Nombre Parque EólicoNombre Parque Eólico Wind FarmWind Farm

Expansion of current Wind FarmExpansion of current Wind Farm

Evolution and present statusEvolution and present status

©2007 Nombre del cliente– CONFIDENTIAL – Nombre Parque Eólico

Project criteria for existing Wind Farm

2

Best available technology

selection

• 12 Neg-Micon NM 900/52/55 IEC Class II, 900 KW. Total: 10.8 MW

• Maximum compliance with environmental constraints during construction and operation

• Future expansions are taken into consideration when M26 was conceived

©2007 Nombre del cliente– CONFIDENTIAL – Nombre Parque Eólico

Project criteria for the project Wind Farm

3

Best available technology14 x 2,750 KW turbines

Total power deployed: 38.5 MW Total production: 150,805 MWh/year 3,917 net equivalent hours Power line: already existing (ready for 100 MW) Power Transfer Station: already existing (minor

modifications) Total natural area affected: 7.9 ha

©2007 Nombre del cliente– CONFIDENTIAL – Nombre Parque Eólico

Best available technology

Current turbine900 KW

Projected turbine2.750 KW

0 ft

148 ft

302 ft

466 ft

157 ft32

8 ft

4©2007 Nombre del cliente– CONFIDENTIAL – Nombre Parque Eólico

Wind Farm Power Station Minor modifications to adapt to new requirements:

Adition of 3 new power cells (building ready)

Replacement of trafo protection cell 20/66 kV by 2.000 AReplacement of trafo protection cell 20/66 kV by 2.000 A

New cells for M27New cells for M27

5©2007 Nombre del cliente– CONFIDENTIAL – Nombre Parque Eólico

6

Substitution of traditional electricity production methods responsible for ‘greenhouse effect’

Comparison against a coal fuelled plant(Source: Energy National Comission)

Energy balance

M

Annual production MWh 150,805

Dwellings supplied 45,512

CO2 avoided t 147,913

SO2 avoided t 3,868

NOx avoided t 546

©2007 Nombre del cliente– CONFIDENTIAL – Nombre Parque Eólico

Wind farm Power Station Slight modifications

Replacement of current transformer (ground structure already in place)

7©2007 Nombre del cliente– CONFIDENTIAL – Nombre Parque Eólico

Alternatives consideredComplaint solving (II)

8

July 2004Public enquiry for Expansion

December 1999Administrative approval10,8 MW

July 2002Expansion request to49,3 MW

July 2003Expansion request publication

December 2003begins operation

December 2002Power Line Administrativeapproval

©2007 Nombre del cliente– CONFIDENTIAL – Nombre Parque Eólico

Complaint solving (II)

Access track layout changes

Minimization of affection to gypsum soils and shrubs

New track layout through cultivated land

Minimization of the visual impact by retracing of tracks through endorreic valleys

9

July 2004Public enquiry for Expansion

December 1999Administrative approval10,8 MW

July 2002Expansion request to49,3 MW

July 2003Expansion request publication

December 2003begins operation

December 2002Power Line Administrativeapproval

©2007 Nombre del cliente– CONFIDENTIAL – Nombre Parque Eólico

Complaint solving (II)

Land use changes as a result of compensatory measures

9.5 ha of land are removed from cultivation and left to natural regeneration

10

July 2004Public enquiry for Expansion

December 1999Administrative approval10,8 MW

July 2002Expansion request to49,3 MW

July 2003Expansion request publication

December 2003begins operation

December 2002Power Line Administrativeapproval

©2007 Nombre del cliente– CONFIDENTIAL – Nombre Parque Eólico

Project timeline

July 2002Request for power expansion to 49,3 MW

July 2003Expansion request published officially

July 2004Official Bulletin publication and public enquiry period

2002 2003 2004

11

Since July 2005, the Wind Farm is awaiting administrative

approval. This authorisation does not relate to the resolution of

issues regarding the connection to the electricity grid.

July 2005Approval and publication in Official bulletin

Awaiting administrative approval

2005 2006 2007

©2007 Nombre del cliente– CONFIDENTIAL – Nombre Parque Eólico

12

Created by Enviria Proyectos

February 2007