limit states in construction_mendis
TRANSCRIPT
-
8/2/2019 Limit States in Construction_Mendis
1/34
102
NEW LIMIT STATES IN CONSTRUCTION
3.1 Construction Optimisation
Although the structural cost forms a relatively small portion of the overall development cost,
the structural component is a critical path activity for multi-storey building construction.
Therefore it is imperative that the structural design focuses on a solution that considers
construction time as a leading parameter.
The optimisation process of the construction process can be broken down into three broad
areas:
Optimisation of labour and time to complete the building.
Optimisation of construction time. Design for construction time.
Optimisation of labour and time
Studies have revealed that labour can account for as much as 50% of the total cost of
construction. For concrete structures the labour can be minimised in two ways. The first is by
extensive use of factory made prefabricated materials which typically use lower man-hours.The second is to minimise the labour associated with formwork, by using systems which can
be reused many times.
Optimisation of Construction time
There are tremendous financial benefits of early completion. Early completion not only lowers
the interest bill, but will also attract an early income stream in the form of rental income frompotential building occupants.
Recent trends in the construction procedures to increase speed of construction include:
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
2/34
103
Carrying out demolition of existing structures, bulk excavations, piling and excavation
protection structures over the site, concurrently with the design and documentation of
the redevelopment.
Use of sophisticated formwork system to construct the lift cores as quick as possible,
well advanced from the remainder of the construction, providing more time for the
critical activities of lift installation and vertical service distribution. Structurally the core
typically forms part of the necessary vertical and lateral support system during the
construction phase.
Early completion of finishes generally governs building completion. There is a growing
trend to complete floor levels, clear of all formwork, as quick as possible providing the
various trades with a clean working platform to proceed with the labour intensive
service installation.
Construction systems incorporating High-performance concrete provide a highly-effective
solution to address the above objectives.
With reference to Fig 3.1, it can be seen that for nearly 80% of the construction period the
construction of structure is the critical activity.
Fig 3.1 Simplified chart of High Rise construction
From these facts it may be concluded that structural designers need to focus their efforts in
developing structural systems and details to suit faster construction. The traditional least cost
structures rarely optimise construction speed and more importantly rarely minimises total cost.
A cost premium on the structural components may be involved, and therefore a cost benefit
study should be carried out to ensure that there is a cost benefit on the total development
cost.
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
3/34
104
Construction systems incorporating High-performance concrete (HPC) provide a highly-
effective solution to address the above objectives.
Construction of some key components is discussed below.
Core Construction
This section will discuss aspects of core construction
For tall buildings the core forms the principal structural element for both the gravity
load-resisting system and the lateral load-resisting system, with the latter becoming
increasing important with increasing height of the building. The size and location of
the core is predominantly governed by architectural considerations.
The cost of the core for a typical tall building is estimated to be 38% of the total
structural cost or 4 to 5% of the total development cost. The core is typically the critical construction activity for high-rise development. Any
delay in the core construction will not only delay construction of the other structural
components but will also delay all other activities associated with architectural and
mechanical-electrical services.
Important factors that govern core construction time are:
- To employ an efficient formwork which is readily available and requires minimum
set-up time
- To minimise transitions in the shape and size, up the height of building
- To minimise the number of transitions in wall thickness. Transitions take up
valuable construction time. This can be achieved by greater use of varying
concrete strength and reinforcement content to increase wall strength.
In Australia, and many other countries, introduction of high strength concrete with 28
day strengths of up to 120MPa has made reinforced concrete a feasible option for tall
buildings which demand large force-resistant capacities in the core walls.
- Compared to Steel, Materials for reinforced concrete are readily available with
minimum lead times. Also strengths can be modified at short notice without
changing wall thickness, which may have architectural implications, by changingthe reinforcement content or concrete strength.
- With the core construction being on the critical path, design changes are
inevitable. Reinforced concrete can cater for modifications with relative ease.
The importance of speed of core construction is reflected by the fact that advance
formwork systems have been developed specifically for core construction. Although
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
4/34
105
the initial capital cost of such formwork system is high, up to $1M, the savings
associated with reduction in construction time will more than offset this penalty.
The two most common advance formwork systems employed for core construction
are:
- Slip-form - where the concrete is poured continuously whilst the formwork is
continuously slipped up, by use of hydraulic jacks anchoring off the set concrete
below. This is a 24 hour per day operation requiring skilled labour force. All
stages of operation such as placing of reinforcement, concrete supply etc., must
be reliable and efficient. Unplanned stops in the operation can be costly (Fig 3.1).
HPC with appropriate setting times for concrete is essential for slip-form
construction.
- Jump-form- a more traditional formwork system, where a storey height of core is
poured at a time. The formwork is supported off the poured core below. On
completion of the pour the formwork is jumped by another storey height, for the
next cycle.
These advanced formwork systems do not rely on the status of the construction of
other structural elements, as it is a self-supporting system. Therefore it is prudent to
complete the core as quick as possible, so on completion the costly system can be
removed from site and utilised on another project. HSC is essential for these systems.
Now innovative jump form systems have been developed (e.g. Eureka Tower
Melbourne) to jump 2 storeys at a time (Fig. 3.2).
Fig 3.2 Typical example of an advanced formwork system (Eureka Tower Melbourne)
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
5/34
-
8/2/2019 Limit States in Construction_Mendis
6/34
107
When combined with use of high strength concrete it becomes a very efficient column
system in terms of strength and buildability. Fig 3.3 illustrates how this form of
construction can be effectively utilised, with discrete activities taking place at several
levels simultaneously, in an orderly and uncluttered environment.
Fig 3.3 High-strength Concrete filled Steel tube column in High Rise applications
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
7/34
108
3.2 Early-Age Concrete Including Maturity Method to Predict the
Strengths
With the need of speed in construction, an accurate prediction of early age properties of high
strength concrete is important. The following section discusses the available methods in
predicting compressive strength of concrete at early age using a case study.
According to code procedures
The Australian Standard on Specification and supply of concrete AS1379 (2007) requires
concrete samples to be tested in accordance with AS1012 Parts 1, 8 and 9. According to
AS1012 (1999), the concrete samples are cured under standard-moist conditions where the
samples are subjected to constant temperatures of 23 2C and 27 2C for a standard
temperate zone and standard tropical zone respectively. In ASTM C192/C192M (ASTM
2007), the curing temperature is set at 23 2C. On the other hand, the Australian Concrete
Structures Standard, AS3600 (2009) and ACI 318 (2011) state that accompanying cylinder
specimens of the same concrete batch should be stored and cured under conditions similar to
those of the in-situ concrete. What constitute conditions similar to the in-situ concrete are
open to interpretation.
Temperature Matched Curing
The standard method of testing according to AS1012 (1999) prescribes a curing regime and
boundary conditions that are essentially different from those under which the in-situ concrete
is cured. Slabs have a high surface to volume ratio and while the top surface is exposed to
variable temperature profiles, the other surfaces are sealed by formwork. It is well known that
the curing temperature of concrete is an important factor governing early-age strength
development.
Temperature Matched Curing (TMC) is well established for assessing strength in-situ and is
widely used in the industry. TMC is a process by which test specimens of concrete, from a
representative sample of the concrete that is placed in an in-situ or precast element, are
cured by keeping them in a chamber at the same temperature as a pre-selected point in the
element. The TMC system can function under isothermal, near adiabatic, pre-recorded, and
even real-time profile conditions. The system is capable of accurately simulating the in-situ
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
8/34
109
Postcastinginput
temperatureRealtime
tem erature
OR
Water
bath
Heater/
cooler
Process
ControlOn/off
Temperature
Concretesamples
curing temperature variation by controlling the temperature of a water bath for estimating the
real strength development in concrete. The main components of a TMC system are depicted
in a schematic drawing (Fig 3.4).
The system has an embedded process controller to precisely regulate the curing temperatureprofile. Accurate temperature matching is enabled using proportional, integral and derivative
control of feedback temperature data obtained from sensors embedded into one or two
concrete specimens within the conditioning chamber. The sensors are part of the eight
thermocouple inputs located at the temperature controller. A thermocouple connected to one
of the eight thermocouple inputs is also permanently positioned in the chamber to provide
water temperature measurements. More details about the particular system can be found in
reference (Mak and Torii, 1995).
Fig 3.4 Components of TMC systems
Extensive investigation has shown that TMC is able to predict the in-situ strength. However,
the technology remains costly and inaccessible to small to medium manufacturers.
Maturity method
The maturity method is a common method used in predicting the early-age of in-situ concrete.
The maturity method is used to account for the combined effect of temperature and time on
the development of the hydration reaction and the mechanical properties of concrete. The
nonlinear maturity function based on the Arrhenius law, which is also known as equivalent
age function is defined by Eq. (3.1):
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
9/34
110
1 1
0
a
r
Et
R T T
et e t
(3.1)
Where:
te= the equivalent age at the reference temperature, Days
Tr= reference temperature, K
Ea= apparent activation energy, J mol-1
,
R= universal gas constant, 8.314 J mol-1
K-1
T= temperature of the concrete during interval ( t ), K
The reference temperature (Tr) is the standard cured temperature at which test specimens are
cured. In many parts of the world it is 20oC (293K). In Australia it is 23C in temperate zones
and 27C in tropical zones. Once the equivalent age is found, strength maturity functions
(presented in Table 3.1) can be used to find the strength at a particular age.
The procedure to use the maturity method in predicting the compressive strength of concretes
at early age is outlined below (Carino and Lew, 2001):
1. Cast cylinder specimens in accordance with AS1012 (1999). The specimens should
be cured under isothermal conditions (15, 23, 35 and 50C). Conduct compressive
tests at regular age intervals (1, 2, 3, 4, 7 and 28 days).
2. Plot the compressive strength of concrete from the tests (step 1) against the concrete
age for each curing temperature (15, 23, 35 and 50C).3. Conduct linear regression analyses to curve fit the strength maturity function to the
experimental data (step 2). From the curve-fitting process, the values of the
parameters kT, t0 and S are obtained for each curing temperature (15, 23, 35 and
50C).
4. Construct strength maturity curve for the reference temperature of 23C. This curve
provides prediction in concrete strength at different age when the concrete is cured at
a constant temperature of 23C. In order to use this curve to predict the compressive
strength of concrete that is subjected to various temperature conditions, the age at
which the compressive strength is predicted needs to be converted into an equivalent
age with a reference temperature of 23C.
5. To obtain the equivalent age (Eq.3.1), it is necessary to establish the activation
energy Ea. The activation energy can be obtained by plotting the natural logarithms of
kT versus the inverse of the curing temperature (15, 23, 35 and 50C). The negative
of the slope of the straight line equals the activation energy (Ea) divided by the gas
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
10/34
111
constant (R). In the absence of experimental data, Ea/R of 4200 as suggested by Day
(2006) can be used.
6. Using Eq. (3.1), Ea/R from step 5 and the in-situ temperature profile, determine the
equivalent age.
7. The compressive strength of concrete can be predicted using the equivalent age
calculated in step 6 and the strength maturity curve constructed in Step 4.
Table 3.1 Strength-maturity Functions and Parameters
Function Name Strength-maturity function Parameters
Linear
Hyperbolic
S=)
0(1
)0
(
ttT
k
ttT
k
S
(Tank and Carino, 1991)
S = strength at age t,
S = limiting strength,
kT = rate constant, 1/day,
t0 = the age at the start of
strength development
Parabolic
HyperbolicS=
)0
(1
)0
(
ttT
k
ttT
k
S
Knudsen (1982)
As listed above
Exponential S= S
te
Freiesleben and Pedersen
(1985)
t = age,
= a time constant (value 1 is
the rate constant kTfor this
function),
= shape parameter
PlowmanS= )log(Mba
(Plowman, 1956)
a= strength for maturity index
M= 1
b= slope of the line
M= maturity index
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
11/34
112
A case study
In this section, a case study of a post-tensioned slab of an apartment building in Melbourne is
presented to illustrate the maturity method. The prediction of concrete compressive strength
using the method will be compared with the in-situ compressive strength.
The slab has the surface area of approximately 570 m2. The thickness of the slab is 230 mm.
Thin copper-constantan type double T reusable thermocouple wires with cold junction
compensation and linearisation were used to measure the temperature variation at various
locations. Fig 3.5 shows the arrangement of the thermocouples in the slab cross section (100,
150, 220 mm, measured from the surface of the slab), one thermocouple measuring the
ambient temperature variation next to the slab and another one embedded in the ambient
cured cylinders cast beside the slab to obtain compressive strength predictions in accordance
with AS3600 and ASTM C31/C31 M. The measurement was obtained during the winter time
as the range of average daily temperature could be lower than that of standard 23 C. In this
case, the standard testing procedure following the Australian Standards AS1012 may not
accurately represent the in-situ concrete strength. In this standard procedure, the concrete
samples are cured under standard-moist conditions at constant temperatures of 23 2C for a
standard temperate zone.
Fig 3.5 Arrangement of thermocouple wires in the slab
Atypical
temperature
profile measured from the site is shown in Figure (see Fig 3.6). Some
small differences in temperature recorded across the slab depth can clearly be seen. The
thermocouple deeper inside the slab (Channel 3) records higher temperatures. The ambient
cured cylinder temperatures were generally lower than the temperatures recorded inthe in
situconcreteslab.
Timber
formwork
Datalogger
Thermocouple
measuringambient
conditions
Thermocouple
positions(mm)
Moulded
Cylinder
Channel1 10Concreteslab
Channel2Channel3
15
22
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
12/34
113
Fig 3.6 Typical temperature profiles obtained for the thermocouple arrangements
To best represent the temperature across the slab section, the in-situ concrete temperature
profiles (Channels 1, 2 and 3) were averaged to represent a single profile in each case. The
average profile for the third day is duplicated to extend the profiles to a seven day period.
These averaged profile of is presented in Fig 3.7.
Fig 3.7 Average concrete slab temperature profiles
Cylinder specimens were tested at 1 to 28-day age. The concrete mix used is similar to the
concrete mix used on-site. The concrete specimens cured in the laboratory were batched at
the plant and truck-mixed in order to obtain a mix that is similar to the one that was
dispatched to the site. All concrete specimens were ground and conditioned before being
tested at 1 to 28-day age. The specimens were cured under standard and ambient conditions,
isothermal conditions and temperature matched curing (TMC) methods.
10
15
20
25
30
35
0 10 20 30 40 50 60 70 80
Tempera
ture(oC)
Time (hrs)
Channel 1 Channel 2
Channel 3 Ambient
Cylinder
0
5
10
1520
25
30
35
0 40 80 120 160
Temperature(C)
Time (hrs)
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
13/34
114
The specimens were cured in accordance with AS1012 (1999) and AS3600 (2009) for
standard and ambient conditions respectively. The average compressive strengths of the
cylinder specimens are presented in Table 3.2. To evaluate the in-situ strength development
of concrete, some specimens were subjected to representative temperature profiles recorded
from the two building projects using the TMC method. The specimens were cured under
average temperature profiles shown in Figure 3.7. The average compressive strengths are
presented in Table 3.1.
Table 3.2 Standard and Ambient Cured Cylinder Compressive Strengths (fc)
Age
(Days)
C1b, fc(MPa)
Standard cured
23oC
C2b, fc(MPa)
Ambient
cured
TMC C2c,
fc(MPa)
in-situ
1
23
4
7
28
11.2
-24.2
26.4
31.7
42.5
13.4
20.421.9
23.9
28.8
40.3
14.0
21.025.4
26.7
32.3
41.8
The equivalent age can be calculated using Eq. (3.1) based on the temperature profile shown
in Fig 3.7. The equivalent age profile is presented in Fig 3.8. The ratio of the activation energy
against the gas constant, /E R at 4200 with a Tr value of 23C was assumed (as suggested
by Day (2006)). The temperature profiles result in a slightly higher equivalent age for the
channels positioned deeper in the slab section. .
Fig 3.8 Equivalent age profiles for slab at different depths
Fordetermining the strength-maturity function parameters, a linear regression analysis was
conducted to curve fit the strength-maturity functions in Table 3.1 to the compressive strength
010
20
30
40
50
60
70
80
0 20 40 60 80
Equivalentage(hrs)
Elapsed time (hrs)
Channel 1
Channel 2
Channel 3
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
14/34
115
measured for cylinder specimens cured under a reference temperature of 23C. For brevity,
only the result for the Linear Hyperbolic function (Eq. 3.2) is shown. The result of the
regression analysis for the reference temperature of 23C is presented in Fig 3.9. The values
of the parameters kT, t0 and S are 0.43, 0.18 and 43 respectively.
Fig 3.9 Strength predictions from regression analyses
To obtain the compressive strength of concrete subjected to various temperature conditions,
the values of equivalent age should be used. For example, a 3-day age concrete (72 hrs)
subjected to variation of temperature shown in Fig 3.7 has an equivalent age of about 2.7 day
(65 hrs). Using the strength-maturity curve shown in Fig 3.10, the compressive strength of the
concrete is about 22MPa.
Fig 3.10 shows the comparison between the compressive strength prediction using the
maturity method (linear hyperbolic function shown by the thick line in Fig 3.10), the standard
cured approach and the in-situ (denoted TMC C2c) compressive strength. It is shown that the
strength function can reasonably predict the in-situ strength of concrete. The difference
between the strength predictions using the maturity functions and the in-situ strengths were
found to be less than 10% with the exception of the 1 day age.
4
8
12
16
20
24
28
0 1 2 3 4
strength(MPa)
te(days)
Linear Hyperbolic
Standard cured
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
15/34
116
Fig 3.10 Comparison of strength functions with specimens cured under different temperature profiles
1. Development of other mechanical properties over time
Maturity method can equally be used to predict other concrete properties such as tensile
strength and modulus of elasticity over time. However, similar to that reported for
compressive strength prediction, that there exists no single value for the activation
energy (Ea) for all the properties of concrete or different concrete formulations (Zhang et
al., 2008).
For completeness, some of the results reproduced here for discussion. The reader
should refer to the original source for in-depth discussion of the results and analysis.
The detailed mixture proportions of the high performance concrete are provided in Table
3.3, which also indicates the concrete slump, air content and density measured after
casting, and the compressive strength measured at 7 days (50MPa). Over 105 concrete
cylinders (100200 mm) were made from one single batch of concrete to minimize the
variability in the test results.
0
5
10
15
20
25
30
0 1 2 3 4
streng
th(MPa)
te(days)
Linear Hyperbolic
Standard cured
TMC C2c
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
16/34
117
Table 3.3 The mix composition details
Proportions (kg) Properties
Max water 213 Slump 185mm
Cement
(ASTM Type I)
62.5 Air Content 4%
Fine aggregate
(5mm max,), dry
125 Density 2452
kg/m3
Coarse aggregate
(20mm max,), dry
125 fc@ 7 Days 50MPa
Superplasticiser, dry 2.1
Approximately 3 h after setting, when the concrete gains enough strength, they are
subject to different curing environments. For this, three equal groups of concrete
samples (with their moulds and covers) are stored in three environmental chambers with
temperatures previously set to 10 C, 25 C and 40 C and maintained as such until the
time of testing. This procedure ensured that the concrete samples had the same
properties at the onset of strength development for a better comparison.
Fig 3.11 Temperature in concrete samples and environmental chambers
Fig 3.11 presents the concrete temperatures monitored for the 3 groups of cylinders and
their respective curing temperatures during the first day (with curing temperatures
maintained constant until testing). Test results were obtained for the compressive
strength, splitting tensile strength, and modulus of elasticity measured over time at the 3
curing temperatures, respectively.
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
17/34
118
Regression analyses were then conducted to model the development of these properties
as functions of time. Since the early-age development of HPC properties are of prime
interest in this study, the analyses presented in this paper focus mainly on the results
measured during the first 7 days. This ensured more accurate analyses and predictions
for the period of interest, during which the properties of HPC developed relatively fast.
The 28-day test results will be presented later in the paper as additional information. The
following empirical exponential equation, adapted from the well-known relationship
suggested by the (CEB-FIP, 1990)[20], was used to model the development of each
selected property of concrete:
1 (3.2)
where P(t) represents a given property as a function of time, P7 is the property value at 7
days, tis the time elapsed after the setting time, and A and Bare constants obtained by
regression analysis (Figs 3.12 and 3.13). The obtained regression curves for the
development of these properties were then used to determine the activation energy
factors and develop the property-maturity relations. Note that by using the time elapsed
after setting as the time zero in the above equation ensures the validity of the model for
concretes that may have different setting times.
Fig 3.12 Splitting tensile strength measured for 3 curing temperatures
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
18/34
119
Fig 3.13 Modulus of elasticity measured for 3 curing temperatures
To estimate the equivalent age, the range of values presented for Ea presented may be
assumed.
To determine the activation energy for the properties such as tensile strength and
modulus of elasticity, the followings steps are recommended:
1. The determination ofK(T) from the initial slopes of the relative property P/Pu curves
for different temperatures (at t=to), where the Pu is the ultimate value of the property;
2. The activation energy can be obtained by plotting the natural logarithms of kT versus
the inverse of the curing temperature (15, 23, 35 and 50C). The negative of the slope
of the straight line equals the activation energy (Ea) divided by the gas constant (R).
3. The equivalent age can be determined using
1 1
0
a
r
Et
R T T
et e t
(3.3)
And the properties of concrete for different temperature profiles can be predicted using
the equivalent age and the curve for the reference temperature.
Zhang et al., 2008 report experimental results conveying important information on the
activation energy: (i) different properties may have different Ea for a given concrete; (ii)
different concretes may have different Ea for a given property; and (iii) different
development stage of a given property of a given concrete may have different Ea. The
experimental investigation demonstrates that the properties of Ea/R vary as the
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
19/34
120
properties develop over time. The range of values listed is varying from 3763 K to 7781 K
for tensile strength and from 7145 K to 8435 K for modulus of elasticity.
2. Effect of Cementitious Materials on Concrete Strength Development
A recent investigation of the accuracy of the maturity method to estimate the strength of
concrete with different cementitious materials such as fly ash and slag is reported in
(Brooks et al, 2007). The reference discusses the strength development of mortar cubes,
made from Type I cement and various replacement levels of Class C fly ash, Class F fly
ash, and ground-granulated blast-furnace slag which are cured at isothermal curing
temperatures of 8, 23, and 40C. The temperature and activation energy values were
determined for these cementitious systems. Table 3.4 lists a summary of mixtures tested:
Table 3.4 Summary of Mixtures Tested during This Study (Courtesy: Brooks et al, 2007)
Data from the reference (Brooks et al, 2007) is used to make up the Excel spreadsheet
(strength prediction of concrete with varying fly ash content.xls). The excel file makes
use of the data provided in the reference to estimate the equivalent age for each of the
mixes listed in Table 3.4. For the calculations, the average concrete slab temperature for
Fig 3.7 is assumed. The reference temperature is set to 23C. Analysis results
determined with exponential strength-age linear hyperbolic function according to (Tank
and Carino, 1991, see Table 3.1) is used for the strength calculations. The model
parameters which are based on experimental results are listed in Table 3.5. These are
obtained following the steps listed in Section 3 (Maturity Method).
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
20/34
121
Table 3.5: Analysis Results Determined with Strength-Age Function (Courtesy: Brooks et al, 2007)
The results of the experimental study show that composition of the cementitious
materials in the system significantly influences the maturity method to accurately
estimate the strength development. The effect of addition of fly ash of different types on
concrete strength development is shown in Fig 3.14. As can be noted, the Class F fly ash
results in significantly lower strength development of concrete when compared to that of
Class C fly ash.
Fig 3.14 Effect of addition of fly ash of different types on concrete strength development
The amount of longterm strength reduction, due to curing at high temperatures
compared with curing at room temperature, is equally found to be influenced by the type
of cementitious system used in the concrete mixture.
Sirivivatnanon et al. (2009) presented results from research of two concrete mixes
supplied to two building projects over a 16-month period covering two winter seasons in
Sydney. In this investigation, real-time in-situ concrete temperatures in post-tensioned
slab were simulated in a temperature matched curing tank in a laboratory. Concrete
0.0
10.0
20.0
30.0
40.0
0.0 50.0 100.0 150.0
f'c(Mpa)
te (hr)
ClassCflyashC15
C25
C35
IA
0.0
10.0
20.0
30.0
40.0
0.0 50.0 100.0 150.0
f'c(Mpa)
te (hr)
ClassFflyashIA
F15
F25
F35
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
21/34
122
cylinders sampled from building sites were subjected to curing conditions identical to
those experienced in the slabs in order to determine as accurate as possible the in-situ
concrete strength development. Additional concrete cylinders cast from the same
concrete were cured using four different curing methods: air curing, insulated air-curing,
semi-adiabatic curing and standard AS 1012 water curing. Comparisons were made
between the cylinder strengths cured with the four methods and the estimated in-situ
concrete strengths for twenty concrete slabs cast in ambient temperatures ranging from
10C to 25C. The anchorage performance of post-tensioning strands at initial and final
stressing was also monitored. It was found that the 4-day air-cured strengths consistently
underestimated in-situ concrete strength by about 10% and had the poorest correlation
to in-situ strength of any of the curing regimes investigated. This finding suggests that
strengths derived from air cured cylinders cannot necessarily be considered to provide
curing conditions similar to those of concrete in the work as noted in AS3600 (Section 17
in 2009 Edition). The 1-day and 4-day in-situ strength of 9 MPa and 24.5 MPa was found
to be satisfactory for the initial and final stressing of 12.7mm diameter prestressing
strands for both types of concrete without the need for prescriptive binder specifications.
Summary
Benefits of Maturity
The benefits of using maturity as contrasted with traditional quality control procedures
are:
It provides a real-time, in-place indication of the strength of the concrete.
It is a non-destructive testing method as contrasted to breaking cylinders in the
laboratory.
Itprovidesearlyqualityverificationoftheinplaceconcrete,oftenwithinhoursof
itsplacement.
Itacceleratestheconstructionprocessbyallowingthepavementtobeopenedto
traffic
or
formwork
stripped
from
structures
(or
for
posttensioned
construction
helpsearlystressingsequence).
Itreducesthequantityandcostofsamplingandtestingbyreducingthenumberof
cylindersthatneedtobecastandbrokentodeterminestrength.
Thematuritymethod isreadilyassessabletomostmaterials laboratoriesbecause
itisbasedontraditionalcylindercompressivestrengthtestsforitsdevelopment.
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
22/34
123
Weaknesses of Maturity
The maturity method also has its weaknesses. Changes in the brand of cement, the
source and type of pozzolonic admixtures, the source of the aggregate or the water to
cement ratio can result in a change in the strength-maturity relationship and require anew calibration curve. The method also cannot account for humidity conditions during
curing, that is, if there is not enough moisture present for hydration to occur the strength
gain will not be realized as predicted by the maturity curve. It is not accurate when there
are large temperature swings during the curing process. The method also cannot
account for concreting practices that result in inadequate consolidation, poor placement
techniques, inadequate curing, lack of protection during early ages, or fluctuations in air
content.
Volume Changes at Early Age
If the heat produced during the hydration reaction is not transmitted to the environment at the
same rate as it has been produced, the temperature rise in the concrete member might
become significant. Like any other material, concrete is susceptible to volume changes when
subjected to varying temperatures. The thermal expansion coefficient of concrete is about 10-
1510-6
per C (Neville, 1996). Temperature is one of the main causes of volume changes in
the early age concrete, besides autogenous deformation.
Temperature raises as a consequence of exothermic hydration reaction and the results
volume changes. If the deformation due to the volume change is restrained, stresses develop
in the member, often referred to as thermal stresses. In practice, restraints can be provided by
other adjacent structural members such as (the building core, columns or beams).
Reinforcements can also provide restraining effects internally. If concrete member was set
without any restraints, the volume changes would occur freely and no stresses would develop
in the member. In case of a restrained member, compressive and tensile stresses could
potentially develop due to heat development and cooling phases, respectively.
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
23/34
124
Input parameter for thermal analysis
Parameter Value
Thermal conductivity 2.6 W/mK
Volumetric specific heat 2400 J/m3K
Convection coefficient in boundary 10 W/m2K
Arrhenius Constant 6000
Initial temperature 20 C
Coefficient thermal expansion () 15 10-6 per C
Properties of the concrete mix such as conductivity and capacitance are often assumed
constant. In reality these properties vary over time and are dependent on concrete maturity.
The thermal conductivity of concrete is reported to decrease over time as the concrete
matures (Gibbon and Ballim, 1998). The value depends on the moisture content and
temperature evolution, as well as the type of cement and aggregate of the concrete mix. Theparameters commonly adopted for concrete are summarized in Table given here.
Early Age Creep
Important factors that may contribute to cracking and failure of the early-age concrete are the
ambient conditions (e.g. temperature, humidity) and properties such as creep and shrinkage.
For a restrained concrete element, creep can occur due to thermal expansion and shrinkage.
Creep is considered as a time dependent deformation of concrete due to the imposed
external mechanical load or as a result of thermal expansion and shrinkage associated with
the hydration reaction. Immediate deformations due to applied load are referred to as the
nominal elastic strains (Neville 1996). This is not completely correct since there will always be
some early creep, but it is in practice good enough for most purposes. Creep can then be
taken as the increase in strains as a function of time, after this point as shown in Fig 3.15.
Additionally, there will also be time-dependent shrinkage, unaffected of whether the concrete
is loaded or not. Shrinkage is a result of chemical and physical changes in the concrete
volume during the hydration process. It can be divided into plastic shrinkage and drying
shrinkage. Plastic shrinkage occurs while the concrete is in the plastic phase. Drying
shrinkage is mostly affected by environ-mental conditions such as wind speed, temperature
and relative humidity. As shown in the figure, there are two types of creep which can make up
the total creep, depending on the moisture content of the environment. If there is no moisture
movement between the concrete and the environment, it can roughly be assumed that all
creep is basic creep, even though this is also a simplification.
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
24/34
125
Fig 3.15 Time-dependent strains in concrete subjected to external loading over a time, Courtesy: Neville
(1996)
Estimation of the early age creep effects is essential in accurately estimating the development
of stresses that are induced in the concrete member. The stresses can be caused by thermal
effects, autogenous deformations or by application of external actions such as post-tensioning
loads. It is reported that creep deformation of concrete at early ages may lead to stress
fluctuations that reach magnitudes of 50% or higher (see for eg., Faria et al., 2006). At the
same time, it is important to note that with the evolution of the hydration reaction makes the
material properties of concrete such as the elastic modulus, compressive and tensile
strengths to be dynamic.
Elastic materials have the ability to fully regain the initial shape after being deformed.
Concrete at early ages cannot be assumed to be elastic. A visco-elastic material exhibits both
viscous and elastic characteristics under deformation. While elastic deformations are always
recoverable upon unloading, viscous deformations are never recoverable (Neville 1996).
Considering Fig 3.16, the instant that the stress is being applied to the concrete member, the
strain is elastic and thus recoverable if the stress is removed immediately. Obviously, if the
magnitude of the applied load is close to the concrete strength, this would not be the case due
to cracking and plastic deformations.
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
25/34
126
ElasticStrain
t
Fig 3.16 Elastic and time dependent strains of concrete due an imposed load [After stergaard et al.
(2001)]
A strong aging tendency of concrete material in the first two days after casting has been
observed at-several occasions (Altoubat and Lange 2001; Bissonnette and Pigeon 1995).
Aging can be explained as the concrete hardening and gaining strength. The concrete is very
susceptible to creep at early ages, but quickly ages and therefore becomes more resistant as
it hardens.
According to the linear theory, the strain is proportional to the applied stress. Hence, the strain
at time tcaused by a constant uniaxial stress applied at time tis given by:
)',(.)( ttJt
The compliance function J(t, t) for a specimen subject to constant stress is given by the
following expression:
J(t, t) = q1+C0 (t, t)+Cd (t, t,t0)
Where, q1 is the instantaneous strain due to unit load, C0(t, t) is the basic creep compliance
function, and Cd (t, t, t0) is the drying creep compliance function, t is the age of concrete at
time of loading in days and tis the current age of concrete in days.
For a variable stress history, the principle of superposition is assumed to be valid. There is a
great many number of creep models proposed in the literature. For consideration of early age
effects, however, Bazants B3 model and the Double Power Law (DPL) is commonly used.
The creep response to a load applied at slightly different ages changes rapidly at this stage of
the hydration process due to the strong aging. Higher creep compliance is reported for
concrete at earlier ages. Prior to one day, even a light load was observed to produce twice the
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
26/34
127
amount of creep of that only a few hours later, using identical concrete mixes (Atrushi, 2003,
Ostergaard, 2003).
Construction Issues and the role of Early Age Concrete
Although high early strength concrete (HESC) concrete is an obvious choice for construction,
particularly for multi-storey buildings, many instances of localised failures have been reported
during construction. These are partly due to wrong estimates of the strength prediction of the
concrete strengths. A wide range of other defects such as excessive floor sagging, cracking,
spalling, honeycombs, increased long term deflections, bulges and misalignments are also
considered as failures that result in serious serviceability problems (Feld, 1964; Aalami and
Kelly, 2001). In the following section, typical examples of failures related to both precast and
post-tensioned industries are presented.
Post-tensioned slabs Anchorage failures
In post-tensioned systems, the prestressing force is transmitted to the concrete mainly by the
direct bearing of a steel anchorage plate or casting on the concrete. An external anchorage is
used for stressing the strand (live end) and an internal anchorage is used to resist the loads
by stressing of the strand (dead-end). A typical slab edge anchorage assembly is presented in
Fig 3.17. At the dead-end, the strands coming out of the duct tube are spread out and are
bent with their ends to form the shape of an onion. The anchorage zone of a post-tensioned
concrete member is a critical portion of the member where the concentrated PT forces spread
to a uniform stress distribution in the concrete.
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
27/34
128
Fig 3.17 Anchorage in slab edge (dimensions in mm)
The common criteria for acceptance of concrete used in post-tensioned applications having
12.7 mm diameter strands in Australia are;
Minimum 28 day characteristic cylinder strength (fc) of 32 MPa
Compressive strength at final stress transfer of 22 MPa typically at 3 to 5 days after
concrete
placement
Compressive strength of 7 MPa at 24 hours after concrete placement for initial
stressing at
25% of the ultimate stress.
At these times, i.e., 1-7 days after the concrete pour when the post-tensioning procedure is to
be carried out, while the concrete is curing and the properties of concrete evolve over time
(Choong et al., 2005). One major issue with the post-tensioning of slabs is the failure of the
concrete material at the anchorage zone locations. Failures happen due to stress
concentrations in spite of factors of safety and heavy reinforcement, usually in the form of
loops or spirals, as shown in Fig 3.17. A typical anchorage zone failure in a post-tensioned
suspended slab is shown in Fig 3.18. The failures, which mostly happen during the post-
tensioning process, can be serious and explosive in nature. They happen at the second stage
of post-tensioning at either of live or dead-end anchorages. As can be seen (Fig 3.18), they
require resources for replacement and repair which can substantially increase the
construction cost. Reinforcement congestion in the local zone, poor concrete quality and
inappropriate workmanship has been blamed for the failures. Inadequate strength prediction
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
28/34
129
of in-situ concrete at the time of application of the post-tensioning has been another prevalent
hypothesis [2] (CPN29, 1996). Anchorage failures have been occurring at the dead and live
ends, resulting in loss of load in the strand, delamination and spalling of concrete around the
anchorage. In many instances, where the concrete cover is broken off, grooves can be
observed demonstrating slippage of wires and strand assembly with respect to surrounding
concrete.
Fig 3.18 Failed anchorage in slab edge photographed on construction site
For the live end, the duct covers the strands entirely and the PT load is transmitted directly to
the anchorage plate. As regards to dead-end anchors, which constitute a more critical case,
the PT load is resisted initially by bonding effect of the straight part of the strand. This straight
part of the strand, about 800 ahead of the anchor plate is bonded to the concrete (see, Fig
3.17). When the bond mechanism of the strands is exhausted, the load is directed to the
anchorage assembly and transmitted to the surrounding concrete. Clearly, there are two
contributing factors in resisting the PT load: 1) the bond strength of the straight part of the
strand; and, 2) the anchorage action due to the anchorage plate. In details, the onions which
are themselves made up of bent wires, are equally bonded to the surrounding concrete.
A comprehensive research project is carried out at the University of Melbourne sponsored by
Australian Research Council and Holcim to investigate this problem. In view of the anchorage
description, it is noted that extensive number of variables are involved. The preferred option
was to investigate the problem within the framework of finite elements. Sofi et al. (2007) report
the results of the experimental work and the modelling approach adopted to investigate the
behaviour of anchorage zone concrete. The experiments were carried out in an attempt to
obtain the input parameters necessary for the finite elements and to validate the models. In
this paper, a short literature review of bond mechanism is presented first followed by a
description of the experimental work. This is followed by a discussion of the models and the
results (see Sofi et al., 2011).
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
29/34
130
In recent times, questions have been raised as to the possible negative impacts of fly ash
inclusions into concrete and the potential for increased risk of anchor failure as a result of
impact on early age concrete properties relevant to when final stressing is applied. Key
concerns appear to include potential loss of bond between strands and concrete, lower early
age tensile properties and compressive strength. Some specifications limit the percentage of
fly ash allowed in a post tensioned concrete mix to be no greater than 10% by weight of
Portland cement for these reasons.
Sirivivatnanon et al. (2009) conducted an experimental study on implications of using fly ash
in post-tensioned concrete.
They concluded that;
Fly ash concretes can be easily designed to meet early age requirements specified for
post tensioning applications.
Concrete strength gain characteristics for control (non fly ash) and fly ash concrete
mixes are well understood and are often optimised for particular design and
constructional applications.
The research indicates that the bond strength (as determined by pullout load) between
tendons and concrete is a function of the compressive strength of the concrete and not
the composition of the cementitious component. In particular, fly ash inclusions of up to
30% appear to have no adverse effect on bond at the same compressive strength.
There is no evidence in the technical literature to support the hypothesis that increasing
fly ash contents in concrete (certainly to levels up to 30%) will reduce bond strengths
between tendons and concrete.
Precast Walls Support and Anchorage Systems during Construction
The use of precast allows not only the speedy erection of the structure, but also flexibility and
overall program shortening. This is achieved by allowing the production of components at the
same time the footing system is being prepared1.
A minimum amount of propping allows the following trades to commence work on the
structure earlier than conventional construction methods. During construction the lateral load
1http://www.npcaa.com.au/images/file/Skeletal%20frame%20struct.pdf
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
30/34
131
path for a building under construction is incomplete. Therefore, external supports in the form
of vertical struts are provided to resist the lateral wind loads and to provide stability for the
newly installed precast elements.
For large panels, the joints between panels are generally located at rafter centres so that theroof framing (or portal frames when panels are used as cladding only) laterally supports both
panels. For smaller panels, an intermediate strut can be provided to laterally support the
panels at the intermediate joint location. Early age concrete strength is very important and
some failures are reported due to problems in reaching specified strength.
Fig 3.19 Rafter to panel connection at joint
Cast-in headed anchors provide a means of making bolted or welded connections to other
concrete members. According to the National Precast Concrete Association of Australia
(NPCCA), the usual forms of these anchors are illustrated in Fig 3.20.
Fig 3.20 Types of anchors, (Courtesy, NPCAA Manual)
Ferrules, which are internally-threaded, steel sleeves to take a bolt. They are anchored by
transverse reinforcement attached to the base by welding, or, through a transverse hole in the
base of the sleeve, or, with a J-bolt screwed or butt-welded to the base. A common
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
31/34
132
application for a ferrule is the restraint fixing for a wall panel. Ferrules for structural
connections are typically 75100 mm long and the usual bolt diameters are 20 and 24 mm.
Plates with stud anchors provide a means to weld a fixing bracket in its correct position after
erection of the member. Such brackets should reach their yield strength prior to the load
reaching the calculated capacity of the cast-in stud assembly.
Fig 3.21 Failure modes of anchors (Courtesy, NPCAA handbook)
Figure 3.21 depicts failure modes of anchors asreported by the National Precast Concrete Associationof Australia. The following failure modes of an anchorare possible (NPCAA):
Steel failure of the anchor shaft or bolt in tension
Steel failure of the anchor shaft or bolt in shear
Breakout of a prism of concrete surrounding the
anchor in tension
Breakout of a prism of concrete towards an edge in
shear
Crushing of the concrete over the bearing area at
the base of the anchor (pullout)
Rotational pryout of an anchor body subjected to
shear
Side-face blowout when the anchor is located close
to an edge in conjunction with deep embedment
(greater than 200 mm)
Splitting of the concrete in the vicinity of the anchor.
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
32/34
133
The type of failure cones in high strength concrete are generally deeper than those in normal
strength concrete. This is an indication that higher compressive strength of concrete reduces
the possibility of local crushing and thus enhances the interlock effects. Some useful results
are also available in Joshi (2001) and Yin (2002).
REFERENCES
1. Aalami, BO and Kelley, GS 2001, Structural design of post-tensioned floors, Concrete
International, v.23(1), Pp.31-36.
2. ACI318-11, Building code requirements for structural concrete (ACI 318-11) and Commentary
(ACI 318R-11)..
3. Altoubat, SA and Lange, DA 2001, 'Tensile Basic Creep: Mea-surements and Behaviour at
Early Age', ACI Materials Journal, vol. 98, no. 5, pp. 386-93.
4. AS 1012.8.1, Method of testing concrete: Method of making and curing concrete -
compression and indirect tensile test specimens. Committee BD-042, Australian Standards
1999.
5. AS 3600, Concrete structures. Committee BD-002, Australian Standards 2001.
6. ASTM C192/C192 M-10, Making and Curing Concrete Test Specimens in the Field, American
society for testing and materials (ASTM). West Conshohocken, Pennsylvania; 2007.
7. Atrushi, DS 2003, 'Tensile and Compressive Creep of Early Age Concrete: Testing and
Modelling', Doctoral thesis, The Norwegian University of Science and Technology.
8. Baant, ZP and Panula, L 1978, 'Practical prediction of time de-pendent deformations of
concrete', Materials and Structures, vol. 11, no. 65, pp. 307-28.
9. Bissonnette, B and Pigeon, M 1995, 'Tensile creep at early ages of ordinary, silica fume and
fiber reinforced concretes', Ce-ment and Concrete Research, vol. 25, no. 5, pp. 1075-85.
10. Brooks, AG1; Schindler, AK and Barnes, RW., 2007 Maturity method evaluated for various
cementitious materials, Journal of materials in civil engineering, v. 19(12), pp. 1017-1025.
11. Brundtland Report: 1987, The Report of the Brundtland Commission, Our Common Future,
published by Oxford University Press..
12. Carino, N. J. and Lew, H. S., The Maturity Method: From Theory to Application. In: Chang, P.
C., editors. Structures Congress and Exposition. Washington, D.C.: American Society of Civil
Engineers; 2001. p. 19.13. CED-FIB, CEB-FIP Model Code 1990, Information Bulletin No. 213/214, Euro-International
Concrete Committee, Lausanne, 1993, 437 pp.
14. Choong, J., Mendis, P.A., Mak, S.L., and Baweja, D., More Accurate Concrete Strength
Predictions for Post-Tensioned Slab Construction, Proceedings, Concrete Institute of
Australia, 22nd Biennial Conference, Concrete 2005, Melbourne, Australia, October, 2005.
15. CPN29, Prestressed concrete anchorage zones. Concrete Institute of Australia 1996; 1-13.
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
33/34
134
16. Day, K. W., Concrete mix design, quality control and specification. London: E. and F. N.
Spon; 2006.
17. Faria, R, Azenha, M and Figueiras, (2006), 'Modelling of con-crete at early ages: Application
to an externally restrained slab', Cement and Concrete Composites, vol. 28, pp. 572-85.
18. Feld, J., 1964, Lessons from failures of concrete structures, American Concrete Institute
monograph, v.1(1), Pp. 179.
19. Flower, J., Sanjayan, G., and Baweja,D, Environmental Impacts of Concrete Production and
Construction, Proceedings, Concrete Institute of Australia Biennial Conference, Concrete
2005, Melbourne, Australia, October, 2005
20. Freiesleben Hansen, P. and Pedersen, E. J., Curing of concrete structures, Comit euro-
international du bton (CEB) Information Bulletin, (1985)166.
21. Gibbon, GJ and Ballim, Y 1998, 'Determination of the thermal conductivity of concrete during
the early stages of hydration', Magazine of Concrete Research, vol. 50, no. 3, pp. 229-35.
22. Jenkins, D, Baweja, D, Portella, J., Optimising Building Design for Sustainability Using High
Performance Concrete , 2011.
23. Joshi, T., Behaviour Experimental Investigation of PostInstalled Anchors in Highstrength
Concrete,MastersThesis(supervisedbyP.Mendis),TheUniversityofMelbourne,2001
24. Knudsen, T., Modelling hydration of Portland cement: Effect of particle size distribution,
Engineering Foundation Conference on Characterization and Performance Prediction of
Cement and Concrete, Henniker, N. H. (Ed.), (1982)125.
25. Lin,Y.,BehaviourofScrewAnchorsinHighstrengthConcrete,MastersThesis(supervisedby
P.Mendis),TheUniversityofMelbourne,2002
26. Mak, S. L. and Torii, K., Strength development of high strength concretes with and without
silica fume under the influence of high hydration temperatures. Cement and ConcreteResearch 1995; 25(8); 1791-1802.
27. Neville, AM 1996, Properties of Concrete, 4th and final edn, Wiley, Harlow, Essex.
28. Ngo, T., Mendis, P., Aye, L., Gammampila, R., Crawford, R., Life cycle assessment of steel
and concrete framed high rise commercial buildings, International Conference on
Sustainable Built Environment, ICSBE 2010, Sri Lanka
29. NPCAA *(2009), Precast Concrete Handbook, 2nd edition, National Precast Concrete
Institute of Australia.
30. Plowman, J. M., Maturity and the strength of concrete, Magazine of Concrete Research,
8(22), (1956)13.
31. Sirivivatnanon, V, Baweja, D. and Khatri, R.P., Evaluation of In-situ Concrete Strengths for
Post-Tensioning of Concrete Slabs, 2009
32. Sofi, M., Mendis, P.A., Baweja, D. and Mak, S.L., Behaviour of Post-Tensioning Anchors in
Early Age Concrete Slabs, Proceedings, Concrete Institute of Australia 23rd Biennial
Conference, Concrete 2007, Adelaide, Australia, October, 2007.
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012
2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka
-
8/2/2019 Limit States in Construction_Mendis
34/34
33. Sofi, M., Mendis, P.A., Baweja, D. and Elvira, E., Bond Performance of Strand and Wire in
Early Age Concrete, 9th International Symposium on High Performance Concrete:Design,
Verification and Utilisation, 9-11 August 2011, New Zealand.
34. Stergaard, L, Lange, DA, Altoubat, SA and Stang, H 2001, 'Tensile basic creep of early-age
concrete under constant load', Cement and Concrete Research, vol. 31, no. 12, pp. 1895-9.
35. Tank, R. C. and Carino, N. J., Rate constant functions for strength development of concrete',
ACI Materials Journal, 88(1), (1991) 74-83.
36. Zhang, J., Cusson, D., Monteiro, P. and Harvey, J. (2008), New perspectives on maturity
method and approach for high performance concrete applications, Cement and Concrete
Research, 3814381446.
Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012