Lets and Quantities Report Lets and Quantities Report Mark Wolfgram Mark Wolfgram Division of Transportation Investment Division of Transportation Investment Management Management Wisconsin Transportation Builders Association Wisconsin Transportation Builders Association Annual Meeting – September 25, 2008 Annual Meeting – September 25, 2008 State Highway Program Update State Highway Program Update

Upload: shanon-anderson

Post on 29-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Lets and Quantities ReportLets and Quantities Report

Mark WolfgramMark WolfgramDivision of Transportation Investment ManagementDivision of Transportation Investment Management

Wisconsin Transportation Builders Wisconsin Transportation Builders

AssociationAssociation

Annual Meeting – September 25, 2008Annual Meeting – September 25, 2008

State Highway Program UpdateState Highway Program Update

2

FY08 Financial Recap

State budget not passed until the end of October, a record 4 months late

Budget repair bill not passed until mid-May, nearly the end of the fiscal year

When the smoke cleared………

3

FY08 Financial Recap

Major highway program was up $7 million

SE freeway rehabilitation and local highway programs were unchanged

However, as in FY07, late resolution of financing led to a higher proportion of lets later in the fiscal year

State rehabilitation program was up $6 million over the starting budget

4

$792 Improvement Program

Million

sFinal FY08 LET Level

$4 Maintenance/Operations$796

5

Million

s

Improvement Portion of LetsExceeds Goal

Let Goal

Range

$792

$740

$760

Main Reasons?

1. Assembly Budget was used to set the let goal last year

2. Final budget was higher

6

History Of LetsMillions

$0

$200

$400

$600

$800

$1,000

$1,200

' 90 '91 '92 '93 '94 '95 '96 '97 '98 '99 '00 '01 '02 '03 '04 '05 '06 '07 '08

331 353

426 403 406 416 442473

534597 606

645 639639 662

745

1023

MQ

MQ708

792

7

History Of Construction Costs

0

100

200

300

400

' 90 '91 '92 '93 '94 '95 '96 '97 '98 '99 '00 '01 '02 '03 '04 '05 '06 '07 '08

Index 1990=100

8

History Of Construction Costs

0

100

200

300

400

' 90 '91 '92 '93 '94 '95 '96 '97 '98 '99 '00 '01 '02 '03 '04 '05 '06 '07 '08

Index 1990=100

Prices Up 3x 1990

9

History Of Lets – Constant $Millions

$0

$50

$100

$150

$200

$250

$300

$350

$400

$450

' 90 '91 '92 '93 '94 '95 '96 '97 '98 '99 '00 '01 '02 '03 '04 '05 '06 '07 '08

331 331

408

297284 280

295280

309

363

328 330

360346 345

Highway Construction Cost Index used to provide constant dollar comparison

352

413

MQ

MQ

276263

10

Final vs. Estimated Quantities For FY08

0

0.5

1

1.5

2

2.5

3

Asphalt Concrete Bridge

Deck

Grinding Rubblizing

Estimated

Final

Millions

(Tons) (Sq Yds) (Sq Ft)

(Sq Yds)

Even

Even

(Sq Yds)

-11%

+38%

-8%

11

Final vs. Estimated Quantities For FY08

0

10

20

30

40

50

Excavation Base Course Milling Striping

Estimated

Final

Millions

(Lin Ft) (Cu Yds)

(Sq Yds)(Tons)

+5%

+40%

Even+1%

12

Looking Ahead and Setting the FY09

Program

13

Setting the FY09 Program

1. Update all project cost estimates to FY09 dollars

2. Confirm a funding level for each program State Rehabilitation Major Highway SE Freeway Rehabilitation Local Highway

3. Add federal earmarks and carryover balances

4. Subtract funding needed for design/construction delivery and contract change orders

14

Setting the FY09 Program

5. Result: State/Fed funding level for lets and non-lets in each program

6. Finalize schedule of lets and non-lets needed to deliver the program

15

Program Funds Going To Lets

40%

50%

60%

70%

'00 '01 '02 '03 '04 '05 '06 '07 '08

% Program Funds Going To Lets

16

Program Funds Going to Lets

50%

60%

70%

'03 '04 '05 '06 '07 '08

% Program Funds Going To Lets

50%

60%

70%

'03 '04 '05 '06 '07 '08

State Highway Rehab

Program

Major Highway Program

66%

58%

17

Setting the FY09 Program

5. Result: State/Fed funding level for lets and non-lets in each program

6. Finalize schedule of lets and non-lets needed to deliver the program

7. Identify contingency projects to have ready in FY09 in case they’re needed

Delivery timetable slips

Increased funding becomes available

18

Projected FY09 LET Level

$875-895

$870-890 Improvement Program

Million

s

$5 Maintenance & Operations

As of September 25, 2008

19

Caveats On FY09 Let Level

FundingFunding??

20

Quantity Estimates Based on FY09

ProgramAs Of September 25, 2008

21

Estimated Excavation Quantities For FY09

17.2

13.6

17.2

0 5 10 15 20

'09

'08

'07

'06

Millions Of Cubic Yards

17.5

22

Estimated Base Course Quantities For FY09

5.1

4.9

6.8

0 1 2 3 4 5 6 7

'09

'08

'07

'06

Millions Of Tons

5.6

23

Estimated Concrete Quantities For FY09

2.0

1.8

2.7

0 1 2 3

'09

'08

'07

'06

Millions Of Square Yards

2.0

24

Estimated Bridge Deck Quantities For FY09

2.0

2.0

1.7

0 1 2 3

'09

'08

'07

'06

Millions Of Square Feet

2.0

25

Estimated Asphalt Quantities For FY09

2.9

3.4

3.2

0 1 2 3 4

'09

'08

'07

'06

Millions Of Tons

2.8

26

Estimated Milling Quantities For FY09

7.5

7.7

4.8

0 1 2 3 4 5 6 7 8

'09

'08

'07

'06

Millions Of Square Yards

6.6

27

Estimated Grinding Quantities For FY09

529.2

413.2

271.4

0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900 950

'09

'08

'07

'06

Thousands Of Square Yards

925.0

28

Estimated Rubblizing Quantities For FY09

648.8

946.8

629.2

0 100 200 300 400 500 600 700 800 900 1000

'09

'08

'07

'06

Thousands Of Square Yards

690.6

29

Estimated Striping Quantities For FY09

33.4

36.7

46.1

0 10 20 30 40 50

'09

'08

'07

'06

Millions Of Linear Feet

22.4

30

A Recap…

Concrete EvenExcavation +2%Milling -12%Asphalt -3%Base Course +10%

Rubblizing +6%Striping -33%Bridge Deck EvenGrinding

+75%

Estimated FY09 vs. Final FY08

31

An Update on Majors

32

August TPC Report

20 Major projects enumerated and in varying stages of construction

Reported an increase in cost of $321 million (2009 $)

$307 million for energy, materials and real estate

$14 million for scope and design refinements

8 projects under study for potential enumeration

$0

$400

'09 '10 '11 '12 '13 '14 '15 '16 '17 '18 '19 '20

Program Level

Millions Of 2009 Dollars

Current Schedule Of Costs = $2.48 Billion

Majors ScheduleAs of August TPC Report

$0

$400

'09 '10 '11 '12 '13 '14 '15 '16 '17 '18 '19 '20

Program Level

Millions Of 2009 Dollars

Reschedule and Scope USH 41 Work To Interstate Standards

?

?

Costs Moving to ’16 and Beyond are Currently

Unknown

?

35

Future Enumerations?

Program is fully scheduled over the next 6 years, maybe longer

Timing of future enumerations depends on the future rate of increase in project costs vs. the funding available

36

Questions?Questions?