaneously penalizes short term parking vehicles by charging for duration much
higher than actual.
RFID and Smart Card technologies are two alternatives for reliable and automated operation of parking
systems. Both the technologies have high end options that need to be configured according to the site
requirement. These systems have not yet been used anywhere in the city. Chapter 3 discusses these
technologies and based up on the level of complexity in RFID system in terms of awareness among
citizens, support from enforcement agency, adaptability, requirement of skill level to operate in existing
parking behavior and conditions it is proposed to opt for a technology that is one stage lower. It would
also be difficult to judge the performance level and cost effectiveness of such hi-tech system in first stage
of implementation of parking management in the city. High end RFID system needs to have RFID tags on
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
86
each vehicle that uses the parking lots or enters congestion prone zone. Cost of equipments involved in
installing this system is high as compared to smart card technology.
Smart Card technology in combination with human intervention is an alternative that could be evaluated
for proposing pilot project of parking scheme to achieve a common parking demand management
mechanism for the entire city. Two options proposed for smart card based management have been
described below with the costs and components involved.
Option 1 Option 2
Fixed Parking Meters on Street
(Electronic) -
40,000 Rs. Portable Parking Meters
(electronic) – With Printing Facility
9,500 Rs.
Simple Storage Smart Card
(Magnetic Strip – 2 KB)
75 Rs. Simple Storage Smart Card
(Magnetic Strip – 2 KB)
75 Rs.
Underground wiring 180 Rs./m Connectivity Tower 35,000 Rs.
Backend Processing Software 80,00,000 Rs. Backend Processing Software 80,00,000 Rs.
Mainframe Computer 2,50,000 Rs. Attendants (Salary/month) 4,000 Rs.
Mainframe Computer 2,50,000 Rs. Table 5.9: Smart Card Technology Options
Total number of bays available for each category of vehicles that includes 2w, 3w, 4w and cycles is 691,
74, 101 and 506 respectively. The cost to manage one parking bay for different category of vehicle has
been calculated in later section of the chapter that derives a pricing model for the proposed scheme. Cost
of managing the parking space shall depend on the supply level variation. Out of the above two options
following are the issues that need to be addressed during operation.
Option – 1
i) It needs to be ensured that every parking vehicle uses the meters fixed on –street to pay
parking charge
ii) Safety of these equipments placed on-street is one major issue in the proposed management
plan
iii) Awareness among all the stakeholders like citizens of the city, enforcement agency, regulator,
management and operation team is necessary
iv) High volume of 2w makes it difficult to keep vigilance on every parking lot
v) Such a high end management system if requires vigilance and supervision staff would add to
costs
vi) Capacity of agencies involved in the execution and operation of the project needs to be
checked
vii) Marketing and enforcement of the scheme needs to be done efficiently
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
87
Option – 2
i) The system needs to be manned at every 100 m on either side which requires 33 attendants
approximately.
ii) Skilled staff and training system needs to be available to run the system
iii) Incentive to the attendants and enforcement staff should be provided to ensure dedicated
service and no fraud
iv) Awareness and marketing among citizens of the city needs to be brought
Specifications for some of the items mentioned in the above table are as follows:
i) Initial volume of smart cards to be manufactured is 2,250 and shall be purchased from
qualified manufacturer with reorder level at 75% sale.
ii) Monthly requirement of cards shall be 900 with an estimate of 20% medium to long term
vehicles buying them
iii) Option-1 shall have the meters connected to the control room through underground wiring
while option-2 shall have wireless communication
iv) Monthly sale of smart cards is estimated to be 4500 based on the medium to long term 2w and
4w parking vehicle volume.
5.1.5 Pricing and Financial Model (Nirav)
Parking pricing is one of the several mechanisms to manage parking demand or congestion. For the
desired study there is very little existing data and negligible past data that can help to start any such study
for the first time in a city like Ahmedabad. Parking pricing has thus been selected as a tool to investigate
and regulate the existing parking demand and achieve the objective of promotion of pedestrian movement
and bicycle use. Maninagar has been selected as the pilot case to understand the parking behavior and
implement parking management program. Parking till now has been provided as a cross subsidized
service that if charged at its true economic cost to the user would not be affordable to everyone. As the
study says on-street parking in combination with free off-street parking lot is a suitable strategy to
allocate space for existing demand, we try to derive a pricing mechanism that makes the scheme
financially viable. Three pricing schemes have been proposed out of which the most efficient one shall be
recommended. Following are the pricing schemes proposed.
i. Flat Rate pricing scheme – The parking fees under this scheme shall be for a long duration in first
slot eg. for 4 hours and additional for subsequent hours. The study shows that average parking
duration for vehicles at Maninagar is 38 min. which is much lower than the time duration of first
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
88
slot. Volume of long term parkin vehicles is also less than 10%. This scheme is invariably
promoting long term parking vehicles and thus promoting congestion by penalizing short term
parking vehicles. This scheme is currently being employed at Kalupur Railway Station off-street
parking facility and provides service to daily commuters from the railway. Charge for 2-w is 5 Rs.
While 4-w are charged 10 Rs. This scheme is not based on any demand management principles
and has been put in place to generate revenue from railway land. This pricing scheme can be
directly rejected since the demand management mechanism does not intend to penalize short term
parking vehicles by imposing long term fees but tries to provide incentive to short term trips
having minimum frequencies by charging lower fees in proportion to long term parking vehicles.
ii. Hourly Parking Fees – The fees for every hour is same and thereby increases in a linear pattern.
Existing on-street parking facility at CG Road adopts this scheme and the fare currently being
charged has been described in section 5.3.4. This pricing is an hourly flat rate mechanism that
does not incentivize short term parking vehicles over long term parking vehicles. Since past data
was inexistent in term of volume of vehicle category it was difficult to determine the price
elasticity of demand. This can be considered as one of the pricing strategies to be implemented.
iii. Short Term Incremental Pricing – This pricing strategy is currently not being practiced anywhere
in the city. Basic concept of this mechanism is classifying parking vehicles in smallest possible
time slots based on the average parking duration. The study adopts 30 minutes as the minimum
time slot for parking since average parking duration is 38 min. Parking fees in this mechanism
rises with fixed percentage over previous time slot to regulate and minimize long term parking
vehicles.
Objective of pricing mechanism is to achieve objectives of demand management in form of reduction in
parking duration, reduction in frequency of trips, shifting out long term parking vehicles from congestion
areas, provide controlled parking space and easy traffic movement etc. The proposed scheme provides
parking facility in combination of paid on-street parking system and free off-street parking scheme. There
are two basic costs involved which are; i) Physical Infrastructure costs and ii) Management Costs
Following flowchart shows the process of pricing for the proposed facility. This can be considered as
general pricing mechanism for demand management objective in the city.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
89
Following are the assumptions on which the model has been based:
i) Life of the project is 12 years after which the scheme needs to be redesigned (consultation
with CG Road paid parking facility management)
ii) Payback period of the project is considered as 3 years for computing parking pricing and
servicing the future demand through suitable review methods
iii) Project development duration is 12 months
iv) Growth rate of 2w is 21% per annum and 4w is 14% per annum with an average of 18% P.A.
v) Parking space for 3w and cycles shall not be charged in both on and off street spaces
vi) Pricing shall be designed for supply level of either 100% and/or 85% to propose pricing
mechanism
vii) Fees increment factor of 12% has been considered for every subsequent time slot for
incremental pricing over linear pricing model (Demand peaks and drops by approx. 12% in
morning peak)
viii) Facility shall be funded and operated/managed by the municipality considering risk free rate of
return of 7.5% (return on government bonds) and 5% rate of inflation for calculating break
even time or entirely contracted to private sector.
ix) The pricing shall be reviewed at the end of first year of operation and revised based on the
change in rate of return and increment in rate of demand
x) The demand is expected to double in every 5 year based on vehicular growth rate and land use
pattern (Traffic study GIDB 2004)
Type of Parking
On-street Parking Off-street parking Combined Parking
Physical
Infrastructure Cost
Management Cost
Smart Card RFID System Manual Collection
Pricing Scheme Fixed Meter System Portable Meter System
SCHEME 1
SCHEME 2 SCHEME 4
SCHEME 3 Hourly Linear Pricing
Incremental Short Term
Parking Pricing
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
90
xi) Off-street parking lot is at ground level and provided free of to the users
xii) There exists no subsidy component in the model and the price increment is taken as 10% YoY
which is subject to change up on the annual review of the project
Limitations to this modeling are as follows:
i) There exists no past data that can provide a base price to start with and understand the price
elasticity of demand.
ii) The proposed case has no formal parking arrangement existent
iii) Schemes like park and ride facility, off-street parking space sharing etc. cannot be
implemented currently since trip lengths are short and off-street spaces are of low capacity
iv) The model has three basic parameters of demand, supply and price out of which one needs to
be kept constant (supply).
Following tables broadly show the costs involved in developing the scheme in terms of physical
infrastructure cost and management cost.
Project Option Cost (Rs.)
1 Option 1 (Fixed Meter on-street) 5.44 (4.62 + 0.82) Crore
Variable Cost / Day 6660 Rs.
2 Option 2 (Portable Meter) 5.52 (4.62 + 0.90) Crore
Variable Cost / Day 9350 Rs.
Table 5.10: Project Cost Options
As shown in the above table the parking scheme provides with two options that shall be checked for
linear and incremental pricing for two supply levels of 100% and 85%. This shall require provide us with
eight pricing alternatives out of which one has to be implemented according to the operational issues and
conditions. Following table shows the expected revenue per ECS per day at two different supply levels.
Options
Supply Level Option 1(Fixed Meter) Option 2(Portable Meter)
100% 122 120
85% 144 141
Table 5.11: Expected Revenue Comparison
Based on the above table we find that the revenue difference between option-1 and option 2 is marginal
while the operational issues are more complicated in fixed meter system than portable meter system in
terms of enforcement, awareness, institutional setup etc. It is therefore proposed to provide portable meter
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
91
smart card run pricing scheme. Further if we provide 100% of the capacity then the existing off-street
parking spaces remain idle and don‟t operate to their full capacity. Existing peak demand is of an area
3050 m2 that is almost 15% higher than the proposed area of supply. The space design also makes 15% of
the peak hour volume shift to off-street parking spaces or other alternative spaces.
As proposed, pricing shall be applicable only to 2w and 4w volumes with 30% deduction in daily revenue
as experienced at C G Road. This deduction is because of absence of attendant, problems with meter,
break time/shift change and/or other reasons. Daily cost per ECS of the project is 22483 Rs. And daily
demand is almost 3212 ECS with 320 ECS during peak hour. 2w turnover is high that contributes to high
daily ECS volume. Preliminary fare calculation is done by calculating expected revenue per day at 12.5%
RoR which is 120 Rs./ECS/day. This amount gives break even at 7 years and 10 months which cannot be
considered as an appropriate pay back duration if the work is supposed to be contracted. Pricing schemes
were therefore calculated taking into consideration different pay back periods and a pay back period of 4
years was found to provide with acceptable pricing scheme. This calculation gave following linear and
incremental pricing scheme.
Linear Pricing Scheme
The expected daily revenue was distributed between both the vehicle categories based on the % of
vehicles in different time slots.
Table 5.12: Linear Pricing Scheme
The pricing scheme gives a payback period of 4 years but has certain drawbacks as follows:
i. The duration slots are hourly that don‟t incentivize the short term parking vehicles
ii. Due to linear pricing possibility of converting long term parking in to short term parking
reduces since hourly fess is same.
Incremental pricing scheme tries to minimize long term trips by charging exponentially higher than short
term parking vehicles as per the following pricing scheme.
Vehicle Type 1 hr 2 hr 3 hr 4 hr 5 hr Monthly
revenue
2-Wheeler 6 12 18 24 30
Number Of
Vehicles 8747 796 218 62 0 1416366
4-Wheeler 10 20 30 40 50
Number Of
Vehicles 850 394 49 24 12 407682
1824048
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
92
Incremental Pricing Scheme
Vehicle Type 30 min 1 Hr 1.5 Hr 2 Hr. 2.5 Hr. 3 Hr. 3.5 Hr 4 Hr.
Monthly
Revenue
2-Wheeler 3 6.36 10.12 14.34 19.10 24.35 30.27 36.90
Number of
Vehicles 5729 2264 754.56 530 265 124 94 62 1260706
4-Wheeler 10 21.2 33.75 47.80 63.53 81.20 100.90 123 Number of
Vehicles 850 321 49 24 12 0 0 0 396446
1657152
Table 5.13: Incremental Pricing Scheme
This pricing scheme collects less revenue than linear pricing but has fair chance of converting long term
trips to short term trips and increasing the turnover. Other pricing schemes can be time of day pricing,
eco-pricing (based on emission levels of different vehicle categories), real time pricing (based on
instantaneous parking demand).
Implementation of any of the above scheme and the success depends highly on the field staff and
collection mechanism on ground. Two major contributing factors for success of any parking scheme are
enforcement and institutional arrangement to operate and manage the facility. Next section discusses the
detailed management plan for the city based on results derived from the above studies.
5.2 Demand Management Plan (Nirav, Ambika)
The flowchart shows the parking management mechanism in detail that includes all the aspects ranging
from technical studies to institutional framework and future demand management. Parking demand
management as per literature analysis can be done in following three ways;
i. Parking pricing
ii. Regulating supply and
iii. Enforcement mechanism.
Major factors contributing to the development of any parking plan are demand, supply availability and
pricing possibility. The service involves several stakeholders that include the municipality, traffic police,
citizens, city police and media. The flowchart tries to define a mechanism that can help the municipality
to develop a common parking plan applicable to parking demand on spaces under its governance. The
process tries to involve all the stakeholders and set a general guideline that can be applicable to any
further study on this issue in the land under limits of AMC.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
93
Parking Demand Management
Identification of City
Characteristics
a. Broad Land Use Pattern and
Economic Structure
b. Demographics
c. Vehicular Ownership Pattern
d. Road Network Pattern etc.
Determining Study
Zones and Area of
Extent
Physical Maps, Governing
Limits, Extent of
Application of Study etc.
Representative Case Selection
to be Studies in Detail
Literature Studies
Data Collection
Primary Data Secondary Data
Schedule of Rates
Tech. Alternatives and Cost
Manpower and Enforcement
Cost
Building Use Conversion Data
Site Survey Based
Parking Volumes, Accumulation,
Land Use, Inventory, Duration,
OD & CVC.
Questionnaire Based
Parking Vehicle Interview (Trip
Purpose, Trip Length, Trip
Frequency)
Selection of Location for Pilot
Project
Primary Data
Analysis
Identification of Stakeholders and
Understanding their role (existing)
in the study
Stakeholder Consultation
A
A
Management
Options
Development
Schemes
i. Paper Ticket
ii. RFID Tags
iii. Smart Card
etc.
i. Park n Ride
ii. Time Limits
iii. Parking
Free Days
iv. Pricing etc.
Detailed Site Analysis
(Physical Characteristic
Analysis, Parking
Behaviour Analysis etc.)
Demand Assessment and
Physical Design Options
Critical Site Analysis
(Demand in different
sections, site specific
observations, travel
pattern, land use
impacts, congestion
zones etc.
i. On-street
ii. Off-street
iii. Combined
Final Design
Proposal
B
C
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
94
Based on the studies conducted in the city the demand management plan is the basic framework that can
be adopted to propose a parking management program and facility for any street in the city. One of the
objectives of the study is policy formulation that shall regulate parking in the city through fair
management mechanism. AMC is responsible for the overall implementation, management and operation
of parking facilities in the city. The process takes into consideration all the stakeholders who can
substantially contribute to the policy formulation through mutual consultation with the administrative
authority i.e. AMC and AUDA.
B
Development of Detailed
Management Plan – Site Specific
Eg: On-street Paid
Parking (Maninagar)
Enforcement Plan Operational Plan
Pricing Scheme &
Financial Model
Detailed Management
Team and Field Staff Role of Traffic Police
Towing Operation
Details
Incentive Model
Penalty Structure
Annual Review of
Operations &
Feedback
Technology and
Management Inputs
from Literature
AMC Functions
Management &
Future Demand
management
Decision on
Outsourcing
Feedback from
Users and
Consultation
from Experts
Existing Norms
and Regulation
and Legal
Framework
C
Policy Formulation
Contribution from Consultants &
Other Stakeholders
Management
of Facility on
PPP Basis
Awareness among
citizens through
media and
publicity
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
95
There is also a need felt to revise the existing parking norms in the GDCR that shall try to minimize
parking space provision in new building developments. This would be done with an objective to de-
motivate the use and purchase of personal transport.
The plan tries to make the management and development of parking condition as a separate institution in
the city. It can be expected through this plan that the administrative authority can sustain the facility
without contracting out the management of any facilities that it proposes to develop.
Major issues that need to be addressed currently are capacity building of the regulating institute i.e. AMC,
traffic police department, enforcement and public awareness. The feedback process provides room for the
institutional capacity building and continual improvement of management practices of parking facilities.
Enforcement is also one grey area that needs to be worked up on to achieve desired efficiency in
operations and minimize the rate of parking infringements. Following are the existing issues and
recommendations to improve the enforcement condition in the city.
Issues in Enforcement
i. Traffic police department currently practices traffic enforcement operations in the city and has
limited staff to carry out enforcement operations in the city
ii. The traffic enforcement operations (towing) have been outsourced to private operators who
lack in efficiency and fleet
iii. There are total of 20 towing trucks for the entire city and very less number of impoundment
areas
iv. There are only eight impoundment areas in the entire city and are gradually being used by the
municipal authority to build different facilities like shopping complexes and public buildings.
v. Majority of the parking infringements are settled on site through bribes which is usually an
amount of 50 Rs. For 2-wheeler and 100 Rs. for 4-wheeler against an official fine of 100 Rs.
and 200 Rs. respectively.
vi. Condition of towing fleet is bad with several breakdowns of towing trucks and absenteeism of
towing crew.
vii. Growing number of vehicles in the city is major hurdle for a limited number of traffic officials
since it becomes difficult for them to control such a huge volume
viii. Number of infringement on majority of the streets exceed beyond the capacity of towing crew
deployed for particular street or area.
ix. Lack of awareness among the citizens towards traffic rules and parking behavior is also one of
the major contributing reasons for deteriorated parking and traffic conditions in the city.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
96
Recommendations for Enforcement
i. Penalties for parking or traffic infringements should be increased from the existing levels since
amount spent by the offender to bribe the official is highly affordable
ii. Incentive mechanism should be introduced and towing crew and police official should be
incentivized from the penalty charges collected from the offender
iii. Currently payment to outsourced towing operators is done on daily mileage basis which
should be converted to reported number of infringements per day
iv. Training of the enforcement crew should be done to minimize inefficiency and spread
awareness among citizens for traffic and parking rules
v. Involvement of media should be done to spread information of parking improvement program
and involvement of all the stakeholders should be done by conducting seminars and public
campaigns
vi. Fleet size in form of towing cranes, towing crew, interceptor vans, enforcement inventory etc.
should be increased from revenues collected from parking
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
97
Chapter 6: Conclusion and Recommended Policy Directives
Conclusion has been presented in form of policy directives that have been derived from the analysis and
observations of the study undertaken. Following is a draft of policy directives that can be recommended
to the policy maker for formulating a detailed parking policy for the city and parking demand
management programs.
We recommend that AMC/AUDA adopt a comprehensive parking management system with the
following goals:
Improving the quality of public spaces for pedestrians, cyclists, and hawkers
Reducing pollution, noise, and congestion by discouraging the use of private motor vehicles
Raising revenue for public transport and for bicycle and pedestrian infrastructure
As a first step, we suggest that AMC/AUDA implement pricing pilot schemes in two or three business
districts. In the long-run, AMC/AUDA should create a structured and organized parking plan for the
entire city, based on the density and character (residential, commercial, mixed use, etc) of each area. The
plan should address on-street parking as well as the Development Control Regulations that govern the
provision of off-street parking. The following policies guidelines/recommendations can help guide the
pilot projects and the drafting of the overall parking plan.
(1) On a case-by-case basis, AMC/AUDA will designate areas where parking is allowed.
Haphazard parking interrupts pedestrian space and creates congestion by blocking the movement of
through traffic. Based on the amount of vehicular traffic on each road, AMC/AUDA should
determine how much road space can be allocated for parking where necessary. The parking areas can
be delineated through curbs, painted lines, and/or signage. CG Road is one example of a location
where physical restructuring of the road space has helped define where parking is permitted.
(2) AMC/AUDA will charge private motor vehicle users to park in designated parking areas.
Motor vehicle users do not pay the full cost of the public streets on which they operate and park their
vehicles. A parking charge can help ensure that these costs are borne by motor vehicle users rather
than the public at large. Parking fees are consistent with the National Urban Transport Policy, which
calls on local bodies to institute “a high parking fee that truly represents the value of the land
occupied.”
(3) AMC/AUDA will fine and/or tow vehicles that are parked outside the designated areas.
AMC/AUDA will forgo revenue if people can avoid paying by parking outside the area where
parking is charged. For example, car drivers who park on CG Road‟s main carriageway can avoid
paying the fee that is charged for parking in the bays accessed via the service lane. Where parking
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
98
causes congestion, enforcement can help prevent parked vehicles from encroaching on the area
reserved for through movement.
(4) Fees will be set to maintain an 85 percent occupancy level. Fees will vary geographically, by
duration, and/or by time of day. The fee schedule will discourage long-term parking.
Parking fees will be calibrated according to local circumstances since parking demand varies over
the course of the day and from one part of the city to another. The fee will be raised to the point at
which most parking spaces are occupied, but not so high that drivers circle around looking for an
open area in which to park. International experience suggests that this balance can be struck at an 85
percent occupancy level. The rate can increase as a function of time to discourage all-day parking.
Many prime on-street parking spaces are occupied by shopkeepers' vehicles for the entire day,
reducing the amount of space available to customers. Variable charges are recommended in the
National Urban Transport Policy.
(5) The fee for four-wheelers will be five times the fee for two-wheelers. Cyclists will not be
charged.
The differentiated fee structure reflects the fact that cars produce higher greenhouse gas emissions
and occupy more road space than two-wheelers. The parking policy aims to promote non-motorised
transport, so cyclists do not pay parking fees.
(6) A major share of the parking fee revenue will be returned to the area where it was collected.
To ensure that parking fees result in tangible benefits in the areas where they are collected, a share of
the parking revenue will be returned for local projects, which could include the construction of
footpaths, tree planting, or traffic safety improvements.
(7) AMC/AUDA will not spend public funds to build off-street parking.
Scarce public funds are better spent improving the public transport system and building pedestrian
and cycle infrastructure than building off-street parking. If AMC/AUDA begin charging for on-street
parking, building owners and developers will have more of an incentive to provide off-street parking,
at no cost to AMC/AUDA.
(8) AMC/AUDA will avoid conversion of existing open spaces which have potential for multiuse
activities and ecological value into multi storied parking structures.
(9) AMC/AUDA will urge the Gujarat government to reduce and/or eliminate ‘minimum’ parking
requirements in the General Development Control Regulations.
The current „minimum‟ parking requirements calls for a fixed amount of parking, whether or not
future residents or commercial customers are likely to need the space and regardless of the
neighbourhood context. For example, a centrally-located middle-income housing complex is required
to have the same proportion of floor area dedicated to parking as a high-end residential building on
the outskirts of the city whose residents will own cars. If AMC/AUDA limit on-street parking, then
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
99
developers will have an incentive to provide off-street parking whether or not the Development
Control Regulations require them to do so.
(10) AMC/AUDA will encourage residential building owners to sell or rent parking spaces
separately from the residential space itself. AMC/AUDA will help facilitate shared parking
arrangements among building owners.
Presently all residents of a building end up paying equal fractions of the capital and maintenance
costs of the parking area, whether or not they actually park vehicles there. “Unbundled” parking will
reward those who do not own vehicles. Under shared parking agreements, daytime and night time
users can share the same parking lot, thereby reducing the overall area required. For example, a
residential building could make some spaces available to office workers since the residents take their
vehicles out during the day.
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
100
Annexure
Annexure A: Shops/Offices questionnaire
Surveyor
Respondent
Shop/Office Name
Type of Business
Shop / Office Area Time since here
Sex Age Employee/Employer No. of Employees
Working Hours
Number and Type of vehicles brought by the staff
cycle 2w 3w 4w others
Monthly Business
weekdays weekends
Customers Visit weekdays weekends
number of trips per day by vehicle type
cycle 2w 3w 4w others
Parking area On Street
Off Street
If Off street then Shared Exclusiv
e
Paid Not Paid
Fare 2W 4W Others
Rank on a scale of 1-4 , parking difficulty for staff and visitors
1 Highly difficult
2 Difficult 3 Moderate
4 Easy
visitors parking area
On Street
Off Street
If Off street then Shared Exclusiv
e
Paid Not Paid
Fare 2W 4W Others
Rate on a scale of 1-5 the level of security in parking
comment on the parking conditions in your localty
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
101
Annexure B: Parking Vehicle questionnaire
Surveyor
Respondent
Type of Vehicle
Profession
Trip Purpose Frequency of trips
Parking Duration (min) or
Time of Arrival Time of
Departure
Type of Parking On
Street
Off Street
number of trips per day on the vehicle
If Off street then Shared Exclusiv
e Paid
Not Paid
Fare 2W 4W Others
Rank on a scale of 1-4 , parking difficulty
1 Highly difficult
2 Difficult 3 Moderate 4 Easy
Rate on a scale of 1-5 the level of security in parking
If provided with regulated parking how much are you willing to pay
comment on the parking conditions in your localty
Annexure C: On Street Parking Duration
Parking Lot 1 cycle time of entry time of exit parking duration
x1
x2
x3
x4
…..
xn
2 Wheeler
x1
x2
x3
x4
…..
xn
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
102
Annexure D: Parking Volume Counts - On Street Parking
Date Location Direction Surveyor
Vehicle type
Sr.No. Time Cycles 2Wheelers Cars Buses Auto Riskshaw Others Total
Nirav Vidwans (0727MPB), Ambika Pandey (0719MPB) MBA (Infrastructure) – TERI University
103
References
Barbara J. Chance, Summary of the Beirut On-Street Parking Improvement Program, World Parking
Symposium III, 2001.
BPMC (Bombay Provincial Municipal Corporation) Gujarat Act, 1999 (Act No. 3 of 1999.
David King, Michael Manville, Donald Shoup, Elsevier, The political calculus of congestion pricing,
Transport Policy 14 (2007) 111–123.
Deren Han, Hai Yang, Congestion pricing in the absence of demand functions, Elsevier,
Transportation Research Part E 45 (2009) 159–171.
Detail Project Report, BRTS Phase-II, Ahmedabad Municipal Corporation, August 2008.
Donald Shoup, The high cost of free parking, Journal of Planning and Education Research, 2001, vol.
17, pp. 3-20.
Economic Survey of Delhi, Chapter – 12, Transport, 2005-06.
Environmental Pollution (Control and Prevention) Authority, Briefing Paper, Feb 5, 2009.
Gujarat Development Control Regulations, 1999.
Ian Maher, Pricing Municipal Parking to Enable Mobility, Science Direct, 2002.
Khanna S.K., Justo C.E.C, Highway and Transportation Engineering, Nemchand Brothers, 1976.
National Urban Transport Policy, Ministry of Urban Development, GoI, 2001.
Perth Parking Policy, Transport Report 393, May 1998.
Robert W. Poole, Jr. and Benjamin Dachis, Congestion Pricing for the New York Airports: Reducing
Delays while Promoting Growth and Competition, December 2007.
TDM Encyclopaedia, VTPI, Parking Evaluation, Evaluating Parking Problems, Solutions, Costs, and
Benefits, 22nd July 2008.