limit states in construction_mendis

Upload: thilina-udara-de-silva

Post on 06-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 Limit States in Construction_Mendis

    1/34

    102

    NEW LIMIT STATES IN CONSTRUCTION

    3.1 Construction Optimisation

    Although the structural cost forms a relatively small portion of the overall development cost,

    the structural component is a critical path activity for multi-storey building construction.

    Therefore it is imperative that the structural design focuses on a solution that considers

    construction time as a leading parameter.

    The optimisation process of the construction process can be broken down into three broad

    areas:

    Optimisation of labour and time to complete the building.

    Optimisation of construction time. Design for construction time.

    Optimisation of labour and time

    Studies have revealed that labour can account for as much as 50% of the total cost of

    construction. For concrete structures the labour can be minimised in two ways. The first is by

    extensive use of factory made prefabricated materials which typically use lower man-hours.The second is to minimise the labour associated with formwork, by using systems which can

    be reused many times.

    Optimisation of Construction time

    There are tremendous financial benefits of early completion. Early completion not only lowers

    the interest bill, but will also attract an early income stream in the form of rental income frompotential building occupants.

    Recent trends in the construction procedures to increase speed of construction include:

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    2/34

    103

    Carrying out demolition of existing structures, bulk excavations, piling and excavation

    protection structures over the site, concurrently with the design and documentation of

    the redevelopment.

    Use of sophisticated formwork system to construct the lift cores as quick as possible,

    well advanced from the remainder of the construction, providing more time for the

    critical activities of lift installation and vertical service distribution. Structurally the core

    typically forms part of the necessary vertical and lateral support system during the

    construction phase.

    Early completion of finishes generally governs building completion. There is a growing

    trend to complete floor levels, clear of all formwork, as quick as possible providing the

    various trades with a clean working platform to proceed with the labour intensive

    service installation.

    Construction systems incorporating High-performance concrete provide a highly-effective

    solution to address the above objectives.

    With reference to Fig 3.1, it can be seen that for nearly 80% of the construction period the

    construction of structure is the critical activity.

    Fig 3.1 Simplified chart of High Rise construction

    From these facts it may be concluded that structural designers need to focus their efforts in

    developing structural systems and details to suit faster construction. The traditional least cost

    structures rarely optimise construction speed and more importantly rarely minimises total cost.

    A cost premium on the structural components may be involved, and therefore a cost benefit

    study should be carried out to ensure that there is a cost benefit on the total development

    cost.

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    3/34

    104

    Construction systems incorporating High-performance concrete (HPC) provide a highly-

    effective solution to address the above objectives.

    Construction of some key components is discussed below.

    Core Construction

    This section will discuss aspects of core construction

    For tall buildings the core forms the principal structural element for both the gravity

    load-resisting system and the lateral load-resisting system, with the latter becoming

    increasing important with increasing height of the building. The size and location of

    the core is predominantly governed by architectural considerations.

    The cost of the core for a typical tall building is estimated to be 38% of the total

    structural cost or 4 to 5% of the total development cost. The core is typically the critical construction activity for high-rise development. Any

    delay in the core construction will not only delay construction of the other structural

    components but will also delay all other activities associated with architectural and

    mechanical-electrical services.

    Important factors that govern core construction time are:

    - To employ an efficient formwork which is readily available and requires minimum

    set-up time

    - To minimise transitions in the shape and size, up the height of building

    - To minimise the number of transitions in wall thickness. Transitions take up

    valuable construction time. This can be achieved by greater use of varying

    concrete strength and reinforcement content to increase wall strength.

    In Australia, and many other countries, introduction of high strength concrete with 28

    day strengths of up to 120MPa has made reinforced concrete a feasible option for tall

    buildings which demand large force-resistant capacities in the core walls.

    - Compared to Steel, Materials for reinforced concrete are readily available with

    minimum lead times. Also strengths can be modified at short notice without

    changing wall thickness, which may have architectural implications, by changingthe reinforcement content or concrete strength.

    - With the core construction being on the critical path, design changes are

    inevitable. Reinforced concrete can cater for modifications with relative ease.

    The importance of speed of core construction is reflected by the fact that advance

    formwork systems have been developed specifically for core construction. Although

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    4/34

    105

    the initial capital cost of such formwork system is high, up to $1M, the savings

    associated with reduction in construction time will more than offset this penalty.

    The two most common advance formwork systems employed for core construction

    are:

    - Slip-form - where the concrete is poured continuously whilst the formwork is

    continuously slipped up, by use of hydraulic jacks anchoring off the set concrete

    below. This is a 24 hour per day operation requiring skilled labour force. All

    stages of operation such as placing of reinforcement, concrete supply etc., must

    be reliable and efficient. Unplanned stops in the operation can be costly (Fig 3.1).

    HPC with appropriate setting times for concrete is essential for slip-form

    construction.

    - Jump-form- a more traditional formwork system, where a storey height of core is

    poured at a time. The formwork is supported off the poured core below. On

    completion of the pour the formwork is jumped by another storey height, for the

    next cycle.

    These advanced formwork systems do not rely on the status of the construction of

    other structural elements, as it is a self-supporting system. Therefore it is prudent to

    complete the core as quick as possible, so on completion the costly system can be

    removed from site and utilised on another project. HSC is essential for these systems.

    Now innovative jump form systems have been developed (e.g. Eureka Tower

    Melbourne) to jump 2 storeys at a time (Fig. 3.2).

    Fig 3.2 Typical example of an advanced formwork system (Eureka Tower Melbourne)

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    5/34

  • 8/2/2019 Limit States in Construction_Mendis

    6/34

    107

    When combined with use of high strength concrete it becomes a very efficient column

    system in terms of strength and buildability. Fig 3.3 illustrates how this form of

    construction can be effectively utilised, with discrete activities taking place at several

    levels simultaneously, in an orderly and uncluttered environment.

    Fig 3.3 High-strength Concrete filled Steel tube column in High Rise applications

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    7/34

    108

    3.2 Early-Age Concrete Including Maturity Method to Predict the

    Strengths

    With the need of speed in construction, an accurate prediction of early age properties of high

    strength concrete is important. The following section discusses the available methods in

    predicting compressive strength of concrete at early age using a case study.

    According to code procedures

    The Australian Standard on Specification and supply of concrete AS1379 (2007) requires

    concrete samples to be tested in accordance with AS1012 Parts 1, 8 and 9. According to

    AS1012 (1999), the concrete samples are cured under standard-moist conditions where the

    samples are subjected to constant temperatures of 23 2C and 27 2C for a standard

    temperate zone and standard tropical zone respectively. In ASTM C192/C192M (ASTM

    2007), the curing temperature is set at 23 2C. On the other hand, the Australian Concrete

    Structures Standard, AS3600 (2009) and ACI 318 (2011) state that accompanying cylinder

    specimens of the same concrete batch should be stored and cured under conditions similar to

    those of the in-situ concrete. What constitute conditions similar to the in-situ concrete are

    open to interpretation.

    Temperature Matched Curing

    The standard method of testing according to AS1012 (1999) prescribes a curing regime and

    boundary conditions that are essentially different from those under which the in-situ concrete

    is cured. Slabs have a high surface to volume ratio and while the top surface is exposed to

    variable temperature profiles, the other surfaces are sealed by formwork. It is well known that

    the curing temperature of concrete is an important factor governing early-age strength

    development.

    Temperature Matched Curing (TMC) is well established for assessing strength in-situ and is

    widely used in the industry. TMC is a process by which test specimens of concrete, from a

    representative sample of the concrete that is placed in an in-situ or precast element, are

    cured by keeping them in a chamber at the same temperature as a pre-selected point in the

    element. The TMC system can function under isothermal, near adiabatic, pre-recorded, and

    even real-time profile conditions. The system is capable of accurately simulating the in-situ

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    8/34

    109

    Postcastinginput

    temperatureRealtime

    tem erature

    OR

    Water

    bath

    Heater/

    cooler

    Process

    ControlOn/off

    Temperature

    Concretesamples

    curing temperature variation by controlling the temperature of a water bath for estimating the

    real strength development in concrete. The main components of a TMC system are depicted

    in a schematic drawing (Fig 3.4).

    The system has an embedded process controller to precisely regulate the curing temperatureprofile. Accurate temperature matching is enabled using proportional, integral and derivative

    control of feedback temperature data obtained from sensors embedded into one or two

    concrete specimens within the conditioning chamber. The sensors are part of the eight

    thermocouple inputs located at the temperature controller. A thermocouple connected to one

    of the eight thermocouple inputs is also permanently positioned in the chamber to provide

    water temperature measurements. More details about the particular system can be found in

    reference (Mak and Torii, 1995).

    Fig 3.4 Components of TMC systems

    Extensive investigation has shown that TMC is able to predict the in-situ strength. However,

    the technology remains costly and inaccessible to small to medium manufacturers.

    Maturity method

    The maturity method is a common method used in predicting the early-age of in-situ concrete.

    The maturity method is used to account for the combined effect of temperature and time on

    the development of the hydration reaction and the mechanical properties of concrete. The

    nonlinear maturity function based on the Arrhenius law, which is also known as equivalent

    age function is defined by Eq. (3.1):

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    9/34

    110

    1 1

    0

    a

    r

    Et

    R T T

    et e t

    (3.1)

    Where:

    te= the equivalent age at the reference temperature, Days

    Tr= reference temperature, K

    Ea= apparent activation energy, J mol-1

    ,

    R= universal gas constant, 8.314 J mol-1

    K-1

    T= temperature of the concrete during interval ( t ), K

    The reference temperature (Tr) is the standard cured temperature at which test specimens are

    cured. In many parts of the world it is 20oC (293K). In Australia it is 23C in temperate zones

    and 27C in tropical zones. Once the equivalent age is found, strength maturity functions

    (presented in Table 3.1) can be used to find the strength at a particular age.

    The procedure to use the maturity method in predicting the compressive strength of concretes

    at early age is outlined below (Carino and Lew, 2001):

    1. Cast cylinder specimens in accordance with AS1012 (1999). The specimens should

    be cured under isothermal conditions (15, 23, 35 and 50C). Conduct compressive

    tests at regular age intervals (1, 2, 3, 4, 7 and 28 days).

    2. Plot the compressive strength of concrete from the tests (step 1) against the concrete

    age for each curing temperature (15, 23, 35 and 50C).3. Conduct linear regression analyses to curve fit the strength maturity function to the

    experimental data (step 2). From the curve-fitting process, the values of the

    parameters kT, t0 and S are obtained for each curing temperature (15, 23, 35 and

    50C).

    4. Construct strength maturity curve for the reference temperature of 23C. This curve

    provides prediction in concrete strength at different age when the concrete is cured at

    a constant temperature of 23C. In order to use this curve to predict the compressive

    strength of concrete that is subjected to various temperature conditions, the age at

    which the compressive strength is predicted needs to be converted into an equivalent

    age with a reference temperature of 23C.

    5. To obtain the equivalent age (Eq.3.1), it is necessary to establish the activation

    energy Ea. The activation energy can be obtained by plotting the natural logarithms of

    kT versus the inverse of the curing temperature (15, 23, 35 and 50C). The negative

    of the slope of the straight line equals the activation energy (Ea) divided by the gas

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    10/34

    111

    constant (R). In the absence of experimental data, Ea/R of 4200 as suggested by Day

    (2006) can be used.

    6. Using Eq. (3.1), Ea/R from step 5 and the in-situ temperature profile, determine the

    equivalent age.

    7. The compressive strength of concrete can be predicted using the equivalent age

    calculated in step 6 and the strength maturity curve constructed in Step 4.

    Table 3.1 Strength-maturity Functions and Parameters

    Function Name Strength-maturity function Parameters

    Linear

    Hyperbolic

    S=)

    0(1

    )0

    (

    ttT

    k

    ttT

    k

    S

    (Tank and Carino, 1991)

    S = strength at age t,

    S = limiting strength,

    kT = rate constant, 1/day,

    t0 = the age at the start of

    strength development

    Parabolic

    HyperbolicS=

    )0

    (1

    )0

    (

    ttT

    k

    ttT

    k

    S

    Knudsen (1982)

    As listed above

    Exponential S= S

    te

    Freiesleben and Pedersen

    (1985)

    t = age,

    = a time constant (value 1 is

    the rate constant kTfor this

    function),

    = shape parameter

    PlowmanS= )log(Mba

    (Plowman, 1956)

    a= strength for maturity index

    M= 1

    b= slope of the line

    M= maturity index

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    11/34

    112

    A case study

    In this section, a case study of a post-tensioned slab of an apartment building in Melbourne is

    presented to illustrate the maturity method. The prediction of concrete compressive strength

    using the method will be compared with the in-situ compressive strength.

    The slab has the surface area of approximately 570 m2. The thickness of the slab is 230 mm.

    Thin copper-constantan type double T reusable thermocouple wires with cold junction

    compensation and linearisation were used to measure the temperature variation at various

    locations. Fig 3.5 shows the arrangement of the thermocouples in the slab cross section (100,

    150, 220 mm, measured from the surface of the slab), one thermocouple measuring the

    ambient temperature variation next to the slab and another one embedded in the ambient

    cured cylinders cast beside the slab to obtain compressive strength predictions in accordance

    with AS3600 and ASTM C31/C31 M. The measurement was obtained during the winter time

    as the range of average daily temperature could be lower than that of standard 23 C. In this

    case, the standard testing procedure following the Australian Standards AS1012 may not

    accurately represent the in-situ concrete strength. In this standard procedure, the concrete

    samples are cured under standard-moist conditions at constant temperatures of 23 2C for a

    standard temperate zone.

    Fig 3.5 Arrangement of thermocouple wires in the slab

    Atypical

    temperature

    profile measured from the site is shown in Figure (see Fig 3.6). Some

    small differences in temperature recorded across the slab depth can clearly be seen. The

    thermocouple deeper inside the slab (Channel 3) records higher temperatures. The ambient

    cured cylinder temperatures were generally lower than the temperatures recorded inthe in

    situconcreteslab.

    Timber

    formwork

    Datalogger

    Thermocouple

    measuringambient

    conditions

    Thermocouple

    positions(mm)

    Moulded

    Cylinder

    Channel1 10Concreteslab

    Channel2Channel3

    15

    22

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    12/34

    113

    Fig 3.6 Typical temperature profiles obtained for the thermocouple arrangements

    To best represent the temperature across the slab section, the in-situ concrete temperature

    profiles (Channels 1, 2 and 3) were averaged to represent a single profile in each case. The

    average profile for the third day is duplicated to extend the profiles to a seven day period.

    These averaged profile of is presented in Fig 3.7.

    Fig 3.7 Average concrete slab temperature profiles

    Cylinder specimens were tested at 1 to 28-day age. The concrete mix used is similar to the

    concrete mix used on-site. The concrete specimens cured in the laboratory were batched at

    the plant and truck-mixed in order to obtain a mix that is similar to the one that was

    dispatched to the site. All concrete specimens were ground and conditioned before being

    tested at 1 to 28-day age. The specimens were cured under standard and ambient conditions,

    isothermal conditions and temperature matched curing (TMC) methods.

    10

    15

    20

    25

    30

    35

    0 10 20 30 40 50 60 70 80

    Tempera

    ture(oC)

    Time (hrs)

    Channel 1 Channel 2

    Channel 3 Ambient

    Cylinder

    0

    5

    10

    1520

    25

    30

    35

    0 40 80 120 160

    Temperature(C)

    Time (hrs)

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    13/34

    114

    The specimens were cured in accordance with AS1012 (1999) and AS3600 (2009) for

    standard and ambient conditions respectively. The average compressive strengths of the

    cylinder specimens are presented in Table 3.2. To evaluate the in-situ strength development

    of concrete, some specimens were subjected to representative temperature profiles recorded

    from the two building projects using the TMC method. The specimens were cured under

    average temperature profiles shown in Figure 3.7. The average compressive strengths are

    presented in Table 3.1.

    Table 3.2 Standard and Ambient Cured Cylinder Compressive Strengths (fc)

    Age

    (Days)

    C1b, fc(MPa)

    Standard cured

    23oC

    C2b, fc(MPa)

    Ambient

    cured

    TMC C2c,

    fc(MPa)

    in-situ

    1

    23

    4

    7

    28

    11.2

    -24.2

    26.4

    31.7

    42.5

    13.4

    20.421.9

    23.9

    28.8

    40.3

    14.0

    21.025.4

    26.7

    32.3

    41.8

    The equivalent age can be calculated using Eq. (3.1) based on the temperature profile shown

    in Fig 3.7. The equivalent age profile is presented in Fig 3.8. The ratio of the activation energy

    against the gas constant, /E R at 4200 with a Tr value of 23C was assumed (as suggested

    by Day (2006)). The temperature profiles result in a slightly higher equivalent age for the

    channels positioned deeper in the slab section. .

    Fig 3.8 Equivalent age profiles for slab at different depths

    Fordetermining the strength-maturity function parameters, a linear regression analysis was

    conducted to curve fit the strength-maturity functions in Table 3.1 to the compressive strength

    010

    20

    30

    40

    50

    60

    70

    80

    0 20 40 60 80

    Equivalentage(hrs)

    Elapsed time (hrs)

    Channel 1

    Channel 2

    Channel 3

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    14/34

    115

    measured for cylinder specimens cured under a reference temperature of 23C. For brevity,

    only the result for the Linear Hyperbolic function (Eq. 3.2) is shown. The result of the

    regression analysis for the reference temperature of 23C is presented in Fig 3.9. The values

    of the parameters kT, t0 and S are 0.43, 0.18 and 43 respectively.

    Fig 3.9 Strength predictions from regression analyses

    To obtain the compressive strength of concrete subjected to various temperature conditions,

    the values of equivalent age should be used. For example, a 3-day age concrete (72 hrs)

    subjected to variation of temperature shown in Fig 3.7 has an equivalent age of about 2.7 day

    (65 hrs). Using the strength-maturity curve shown in Fig 3.10, the compressive strength of the

    concrete is about 22MPa.

    Fig 3.10 shows the comparison between the compressive strength prediction using the

    maturity method (linear hyperbolic function shown by the thick line in Fig 3.10), the standard

    cured approach and the in-situ (denoted TMC C2c) compressive strength. It is shown that the

    strength function can reasonably predict the in-situ strength of concrete. The difference

    between the strength predictions using the maturity functions and the in-situ strengths were

    found to be less than 10% with the exception of the 1 day age.

    4

    8

    12

    16

    20

    24

    28

    0 1 2 3 4

    strength(MPa)

    te(days)

    Linear Hyperbolic

    Standard cured

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    15/34

    116

    Fig 3.10 Comparison of strength functions with specimens cured under different temperature profiles

    1. Development of other mechanical properties over time

    Maturity method can equally be used to predict other concrete properties such as tensile

    strength and modulus of elasticity over time. However, similar to that reported for

    compressive strength prediction, that there exists no single value for the activation

    energy (Ea) for all the properties of concrete or different concrete formulations (Zhang et

    al., 2008).

    For completeness, some of the results reproduced here for discussion. The reader

    should refer to the original source for in-depth discussion of the results and analysis.

    The detailed mixture proportions of the high performance concrete are provided in Table

    3.3, which also indicates the concrete slump, air content and density measured after

    casting, and the compressive strength measured at 7 days (50MPa). Over 105 concrete

    cylinders (100200 mm) were made from one single batch of concrete to minimize the

    variability in the test results.

    0

    5

    10

    15

    20

    25

    30

    0 1 2 3 4

    streng

    th(MPa)

    te(days)

    Linear Hyperbolic

    Standard cured

    TMC C2c

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    16/34

    117

    Table 3.3 The mix composition details

    Proportions (kg) Properties

    Max water 213 Slump 185mm

    Cement

    (ASTM Type I)

    62.5 Air Content 4%

    Fine aggregate

    (5mm max,), dry

    125 Density 2452

    kg/m3

    Coarse aggregate

    (20mm max,), dry

    125 fc@ 7 Days 50MPa

    Superplasticiser, dry 2.1

    Approximately 3 h after setting, when the concrete gains enough strength, they are

    subject to different curing environments. For this, three equal groups of concrete

    samples (with their moulds and covers) are stored in three environmental chambers with

    temperatures previously set to 10 C, 25 C and 40 C and maintained as such until the

    time of testing. This procedure ensured that the concrete samples had the same

    properties at the onset of strength development for a better comparison.

    Fig 3.11 Temperature in concrete samples and environmental chambers

    Fig 3.11 presents the concrete temperatures monitored for the 3 groups of cylinders and

    their respective curing temperatures during the first day (with curing temperatures

    maintained constant until testing). Test results were obtained for the compressive

    strength, splitting tensile strength, and modulus of elasticity measured over time at the 3

    curing temperatures, respectively.

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    17/34

    118

    Regression analyses were then conducted to model the development of these properties

    as functions of time. Since the early-age development of HPC properties are of prime

    interest in this study, the analyses presented in this paper focus mainly on the results

    measured during the first 7 days. This ensured more accurate analyses and predictions

    for the period of interest, during which the properties of HPC developed relatively fast.

    The 28-day test results will be presented later in the paper as additional information. The

    following empirical exponential equation, adapted from the well-known relationship

    suggested by the (CEB-FIP, 1990)[20], was used to model the development of each

    selected property of concrete:

    1 (3.2)

    where P(t) represents a given property as a function of time, P7 is the property value at 7

    days, tis the time elapsed after the setting time, and A and Bare constants obtained by

    regression analysis (Figs 3.12 and 3.13). The obtained regression curves for the

    development of these properties were then used to determine the activation energy

    factors and develop the property-maturity relations. Note that by using the time elapsed

    after setting as the time zero in the above equation ensures the validity of the model for

    concretes that may have different setting times.

    Fig 3.12 Splitting tensile strength measured for 3 curing temperatures

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    18/34

    119

    Fig 3.13 Modulus of elasticity measured for 3 curing temperatures

    To estimate the equivalent age, the range of values presented for Ea presented may be

    assumed.

    To determine the activation energy for the properties such as tensile strength and

    modulus of elasticity, the followings steps are recommended:

    1. The determination ofK(T) from the initial slopes of the relative property P/Pu curves

    for different temperatures (at t=to), where the Pu is the ultimate value of the property;

    2. The activation energy can be obtained by plotting the natural logarithms of kT versus

    the inverse of the curing temperature (15, 23, 35 and 50C). The negative of the slope

    of the straight line equals the activation energy (Ea) divided by the gas constant (R).

    3. The equivalent age can be determined using

    1 1

    0

    a

    r

    Et

    R T T

    et e t

    (3.3)

    And the properties of concrete for different temperature profiles can be predicted using

    the equivalent age and the curve for the reference temperature.

    Zhang et al., 2008 report experimental results conveying important information on the

    activation energy: (i) different properties may have different Ea for a given concrete; (ii)

    different concretes may have different Ea for a given property; and (iii) different

    development stage of a given property of a given concrete may have different Ea. The

    experimental investigation demonstrates that the properties of Ea/R vary as the

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    19/34

    120

    properties develop over time. The range of values listed is varying from 3763 K to 7781 K

    for tensile strength and from 7145 K to 8435 K for modulus of elasticity.

    2. Effect of Cementitious Materials on Concrete Strength Development

    A recent investigation of the accuracy of the maturity method to estimate the strength of

    concrete with different cementitious materials such as fly ash and slag is reported in

    (Brooks et al, 2007). The reference discusses the strength development of mortar cubes,

    made from Type I cement and various replacement levels of Class C fly ash, Class F fly

    ash, and ground-granulated blast-furnace slag which are cured at isothermal curing

    temperatures of 8, 23, and 40C. The temperature and activation energy values were

    determined for these cementitious systems. Table 3.4 lists a summary of mixtures tested:

    Table 3.4 Summary of Mixtures Tested during This Study (Courtesy: Brooks et al, 2007)

    Data from the reference (Brooks et al, 2007) is used to make up the Excel spreadsheet

    (strength prediction of concrete with varying fly ash content.xls). The excel file makes

    use of the data provided in the reference to estimate the equivalent age for each of the

    mixes listed in Table 3.4. For the calculations, the average concrete slab temperature for

    Fig 3.7 is assumed. The reference temperature is set to 23C. Analysis results

    determined with exponential strength-age linear hyperbolic function according to (Tank

    and Carino, 1991, see Table 3.1) is used for the strength calculations. The model

    parameters which are based on experimental results are listed in Table 3.5. These are

    obtained following the steps listed in Section 3 (Maturity Method).

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    20/34

    121

    Table 3.5: Analysis Results Determined with Strength-Age Function (Courtesy: Brooks et al, 2007)

    The results of the experimental study show that composition of the cementitious

    materials in the system significantly influences the maturity method to accurately

    estimate the strength development. The effect of addition of fly ash of different types on

    concrete strength development is shown in Fig 3.14. As can be noted, the Class F fly ash

    results in significantly lower strength development of concrete when compared to that of

    Class C fly ash.

    Fig 3.14 Effect of addition of fly ash of different types on concrete strength development

    The amount of longterm strength reduction, due to curing at high temperatures

    compared with curing at room temperature, is equally found to be influenced by the type

    of cementitious system used in the concrete mixture.

    Sirivivatnanon et al. (2009) presented results from research of two concrete mixes

    supplied to two building projects over a 16-month period covering two winter seasons in

    Sydney. In this investigation, real-time in-situ concrete temperatures in post-tensioned

    slab were simulated in a temperature matched curing tank in a laboratory. Concrete

    0.0

    10.0

    20.0

    30.0

    40.0

    0.0 50.0 100.0 150.0

    f'c(Mpa)

    te (hr)

    ClassCflyashC15

    C25

    C35

    IA

    0.0

    10.0

    20.0

    30.0

    40.0

    0.0 50.0 100.0 150.0

    f'c(Mpa)

    te (hr)

    ClassFflyashIA

    F15

    F25

    F35

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    21/34

    122

    cylinders sampled from building sites were subjected to curing conditions identical to

    those experienced in the slabs in order to determine as accurate as possible the in-situ

    concrete strength development. Additional concrete cylinders cast from the same

    concrete were cured using four different curing methods: air curing, insulated air-curing,

    semi-adiabatic curing and standard AS 1012 water curing. Comparisons were made

    between the cylinder strengths cured with the four methods and the estimated in-situ

    concrete strengths for twenty concrete slabs cast in ambient temperatures ranging from

    10C to 25C. The anchorage performance of post-tensioning strands at initial and final

    stressing was also monitored. It was found that the 4-day air-cured strengths consistently

    underestimated in-situ concrete strength by about 10% and had the poorest correlation

    to in-situ strength of any of the curing regimes investigated. This finding suggests that

    strengths derived from air cured cylinders cannot necessarily be considered to provide

    curing conditions similar to those of concrete in the work as noted in AS3600 (Section 17

    in 2009 Edition). The 1-day and 4-day in-situ strength of 9 MPa and 24.5 MPa was found

    to be satisfactory for the initial and final stressing of 12.7mm diameter prestressing

    strands for both types of concrete without the need for prescriptive binder specifications.

    Summary

    Benefits of Maturity

    The benefits of using maturity as contrasted with traditional quality control procedures

    are:

    It provides a real-time, in-place indication of the strength of the concrete.

    It is a non-destructive testing method as contrasted to breaking cylinders in the

    laboratory.

    Itprovidesearlyqualityverificationoftheinplaceconcrete,oftenwithinhoursof

    itsplacement.

    Itacceleratestheconstructionprocessbyallowingthepavementtobeopenedto

    traffic

    or

    formwork

    stripped

    from

    structures

    (or

    for

    posttensioned

    construction

    helpsearlystressingsequence).

    Itreducesthequantityandcostofsamplingandtestingbyreducingthenumberof

    cylindersthatneedtobecastandbrokentodeterminestrength.

    Thematuritymethod isreadilyassessabletomostmaterials laboratoriesbecause

    itisbasedontraditionalcylindercompressivestrengthtestsforitsdevelopment.

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    22/34

    123

    Weaknesses of Maturity

    The maturity method also has its weaknesses. Changes in the brand of cement, the

    source and type of pozzolonic admixtures, the source of the aggregate or the water to

    cement ratio can result in a change in the strength-maturity relationship and require anew calibration curve. The method also cannot account for humidity conditions during

    curing, that is, if there is not enough moisture present for hydration to occur the strength

    gain will not be realized as predicted by the maturity curve. It is not accurate when there

    are large temperature swings during the curing process. The method also cannot

    account for concreting practices that result in inadequate consolidation, poor placement

    techniques, inadequate curing, lack of protection during early ages, or fluctuations in air

    content.

    Volume Changes at Early Age

    If the heat produced during the hydration reaction is not transmitted to the environment at the

    same rate as it has been produced, the temperature rise in the concrete member might

    become significant. Like any other material, concrete is susceptible to volume changes when

    subjected to varying temperatures. The thermal expansion coefficient of concrete is about 10-

    1510-6

    per C (Neville, 1996). Temperature is one of the main causes of volume changes in

    the early age concrete, besides autogenous deformation.

    Temperature raises as a consequence of exothermic hydration reaction and the results

    volume changes. If the deformation due to the volume change is restrained, stresses develop

    in the member, often referred to as thermal stresses. In practice, restraints can be provided by

    other adjacent structural members such as (the building core, columns or beams).

    Reinforcements can also provide restraining effects internally. If concrete member was set

    without any restraints, the volume changes would occur freely and no stresses would develop

    in the member. In case of a restrained member, compressive and tensile stresses could

    potentially develop due to heat development and cooling phases, respectively.

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    23/34

    124

    Input parameter for thermal analysis

    Parameter Value

    Thermal conductivity 2.6 W/mK

    Volumetric specific heat 2400 J/m3K

    Convection coefficient in boundary 10 W/m2K

    Arrhenius Constant 6000

    Initial temperature 20 C

    Coefficient thermal expansion () 15 10-6 per C

    Properties of the concrete mix such as conductivity and capacitance are often assumed

    constant. In reality these properties vary over time and are dependent on concrete maturity.

    The thermal conductivity of concrete is reported to decrease over time as the concrete

    matures (Gibbon and Ballim, 1998). The value depends on the moisture content and

    temperature evolution, as well as the type of cement and aggregate of the concrete mix. Theparameters commonly adopted for concrete are summarized in Table given here.

    Early Age Creep

    Important factors that may contribute to cracking and failure of the early-age concrete are the

    ambient conditions (e.g. temperature, humidity) and properties such as creep and shrinkage.

    For a restrained concrete element, creep can occur due to thermal expansion and shrinkage.

    Creep is considered as a time dependent deformation of concrete due to the imposed

    external mechanical load or as a result of thermal expansion and shrinkage associated with

    the hydration reaction. Immediate deformations due to applied load are referred to as the

    nominal elastic strains (Neville 1996). This is not completely correct since there will always be

    some early creep, but it is in practice good enough for most purposes. Creep can then be

    taken as the increase in strains as a function of time, after this point as shown in Fig 3.15.

    Additionally, there will also be time-dependent shrinkage, unaffected of whether the concrete

    is loaded or not. Shrinkage is a result of chemical and physical changes in the concrete

    volume during the hydration process. It can be divided into plastic shrinkage and drying

    shrinkage. Plastic shrinkage occurs while the concrete is in the plastic phase. Drying

    shrinkage is mostly affected by environ-mental conditions such as wind speed, temperature

    and relative humidity. As shown in the figure, there are two types of creep which can make up

    the total creep, depending on the moisture content of the environment. If there is no moisture

    movement between the concrete and the environment, it can roughly be assumed that all

    creep is basic creep, even though this is also a simplification.

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    24/34

    125

    Fig 3.15 Time-dependent strains in concrete subjected to external loading over a time, Courtesy: Neville

    (1996)

    Estimation of the early age creep effects is essential in accurately estimating the development

    of stresses that are induced in the concrete member. The stresses can be caused by thermal

    effects, autogenous deformations or by application of external actions such as post-tensioning

    loads. It is reported that creep deformation of concrete at early ages may lead to stress

    fluctuations that reach magnitudes of 50% or higher (see for eg., Faria et al., 2006). At the

    same time, it is important to note that with the evolution of the hydration reaction makes the

    material properties of concrete such as the elastic modulus, compressive and tensile

    strengths to be dynamic.

    Elastic materials have the ability to fully regain the initial shape after being deformed.

    Concrete at early ages cannot be assumed to be elastic. A visco-elastic material exhibits both

    viscous and elastic characteristics under deformation. While elastic deformations are always

    recoverable upon unloading, viscous deformations are never recoverable (Neville 1996).

    Considering Fig 3.16, the instant that the stress is being applied to the concrete member, the

    strain is elastic and thus recoverable if the stress is removed immediately. Obviously, if the

    magnitude of the applied load is close to the concrete strength, this would not be the case due

    to cracking and plastic deformations.

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    25/34

    126

    ElasticStrain

    t

    Fig 3.16 Elastic and time dependent strains of concrete due an imposed load [After stergaard et al.

    (2001)]

    A strong aging tendency of concrete material in the first two days after casting has been

    observed at-several occasions (Altoubat and Lange 2001; Bissonnette and Pigeon 1995).

    Aging can be explained as the concrete hardening and gaining strength. The concrete is very

    susceptible to creep at early ages, but quickly ages and therefore becomes more resistant as

    it hardens.

    According to the linear theory, the strain is proportional to the applied stress. Hence, the strain

    at time tcaused by a constant uniaxial stress applied at time tis given by:

    )',(.)( ttJt

    The compliance function J(t, t) for a specimen subject to constant stress is given by the

    following expression:

    J(t, t) = q1+C0 (t, t)+Cd (t, t,t0)

    Where, q1 is the instantaneous strain due to unit load, C0(t, t) is the basic creep compliance

    function, and Cd (t, t, t0) is the drying creep compliance function, t is the age of concrete at

    time of loading in days and tis the current age of concrete in days.

    For a variable stress history, the principle of superposition is assumed to be valid. There is a

    great many number of creep models proposed in the literature. For consideration of early age

    effects, however, Bazants B3 model and the Double Power Law (DPL) is commonly used.

    The creep response to a load applied at slightly different ages changes rapidly at this stage of

    the hydration process due to the strong aging. Higher creep compliance is reported for

    concrete at earlier ages. Prior to one day, even a light load was observed to produce twice the

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    26/34

    127

    amount of creep of that only a few hours later, using identical concrete mixes (Atrushi, 2003,

    Ostergaard, 2003).

    Construction Issues and the role of Early Age Concrete

    Although high early strength concrete (HESC) concrete is an obvious choice for construction,

    particularly for multi-storey buildings, many instances of localised failures have been reported

    during construction. These are partly due to wrong estimates of the strength prediction of the

    concrete strengths. A wide range of other defects such as excessive floor sagging, cracking,

    spalling, honeycombs, increased long term deflections, bulges and misalignments are also

    considered as failures that result in serious serviceability problems (Feld, 1964; Aalami and

    Kelly, 2001). In the following section, typical examples of failures related to both precast and

    post-tensioned industries are presented.

    Post-tensioned slabs Anchorage failures

    In post-tensioned systems, the prestressing force is transmitted to the concrete mainly by the

    direct bearing of a steel anchorage plate or casting on the concrete. An external anchorage is

    used for stressing the strand (live end) and an internal anchorage is used to resist the loads

    by stressing of the strand (dead-end). A typical slab edge anchorage assembly is presented in

    Fig 3.17. At the dead-end, the strands coming out of the duct tube are spread out and are

    bent with their ends to form the shape of an onion. The anchorage zone of a post-tensioned

    concrete member is a critical portion of the member where the concentrated PT forces spread

    to a uniform stress distribution in the concrete.

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    27/34

    128

    Fig 3.17 Anchorage in slab edge (dimensions in mm)

    The common criteria for acceptance of concrete used in post-tensioned applications having

    12.7 mm diameter strands in Australia are;

    Minimum 28 day characteristic cylinder strength (fc) of 32 MPa

    Compressive strength at final stress transfer of 22 MPa typically at 3 to 5 days after

    concrete

    placement

    Compressive strength of 7 MPa at 24 hours after concrete placement for initial

    stressing at

    25% of the ultimate stress.

    At these times, i.e., 1-7 days after the concrete pour when the post-tensioning procedure is to

    be carried out, while the concrete is curing and the properties of concrete evolve over time

    (Choong et al., 2005). One major issue with the post-tensioning of slabs is the failure of the

    concrete material at the anchorage zone locations. Failures happen due to stress

    concentrations in spite of factors of safety and heavy reinforcement, usually in the form of

    loops or spirals, as shown in Fig 3.17. A typical anchorage zone failure in a post-tensioned

    suspended slab is shown in Fig 3.18. The failures, which mostly happen during the post-

    tensioning process, can be serious and explosive in nature. They happen at the second stage

    of post-tensioning at either of live or dead-end anchorages. As can be seen (Fig 3.18), they

    require resources for replacement and repair which can substantially increase the

    construction cost. Reinforcement congestion in the local zone, poor concrete quality and

    inappropriate workmanship has been blamed for the failures. Inadequate strength prediction

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    28/34

    129

    of in-situ concrete at the time of application of the post-tensioning has been another prevalent

    hypothesis [2] (CPN29, 1996). Anchorage failures have been occurring at the dead and live

    ends, resulting in loss of load in the strand, delamination and spalling of concrete around the

    anchorage. In many instances, where the concrete cover is broken off, grooves can be

    observed demonstrating slippage of wires and strand assembly with respect to surrounding

    concrete.

    Fig 3.18 Failed anchorage in slab edge photographed on construction site

    For the live end, the duct covers the strands entirely and the PT load is transmitted directly to

    the anchorage plate. As regards to dead-end anchors, which constitute a more critical case,

    the PT load is resisted initially by bonding effect of the straight part of the strand. This straight

    part of the strand, about 800 ahead of the anchor plate is bonded to the concrete (see, Fig

    3.17). When the bond mechanism of the strands is exhausted, the load is directed to the

    anchorage assembly and transmitted to the surrounding concrete. Clearly, there are two

    contributing factors in resisting the PT load: 1) the bond strength of the straight part of the

    strand; and, 2) the anchorage action due to the anchorage plate. In details, the onions which

    are themselves made up of bent wires, are equally bonded to the surrounding concrete.

    A comprehensive research project is carried out at the University of Melbourne sponsored by

    Australian Research Council and Holcim to investigate this problem. In view of the anchorage

    description, it is noted that extensive number of variables are involved. The preferred option

    was to investigate the problem within the framework of finite elements. Sofi et al. (2007) report

    the results of the experimental work and the modelling approach adopted to investigate the

    behaviour of anchorage zone concrete. The experiments were carried out in an attempt to

    obtain the input parameters necessary for the finite elements and to validate the models. In

    this paper, a short literature review of bond mechanism is presented first followed by a

    description of the experimental work. This is followed by a discussion of the models and the

    results (see Sofi et al., 2011).

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    29/34

    130

    In recent times, questions have been raised as to the possible negative impacts of fly ash

    inclusions into concrete and the potential for increased risk of anchor failure as a result of

    impact on early age concrete properties relevant to when final stressing is applied. Key

    concerns appear to include potential loss of bond between strands and concrete, lower early

    age tensile properties and compressive strength. Some specifications limit the percentage of

    fly ash allowed in a post tensioned concrete mix to be no greater than 10% by weight of

    Portland cement for these reasons.

    Sirivivatnanon et al. (2009) conducted an experimental study on implications of using fly ash

    in post-tensioned concrete.

    They concluded that;

    Fly ash concretes can be easily designed to meet early age requirements specified for

    post tensioning applications.

    Concrete strength gain characteristics for control (non fly ash) and fly ash concrete

    mixes are well understood and are often optimised for particular design and

    constructional applications.

    The research indicates that the bond strength (as determined by pullout load) between

    tendons and concrete is a function of the compressive strength of the concrete and not

    the composition of the cementitious component. In particular, fly ash inclusions of up to

    30% appear to have no adverse effect on bond at the same compressive strength.

    There is no evidence in the technical literature to support the hypothesis that increasing

    fly ash contents in concrete (certainly to levels up to 30%) will reduce bond strengths

    between tendons and concrete.

    Precast Walls Support and Anchorage Systems during Construction

    The use of precast allows not only the speedy erection of the structure, but also flexibility and

    overall program shortening. This is achieved by allowing the production of components at the

    same time the footing system is being prepared1.

    A minimum amount of propping allows the following trades to commence work on the

    structure earlier than conventional construction methods. During construction the lateral load

    1http://www.npcaa.com.au/images/file/Skeletal%20frame%20struct.pdf

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    30/34

    131

    path for a building under construction is incomplete. Therefore, external supports in the form

    of vertical struts are provided to resist the lateral wind loads and to provide stability for the

    newly installed precast elements.

    For large panels, the joints between panels are generally located at rafter centres so that theroof framing (or portal frames when panels are used as cladding only) laterally supports both

    panels. For smaller panels, an intermediate strut can be provided to laterally support the

    panels at the intermediate joint location. Early age concrete strength is very important and

    some failures are reported due to problems in reaching specified strength.

    Fig 3.19 Rafter to panel connection at joint

    Cast-in headed anchors provide a means of making bolted or welded connections to other

    concrete members. According to the National Precast Concrete Association of Australia

    (NPCCA), the usual forms of these anchors are illustrated in Fig 3.20.

    Fig 3.20 Types of anchors, (Courtesy, NPCAA Manual)

    Ferrules, which are internally-threaded, steel sleeves to take a bolt. They are anchored by

    transverse reinforcement attached to the base by welding, or, through a transverse hole in the

    base of the sleeve, or, with a J-bolt screwed or butt-welded to the base. A common

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    31/34

    132

    application for a ferrule is the restraint fixing for a wall panel. Ferrules for structural

    connections are typically 75100 mm long and the usual bolt diameters are 20 and 24 mm.

    Plates with stud anchors provide a means to weld a fixing bracket in its correct position after

    erection of the member. Such brackets should reach their yield strength prior to the load

    reaching the calculated capacity of the cast-in stud assembly.

    Fig 3.21 Failure modes of anchors (Courtesy, NPCAA handbook)

    Figure 3.21 depicts failure modes of anchors asreported by the National Precast Concrete Associationof Australia. The following failure modes of an anchorare possible (NPCAA):

    Steel failure of the anchor shaft or bolt in tension

    Steel failure of the anchor shaft or bolt in shear

    Breakout of a prism of concrete surrounding the

    anchor in tension

    Breakout of a prism of concrete towards an edge in

    shear

    Crushing of the concrete over the bearing area at

    the base of the anchor (pullout)

    Rotational pryout of an anchor body subjected to

    shear

    Side-face blowout when the anchor is located close

    to an edge in conjunction with deep embedment

    (greater than 200 mm)

    Splitting of the concrete in the vicinity of the anchor.

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    32/34

    133

    The type of failure cones in high strength concrete are generally deeper than those in normal

    strength concrete. This is an indication that higher compressive strength of concrete reduces

    the possibility of local crushing and thus enhances the interlock effects. Some useful results

    are also available in Joshi (2001) and Yin (2002).

    REFERENCES

    1. Aalami, BO and Kelley, GS 2001, Structural design of post-tensioned floors, Concrete

    International, v.23(1), Pp.31-36.

    2. ACI318-11, Building code requirements for structural concrete (ACI 318-11) and Commentary

    (ACI 318R-11)..

    3. Altoubat, SA and Lange, DA 2001, 'Tensile Basic Creep: Mea-surements and Behaviour at

    Early Age', ACI Materials Journal, vol. 98, no. 5, pp. 386-93.

    4. AS 1012.8.1, Method of testing concrete: Method of making and curing concrete -

    compression and indirect tensile test specimens. Committee BD-042, Australian Standards

    1999.

    5. AS 3600, Concrete structures. Committee BD-002, Australian Standards 2001.

    6. ASTM C192/C192 M-10, Making and Curing Concrete Test Specimens in the Field, American

    society for testing and materials (ASTM). West Conshohocken, Pennsylvania; 2007.

    7. Atrushi, DS 2003, 'Tensile and Compressive Creep of Early Age Concrete: Testing and

    Modelling', Doctoral thesis, The Norwegian University of Science and Technology.

    8. Baant, ZP and Panula, L 1978, 'Practical prediction of time de-pendent deformations of

    concrete', Materials and Structures, vol. 11, no. 65, pp. 307-28.

    9. Bissonnette, B and Pigeon, M 1995, 'Tensile creep at early ages of ordinary, silica fume and

    fiber reinforced concretes', Ce-ment and Concrete Research, vol. 25, no. 5, pp. 1075-85.

    10. Brooks, AG1; Schindler, AK and Barnes, RW., 2007 Maturity method evaluated for various

    cementitious materials, Journal of materials in civil engineering, v. 19(12), pp. 1017-1025.

    11. Brundtland Report: 1987, The Report of the Brundtland Commission, Our Common Future,

    published by Oxford University Press..

    12. Carino, N. J. and Lew, H. S., The Maturity Method: From Theory to Application. In: Chang, P.

    C., editors. Structures Congress and Exposition. Washington, D.C.: American Society of Civil

    Engineers; 2001. p. 19.13. CED-FIB, CEB-FIP Model Code 1990, Information Bulletin No. 213/214, Euro-International

    Concrete Committee, Lausanne, 1993, 437 pp.

    14. Choong, J., Mendis, P.A., Mak, S.L., and Baweja, D., More Accurate Concrete Strength

    Predictions for Post-Tensioned Slab Construction, Proceedings, Concrete Institute of

    Australia, 22nd Biennial Conference, Concrete 2005, Melbourne, Australia, October, 2005.

    15. CPN29, Prestressed concrete anchorage zones. Concrete Institute of Australia 1996; 1-13.

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    33/34

    134

    16. Day, K. W., Concrete mix design, quality control and specification. London: E. and F. N.

    Spon; 2006.

    17. Faria, R, Azenha, M and Figueiras, (2006), 'Modelling of con-crete at early ages: Application

    to an externally restrained slab', Cement and Concrete Composites, vol. 28, pp. 572-85.

    18. Feld, J., 1964, Lessons from failures of concrete structures, American Concrete Institute

    monograph, v.1(1), Pp. 179.

    19. Flower, J., Sanjayan, G., and Baweja,D, Environmental Impacts of Concrete Production and

    Construction, Proceedings, Concrete Institute of Australia Biennial Conference, Concrete

    2005, Melbourne, Australia, October, 2005

    20. Freiesleben Hansen, P. and Pedersen, E. J., Curing of concrete structures, Comit euro-

    international du bton (CEB) Information Bulletin, (1985)166.

    21. Gibbon, GJ and Ballim, Y 1998, 'Determination of the thermal conductivity of concrete during

    the early stages of hydration', Magazine of Concrete Research, vol. 50, no. 3, pp. 229-35.

    22. Jenkins, D, Baweja, D, Portella, J., Optimising Building Design for Sustainability Using High

    Performance Concrete , 2011.

    23. Joshi, T., Behaviour Experimental Investigation of PostInstalled Anchors in Highstrength

    Concrete,MastersThesis(supervisedbyP.Mendis),TheUniversityofMelbourne,2001

    24. Knudsen, T., Modelling hydration of Portland cement: Effect of particle size distribution,

    Engineering Foundation Conference on Characterization and Performance Prediction of

    Cement and Concrete, Henniker, N. H. (Ed.), (1982)125.

    25. Lin,Y.,BehaviourofScrewAnchorsinHighstrengthConcrete,MastersThesis(supervisedby

    P.Mendis),TheUniversityofMelbourne,2002

    26. Mak, S. L. and Torii, K., Strength development of high strength concretes with and without

    silica fume under the influence of high hydration temperatures. Cement and ConcreteResearch 1995; 25(8); 1791-1802.

    27. Neville, AM 1996, Properties of Concrete, 4th and final edn, Wiley, Harlow, Essex.

    28. Ngo, T., Mendis, P., Aye, L., Gammampila, R., Crawford, R., Life cycle assessment of steel

    and concrete framed high rise commercial buildings, International Conference on

    Sustainable Built Environment, ICSBE 2010, Sri Lanka

    29. NPCAA *(2009), Precast Concrete Handbook, 2nd edition, National Precast Concrete

    Institute of Australia.

    30. Plowman, J. M., Maturity and the strength of concrete, Magazine of Concrete Research,

    8(22), (1956)13.

    31. Sirivivatnanon, V, Baweja, D. and Khatri, R.P., Evaluation of In-situ Concrete Strengths for

    Post-Tensioning of Concrete Slabs, 2009

    32. Sofi, M., Mendis, P.A., Baweja, D. and Mak, S.L., Behaviour of Post-Tensioning Anchors in

    Early Age Concrete Slabs, Proceedings, Concrete Institute of Australia 23rd Biennial

    Conference, Concrete 2007, Adelaide, Australia, October, 2007.

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012

    2nd International Conference on Sustainable Built Environment (ICSBE) 201214th, 15th, 16th December 2012Kandy, Sri Lanka

  • 8/2/2019 Limit States in Construction_Mendis

    34/34

    33. Sofi, M., Mendis, P.A., Baweja, D. and Elvira, E., Bond Performance of Strand and Wire in

    Early Age Concrete, 9th International Symposium on High Performance Concrete:Design,

    Verification and Utilisation, 9-11 August 2011, New Zealand.

    34. Stergaard, L, Lange, DA, Altoubat, SA and Stang, H 2001, 'Tensile basic creep of early-age

    concrete under constant load', Cement and Concrete Research, vol. 31, no. 12, pp. 1895-9.

    35. Tank, R. C. and Carino, N. J., Rate constant functions for strength development of concrete',

    ACI Materials Journal, 88(1), (1991) 74-83.

    36. Zhang, J., Cusson, D., Monteiro, P. and Harvey, J. (2008), New perspectives on maturity

    method and approach for high performance concrete applications, Cement and Concrete

    Research, 3814381446.

    Pre-Conference Workshop on High Performance Concrete Design and Applications January 2012