LEASING for aWIND FARM
Dennis Stein
Farm Management Educator
MSU Extension
1
MSU is an affirmative-action, equal-opportunity employer. Michigan State University Extension programs and materials are open to all without regard to race, color, national origin, gender, gender identity, religion, age, height, weight,
disability, political beliefs, sexual orientation, marital status, family status or veteran status.
2
2
Federal Wind Industry Incentives
Federal Tax Credits (choose one) 30% renewable energy production tax credit
on equip cost
2.1cents/kilowatt hour for up to 10 years
Renewable energy grants up to 30% of investment
3
Industry Incentives (cont.)
Clean Renewable Energy Bonds (tax credit bonds- equivalent to interest free loan) Bond holder receives federal tax credits not interest
Business and Industry Guaranteed Loans – $10 million max
Accelerated depreciation – 5 year
4
3
Industry Incentives (cont.)
Renewable Energy Credits – RECS or Green Tags Sold separately from elec. so producers
market environmental and elec benefits separately
1 credit for each MWh (1 megawatt hour) produced
1 MWh = 1000 kWh, avg family uses 800 kWh/mo
5
6
4
7
ONSITE DATA
Anemometers
Research Facilities
Terrain
Neighborhood
Existing Turbines
Data, Data, Data
8
5
9
Who All Gets Involved
Wind Developer
State Government
Local Government
Federal Agencies
Community Groups & Activists
Environmental Organizations & Activists
General Public 10
6
Regulations
Sighting Visual & Noise Wildlife Impact Development Stages County / township Zoning? Safety? Synchronization with Power Grid Property Tax
11
The Developer’s Dilemma:
12
7
How will you be compensated?
What are your payments for easements? One-time, up-front, or periodic?
What unit is used?
What are your lease payments? Per turbine, per megawatt, or a “royalty?”
What is the payment zone, pool, project
Definitions matter!
How will accuracy be verified?
Key Terms of Agreement
3 -Active Phases; Development –Construction – Operations –
Rates & type of compensation
Site selection- will I get a turbine?
4th Phase Re-powering or Decommissioning
14
8
Property Line Setback
15
Land impacted by turbine:- payment zone: turbine, 300, 500, 660 feet radius
- set back: turbine to turbine (1400 feet radius = 141.29 acres)
- set back: closest home (1400 feet = .265 miles)
- set back: other_______________
Land Develop-
ment Steriliza-
tion Issues:
16
144.86 acres
9
Property Line SetbackHalf Section Land With 3 Times Turbine Height
1.5 mW Turbines
Set-Back AreaMaximum Turbines = 4
17
PSYCHOLOGY of LEASING
- Landowner’s mind frame becomes a negotiator, a price maker – not taker
- Land man is paid by wind developer,
experienced negotiator,
well educated in his craft,
smooth talker
18
10
Psychology of Leasing
Landowner has the choice to say “No”
May not arrive at an agreement initially–OK – may take years
Use Dogged Determination
Good leases take time
and last a long time
19
Phases of wind farm development
1. Evaluation and Land acquisition phase Field representatives make contact with landowners and
secure property leases
2. Development phase Site is surveyed, developed, turbines installed
3. Production phase Turbines operational and produce energy
4. Re-power or Decommission phase
20
11
21
Five questions you must ask...
1. How long will agreement last?
2. What development rights am I selling?
3. What are your obligations under the
agreement?
4. How will you be compensated?
5. What happens when the project ends?
22
12
What are your obligations under the agreement?
Surface uses – what will be required to satisfy “non-obstruction” requirements?
Indemnity(!) Will increased insurance be required?
What about third-party waivers?
Property taxes?
Compliance with government programs (CRP, EQIP, WHIP)?
23
Lease Terms
Lease vs. Easement –
Should be a lease with a defined termination date
24
13
Lease Terms (cont.)
Landowner Termination Rights
Default and Forfeiture ClauseTime needed to create a default (60 days?)
Lessor to hold and become owner of improvements
Require lessee to indemnify landowner for lessee operations
25
Lease Terms (cont.)
Once turbine placed specify release of remaining land from lease or establish compensation for extra land held as part of the contract $ per acre per year (very important!!!)
Most favored lease clause so you have same terms as anyone else signing similar agreements be sure of the term of this clause (watch when this expires)
26
14
Lease Terms (cont.)
Be comfortable with every paragraph before signing
Get verbal promises in writing (most have a clause that states that all promises, presentations, written materials provided to the landowner are void and unenforceable)
Attorney’s advice at beginning and end
Take photos before Lessee’s operation begins
27
Lease Terms (cont.)
Landowner approve turbine location, roads, road material, power lines, related structures
Clearly state your rights to continue current uses of property
Establish the height and distance from turbines of any future new buildings you construct
Specify if trees can be replaced and what areas new ones can be planted
28
15
Lease Terms (cont.)
Tile repair: Your contractor or their contractor to do the work?
Owner right to approve lease assignment and original developer still liable to you if assignee defaults
Surface damages Paid for total market value of crop loss
Renter vs landowner -crop loss $$
Specify formula for crop loss calculation
Landowner approve cropland restoration plan
29
Lease Terms (cont.)
Once turbine placed specify release of remaining land from lease or establish compensation for extra land held as part of the contract $/acre (very important!!!)
Most favored lease clause so you have same terms as anyone else signing similar agreements be sure of the term of this clause (watch when and how this expires)
30
16
Lease Terms (cont.)
Be comfortable with every paragraph before signing
Get verbal promises in writing (most agreements have a clause that states that all promises, presentations, written materials provided to the landowner are void and unenforceable)
Attorney’s advice at beginning and end
Take photos before Lessee’s operation begins
31
Lease Terms (cont.)
Bond or irrevocable letter of credit No operations on site until bond to landowner
Insures funds available for land restoration, equipment decommissioning
$100,000 minimum per tubine
Provides security to pay all land damages
Review every 5 years and have provision to increase values as necessary
32
17
Lease Terms (cont.)
Bond or irrevocable letter of credit No operations on site until bond to township
or landowner is in place
Insures funds available for land restoration, equipment decommissioning
$100,000 minimum per turbine(inflation index)
Provides security to pay all land damages
Review every 5 years and have provision to increase values as necessary
33
How will you be compensated?
What are your payments for easements? One-time, up-front, or periodic?
What unit is used?
What are your lease payments? Per turbine, per megawatt, or a “royalty %?”
Definitions matter
How will accuracy be verified?
34
18
Financial Terms (cont.)
Operational Phase – Three Compensation Choices 1. One time payment
2. Fixed annual rent
3. Fixed royalty payment per KWH
4. Royalty % + % green payments
Be sure you have payments indexed that allows payment to track current values
35
Financial Terms
Three periods to receive income: Evaluationphase, Development phase, Operational phase
The lease is actually a sale of development rights – compensation should be adequate
Evaluation Phase – keep as short as possible –2 to 5 years (with ? year auto extension)
Charge high enough to provide incentive to either develop wind farm or terminate lease
$ _____ per acre/year , or $0,000 minimum /yr
36
19
Financial Terms (cont.)
Development Phase or Construction Period Limit to 3-4 years
Annual rental continues until power produced Type of crop to set annual rent as minimum
One time payment when turbine and other equipment installed - = + $10,000
Fees for roads, buildings, power lines (above and below ground)
37
Estimated Gross Revenue Generation from a Wind Turbine- no REC
turbine MW
efficiency spin time gross MW $/MW Electricity $ Energy onlyTotal Annual $
Revenues
1.50 35% 75% 3,449 $45.00 $155,216 3.0% $4,656.49
1.50 35% 75% 3,449 $45.00 $155,216 3.5% $5,432.57
1.50 35% 75% 3,449 $45.00 $155,216 4.0% $6,208.65
1.50 35% 75% 3,449 $45.00 $155,216 4.5% $ 6,984.73
1.50 35% 75% 3,449 $45.00 $155,216 5.0% $7,760.81
38
20
Estimated Gross Revenue With $10 REC/Green Credits
turbine MW
efficiencyspin time
gross MW$/MW
Electricity$ Energy
onlyTotal Annual $
Revenues
1.50 35% 75% 3,449 $50.00 $172,463 3.0% $ 6,208.65
1.50 35% 75% 3,449 $50.00 $172,463 3.5% $ 7,243.43
1.50 35% 75% 3,449 $50.00 $172,463 4.0% $ 8,278.20
1.50 35% 75% 3,449 $50.00 $172,463 4.5% $ 9,312.98
1.50 35% 75% 3,449 $50.00 $172,463 5.0% $10,347.75
39
Re-Powering okay but renegotiate
40
21
Decommissioning4 - 5 feet below grade?
400 cu ydsPerformance bond for 1.5 x cost of removal
180 days
41
What happens when the project ends?
After project term is completed, will the agreement provide for: disassembly and
removal of equipment?
restoration of grades and soils?
replacing vegetation?
What assurances are in place?
42
22
Considerations
Issues of condemnation power for transmission lines?
Spacing and setback requirements?
Standard terms of payment and audit privileges?
Insurance requirements?
Decommissioning indemnity funds?
43
Summary Comments
44
1. Landowner groups often can develop superior contract arrangements2. Be sure that you know how and for what you will be paid
1. Turbines, roads, power lines, transmission lines, met-towers, communication towers, power stations
3. Make sure payments are indexed to keep up with inflation4. Be sure that you do not give your rights away in the agreement for
free5. Calculate the land that will be lost or that will now have development
restrictions1. Tile2. Irrigation3. Development for homes
6. You can choose to not have any surface development on your land7. You can choose to not lease your property at all
23
Do oil and air mix?
45
Dennis Stein Farm Management Educator,
Michigan State University Extension
362 Green St., Caro, MI 48723
Phone: 989-672-3870
http://miwind.msue.msu.edu/
Email: [email protected]
Web Page: http://www.msu.edu/user/steind
46
24
47
Low frequency Noise
More difficult to measure than audible noise
Can be a factor at greater distances
More complaints inside homes and at night
Measurement standard can be included as part of a zoning ordinance
48
25
Shadow Flicker
Caused by sun rising or setting behind the blades of turbine
Casts flickering shadows on nearby premises, can be an annoyance or distraction to residences
Can be dealt with via set backs, or shutting down turbines during brief periods of shadow disturbance during the day
49
Ice
Huron Wind Farm,
Tiverton, Ontario
Setbacks and signage can help mitigate potential hazard
50
26
Noise
Most wind turbines register about 50 decibels (refrigerator sound level) from 800 feet away
Zoning can dictate allowable sound level at property line or nearest residence
Known as a “Noise setback”
More restrictive in more urban areas – e.g. CA county has a 2 mile set-back for noise
51
Avian Impacts
Early wind installation at Altamount Pass, CA, in migratory bird path caused bird kills
1980s, 7,000 turbines, mountain pass, lattice towers –all problematic
Since then, environmental impacts are assessed when siting towers
Average today – one bird killed per turbine per year in U.S., far less than cats or car windshields
52
27
Visual Impact
Depends greatly on population of area and general aesthetics
Ugly or Beautiful?
Zoning can address number turbines in particular area, or what color they must be.
53
Setback from the Road
Huron WindFarm
Tiverton, Ontario
Photography by Winton Dahlstrom
54
28
To have an impact on zoning…
Get involved!
Go to meetings, talk to commissioners or planning board
55
Wind “Rights” Steriliza-
tion Issues:
56
29
Property Line SetbackHalf Section Land With 1.5 Times Turbine Height
1.5 mW Turbines
Set-Back Area Maximum Turbines = 1157