lecture # 13 investment alternatives i
TRANSCRIPT
Lecture # 13
Investment Alternatives
PW and AW methods
1 Dr. A. Alim
Investment Alternatives
• One of the important functions of financial
management and engineering is the creation
of “alternatives”.
• If there are no alternatives to consider then
there really is no problem to solve!
• Given a set of “feasible” alternatives,
engineering economy attempts to identify the
“best” economic approach to a given problem.
2
Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 ,
by L. Blank and A. Tarquin, and also from Engineering Economics 4N04 class notes, McMaster
University © 2001-2007.
Assessing Alternatives
• Feasible Alternatives
Feasible Set
Mutually Exclusive Set Independent Set OR
3
Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 ,
by L. Blank and A. Tarquin, and also from Engineering Economics 4N04 class notes, McMaster
University © 2001-2007.
Four Types of Categories:
In addition to the two outcomes listed earlier:
• Mutually Exclusive Set
• Independent Project Set
We may also have two additional outcomes:
• The single Project.
• The “Do Nothing” (DN) option
4 Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 ,
by L. Blank and A. Tarquin, and also from Engineering Economics 4N04 class notes, McMaster
University © 2001-2007.
The Single Project
• Called “The Unconstrained” Project selection problem
• No comparison to competing or alternative projects
• Acceptance or Rejection is based upon specified criteria
5
Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 , by
L. Blank and A. Tarquin, and also from Engineering Economics 4N04 class notes, McMaster University ©
2001-2007.
Do Nothing Option
• The firm may decide to reject all alternatives and decide to do nothing.
• Therefore, the do nothing is always “an option”.
• In that case, the company maintains the current approach and simply invest their funds at MARR (e.g. in a bank) until a decision is made at a future date.
• In projects involving safety or legal aspects, the do nothing is not considered.
6
Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 ,
by L. Blank and A. Tarquin, and also from Engineering Economics 4N04 class notes, McMaster
University © 2001-2007.
Independent Project Set
Funds exist to allow the selection of all
feasible alternatives.
Each project is judged independently of
the others, i.e. same as single project.
An interesting case of “partially
independent” project set occurs when
funds exist for some but not all feasible
alternatives. We will discuss this case
later, under optimization.
7
Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 , by
L. Blank and A. Tarquin, and also from Engineering Economics 4N04 class notes, McMaster University ©
2001-2007.
Mutually Exclusive (ME) Set
Only one of the feasible (viable)
projects can be funded.
Once selected, the others in the set
are “excluded”.
Each of the identified feasible
(viable) projects is (are) considered
an “alternative”.
8
Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 , by
L. Blank and A. Tarquin, and also from Engineering Economics 4N04 class notes, McMaster University ©
2001-2007.
Example
Distillation tower to separate
L-L extraction to separate
Solid adsorption to separate
Stream with mixed components
Funds exist for only one alternative !
Mutually Exclusive (ME) Set
9 Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 , by
L. Blank and A. Tarquin, and also from Engineering Economics 4N04 class notes, McMaster University ©
2001-2007.
Cash Flow Types for Projects
Revenue – each alternative generates costs and revenues over the estimated life of the project.
Selection criterion: Select the alternative that maximizes the economic measure of merit (PW or AW)
Service – each alternative has only current and future costs over the estimated life of the project.
Selection criterion: Select the alternative that minimizes the economic measure of merit, which is a cost-based measure (PW or AW)
10 Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 , by L. Blank and A. Tarquin, and also from
Engineering Economics 4N04 class notes, McMaster University © 2001-2007.
Investment Alternatives
How do we choose among alternatives ?
Basically, any of the profitability measurements could be used:
PW (or AW): * Reject a revenue project if PW (or AW) at
MARR is negative. Reject a service project
if PW of cost is more than a preset level.
* Select the project with the most favorable
PW or AW among alternatives.
PBP: * Reject a project if PBP>PBP (ref)
* Pick the shortest PBP among alternatives
* Not recommended, and must never be the
only method used.
11
Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 ,
by L. Blank and A. Tarquin, and also from Engineering Economics 4N04 class notes, McMaster
University © 2001-2007.
Examples
• Calculate PW of each alternative at MARR
• Selection criterion: Select alternative with most favorable PW value, that is,
numerically largest PW value (most positive)
PW1 PW2 Select
$-1,500 $-500 2
-2,500 500 2
2,500 1,500 1
Note : Not the absolute
value
12 Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 , by L. Blank
and A. Tarquin, and also from Engineering Economics 4N04 class notes, McMaster University © 2001-2007.
Investment Alternatives How do we choose among alternatives ?
In addition, we can also use the ROI or DCFRR method :
ROI: Reject a project if ROI<MARR
DCFRR (IRR): Reject a project if DCFRR<MARR
Among alternatives, it is not always true that the highest ROI
or DCFRR is the most preferred. If we are to use the ROI or
the DCFRR methods then we must apply incremental analysis
among alternatives.
13 Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 ,
by L. Blank and A. Tarquin, and also from Engineering Economics 4N04 class notes, McMaster
University © 2001-2007.
Investment Alternatives Summary - How do we choose among alternatives ?
PW or AW: Select the most positive (profit/cash
flow) or least negative (cost)
PBP : Not recommended as sole method.
ROI or DCFRR: May be used, but must apply
incremental analysis.
14
Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, ©
2005 , by L. Blank and A. Tarquin, and also from Engineering Economics 4N04 class notes,
McMaster University © 2001-2007.
Investment Alternatives
15
Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, ©
2005 , by L. Blank and A. Tarquin, and also from Engineering Economics 4N04 class notes,
McMaster University © 2001-2007.
Let’s discuss details of PW and AW in this class. Next class we will address the ROI and the DCFRR approaches and the concept of incremental analysis.
PW analysis of Investment Alternatives
• Alternatives must be compared at the same project life. • For Alternatives with unequal lives, we apply the “lowest common multiple” • LCM – Evaluate the alternatives over the lowest common multiple of lives, e.g. lives of 4 and 6 years, use n=12 and assume re-investment at same cash flow estimates.
16 Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 , by
L. Blank and A. Tarquin, and also from Engineering Economics 4N04 class notes, McMaster University ©
2001-2007.
LCM Approach The assumptions for the analysis of
different-life alternatives are a follows:
1. The service provided by the alternatives will be needed for the LCM of years or more.
2. The selected alternative will be repeated over each life cycle of the LCM in exactly the same manner.
3. The cash flow estimates will be the same in every life cycle.
17 Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 ,
by L. Blank and A. Tarquin, and also from Engineering Economics 4N04 class notes, McMaster
University © 2001-2007.
LCM Example – Cost projects Example 5.14, page 246, Contemporary Engineering Economics, C.S.Park, 4th edition, Pearson Prentice Hall, 2007.
18
A certain mail-order firms wants to install an automatic mailing system to handle product Announcements and invoices. The firm has a choice between two different types of machines. The two machines are designed differently, but have identical capacities and Do exactly the same job. The $12,500 semiautomatic model A will last three years. The Fully automatic model B will cost $15,000 and last four years. The expected cash flows for the two machines including maintenance, salvage, and tax Effects, are as follows: model A model B Number of years 3 4 Initial cost $12,500 $15,000 Annual expenses $5,000 $4,000 Salvage value $2,000 $1,500 If the MARR is 15%, using the PW method, which machine should the firm purchase? NOTE: This is a service project with two alternatives having different service lives.
19
20 Clearly, model B is the better choice.
The use of Annual Worth (AW) for selecting among alternatives
• AW may be used instead of PW to select among alternatives!
• Recall the criterion discussed earlier, depending on type of cash flows in the project.
21
Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 ,
by L. Blank and A. Tarquin, and also from Engineering Economics 4N04 class notes, McMaster
University © 2001-2007.
Cash Flow Types for Projects
Revenue – each alternative generates costs and revenues over the estimated life of the project.
Selection criterion: Select the alternative that maximizes the economic measure of merit (PW or AW)
Service – each alternative has only current and future costs over the estimated life of the project.
Selection criterion: Select the alternative that minimizes the economic measure of merit, which is a cost-based measure (PW or AW)
24
Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 , by L. Blank and A. Tarquin, and also from
Engineering Economics 4N04 class notes, McMaster University © 2001-2007.
The use of Annual Worth for selecting among alternatives
• Popular Analysis Technique
• Easily understood-results are reported in $/time period
– Eliminates the LCM problem associated with the present worth method
– Only have to evaluate only one life cycle of a project
23
Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 ,
by L. Blank and A. Tarquin, and also from Engineering Economics 4N04 class notes, McMaster
University © 2001-2007.
Previous example – Solution using the AW method
24
Recall we calculated PW for one cycle for each model: For model A, PW(15%) = - $22,601 Hence AW = -$22,601(A/P,15%,3) = -$9,899 For model B, PW(15%) = - $25,562 Hence AW = -$25,562(A/P,15%,4) = -$8,953 Hence, model B is the better choice
• 3 investments. Need to evaluate profitability of each.
• Use ROI, PBP, NPV, and DCFRR.
• Assume straight line depreciation.
• Tax rate is 35%
• MARR is 15%
• Use MARR as interest rate for time value of money.
• Ignore land value.
Example (Evaluating alternatives using AW):
Modified example 8-3, Peters, page 331
25
Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 ,
by L. Blank and A. Tarquin, and also from Engineering Economics 4N04 class notes, McMaster
University © 2001-2007.
Investment #
Fixed capital
$
Working capital
$
Salvage value
$
Service life, years
GI – E
$
1 100,000 10,000 10,000 5 See yearly tabulation
2 170,000 10,000 15,000 7 64,615
(constant)
3 210,000 15,000 20,000 8 73,846
(constant)
For investment # 1:
Year 1 2 3 4 5
GI – E
$
46,154 47,692 55,385 61,539 66,154
26
Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 , by L. Blank and A. Tarquin, and also
from Engineering Economics 4N04 class notes, McMaster University © 2001-2007.
27
Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 ,
by L. Blank and A. Tarquin, and also from Engineering Economics 4N04 class notes, McMaster
University © 2001-2007.
Comparing investments 1,2, and 3 on AW basis:
PW of CFAT (one cycle) n years AW of CFAT
Investment 1 38,509.00$ 5 $11,487.83
Investment 2 36,378.00$ 7 $8,743.83
Investment 3 39,133.00$ 8 $8,720.79
Investment 1 has the highest AW, hence we select it.
28
Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 ,
by L. Blank and A. Tarquin, and also from Engineering Economics 4N04 class notes, McMaster
University © 2001-2007.
(Evaluating alternatives using AW), Example 6.4 page 157, Blank and
Tarquin, 7th ed. McGraw Hill, 2012.:
29
Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 ,
by L. Blank and A. Tarquin, and also from Engineering Economics 4N04 class notes, McMaster
University © 2001-2007.
Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 , by L. Blank and A. Tarquin, and also from
Engineering Economics 4N04 class notes, McMaster University © 2001-2007. 31
31
Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 ,
by L. Blank and A. Tarquin, and also from Engineering Economics 4N04 class notes, McMaster
University © 2001-2007.
Advantages of AW
* Easier to calculate, uses only one cycle. No need for LCM calculation.
* Applicable to a variety of engineering economy studies:
– Breakeven Analysis
– Economic Value Added analysis (EVA)
– Asset Replacement
32
Material used in this lecture is sourced from “Engineering Economics”, 6th ed. McGraw Hill, © 2005 , by L. Blank and A. Tarquin, and also from
Engineering Economics 4N04 class notes, McMaster University © 2001-2007.