    Earthwork Activities

    A) Site clearing & grubbing

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    3/44

    4/8/2016 3

    Earthwork Activities

    A) Site clearing & grubbing • removal of trees, shrubs, and other vegetation

    • removing stumps and root mat at least 600mm

    below sub-grade

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    4/44

    4/8/2016 4

    Earthwork Activities

    B) Stripping Top Soil (to be done after site clearing)

    • Top soil - resulting from decomposition of vegetative matter -

    unsuitable for use in embankment- Strip the top soil eg 150mm thick as mentioned in BQ/

    drawings – stockpile - to be used for turfing work/ landscape

    or to waste

    • Some project, stripping of top soil is given as a separate item(Quantity as ‘Lump Sum’ or using rate ‘per meter square’) and

    some used as part of the excavation

    Eg Description in BQ:

    ‘Strip top soil to an average depth of 150mm and stockpilesfor reuse or dispose …… m2 or hectars

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    5/44

    4/8/2016 5

    Earthwork Activities

    B) Stripping Top Soil 

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    6/44

    4/8/2016 6

    Earthwork Activities

    C) Excavation & Embankment

    Description in BQ eg

    1) Excavate all the unsuitable material until hard formation and

    refill with suitable matls as shown in the drawings and as

    directed by the SO all in accordance with the specifications

    …… m3 (quantity) 

    2) Excavation (earth) and transport as shown in the drawingsand as directed by the SO all in accordance with the

    specifications …… cu.m

    3) Excavation in rock …. cu.m (Prov Quantities ?)

    4) Form embankment to the slope and levels as shown in thedrawings from excavated materials and as directed by the SO

    all in accordance with the specifications …… cu.m

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    7/44

    4/8/2016 7

    Graphical Presentation of earthwork:

    3 kinds of views in the contract documents to show

    construction features

    1. Plan view – horizontal alignment of features (for roads, drainages,sewwerage etc)

    2. Profile view (longitudinal section) – a vertical view – along the centreline of the work (for roads, drainages & sewerage)

    3. Cross section view – a view formed by a plane cutting the work atright angles to its horizontal alignment (in plan) – for a road project the

    cross section at every 50 meter or other suitable intervals – for a building

    project, cross sections across building platform for few locations both

    along X axis and Y axis

    (Section X-X and Section Y-Y)

    Earthwork for Road projects - Drawings 1, 2 and 3 are given in Contract

    document

    Earthwork of building projects - Drawings 1 and 3 are given

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    8/44

    Figure 2.2 -Profile View (Longitudinal Section) pg 23

    4/8/2016 8

    Formationlevel

    Existing

    Ground

    Level

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    9/44

    Figure 2.3 – Earthwork Cross Sections (pg 66)

    4/8/2016 9

    Plateform Level

    Existing

    Ground Level

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    10/44

    4/8/2016 10

    Cross Sections- Cut and Fill

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    11/44

    4/8/2016 11

    Earthwork Quantities:

    Earthwork computation involve:1. Balancing cuts and fills

    2. Calculating earthwork volume3. Planning the most economical material hauls – to left or right ?

    1. Calculating earthwork volume:

    Calculate a cross sectional end areasa) Use computer softwares or digitizing tablet

    b) Use a planimeter (to measure are of cut or fill )

    c) Sub divide of the project area into geometric figures eg

    triangles, squares or rectangulars and the use of the trapezoidal formula- Triangle =1/2 hw

    - Trapezoid = (h1+h2)x w where w= distance between 2 parallel sides

    h1 & h2 lengths of the parellel sides

    •  Average end area = (A1 + A2)/2 in m2

    • Volume = A1+A2 L/2 in m3

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    12/44

    Fig. 2.4 Cross Sectional Area- Division of a cross

    section drawing into triangles & trapezoidals -(pg 68)

    4/8/2016 12

    Existing

    Ground

    Level

    Formation

    level

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    13/44

    Volume Calculation – Average end area (pg 69)

    Volume = (A1+A2)/2 x L

    4/8/2016 13

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    14/44

    Calculation of Volume 1 – Example 3.2 ms 70

    4/8/2016 14

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    15/44

    Volume Calculation 2 (pg 70)

    4/8/201615

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    16/44

    4/8/2016 16

    Earthwork Quantities:

    Calculating earthwork volume:

    Example 1: Volume = 257,018 ccy

    Example 2: Volume = 250,556 ccy

    Same project but different in volume is due to

    - In Example 1 – more cross-sectional areas are

    taken ( 9 end areas) compare to Example 2 (only 7

    end areas )

    You will get accurate answer if you take more cross

    sections !

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    17/44

    4/8/2016 17

    Earthwork Quantities:

    Calculating earthwork volume:

    Net Volume• Volume of material in cut is different with volume of material in

    fill

    • Volumes for the fill = compacted volume= c meter cube

    • Volumes from the cut = natural volume (in situ volume) = bankvolume = b meter cube

    • If the cut and fill volumes are to be combined, they must be

    converted into compatible volume

    • b= (c meter cube)/0.9 …… Refer Table 3.1 Peurifoy pg 73

    Table 2.1 Earthwork Vol.xls 

    Table 3 1 Earthwork Volume Calculation Sheet

    http://localhost/var/www/apps/conversion/tmp/scratch_3/Table%202.1%20Earthwork%20Vol.xlshttp://localhost/var/www/apps/conversion/tmp/scratch_3/Table%202.1%20Earthwork%20Vol.xls

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    18/44

    Table 3.1 – Earthwork Volume Calculation SheetTable 3.1.docx 

    4/8/2016 18

    Calculating earthwork volume:

    http://localhost/var/www/apps/conversion/tmp/scratch_3/Table%202.3.docxhttp://localhost/var/www/apps/conversion/tmp/scratch_3/Table%202.3.docx

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    19/44

    4/8/2016 19

    Calculating earthwork volume:An Earthwork volume sheet – refer Table 3.1

    •  Column 1 – Stations refer to surveyor notation (chainages) at 100 ft

    interval (abt 30 m)

    Distance between Stations = 50 ft or 100 ft (15 m or 30m)•  Column 2 - End Area Cut (ft square) or meter sq – calculate cross

    sectional areas in cut cros sectional in cut

    •  Column 3 - End Area Fill (ft square) – meter sq – calculate cros sectional

    areas in fill

    •  Column 4 - Volume of Cut between the adjacent preceding stn and the

    stn - Use average end area formula – (A1+A2)/2 x L = b cubic

    meter ( in the example they used yd cube) , b= bank volume

    •  Column 5 - Volume of Fill – use avg end area formula = c cubic meter(m3) where c= compacted volume

    •  Column 6 – Stripping vol in the cut – width of cut x avg depth x distance

    between stns = b cubic meter, not suitable for use in

    embankment (will be deducted)

    Calculating earthwork volume:

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    20/44

    4/8/2016 20

    Calculating earthwork volume: An Earthwork volume sheet – refer Table 3.1 …. Continue 

    • Column 7- Stripping volume in the fill – width of fill x avg depth x distance

    between stn = c cubic meter•  Column 8 - Total vol of cut = vol of cut (column 4 – vol of stripping cut in

    col 6 = b cubic meter

    •  Column 9 - Total Fill = vol of fill in column 5 + vol of stripping fill in col 7

    = c m3

    •  Column 10 – Adjusted Fill = total fill vol converted from compacted vol to

    bank volumn (bcm) (m3) c m3/0.9 = b m3

    •  Column 11 – Algebraic Sum = vol in col 8 – vol in col 10 , + ve cut, -ve fill

    = b m3

    •  Column 12 – Mass Ordinate = the running total of col 11, +ve cut, -ve fill

    ( cut will be added and fill will be substracted)

    E th k V l & M Di (MD)

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    21/44

    4/8/2016 21

    Earthwork Volume & Mass Diagram (MD)

    Table 3.1 pg 73

    • Earth moving = operation where material is removedfrom high spots (cut) & deposited in low spots (fill) – 

    any deficit to get from borrow & excess to dump

    M Di (MD)

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    22/44

    4/8/2016 22

    Mass Diagram (MD) 

    • MD is the most effective tools for planning movement

    of material on any project of linear extent

    • a graphical means for measuring haul distance inmeters (stations) and earthwork volume in m3

    •  the movement = 1 cubic meter, through a distance of

    one station• Mass diagram only for matl that must be transported

    beyond the limit of 2 cross section (200 ft or 100m)

    • If having both cut & fill between stations, cut matl will

    be used for fill requirement between 2 consecutive

    stns. Only the excess vol is to be carried forward for

    MD

    M Di (MD)

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    23/44

    4/8/2016 23

    Mass Diagram (MD)

    •  An Earthwork Profile is a plot of the net earthwork

    along a roadway or airstrip

    • Net cut values are plotted above the X-axis (positive Yvalue)

    • Net fill values are plotted below the X-axis (negative Y

    value)• Presents a picture of the earthwork requirements

    Figure 2 6 (pg 76 A Mass Diagram

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    24/44

    Figure 2.6 (pg 76 – A Mass Diagram

    4/8/2016 24

    Highest pt in MD at the end

    of cut & beginning of fill

    Existing

    Ground

    Level

    Formation

    level

    Lowest pt in

    MDat the end of

    fill and beginningof cut

    M Di (MD)

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    25/44

    4/8/2016 25

    Mass Diagram (MD)

    M Di (MD)

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    26/44

    4/8/2016 26

    Mass Diagram (MD)

    •  A Mass Haul Diagram is a con t inuous curve

    represent ing the cumulat ive volum e of ear thwork

    along the l inear prof i le of a roadway or air f ield

    • The accumulated volume of earthwork at the

    horizontal axis (Y=0) is 0

    • When a horizontal line intersects two or more pointsalong the curve, the accumulated volumes at those

    points are equal

    •  A negative value at the end of the curve indicates that

    borrow is required to complete the fill•  A positive value at the end of the curve indicates that

    a waste operation will be the net result

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    27/44

    Mass Diagram (MD)

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    28/44

    4/8/2016 28

    Mass Diagram (MD)

    • The accumulated volume of earthwork at the

    horizontal axis (Y=0) is 0

    • When a horizontal line intersects two or more

    points along the curve, the accumulated

    volumes at those points are equal

    •  A negative value at the end of the curve

    indicates that borrow is required to complete

    the fill

    •  A positive value at the end of the curve

    indicates that a waste operation will be the net

    result

    Mass Diagram (MD)

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    29/44

    4/8/2016 29

    Mass Diagram (MD) 

    • Table 3.1 – 

    Column (1) is Stations of a project (Chainage)

    Column (12) is cumulative sum of excavation &embankment

    • The Table 2.1 gives information on:

    1) Quantities of matl, 2) Avg haul distance,3) Types of equipment to be considered

    • Refer Figure 3.13 Peurifoy pg 76, For Mass Diagram,+ ve mass ordinate above datum = volume of matl is

    surplus

    - ve below datum = volume of mtl is deficient

    Mass Diagram Properties

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    30/44

    4/8/2016 30

    Mass Diagram Properties

    A MD is a running total of the quantity of matl can show

    surplus or deficient

    • Excavation = ascending MD curve – between stn A&B, and between D & E

    •  Filling =decending MD curve – between B & D

    • Volume of cut/fill can be calculated by a projection ofthe mass diagram line pts to the vertical scale

    • Maximum or minimum pts on the MD = a change from

    excavation to filling or vice versa at pts B and D

    • When MD curve crosses the Datum Line (zero

    volume) at C, no excess or deficit of matl at pt C

    •  At Stn E = waste situation, excess matl will have to be

    hauled to dumping site

    Characteristic of Mass Haul Diagram ref Shrivastava

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    31/44

    4/8/2016 31

    Characteristic of Mass-Haul Diagram  – ref Shrivastava pg 145

    • Mass haul curve represents the algebraic summation of the qty

    of earthwork in the direction in which the chainage of the

    station progresses

    • If the algebraic summation (or cumulative volume) is plus it

    indicates the cutting and is plotted upwards. If minus, it

    indicates the filling and is plotted downwards, with reference to

    base line

    • The slope of the mass-haul curve changes with the volume

    between station. If the curve is ascending, it indicates

    excavation or cut. Decending curve indicate embankment or

    fill.• The lowest point of a loop that form a sag, it occurs at the end

    of the fill. The highest point of a loop that form peak, it occurs

    at the end of the cut

    Characteristic of Mass Haul Diagram ref Shrivastava

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    32/44

    4/8/2016 32

    Characteristic of Mass-Haul Diagram  – ref Shrivastava pg 145 -continue

    • The vertical distance between a valley point and the next

    forward ridge point gives the total volume of the cut. And the

    vertical distance between a ridge point and the next forward

    valley point gives the total volume of the fill.

    • Between any 2 consecutive pts where a horizontal line or base

    line intersects the mass haul curve, the qty of earthwork is

    balanced.

    • If the loop of the mass-haul curve is above the balance line,

    the excavated matl is to be moved in the direction in which the

    station progresses or from left to the right in the MHD. Where

    the loop is below the base line, the excavated matl is to bemoved in the opposite direction or from right to left

    • The maximum ordinate of any loop represent the total qty of

    earthwork that is to be moved from cut to fill

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    33/44

    4/8/2016 33

    Using Mass Diagram

    • MD is an analysis tool for selecting appropriate equipment for excavating

    and hauling matl

    •  Analysis using balance lines & calculating avg hauls

    Balance lines:

    • Horizontal line of specific length that intersects the MD in 2 places

    • Can be constructed so that its length is the maximum haul distance for diff

    type of equipment• Max haul distance the limiting economical haul distance for a particular

    equipment (mc) – use to fix location for mc

    • Ref- Table 3.2 pg 77

    Machines Type Economical Haul Distance

    Large dozer- pushing matl Up to 90m (300 ft)

    Scrapers 90 to 1500m (300-5000ft)

    Loader & Trucks Haul greater than 1500m

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    34/44

    4/8/2016 34

    Balance lines: - continue..

    • Fig 2.7 shown a balance line AC

    • For a large push-loader scraper, the distance between stns A

    and C= 1500m (5000 ft) ref Table 2.2

    • Between the ends of the balance in (A and C), at C the cut

    volume = fill volume

    • Between stn A and C, the amount of matl the scrapers will

    haul = the vertical scale =‘Q’ 

    • The avg haul the multiple balance lines and the area shown

    is a rectangular.

    • The avg haul distance = the length of a horizontal line placed

    1/3 of the distance from balance line in the direction of thehigh or low pt of the curve

    • It is when the general shape of the MD is a triangle ( 2

    triangles)

    Fi 3 14 ( 8) MD i h b l li

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    35/44

    Figure 3.14 (pg78) – MD with a balance line

    4/8/2016 35

    B l li ti

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    36/44

    4/8/2016 36

    Balance lines: - continue..

    Ref Fig 3.15  pg 79 – multiple balance lines

    •  Avg haul for an equipment, where distance = midway between balance

    lines

    • When the curve is above the balance line – direction of haul is from left to

    right i.e up stationing

    • When the curve is below the balance line – direction of haul is from right to

    left i.e down stationing

    • Length of the balance line = max or min haul distances for the balancedearthmoving operation - to conform to capabilities of equipment to be

    utilised

    • Equipment/mc to operate at haul distances within its range of efficiency

    • In fig 2.8, dozers will be used to push the short haul matl.

    • Using dozers the excavation between stns C and D will be placed betweenstns D and E

    • Using a scraper – to excavate matl between stn A and C & haul to fill

    between stns E and G

    Note: In Fig 2.8, yardage= volume in yd3 or for us to use m3

    Figure 3 15 – 2 balance lines of a MD

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    37/44

    Figure 3.15 – 2 balance lines of a MD

    4/8/2016 37

    igure 3.14 – Using MD & Profile to determine avg haul grades

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    38/44

    g g g g

    4/8/2016 38

    1/2h

    1/2h

    Average Grade:

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    39/44

    4/8/2016 39

    Average Grade:• When the MD & the project profile are plotted one on top of the

    other, ref Fig 3.14. and Fig 3.15 , the avg haul grades of the

    earthmoving operation can be approximated• On profile view, draw a horizontal line that divide the cut area

    in half in vertical dimension. Do the same to fill area.

    • The diff in elevation between these 2 lines provide the vertical

    distance to use in calculating the avg grade for the haulinvolving the matl in the balance

    •  Avg grade % = (Change in elevation/Avg haul distance) x 100

    •  Ref Fig 3.14 - The avg grade from the cut to the fill

    •   = (-18 ft/203)x100 = -8.9%• The return trip will be up a 8.9% grade

    (involve transport cost)

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    40/44

    Haul Distances: continue

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    41/44

    4/8/2016 41

    Haul Distances: ….continue 

    Ref Table 3.3 Table 3.3 Earthwork Vol For MD.xls 

    • Column 12 - lowest pt of the valley = -28,539 at Stn 5 +00

    - high pt of -17,080 at Stn 8+ 00- 2nd lowest pt = -22,670 at Stn 10 +00

    Sum of values of of the peak and low pts = total excavation to

    be moved longitudinally,

    b =[(28,539 – 17,080) + (22,670-17,080) + (17,080-0) =33,188 yd3]

    • Haul 1 = 11,459 yd3

    • Haul 2 = 5,590 yd3

    • Haul 3 = 17,080 yd3

    Ref Fig 3.17

    Calculating Haul Distances: Ref MD

    http://localhost/var/www/apps/conversion/tmp/scratch_3/Table%202.3%20Earthwork%20Vol%20For%20MD.xlshttp://localhost/var/www/apps/conversion/tmp/scratch_3/Table%202.3%20Earthwork%20Vol%20For%20MD.xls

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    42/44

    4/8/2016 42

    Calculating Haul Distances: Ref MD

     Avg haul distance for any individual haul,

    = area enclosed by the balance line and zero datum / amount of

    matl hauled

    Graphically = the vertical mid point of the area

    = Area from 0 +00 to 15+ 00h0 =0, h1= 3631, h2=13,641....h13=17080, h14= 8502, h15=0

    = 213,654 stn-yrd

     Avg haul distance= 213,654/17,080 =12.51 stn

    Graphically = 12,200 ft

    SBC2253_OCW_Mass_Haul_Diagrams.pdf  

    Fig 3 17 Mass Diagram – plotted from data Table 3 3

    http://localhost/var/www/apps/conversion/tmp/scratch_3/SBC2253_OCW_Mass_Haul_Diagrams.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_3/SBC2253_OCW_Mass_Haul_Diagrams.pdf

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2

    43/44

    Fig 3.17 Mass Diagram – plotted from data Table 3.3

    4/8/2016 43

    Haul 1Haul 2

    Haul 3

    28,539

    17,080

    22,670

  • 8/17/2019 Lecture 3A-Earthwork & MS Diagram 2